Beruflich Dokumente
Kultur Dokumente
1s IEEE International Conference on Power Electronics, Intelligent Control and Energy Systems (ICPEICES-2016)
Abstract-The Paper presents study of 11 kV In this paper, Jaipur city distribution network has
distribution network of Jaipur city, with shunt capacitor been studied to assess the impact of shunt capacitor banks
placement at 11kV voltage level. In the current scenario
on losses, lines & transformers loading and network
utilities are managing the expansion of distribution network
without planning the shunt capacitors. This paper provides
voItage profile. The effect of capacitors on network lines,
an analysis of distribution losses in Jaipur city by modeling transformers, Substation power factor & system loadings
the present scenario of distribution network operating have been researched both with & without Capacitor Bank
without shunt capacitor banks. The model of 260 bus over the Test system.
network is designed and reactive power requirement for
constant power load are calculated from load flow studies by 11. LITERATURE STUDY
using Mi-power Software. The proposed model is designed
with capacitor installation, calculating the reactive power There are several methods of voItage control [2],
requirements of real time existing system. Comparative similar to utilizing tap changing transformers, excitation
studies have been carried with updated system parameters control, induction regulators etc. the system voItage is
for power flow. The effect of capacitors on network lines, changed in accordance with the load to obtain a fairly
transformers, Substation power factor &system loadings
constant voItage at the consumer's end of the system. In a
have been researched both with & without Capacitor Bank
over the Test system. An overall financial analysis detailing
distribution system, the voItage profile of grid reduces as
annual cost & energy saving is also presented. Lastly we scales away from substations, also the losses increases
capacity utilization factor suggesting for optimal utilization squarely [3]. The reason is the deficient amount of
of capacitor banks with case studies, are followed by results reactive power, which can be delivered by shunt
with simulated changes in swing bus voltage have been
capacitors if provided in the system. Several researchers
addressed.
Keywords-Capacitor Bank Placement; Optimum
have pointed out the importance of shunt capacitor
Capacitor Utilization; Jaipur City 260 Bus Distribution placement, Grainger & Lee [4] created a nonlinear
Network; Reactive Compensation; Loss Reduction programming based theory in which location of capacitor
and its capacity were identified as continuous variables.
L INTRODUCTION
Grainger [5] also expressed the capacitor placement and
Worldwide the population is forming changes in the voItage regulators problem and suggested decoupled
old structural grid equipment's and devices. Therefore, the solution methodology for distribution system. Baran and
utility had to maintain grid efficiency by performing Wu [6,7] explored with a mixed integer programming.
regular system studies and deploying up to date measures Similarly Sundharajan and Pahwa [8] applied genetic
to cope up with instability problems. Distribution algorithm approach for optimal placement of capacitors.
networks are continuously expanding and are becoming Similar work presented by R.S. Rao & S.V.L.
complicated day by day [1]. Narsimham[9] through a well-organized way of capacitor
The major problem in running old system network placement in radial distribution systems by a new
with increase in load growth raises the necessity of algorithm that employs Plant growth Simulation
fulfilling the reactive power requirements in the Algorithm (PGSA) is used to estimate the optimal size of
distribution networks. Shunt capacitor banks are being capacitors at the optimal buses, with an objective of
installed at 33 kV voItages at Extra High VoItage (EHV) improving the voItage profile and reduction of power
sub-stations. Very few capacitor banks are installed in losses were achieved.
distribution network at 11 kV voItage level. Distribution The optimal capacitor placement is a complicated
losses may be reduced significantly if capacitor Banks are combination based optimization problem, many different
installed at 11 kV voItage level. optimization techniques and algorithms have been
978-1-4673-8587-9/16/$31.00 ©2016 IEEE [1)
t
1s IEEE International Conference on Power Electronics, Intelligent Control and Energy Systems (ICPEICES-2016)
progressed. The forces of refining the overall productivity Initially the test system data is accumulated for line
of power distribution have forced the operators to work on conductors to be used, the r/x ratio of distribution
loss reduction. transformer units; copper losses as weil as the bus bar
voItage limits were being identified. The simulation model
III. TEST SYSTEM DESCRIPTION with pattern of radial power tlow in Jaipur network is
prepared in the Mi-Power software. The Table 2 lists the
The designed system is a real-time network of Jaipur
input parameters of the test system obtained after
city (Rajasthan State Power System). It is designed & modeling.
simulatedin the software 'Mi-Power' [10] developed by TABLE 2: INPUT SYSTEM PARAMETERS
M/s PRDC Bangalore. The software offers platform to
Sr. No. Input Data Data Values
design, analyzeand perform load tlow analysis with I Total Real Power Load 691.181 MW
detailed report analysis. The distribution line set up is 2 Total Reactive Power Load 518.386 MV A r
obtained by using power map. It describes the connectivity 3 Load Power Factor 0.80
of 33 kV line &11 KV sub-station of Jaipur city. The 4 Number of Generator Buses (Swing Bus) I
network designed is of Jaipur city representing peak load 5 Total Number ofBuses 260
of approximately 691 MW. The power is supplied by 6 Number of 132 kV Buses 18
swing bus to the system of seventeen 132 kV GSS and one 7 Number of33 kV Buses 121
hundred & twenty one number of 33 kV GSS delivering to 8 Number of II kV Buses 121
one hundred and twenty one number of 11 kV GSS 9 Number of Total Lines 164
10 Number of 132 kV Lines 17
covering major load of Jaipur city. An amount of one
II Number of33 kV Lines III
hundred and sixty four number of transmission lines are
12 Number of Total Transfomers 138
drawn using the power map which are connecting these
13 Number of 132 /33 kV Transfomers 17
sub-stations. 14 Number of33111 kV Transfomers 121
As per Indian Electricity Grid Code 2008 [11] 15 Number ofLoad Buses ( lI kV level) 121
minimum and maximum voltage limits at various voItage
levels are presented in Table 1. IV. CAPACITOR PLACEMENT & L OAD FLOW STUDIES
TABLE I: VOLTAGE LIMITS ATVARIOUS LEVELS
Load is represented at 11 kV voItage level. There are
Voltage Variation Minimum Maximum
121 load buses being connected to the various GSS of
Level Limits Voltage Voltage
Jaipur City distribution network.The majority of load
- 7.57%
132 kV 122KV 145KV includes residential, small scale industry as weil as
+ 9.84%
educational hubs of the city have been considered along
- 9.09%
33 kV 30KV 36KV with bus wise connectivity from distribution feeders. Load
+ 9.09%
tlow study has been carried out of Jaipur city network
- 9.09%
II kV 10KV 12KV using MiPower software. Following two cases have been
+ 9.09%
deliberated in the load tlow study:
The single line diagram of Jaipur city presented in Case 1: Load tlow study of existing Jaipur city
Fig. 1 represent real time power system, grids with buses, network without shunt capacitor banks at 11 kV voItage
transformers and loads represented in colour specific level.
Case 11: Load tlow study of existing Jaipur city
codes.
n �tw�� �t� �hunt capacitor b�� �s at 11 kV voItage le� � .
. . _ _
. � .. ""'::
-� -
'- --- .
.l:
-- -�
.= " . - - --
=t" �
"!!.-.
--�' .
, _
-
-
,
� .
� - ...
" .
'J -r .,-r
_
". .,.. '; t T
_
, '"
"""'-w-
� .. . 5::�':;"_
""': . ...... : r ;T . ,...
�: ��
Fig. I: Single Line Diagram of Jaipur City N etwork Fig. 2: LFA Power Flow in MW & Mvar CASE-I
[21
t
1s IEEE International Conference on Power Electronics, Intelligent Control and Energy Systems (ICPEICES-2016)
.. '..... _ ...... '�,_.,"' ... , •• _ ••,., .... ", ................ ,u .... , _ . . .. _ .. __ _
5 Total Project Cost (3+4) 106550662.88
Rs. in
(Combined Capacity is 434.8 MVAr) I
Ten Crore Sixty Five Lakhs Fifty Thousand Seven
words Hundred & Sixty Two
On the basis of cost of 3 MVAR and l.6 MVAR
capacitor banks, the total cost of proposed shunt capacitor
banks which is to be installed in the Jaipur city network is
tabulated at Table 4.
An averagecost of 10 crores has to be invested to
provide loss reduction & energy savings in Jaipur City.
.=.:...• .:'
-,.. -.-
.:r."'!f "T
- T
C. Savings Obtained from Lass Reduction
.f..1"':R:.��.
T �
�.::t ·t��.. ....
"y
1
- .
;--: .:
.. ..
. - y
. .
.....
-...� � -.. -.- �.� .. ;�-.- :;�, .... In Case 11 total system losses are reduced as
� � ....':":"�.:'
Y"... ':;'a
. ""!I"".!• ;' ':I""T
-
ij-. T..-=-�. E��=' compared to Case I. The losses are reduced from 18.00
� ..:!" .;'" T .; :' ....
__
""'!'" ...- ..
_ _
n"' ::.a'
-�. ... ' E:.�i.=:;'
Sr. No. Particulars (lI kV Capacitor Bank) Cost(Rs.) E. Effect on Distribution Network Lines Loadings
I Cost of one 3 Mvar 671903 .02
2 Cost of one 1.6 Mvar 483958.12
The simulations studies for constant power load and
3 Cost of Total 106 Number of3 Mvar 71221720.12 capacitor bank placements at distribution level suggests a
(Total capacity 3 IBMvar) reduction in percentage of loading of network lines which
4 Cost of Total 73 Number of 1.6 Mvar 35328942.76 were previously in the zone of higher loading when the
(Total capacity I16.8 Mvar) system is operated without capacitor.
[31
t
1s IEEE International Conference on Power Electronics, Intelligent Control and Energy Systems (ICPEICES-2016)
TABLE 6: DISTRIBUTION LINE LOADINGS FOR CASE I & CASE II The power factor of transformers in Case 11 have been
Sr. No. No. orLines Loaded between Case I Case TI significantly improved as compared to Case I. For fixed
1 Above 75% 17 11 Power demand after switching the capacitor bank reactive
2 50% -75% 19 12
3 25%-50% 46 45 power tlow (MVAR) in system reduced as a resuIt of
4 01%-25% 46 60 compensation.
F. Effect on Min-Max Bus Voltage Limits VI. O PTIMAL UTILIZATION OF CAPACITOR BANK
The utilization of capacitor banks provided a line up The Utilities are advised to use capacitor banks to
control in the number of Iines which were on a verge of fulfill the reactive power requirements. Load growth
crossing minimum voItage limit the simulation studies maximizes the amount of reactive power demand (motors,
observes a better voItage profile with better utilization of compressors, etc.) in the system. Thus to provide reactive
capacitor banks. support to them capacitor banks are necessary, which will
TABLE 7: Bus VOLTAGE LIMITS FOR CASE I & CASE II
increase the voItage by around 0.5-2% in its nearby area.
Since there is no generation at any level, the voItage drops
on the network, across the transformer, and on the
secondary and service lines. Due to low network voItage,
G. Effect on Reactive Power Flow on Lines capacitor banks are being under-utilized. Capacitor banks
can be utilized up to their rated capacity by improving the
Capacitor banks inject reactive power in the system.
11 kV voItages.
For fixed reactive power demand after switching the
capacitor banks reactive power tlow in network lines Case Study is being performed on 11 kV voItage
reduced because reactive power part of load is profile of Jaipur city network by changing the swing bus
compensated by capacitor bank. Graphical representation voItage. Four different cases considered to visualize the
of reactive tlow studies for case I & 11 has been effect of optimum utilization of capacitor with a change in
represented in Fig. 4. voItage profile. The swing bus voItage has been varied in
Simulation studies indicate that reactive power tlow four cases (at 0.95, 0.97, 1.00, and 1.02) &load tlow
on network lines in Case 11 have been significantly studies for simulated model in each different sections have
reduced as compared to Case I. Numbered network lines been compared. The effect of Bus voItage on capacitor
has been represented. The fall of trend in graph c1early bank output as weil as the capacitor capacity utilization
depicts the amount of compensation being provided by factor has been represented in Table 8 & Table 9
using shunt capacitors & the amount of compensation respectively.
capable in maintaining the system power factor too. TABLE 8: EFFECT OF Bus VOLTAGE ON CAPACITOR BANK OUTPUT
30 ,-
-- Case Number Swin2 Bus Volta2e (pu) Total MVAr Generated
�WITHOUT CAPACITOR
25 +4.--- --- Case- I 0.95 354.535
_WITH CAPAcrrOR
20 +---��----
Case- 2 0.97 374.092
Case- 3 l.00 404.057
15 +-----�����-- Case-4 l.02 24.455
10 +-------���
Shunt capacitor bank Capacity utilization factor is
defined below.
actual output ofcapacitor bank
3 § � � g g § %CUF= 100
capacity ofcapacitor bank at nominal system volage
� � � � � � � � *
� � � �
00
� � � � �
� "l Cl � � � Cl Cl i!i � � � � � �
By using load tlow studies, CUF calculated as shown
Fig. 4: Reactive Flüw Studies für Case I & Case II
in Table 9.
TABLE 9: CAPACITOR UTiLIZATlON FACTOR
H Effect on Trans/armer Reactive Flows
,. Callacity
�WITHOUT CAPACITOR lllllllt Parameters %CUF
...... Utilizatioll Factor
12 _WITH CAPAcrrOR
10 \. Case 1
3 4. 34
5 5 * 100 81.54%
� =
434.80
=
6 374.092
Case 2 * 100 86 04%
•
434 .80
= = .
2 .......
....-.... J-&. -- 404.0 7
0 5 *
=
����0��#�����������
�/#�r��#//���/��//�
� �(:j
(0) q,q;. -4Q �� ����..:s � <:i�����4 � t:O� �� �v4
424 . 4
Case 4 55 * 100 97 62%
434.80
= = .
[41
t
1s IEEE International Conference on Power Electronics, Intelligent Control and Energy Systems (ICPEICES-2016)
[51
t
1s IEEE International Conference on Power Electronics, Intelligent Control and Energy Systems (ICPEICES-2016)
1.000 1.(191 0.'''''
1.000 1.(191 0.'''''
1.000 1.(191 0.'''''
1.000 1.(191 0.'''''
1.000 1.(191 0.'''''
1.000 1.(191 0.'''''
1.000 1.(191 0.'''''
1.000 1.(191 0.'''''
1.000 1.(191 0.'''''
1.000 1.(191 0.'''''
1.000 1.0'0 0.9<"
1.000 1.0'0 0.9<"
1.000 1.0'0 0.""
1.000 1.0'0 0.9<"
1.000 1.0'0 0.9<"
1.000 1.0'0 0.9<"
1.000 1.0'0 0.9<"
1.000 1.0'0 0.""
1.000 1.0'0 0.9<"
1.000 1.0'0 0.9<"
1.000 1.0'0 0.9<"
1.000 1.0'0 0.9<"
1.000 1.0'0 0.""
1.000 1.0'0 0.9<"
1.000 1.0'0 0.9<"
1.000 1.0'0 0.9<"
1.000 1.0'0 0.9<"
1.000 1.0'0 0.""
1.000 1.0'0 0.9<"
1.000 1.0'0 0.9<"
1.000 1.0'0 0.9<"
1.000 1.0'0 0.9<"
1.000 1.0'0 0.""
1.000 1.0'0 0.9<"
1.000 1.0'0 0.9<"
1.000 1.0'0 0.9<"
1.000 1.0'0 0.9<"
1.000 1.0'0 0.""
1.000 1.0'0 0.9<"
1.000 1.0'0 0.9<"
1.000 1.0'0 0.9<"
1.000 1.0'0 0.9<"
1.000 1.0'0 0.""
1.000 1.0'0 0.9<"
1.000 1.0'0 0.9<"
1.000 1.0'0 0.9<"
1.000 1.0'0 0.9<"
1.000 1.0'0 0.9<"
1.000 1.0'0 0.9<"
1.000 1.0'0 0.9<"
1.000 1.0'0 0.9<"
1.000 1.0'0 0.9<"
1.000 1.0'0 0.9<0
1.000 1.0'0 0.9<0
1.000 1.0'0 0.9<0
1.000 1.0'0 0.9<0
1.000 1.0'0 0.9<0
1.000 1.0'0 0.9<0
1.000 1.0'0 0.9<0
1.000 1.0'0 0.9<0
1.000 1.0'0 0.9<0
1.000 1.0'0 0.9<0
1.000 1.0'0 0.9<0
1.000 1.0'0 0.9<0
1.000 1.0'0 0.9<0
1.000 1.0'0 0.9<0
1.000 1.0'0 0.9<0
1.000 1.0'0 0.9<0
1.000 1.0'0 0.9<0
1.000 1.0'0 0.9<0
1.000 1.0'0 0.9<0
1.000 1.0'0 0.9<0
1.000 1.0'0 0.9<0
1.000 1.0'0 0.9<0
1.000 1.0'0 0.9<0
1.000 1.0'0 0.9<0
1.000 1.0'0 0.9<0
1.000 1.0'0 0.9<0
1.000 1.0'0 0.9<0
1.000 1.0'0 0.9<0
1.000 1.0'0 0.9<0
1.000 1.0'0 0.9<0
1.000 1.0'0 0.9<0
1.000 1.0'0 0.9<0
1.000 1.0'0 0.9<0
1.000 1.0'0 0.9<0
1.000 1.0'0 0.9<0
1.000 1.0'0 0.9<0
1.000 1.0'0 0.9<0
1.000 1.0'0 0.9<0
1.000 1.0'0 0.9<0
1.000 1.0'0 0.9<0
1.000 1.0'0 0.9<0
1.000 1.0'0 0.9<0
1.000 1.0'0 0.9<0
1.000 1.0'0 0.9<0
1.000 1.0'0 0.9<0
1.000 1.0'0 0.9<0
1.000 1.0'0 0.9<0
1.000 1.0'0 0.9<0
1.000 1.0'0 0.9<0
1.000 1.0'0 0.9<0
1.000 1.0'0 0.9<0
1.000 1.0'0 0.9<0
1.000 1.0'0 0.9<0
1.000 1.0'0 0.9<0
1.000 1.0'0 0.9<0
1.000 1.0'0 0.9<0
1.000 1.0'0 0.9<0
1.000 1.0'0 0.9<0
1.000 1.0'0 0.9<0
1.000 1.0'0 0.9<0
1.000 1.0'0 0.9<0
1.000 1.0'0 0.9<0
1.000 1.0'0 0.9<0
1.000 1.0'0 0.9<0
1.000 1.0'0 0.9<0
1.000 1.0'0 0.9<0
1.000 1.0'0 0.9<0
1.000 1.0'0 0.9<0
1.000 1.0'0 0.9<0
1.000 1.0'0 0.9<0
1.000 1.0'0 0.9<0
1.000 1.0'0 0.9<0
1.000 1.0'0 0.9<0
1.000 1.0'0 0.9<0
1.000 1.0'0 0.9<0
1.000 1.0'0 0.9<0
1.000 1.0'0 0.9<0
1.000 1.0'0 0.9<0 0.00 0.00
[6)