Beruflich Dokumente
Kultur Dokumente
1.0.0 SCOPE
1.1.0. This chapter covers the minimum requirements for the materials and
application of concrete coating to the exterior surface of line pipes to be used
for submerged crossing & water logged areas.
2.2.0 The concrete unit weight shall be minimum 2400 Kg/m 3 and the concrete mix
shall be 1:1½:3 (1 cement: 1½ coarse sand: 3 graded stone aggregates) with
cube compressive strength not less than 210 kg/cm2 in 28 days and 140
Kg/cm 2 in 7 days, during work tests conducted in accordance with IS: 516. The
specification of ingratiates of coating are as under:
a) Ordinary Portland cement in accordance with IS: 269 shall be used unless
otherwise specified. The acceptance, rejection, storage, preservations, etc.
shall comply with IS: 269 Cement, which has hardened or partially set, shall
not be used. Test certificates from the cement manufacturers are available &
checked for every lot of cement delivered to site.
b) Sand shall be clean and free from injurious amounts of salt, alkali, deleterious
substances or organic impurities and should conform to IS: 383. Sand shall be
tested for organic impurities as per IS: 2386 (part-II).
d) The water shall preferably be limpid, fresh and clean and shall not contain
chloride and Sulphates. It shall be free from magnesium salts. It shall conform
to the requirements specified in IS: 456. Water from each source shall be
should tested and test results shall be reviewed for their acceptability before
use.
e) Iron or Barium ore aggregate may be substituted for sand to produce a denser
concrete weight coating.
Page 1 of 13
CONSTRUCTION MANUAL-MAINLINE
PIPELINES DIVISION
2.3.0 Concrete coating shall be applied either using casting or impingement method
(as specified).
2.4.0 The equipment used for performing the concrete coating shall be capable of
doing so with a reasonable degree of uniformity with respect to thickness,
density and strength. The proportioning equipment and procedure shall be of
the type to assure consistently proportioned materials by weight and the mixes
and shall ensure through mixing of all materials. Any equipment that tends to
separate the ingredients shall not be used.
b) The type of mix, i.e. the correct combination of the cement, aggregates and
water is first determined and to this purpose, not less than five (5) samples of
concrete shall be prepared. For each mix the following shall be accurately
checked and recorded:
Page 2 of 13
CONSTRUCTION MANUAL-MAINLINE
PIPELINES DIVISION
c) Samples shall be prepared and tested in accordance with IS: 2386 (Part -III) to
determine the dry specific gravity of the concrete and the saturated weight after
immersion. Test for concrete specific gravity at intermediate time (7 days after
coating) shall be performed.
d) If the results of the above tests do not meet the requirements, the mix shall be
modified and concrete samples tested until a proper mix has been determined.
c) The calibration of the weight-batcher and the water meter shall be checked at
frequent intervals. Two test cylinders each per day shall be obtained from
Page 3 of 13
CONSTRUCTION MANUAL-MAINLINE
PIPELINES DIVISION
batches and tested at the end of seven (7) days after coating, for compressive
strength and specific gravity.
c) Pipes supported at their ends are adequately braced with interior struts or rings
to prevent undue flexure or ovality during coating and handling before
stockpiling.
2.6.3 REINFORCEMENT APPLICATION
a) Reinforcement is placed around the pipe in such a way as to cover the whole
pipe length or sections to be concrete coated. The reinforcement shall
terminate at a distance of 37.5 to 40 cm from the ends of each length of pipe.
b) When the concrete coating is formed in sections, steel reinforcement layers
shall not remain exposed in the spaces between continuous concrete coating
section.
c) When casting method is used for placing of concrete coating, reinforcement
shall rest on synthetic resin spacers forming a "crown" whose number shall be
such as to avoid any contact with the pipe's protective coating. Spacing
between the two consecutive "crown" centres shall be 500 to 1000 mm.
d) When impingement method is used for placing of concrete coating, placement
of reinforcement could start after first layer of concrete has been applied to the
pipe section, so that it has the same function of spacers. In this case, it shall be
ensured that there is no contact between steel reinforcement and pipe
protective coating.
Page 4 of 13
CONSTRUCTION MANUAL-MAINLINE
PIPELINES DIVISION
e) Splices and attachments is done by binding with soft steel wire of 1.5 mm
diameter. Circular and longitudinal joints of wire fabric in sheets are lapped at
least for one mesh. When wire fabric in rolls (ribbon mesh) is used, the spiral
lap shall be one mesh while the spliced lap shall be three meshes.
c) If casting method is used, once reinforcement and mould have been applied
around the pipe, concrete mix is poured through an opening on the upper
section of the same mould. Concrete shall not be poured from a height greater
than one (1) meter. During pouring of concrete, vibrator sets applied inside of
pipe or outside the mould shall vibrate the mix so as to obtain the best possible
compactness. Pouring rate and duration of vibration shall be such as to
achieve proper consolidation of concrete and to avoid over vibration, causing
segregation.
Page 5 of 13
CONSTRUCTION MANUAL-MAINLINE
PIPELINES DIVISION
g) All pipes are kept clean and free from cement concrete and grout either inside
or outside of the uncoated sections. Cement concrete and grout accidentally
present on said surfaces after concrete placing completion is fully removed
before their setting.
h) Metal bevel protectors are kept in place throughout the coating application and
after.
2.7.0 CURING
Page 6 of 13
CONSTRUCTION MANUAL-MAINLINE
PIPELINES DIVISION
and preferably before the pipe is removed from the concrete coating
apparatus. The surface of he concrete is lightly sprayed with water before
applying the curing compound. The membrane-curing period shall not be less
than 4 days, during which coated pipes shall not be disturbed and the pipe
surface is kept wet for seven (7) days after application of he concrete coating.
c) Before handling and hauling the concrete pipes, a check shall be made to
make sure that the concrete coating is cured. Stacking and shipment of the
coated pipes shall be initiated only after seven (7) days ensuring that the
concrete coating suffers no damage.
a) Minimum one test pipe shall be selected from the day's production during the
course of production. All weighing of concrete coated pipe lengths is performed
using suitable weighing device having an accuracy of one half of one percent
(0.5%). Calibration of the weighing device is checked at frequent intervals.
b) Also before delivering concrete coated pipes, every pipe length shall be
visually inspected to detect whether any damages and/or defects are present.
Repairable concrete shall be clearly marked, while the non-repairable ones
shall be removed from the pipe lengths.
c) One for every twenty concrete coated pipes, if the scale of work or production
is small, is subjected to water absorption test as follows:
Page 7 of 13
CONSTRUCTION MANUAL-MAINLINE
PIPELINES DIVISION
(i) The concrete pipe is weighed in air when dry and the weight recorded as "dry
weight".
(ii) The pipe length is completely submerged in water of known specific gravity.
2.10.1 The repairing of damaged concrete coating shall be carried out as permitted
and in the manner as outlined in approved procedure for the same.
2.11.1 Causes for the rejection of the concrete coating includes but not limited to the
following:
2.12.0 MARKING
2.12.1 Every concrete coated pipe length is clearly marked by a type of paint (i.e. red
and/or white lead paint). Markings out of concrete coating is made inside of
pipe close to bevel end, in such a way that the area involved by welding
operations is not affected by paint.
Page 8 of 13
CONSTRUCTION MANUAL-MAINLINE
PIPELINES DIVISION
2.12.2 For each concrete coated pipe length, at one of the two ends, the field
identification number and the date of concrete placing is marked, while the dry
as well as the wet weight along with number of days after coating is marked at
the other end.
5.0.0 EQUIPMENT/INSTRUMENTS
5.1.0 IOCL
5.2.0 CONTRACTOR
6.0.0 MANPOWER
6.1.0 IOCL
6.1.1 Engineer/Supervisor.
6.2.0 CONTRACTOR
Page 9 of 13
CONSTRUCTION MANUAL-MAINLINE
PIPELINES DIVISION
7.1.0 Before commencement of concrete coating, a trial coating and field as well as
laboratory tests is carried out for procedure qualification. Only approved
procedure shall be followed for production concrete coating.
7.2.0 Hardened or partially set cement is not used & test certificate from cement
manufacturers for each lot is verified before its use.
7.3.0 For concrete coating of pipes to be used in marshy areas and areas where
water is saline, sulphate resistant cement is used.
7.4.0 Fine aggregate of 10 mm nominal size graded from course aggregate is used
unless otherwise specified.
7.5.0 Sand to be used is clean & free-from salt, alkali, deleterious substances or
organic impurities. It is tested for organic impurities before use.
7.6.0 If required, iron or barium ore aggregate are used in place of sand for
producing a denser concrete weight coating.
7.7.0 Water to be used, is tested and reports verified. Water is limpid, fresh & clean
and does not contain chlorides, sulphates & magnesium salts.
7.8.0 When concrete coating is applied by casting method wire fabric (sheets) are
used and in case of application of coating by impingement method ribbon
mash (rolls) are used.
7.9.0 Unit weight of concrete is minimum 2400 kg/m 3 & concrete mix is 1: 1½: 3 (1
cement: 1½ course sand: 3 graded stone aggregate). The comprehensive
strength of cubes is not less than 210 kg/cm2 in 28 days & 140 kg/cm2 in 7
days.
7.10.0 The gap between continuous concrete weighting at the welding joints is
suitably filled as per approved method.
a) Field identification number, mill serial number, length, weight & nominal
average outside diameter of each line pipe. Concrete coating on any line pipe
Page 10 of 13
CONSTRUCTION MANUAL-MAINLINE
PIPELINES DIVISION
is not allowed until and unless this information has been recorded in the
logbook.
c) "Unit dry weight", "negative buoyancy" and "unit saturated weight" of each
concrete coated pipe.
7.12.0 It is ensured that weight-batcher and water meter is calibrated. The calibration
is checked at frequent intervals.
7.13.0 Prior to placing of reinforcement, the protective coating of each pipe is carefully
inspected and any damage is repaired before placing the concrete. All foreign
matters are removed from the surface of protective coating before placing the
concrete.
7.14.0 Pipe supports at the ends are adequately braced with interior struts or rings to
prevent undue flexure or ovality during coating and handling.
7.16.0 In case of casting method, the reinforcement rests on synthetic resin spacers
forming a "crown" whose number are such as to avoid any contact with the
pipe's protective coating. Spacing between to consecutive crowns are
minimum 500 to 1000 mm or as specified.
7.17.0 In case of impingement method, placement of reinforcement can start after first
layer of concrete has been applied on pipe. It is ensured that steel
reinforcement is not in contact with protective coating of pipe.
7.18.0 Concrete mix is placed on pipe within 45 minutes after adding water to mix.
Containers used for placing of concrete are continuously cleaned and are free-
from hardened or partially hardened concrete.
7.19.0 In case of casting method, concrete is not be poured from a height more than
one metre. During pouring, vibrator is run continuously. In case of impingement
Page 11 of 13
CONSTRUCTION MANUAL-MAINLINE
PIPELINES DIVISION
7.20.0 Casting is not interrupted or passes stopped for more than 45 minutes. If
interruption is for more than 45 minutes, before placing fresh concrete, the
c ontact surfaces is carefully cleaned at wetted to ensured good bond between
the fresh material and previously placed material.
7.21.0 At the time of casting or placing of concrete, it is ensured that the temperature
of coating does not exceed 32° C.
7.22.0 The coating at each end of the pipe is bevelled to a slope of 2: 1 and it is
terminated at about 100 mm short of the end of corrosion coating on the pipe
surface.
7.23.0 The exposed surface of concrete is protected from direct sunshine, drying
winds, rain, etc. The curing compound is applied immediately after completion
of coating. The membrane curing is not less than 4 days during which period
the coated pipe is not disturbed and exposed coating surface is kept wet for
seven (7) days.
7.24.0 The stacking and shipment of coated pipe is allowed only after seven days
provided the concrete coating surface suffers no damage.
7.25.0 Each concrete coated pipe is weighed as soon as it is feasible to move it for
taking wet weight and after 28 days of placement of concrete for dry weight.
These values should be marked with paint inside the pipe.
7.27.0 After curing, every concrete coated pipe is non-destructively tested by such
means as "ringing" to determine any defects present.
7.28.0 Each concrete coated pipe is visually inspected and also checked for insulation
between steel reinforcement and the pipe using a Megger.
7.29.0 Each concrete coated pipe is clearly marked with red or white paint inside the
pipe close to bevel end is such a way that the area involved by welding
operation is not affected by paint. At one of the ends, the field identification
number and the date of concrete placing is marked while at the other end dry
Page 12 of 13
CONSTRUCTION MANUAL-MAINLINE
PIPELINES DIVISION
as well as wet weight along with the number of days after which the weight was
taken, is marked.
8.0.0 RESPONSIBILITIES
Page 13 of 13
CONSTRUCTION MANUAL-MAINLINE