Beruflich Dokumente
Kultur Dokumente
Internship Report
By
TALHA ARSHAD
BSc. Electrical Engineering
Superior University, Lahore
Internship Program
Gujranwala Electric Power Company (GEPCO)
15 July to 31 August, 2015
Contents
About GEPCO……………………………………………………………………………………………………………………………….
1. Lectures………………………………………………………………………..............................................
1.2 Different Questions…………………………………………………..................................................
1.3 Grounding……………………………………………………………………………………………………………….
1.4 Environmental Engineering…………………………………......................................................
1.5 Transformers…………………………………………………………………………………………………………..
HAFIZABAD, MANDI BAHAWALDIN and GUJRAWALA. It Deals with 11kv and below
voltages till 2007. From 2007 onwards, it deals with 220kv and below voltages. In 2012,
with the help of USAID, new technologies including different software (ArcGIS +
Synergee Electric) were given to GEPCO.
GEPCO has total 56 Grid stations from which 52 are of 132kv and 4 are of 66kv, and
soon they will be upgraded to 132kv. These remaining grids of 66kv are in upgrading
process to 132kv. Furthermore it has 7 new Grid stations under construction. It has total
transmission line of 2500Km and about 175Km line is now under construction. WAPDA
provides 1700MV to GEPCO. While requirement is roundabout 2100MV.
Grounding is the process of removing the excess charge on an object by means of the
transfer of electrons between it and another object of substantial size. When a charged
object is grounded, the excess charge is balanced by the transfer of electrons between
the charged object and a ground.
This process of grounding works because excess electrons find each other repulsive. As
is always the case, repulsive affects between like-charged electrons forces them to look
for a means of spatially separating themselves from each other.
This spatial separation is achieved by moving to a larger object that allows a greater
surface area over which to spread. Because of the relative size of a person compared to
a typical electroscope, the excess electrons (nearly all of them) are capable of reducing
the repulsive forces by moving into the person (i.e., the ground).
Like contact charging discussed earlier, grounding is simply another example of charge
sharing between two objects. The extent to which an object is willing to share excess
charge is proportional to its size.
So an effective ground is simply an object with significant enough size to share the
overwhelming majority of excess charge.
Environmental Engineering
Environmental Engineering
2. WAPDA:
Water and Power Development Authority
The Water and Power Development Authority is a
government-owned public utility maintaining power and
water in Pakistan, although it does not manage thermal
power. WAPDA includes Tarbela and Mangla dams
among its resources.
3. FUNCTIONING:
Water dams
1. On Large Scale
2. On Small Scale
Power Wings
1. Transmission (NTDC)
2. Distribution (WAPDA)
Transformers
Transformers
Since the frequency of DC is zero so there will be no varying magnetic field and no voltage will
be produced on the secondary winding. and if we give DC to the input of transformer then
since the resistance of windings of transformer are very small and inductive reactance will b
zero then there will be a very huge current flow will occur through winding and it will burn.
XL = 2πfL
This inductive reactance limits the current in case of AC voltage.
There are three terminals at input of a transformer which are three phases while at output ,
there are four terminal and the fourth one is common(Ground).
Types of Transformer
Purpose of Transformer:
Delta connection:
No common terminal. Join end1 of one winding with the end2 of other winding and do it as
same for all windings. e.g.
Y-Connection:
Three phases and one common terminal. to make windings in Y-connected , short the
three same terminals of all windings. e.g
Environmental Effects:
We cannot neglect the effect of surroundings on our project because they are part of it.
When a project becomes finalized then ADB (Asian Development Bank ) passes budget
for project. First step is to purchase the piece of land.
Minimum 8 kanals’ of land is required for a Grid station but if 8 kanal’s are not available
like in big cities then we build smart Gird stations.
For placement of poles on a land, specific amount is given to the owner for the use of
land to place a pole for a specific time.
Civil people do all the work of construction.E.g.For building a transmission line in
Gujranwala, we cut about 190 trees and paid the money for these trees to the Forest
department of Pakistan. Costing about RS: 6000 per tree.