Beruflich Dokumente
Kultur Dokumente
0 1
RAPID P0022 0058 CON MST 0001 0001
OWNER Approval:
Name:
Date (DD-MMM-YY):
Signature:
Document Class: Z
MUHAMMAD PETRO
0 11-SEP-17 IFE – Issued For IMPLEMENTATION LUM TUCK KUEN
LUTFI ALEXANDER
MUHAMMAD PETRO
A 16-AUG-17 IFR – Issued For Review LUM TUCK KUEN
LUTFI ALEXANDER
DATE WRITTEN BY CHECKED BY APPROVED BY
REV. STATUS – REVISION MEMO
DD-MMM-YY (name & signature) (name & signature) (name & signature)
Sections changed in last revision are identified by a vertical line in the right margin.
0 2
RAPID P0022 0058 CON MST 0001 0001
HOLD’s
0 3
RAPID P0022 0058 CON MST 0001 0001
1 SCOPE 4
2 PURPOSE 4
3 PRE-REQUISITES 4
7 TESTS TO BE CONDUCTED 5
0 4
RAPID P0022 0058 CON MST 0001 0001
1 SCOPE
This procedure covers the Pre commissioning Test for Transformers.
2 PURPOSE
This procedure is prepared to carry out various pre- commissioning tests to be conducted in
systematic manner for Transformers to ensure the healthiness and performance of the equipment.
3 PRE-REQUISITES
0 5
RAPID P0022 0058 CON MST 0001 0001
4. Ensure protection MCB is provided in the circuit of AC supply used for testing
5. Ensure Proper Tools & Tackles are Available for carrying out Tests.
6. Ensure Proper PPE (Personal Protective Equipment) are used
7. Ensure the Healthiness of the test leads (Check for any insulation Damages).
8. Competent Authority to maintain shutdown & Work permit system in existing Live Bay
works.
9. Any conducting element should be carried horizontally at waist level in the area used for
pre commissioning tests.
7 TESTS TO BE CONDUCTED
1. Polarization Index Test (Insulation Resistance measurement Test).
2. Magnetic Balance Test.
3. Winding Resistance Test.
4. Turns ratio test
5. Vector Group Test.
6. Magnetizing Current Test.
Equipment’s required:
1. Insulation Tester
2. Test Leads
Test Procedure:
The polarization Index is nothing but the ratio of the insulation resistance measured at 10 minutes
to the 1 minute. The above test is to be conducted at the following points.
1. Windings of the transformer to earth.
2. Between HV and LV winding.
Windings to earth:
1. Connect the line terminal of the Megger to winding of the transformer.
0 6
RAPID P0022 0058 CON MST 0001 0001
Test Procedure:
1. Keep tap in normal position.
2. Apply A.C supply across one phase of the windings.
3. Measure the voltage on the other two phases of the windings.
4. Measure the voltage on the voltage induced on the other windings.
0 7
RAPID P0022 0058 CON MST 0001 0001
0 8
RAPID P0022 0058 CON MST 0001 0001
To ensure that the windings in the transformer are of same vector group as that mentioned in the
name plate.
Equipment’s required:
1. Multi-meter
2. Test Leads
Test Procedure:
This test is to confirm the Vector group of the transformer. This more crucial in sub-station where
transformers are paralleled together.
0 9
RAPID P0022 0058 CON MST 0001 0001
2. Repeat the test for other phases of the HV windings & other (IV & LV) windings of the
transformers.
3. The readings to be similar for all the phases of the windings.
Equipment’s required:
1. Transformer oil filter machine
2. Power supply DG set
3. BDV and PPM kit
4. Inlet and Outlet Oil hose
0 10
RAPID P0022 0058 CON MST 0001 0001
oil or BDV of transformer oil. Break down voltage is measured by observing at what
voltage, sparking straits between two electrodes emerged in the oil, separated by specific
gap.
2. Two standard-compliant test electrodes with a typical clearance of 2.5 mm are surrounded
by the dielectric oil. A test voltage is applied to the electrodes and is continuously
increased up to the breakdown voltage to a constant value.
3. Higher the moisture in the oil, lower will be the BDV for transformer oil. BDV of 50 kV and
above is considered good for operation while 60kV and above means the oil is in excellent
condition (when gap between terminals during BDV test is 2.5 mm).
0 11
RAPID P0022 0058 CON MST 0001 0001
3. It may also cause abnormal deterioration of paper used for insulation in the transformer
windings.