Beruflich Dokumente
Kultur Dokumente
0
1. Pressure source and test gauge should be upstream of check valve. If pressure
source is downstream, check valve should have apper removed or jacked?up.
(Pressure must be released downstream of check valve after test completion.)
2. Ensure that test blinds installed are the Correct thickness. Ensure that all items
such as control valves, relief valves, rupture disks, ori ce plates, diaphragm
instruments, expansion joints, etc., which could be damaged during pressure test
have been removed or isolated, as indicated on the pressure test ow diagram.
Ensure that equipment, such as lters, which have internals that may be damaged
during pressure.
3. Ensure that all items such as control valves, relief valves, rupture disks, ori ce
plates, diaphragm instruments, expansion joints, etc., which could be damaged
during pressure test have been removed or isolated, as indicated on the pressure
test ow diagram.
4. Ensure that equipment, such as lters, which have internals that may be damaged
during the pressure test are either blocked from test or that internals have been
removed.
https://qaqc-construction.com/qaqc-systems/piping-hydrostatic-testing-overview/ 1/13
11/9/2019 Piping Hydrostatic Testing (overview) | QA/QC Construction
5. Check all temporary supports that have been called for on the pressure test ow
diagrams, piping arrangement drawings or spool drawing to ensure that they have
been properly installed.
6. Ensure that equipment, such as compressors, which must not be included in the
eld tests have been properly blocked off with the casing drain open.
https://qaqc-construction.com/qaqc-systems/piping-hydrostatic-testing-overview/ 2/13
11/9/2019 Piping Hydrostatic Testing (overview) | QA/QC Construction
Testing
1. The pressure test gauge shall normally be located at grade near the test pump.
3. Care must be exercised not to exceed pressure test speci ed on the pressure test
data.
https://qaqc-construction.com/qaqc-systems/piping-hydrostatic-testing-overview/ 3/13
11/9/2019 Piping Hydrostatic Testing (overview) | QA/QC Construction
4. When conducting a pneumatic test, it is essential that the contract speci cation
for pneumatic testing be adhered to in order to avoid creating a safety hazard.
5. Pneumatic test systems must include double block valves with a bleeder valve
between them to safely isolate the pressure source (by closing block valves and
opening bleeder to atmosphere) when incremental and nal test pressures are
attained.
Test Completion
1. Care shall be exercised in controlling the rate of draining from vessels in respect to
in ow of air through the vent to assure that a vacuum is not applied.
2. CAUTION: Prior to commencing drainage, ensure that all vents are open with
plugs and blind anges removed.
3. After drainage, remove all temporary blinds and blanks, temporary support, and
temporary testing connections.
4. Reinstall all items that were removed for test. Ensure that line Speci cation
gaskets and bolts are being used when reinstalling these items.
https://qaqc-construction.com/qaqc-systems/piping-hydrostatic-testing-overview/ 4/13
11/9/2019 Piping Hydrostatic Testing (overview) | QA/QC Construction
Details of 5 incidents
https://qaqc-construction.com/qaqc-systems/piping-hydrostatic-testing-overview/ 5/13
11/9/2019 Piping Hydrostatic Testing (overview) | QA/QC Construction
https://qaqc-construction.com/qaqc-systems/piping-hydrostatic-testing-overview/ 6/13
11/9/2019 Piping Hydrostatic Testing (overview) | QA/QC Construction
https://qaqc-construction.com/qaqc-systems/piping-hydrostatic-testing-overview/ 7/13
11/9/2019 Piping Hydrostatic Testing (overview) | QA/QC Construction
4: Sphere collapse
The accident happened during the lling of a bar 2000 m LPG sphere. Its legs
collapsed. One person was killed and one seriously injured.
At the time of the accident, the sphere was approximately 80% full of fresh
water.
The vessel’s last hydro-test was 10 years ago and the last inspection of its legs
was 5 years ago.
Severe corrosion of the legs under the concrete re protection was the main
cause. The corrosion occurred due to water ingress between the concrete and
the steel legs.
https://qaqc-construction.com/qaqc-systems/piping-hydrostatic-testing-overview/ 8/13
11/9/2019 Piping Hydrostatic Testing (overview) | QA/QC Construction
The water protective cap located over the concrete was not suf cient to keep
water out. After the accident, it was veri ed that the steel legs had thickness
reductions of up to 8mm, with piting holes of up to 10cm .
After analysis and tests, it has been found that the following factors caused the
collapse:
Water caps over the re-proo ng concrete were of poor design thereby
letting water penetrate between the steel beams and the concrete.
Repairs had been done to the concrete, but with poor workmanship.
The concrete had not adhered to the old concrete, again letting water in.
The deluge system had been tested with salt water, increasing the possibility
of corrosion.
https://qaqc-construction.com/qaqc-systems/piping-hydrostatic-testing-overview/ 9/13
11/9/2019 Piping Hydrostatic Testing (overview) | QA/QC Construction
Sphere collapse
The gear box exploded, and threw missiles around seriously damaging
surrounding piping and structure. Fortunately there was no injury.
https://qaqc-construction.com/qaqc-systems/piping-hydrostatic-testing-overview/ 10/13
11/9/2019 Piping Hydrostatic Testing (overview) | QA/QC Construction
SPECIFIC RECOMMENDATIONS
For each case the speci c recommendation are generally obvious:
1st incident : Water tempearture is critical when hydro testing. TFE speci cation (GS
PVV 211) states taht both metal and water temperature during pressure testing shall
be maintained at least at 16ºC or at least 10ºC above the impact test temperature of
the metal.
2nd and 3rd incidents : Venting systems shall be inspected and checked before lling
and emptying operations.
5th incident : obviously a gear-box is not pressure vessel, but productivity may lead to
a risky attitude.
https://qaqc-construction.com/qaqc-systems/piping-hydrostatic-testing-overview/ 11/13