HARGA SATUAN BAHAN DAN UPAH (HSBU)

KOTA PANGKALPINANG
TAHUN 2017

NO. UPAH SATUAN


1 Mandor Lapangan OH
2 Mekanik OH
3 Mekanik Pembantu OH
4 Kepala tukang OH
5 Tukang OH
6 Operator Terlatih OH
7 Operator Kurang Terlatih OH
8 Pembantu Operator OH
9 Supir OH
10 Pembantu Supir / Kenek OH
11 Pekerja/ Buruh Lapangan Tak Terlatih OH
12 Buruh Lapangan Agak Terlatih OH
13 Buruh Lapangan Terlatih OH
14 Penjaga OH
15 Pemasak Aspal OH

NO. BAHAN / MATERIAL SATUAN


1 Aditive anti penglupasan Ltr
2 Alat Bantu set
3 Aluminium T = 0,8 mm m²
4 Amplas m'
5 Aquaprouf kg
6 Aquaprouf gln
7 Asbes gelombang besar kaki
8 Asbes gelombang kecil (lbr 105 cm) kaki
9 Aspal curah Kg
10 Aspal drum Kg
11 Aspal emulsi kg
12 Atap Aluminium gelombang = 0.55 mm m²
13 Atap Zinc Alum 0.3mm m²
14 Atap asbes gelombang uk 1,80 x 1,05 (m) tebal mm Lembar
15 Atap asbes gelombang uk 1,50 x 0,90 (m) tebal mm Lembar
16 Atap asbes gelombang uk 2,40 x 1,05 (m) tebal mm Lembar
17 Atap asbes gelombang uk 3,00 x 1,05 (m) tebal mm Lembar
18 Atap genteng beton (jenis press) Buah
19 Atap genteng kodok Buah
20 Atap genteng soka Buah
21 Atap metal (standar rainbow) Lembar
22 Atap metal Lembar
23 Atap metal berpasir Lembar
24 Atap polycarbonat M'
25 Atap seng gelombang bjls 20 uk 0,914 x 1,829 (m) Lembar
26 Ayakan pasir m'
27 Ayakan pasir m'
28 Baja Ringan m²
29 Bak cuci piring (sink) stainless steel 1 lobang bh
30 Bak cuci piring (sink) stainless steel 2 lobang bh
31 Bak cuci piring (stainless steel) bh
32 Bak fiberglass = 1 m³ bh
33 Bak Fiber 55x55 bh
34 Ban dalam Arco bh
35 Ban luar Arco bh
36 Ban luar Arco bh
NO. BAHAN / MATERIAL SATUAN
37 Bataco 9 X 15 X 38 Cm ( kosong ) Kp
38 Bataco 9 X 15 X 38 Cm ( padat ) Kp
39 Batu alam andesit m²
40 Batu alam palimanan m²
41 Batu bata besar (8x8x20) cm bh
42 Batu bata kecil (5x8x20) cm bh
43 Batu Belah / Batu Gunung 4 Kubik
44 Batu gunung 4 Kubik
45 Batu kerikil m³
46 Batu Kacang m³
47 Batu Pecah 1/2 4 Kubik
48 Batu pecah 2/3 4 Kubik
49 Batu pecah 3/5 4 Kubik
50 Batu pecah 3/5 m³
51 Batu Pecah 5/7 m³
52 Baut Dinabold 3" bh
53 Baut Klem Buah
54 Baut Ruping bh
55 Baut Screew canal bh
56 Baut Screew reng bh
57 Benang bh
58 Bensin / Premium ltr
59 Besi Beton kg
60 Besi beton D 6 mm Kg
61 Besi beton D 8 mm Kg
62 Besi beton D 10 mm Kg
63 Besi beton D 12 mm Kg
64 Besi beton D 16 mm Kg
65 Besi Hollow uk. 40 x 20 cm x 1,8 mm m
66 Besi Hollow uk. 40 x 40 cm x 2 mm m
67 Besi Kanal 100.50.5 btg
68 Besi Siku L.40.40.4 btg
69 Besi Siku L.30.30.3 btg
70 Besi Siku L.50.50.5 btg
71 Besi Siku L.70.70.7 btg
72 Bilksem spit penangkal petir Buah
73 Blind Flange Ø 100 mm unit

NO. BAHAN / MATERIAL SATUAN


74 Blind Flange Ø 150 mm unit
75 Blind Flange Ø 200 mm unit
76 Blind Flange Ø 250 mm unit
77 Blind Flange Ø 300 mm unit
78 Blind Flange Ø 50 mm unit
79 Blind Flange Ø 75 mm unit
80 Body kunci pilar merk "Morechi" set
81 Bola Lampu 18 watt merk Philips bh
82 Bola Lampu 8 watt merk Philips bh
83 Bola lampu pijar philips 40W bh
84 Bola Lampu SL. 24 watt bh
85 Box MCB Presto 4 Group bh
86 Box sekring, 1 phace Buah
87 Box sekring, 2 phace Buah
88 Bubungan atap (nok)genteng (standar KIA) bh
89 Bubungan atap (nok) genteng beton bh
90 Bubungan atap (nok) genteng kodok Bh
91 Bubungan atap (nok)genteng metal berpasir M
92 Bubungan atap (nok) metal (biasa/polos) M
93 Bubungan atap (nok) metal (standar rainbow) M
94 Calsiboard m²
95 Canal baja ringan @75.70 btg
96 Cat besi galvanis kg
97 Cat besi merk ' GENDANG" isi 5 liter gln
98 Cat besi merk "GENDANG" ltr
99 Cat besi merk "PLATONE" kg
100 Cat besi merk "PLATONE" isi 4 kg gln
101 Cat besi merk "PLATONE" pail
102 Cat coating Kg
103 Cat coating batu alam Merk Beta klg
104 Cat genteng (biasa) Kg
105 Cat genteng kw II Kg
106 Cat genteng special kg
107 Cat jembatan Kg
108 Cat menie Kg
109 Cat minyak Kg
110 Cat penutup Kg
111 Cat mengkilap/minyak merk Mowilex Kg
112 Cat mengkilap/minyak merk Platone Kg
113 Cat meni besi / kayu kg
114 Cat meni besi/kayu merk Gendang Kg
115 Cat minyak kuda terbang warna hijau uk.0,9L klg

NO. BAHAN / MATERIAL SATUAN


116 Cat minyak merk Platone ltr
117 Cat Perak kg
118 Cat tembok kg
119 Cat tembok merk " NIPPON " fiel
120 Cat tembok " EX PLATONE" Kg
121 Cat tembok EXT " EX MOWILEX " Kg
122 Cat tembok IN "EX MOWILOX " Kg
123 Cat tembok merk "KENLUX" isi 25 liter fiel
124 Cat vernis Kg
125 Cat tembok merk "Mowilex" isi 20 liter fiel
126 Cat tembok merk "NIPPON" 5 kg
127 Cat tembok merk "NIPPON" isi 25 liter fiel
128 Cat tembok merk "PLATONE" 5 kg
129 Cat tembok merk "PLATONE" isi 25 liter 20 Kg
130 Cat tembok merk BALILUX fiel
131 Cat tembok merk Dulux fiel
132 Cat tembok merk Lippo ltr
133 Cat tembok merk Nippon Q- Lux ltr
134 Cat tembok merk SANALUX isi 25 liter fiel
135 Cat tembok merk TULIP isi 25 liter fiel
136 Cat tembok merk Vinilux isi 25 liter fiel
137 Cat waterprofing 4 kg
138 Closed jongkok keramik leher bengkok bh
139 Closet duduk setara American Standard bh
140 Closet duduk keramik uk.Besar lengkap merk Toto set
Closet duduk keramik uk.Kecil + Tutup Merk American
141 bh
Standard
142 Closet duduk/Monoblock Buah
143 Closet duduk Monoblock merk Qolu 208 set
144 Closet jongkok keramik American Standard bh
145 Closet jongkok porcelaint (lokal) Bh
146 Compound gypsum sak
147 conblock tebal 6 cm (polos) m²
148 conblock tebal 6 cm (warna) m²
149 Daun pintu aluminium polos utk WC (80 x 200) cm bh
150 Daun pintu fiber (PVC) wc corak bh
151 Daun pintu fiber (PVC) wc polos bh
152 Dempul kg
153 Dempul kayu Kg
154 Dina bolt (ramsat) Unit
155 Dolken Kayu Ø 8 - 10 Cm btg
NO. BAHAN / MATERIAL SATUAN
156 Door closer Unit
157 Door stop Unit
158 Elbo 1 1/2" bh
159 Elbo 1 1/4" bh
160 Elbo 1" bh
161 Elbo 1/2" bh
162 Elbo 2 1/2" bh
163 Elbo 2" bh
164 Elbo 3" bh
165 Elbow uk.5/8 bh
166 Elbow 1/2 berderat bh
167 Elbow 2" bh
168 Ember cor bh
169 Engsel Pintu/jendela 3" Buah
170 Engsel Pintu/jendela 4" Buah
171 Engsel Pintu/jendela 5" Buah
172 Engsel putar jendela/ventilasi Buah
173 Eternit 1 x 1 m m²
174 Fibre plat 0,60 x 1,20 (m) m²
175 floor drain (besi) bh
176 floor drain (PVC) bh
177 Floor drain stenlies bh
178 Folding gate t = 0.4 mm m²
179 Folding gate t = 0.5 mm m²
180 Folding gate t = 0.8 mm m²
181 Frame saklar merk Panasonic bh
182 Gate valve/stop kran Ø 1/2 (inch) kuningan Bh
183 Gate valve/stop kran Ø 3/4 (inch) kuningan Bh
184 Genteng beton bh
185 Genteng beton minimalis kpg
186 Genteng bubungan keramik bh
187 Genteng bubungan soka bh
188 Genteng Keramik bh
189 Genteng Metal kpg
190 Genteng rabung Beton bh
191 Genteng soka / kodok bh
192 Gergaji Besi bh
193 Gerinda Bosch Gws 7.100 unit
194 Gerobak sorong (arco) merk Jago bh
195 Glassblok 20 x 20 cm Buah
196 Gorong - gorong Ø 100 Cm. bh
197 Gorong - gorong Ø 40 Cm. bh
198 Gorong - gorong Ø 60 Cm. bh
199 Gorong - gorong Ø 80 Cm. bh
NO. BAHAN / MATERIAL SATUAN
200 GRC board uk. (1 x 4) m2 kpg
201 Grendel (Biasa) bh
202 Grendel (Istimewa) bh
203 Grendel kuning biasa bh
204 Grendel kuningan bh
205 Gunting Canal bh
206 Gypsum board polos 1,22 x 2,44 (m) Lembar
207 Handle jendela Buah
208 Hendle pintu Buah
209 Handle untuk pintu kaca lebar Buah
210 Hallow semi galvanis Buah
211 Ijuk m²
212 Inbodus bulat bh
213 Isolasi kabel bh
214 Isolasi pipa bh
215 Jendela Rangka Aluminium, kaca T.5 mm < (60 cm) unit
216 Jendela Rangka Aluminium, kaca T.5 mm > (60 cm) unit
217 Jet Washer merk " Precio" bh
218 Kabel biasa 100 m
219 Kabel bulat 50 m
220 Kabel NYY 4 x 2,5 mm² m'
221 Kabel SR 2 x 10 m'
222 Kaca bening 3 mm m²
223 Kaca bening 5 mm m²
224 Kaca gelap (Ryben) tebal 5 mm m²
225 Kaca naco reben 5 mm (lengkap) Uk.15 x 70 cm + besi tengah bh
226 Kaca rayben 5 mm m²
227 Kaca Ryben 5 mm uk. 0,60 x 0,48 m2= 16 keping peti
228 Kaca Ryben 5 mm uk. 1,20 x 1,50 m2= 10 keping peti
229 Kaca wastafel bh
230 Kait kassa Kg
231 Kait angin biasa Buah
232 Kait angin istimewa Buah
233 Kapur sirih kg
234 Kapur talang m'
235 Karpet talang lebar 90 cm m'
236 Karpet talang T55/T90 m²
237 Kasau 4 x 6 btg
238 Kawat beton kg
239 Kawat duri 8 kg
240 Kawat harmonika m²
241 Kawat kassa/kawat loket m²

NO. BAHAN / MATERIAL SATUAN


242 Kawat las listrik Kg
243 Kawat nyamuk logam m²
244 Kawat nyamuk plastik m²
245 Kawat seng Kg
246 Kayu gergajian kelas I, balok m³
247 Kayu gergajian kelas I, papan m³
248 Kayu gergajian kelas II, balok m³
249 Kayu gergajian kelas II, papan m³
250 Kayu gergajian kelas IV, papan m³
251 Kayu reng 2 x 3 cm m³
252 Kayu reng 3 x 4 cm m³
253 Kayu untuk perancah m³
254 Kepek bh
255 Keramik 10x20 cm Bh
256 Keramik 20x20 cm corak m²
257 Keramik 20x20 cm polos m²
258 Keramik 20x25 cm corak m²
259 Keramik 20x25 cm polos m²
260 Keramik 30x30 cm corak m²
261 Keramik 30x30 cm polos m²
262 Keramik 40x40 cm corak m²
263 Keramik 40x40 cm polos m²
264 Keramik 60x60 cm ex indogres/nitogranit m²
265 Keramik 60x60 cm ex KIA polos m²
266 Keramik 60x60 Merk Nirogranite/ Granito m²
267 Keramik 60x60 Merk"Nirogranite" m²
268 Keramik Anti Gores 40/40 m²
269 Keramik Anti Gores 60/60 m²
270 Keramik KM/WC antislip uk. 20 x 20 m²
271 Keramik mozaik 30x30 cm Bh
272 Keran 1/2" bh
273 Keran 1/2" PVC merk Sunho bh
274 Keran air utk wastaffel bh
275 Klep uk. 1/2 kuningan utk mesin air bh
276 Knee / elbow PVC 1 (inch) bh
277 Knee / elbow PVC 1/2 (inch) bh
278 Knee / elbow PVC 3/4 (inch) bh
279 Kompon gypsum Kg
280 Kran air 3/4 Bh

NO. BAHAN / MATERIAL SATUAN


281 Kuas bh
282 Kuas 1,5" Ace bh
283 Kuas 2" Ace bh
284 Kuas 3" Ace bh
285 Kuas 3" Ace bh
286 Kuas 4" Ace bh
287 Kuas roll besar merk Ace bh
288 Kuas roll kecil Ace bh
289 Kuku keramik p=10 cm warna hitam bh
290 Kunci jendela bh
291 Kunci lemari set
292 Kunci pintu tanam (biasa) set
293 Kunci pintu tanam ( istimewa) set
294 Kunci selot Buah
295 Kunci tanam biasa Buah
296 Kusn, pintu fiber Unit
297 Kusen Aluminium T.3 Inci warna hitam m'
298 Kusen Aluminium T.3 Inci warna silver m'
299 Kusen Aluminium T.4 Inci warna coklat m'
300 Kusen Aluminium T.4 Inci warna hitam m'
301 Kusen Aluminium T.4 Inci warna silver m'
302 Lakban Dak Uk. 1" bh
303 Lakban Kertas Uk. 1" bh
304 Lampu baret 32 watt (lengkap) Titik
305 Lampu SL bulat 20 W + aksesories Titik
306 Lampu taman triple 20 W + aksesories Titik
307 Lampu 11 watt merk Philips bh
308 Lampu 14 watt merk Philips bh
309 Lampu 18 watt merk Philips bh
310 Lampu 19 watt merk Panasonic bh
311 Lampu 20 watt merk Visalux bh
312 Lampu 22 watt merk Panasonic bh
313 Lampu 23 watt merk Philips bh
314 Lampu 24 watt merk Visalux bh
315 Lampu 25 watt merk Panasonic bh
316 Lampu 5 watt merk Pilips bh
317 Lampu 8 watt merk Philips bh
318 Lampu pijar bh
319 Lampu TL 20 W Lengkap merk Philips bh
320 Lampu XL. 18 watt bh
321 Lem fox Kg
322 Lem kayu Kg
323 Lem pipa (kaleng kecil) klg
324 Lem pipa UK. 400 gr klg
325 Lis kayu kembang 5/7 m'

NO. BAHAN / MATERIAL SATUAN


326 Lis Kayu profil uk. 2 x 3 cm btg
327 Lis Kayu profil uk. 3 x 4 cm btg
328 Lis kayu profil uk. 3x3 cm btg
329 Lisplank Woodplank lebar 20 cm tektur p = 4 m' kpg
330 List Gypsum besar m'
331 List Gypsum sedang m'
332 Listplank GRC m'
333 Mata Potong keramik Bosch bh
334 MCB set
335 Melamin putih kpg
336 Mesin air jet pump merk "Simizu" set
337 Mesin Air panasonic 129 non Automatic unit
338 Metal Roof (Biasa) m²
339 Metal Roof (Pasir) m²
340 Minyak pelarut (solvent) Liter
341 Minyak cat ltr
342 Minyak Gemuk klg
343 Minyak gemuk kg
344 Multilplek 12 mm (4x8) Lembar
345 Multiplek 15 mm (4x8) Lembar
346 Multipleks 18 mm (4x8) Lembar
347 Multipleks 6 mm 1,22 x 2,44 m Lembar
348 Multipleks 9 mm 4x8 inch Lembar
349 Nat Keramik warna kuning merk AM bks
350 Pagar panel beton tinggi = 2 m m'
351 Paku anti karat Kg
352 Paku asbes kg
353 Paku berbagai ukuran (1/2”-1”) kg
354 Paku biasa 2”-5” kg
355 Paku jembatan kg
356 Paku sekrup 1 cm-2.5 cm kg
357 Paku seng bh
358 Paku tembok kg
359 Paku ulir kg
360 Paku ulir asbes Kg
361 Papan racuk 2x20x400 m³
362 Pasir Beton 6 Kubik
363 Pasir pasang 6 Kubik
364 Pasir urug 5 Kubik
365 Pengencer klg
366 Pengencer/thinner
367 Pintu alumunium corak untuk WC (80X200)cm Buah
368 Pintu alumunium lengkap (90x200)cm Buah
369 Pintu alumunium polos untuk WC (80X200)cm Buah
370 Pintu fiber PVC (70x200) wc corak Buah
371 Pintu fiber PVC (70x200) wc polos Buah
372 Pintu fiber PVC (80x200) wc corak Buah
373 Pintu fiber PVC (80x200) wc polos Buah
374 Pipa 1 1/2" merk Wavin btg
375 Pipa 1 1/2" merk UNILON btg
376 Pipa 1 1/4" merk Wavin btg
377 Pipa 1" merk Wavin btg
NO. BAHAN / MATERIAL SATUAN
378 Pipa 1" merk UNILON btg
379 Pipa 1/2" merk wavin btg
380 Pipa 2 "merk UNILON btg
381 Pipa 2" merk Wavin btg
382 Pipa 3" merk Wavin btg
383 Pipa 3" merk Unilon btg
384 Pipa 3/4" merk Wavin btg
385 Pipa 3/4"merk Unilon btg
386 Pipa besi galvanis Ø 1(inch) m'
387 Pipa besi galvanis Ø 2 (inch) m'
388 Pipa besi galvanis Ø 3 (inch) m'
389 Pipa besi galvanis Ø 4(inch) m'
390 Pipa PVC Ø 1 (inch) AW m'
391 Pipa PVC Ø 1.5 (inch) AW m'
392 Pipa PVC Ø 2 (inch) AW m'
393 Pipa PVC Ø 3 (inch) AW m'
394 Pipa PVC Ø 4-6 (inch) AW m'
395 Pipa PVC Ø 1/2 (inch) AW m'
396 Pipa PVC Ø 3/4 (inch) AW m'
397 Plamir tembok 25 kg
398 Plint keramik 10 x 30 cm (motif) Bh
399 Plint keramik 10 x 30 cm (polos) Bh
400 Plint keramik 10 x 40 cm (motif) Bh
401 Plint keramik 10 x 40 cm (polos) Bh
402 Plint keramik 10 x 60 cm Ex. indogress Bh
403 Plat besi 1,2 mm (4x8) kpg
404 Plat besi 1,5 mm (4X8) kpg
405 Plat besi 1,8 mm (4X8) kpg
406 Plat besi 2 mm (4X8) kpg
407 Plat besi 2,5 mm (4x8) kpg
408 Plat besi 3 mm (4x8) kpg
409 Plat besi 5 mm (4x8) kpg
410 Plat kembang 3 mm m²
411 Plywood 4 mm lbr
412 Plywood 9 mm lbr
413 Pompa air (dengan otomatis) Buah
414 Pompa air (jet pump) Buah
415 Pompa air (non otomatis) Buah
416 Porcelaint uk. 11x11 cm Buah
Rangka atap baja ringan (kuda-kuda, gording, assesories)
417 m²
galvanize
418 Reducer PVC dari ½ (inch) ke 1 (inch) Buah
419 Reducer PVC dari ½ (inch) ke 3/4 (inch) Buah
420 Reducer PVC dari ¾ (inch) ke 1 (inch) Buah
421 Rangka Besi Hollow + Plafond Gypsum m²
422 Reng baja ringan btg
423 Rel pintu dorong
424 Residu/ter Liter
425 Roll cat Liter
426 Rolling Door m²
427 Rooster keramik uk. 20x20 (cm) bh
428 Rooster keramik uk. 30x30 (cm) bh

NO. BAHAN / MATERIAL SATUAN


429 Rubber Bearing cm³
430 Rumah lampu down light bh
431 Saklar unit
432 Saklar Double Inbow Broco bh
433 Saklar Engkle Inbow Broco bh
434 Saklar Ganda unit
435 Sambungan pipa 3/4 ke 1/2 bh
436 Sdd 1/2" bh
437 SDL 1 1/4" bh
438 SDL 1" bh
439 Sealant Tube
440 Semen portland Kg
441 Semen putih 40 Kg
442 Semen warna Kg
443 Sekrup Gypsum ktk
444 Semen Holcim sak
445 Semen putih sak
446 Semen Tigaroda sak
447 Seng BJLS 28 lembar 90 cm Lember
448 Seng Aluminium 3 mm m²
449 Seng Fiber Fuso 10 kaki kpg
450 Seng gelombang Bjls 20 kaki
451 Seng gelombang Bjls 20 panjang 3 meter kpg
452 Seng plat 3x6' BJLS 28 m²
453 Seng Spandek tebal 0,3 panjang 6 m kpg
454 Shower + stop kran set
455 Shower bidet Buah
456 Shower mandi Buah
457 Sikat baja Buah
458 Shower WC bh
459 Skrup gypsum ktk
460 Skrup lisplank ktk
461 Slot jendela bh
462 Slot pintu Bh
463 Socket PVC Ø 1 (inch) bh
464 Socket PVC Ø ½ (inch) bh
465 Socket PVC Ø ¾ (inch) bh
466 Soda api Kg
467 Spring knip Buah
468 Steker arda Uticon bh
469 Stop kontak ganda/tiga bh
470 Stop kontak lantai bh
471 Stop kontak saklar bh
472 Stop kontak tunggal bh
473 Stop kontak ukntuk AC bh
474 Talang Karpet 55 cm m'
475 Talang seng m'
476 Tanah puru m³
477 Tangki air fiberglass (oranye) 1000 liter bh

NO. BAHAN / MATERIAL SATUAN


478 Tangki air fiberglass (oranye) 2000 liter bh
479 Tangki air fiberglass (oranye) 3000 liter bh
480 Tangki air fiberglass (oranye) 500 liter set
481 Tangki air /hydrant umum polyethylene 500 liter lbr
482 Tegel plint 10/20 cm bh
483 Tempat cat roll bh
484 Tempat handuk steenlis bh
485 Tempat sabun cair botol bh
486 Tempat sabun fisensi bh
487 Tempat sabun merk "Toto" bh
488 Ter kg
489 Ter kaleng besar klg
490 Thiner botol btl
491 Thiner cobrahitam 5 ltr klg
492 Timbunan tanah puru m³
493 Triplek tebal 2,5 mm uk 1,22 x 2,44 m Lembar
494 Triplek tebal 4 mm uk 1,22 x 2,44 m Lembar
495 Ubin abu - abu 20 x 20 cm buah
496 Ubin berwarna 20 x 20 cm buah
497 Urinoar bh
498 Vernis kg
499 Vitting Down Light uk. 4" merk Zetalux bh
500 Vitting Plafond segi empat merk Broco bh
501 Vlok 1/2 ke 3/4 bh
502 Vlok soket 2" ke 1 1/2" bh
503 Vlok soket 3/4" ke 1/2" bh
504 Westapel set
505 Water drain bh
506 Water drain + assesories Set
507 Water meter dia 1' + pipa gip Unit
497 SDL 1 1/4" bh
498 SDL 1" bh
499 Sealant Tube
500 Sekrup Gypsum ktk
501 Semen Holcim sak
502 Semen putih sak
503 Semen Tigaroda sak
504 Seng Fiber Fuso 10 kaki lbr
505 Seng fibreglass lbr
506 Seng plat BJLS 27 uk. 0.3 x 1.83 (m) lbr
507 Seng plat BJLS 27 uk. 0.9 x 1.83 (m) lbr
508 Sherra block bh
509 sikat baja bh
510 Sirtu m³
511 Skrup fixer bh
512 Skrup lisplank bh
513 Slot jendela 2" bh

NO. BAHAN / MATERIAL SATUAN


514 Slot pintu bh
515 Slot tanam merk " Ferza" set
516 Slot ventilasi / bouwvenlight bh
517 Socket PVC ø 1 (inch) bh
518 Socket PVC ø 1/2 (inch) bh
519 Socket PVC ø 3/4 (inch) bh
520 Soda api kg
521 Softboard uk. 1,20 x 2,40 (m), tebal 4 mm lbr
522 Soket D/L 1 x 1/2 bh
523 Soket keran uk 1/2 bh
524 soket pipa mesin air uk. 1/2 bh
525 spring Knip bh
526 Steker arda Uticon bh
527 Stone Coating kg
528 Stop kontak + instalasi titik
529 Stop kontak AC merk Panasonic bh
530 Stop kontak broco bh
531 Stop kran 3/4" bh
532 Streorox - 100 kg
533 Sunscreen alumunium m²
534 Support Pelintasan Pipa bh
535 T doos bh
536 Talang Alumunium m²
537 Talang Karpet lebar 55 cm (tebal) m'
538 Talang Karpet lebar 55 cm (tipis) m'
539 Talang seng (tebal) m'
540 Talang seng (tipis) m'
541 Tangki air / hydrant umum fiberglass 1.000 liter bh
542 Tangki air / hydrant umum fiberglass 2.000 liter bh
543 Tangki air / hydrant umum fiberglass 3.000 liter bh
544 Tangki air / hydrant umum fiberglass 6.000 liter (horizontal) bh
545 Tangki air / hydrant umum polyethylene 1.000 liter bh
546 Tangki air / hydrant umum polyethylene 2.000 liter bh
547 Tangki air / hydrant umum polyethylene 3.000 liter bh
548 Tangki air / hydrant umum polyethylene 4.000 liter bh
549 Tangki air / hydrant umum polyethylene 5.000 liter bh
550 Tangki air / hydrant umum polyethylene 500 liter bh
551 Tangki air 1000 liter merk "Tedmond" bh
552 Tangki air fiberglass (oranye) 2.000 liter bh
553 Tangki air fiberglass (oranye) 3.000 liter bh

NO. BAHAN / MATERIAL SATUAN


554 Tangki air fiberglass (oranye) 500 liter bh
555 Tangki HU 2000 Liter bh
556 Tangkiy 1000 L (oranye) bh
557 Tangkiy HU 1000 L bh
558 Tangkiy Oranye 2000 L bh
559 Tangky Oranye 500 L bh
560 Tarikan pintu 2 uk 45cm bulat set
561 Teak Oil ltr
562 Teak wood 0,30 x 0,60 (m), tebal 4 mm lbr
563 Teak wood 0,90 x 2,10 (m), tebal 4 mm lbr
564 Teak wood 1,20 x 2,40 (m), tebal 4 mm lbr
565 Tee 100 x 80 bh
566 Tee 80 x 50 bh
567 Tee all socket PVC ø 100 x 50 (mm) unit
568 Tee all socket PVC ø 225 x 100 (mm) unit
569 Tee all socket PVC ø 50 x 50 (mm) unit
570 Tee all socket PVC ø 80 x 50 (mm) unit
571 TEE PVC 100 x 100 bh
572 TEE PVC 80 x 80 bh
573 Tee Y 100 x 100 bh
574 Tempat cat roll bh
575 Tempat sabun keramik bh
576 Tempat sabun merk "Toto" bh
577 Ter Kg
578 Teralis jendela lbg
579 Teralis pintu lbg
580 Thiner botol btl
581 Thiner Cobrahitam 5 ltr klg
582 Timbunan biasa m³
583 Timbunan pilihan / tanah puru m³
584 Triplek 12 mm lbr
585 Triplek 15 mm lbr
586 Triplek 2,2 mm lbr
587 Triplek 3,0 mm lbr
588 Triplek 4,0 mm lbr
589 Triplek 6,0 mm lbr
590 Triplek 9,0 mm lbr
591 Ubin abu-abu 20 x 20 (cm) bh
592 Ubin berwarna 20 x 20 (cm) bh
593 Ubin motif (mozaik) m²

NO. BAHAN / MATERIAL SATUAN


594 Ubin wafel bh
595 Urinoir unit
596 Venetion blinds m²
597 Vertical blinds m²
598 Vlok 1/2 ke 3/4 bh
599 Vlok soket 2" ke 1 1/2" bh
600 Vlok soket 3/4" ke 1/2" bh
601 Wallpaper bermotif m²
602 Wallpaper polos m²
603 Water Meter 3/4 bh
604 water meter dia 1"+pipa gip unit
605 Westapel keramik uk.besar bh
606 Westapel keramik uk.Kecil bh

NO. PERALATAN (BIAYA PEMILIKAN DAN OPERASI) SATUAN

1 ASPHALT MIXING PLANT jam


2 ASPHALT FINISHER jam
3 ASPHALT SPRAYER jam
4 BULLDOZER 100-150 HP jam
5 COMPRESSOR 4000-6500 L\M jam
6 CONCRETE MIXER 0.3-0.6 M3 jam
7 CRANE 10-15 TON jam
8 DUMP TRUCK 3-4 M3 jam
9 DUMP TRUCK jam
10 EXCAVATOR 80-140 HP jam
11 FLAT BED TRUCK 3-4 M3 jam
12 GENERATOR SET jam
13 MOTOR GRADER >100 HP jam
14 TRACK LOADER 75-100 HP jam
15 WHEEL LOADER 1.0-1.6 M3 jam
16 THREE WHEEL ROLLER 6-8 T jam
17 TANDEM ROLLER 6-8 T. jam
18 TIRE ROLLER 8-10 T. jam
19 VIBRATORY ROLLER 5-8 T. jam
20 CONCRETE VIBRATOR jam
21 STONE CRUSHER jam
22 WATER PUMP 70-100 mm jam
23 WATER TANKER 3000-4500 L. jam
24 PEDESTRIAN ROLLER jam
25 STAMPER jam
26 JACK HAMMER jam
27 FULVI MIXER jam
28 CONCRETE PUMP jam
29 TRAILER 20 TON jam
30 PILE DRIVER + HAMMER jam
31 CRANE ON TRACK 35 TON jam
32 WELDING SET jam
33 BORE PILE MACHINE jam
34 ASPHALT LIQUID MIXER jam
35 BORE PILE MACHINE jam
36 BLENDING EQUIPMENT jam
BU)

HARGA DASAR
Rp 133,100.00
Rp 133,100.00
Rp 108,900.00
Rp 145,200.00
Rp 121,000.00
Rp 121,000.00
Rp 96,800.00
Rp 96,800.00
Rp 108,900.00
Rp 96,800.00
Rp 96,800.00
Rp 96,800.00
Rp 108,900.00
Rp 108,900.00
Rp 108,900.00

HARGA DASAR
Rp 65,000.00
Rp 176,000.00
Rp 176,000.00
Rp 10,000.00
Rp 50,000.00
Rp 186,000.00
Rp 16,500.00
Rp 9,000.00
Rp 1,851,000.00
Rp 2,001,000.00
Rp 261,000.00
Rp 161,500.00
Rp 56,000.00
Rp 54,600.00
Rp 65,400.00
Rp 72,800.00
Rp 91,000.00
Rp 6,150.00
Rp 4,000.00
Rp 4,000.00
Rp 40,000.00
Rp 30,000.00
Rp 46,000.00
Rp 2,150,000.00
Rp 17,000.00
Rp 20,000.00
Rp 21,250.00
Rp 171,000.00
Rp 100,000.00
Rp 450,000.00
Rp 449,000.00
Rp 83,500.00
Rp 175,000.00
Rp 20,000.00
Rp 35,000.00
Rp 41,000.00
HARGA DASAR
Rp 1,900.00
Rp 1,900.00
Rp 201,000.00
Rp 151,000.00
Rp 1,200.00
Rp 2,250.00
Rp 1,000,000.00
Rp 1,000,000.00
Rp 301,000.00
Rp 171,000.00
Rp 350,000.00
Rp 350,000.00
Rp 350,000.00
Rp 326,000.00
Rp 281,000.00
Rp 1,500.00
Rp 25,750.00
Rp 500.00
Rp 180.00
Rp 170.00
Rp 3,000.00
Rp 8,600.00
Rp 15,500.00
Rp 23,750.00
Rp 36,500.00
Rp 55,000.00
Rp 75,500.00
Rp 147,500.00
Rp 38,000.00
Rp 49,000.00
Rp 1,123,000.00
Rp 100,000.00
Rp 55,000.00
Rp 174,250.00
Rp 482,250.00
Rp 111,000.00
Rp 81,000.00

HARGA DASAR
Rp 141,000.00
Rp 191,000.00
Rp 271,000.00
Rp 281,000.00
Rp 71,000.00
Rp 81,000.00
Rp 165,000.00
Rp 35,000.00
Rp 27,500.00
Rp 13,500.00
Rp 46,000.00
Rp 35,000.00
Rp 53,500.00
Rp 53,500.00
Rp 5,000.00
Rp 6,500.00
Rp 5,000.00
Rp 27,000.00
Rp 22,000.00
Rp 33,000.00
Rp 68,000.00
Rp 67,000.00
Rp 50,000.00
Rp 85,500.00
Rp 28,750.00
Rp 51,250.00
Rp 207,500.00
Rp 411,000.00
Rp 51,000.00
Rp 70,000.00
Rp 140,000.00
Rp 33,000.00
Rp 170,000.00
Rp 51,000.00
Rp 35,000.00
Rp 50,000.00
Rp 50,500.00
Rp 80,000.00
Rp 50,000.00
Rp 35,000.00
Rp 26,750.00
Rp 51,500.00

HARGA DASAR
Rp 49,500.00
Rp 50,000.00
Rp 48,000.00
Rp 325,000.00
Rp 241,714.29
Rp 230,000.00
Rp 148,000.00
Rp 136,000.00
Rp 50,000.00
Rp 1,055,000.00
Rp 84,000.00
Rp 325,000.00
Rp 84,000.00
Rp 325,000.00
Rp 220,000.00
Rp 1,851,000.00
Rp 17,000.00
Rp 258,000.00
Rp 176,000.00
Rp 200,000.00
Rp 600,000.00
Rp 200,000.00
Rp 170,000.00
Rp 650,000.00
Rp 2,250,000.00
Rp 725,000.00
Rp 1,000,000.00
Rp 1,451,000.00
Rp 425,000.00
Rp 120,000.00
Rp 75,000.00
Rp 1,550.00
Rp 1,950.00
Rp 201,000.00
Rp 277,500.00
Rp 212,500.00
Rp 46,000.00
Rp 35,000.00
Rp 1,500.00
Rp 25,000.00
HARGA DASAR
Rp 122,500.00
Rp 33,500.00
Rp 5,000.00
Rp 4,000.00
Rp 4,000.00
Rp 2,250.00
Rp 9,500.00
Rp 6,500.00
Rp 14,000.00
Rp 500.00
Rp 3,000.00
Rp 7,000.00
Rp 6,000.00
Rp 30,000.00
Rp 40,000.00
Rp 50,000.00
Rp 11,000.00
Rp 21,000.00
Rp 70,000.00
Rp 30,000.00
Rp 15,000.00
Rp 85,000.00
Rp 716,000.00
Rp 936,000.00
Rp 1,101,000.00
Rp 10,000.00
Rp 57,500.00
Rp 86,000.00
Rp 6,000.00
Rp 5,500.00
Rp 21,000.00
Rp 6,500.00
Rp 12,000.00
Rp 30,000.00
Rp 6,500.00
Rp 5,125.00
Rp 24,500.00
Rp 775,000.00
Rp 470,000.00
Rp 23,000.00
Rp 551,000.00
Rp 342,000.00
Rp 435,500.00
Rp 496,000.00
HARGA DASAR
Rp 29,600.00
Rp 10,000.00
Rp 30,000.00
Rp 6,500.00
Rp 15,300.00
Rp 160,000.00
Rp 66,250.00
Rp 8,500.00
Rp 125,000.00
Rp 126,000.00
Rp 21,000.00
Rp 13,000.00
Rp 100.00
Rp 10,000.00
Rp 4,000.00
Rp 276,000.00
Rp 551,000.00
Rp 60,000.00
Rp 190,000.00
Rp 210,000.00
Rp 25,000.00
Rp 6,000.00
Rp 96,000.00
Rp 133,500.00
Rp 1,501,000.00
Rp 36,200.00
Rp 188,000.00
Rp 177,000.00
Rp 1,651,000.00
Rp 300,000.00
Rp 18,000.00
Rp 5,000.00
Rp 18,000.00
Rp 61,000.00
Rp 10,333.33
Rp 20,000.00
Rp 20,000.00
Rp 30,000.00
Rp 16,500.00
Rp 135,000.00
Rp 23,000.00
Rp 25,000.00

HARGA DASAR
Rp 30,000.00
Rp 40,000.00
Rp 25,000.00
Rp 16,000.00
Rp 76,000.00
Rp 29,000.00
Rp 36,000.00
Rp 41,000.00
Rp 11,000.00
Rp 14,333.33
Rp 20,333.33
Rp 26,000.00
Rp 6,500.00
Rp 3,500.00
Rp 59,000.00
Rp 49,500.00
Rp 58,000.00
Rp 55,000.00
Rp 58,000.00
Rp 47,000.00
Rp 60,000.00
Rp 52,000.00
Rp 330,000.00
Rp 171,000.00
Rp 275,000.00
Rp 275,000.00
Rp 142,000.00
Rp 186,000.00
Rp 55,500.00
Rp 6,000.00
Rp 16,000.00
Rp 16,500.00
Rp 65,000.00
Rp 49,000.00
Rp 4,000.00
Rp 2,250.00
Rp 2,750.00
Rp 4,500.00
Rp 19,000.00

HARGA DASAR
Rp 17,000.00
Rp 15,000.00
Rp 18,750.00
Rp 30,000.00
Rp 29,500.00
Rp 36,500.00
Rp 33,500.00
Rp 19,500.00
Rp 700.00
Rp 8,500.00
Rp 20,000.00
Rp 135,000.00
Rp 300,000.00
Rp 30,000.00
Rp 8,500.00
Rp 239,333.33
Rp 56,000.00
Rp 51,000.00
Rp 101,000.00
Rp 101,000.00
Rp 96,000.00
Rp 12,500.00
Rp 4,000.00
Rp 32,000.00
Rp 30,000.00
Rp 33,000.00
Rp 30,000.00
Rp 31,500.00
Rp 35,000.00
Rp 37,000.00
Rp 37,000.00
Rp 42,000.00
Rp 38,000.00
Rp 37,000.00
Rp 44,000.00
Rp 25,000.00
Rp 27,500.00
Rp 7,500.00
Rp 86,000.00
Rp 33,000.00
Rp 16,000.00
Rp 42,500.00
Rp 6,000.00
Rp 36,000.00
Rp 39,000.00

HARGA DASAR
Rp 20,000.00
Rp 24,000.00
Rp 18,000.00
Rp 65,000.00
Rp 19,000.00
Rp 16,000.00
Rp 61,000.00
Rp 110,000.00
Rp 46,000.00
Rp 125,000.00
Rp 1,750,000.00
Rp 410,000.00
Rp 30,000.00
Rp 42,000.00
Rp 7,000.00
Rp 7,000.00
Rp 26,000.00
Rp 61,000.00
Rp 175,000.00
Rp 230,000.00
Rp 262,500.00
Rp 100,000.00
Rp 150,000.00
Rp 13,000.00
Rp 401,000.00
Rp 18,000.00
Rp 20,000.00
Rp 30,000.00
Rp 11,500.00
Rp 19,333.33
Rp 60,000.00
Rp 20,000.00
Rp 47,000.00
Rp 25,000.00
Rp 20,000.00
Rp 32,000.00
Rp 350,000.00
Rp 350,000.00
Rp 235,000.00
Rp 7,000.00
Rp 14,250.00
Rp 513,500.00
Rp 1,076,000.00
Rp 192,666.67
Rp 325,000.00
Rp 225,000.00
Rp 228,500.00
Rp 221,000.00
Rp 56,500.00
Rp 55,000.00
Rp 51,000.00
Rp 34,500.00
HARGA DASAR
Rp 31,000.00
Rp 18,500.00
Rp 67,000.00
Rp 72,000.00
Rp 147,500.00
Rp 131,000.00
Rp 25,500.00
Rp 24,000.00
Rp 160,000.00
Rp 250,000.00
Rp 400,000.00
Rp 550,000.00
Rp 36,000.00
Rp 58,000.00
Rp 73,000.00
Rp 150,000.00
Rp 236,000.00
Rp 19,000.00
Rp 26,000.00
Rp 200,000.00
Rp 6,000.00
Rp 6,000.00
Rp 6,000.00
Rp 6,000.00
Rp 4,000.00
Rp 421,000.00
Rp 501,000.00
Rp 596,000.00
Rp 621,000.00
Rp 826,000.00
Rp 901,000.00
Rp 1,451,000.00
Rp 1,071,000.00
Rp 85,000.00
Rp 150,000.00
Rp 560,000.00
Rp 1,650,000.00
Rp 420,000.00
Rp 61,000.00
Rp 75,500.00
Rp 4,000.00
Rp 3,000.00
Rp 4,000.00
Rp 121,000.00
Rp 36,000.00
Rp 185,000.00
Rp 46,000.00
Rp 32,250.00
Rp 276,000.00
Rp 40,000.00
Rp 55,000.00

HARGA DASAR
Rp 1,365.00
Rp 32,000.00
Rp 20,000.00
Rp 20,000.00
Rp 15,000.00
Rp 20,000.00
Rp 3,000.00
Rp 2,500.00
Rp 7,000.00
Rp 4,000.00
Rp 25,000.00
Rp 70,500.00
Rp 115,000.00
Rp 13,000.00
Rp 72,500.00
Rp 62,000.00
Rp 112,500.00
Rp 63,000.00
Rp 21,000.00
Rp 73,500.00
Rp 126,000.00
Rp 7,000.00
Rp 58,000.00
Rp 28,000.00
Rp 330,000.00
Rp 175,000.00
Rp 70,000.00
Rp 100,000.00
Rp 10,000.00
Rp 70,000.00
Rp 60,000.00
Rp 75,000.00
Rp 10,000.00
Rp 18,000.00
Rp 4,000.00
Rp 2,500.00
Rp 3,000.00
Rp 18,000.00
Rp 20,000.00
Rp 10,000.00
Rp 11,000.00
Rp 11,000.00
Rp 11,000.00
Rp 15,000.00
Rp 75,000.00
Rp 15,000.00
Rp 22,500.00
Rp 51,000.00
Rp 1,350,000.00

HARGA DASAR
Rp 2,750,000.00
Rp 4,200,000.00
Rp 850,000.00
Rp 91,000.00
Rp 6,000.00
Rp 1,700.00
Rp 275,000.00
Rp 75,000.00
Rp 61,000.00
Rp 131,000.00
Rp 91,000.00
Rp 110,000.00
Rp 7,000.00
Rp 125,000.00
Rp 51,000.00
Rp 55,000.00
Rp 85,000.00
Rp 56,000.00
Rp 56,000.00
Rp 1,911,000.00
Rp 50,000.00
Rp 32,000.00
Rp 10,000.00
Rp 3,000.00
Rp 6,000.00
Rp 30,000.00
Rp 826,000.00
Rp 21,000.00
Rp 21,000.00
Rp 21,000.00
Rp 7,000.00
Rp 4,000.00
Rp 25,000.00
Rp 60,000.00
Rp 62,000.00
Rp 112,500.00
Rp 63,000.00
Rp 110,000.00
Rp 63,150.00
Rp 41,480.00
Rp 51,600.00
Rp 2,834.80
Rp 9,000.00
Rp 138,610.00
Rp 2,100.00
Rp 1,600.00
Rp 8,500.00

HARGA DASAR
Rp 18,000.00
Rp 65,000.00
Rp 11,752.50
Rp 400.00
Rp 2,500.00
Rp 3,000.00
Rp 18,000.00
Rp 67,000.00
Rp 3,000.00
Rp 3,000.00
Rp 3,000.00
Rp 20,000.00
Rp 9,000.00
Rp 70,000.00
Rp 159,378.00
Rp 75,000.00
Rp 15,000.00
Rp 15,000.00
Rp 7,704.50
Rp 1,623,500.00
Rp 721,500.00
Rp 1,500.00
Rp 41,000.00
Rp 15,000.00
Rp 9,000.00
Rp 55,000.00
Rp 37,500.00
Rp 1,350,000.00
Rp 2,750,000.00
Rp 4,200,000.00
Rp 21,189,000.00
Rp 1,350,000.00
Rp 2,750,000.00
Rp 4,200,000.00
Rp 7,741,535.00
Rp 9,049,545.00
Rp 850,000.00
Rp 1,350,000.00
Rp 2,750,000.00
Rp 4,200,000.00

HARGA DASAR
Rp 850,000.00
Rp 5,391,000.00
Rp 1,300,000.00
Rp 2,751,000.00
Rp 2,750,000.00
Rp 850,000.00
Rp 250,000.00
Rp 3,200.00
Rp 52,865.00
Rp 83,500.00
Rp 160,000.00
Rp 326,600.00
Rp 191,575.00
Rp 447,545.00
Rp 447,545.00
Rp 226,170.00
Rp 352,670.00
Rp 369,500.00
Rp 213,850.00
Rp 266,375.00
Rp 18,000.00
Rp 35,000.00
Rp 80,000.00
Rp 16,000.00
Rp 276,000.00
Rp 688,500.00
Rp 7,000.00
Rp 125,000.00
Rp 39,500.00
Rp 67,000.00
Rp 190,000.00
Rp 245,000.00
Rp 56,000.00
Rp 55,000.00
Rp 85,000.00
Rp 100,000.00
Rp 150,000.00
Rp 7,578.00
Rp 9,804.40
Rp 112,320.00

HARGA DASAR
Rp 7,578.00
Rp 1,016,795.00
Rp 81,960.00
Rp 64,250.00
Rp 3,000.00
Rp 6,000.00
Rp 3,000.00
Rp 201,000.00
Rp 38,950.00
Rp 833,150.00
Rp 605,670.00
Rp 1,501,000.00
Rp 601,000.00

BIAYA
OPERASIONAL /
SEWA
Rp 5,232,308.86
Rp 392,030.51
Rp 84,175.31
Rp 622,230.79
Rp 170,269.58
Rp 108,171.74
Rp 518,932.74
Rp 255,663.39
Rp 462,895.88
Rp 674,624.30
Rp 394,439.74
Rp 437,845.32
Rp 777,022.26
Rp 450,949.75
Rp 534,530.14
Rp 190,773.88
Rp 275,356.63
Rp 335,917.57
Rp 355,780.63
Rp 38,187.32
Rp 853,015.42
Rp 32,353.55
Rp 231,696.34
Rp 57,017.69
Rp 42,774.27
Rp 23,315.76
Rp 816,085.13
Rp 225,866.55
Rp 414,697.83
Rp 160,160.79
Rp 591,200.92
Rp 92,638.12
Rp 1,097,738.21
Rp 32,705.11
Rp 591,356.21
Rp 188,547.89
KODE HARGA SATUAN (Rp.)
URAIAN PEKERJAAN
ANAL BAHAN UPAH

A PEKERJAAN PERSIAPAN

A.1 1 m² Pembuatan Pagar Sementara dari Seng Gelombang tinggi 2 meter


0.2000 Oh Pekerja 96,800.00
0.4000 Oh Tukang Kayu 121,000.00
0.0200 Oh Kepala Tukang 145,200.00
0.0200 Oh Mandor 133,100.00
1.2500 Btg Dolken Kayu dia.8-10/400cm 16,800.00
2.5000 Kg Semen Portland 1,668.00
1.2000 Lbr Seng Gelombang 60,000.00
0.0050 M³ Pasir Beton 162,748.88
0.0090 M³ Batu Pecah 3 - 5cm 455,000.00
0.0720 M³ Kayu Balok kls. III 2,880,000.00
0.0600 Kg Paku Biasa 2"-5" 16,200.00
0.4500 Ltr Residu / Ter 15,840.00
JUMLAH

A.2 1 m² Pembuatan Pagar Sementara dari Kawat duri tinggi 1,8 meter
0.2000 Oh Pekerja 96,800.00
0.3000 Oh Tukang Kayu 121,000.00
0.0200 Oh Kepala Tukang 145,200.00
0.0200 Oh Mandor 133,100.00
1.0000 Btg Dolken Kayu dia.8-10/400cm 16,800.00
2.0000 Kg Semen Portland 1,668.00
25.0000 M' Kawat Duri 22,212.00
0.0050 M³ Pasir Beton 162,748.88
0.0090 M³ Batu Pecah 3 - 5cm 455,000.00
0.0600 Kg Paku Biasa 2"-5" 16,200.00
JUMLAH
KODE HARGA SATUAN (Rp.)
URAIAN PEKERJAAN
ANAL BAHAN UPAH

A.3 1 m' Pengukuran & Pemasangan Bowplank


0.1000 Oh Pekerja 96,800.00
0.1000 Oh Tukang Kayu 121,000.00
0.0100 Oh Kepala Tukang 145,200.00
0.0050 Oh Mandor 133,100.00
0.0120 M³ Kayu Balok kls. IV 2,070,000.00
0.0200 Kg Paku Biasa 2"-5" 16,200.00
0.0070 M³ Kayu Papan Kls. IV 1,920,000.00
JUMLAH

A.4 1 m² Pembuatan Kantor Sementara Lantai Plesteran


2.0000 Oh Pekerja 96,800.00
2.0000 Oh Tukang Kayu 121,000.00
1.0000 Oh Tukang batu 129,300.00
0.3000 Oh Kepala Tukang 145,200.00
0.0500 Oh Mandor 133,100.00
1.2500 Btg Dolken Kayu dia.8-10/400cm 16,800.00
0.1800 M³ Kayu Papan Kls. III 2,310,000.00
0.0800 Kg Paku Biasa 2"-5" 16,200.00
1.1000 Kg Besi Strip 2 x 3 cm 17,160.00
35.0000 Kg Semen Portland 1,668.00
0.1500 M³ Pasir Pasang 148,179.36
0.1000 M³ Pasir Beton 162,748.88
0.1500 M³ Batu Pecah 3 - 5cm 455,000.00
30.0000 Bh Batu Bata 1,560.00
0.2500 Lbr Seng Gelombang 60,000.00
0.2000 Bh Jendela Nako 201,840.00
0.0800 M² Kaca Polos 5mm 159,000.00
0.1500 Bh Kunci Tanam biasa 204,000.00
0.0600 Lbr Playwood 120 x 240cm tebal = 4mm 95,700.00
JUMLAH

A.5 1 m² Pembuatan Gudang Semen & Peralatan


1.0000 Oh Pekerja 96,800.00
2.0000 Oh Tukang Kayu 121,000.00
0.2000 Oh Kepala Tukang 145,200.00
0.0500 Oh Mandor 133,100.00
KODE HARGA SATUAN (Rp.)
URAIAN PEKERJAAN
ANAL BAHAN UPAH

1.7000 Btg Dolken Kayu dia.8-10/400cm 16,800.00


0.2100 M³ Kayu Papan Kls. III 2,310,000.00
0.3000 Kg Paku Biasa 2"-5" 16,200.00
10.5000 Kg Semen Portland 1,668.00
0.0300 M³ Pasir Beton 162,748.88
0.0500 M³ Batu Pecah 3 - 5cm 455,000.00
1.5000 Lbr Seng Gelombang 60,000.00
0.2500 Lbr Seng BJLS 30 lebar 45 cm 48,000.00
JUMLAH

A.6 1 m² Pembuatan Bedeng Pekerja


1.0000 Oh Pekerja 96,800.00
2.0000 Oh Tukang Kayu 121,000.00
0.2000 Oh Kepala Tukang 145,200.00
0.0500 Oh Mandor 133,100.00
1.2500 Btg Dolken Kayu dia.8-10/400cm 16,800.00
0.1860 M³ Kayu Papan Kls. III 2,310,000.00
0.3000 Kg Paku Biasa 2"-5" 16,200.00
18.0000 Kg Semen Portland 1,668.00
0.0300 M³ Pasir Beton 162,748.88
0.0500 M³ Batu Pecah 3 - 5cm 455,000.00
1.5000 Lbr Seng Gelombang 60,000.00
1.3500 Lbr Playwood 120 x 240cm tebal = 4mm 95,700.00
JUMLAH

A.7 1 m² Pembersihan Lapangan & Perataan


0.1000 Oh Pekerja 96,800.00
0.0500 Oh Mandor 133,100.00
JUMLAH

A.8 1 m² Pembuatan Jalan Sementara


1.0000 Oh Pekerja 96,800.00
0.0050 Oh Mandor 133,100.00
0.1500 M³ Batu belah 15 - 25cm 560,000.00
0.0900 M³ Batu Pecah 5 - 7cm 455,000.00
0.0100 M³ Pasir Pasang 148,179.36
JUMLAH
KODE HARGA SATUAN (Rp.)
URAIAN PEKERJAAN
ANAL BAHAN UPAH

A.9 1 m³ Bongkaran Beton Bertulang


13.3340 Oh Pekerja 96,800.00
0.6660 Oh Mandor 133,100.00
JUMLAH

A.10 1 m³ Bongkaran Dinding Tembok Bata


6.6670 Oh Pekerja 96,800.00
0.3330 Oh Mandor 133,100.00
JUMLAH

A.11 10 m² Bongkaran Lantai


2.0000 Oh Pekerja 96,800.00
0.1000 Oh Mandor 133,100.00
JUMLAH
Untuk 1 m²

A.12 1 m² Pemasangan Pagar Kawat Jaring Galvanis P = 240cm


0.0420 Oh Pekerja 96,800.00
0.0040 Oh Tukang Besi 129,300.00
0.0020 Oh Kepala Tukang 145,200.00
0.0420 Oh Mandor 133,100.00
0.1434 Lbr Kawat Jaring Galvanis 24,000.00
JUMLAH

A.13 1 m² Pemasangan Panel Beton Pracetak uk. 5 x 50 x 213cm


0.3750 Oh Pekerja 96,800.00
0.1250 Oh Tukang Batu 129,300.00
0.0120 Oh Kepala Tukang 145,200.00
0.0190 Oh Mandor 133,100.00
0.9860 Lbr Panel Beton (Cetakan)
0.5250 Btg Kolom Beton (Cetakan)
45.0000 Kg Semen Portland 1,668.00
0.0740 M³ Pasir Beton 162,748.88
0.1460 M³ Batu Pecah 3 - 5cm 455,000.00
JUMLAH
KODE HARGA SATUAN (Rp.)
URAIAN PEKERJAAN
ANAL BAHAN UPAH

A.14 1 m² Pembuatan Bak Adukan 40 x 50 x 20cm


0.3000 Oh Tukang Kayu 121,000.00
0.0360 M³ Kayu Papan Kls. IV 1,920,000.00
0.0140 M³ Kayu Balok Kls. IV 2,070,000.00
0.0800 Kg Paku Biasa 2"-5" 16,200.00
JUMLAH

A.15 1 m² Pembuatan Stegger


0.1700 Oh Pekerja 96,800.00
0.2500 Oh Tukang Kayu 121,000.00
0.0020 Oh Kepala Tukang 145,200.00
0.0130 Oh Mandor 133,100.00
1.2500 Btg Dolken Kayu dia.8-10/400cm 16,800.00
0.3000 Kg Paku Biasa 2"-5" 16,200.00
JUMLAH

A.16 10 m² Menurunkan Atap Genteng / Sirap


0.2000 Oh Pekerja 96,800.00
0.1000 Oh Mandor 133,100.00
JUMLAH
Untuk 1 m²

A.17 10 m² Menurunkan Atap Seng


0.5000 Oh Pekerja 96,800.00
1.0000 Oh Mandor 133,100.00
JUMLAH
Untuk 1 m²

A.18 10 m² Membongkar Rangka Atap


1.0000 Oh Pekerja 96,800.00
0.2500 Oh Tukang Kayu 121,000.00
0.0250 Oh Kepala Tukang 145,200.00
0.0500 Oh Mandor 133,100.00
JUMLAH
Untuk 1 m²

A.19 1 m³ Membongkar Rangka Kuda-Kuda Kayu


KODE HARGA SATUAN (Rp.)
URAIAN PEKERJAAN
ANAL BAHAN UPAH

4.0000 Oh Pekerja 96,800.00


6.0000 Oh Tukang Kayu 121,000.00
0.6000 Oh Kepala Tukang 145,200.00
0.2000 Oh Mandor 133,100.00
JUMLAH

A.20 10 m² Membongkar Langit-Langit & Rangka


2.0000 Oh Pekerja 96,800.00
0.2500 Oh Tukang Kayu 121,000.00
0.0250 Oh Kepala Tukang 145,200.00
0.0500 Oh Mandor 133,100.00
JUMLAH
Untuk 1 m²
JUMLAH (Rp) JUMLAH UPAH +
BAHAN UPAH BAHAN (Rp.)

19,360.00
48,400.00
2,904.00
2,662.00
21,000.00
4,170.00
72,000.00
813.74
4,095.00
207,360.00
972.00
7,128.00
317,538.74 73,326.00 390,864.74

19,360.00
36,300.00
2,904.00
2,662.00
16,800.00
3,336.00
555,300.00
813.74
4,095.00
972.00
581,316.74 61,226.00 642,542.74
JUMLAH (Rp) JUMLAH UPAH +
BAHAN UPAH BAHAN (Rp.)

9,680.00
12,100.00
1,452.00
665.50
24,840.00
324.00
13,440.00
38,604.00 23,897.50 62,501.50

193,600.00
242,000.00
129,300.00
43,560.00
6,655.00
21,000.00
415,800.00
1,296.00
18,876.00
58,380.00
22,226.90
16,274.89
68,250.00
46,800.00
15,000.00
40,368.00
12,720.00
30,600.00
5,742.00
773,333.79 615,115.00 1,388,448.79

96,800.00
242,000.00
29,040.00
6,655.00
JUMLAH (Rp) JUMLAH UPAH +
BAHAN UPAH BAHAN (Rp.)

28,560.00
485,100.00
4,860.00
17,514.00
4,882.47
22,750.00
90,000.00
12,000.00
665,666.47 374,495.00 1,040,161.47

96,800.00
242,000.00
29,040.00
6,655.00
21,000.00
429,660.00
4,860.00
30,024.00
4,882.47
22,750.00
90,000.00
129,195.00
732,371.47 374,495.00 1,106,866.47

9,680.00
6,655.00
16,335.00 16,335.00

96,800.00
665.50
84,000.00
40,950.00
1,481.79
126,431.79 97,465.50 223,897.29
JUMLAH (Rp) JUMLAH UPAH +
BAHAN UPAH BAHAN (Rp.)

1,290,731.20
88,644.60
1,379,375.80 1,379,375.80

645,365.60
44,322.30
689,687.90 689,687.90 6.67 m2 103,453.19

193,600.00
13,310.00
206,910.00 206,910.00 1,310,981.76
20,691.00

4,065.60
517.20
290.40
5,590.20
3,441.60
3,441.60 10,463.40 13,905.00

36,300.00
16,162.50
1,742.40
2,528.90
-
-
75,060.00
12,043.42
66,430.00
153,533.42 56,733.80 210,267.22
JUMLAH (Rp) JUMLAH UPAH +
BAHAN UPAH BAHAN (Rp.)

36,300.00
69,120.00
28,980.00
1,296.00
99,396.00 36,300.00 135,696.00

16,456.00
30,250.00
290.40
1,730.30
21,000.00
4,860.00
25,860.00 48,726.70 74,586.70

19,360.00
13,310.00
32,670.00 32,670.00
3,267.00

48,400.00
133,100.00
181,500.00 181,500.00
18,150.00

96,800.00
30,250.00
3,630.00
6,655.00
137,335.00 137,335.00
13,733.50
JUMLAH (Rp) JUMLAH UPAH +
BAHAN UPAH BAHAN (Rp.)

387,200.00
726,000.00
87,120.00
26,620.00
1,226,940.00 1,226,940.00

193,600.00
30,250.00
3,630.00
6,655.00
234,135.00 234,135.00
23,413.50
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

B PEKERJAAN TANAH

B.1 1 m³ Galian Tanah Biasa sedalam 1m


0.7500 Oh Pekerja 96,800.00
0.0250 Oh Mandor 133,100.00
JUMLAH

B.2 1 m³ Galian Tanah Biasa sedalam 2m


0.9000 Oh Pekerja 96,800.00
0.0450 Oh Mandor 133,100.00
JUMLAH

B.3 1 m³ Galian Tanah Biasa sedalam 3m


1.0500 Oh Pekerja 96,800.00
0.0670 Oh Mandor 133,100.00
JUMLAH

B.4 1 m³ Galian Tanah Keras sedalam 1m


1.0000 Oh Pekerja 96,800.00
0.0320 Oh Mandor 133,100.00
JUMLAH

B.5 1 m³ Galian Tanah Cadas sedalam 1m


1.5000 Oh Pekerja 96,800.00
0.0600 Oh Mandor 133,100.00
JUMLAH

B.6 1 m³ Galian Tanah Lumpur sedalam 1m


1.2000 Oh Pekerja 96,800.00
0.0450 Oh Mandor 133,100.00
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

JUMLAH

B.7 1 m² Stripping Tanah Tebing setinggi 1m


0.0500 Oh Pekerja 96,800.00
0.0050 Oh Mandor 133,100.00
JUMLAH

B.8 1 m³ Buangan Tanah sejauh 30m


0.3300 Oh Pekerja 96,800.00
0.0100 Oh Mandor 133,100.00
JUMLAH

B.9 1 m³ Pengurugan Tanah Kembali


0.5000 Oh Pekerja 96,800.00
0.0500 Oh Mandor 133,100.00
JUMLAH

B.10 1 m³ Pemadatan Tanah tiap 20cm


0.5000 Oh Pekerja 96,800.00
0.0500 Oh Mandor 133,100.00
JUMLAH

B.11 1 m³ Pengurugan Pasir


0.3000 Oh Pekerja 96,800.00
0.0100 Oh Mandor 133,100.00
1.2000 M³ Pasir Urug 115,968.16 139,161.79
JUMLAH 139,161.79

B.12 1 m³ Urugan Tanah Puru


0.3000 Oh Pekerja 96,800.00
0.0100 Oh Mandor 133,100.00
1.2000 M³ Timbunan Pilihan / Tanah Puru 92,293.60 110,752.32
JUMLAH 110,752.32

B.13 1 m³ Urugan Sirtu


0.2500 Oh Pekerja 96,800.00
0.0250 Oh Mandor 133,100.00
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

1.2000 M³ Sirtu 15,000.00 18,000.00


JUMLAH 18,000.00
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

72,600.00
3,327.50
75,927.50 75,927.50

87,120.00
5,989.50
93,109.50 93,109.50

101,640.00
8,917.70
110,557.70 110,557.70

96,800.00
4,259.20
101,059.20 101,059.20

145,200.00
7,986.00
153,186.00 153,186.00

116,160.00
5,989.50
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

122,149.50 122,149.50

4,840.00
665.50
5,505.50 5,505.50

31,944.00
1,331.00
33,275.00 33,275.00

48,400.00
6,655.00
55,055.00 55,055.00

48,400.00
6,655.00
55,055.00 55,055.00

29,040.00
1,331.00

30,371.00 169,532.79

29,040.00
1,331.00

30,371.00 141,123.32

24,200.00
3,327.50
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

27,527.50 45,527.50
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

C PEKERJAAN PONDASI

C.1 1 m³ Pasangan Pondasi Bt. Belah ad. 1 : 3


1.5000 Oh Pekerja 96,800.00
0.7500 Oh Tukang Batu 121,000.00
0.0750 Oh Kepala Tukang 145,200.00
0.0750 Oh Mandor 133,100.00
1.2000 M³ Batu belah 15 - 25cm 560,000.00 672,000.00
202.0000 Kg Semen Portland 1,668.00 336,936.00
0.4850 M³ Pasir Pasang 113,750.00 55,168.75
JUMLAH 1,064,104.75

C.2 1 m³ Pasangan Pondasi Bt. Belah ad. 1 : 4


1.5000 Oh Pekerja 96,800.00
0.7500 Oh Tukang Batu 121,000.00
0.0750 Oh Kepala Tukang 145,200.00
0.0750 Oh Mandor 133,100.00
1.2000 M³ Batu belah 15 - 25cm 560,000.00 672,000.00
163.0000 Kg Semen Portland 1,668.00 271,884.00
0.5200 M³ Pasir Pasang 113,750.00 59,150.00
JUMLAH 1,003,034.00

C.3 1 m³ Pasangan Pondasi Bt. Belah ad. 1 : 5


1.5000 Oh Pekerja 96,800.00
0.7500 Oh Tukang Batu 121,000.00
0.0750 Oh Kepala Tukang 145,200.00
0.0750 Oh Mandor 133,100.00
1.2000 M³ Batu belah 15 - 25cm 560,000.00 672,000.00
136.0000 Kg Semen Portland 1,668.00 226,848.00
0.5440 M³ Pasir Pasang 113,750.00 61,880.00
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

JUMLAH 960,728.00

C.4 1 m³ Pasangan Pondasi Bt. Belah ad. 1 : 6


1.5000 Oh Pekerja 96,800.00
0.7500 Oh Tukang Batu 121,000.00
0.0750 Oh Kepala Tukang 145,200.00
0.0750 Oh Mandor 133,100.00
1.2000 M³ Batu belah 15 - 25cm 560,000.00 672,000.00
117.0000 Kg Semen Portland 1,668.00 195,156.00
0.5610 M³ Pasir Pasang 113,750.00 63,813.75
JUMLAH 930,969.75

C.5 1 m³ Pasangan Pondasi Bt. Belah ad. 1 : 8


1.5000 Oh Pekerja 96,800.00
0.7500 Oh Tukang Batu 121,000.00
0.0750 Oh Kepala Tukang 145,200.00
0.0750 Oh Mandor 133,100.00
1.2000 M³ Batu belah 15 - 25cm 560,000.00 672,000.00
91.0000 Kg Semen Portland 1,668.00 151,788.00
0.5840 M³ Pasir Pasang 113,750.00 66,430.00
JUMLAH 890,218.00

C.6 1 m³ Pasangan Bt. Gunung ad. 1 : 4


1.5000 Oh Pekerja 96,800.00
0.7500 Oh Tukang Batu 121,000.00
0.0750 Oh Kepala Tukang 145,200.00
0.0750 Oh Mandor 133,100.00
1.2000 M³ Bt. Gunung 405,510.00 486,612.00
163.0000 Kg Semen Portland 1,668.00 271,884.00
0.5200 M³ Pasir Urug 115,968.16 60,303.44
JUMLAH 818,799.44

C.7 1 m³ Pasangan Bt. Kosong (Anstamping)


0.7800 Oh Pekerja 96,800.00
0.3900 Oh Tukang Batu 121,000.00
0.0390 Oh Kepala Tukang 145,200.00
0.0390 Oh Mandor 133,100.00
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

1.2000 M³ Batu belah 15 - 25cm 560,000.00 672,000.00


0.4320 M³ Pasir Urug 115,968.16 50,098.25
JUMLAH 722,098.25

C.8 1 m³ Pasangan Pondasi Sumuran dia. 100cm


2.4000 Oh Pekerja 96,800.00
0.8000 Oh Tukang Batu 121,000.00
0.0800 Oh Kepala Tukang 145,200.00
0.1190 Oh Mandor 133,100.00
0.4500 M³ Batu belah < 15cm 560,000.00 252,000.00
194.0000 Kg Semen Portland 1,668.00 323,592.00
0.3120 M³ Pasir Beton 113,750.00 35,490.00
0.4680 M³ Batu Pecah 1 - 3cm 455,000.00 212,940.00
JUMLAH 824,022.00

C.9 1 M' Pembuatan Tiang Pancang Beton Bertulang = 35 x 35cm


0.8000 Oh Pekerja 96,800.00
0.5000 Oh Tukang Batu 121,000.00
0.0500 Oh Kepala Tukang 145,200.00
0.0400 Oh Mandor 133,100.00
0.0160 M³ Pasir urug 115,968.16 1,855.49
0.0800 M³ Pasir Pasangan 113,750.00 9,100.00
0.1250 M³ Batu Pecah 3 - 5cm 455,000.00 56,875.00
49.0000 Kg Semen Portland 1,668.00 81,732.00
34.5000 Kg Besi beton Ø16mm 9,446.20 325,893.99
0.7000 Kg Kawat Beton 20,736.00 14,515.20
0.0270 M³ Kayu Papan Kls. III 2,310,000.00 62,370.00
0.1200 Kg Paku Biasa 2"-5" 16,200.00 1,944.00
JUMLAH 554,285.68

C.10 1 M' Pembuatan Tiang Pancang Beton Bertulang = 40 x 40cm


1.0000 Oh Pekerja 96,800.00
0.6700 Oh Tukang Batu 121,000.00
0.0670 Oh Kepala Tukang 145,200.00
0.0500 Oh Mandor 133,100.00
0.0190 M3 Pasir urug 115,968.16 2,203.40
0.0940 M3 Pasir Pasangan 113,750.00 10,692.50
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

0.1500 M3 Batu Pecah 3 - 5cm 455,000.00 68,250.00


60.5000 Kg Semen 1,668.00 100,914.00
45.0000 Kg Besi beton Ø16mm 9,446.20 425,079.11
0.9000 Kg Kawat Beton 20,736.00 18,662.40
0.0320 M3 Kayu Papan Kls. III 2,310,000.00 73,920.00
0.1200 Kg Paku Biasa 2"-5" 16,200.00 1,944.00
JUMLAH 701,665.41

C.11 1 m³ Pasangan Cerucuk Alas Pondasi


5.0000 Oh Pekerja 96,800.00
1.5000 Oh Tukang Kayu 121,000.00
1.5000 Oh Kepala Tukang 145,200.00
0.2500 Oh Mandor 133,100.00
35.0000 Btg Dolken Kayu dia.8-10/400cm 16,800.00 588,000.00
JUMLAH 588,000.00

C.12 10 M' Pasangan Cerucuk Penahan Badan Jalan


6.0000 Oh Pekerja 96,800.00
18.0000 Oh Tukang Kayu 121,000.00
1.8000 Oh Kepala Tukang 145,200.00
0.3000 Oh Mandor 133,100.00
100.0000 Btg Dolken Kayu dia.8-10/400cm 16,800.00 1,680,000.00
JUMLAH 1,680,000.00
Untuk 1 M'

C.13 1 M' Pasangan Pipa Rembes & Ijuk


0.1000 Oh Pekerja 96,800.00
0.0200 Oh Mandor 133,100.00
2.0000 M' Pipa PVC dia 2" 22,250.00 44,500.00
0.5000 Kg Ijuk 3,960.00 1,980.00
JUMLAH 46,480.00

C.14 10 M' Dewatering


0.3000 Oh Pekerja 96,800.00
0.2000 Oh Mandor 133,100.00
6.0000 Ltr Bensin 8,340.00 50,040.00
0.5000 Ltr Olie 39,600.00 19,800.00
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

1.6000 Ls Perbaikan Pompa 231,000.00 369,600.00


1.6000 Ls Sparepart 236,500.00 378,400.00
JUMLAH 817,840.00
Untuk 1 M'

C.15 1 M' Kistdam Kayu


0.4000 Oh Pekerja 96,800.00
0.2000 Oh Tukang Kayu 121,000.00
0.2000 Oh Kepala Tukang 145,200.00
0.2000 Oh Mandor 133,100.00
2.5000 Btg Dolken Kayu dia.8-10/400cm 16,800.00 42,000.00
0.0200 M³ Kayu Kls. IV 2,070,000.00 41,400.00
JUMLAH 83,400.00
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

145,200.00
90,750.00
10,890.00
9,982.50

256,822.50 1,320,927.25

145,200.00
90,750.00
10,890.00
9,982.50

256,822.50 1,259,856.50

145,200.00
90,750.00
10,890.00
9,982.50
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

256,822.50 1,217,550.50

145,200.00
90,750.00
10,890.00
9,982.50

256,822.50 1,187,792.25

145,200.00
90,750.00
10,890.00
9,982.50

256,822.50 1,147,040.50

145,200.00
90,750.00
10,890.00
9,982.50

256,822.50 1,075,621.94

75,504.00
47,190.00
5,662.80
5,190.90
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

133,547.70 855,645.95

232,320.00
96,800.00
11,616.00
15,838.90

356,574.90 1,180,596.90

77,440.00
60,500.00
7,260.00
5,324.00

150,524.00 704,809.68

96,800.00
81,070.00
9,728.40
6,655.00
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

194,253.40 895,918.81

484,000.00
181,500.00
217,800.00
33,275.00

916,575.00 1,504,575.00

580,800.00
2,178,000.00
261,360.00
39,930.00

3,060,090.00 4,740,090.00
474,009.00

9,680.00
2,662.00

3,960
12,342.00 58,822.00 3,780

29,040.00
26,620.00
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

55,660.00 873,500.00 236,500.00


87,350.00

38,720.00
24,200.00
29,040.00
26,620.00

118,580.00 201,980.00
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

D PEKERJAAN BETON

D.1 10 Kg Pembesian dengan Besi Polos / Ulir


0.0700 Oh Pekerja 96,800.00
0.0700 Oh Tukang Besi 121,000.00
0.0070 Oh Kepala Tukang 145,200.00
0.0040 Oh Mandor 133,100.00
10.5000 Kg Besi Beton Ø8mm 9,881.26 103,753.18
0.1500 Kg Kawat Beton 20,736.00 3,110.40
JUMLAH 106,863.58
Untuk 1 Kg

D.2 10 Kg Pemasangan Jaring Kawat Baja (Wiremesh)


0.0250 Oh Pekerja 96,800.00
0.0250 Oh Tukang Besi 121,000.00
0.0250 Oh Kepala Tukang 145,200.00
0.0010 Oh Mandor 133,100.00
10.2000 Kg Jaring Kawat Baja Dilas 25,200.00 257,040.00
0.0500 Kg Kawat Beton 20,736.00 1,036.80
JUMLAH 258,076.80
Untuk 1 Kg

D.3 1 m² Pemasangan Bekisting Pondasi


0.5200 Oh Pekerja 96,800.00
0.2600 Oh Tukang Kayu 121,000.00
0.0260 Oh Kepala Tukang 145,200.00
0.0260 Oh Mandor 133,100.00
0.0400 M³ Kayu Papan kls. III 2,310,000.00 92,400.00
0.3000 Kg Paku Biasa 2"-5" 16,200.00 4,860.00
0.1000 Ltr Minyak Bekisting 3,240.00 324.00
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

JUMLAH 97,584.00

D.4 1 m² Pemasangan Bekisting Sloof


0.5200 Oh Pekerja 96,800.00
0.2600 Oh Tukang Kayu 121,000.00
0.0260 Oh Kepala Tukang 145,200.00
0.0260 Oh Mandor 133,100.00
0.0450 M³ Kayu Papan kls. III 2,310,000.00 103,950.00
0.3000 Kg Paku Biasa 2"-5" 16,200.00 4,860.00
0.1000 Ltr Minyak Bekisting 3,240.00 324.00
JUMLAH 109,134.00

D.5 1 m² Pemasangan Bekisting Kolom


0.6600 Oh Pekerja 96,800.00
0.3300 Oh Tukang Kayu 121,000.00
0.0330 Oh Kepala Tukang 145,200.00
0.0330 Oh Mandor 133,100.00
0.0400 M³ Kayu Papan kls. III 2,310,000.00 92,400.00
0.4000 Kg Paku Biasa 2"-5" 16,200.00 6,480.00
0.2000 Ltr Minyak Bekisting 3,240.00 648.00
0.0150 M³ Kayu Balok kls.III 2,880,000.00 43,200.00
0.3500 Lbr Playwood 120 x 240cm tebal = 4mm 95,700.00 33,495.00
2.0000 Btg Dolken Kayu dia.8-10/400cm 16,800.00 33,600.00
JUMLAH 209,823.00

D.6 1 m² Pemasangan Bekisting Balok


0.6600 Oh Pekerja 96,800.00
0.3300 Oh Tukang Kayu 121,000.00
0.0330 Oh Kepala Tukang 145,200.00
0.0330 Oh Mandor 133,100.00
0.0400 M³ Kayu Papan kls. III 2,310,000.00 92,400.00
0.4000 Kg Paku Biasa 2"-5" 16,200.00 6,480.00
0.2000 Ltr Minyak Bekisting 3,240.00 648.00
0.0180 M³ Kayu Balok kls.III 2,880,000.00 51,840.00
0.3500 Lbr Playwood 120 x 240cm tebal = 4mm 95,700.00 33,495.00
2.0000 Btg Dolken Kayu dia.8-10/400cm 16,800.00 33,600.00
JUMLAH 218,463.00
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

D.7 1 m² Pemasangan Bekisting Lantai


0.6600 Oh Pekerja 96,800.00
0.3300 Oh Tukang Kayu 121,000.00
0.0330 Oh Kepala Tukang 145,200.00
0.0330 Oh Mandor 133,100.00
0.0400 M³ Kayu Papan kls. III 2,310,000.00 92,400.00
0.4000 Kg Paku Biasa 2"-5" 16,200.00 6,480.00
0.2000 Ltr Minyak Bekisting 3,240.00 648.00
0.0150 M³ Kayu Balok kls.III 2,880,000.00 43,200.00
0.3500 Lbr Playwood 120 x 240cm tebal = 4mm 95,700.00 33,495.00
6.0000 Btg Dolken Kayu dia.8-10/400cm 16,800.00 100,800.00
JUMLAH 277,023.00

D.8 1 m² Pemasangan Bekisting Dinding


0.6600 Oh Pekerja 96,800.00
0.3300 Oh Tukang Kayu 121,000.00
0.0330 Oh Kepala Tukang 145,200.00
0.0330 Oh Mandor 133,100.00
0.0300 M³ Kayu Papan kls. III 2,310,000.00 69,300.00
0.4000 Kg Paku Biasa 2"-5" 16,200.00 6,480.00
0.2000 Ltr Minyak Bekisting 3,240.00 648.00
0.0200 M³ Kayu Balok kls.III 2,880,000.00 57,600.00
0.3500 Lbr Playwood 120 x 240cm tebal = 4mm 95,700.00 33,495.00
3.0000 Btg Dolken Kayu dia.8-10/400cm 16,800.00 50,400.00
4.0000 Bh Spacer / Penjaga Jarak Bekisting -
JUMLAH 217,923.00

D.9 1 m² Pemasangan Bekisting Tangga


0.6600 Oh Pekerja 96,800.00
0.3300 Oh Tukang Kayu 121,000.00
0.0330 Oh Kepala Tukang 145,200.00
0.0330 Oh Mandor 133,100.00
0.0300 M³ Kayu Papan kls. III 2,310,000.00 69,300.00
0.4000 Kg Paku Biasa 2"-5" 16,200.00 6,480.00
0.1500 Ltr Minyak Bekisting 3,240.00 486.00
0.0150 M³ Kayu Balok kls.III 2,880,000.00 43,200.00
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

0.3500 Lbr Playwood 120 x 240cm tebal = 4mm 95,700.00 33,495.00


2.0000 Btg Dolken Kayu dia.8-10/400cm 16,800.00 33,600.00
JUMLAH 186,561.00

D.10 1 m³ Pondasi Beton Bertulang = 150kg besi + Bekisting


5.3000 Oh Pekerja 96,800.00
0.2750 Oh Tukang Batu 121,000.00
1.3000 Oh Tukang Kayu 121,000.00
1.0500 Oh Tukang Besi 121,000.00
0.2620 Oh Kepala Tukang 145,200.00
0.2650 Oh Mandor 133,100.00
0.2000 M³ Kayu Papan kls. III 2,310,000.00 462,000.00
1.5000 Kg Paku Biasa 2"-5" 16,200.00 24,300.00
0.4000 Ltr Minyak Bekisting 3,240.00 1,296.00
157.5000 Kg Besi Beton Ø12mm 9,235.25 1,454,551.86
2.2500 Kg Kawat Beton 20,736.00 46,656.00
336.0000 Kg Semen Portland 1,668.00 560,448.00
0.5400 M³ Pasir Beton 162,748.88 87,884.40
0.8100 M³ Batu Pecah 1 - 3cm 455,000.00 368,550.00
JUMLAH 3,005,686.26

D.11 1 m³ Sloof Beton Bertulang = 200kg besi + Bekisting


5.6500 Oh Pekerja 96,800.00
0.2750 Oh Tukang Batu 121,000.00
1.5600 Oh Tukang Kayu 121,000.00
1.4000 Oh Tukang Besi 121,000.00
0.3230 Oh Kepala Tukang 145,200.00
0.2830 Oh Mandor 133,100.00
0.2700 M³ Kayu Papan kls. III 2,310,000.00 623,700.00
2.0000 Kg Paku Biasa 2"-5" 16,200.00 32,400.00
0.6000 Ltr Minyak Bekisting 3,240.00 1,944.00
210.0000 Kg Besi Beton Ø10mm 9,475.81 1,989,919.35
3.0000 Kg Kawat Beton 20,736.00 62,208.00
336.0000 Kg Semen Portland 1,668.00 560,448.00
0.5400 M³ Pasir Beton 162,748.88 87,884.40
0.8100 M³ Batu Pecah 1 - 3cm 455,000.00 368,550.00
JUMLAH 3,727,053.75
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

D.12 1 m³ Kolom Beton Bertulang = 150kg besi + Bekisting


5.3000 Oh Pekerja 96,800.00
0.2750 Oh Tukang Batu 121,000.00
1.3000 Oh Tukang Kayu 121,000.00
1.0500 Oh Tukang Besi 121,000.00
0.2650 Oh Kepala Tukang 145,200.00
0.2650 Oh Mandor 133,100.00
0.3200 M³ Kayu Papan kls. III 2,310,000.00 739,200.00
3.2000 Kg Paku Biasa 2"-5" 16,200.00 51,840.00
1.6000 Ltr Minyak Bekisting 3,240.00 5,184.00
157.5000 Kg Besi Beton Ø10mm 9,475.81 1,492,439.52
2.2500 Kg Kawat Beton 20,736.00 46,656.00
336.0000 Kg Semen Portland 1,668.00 560,448.00
0.5400 M³ Pasir Beton 162,748.88 87,884.40
0.8100 M³ Batu Pecah 1 - 3cm 455,000.00 368,550.00
0.1200 M³ Kayu Balok kls.III 2,880,000.00 345,600.00
2.8000 Lbr Playwood 120 x 240cm tebal = 4mm 95,700.00 267,960.00
32.0000 Btg Dolken Kayu dia.8-10/400cm 16,800.00 537,600.00
JUMLAH 4,503,361.91

D.13 1 m³ Kolom Beton Bertulang = 300kg besi + Bekisting


7.0500 Oh Pekerja 96,800.00
0.2750 Oh Tukang Batu 121,000.00
1.6500 Oh Tukang Kayu 121,000.00
2.1000 Oh Tukang Besi 121,000.00
0.4030 Oh Kepala Tukang 145,200.00
0.3530 Oh Mandor 133,100.00
0.4000 M³ Kayu Papan kls. III 2,310,000.00 924,000.00
4.0000 Kg Paku Biasa 2"-5" 16,200.00 64,800.00
2.0000 Ltr Minyak Bekisting 3,240.00 6,480.00
315.0000 Kg Besi beton Ø16mm 9,446.20 2,975,553.80
4.5000 Kg Kawat Beton 20,736.00 93,312.00
336.0000 Kg Semen Portland 1,668.00 560,448.00
0.5400 M³ Pasir Beton 162,748.88 87,884.40
0.8100 M³ Batu Pecah 1 - 3cm 455,000.00 368,550.00
0.1500 M³ Kayu Balok kls.III 2,880,000.00 432,000.00
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

3.5000 Lbr Playwood 120 x 240cm tebal = 4mm 95,700.00 334,950.00


20.0000 Btg Dolken Kayu dia.8-10/400cm 16,800.00 336,000.00
JUMLAH 6,183,978.19

D.14 1 m³ Balok Beton Bertulang = 200kg besi + Bekisting


6.3500 Oh Pekerja 96,800.00
0.2750 Oh Tukang Batu 121,000.00
1.6500 Oh Tukang Kayu 121,000.00
1.4000 Oh Tukang Besi 121,000.00
0.3330 Oh Kepala Tukang 145,200.00
0.3180 Oh Mandor 133,100.00
0.3200 M³ Kayu Papan kls. III 2,310,000.00 739,200.00
3.2000 Kg Paku Biasa 2"-5" 16,200.00 51,840.00
1.6000 Ltr Minyak Bekisting 3,240.00 5,184.00
210.0000 Kg Besi Beton Ø10mm 9,475.81 1,989,919.35
3.0000 Kg Kawat Beton 20,736.00 62,208.00
336.0000 Kg Semen Portland 1,668.00 560,448.00
0.5400 M³ Pasir Beton 162,748.88 87,884.40
0.8100 M³ Batu Pecah 1 - 3cm 455,000.00 368,550.00
0.1400 M³ Kayu Balok kls.III 2,880,000.00 403,200.00
2.8000 Lbr Playwood 120 x 240cm tebal = 4mm 95,700.00 267,960.00
16.0000 Btg Dolken Kayu dia.8-10/400cm 16,800.00 268,800.00
JUMLAH 4,805,193.75

D.15 1 m³ Lantai Beton Bertulang = 200kg besi + Bekisting


5.6000 Oh Pekerja 96,800.00
2.3000 Oh Tukang Batu 121,000.00
0.3500 Oh Tukang Kayu 121,000.00
1.4000 Oh Tukang Besi 121,000.00
0.0450 Oh Kepala Tukang 145,200.00
0.2020 Oh Mandor 133,100.00
0.2500 M³ Kayu Papan kls. III 2,310,000.00 577,500.00
3.0000 Kg Paku Biasa 2"-5" 16,200.00 48,600.00
1.6000 Ltr Minyak Bekisting 3,240.00 5,184.00
200.0000 Kg Besi Beton Ø8mm 9,881.26 1,976,251.06
3.0000 Kg Kawat Beton 20,736.00 62,208.00
323.0000 Kg Semen Portland 1,668.00 538,764.00
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

0.5200 M³ Pasir Beton 162,748.88 84,629.42


0.7800 M³ Batu Pecah 1 - 3cm 455,000.00 354,900.00
0.1050 M³ Kayu Balok kls.III 2,880,000.00 302,400.00
2.5000 Lbr Playwood 120 x 240cm tebal = 4mm 95,700.00 239,250.00
14.0000 Btg Dolken Kayu dia.8-10/400cm 16,800.00 235,200.00
JUMLAH 4,424,886.48

D.16 1 m³ Dinding Beton Bertulang = 150kg besi + Bekisting


5.3000 Oh Pekerja 96,800.00
0.2750 Oh Tukang Batu 121,000.00
1.3000 Oh Tukang Kayu 121,000.00
1.0500 Oh Tukang Besi 121,000.00
0.2620 Oh Kepala Tukang 145,200.00
0.2650 Oh Mandor 133,100.00
0.2400 M³ Kayu Papan kls. III 2,310,000.00 554,400.00
3.2000 Kg Paku Biasa 2"-5" 16,200.00 51,840.00
1.6000 Ltr Minyak Bekisting 3,240.00 5,184.00
157.5000 Kg Besi Beton Ø8mm 9,881.26 1,556,297.71
2.2500 Kg Kawat Beton 20,736.00 46,656.00
336.0000 Kg Semen Portland 1,668.00 560,448.00
0.5400 M³ Pasir Beton 162,748.88 87,884.40
0.8100 M³ Batu Pecah 1 - 3cm 455,000.00 368,550.00
0.1600 M³ Kayu Balok kls.III 2,880,000.00 460,800.00
2.8000 Lbr Playwood 120 x 240cm tebal = 4mm 95,700.00 267,960.00
24.0000 Btg Dolken Kayu dia.8-10/400cm 16,800.00 403,200.00
JUMLAH 4,363,220.11

D.17 1 m³ Dinding Beton Bertulang = 200kg besi + Bekisting


5.6500 Oh Pekerja 96,800.00
0.2750 Oh Tukang Batu 121,000.00
1.5600 Oh Tukang Kayu 121,000.00
1.4000 Oh Tukang Besi 121,000.00
0.3230 Oh Kepala Tukang 145,200.00
0.2830 Oh Mandor 133,100.00
0.2500 M³ Kayu Papan kls. III 2,310,000.00 577,500.00
3.0000 Kg Paku Biasa 2"-5" 16,200.00 48,600.00
1.2000 Ltr Minyak Bekisting 3,240.00 3,888.00
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

210.0000 Kg Besi Beton Ø10mm 9,475.81 1,989,919.35


3.0000 Kg Kawat Beton 20,736.00 62,208.00
336.0000 Kg Semen Portland 1,668.00 560,448.00
0.5400 M³ Pasir Beton 162,748.88 87,884.40
0.8100 M³ Batu Pecah 1 - 3cm 455,000.00 368,550.00
0.1050 M³ Kayu Balok kls.III 2,880,000.00 302,400.00
2.5000 Lbr Playwood 120 x 240cm tebal = 4mm 95,700.00 239,250.00
14.0000 Btg Dolken Kayu dia.8-10/400cm 16,800.00 235,200.00
JUMLAH 4,475,847.75

D.18 1 m' Kolom Praktis Beton Bertulang = 11 x 11cm


0.1800 Oh Pekerja 96,800.00
0.0200 Oh Tukang Batu 121,000.00
0.0200 Oh Tukang Kayu 121,000.00
0.0200 Oh Tukang Besi 121,000.00
0.0060 Oh Kepala Tukang 145,200.00
0.0090 Oh Mandor 133,100.00
0.0020 M³ Kayu Papan kls. III 2,310,000.00 4,620.00
0.0100 Kg Paku Biasa 2"-5" 16,200.00 162.00
3.0000 Kg Besi Beton Ø8mm 9,881.26 29,643.77
0.4500 Kg Kawat Beton 20,736.00 9,331.20
4.0000 Kg Semen Portland 1,668.00 6,672.00
0.0060 M³ Pasir Beton 162,748.88 976.49
0.0090 M³ Batu Pecah 1 - 3cm 455,000.00 4,095.00
JUMLAH 55,500.46

D.19 1 m' Ring Balok Praktis Beton Bertulang = 10 x 15cm


0.2970 Oh Pekerja 96,800.00
0.0330 Oh Tukang Batu 121,000.00
0.0330 Oh Tukang Kayu 121,000.00
0.0330 Oh Tukang Besi 121,000.00
0.0100 Oh Kepala Tukang 145,200.00
0.0150 Oh Mandor 133,100.00
0.0030 M³ Kayu Papan kls. III 2,310,000.00 6,930.00
0.0200 Kg Paku Biasa 2"-5" 16,200.00 324.00
3.6000 Kg Besi Beton Ø8mm 9,881.26 35,572.52
0.0500 Kg Kawat Beton 20,736.00 1,036.80
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

5.5000 Kg Semen Portland 1,668.00 9,174.00


0.0090 M³ Pasir Beton 162,748.88 1,464.74
0.0150 M³ Batu Pecah 1 - 3cm 455,000.00 6,825.00
JUMLAH 61,327.06

D.20 1 m³ Beton Tumbuk ad. 1 : 3 : 5


1.6500 Oh Pekerja 96,800.00
0.2500 Oh Tukang Batu 121,000.00
0.0250 Oh Kepala Tukang 145,200.00
0.0800 Oh Mandor 133,100.00
0.8700 M³ Batu Pecah 3 - 5cm 455,000.00 395,850.00
0.5200 M³ Pasir Beton 162,748.88 84,629.42
218.0000 Kg Semen Portland 1,668.00 363,624.00
JUMLAH 844,103.42

D.21 1 m³ Beton Tumbuk ad. 1 : 4 : 6


1.6500 Oh Pekerja 96,800.00
0.2500 Oh Tukang Batu 121,000.00
0.0250 Oh Kepala Tukang 145,200.00
0.0800 Oh Mandor 133,100.00
0.9400 M³ Batu pecah 3 - 5cm 455,000.00 427,700.00
0.5700 M³ Pasir Beton 162,748.88 92,766.86
173.0000 Kg Semen Portland 1,668.00 288,564.00
JUMLAH 809,030.86

D.22 1 m³ Beton Tumbuk ad. 1 : 2 : 4


1.6500 Oh Pekerja 96,800.00
0.2500 Oh Tukang Batu 121,000.00
0.0250 Oh Kepala Tukang 145,200.00
0.0800 Oh Mandor 133,100.00
0.9000 M³ Batu pecah 3 - 5cm 455,000.00 409,500.00
0.4500 M³ Pasir Beton 162,748.88 73,237.00
280.0000 Kg Semen Portland 1,668.00 467,040.00
JUMLAH 949,777.00
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

6,776.00
8,470.00
1,016.40
532.40

16,794.80 123,658.38
12,365.84

2,420.00
3,025.00
3,630.00
133.10

9,208.10 267,284.90
26,728.49

50,336.00
31,460.00
3,775.20
3,460.60
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

89,031.80 186,615.80

50,336.00
31,460.00
3,775.20
3,460.60

89,031.80 198,165.80

63,888.00
39,930.00
4,791.60
4,392.30

113,001.90 322,824.90

63,888.00
39,930.00
4,791.60
4,392.30

113,001.90 331,464.90
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

63,888.00
39,930.00
4,791.60
4,392.30

113,001.90 390,024.90

63,888.00
39,930.00
4,791.60
4,392.30

113,001.90 330,924.90

63,888.00
39,930.00
4,791.60
4,392.30
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

113,001.90 299,562.90

513,040.00
33,275.00 4,625,000
157,300.00
127,050.00 50
38,042.40 205,000
35,271.50 10,250,000

9,250,000 1,000,000

903,978.90 3,909,665.16

546,920.00
33,275.00
188,760.00
169,400.00
46,899.60
37,667.30

1,022,921.90 4,749,975.65
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

513,040.00
33,275.00
157,300.00
127,050.00
38,478.00
35,271.50

904,414.50 5,407,776.41

682,440.00
33,275.00
199,650.00
254,100.00
58,515.60
46,984.30
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

1,274,964.90 7,458,943.09

614,680.00
33,275.00
199,650.00
169,400.00
48,351.60
42,325.80

1,107,682.40 5,912,876.15

542,080.00
278,300.00
42,350.00
169,400.00
6,534.00
26,886.20
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

P L T
1,065,550.20 5,490,436.68 515 1 0.1 51.5 282,757,488.91

513,040.00
33,275.00
157,300.00
127,050.00
38,042.40
35,271.50

903,978.90 5,267,199.01

546,920.00
33,275.00
188,760.00
169,400.00
46,899.60
37,667.30
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

1,022,921.90 5,498,769.65

17,424.00
2,420.00
2,420.00
2,420.00
871.20
1,197.90

26,753.10 82,253.56

28,749.60
3,993.00
3,993.00
3,993.00
1,452.00
1,996.50
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

44,177.10 105,504.16

159,720.00
30,250.00
3,630.00
10,648.00

204,248.00 1,048,351.42 754,813.02

159,720.00
30,250.00
3,630.00
10,648.00

204,248.00 1,013,278.86

159,720.00
30,250.00
3,630.00
10,648.00

204,248.00 1,154,025.00
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

E PEKERJAAN BESI & ALUMINIUM

E.1 1 Kg Besi Profil


0.0600 Oh Pekerja 96,800.00
0.0600 Oh Tukang Besi 121,000.00
0.0060 Oh Kepala Tukang 145,200.00
0.0030 Oh Mandor 133,100.00
1.1500 Kg Besi Profil 13,677.00 15,728.55
JUMLAH 15,728.55

E.2 1 Kg Rangka Kuda-Kuda Baja IWF


0.0600 Oh Pekerja 96,800.00
0.0600 Oh Tukang Besi 121,000.00
0.0060 Oh Kepala Tukang 145,200.00
0.0030 Oh Mandor 133,100.00
1.1500 Kg Besi Baja IWF 14,948.70 17,191.01
JUMLAH 17,191.01

E.3 10 Cm Pengelasan dengan Las Listrik


0.0400 Oh Pekerja 96,800.00
0.0200 Oh Tukang Las 121,000.00
0.0020 Oh Kepala Tukang 145,200.00
0.0020 Oh Mandor 133,100.00
0.4000 Kg Kawat Las Listrik 28,800.00 11,520.00
0.3000 Ltr Bahan Bakar 8,340.00 2,502.00
0.0400 Ltr Minyak Pelumas 39,600.00 1,584.00
0.1700 Jam Sewa Alat 124,630.00 21,187.10
JUMLAH 36,793.10
Untuk 1 Cm
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

E.4 1 m² Pintu Besi Plat Baja t = 2mm + Rangka Besi Siku L.30.30.3
1.0500 Oh Pekerja 96,800.00
1.0500 Oh Tukang Besi 121,000.00
0.1050 Oh Kepala Tukang 145,200.00
0.0520 Oh Mandor 133,100.00
15.0000 Kg Besi Siku L.30.30.3 8,218.39 123,275.86
32.8000 Kg Besi Plat Baja t = 2mm 17,524.63 574,807.80
0.0500 Kg Kawat Las 28,800.00 1,440.00
JUMLAH 699,523.66

E.5 1 m² Pintu Rolling Door bahan Besi


1.2000 Oh Pekerja 96,800.00
1.2000 Oh Tukang Besi 121,000.00
0.1200 Oh Kepala Tukang 145,200.00
0.0060 Oh Mandor 133,100.00
1.0000 M² Pintu Rolling Door bahan Besi 498,960.00 498,960.00
JUMLAH 498,960.00

E.6 1 m² Pintu Lipat / Rolling Door bahan PVC


0.4400 Oh Pekerja 96,800.00
0.4400 Oh Tukang Besi 121,000.00
0.0440 Oh Kepala Tukang 145,200.00
0.0220 Oh Mandor 133,100.00
1.0000 M² Pintu Lipat / Rolling Door bahan PVC 346,080.00 346,080.00
JUMLAH 346,080.00

E.7 1 m² Pintu Rolling Door bahan Aluminium = 0,6mm


1.0000 Oh Pekerja 96,800.00
1.0000 Oh Tukang Besi 121,000.00
0.1000 Oh Kepala Tukang 145,200.00
0.0500 Oh Mandor 133,100.00
1.0000 M² Pintu Rolling Door bahan Aluminium = 586,080.00 586,080.00
JUMLAH 586,080.00

E.7.a 1 m² Pintu Rolling Door bahan Aluminium = 0,8mm


1.0000 Oh Pekerja 96,800.00
1.0000 Oh Tukang Besi 121,000.00
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

0.1000 Oh Kepala Tukang 145,200.00


0.0500 Oh Mandor 133,100.00
1.0000 M² Pintu Rolling Door bahan Aluminium = 681,120.00 681,120.00
JUMLAH 681,120.00

E.8 1 m² Sunscreen bahan Aluminium


0.0800 Oh Pekerja 96,800.00
0.8000 Oh Tukang Besi 121,000.00
0.0800 Oh Kepala Tukang 145,200.00
0.0040 Oh Mandor 133,100.00
1.0000 M² Sunscreen bahan Aluminium 1,800,000.00 1,800,000.00
JUMLAH 1,800,000.00

E.9 1 m' Kusen Pintu Aluminium


0.0430 Oh Pekerja 96,800.00
0.0430 Oh Tukang Besi 121,000.00
0.0043 Oh Kepala Tukang 145,200.00
0.0021 Oh Mandor 133,100.00
1.1000 M' Profil Aluminium (Kusen Aluminium) 96,000.00 105,600.00
2.0000 Bh Skrup Fixer 1,440.00 2,880.00
0.0600 Tube Sealent 30,000.00 1,800.00
JUMLAH 110,280.00

E.9.a 1 m' Kusen Pintu Aluminium (Gelap)


0.0430 Oh Pekerja 96,800.00
0.0430 Oh Tukang Besi 121,000.00
0.0043 Oh Kepala Tukang 145,200.00
0.0021 Oh Mandor 133,100.00
1.1000 M' Profil Aluminium (Kusen Aluminium) 144,000.00 158,400.00
2.0000 Bh Skrup Fixer 1,440.00 2,880.00
0.0600 Tube Sealent 30,000.00 1,800.00
JUMLAH 163,080.00

E.10 1 m² Pintu Aluminium Strip L = 8 cm


0.0850 Oh Pekerja 96,800.00
0.0850 Oh Tukang Besi 121,000.00
0.0085 Oh Kepala Tukang 145,200.00
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

0.0042 Oh Mandor 133,100.00


4.4000 M' Profil Aluminium -
14.6000 M' Aluminium Strip L = 8cm -
JUMLAH -

E.11 1 m² Pintu/Jendela Kaca Rangka Aluminium


0.0850 Oh Pekerja 96,800.00
0.0850 Oh Tukang Besi 121,000.00
0.0090 Oh Kepala Tukang 145,200.00
0.0050 Oh Mandor 133,100.00
4.4000 M² Profil Aluminium (Pintu Kaca) 385,000.00 1,694,000.00
4.5000 M' Profil Kaca 7,200.00 32,400.00
0.2700 Tube Sealent 30,000.00 8,100.00
JUMLAH 1,734,500.00

E.12 1 m² Terali Besi Strip 2 x 3 cm


1.6700 Oh Pekerja 96,800.00
1.6700 Oh Tukang Besi 121,000.00
0.1670 Oh Kepala Tukang 145,200.00
0.0830 Oh Mandor 133,100.00
6.1770 Kg Besi Strip 2 x 3 cm 10,800.00 66,711.60
27.0800 Cm Pengelasan 165.00 4,468.20
JUMLAH 71,179.80

E.13 1 m² Kawat Nyamuk


0.1000 Oh Pekerja 96,800.00
0.1000 Oh Tukang Besi 121,000.00
0.0100 Oh Kepala Tukang 145,200.00
0.0050 Oh Mandor 133,100.00
1.1000 M² Kawat Nyamuk 30,000.00 33,000.00
11.1100 Cm Pengelasan 165.00 1,833.15
1.7160 Kg Besi Strip 0,2 x 2 cm 10,800.00 18,532.80
JUMLAH 53,365.95

E.14 1 m² Jendela Nako & Teralis


0.2000 Oh Pekerja 96,800.00
0.2000 Oh Tukang Besi 121,000.00
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

0.0200 Oh Kepala Tukang 145,200.00


0.0010 Oh Mandor 133,100.00
1.1000 M² Jendela Nako + Kaca 201,840.00 222,024.00
10.0000 Cm Pengelasan 165.00 1,650.00
7.0000 Kg Besi Strip 2 x 3 cm 10,800.00 75,600.00
JUMLAH 299,274.00

E.15 1 m' Talang Datar / Jurai Seng BJLS 28 lebar 90 cm


0.2000 Oh Pekerja 96,800.00
0.2000 Oh Tukang Besi 121,000.00
0.0200 Oh Kepala Tukang 145,200.00
0.0010 Oh Mandor 133,100.00
1.0500 M' Seng BJLS 28 lebar 90 cm 60,000.00 63,000.00
0.0150 Kg Paku 1" - 2,5" 23,100.00 346.50
0.0190 M³ Papan Kayu kls.III 2,310,000.00 43,890.00
JUMLAH 107,236.50

E.16 1 m' Talang 1/2 Lingkaran D-15 cm, Seng Plat BJLS 30 lebar 45 cm
0.1500 Oh Pekerja 96,800.00
0.3000 Oh Tukang Besi 121,000.00
0.0300 Oh Kepala Tukang 145,200.00
0.0080 Oh Mandor 133,100.00
1.0500 M' Seng BJLS 30 lebar 45 cm 48,000.00 50,400.00
0.0100 Kg Paku 1" - 2,5" 23,100.00 231.00
0.5000 Kg Besi Strip 0,2 x 2 cm 10,800.00 5,400.00
JUMLAH 56,031.00

E.17 1 m² Dinding Partisi, Rangka Besi Hollow 40 x 40 x 2mm uk. 60 x 120 cm


0.2500 Oh Pekerja 96,800.00
0.2500 Oh Tukang Besi 121,000.00
0.0250 Oh Kepala Tukang 145,200.00
0.0130 Oh Mandor 133,100.00
3.5000 M' Besi Hollow 40 x 40 x 2mm 20,400.00 71,400.00
100% x rangka Ls Assesories 20,400.00 20,400.00
JUMLAH 91,800.00

E.18 1 m² Plafond, Rangka Besi Hollow 40 x 40 x 2mm uk. 60 x 60 cm


KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

0.3500 Oh Pekerja 96,800.00


0.3500 Oh Tukang Besi 121,000.00
0.0350 Oh Kepala Tukang 145,200.00
0.0180 Oh Mandor 133,100.00
4.0000 M' Besi Hollow 40 x 40 x 2mm 20,400.00 81,600.00
100% x rangka Ls Assesories 20,400.00 20,400.00
JUMLAH 102,000.00
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

5,808.00
7,260.00
871.20
399.30

14,338.50 30,067.05

5,808.00
7,260.00
871.20
399.30

14,338.50 31,529.51

3,872.00
2,420.00
290.40
266.20

stania
6,848.60 43,641.70 barka
4,364.17 kampak

al kafi
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

barakah
101,640.00
127,050.00
15,246.00
6,921.20
65000
15,931.48 13000

78000 8.16 9558.8235


250,857.20 950,380.86

116,160.00
145,200.00
17,424.00
798.60

279,582.60 778,542.60

42,592.00
53,240.00
6,388.80
2,928.20

105,149.00 451,229.00

96,800.00
121,000.00
14,520.00
6,655.00

238,975.00 825,055.00

96,800.00
121,000.00
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

14,520.00
6,655.00

238,975.00 920,095.00

7,744.00
96,800.00
11,616.00
532.40

116,692.40 1,916,692.40

4,162.40
5,203.00
624.36
279.51

10,269.27 120,549.27

4,162.40
5,203.00
624.36
279.51

10,269.27 173,349.27

8,228.00
10,285.00
1,234.20
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

559.02

20,306.22 20,306.22

8,228.00
10,285.00
1,306.80
665.50
350,000.00

20,485.30 1,754,985.30

161,656.00
202,070.00
24,248.40
11,047.30

399,021.70 470,201.50

9,680.00
12,100.00
1,452.00
665.50

23,897.50 77,263.45

19,360.00
24,200.00
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

2,904.00
133.10

46,597.10 345,871.10

19,360.00
24,200.00
2,904.00
133.10

46,597.10 153,833.60

14,520.00
36,300.00
4,356.00
1,064.80

56,240.80 112,271.80

24,200.00
30,250.00
3,630.00
1,730.30

59,810.30 151,610.30
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

33,880.00
42,350.00
5,082.00
2,395.80

83,707.80 185,707.80
318,344,000

318,344,000

318,344,000

318,344,000
318,344,000

1,591,720,000
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

F PEKERJAAN DINDING

F.1 1 m² Dinding Bt. Bata = 1 bt ad. 1 : 2


0.6000 Oh Pekerja 96,800.00
0.2000 Oh Tukang Batu 121,000.00
0.0200 Oh Kepala Tukang 145,200.00
0.0300 Oh Mandor 133,100.00
140.0000 Bh Bt. Bata (Kecil) 1,530.00 214,200.00
43.5000 Kg Semen Portland 1,668.00 72,558.00
0.0800 M³ Pasir Pasang 148,179.36 11,854.35
JUMLAH 298,612.35

F.2 1 m² Dinding Bt. Bata = 1 bt ad. 1 : 3


0.6000 Oh Pekerja 96,800.00
0.2000 Oh Tukang Batu 121,000.00
0.0200 Oh Kepala Tukang 145,200.00
0.0300 Oh Mandor 133,100.00
140.0000 Bh Bt. Bata (Kecil) 1,530.00 214,200.00
32.9500 Kg Semen Portland 1,668.00 54,960.60
0.0910 M³ Pasir Pasang 148,179.36 13,484.32
JUMLAH 282,644.92

F.3 1 m² Dinding Bt. Bata = 1 bt ad. 1 : 4


0.6000 Oh Pekerja 96,800.00
0.2000 Oh Tukang Batu 121,000.00
0.0200 Oh Kepala Tukang 145,200.00
0.0300 Oh Mandor 133,100.00
140.0000 Bh Bt. Bata (Kecil) 1,530.00 214,200.00
26.5500 Kg Semen Portland 1,668.00 44,285.40
0.0930 M³ Pasir Pasang 148,179.36 13,780.68
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

JUMLAH 272,266.08

F.4 1 m² Dinding Bt. Bata = 1 bt ad. 1 : 5


0.6000 Oh Pekerja 96,800.00
0.2000 Oh Tukang Batu 121,000.00
0.0200 Oh Kepala Tukang 145,200.00
0.0300 Oh Mandor 133,100.00
140.0000 Bh Bt. Bata (Kecil) 1,530.00 214,200.00
22.2000 Kg Semen Portland 1,668.00 37,029.60
0.1020 M³ Pasir Pasang 148,179.36 15,114.29
JUMLAH 266,343.89

F.5 1 m² Dinding Bt. Bata = 1 bt ad. 1 : 6


0.6000 Oh Pekerja 96,800.00
0.2000 Oh Tukang Batu 121,000.00
0.0200 Oh Kepala Tukang 145,200.00
0.0300 Oh Mandor 133,100.00
140.0000 Bh Bt. Bata (Kecil) 1,530.00 214,200.00
18.5000 Kg Semen Portland 1,668.00 30,858.00
0.1220 M³ Pasir Pasang 148,179.36 18,077.88
JUMLAH 263,135.88

F.6 1 m² Dinding Bt. Bata = 1/2 bt ad. 1 : 2


0.3000 Oh Pekerja 96,800.00
0.1000 Oh Tukang Batu 121,000.00
0.0100 Oh Kepala Tukang 145,200.00
0.0150 Oh Mandor 133,100.00
70.0000 Bh Bt. Bata (Kecil) 1,530.00 107,100.00
18.9500 Kg Semen Portland 1,668.00 31,608.60
0.0380 M³ Pasir Pasang 148,179.36 5,630.82
JUMLAH 144,339.42

F.7 1 m² Dinding Bt. Bata = 1/2 bt ad. 1 : 3


0.3000 Oh Pekerja 96,800.00
0.1000 Oh Tukang Batu 121,000.00
0.0100 Oh Kepala Tukang 145,200.00
0.0150 Oh Mandor 133,100.00
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

70.0000 Bh Bt. Bata (Kecil) 1,530.00 107,100.00


14.3700 Kg Semen Portland 1,668.00 23,969.16
0.0400 M³ Pasir Pasang 148,179.36 5,927.17
JUMLAH 136,996.33

F.8 1 m² Dinding Bt. Bata = 1/2 bt ad. 1 : 4


0.3000 Oh Pekerja 96,800.00
0.1000 Oh Tukang Batu 121,000.00
0.0100 Oh Kepala Tukang 145,200.00
0.0150 Oh Mandor 133,100.00
70.0000 Bh Bt. Bata (Kecil) 1,530.00 107,100.00
11.5000 Kg Semen Portland 1,668.00 19,182.00
0.0430 M³ Pasir Pasang 148,179.36 6,371.71
JUMLAH 132,653.71

F.9 1 m² Dinding Bt. Bata = 1/2 bt ad. 1 : 5


0.3000 Oh Pekerja 96,800.00
0.1000 Oh Tukang Batu 121,000.00
0.0100 Oh Kepala Tukang 145,200.00
0.0150 Oh Mandor 133,100.00
70.0000 Bh Bt. Bata (Kecil) 1,530.00 107,100.00
9.6800 Kg Semen Portland 1,668.00 16,146.24
0.0450 M³ Pasir Pasang 148,179.36 6,668.07
JUMLAH 129,914.31

F.10 1 m² Dinding Bt. Bata = 1/2 bt ad. 1 : 6


0.3000 Oh Pekerja 96,800.00
0.1000 Oh Tukang Batu 121,000.00
0.0100 Oh Kepala Tukang 145,200.00
0.0150 Oh Mandor 133,100.00
70.0000 Bh Bt. Bata (Kecil) 1,530.00 107,100.00
8.3200 Kg Semen Portland 1,668.00 13,877.76
0.0490 M³ Pasir Pasang 148,179.36 7,260.79
JUMLAH 128,238.55

F.11 1 m² Dinding Terawang / Rooster 12 x 11 x 24 cm


0.3000 Oh Pekerja 96,800.00
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

0.1000 Oh Tukang Batu 121,000.00


0.0100 Oh Kepala Tukang 145,200.00
0.0150 Oh Mandor 133,100.00
30.0000 Bh Terawang / Rooster 12 x 11 x 24 cm 8,760.00 262,800.00
11.0000 Kg Semen Portland 1,668.00 18,348.00
0.0350 M³ Pasir Pasang 148,179.36 5,186.28
JUMLAH 286,334.28

F.12 1 m² Dinding Terawang / Rooster 20 x x 20 cm


0.3000 Oh Pekerja 96,800.00
0.1000 Oh Tukang Batu 121,000.00
0.0100 Oh Kepala Tukang 145,200.00
0.0150 Oh Mandor 133,100.00
30.0000 Bh Terawang / Rooster 20 x 20 cm 26,400.00 792,000.00
11.0000 Kg Semen Portland 1,668.00 18,348.00
0.0350 M³ Pasir Pasang 148,179.36 5,186.28
JUMLAH 815,534.28

F.13 1 m² Dinding Batako


0.0833 Oh Pekerja 96,800.00
0.0833 Oh Tukang Batu 121,000.00
0.0083 Oh Kepala Tukang 145,200.00
0.0080 Oh Mandor 133,100.00
15.5000 Bh Bataco 10 x 18 x 30cm 2,120.00 32,860.00
5.8333 Kg Semen Portland 1,668.00 9,729.94
0.0133 M³ Pasir Pasang 148,179.36 1,970.79
JUMLAH 44,560.73

F.14 1 m² Pemasangan Glass Block


0.3000 Oh Pekerja 96,800.00
0.1500 Oh Tukang Batu 121,000.00
0.0150 Oh Kepala Tukang 145,200.00
0.0150 Oh Mandor 133,100.00
25.0000 Bh Glass Block 20 x 20cm 28,400.00 710,000.00
14.0000 Kg Semen Portland 1,668.00 23,352.00
0.0320 M³ Pasir Pasang 148,179.36 4,741.74
JUMLAH 738,093.74
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

F.15 1 bh Bak Kontrol Pasangan Batu Bata = 30 x 30cn tinggi = 50cm


3.2000 Oh Pekerja 96,800.00
1.0150 Oh Tukang Batu 121,000.00
0.0015 Oh Kepala Tukang 145,200.00
0.0160 Oh Mandor 133,100.00
0.1450 Bh Bt. Bata (Kecil) 1,530.00 221.85
44.0000 Kg Semen Portland 1,668.00 73,392.00
0.1300 M³ Pasir pasangan 148,179.36 19,263.32
0.0700 M³ Batu Pecah 1 - 3cm 455,000.00 31,850.00
1.6000 Kg Besi Beton Ø8mm 9,881.26 15,810.01
JUMLAH 140,537.18

F.16 1 bh Bak Kontrol Pasangan Batu Bata = 45 x 45cn tinggi = 50cm


1.4200 Oh Pekerja 96,800.00
1.4730 Oh Tukang Batu 121,000.00
0.0470 Oh Kepala Tukang 145,200.00
0.0710 Oh Mandor 133,100.00
0.2500 Bh Bt. Bata (Kecil) 1,530.00 382.50
77.0000 Kg Semen Portland 1,668.00 128,436.00
0.1030 M³ Pasir pasangan 148,179.36 15,262.47
0.0200 M³ Batu Pecah 1 - 3cm 455,000.00 9,100.00
2.6000 Kg Besi Beton Ø8mm 9,881.26 25,691.26
JUMLAH 178,872.24

F.17 1 bh Bak Kontrol Pasangan Batu Bata = 60 x 60cn tinggi = 65cm


2.1600 Oh Pekerja 96,800.00
1.7200 Oh Tukang Batu 121,000.00
0.0720 Oh Kepala Tukang 145,200.00
0.1080 Oh Mandor 133,100.00
0.1000 Oh Tukang Gali 121,000.00
0.3710 Bh Bt. Bata (Kecil) 1,530.00 567.63
114.0000 Kg Semen Portland 1,668.00 190,152.00
0.3040 M³ Pasir pasangan 148,179.36 45,046.53
0.0330 M³ Batu Pecah 1 - 3cm 455,000.00 15,015.00
4.8500 Kg Besi Beton Ø8mm 9,881.26 47,924.09
JUMLAH 298,705.24
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

58,080.00
24,200.00
2,904.00
3,993.00

89,177.00 387,789.35

58,080.00
24,200.00
2,904.00
3,993.00

89,177.00 371,821.92

58,080.00
24,200.00
2,904.00
3,993.00
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

89,177.00 361,443.08

58,080.00
24,200.00
2,904.00
3,993.00

89,177.00 355,520.89

58,080.00
24,200.00
2,904.00
3,993.00

89,177.00 352,312.88

29,040.00
12,100.00
1,452.00
1,996.50

44,588.50 188,927.92

29,040.00
12,100.00
1,452.00
1,996.50
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

44,588.50 181,584.83

151000000
29,040.00 15100000
12,100.00 166100000
1,452.00
1,996.50

44,588.50 177,242.21

29,040.00
12,100.00
1,452.00
1,996.50

44,588.50 174,502.81

29,040.00
12,100.00
1,452.00
1,996.50

44,588.50 172,827.05

29,040.00
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

12,100.00
1,452.00
1,996.50

44,588.50 330,922.78

29,040.00
12,100.00
1,452.00
1,996.50

44,588.50 860,122.78

8,063.44
10,079.30
1,205.16
1,064.80

20,412.70 64,973.43

29,040.00
18,150.00
2,178.00
1,996.50

51,364.50 789,458.24
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

309,760.00
122,815.00
217.80
2,129.60

434,922.40 575,459.58

137,456.00
178,233.00
6,824.40
9,450.10

331,963.50 510,835.74

209,088.00
208,120.00
10,454.40
14,374.80
12,100.00

454,137.20 752,842.44
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

G PEKERJAAN PLESTERAN

G.1 1 m² Plesteran ad. 1 : 1 tebal = 15 mm


0.3000 Oh Pekerja 96,800.00
0.1500 Oh Tukang Batu 121,000.00
0.0150 Oh Kepala Tukang 145,200.00
0.0150 Oh Mandor 133,100.00
15.5040 Kg Semen Portland 1,668.00 25,860.67
0.0160 M³ Pasir Pasang 148,179.36 2,370.87
JUMLAH 28,231.54

G.2 1 m² Plesteran ad. 1 : 2 tebal = 15 mm


0.3000 Oh Pekerja 96,800.00
0.1500 Oh Tukang Batu 121,000.00
0.0150 Oh Kepala Tukang 145,200.00
0.0150 Oh Mandor 133,100.00
10.2240 Kg Semen Portland 1,668.00 17,053.63
0.0200 M³ Pasir Pasang 148,179.36 2,963.59
JUMLAH 20,017.22

G.3 1 m² Plesteran ad. 1 : 3 tebal = 15 mm


0.3000 Oh Pekerja 96,800.00
0.1500 Oh Tukang Batu 121,000.00
0.0150 Oh Kepala Tukang 145,200.00
0.0150 Oh Mandor 133,100.00
7.7760 Kg Semen Portland 1,668.00 12,970.37
0.0230 M³ Pasir Pasang 148,179.36 3,408.13
JUMLAH 16,378.49

G.4 1 m² Plesteran ad. 1 : 4 tebal = 15 mm


KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

0.3000 Oh Pekerja 96,800.00


0.1500 Oh Tukang Batu 121,000.00
0.0150 Oh Kepala Tukang 145,200.00
0.0150 Oh Mandor 133,100.00
6.2400 Kg Semen Portland 1,668.00 10,408.32
0.0240 M³ Pasir Pasang 148,179.36 3,556.30
JUMLAH 13,964.62

G.5 1 m² Plesteran ad. 1 : 5 tebal = 15 mm


0.3000 Oh Pekerja 96,800.00
0.1500 Oh Tukang Batu 121,000.00
0.0150 Oh Kepala Tukang 145,200.00
0.0150 Oh Mandor 133,100.00
5.1840 Kg Semen Portland 1,668.00 8,646.91
0.0260 M³ Pasir Pasang 148,179.36 3,852.66
JUMLAH 12,499.58

G.6 1 m² Plesteran ad. 1 : 6 tebal = 15 mm


0.3000 Oh Pekerja 96,800.00
0.1500 Oh Tukang Batu 121,000.00
0.0150 Oh Kepala Tukang 145,200.00
0.0150 Oh Mandor 133,100.00
4.4160 Kg Semen Portland 1,668.00 7,365.89
0.0270 M³ Pasir Pasang 148,179.36 4,000.84
JUMLAH 11,366.73

G.7 1 m² Plesteran ad. 1 : 7 tebal = 15 mm


0.3000 Oh Pekerja 96,800.00
0.1500 Oh Tukang Batu 121,000.00
0.0150 Oh Kepala Tukang 145,200.00
0.0150 Oh Mandor 133,100.00
3.9360 Kg Semen Portland 1,668.00 6,565.25
0.0280 M³ Pasir Pasang 148,179.36 4,149.02
JUMLAH 10,714.27

G.8 1 m² Plesteran ad. 1 : 8 tebal = 15 mm


0.3000 Oh Pekerja 96,800.00
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

0.1500 Oh Tukang Batu 121,000.00


0.0150 Oh Kepala Tukang 145,200.00
0.0150 Oh Mandor 133,100.00
3.4560 Kg Semen Portland 1,668.00 5,764.61
0.0290 M³ Pasir Pasang 148,179.36 4,297.20
JUMLAH 10,061.81

G.9 1 m² Plesteran ad. 1 : 1 tebal = 20 mm


0.4000 Oh Pekerja 96,800.00
0.2000 Oh Tukang Batu 121,000.00
0.0200 Oh Kepala Tukang 145,200.00
0.0220 Oh Mandor 133,100.00
13.6320 Kg Semen Portland 1,668.00 22,738.18
0.0270 M³ Pasir Pasang 148,179.36 4,000.84
JUMLAH 26,739.02

G.10 1 m² Plesteran ad. 1 : 3 tebal = 20 mm


0.2600 Oh Pekerja 96,800.00
0.2000 Oh Tukang Batu 121,000.00
0.0200 Oh Kepala Tukang 145,200.00
0.0130 Oh Mandor 133,100.00
10.3680 Kg Semen Portland 1,668.00 17,293.82
0.0310 M³ Pasir Pasang 148,179.36 4,593.56
JUMLAH 21,887.38

G.11 1 m² Plesteran ad. 1 : 4 tebal = 20 mm


0.4000 Oh Pekerja 96,800.00
0.2000 Oh Tukang Batu 121,000.00
0.0200 Oh Kepala Tukang 145,200.00
0.0220 Oh Mandor 133,100.00
8.3200 Kg Semen Portland 1,668.00 13,877.76
0.0320 M³ Pasir Pasang 148,179.36 4,741.74
JUMLAH 18,619.50

G.12 1 m² Plesteran ad. 1 : 5 tebal = 20 mm


0.4000 Oh Pekerja 96,800.00
0.2000 Oh Tukang Batu 121,000.00
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

0.0200 Oh Kepala Tukang 145,200.00


0.0220 Oh Mandor 133,100.00
6.9120 Kg Semen Portland 1,668.00 11,529.22
0.0350 M³ Pasir Pasang 148,179.36 5,186.28
JUMLAH 16,715.49

G.13 1 m² Plesteran ad. 1 : 6 tebal = 20 mm


0.4000 Oh Pekerja 96,800.00
0.2000 Oh Tukang Batu 121,000.00
0.0200 Oh Kepala Tukang 145,200.00
0.0220 Oh Mandor 133,100.00
5.8880 Kg Semen Portland 1,668.00 9,821.18
0.0360 M³ Pasir Pasang 148,179.36 5,334.46
JUMLAH 15,155.64

G.14 1 m² Plesteran Ciprat ad. 1 : 2


0.3000 Oh Pekerja 96,800.00
0.1000 Oh Tukang Batu 121,000.00
0.0100 Oh Kepala Tukang 145,200.00
0.0150 Oh Mandor 133,100.00
4.3200 Kg Semen Portland 1,668.00 7,205.76
0.0060 M³ Pasir Pasang 148,179.36 889.08
JUMLAH 8,094.84

G.15 1 m² Finishing Siar Pasangan Bt. Bata


0.1500 Oh Pekerja 96,800.00
0.0750 Oh Tukang Batu 121,000.00
0.0080 Oh Kepala Tukang 145,200.00
0.0080 Oh Mandor 133,100.00
3.1080 Kg Semen Portland 1,668.00 5,184.14
JUMLAH 5,184.14

G.16 1 m² Finishing Siar Pasangan Bt. Kali ad. 1 : 2


0.3000 Oh Pekerja 96,800.00
0.1500 Oh Tukang Batu 121,000.00
0.0150 Oh Kepala Tukang 145,200.00
0.0150 Oh Mandor 133,100.00
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

6.3400 Kg Semen Portland 1,668.00 10,575.12


0.0120 M³ Pasir Pasang 148,179.36 1,778.15
JUMLAH 12,353.27

G.17 1 m² Acian
0.2000 Oh Pekerja 96,800.00
0.1000 Oh Tukang Batu 121,000.00
0.0100 Oh Kepala Tukang 145,200.00
0.0100 Oh Mandor 133,100.00
3.2500 Kg Semen Portland 1,668.00 5,421.00
JUMLAH 5,421.00
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

29,040.00
18,150.00
2,178.00
1,996.50

51,364.50 79,596.04

29,040.00
18,150.00
2,178.00
1,996.50

51,364.50 71,381.72

29,040.00
18,150.00
2,178.00
1,996.50

51,364.50 67,742.99
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

29,040.00
18,150.00
2,178.00
1,996.50

51,364.50 65,329.12

29,040.00
18,150.00
2,178.00
1,996.50

51,364.50 63,864.08

29,040.00
18,150.00
2,178.00
1,996.50

51,364.50 62,731.23

29,040.00
18,150.00
2,178.00
1,996.50

51,364.50 62,078.77

29,040.00
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

18,150.00
2,178.00
1,996.50

51,364.50 61,426.31

38,720.00
24,200.00
2,904.00
2,928.20

68,752.20 95,491.22

25,168.00
24,200.00
2,904.00
1,730.30

54,002.30 75,889.68

38,720.00
24,200.00
2,904.00
2,928.20

68,752.20 87,371.70

38,720.00
24,200.00
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

2,904.00
2,928.20

68,752.20 85,467.69

38,720.00
24,200.00
2,904.00
2,928.20

68,752.20 83,907.84

29,040.00
12,100.00
1,452.00
1,996.50

44,588.50 52,683.34

14,520.00
9,075.00
1,161.60
1,064.80

25,821.40 31,005.54

29,040.00
18,150.00
2,178.00
1,996.50
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

51,364.50 63,717.77

19,360.00
12,100.00
1,452.00
1,331.00

34,243.00 39,664.00
KODE HARGA SATUAN (Rp.)
URAIAN PEKERJAAN
ANAL BAHAN UPAH

I PEKERJAAN LANGIT-LANGIT / PLAFOND

I.1 1 m² Langit-Langit / Plafond Asbes = 4 mm


0.0300 Oh Pekerja 96,800.00
0.0700 Oh Tukang Kayu 121,000.00
0.0070 Oh Kepala Tukang 145,200.00
0.0040 Oh Mandor 133,100.00
1.1000 M² Langit-langit / Plafond Asbes = 4 mm 21,000.00
0.0100 Kg Paku Triplek 30,000.00
JUMLAH

I.1.a 1 m² Langit-Langit / Plafond Asbes = 5 mm


0.0300 Oh Pekerja 96,800.00
0.0700 Oh Tukang Kayu 121,000.00
0.0070 Oh Kepala Tukang 145,200.00
0.0040 Oh Mandor 133,100.00
1.1000 M² Langit-langit / Plafond Asbes = 5 mm 33,000.00
0.0100 Kg Paku Triplek 30,000.00
JUMLAH

I.1.b 1 m² Langit-Langit / Plafond Asbes = 6 mm


0.0300 Oh Pekerja 96,800.00
0.0700 Oh Tukang Kayu 121,000.00
0.0070 Oh Kepala Tukang 145,200.00
0.0040 Oh Mandor 133,100.00
1.1000 M² Langit-langit / Plafond Asbes = 6 mm 34,320.00
0.0100 Kg Paku Triplek 30,000.00
JUMLAH

I.2 1 m² Langit-Langit / Plafond Triplek = 120 x 240 cm tebal 3 mm


KODE HARGA SATUAN (Rp.)
URAIAN PEKERJAAN
ANAL BAHAN UPAH

0.1000 Oh Pekerja 96,800.00


0.1000 Oh Tukang Kayu 121,000.00
0.0100 Oh Kepala Tukang 145,200.00
0.0050 Oh Mandor 133,100.00
0.3750 Lbr Triplek = 120 x 240 cm tebal 3 mm 69,000.00
0.0300 Kg Paku Triplek 30,000.00
JUMLAH

I.2.a 1 m² Langit-Langit / Plafond Triplek = 120 x 240 cm tebal 4 mm


0.1000 Oh Pekerja 96,800.00
0.1000 Oh Tukang Kayu 121,000.00
0.0100 Oh Kepala Tukang 145,200.00
0.0050 Oh Mandor 133,100.00
0.3750 Lbr Triplek = 120 x 240 cm tebal 4 mm 82,500.00
0.0300 Kg Paku Triplek 30,000.00
JUMLAH

I.2.b 1 m² Langit-Langit / Plafond Triplek = 120 x 240 cm tebal 6 mm


0.1000 Oh Pekerja 96,800.00
0.1000 Oh Tukang Kayu 121,000.00
0.0100 Oh Kepala Tukang 145,200.00
0.0050 Oh Mandor 133,100.00
0.3750 Lbr Triplek = 120 x 240 cm tebal 6 mm 90,000.00
0.0300 Kg Paku Triplek 30,000.00
JUMLAH

I.3 1 m² Langit-Langit / Plafond Lambrisering Kayu = 9 mm


0.8000 Oh Pekerja 96,800.00
0.8000 Oh Tukang Kayu 121,000.00
0.0800 Oh Kepala Tukang 145,200.00
0.0400 Oh Mandor 133,100.00
0.0150 M³ Kayu Papan kls. II 3,480,000.00
0.0100 Kg Paku Triplek 30,000.00
JUMLAH

I.4 1 m² Langit-Langit / Plafond Akustik = 30 x 30 cm


0.1200 Oh Pekerja 96,800.00
KODE HARGA SATUAN (Rp.)
URAIAN PEKERJAAN
ANAL BAHAN UPAH

0.1200 Oh Tukang Kayu 121,000.00


0.0120 Oh Kepala Tukang 145,200.00
0.0060 Oh Mandor 133,100.00
12.0000 Lbr Langit-langit / Plafond Akustik = 30 x 30 cm 56,880.00
0.0500 Kg Paku Triplek 30,000.00
JUMLAH

I.5 1 m² Langit-Langit / Plafond Akustik = 30 x 60 cm


0.1200 Oh Pekerja 96,800.00
0.1200 Oh Tukang Kayu 121,000.00
0.0120 Oh Kepala Tukang 145,200.00
0.0060 Oh Mandor 133,100.00
5.8000 Lbr Langit-langit / Plafond Akustik = 30 x 60 cm 57,600.00
0.0500 Kg Paku Triplek 30,000.00
JUMLAH

I.6 1 m² Langit-Langit / Plafond Akustik = 60 x 120 cm


0.1000 Oh Pekerja 96,800.00
0.1000 Oh Tukang Kayu 121,000.00
0.0100 Oh Kepala Tukang 145,200.00
0.0050 Oh Mandor 133,100.00
1.5000 Lbr Langit-langit / Plafond Akustik = 60 x 120 cm
0.0500 Kg Paku Triplek 23,100.00
JUMLAH

I.7 1 m² Langit-Langit / Plafond Akustik = 60 x 120 cm + Rangka Aluminium


0.5000 Oh Pekerja 96,800.00
0.5000 Oh Tukang Kayu 121,000.00
0.0500 Oh Kepala Tukang 145,200.00
0.0250 Oh Mandor 133,100.00
3.6000 M' Profil Aluminium 'T" -
0.1500 Kg Kawat dia. 4mm
1.0500 Bh Ramset 1,950.00
1.5000 Lbr Langit-langit / Plafond Akustik
JUMLAH

I.8 1 m² Langit-Langit / Plafond Gypsum = 120 x 240 cm tebal = 9 mm (Polos)


KODE HARGA SATUAN (Rp.)
URAIAN PEKERJAAN
ANAL BAHAN UPAH

0.1000 Oh Pekerja 96,800.00


0.0500 Oh Tukang Kayu 121,000.00
0.0050 Oh Kepala Tukang 145,200.00
0.0050 Oh Mandor 133,100.00
0.3640 Lbr Gypsum Board 9 mm (Polos) 66,250.00
0.1100 Kg Paku Skrup 60,000.00
JUMLAH

I.8.a 1 m² Langit-Langit / Plafond Gypsum = 120 x 240 cm tebal = 9 mm (Motif)


0.1000 Oh Pekerja 96,800.00
0.0500 Oh Tukang Kayu 121,000.00
0.0050 Oh Kepala Tukang 145,200.00
0.0050 Oh Mandor 133,100.00
0.3640 Lbr Gypsum Board 9 mm (Motif) 145,728.00
0.1100 Kg Paku Skrup 60,000.00
JUMLAH

I.9 1 m' List Langit-Langit Kayu Profil


0.0500 Oh Pekerja 96,800.00
0.0500 Oh Tukang Kayu 121,000.00
0.0050 Oh Kepala Tukang 145,200.00
0.0030 Oh Mandor 133,100.00
1.0500 M' List Kayu Profil 29,400.00
0.0100 Kg Paku 30,000.00
JUMLAH

I.10 1 m' List Gypsum


0.0500 Oh Pekerja 96,800.00
0.0500 Oh Tukang kayu 121,000.00
0.0050 Oh Kepala tukang 145,200.00
0.0030 Oh Mandor 133,100.00
1.1000 M' List Gypsum 19,000.00
0.0100 Kg Paku sekrup 60,000.00
JUMLAH
JUMLAH (Rp) JUMLAH UPAH +
BAHAN UPAH BAHAN (Rp.)

2,904.00
8,470.00
1,016.40
532.40
23,100.00
300.00
23,400.00 12,922.80 36,322.80

2,904.00
8,470.00
1,016.40
532.40
36,300.00
300.00
36,600.00 12,922.80 49,522.80

2,904.00
8,470.00
1,016.40
532.40
37,752.00
300.00
38,052.00 12,922.80 50,974.80
JUMLAH (Rp) JUMLAH UPAH +
BAHAN UPAH BAHAN (Rp.)

9,680.00
12,100.00
1,452.00
665.50
25,875.00
900.00
26,775.00 23,897.50 50,672.50

9,680.00
12,100.00
1,452.00
665.50
30,937.50
900.00
31,837.50 23,897.50 55,735.00

9,680.00
12,100.00
1,452.00
665.50
33,750.00
900.00
34,650.00 23,897.50 58,547.50

77,440.00
96,800.00
11,616.00
5,324.00
52,200.00
300.00
52,500.00 191,180.00 243,680.00

11,616.00
JUMLAH (Rp) JUMLAH UPAH +
BAHAN UPAH BAHAN (Rp.)

14,520.00
1,742.40
798.60
682,560.00
1,500.00
684,060.00 28,677.00 712,737.00

11,616.00
14,520.00
1,742.40
798.60
334,080.00
1,500.00
335,580.00 28,677.00 364,257.00

9,680.00
12,100.00
1,452.00
665.50
-
1,155.00
1,155.00 23,897.50 25,052.50

48,400.00
60,500.00
7,260.00
3,327.50
-
-
2,047.50
-
2,047.50 119,487.50 121,535.00
JUMLAH (Rp) JUMLAH UPAH +
BAHAN UPAH BAHAN (Rp.)

9,680.00
6,050.00
726.00
665.50
24,115.00 33.19316
6,600.00
30,715.00 17,121.50 47,836.50

9,680.00
6,050.00
726.00
665.50
53,044.99
6,600.00
59,644.99 17,121.50 76,766.49

4,840.00
6,050.00
726.00
399.30
30,870.00
300.00
31,170.00 12,015.30 43,185.30

4,840.00
6,050.00
726.00
399.30
20,900.00
600.00
21,500.00 12,015.30 33,515.30
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

H PEKERJAAN PENUTUP LANTAI & DINDING

H.1 1 m² Lantai Keramik 20 x 20 cm (Polos)


0.7000 Oh Pekerja 96,800.00
0.3500 Oh Tukang Keramik 121,000.00
0.0350 Oh Kepala Tukang 145,200.00
0.0350 Oh Mandor 133,100.00
26.5000 Bh Keramik 20 x 20 cm (Polos) 2,022.64 53,600.00
10.4000 Kg Semen Portland 1,668.00 17,347.20
0.0450 M³ Pasir Pasang 148,179.36 6,668.07
1.6200 Kg Semen Warna 14,800.00 23,976.00
JUMLAH 101,591.27

H.1.a 1 m² Lantai Keramik 20 x 20 cm (Motif)


0.7000 Oh Pekerja 96,800.00
0.3500 Oh Tukang Keramik 121,000.00
0.0350 Oh Kepala Tukang 145,200.00
0.0350 Oh Mandor 133,100.00
26.5000 Bh Keramik 20 x 20 cm (Motif) 2,656.60 70,400.00
10.4000 Kg Semen Portland 1,668.00 17,347.20
0.0450 M³ Pasir Pasang 148,179.36 6,668.07
1.6200 Kg Semen Warna 14,800.00 23,976.00
JUMLAH 118,391.27

H.2 1 m' Plint Keramik 10 x 20 cm (Polos)


0.0900 Oh Pekerja 96,800.00
0.0900 Oh Tukang Keramik 121,000.00
0.0350 Oh Kepala Tukang 145,200.00
0.0050 Oh Mandor 133,100.00
5.3000 Bh Plint Keramik 10 x 20 cm (Polos) 1,011.32 5,360.00
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

1.1400 Kg Semen Portland 1,668.00 1,901.52


0.0030 M³ Pasir Pasang 148,179.36 444.54
0.0250 Kg Semen Warna 14,800.00 370.00
JUMLAH 8,076.06

H.2.a 1 m' Plint Keramik 10 x 20 cm (Motif)


0.0900 Oh Pekerja 96,800.00
0.0900 Oh Tukang Keramik 121,000.00
0.0350 Oh Kepala Tukang 145,200.00
0.0050 Oh Mandor 133,100.00
5.3000 Bh Plint Keramik 10 x 20 cm (Motif) 1,328.30 7,040.00
1.1400 Kg Semen Portland 1,668.00 1,901.52
0.0030 M³ Pasir Pasang 148,179.36 444.54
0.0250 Kg Semen Warna 14,800.00 370.00
JUMLAH 9,756.06

H.3 1 m² Lantai Keramik 30 x 30 cm (Polos)


0.7000 Oh Pekerja 96,800.00
0.3500 Oh Tukang Keramik 121,000.00
0.0350 Oh Kepala Tukang 145,200.00
0.0350 Oh Mandor 133,100.00
11.8700 Bh Keramik 30 x 30 cm (Polos) 4,852.57 57,600.00
10.0000 Kg Semen Portland 1,668.00 16,680.00
0.0450 M³ Pasir Pasang 148,179.36 6,668.07
1.5000 Kg Semen Warna 14,800.00 22,200.00
JUMLAH 103,148.07

H.3.a 1 m² Lantai Keramik 30 x 30 cm (Motif)


0.7000 Oh Pekerja 96,800.00
0.3500 Oh Tukang Keramik 121,000.00
0.0350 Oh Kepala Tukang 145,200.00
0.0350 Oh Mandor 133,100.00
11.8700 Bh Keramik 30 x 30 cm (Motif) 5,593.93 66,400.00
10.0000 Kg Semen Portland 1,668.00 16,680.00
0.0450 M³ Pasir Pasang 148,179.36 6,668.07
1.5000 Kg Semen Warna 14,800.00 22,200.00
JUMLAH 111,948.07
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

H.4 1 m' Plint Keramik 10 x 30 cm (Polos)


0.0900 Oh Pekerja 96,800.00
0.0900 Oh Tukang Keramik 121,000.00
0.0350 Oh Kepala Tukang 145,200.00
0.0050 Oh Mandor 133,100.00
3.5400 Bh Plint Keramik 10 x 30 cm (Polos) 1,617.52 5,726.03
1.1400 Kg Semen Portland 1,668.00 1,901.52
0.0030 M³ Pasir Pasang 148,179.36 444.54
0.0250 Kg Semen Warna 14,800.00 370.00
JUMLAH 8,442.09

H.4.a 1 m' Plint Keramik 10 x 30 cm (Motif)


0.0900 Oh Pekerja 96,800.00
0.0900 Oh Tukang Keramik 121,000.00
0.0350 Oh Kepala Tukang 145,200.00
0.0050 Oh Mandor 133,100.00
3.5400 Bh Plint Keramik 10 x 30 cm (Motif) 1,864.64 6,600.84
1.1400 Kg Semen Portland 1,668.00 1,901.52
0.0030 M³ Pasir Pasang 148,179.36 444.54
0.0250 Kg Semen Warna 14,800.00 370.00
JUMLAH 9,316.90

H.5 1 m² Lantai Keramik 40 x 40 cm (Polos)


0.7000 Oh Pekerja 96,800.00
0.3500 Oh Tukang Keramik 121,000.00
0.0350 Oh Kepala Tukang 145,200.00
0.0350 Oh Mandor 133,100.00
6.6300 Bh Keramik 40 x 40 cm (Polos) 10,995.48 72,900.00
9.8000 Kg Semen Portland 1,668.00 16,346.40
0.0450 M³ Pasir Pasang 148,179.36 6,668.07
1.3000 Kg Semen Warna 14,800.00 19,240.00
JUMLAH 115,154.47

H.5.a 1 m² Lantai Keramik 40 x 40 cm (Motif)


0.7000 Oh Pekerja 96,800.00
0.3500 Oh Tukang Keramik 121,000.00
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

0.0350 Oh Kepala Tukang 145,200.00


0.0350 Oh Mandor 133,100.00
6.6300 Bh Keramik 40 x 40 cm (Motif) 10,995.48 72,900.00
9.8000 Kg Semen Portland 1,668.00 16,346.40
0.0450 M³ Pasir Pasang 148,179.36 6,668.07
1.3000 Kg Semen Warna 14,800.00 19,240.00
JUMLAH 115,154.47

H.6 1 m' Plint Keramik 10 x 40 cm (Polos)


0.0900 Oh Pekerja 96,800.00
0.0900 Oh Tukang Keramik 121,000.00
0.0350 Oh Kepala Tukang 145,200.00
0.0050 Oh Mandor 133,100.00
2.6500 Bh Plint Keramik 10 x 40 cm (Polos) 2,748.87 7,284.50
1.1400 Kg Semen Portland 1,668.00 1,901.52
0.0030 M³ Pasir Pasang 148,179.36 444.54
0.1000 Kg Semen Warna 14,800.00 1,480.00
JUMLAH 11,110.56

H.6.a 1 m' Plint Keramik 10 x 40 cm (Motif)


0.0900 Oh Pekerja 96,800.00
0.0900 Oh Tukang Keramik 121,000.00
0.0350 Oh Kepala Tukang 145,200.00
0.0050 Oh Mandor 133,100.00
2.6500 Bh Plint Keramik 10 x 40 cm (Motif) 2,748.87 7,284.50
1.1400 Kg Semen Portland 1,668.00 1,901.52
0.0030 M³ Pasir Pasang 148,179.36 444.54
0.1000 Kg Semen Warna 14,800.00 1,480.00
JUMLAH 11,110.56

H.7 1 m² Lantai Keramik 60 x 60 cm Ex. Indogress


0.7000 Oh Pekerja 96,800.00
0.3500 Oh Tukang Keramik 121,000.00
0.0350 Oh Kepala Tukang 145,200.00
0.0350 Oh Mandor 133,100.00
3.1000 Bh Keramik 60 x 60 cm Ex. Indogress 133,548.39 414,000.00
9.8000 Kg Semen Portland 1,668.00 16,346.40
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

0.0450 M³ Pasir Pasang 148,179.36 6,668.07


1.5000 Kg Semen Warna 14,800.00 22,200.00
JUMLAH 459,214.47

H.7.a 1 m² Lantai Keramik 60 x 60 cm Ex. KIA


0.7000 Oh Pekerja 96,800.00
0.3500 Oh Tukang Keramik 121,000.00
0.0350 Oh Kepala Tukang 145,200.00
0.0350 Oh Mandor 133,100.00
3.1000 Bh Keramik 60 x 60 cm Ex. KIA 67,741.94 210,000.00
9.8000 Kg Semen Portland 1,668.00 16,346.40
0.0450 M³ Pasir Pasang 148,179.36 6,668.07
1.5000 Kg Semen Warna 14,800.00 22,200.00
JUMLAH 255,214.47

H.8 1 m' Plint Keramik 10 x 60 cm Ex. Indogress


0.0900 Oh Pekerja 96,800.00
0.0900 Oh Tukang Keramik 121,000.00
0.0350 Oh Kepala Tukang 145,200.00
0.0050 Oh Mandor 133,100.00
1.7000 Bh Plint Keramik 10 x 60 cm Ex. Indogres 22,258.06 37,838.71
1.1400 Kg Semen Portland 1,668.00 1,901.52
0.0030 M³ Pasir Pasang 148,179.36 444.54
0.1000 Kg Semen Warna 14,800.00 1,480.00
JUMLAH 41,664.77

H.8.a 1 m' Plint Keramik 10 x 60 cm Ex. KIA


0.0900 Oh Pekerja 96,800.00
0.0900 Oh Tukang Keramik 121,000.00
0.0350 Oh Kepala Tukang 145,200.00
0.0050 Oh Mandor 133,100.00
1.7000 Bh Plint Keramik 10 x 60 cm Ex. KIA 11,290.32 19,193.55
1.1400 Kg Semen Portland 1,668.00 1,901.52
0.0030 M³ Pasir Pasang 148,179.36 444.54
0.1000 Kg Semen Warna 14,800.00 1,480.00
JUMLAH 23,019.61
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

H.9 1 m² Lantai Keramik Mozaik 30 x 30 cm


0.7000 Oh Pekerja 96,800.00
0.3500 Oh Tukang Keramik 121,000.00
0.0350 Oh Kepala Tukang 145,200.00
0.0350 Oh Mandor 133,100.00
11.8700 Bh Keramik Mozaik 30 x 30 cm -
14.1500 Kg Semen Portland 1,668.00 23,602.20
0.0390 M³ Pasir Pasang 148,179.36 5,779.00
2.0000 Kg Semen Warna 14,800.00 29,600.00
JUMLAH 58,981.20

H.10 1 m² Lantai Marmer 100 x 100 cm


0.7000 Oh Pekerja 96,800.00
0.3500 Oh Tukang Keramik 121,000.00
0.0350 Oh Kepala Tukang 145,200.00
0.0350 Oh Mandor 133,100.00
1.0600 Bh Marmer 100 x 100 cm 283,018.87 300,000.00
8.1900 Kg Semen Portland 1,668.00 13,660.92
0.0450 M³ Pasir Pasang 148,179.36 6,668.07
0.6500 Kg Semen Warna 14,800.00 9,620.00
JUMLAH 329,948.99

H.11 1 m² Pasangan Conblock = 6cm (Polos)


0.0500 Oh Pekerja 96,800.00
0.1600 Oh Tukang Batu 121,000.00
0.0100 Oh Kepala Tukang 145,200.00
0.2500 Oh Mandor 133,100.00
1.0000 M² Conblock = 6cm (Polos) 58,800.00 58,800.00
JUMLAH 58,800.00

H.12 1 m² Pasangan Conblock = 6cm (Warna)


0.0500 Oh Pekerja 96,800.00
0.1600 Oh Tukang Batu 121,000.00
0.0100 Oh Kepala Tukang 145,200.00
0.2500 Oh Mandor 133,100.00
1.0000 M² Conblock = 6cm (Warna) 63,000.00 63,000.00
JUMLAH 63,000.00
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

H.13 1 m² Dinding Keramik 10 x 20 cm


0.9000 Oh Pekerja 96,800.00
0.4500 Oh Tukang Keramik 121,000.00
0.0450 Oh Kepala Tukang 145,200.00
0.0450 Oh Mandor 133,100.00
53.0000 Bh Keramik 10 x 20 cm 1,328.30 70,400.00
9.3000 Kg Semen Portland 1,668.00 15,512.40
0.0160 M³ Pasir Pasang 148,179.36 2,370.87
2.7500 Kg Semen Warna 14,800.00 40,700.00
JUMLAH 128,983.27

a 1 m² Dinding Keramik 20 x 20 cm (Polos)


0.9000 Oh Pekerja 96,800.00
0.4500 Oh Tukang Keramik 121,000.00
0.0450 Oh Kepala Tukang 145,200.00
0.0450 Oh Mandor 133,100.00
26.5000 Bh Keramik 20 x 20 cm (Polos) 2,022.64 53,600.00
9.3000 Kg Semen Portland 1,668.00 15,512.40
0.0160 M³ Pasir Pasang 148,179.36 2,370.87
1.9400 Kg Semen Warna 14,800.00 28,712.00
JUMLAH 100,195.27

H.14.a 1 m² Dinding Keramik 20 x 20 cm (Motif)


0.9000 Oh Pekerja 96,800.00
0.4500 Oh Tukang Keramik 121,000.00
0.0450 Oh Kepala Tukang 145,200.00
0.0450 Oh Mandor 133,100.00
26.5000 Bh Keramik 20 x 20 cm (Motif) 2,656.60 70,400.00
9.3000 Kg Semen Portland 1,668.00 15,512.40
0.0160 M³ Pasir Pasang 148,179.36 2,370.87
1.9400 Kg Semen Warna 14,800.00 28,712.00
JUMLAH 116,995.27

H.15 1 m² Dinding Marmer 100 x 100 cm


1.3000 Oh Pekerja 96,800.00
0.6500 Oh Tukang Keramik 121,000.00
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

0.0650 Oh Kepala Tukang 145,200.00


0.0650 Oh Mandor 133,100.00
1.0600 Bh Marmer 100 x 100 cm 283,018.87 300,000.00
12.4400 Kg Semen Portland 1,668.00 20,749.92
0.0250 M³ Pasir Pasang 148,179.36 3,704.48
0.6500 Kg Semen Warna 14,800.00 9,620.00
3.0300 Bh Paku Biasa 2"-5" 16,200.00 49,086.00
JUMLAH 383,160.40

H.16 1 m² Dinding Bt. Paras


0.7000 Oh Pekerja 96,800.00
0.3500 Oh Tukang Batu 121,000.00
0.0350 Oh Kepala Tukang 145,200.00
0.0350 Oh Mandor 133,100.00
1.1000 M² Bt. Paras 218,400.00 240,240.00
11.7500 Kg Semen Portland 1,668.00 19,599.00
0.0350 M³ Pasir Pasang 148,179.36 5,186.28
JUMLAH 265,025.28

H.17 1 m² Dinding Bt. Tempel Hitam


0.7000 Oh Pekerja 96,800.00
0.3500 Oh Tukang Batu 121,000.00
0.0350 Oh Kepala Tukang 145,200.00
0.0350 Oh Mandor 133,100.00
1.1000 M² Bt. Tempel Hitam 58,800.00 64,680.00
11.7500 Kg Semen Portland 1,668.00 19,599.00
0.0350 M³ Pasir Pasang 148,179.36 5,186.28
JUMLAH 89,465.28

H.17.a 1 m² Dinding Bt. Alam


0.7000 Oh Pekerja 96,800.00
0.3500 Oh Tukang Batu 121,000.00
0.0350 Oh Kepala Tukang 145,200.00
0.0350 Oh Mandor 133,100.00
1.1000 M² Bt. Alam 252,000.00 277,200.00
11.7500 Kg Semen Portland 1,668.00 19,599.00
0.0350 M³ Pasir Pasang 148,179.36 5,186.28
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

JUMLAH 301,985.28

H.18 1 m² Wallpaper = 50 cm (Polos)


0.3500 Oh Pekerja 96,800.00
0.1750 Oh Tukang Batu 121,000.00
0.0170 Oh Kepala Tukang 145,200.00
0.0020 Oh Mandor 133,100.00
2.2000 M' Wallpaper = 50 cm (Polos) 22,770.00 50,094.00
0.2500 Kg Lem (Fox) 60,000.00 15,000.00
JUMLAH 65,094.00

H.18.a 1 m² Wallpaper = 50 cm (Motif)


0.3500 Oh Pekerja 96,800.00
0.1750 Oh Tukang Batu 121,000.00
0.0170 Oh Kepala Tukang 145,200.00
0.0020 Oh Mandor 133,100.00
2.2000 M' Wallpaper = 50 cm (Motif) 53,130.00 116,886.00
0.2500 Kg Lem (Fox) 60,000.00 15,000.00
JUMLAH 131,886.00
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

67,760.00
42,350.00
5,082.00 Keramik 20 x 20 cm (Polos)
4,658.50
2,400 53600 26.5000 2,022.6415 53,600

1,668

148,179

14,800
119,850.50 221,441.77

67,760.00
42,350.00
5,082.00
4,658.50
2,491 70400 26.5000 2,656.6038 106.26

1,668

148,179

14,800
119,850.50 238,241.77

8,712.00
10,890.00
5,082.00
665.50
1,200
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

1,668

148,179

14,800
25,349.50 33,425.56

8,712.00
10,890.00
5,082.00
665.50
1,245

1,668

148,179

14,800
25,349.50 35,105.56

67,760.00
42,350.00
5,082.00
4,658.50
5,409

1,668

148,179

14,800
119,850.50 222,998.57

67,760.00
42,350.00
5,082.00
4,658.50
5,560 66400 11.8700 5,593.9343

1,668

148,179

14,800
119,850.50 231,798.57
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

8,712.00
10,890.00
5,082.00
665.50
9,600

1,668

148,179

14,800
25,349.50 33,791.59

8,712.00
10,890.00
5,082.00
665.50
16,800

1,668

148,179

14,800
25,349.50 34,666.40

67,760.00
42,350.00
5,082.00
4,658.50
11,493

1,668

148,179

14,800
119,850.50 235,004.97

67,760.00
42,350.00
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

5,082.00
4,658.50
11,765

1,668

148,179

14,800
119,850.50 235,004.97

8,712.00
10,890.00
5,082.00
665.50
9,600

1,668

148,179

14,800
25,349.50 36,460.06

8,712.00
10,890.00
5,082.00
665.50
16,800

1,668

148,179

14,800
25,349.50 36,460.06

67,760.00
42,350.00
5,082.00
4,658.50
133,548

1,668
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

148,179

14,800
119,850.50 579,064.97 36,689,556.58

67,760.00
42,350.00
5,082.00
4,658.50
67,742 210000 3.1000 67,741.9355

1,668

148,179

14,800
119,850.50 375,064.97 23,764,116.58

8,712.00
10,890.00
5,082.00
665.50
30,000

1,668

148,179

14,800
25,349.50 67,014.27

8,712.00
10,890.00
5,082.00
665.50
24,000

1,668

148,179

14,800
25,349.50 48,369.11
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

67,760.00
42,350.00
5,082.00
4,658.50

1,668

148,179

14,800
119,850.50 178,831.70

67,760.00
42,350.00
5,082.00
4,658.50
283,019 300000 1.0600 283018.867925

1,668

148,179

14,800
119,850.50 449,799.49

4,840.00
19,360.00
1,452.00
33,275.00
58,800
58,927.00 117,727.00

4,840.00
19,360.00
1,452.00
33,275.00
63,000
58,927.00 121,927.00
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

87,120.00
54,450.00
6,534.00
5,989.50
1,245

1,668

148,179

14,800
154,093.50 283,076.77

87,120.00
54,450.00
6,534.00
5,989.50
2,400

1,668

148,179

14,800
154,093.50 254,288.77

87,120.00
54,450.00
6,534.00
5,989.50
2,491

1,668

148,179

14,800
154,093.50 271,088.77

125,840.00
78,650.00
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

9,438.00
8,651.50
283,019

1,668

148,179

14,800

100
222,579.50 605,739.90

67,760.00
42,350.00
5,082.00
4,658.50
218,400

1,668

148,179
119,850.50 384,875.78

67,760.00
42,350.00
5,082.00
4,658.50
58,800

1,668

148,179
119,850.50 209,315.78

67,760.00
42,350.00
5,082.00
4,658.50
252,000

1,668

148,179
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

119,850.50 421,835.78

33,880.00
21,175.00
2,468.40
266.20
22,770

60,000
57,789.60 122,883.60

33,880.00
21,175.00
2,468.40
266.20
53,130

60,000
57,789.60 189,675.60
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

J PEKERJAAN PENUTUP ATAP

J.1 1 m² Atap Genteng Kodok Glazuur


0.1500 Oh Pekerja 96,800.00
0.0750 Oh Tukang Kayu 121,000.00
0.0080 Oh Kepala Tukang 145,200.00
0.0080 Oh Mandor 133,100.00
25.0000 Bh Atap Genteng Kodok Glazuur 3,960.00 99,000.00
JUMLAH 99,000.00

J.2 1 m² Bubungan Genteng Kodok Glazuur


0.4000 Oh Pekerja 96,800.00
0.2000 Oh Tukang Kayu 121,000.00
0.0200 Oh Kepala Tukang 145,200.00
0.0020 Oh Mandor 133,100.00
5.0000 Bh Bubungan Genteng Kodok Glazuur 4,800.00 24,000.00
8.0000 Kg Semen Portland 1,668.00 13,344.00
0.0320 M³ Pasir Pasang 148,179.36 4,741.74
JUMLAH 42,085.74

J.3 1 m² Atap Roof Light Fiberglass


0.1400 Oh Pekerja 96,800.00
0.0670 Oh Tukang Kayu 121,000.00
0.0070 Oh Kepala Tukang 145,200.00
0.0070 Oh Mandor 133,100.00
0.6000 Lbr Roof Light Fiberglass = 90 x 180 106,200.00 63,720.00
0.0500 Kg Paku Biasa 1/2" - 1" 23,100.00 1,155.00
JUMLAH 64,875.00

J.4 1 m² Atap Asbes Gelombang = 1,05 x 1,50 m tebal = 4 mm


KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

0.1400 Oh Pekerja 96,800.00


0.0700 Oh Tukang Kayu 121,000.00
0.0070 Oh Kepala Tukang 145,200.00
0.0070 Oh Mandor 133,100.00
0.8000 Lbr Asbes Gelombang = 1,05 x 1,50 m teba 46,200.00 36,960.00
0.1200 Kg Paku Asbes 25,714.29 3,085.71
JUMLAH 40,045.71

J.5 1 m² Atap Asbes Gelombang = 1,05 x 2,10 m tebal = 4 mm


0.1400 Oh Pekerja 96,800.00
0.0700 Oh Tukang Kayu 121,000.00
0.0070 Oh Kepala Tukang 145,200.00
0.0070 Oh Mandor 133,100.00
0.5100 Lbr Asbes Gelombang = 1,05 x 2,10 m teba 76,720.00 39,127.20
0.1200 Kg Paku Asbes 25,714.29 3,085.71
JUMLAH 42,212.91

J.6 1 m² Atap Asbes Gelombang = 1,05 x 2,40 m tebal = 4 mm


0.1400 Oh Pekerja 96,800.00
0.0700 Oh Tukang Kayu 121,000.00
0.0070 Oh Kepala Tukang 145,200.00
0.0070 Oh Mandor 133,100.00
0.4400 Lbr Asbes Gelombang = 1,05 x 2,40 m teba 87,680.00 38,579.20
0.1200 Kg Paku Asbes 25,714.29 3,085.71
JUMLAH 41,664.91

J.7 1 m² Atap Asbes Gelombang = 1,05 x 2,70 m tebal = 4 mm


0.1400 Oh Pekerja 96,800.00
0.0700 Oh Tukang Kayu 121,000.00
0.0070 Oh Kepala Tukang 145,200.00
0.0070 Oh Mandor 133,100.00
0.4200 Lbr Asbes Gelombang = 1,05 x 2,70 m teba 98,640.00 41,428.80
0.1200 Kg Paku Asbes 25,714.29 3,085.71
JUMLAH 44,514.51

J.8 1 m² Atap Asbes Gelombang = 1,05 x 3,00 m tebal = 4 mm


0.1400 Oh Pekerja 96,800.00
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

0.0700 Oh Tukang Kayu 121,000.00


0.0070 Oh Kepala Tukang 145,200.00
0.0070 Oh Mandor 133,100.00
0.3500 Lbr Asbes Gelombang = 1,05 x 3,00 m teba 109,600.00 38,360.00
0.1200 Kg Paku Asbes 25,714.29 3,085.71
JUMLAH 41,445.71

J.9 1 m² Atap Asbes Gelombang = 0,92 x 1,80 m tebal = 5 mm


0.1400 Oh Pekerja 96,800.00
0.0700 Oh Tukang Kayu 121,000.00
0.0070 Oh Kepala Tukang 145,200.00
0.0070 Oh Mandor 133,100.00
0.7500 Lbr Asbes Gelombang = 0,92 x 1,80 m teba 61,920.00 46,440.00
0.1200 Kg Paku Asbes 25,714.29 3,085.71
JUMLAH 49,525.71

J.10 1 m² Atap Asbes Gelombang = 0,92 x 2,00 m tebal = 5 mm


0.1400 Oh Pekerja 96,800.00
0.0700 Oh Tukang Kayu 121,000.00
0.0070 Oh Kepala Tukang 145,200.00
0.0070 Oh Mandor 133,100.00
0.6000 Lbr Asbes Gelombang = 0,92 x 2,00 m teba 70,320.00 42,192.00
0.1200 Kg Paku Asbes 25,714.29 3,085.71
JUMLAH 45,277.71

J.11 1 m² Atap Asbes Gelombang = 0,92 x 2,25 m tebal = 5 mm


0.1400 Oh Pekerja 96,800.00
0.0750 Oh Tukang Kayu 121,000.00
0.0080 Oh Kepala Tukang 145,200.00
0.0080 Oh Mandor 133,100.00
0.6000 Lbr Asbes Gelombang = 0,92 x 2,25 m teba 78,000.00 46,800.00
0.1200 Kg Paku Asbes 25,714.29 3,085.71
JUMLAH 49,885.71

J.12 1 m² Atap Asbes Gelombang = 0,92 x 2,50 m tebal = 5 mm


0.1400 Oh Pekerja 96,800.00
0.0750 Oh Tukang Kayu 121,000.00
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

0.0080 Oh Kepala Tukang 145,200.00


0.0080 Oh Mandor 133,100.00
0.5000 Lbr Asbes Gelombang = 0,92 x 2,50 m teba 87,960.00 43,980.00
0.1200 Kg Paku Asbes 25,714.29 3,085.71
JUMLAH 47,065.71

J.13 1 m² Atap Asbes Gelombang = 1,08 x 1,80 m tebal = 6 mm


0.1400 Oh Pekerja 96,800.00
0.0700 Oh Tukang Kayu 121,000.00
0.0070 Oh Kepala Tukang 145,200.00
0.0070 Oh Mandor 133,100.00
0.5700 Lbr Asbes Gelombang = 1,08 x 1,80 m teba 67,680.00 38,577.60
0.1200 Kg Paku Asbes 25,714.29 3,085.71
JUMLAH 41,663.31

J.14 1 m² Atap Asbes Gelombang = 1,08 x 2,10 m tebal = 6 mm


0.1400 Oh Pekerja 96,800.00
0.0700 Oh Tukang Kayu 121,000.00
0.0070 Oh Kepala Tukang 145,200.00
0.0070 Oh Mandor 133,100.00
0.4900 Lbr Asbes Gelombang = 1,08 x 2,10 m teba 82,800.00 40,572.00
0.1200 Kg Paku Asbes 25,714.29 3,085.71
JUMLAH 43,657.71

J.15 1 m² Atap Asbes Gelombang = 1,08 x 2,40 m tebal = 6 mm


0.1400 Oh Pekerja 96,800.00
0.0700 Oh Tukang Kayu 121,000.00
0.0070 Oh Kepala Tukang 145,200.00
0.0070 Oh Mandor 133,100.00
0.4600 Lbr Asbes Gelombang = 1,08 x 2,40 m teba 92,160.00 42,393.60
0.1200 Kg Paku Asbes 25,714.29 3,085.71
JUMLAH 45,479.31

J.16 1 m² Atap Asbes Gelombang = 1,08 x 2,70 m tebal = 6 mm


0.1400 Oh Pekerja 96,800.00
0.0700 Oh Tukang Kayu 121,000.00
0.0070 Oh Kepala Tukang 145,200.00
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

0.0070 Oh Mandor 133,100.00


0.3800 Lbr Asbes Gelombang = 1,08 x 2,70 m teba 92,880.00 35,294.40
0.1200 Kg Paku Asbes 25,714.29 3,085.71
JUMLAH 38,380.11

J.17 1 m² Atap Asbes Gelombang = 1,08 x 3,00 m tebal = 6 mm


0.1400 Oh Pekerja 96,800.00
0.0700 Oh Tukang Kayu 121,000.00
0.0070 Oh Kepala Tukang 145,200.00
0.0070 Oh Mandor 133,100.00
0.3700 Lbr Asbes Gelombang = 1,08 x 3,00 m teba 103,200.00 38,184.00
0.1200 Kg Paku Asbes 25,714.29 3,085.71
JUMLAH 41,269.71

J.18 1 m' Bubungan Asbes Gelombang


0.0840 Oh Pekerja 96,800.00
0.1250 Oh Tukang Kayu 121,000.00
0.0130 Oh Kepala Tukang 145,200.00
0.0040 Oh Mandor 133,100.00
2.0500 Lbr Bubungan Asbes Gelombang 21,450.00 43,972.50
6.0000 Kg Paku Asbes 25,714.29 154,285.71
JUMLAH 198,258.21

J.19 1 m² Atap Genteng Beton


0.2000 Oh Pekerja 96,800.00
0.1000 Oh Tukang Kayu 121,000.00
0.0100 Oh Kepala Tukang 145,200.00
0.0100 Oh Mandor 133,100.00
11.0000 Bh Atap Genteng Beton 6,600.00 72,600.00
0.0300 Kg Paku Biasa 1/2" - 1" 23,100.00 693.00
JUMLAH 73,293.00

J.19.a 1 m' Bubungan Atap Genteng Beton


0.4000 Oh Pekerja 96,800.00
0.2000 Oh Tukang Kayu 121,000.00
0.0200 Oh Kepala Tukang 145,200.00
0.0200 Oh Mandor 133,100.00
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

3.5000 Bh Bubungan Genteng Beton 7,200.00 25,200.00


0.0500 Kg Paku Biasa 1/2" - 1" 23,100.00 1,155.00
10.8000 Kg Semen Portland 1,668.00 18,014.40
0.0320 M³ Pasir Pasang 148,179.36 4,741.74
1.0000 Kg Semen Warna 14,800.00 14,800.00
JUMLAH 63,911.14

J.20 1 m² Atap Genteng Metal (Polos)


0.2000 Oh Pekerja 96,800.00
0.1000 Oh Tukang Kayu 121,000.00
0.0100 Oh Kepala Tukang 145,200.00
0.0010 Oh Mandor 133,100.00
1.0200 Bh Atap Genteng Metal (Polos) 42,000.00 42,840.00
0.2000 Kg Paku Biasa 1/2" - 1" 23,100.00 4,620.00
JUMLAH 47,460.00

J.20.a 1 m' Bubungan Atap Genteng Metal (Polos)


0.2500 Oh Pekerja 96,800.00
0.1500 Oh Tukang Kayu 121,000.00
0.0150 Oh Kepala Tukang 145,200.00
0.0130 Oh Mandor 133,100.00
1.1000 Bh Bubungan Genteng Metal (Polos) 39,000.00 42,900.00
0.0500 Kg Paku Biasa 1/2" - 1" 23,100.00 1,155.00
JUMLAH 44,055.00

J.21 1 m² Atap Genteng Metal (Berpasir)


0.2000 Oh Pekerja 96,800.00
0.1000 Oh Tukang Kayu 121,000.00
0.0100 Oh Kepala Tukang 145,200.00
0.0010 Oh Mandor 133,100.00
1.0200 Bh Atap Genteng Metal (Berpasir) 69,000.00 70,380.00
0.2000 Kg Paku Biasa 1/2" - 1" 23,100.00 4,620.00
JUMLAH 75,000.00

J.21.a 1 m' Bubungan Atap Genteng Metal (Berpasir)


0.2500 Oh Pekerja 96,800.00
0.1500 Oh Tukang Kayu 121,000.00
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

0.0150 Oh Kepala Tukang 145,200.00


0.0130 Oh Mandor 133,100.00
1.1000 Bh Bubungan Genteng Metal (Berpasir) 53,400.00 58,740.00
0.0500 Kg Paku Biasa 1/2" - 1" 23,100.00 1,155.00
JUMLAH 59,895.00

J.22 1 m² Atap Seng Gelombang


0.1200 Oh Pekerja 96,800.00
0.0600 Oh Tukang Kayu 121,000.00
0.0060 Oh Kepala Tukang 145,200.00
0.0060 Oh Mandor 133,100.00
0.7000 Lbr Atap Seng Gelombang 43,200.00 30,240.00
0.0200 Kg Paku Biasa 1/2" - 1" 23,100.00 462.00
JUMLAH 30,702.00

J.22.a 1 m' Bubungan Atap Seng BJLS 30


0.1500 Oh Pekerja 96,800.00
0.0700 Oh Tukang Kayu 121,000.00
0.0070 Oh Kepala Tukang 145,200.00
0.0060 Oh Mandor 133,100.00
0.3000 Lbr Seng BJLS 30 lebar 45 cm 18,000.00 5,400.00
0.0400 Kg Paku Biasa 1/2" - 1" 23,100.00 924.00
JUMLAH 6,324.00

J.23 1 m² Atap Aluminium Gelombang = 0,55 mm


0.1500 Oh Pekerja 96,800.00
0.7500 Oh Tukang Kayu 121,000.00
0.0800 Oh Kepala Tukang 145,200.00
0.0060 Oh Mandor 133,100.00
1.0500 M² Atap Aluminium Gelombang = 0,55 mm 75,200.00 78,960.00
0.0200 Kg Paku Biasa 1/2" - 1" 23,100.00 462.00
JUMLAH 79,422.00

J.23.a 1 m' Bubungan Atap Aluminium


0.1000 Oh Pekerja 96,800.00
1.0000 Oh Tukang Kayu 121,000.00
0.1000 Oh Kepala Tukang 145,200.00
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

0.0500 Oh Mandor 133,100.00


1.2000 Bh Bubungan Atap Aluminium 72,840.00 87,408.00
0.0400 Kg Paku Biasa 1/2" - 1" 23,100.00 924.00
JUMLAH 88,332.00

J.24 1 m² Atap Genteng Keramik (Setara KIA)


0.1500 Oh Pekerja 96,800.00
0.0750 Oh Tukang Kayu 121,000.00
0.0080 Oh Kepala Tukang 145,200.00
0.0080 Oh Mandor 133,100.00
15.0000 Bh Atap Genteng Keramik (Setara KIA) 15,000.00 225,000.00
JUMLAH 225,000.00

J.24.a 1 m² Bubungan Atap Genteng Keramik (Setara KIA)


0.4000 Oh Pekerja 96,800.00
0.2000 Oh Tukang Kayu 121,000.00
0.0200 Oh Kepala Tukang 145,200.00
0.0200 Oh Mandor 133,100.00
3.5000 Bh Bubungan Atap Genteng Keramik (Setar 11,220.00 39,270.00
0.2000 Kg Paku 1" - 2,5" 23,100.00 4,620.00
10.8000 Kg Semen Portland 1,668.00 18,014.40
0.0320 M³ Pasir Pasang 148,179.36 4,741.74
JUMLAH 66,646.14

J.25 1 m' Aluminium Foil


0.1500 Oh Pekerja 96,800.00
0.0500 Oh Tukang Kayu 121,000.00
0.0050 Oh Kepala Tukang 145,200.00
0.0080 Oh Mandor 133,100.00
1.0500 M² Aluminium Foil 55,062.00 57,815.10
JUMLAH 57,815.10
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

14,520.00
9,075.00
1,161.60
1,064.80

25,821.40 124,821.40

38,720.00
24,200.00
2,904.00
266.20

66,090.20 108,175.94

13,552.00
8,107.00
1,016.40
931.70

23,607.10 88,482.10
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

13,552.00
8,470.00
1,016.40
931.70

23,970.10 64,015.81

13,552.00
8,470.00
1,016.40
931.70

23,970.10 66,183.01

13,552.00
8,470.00
1,016.40
931.70

23,970.10 65,635.01

13,552.00
8,470.00
1,016.40
931.70

23,970.10 68,484.61

13,552.00
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

8,470.00
1,016.40
931.70

23,970.10 65,415.81

13,552.00
8,470.00
1,016.40
931.70

23,970.10 73,495.81

13,552.00
8,470.00
1,016.40
931.70

23,970.10 69,247.81

13,552.00
9,075.00
1,161.60
1,064.80

24,853.40 74,739.11

13,552.00
9,075.00
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

1,161.60
1,064.80

24,853.40 71,919.11

13,552.00
8,470.00
1,016.40
931.70

23,970.10 65,633.41

13,552.00
8,470.00
1,016.40
931.70

23,970.10 67,627.81

13,552.00
8,470.00
1,016.40
931.70

23,970.10 69,449.41

13,552.00
8,470.00
1,016.40
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

931.70

23,970.10 62,350.21

13,552.00
8,470.00
1,016.40
931.70

23,970.10 65,239.81

8,131.20
15,125.00
1,887.60
532.40

25,676.20 223,934.41

19,360.00
12,100.00
1,452.00
1,331.00

34,243.00 107,536.00

38,720.00
24,200.00
2,904.00
2,662.00
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

68,486.00 132,397.14

19,360.00
12,100.00
1,452.00
133.10

33,045.10 80,505.10

24,200.00
18,150.00
2,178.00
1,730.30

46,258.30 90,313.30

19,360.00
12,100.00
1,452.00
133.10

33,045.10 108,045.10

24,200.00
18,150.00
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

2,178.00
1,730.30

46,258.30 106,153.30

11,616.00
7,260.00
871.20
798.60

20,545.80 51,247.80

14,520.00
8,470.00
1,016.40
798.60

24,805.00 31,129.00

14,520.00
90,750.00
11,616.00
798.60

117,684.60 197,106.60

9,680.00
121,000.00
14,520.00
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

6,655.00

151,855.00 240,187.00

14,520.00
9,075.00
1,161.60
1,064.80

25,821.40 250,821.40

38,720.00
24,200.00
2,904.00
2,662.00

68,486.00 135,132.14

14,520.00
6,050.00
726.00
1,064.80

22,360.80 80,175.90
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

K PEKERJAAN KAYU

K.1 1 m³ Kusen Pintu & Jendela Kayu kls. I


7.0000 Oh Pekerja 96,800.00
21.0000 Oh Tukang Kayu 121,000.00
2.1000 Oh Kepala Tukang 145,200.00
0.3500 Oh Mandor 133,100.00
1.1000 M³ Balok Kayu kls. I 3,900,000.00 4,290,000.00
1.2500 Kg Paku Biasa 2"-5" 16,200.00 20,250.00
1.0000 Kg Lem Kayu 15,120.00 15,120.00
JUMLAH 4,325,370.00

K.2 1 m³ Kusen Pintu & Jendela Kayu kls. II


6.0000 Oh Pekerja 96,800.00
18.0000 Oh Tukang Kayu 121,000.00
1.8000 Oh Kepala Tukang 145,200.00
0.3000 Oh Mandor 133,100.00
1.2000 M³ Balok Kayu kls. II 3,300,000.00 3,960,000.00
1.2500 Kg Paku Biasa 2"-5" 16,200.00 20,250.00
1.0000 Kg Lem Kayu 15,120.00 15,120.00
JUMLAH 3,995,370.00

K.2.a 1 m³ Kusen Pintu & Jendela Kayu kls. III


6.0000 Oh Pekerja 96,800.00
18.0000 Oh Tukang Kayu 121,000.00
1.8000 Oh Kepala Tukang 145,200.00
0.3000 Oh Mandor 133,100.00
1.2000 M³ Balok Kayu kls. III 2,880,000.00 3,456,000.00
1.2500 Kg Paku Biasa 2"-5" 16,200.00 20,250.00
1.0000 Kg Lem Kayu 15,120.00 15,120.00
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

JUMLAH 3,491,370.00

K.3 1 m² Daun Pintu Panil Kayu kls. II


1.0000 Oh Pekerja 96,800.00
3.0000 Oh Tukang Kayu 121,000.00
0.3000 Oh Kepala Tukang 145,200.00
0.0500 Oh Mandor 133,100.00
0.0400 M³ Papan Kayu kls. II 3,480,000.00 139,200.00
0.5000 Kg Lem Kayu 15,120.00 7,560.00
JUMLAH 146,760.00

K.3.a 1 m² Daun Pintu Panil Kayu kls. III


1.0000 Oh Pekerja 96,800.00
3.0000 Oh Tukang Kayu 121,000.00
0.3000 Oh Kepala Tukang 145,200.00
0.0500 Oh Mandor 133,100.00
0.0400 M³ Papan Kayu kls. III 2,310,000.00 92,400.00
0.5000 Kg Lem Kayu 15,120.00 7,560.00
JUMLAH 99,960.00

K.4 1 m² Pintu & Jendela Kaca Kayu kls. I


0.8000 Oh Pekerja 96,800.00
2.4000 Oh Tukang Kayu 121,000.00
0.2400 Oh Kepala Tukang 145,200.00
0.0400 Oh Mandor 133,100.00
0.0240 M³ Papan Kayu kls. I 3,900,000.00 93,600.00
0.3000 Kg Lem Kayu 15,120.00 4,536.00
JUMLAH 98,136.00

K.4.a 1 m² Pintu & Jendela Kaca Kayu kls. II


0.8000 Oh Pekerja 96,800.00
2.4000 Oh Tukang Kayu 121,000.00
0.2400 Oh Kepala Tukang 145,200.00
0.0400 Oh Mandor 133,100.00
0.0240 M³ Papan Kayu kls. II 3,480,000.00 83,520.00
0.3000 Kg Lem Kayu 15,120.00 4,536.00
JUMLAH 88,056.00
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

K.4.b 1 m² Pintu & Jendela Kaca Kayu kls. III


0.8000 Oh Pekerja 96,800.00
2.4000 Oh Tukang Kayu 121,000.00
0.2400 Oh Kepala Tukang 145,200.00
0.0400 Oh Mandor 133,100.00
0.0240 M³ Papan Kayu kls. III 2,310,000.00 55,440.00
0.3000 Kg Lem Kayu 15,120.00 4,536.00
JUMLAH 59,976.00

K.5 1 m² Pintu & Jendela Jalusi Kayu kls. I


1.0000 Oh Pekerja 96,800.00
3.0000 Oh Tukang Kayu 121,000.00
0.3000 Oh Kepala Tukang 145,200.00
0.0500 Oh Mandor 133,100.00
0.0640 M³ Papan Kayu kls. I 3,900,000.00 249,600.00
0.5000 Kg Lem Kayu 15,120.00 7,560.00
JUMLAH 257,160.00

K.5.a 1 m² Pintu & Jendela Jalusi Kayu kls. II


1.0000 Oh Pekerja 96,800.00
3.0000 Oh Tukang Kayu 121,000.00
0.3000 Oh Kepala Tukang 145,200.00
0.0500 Oh Mandor 133,100.00
0.0640 M³ Papan Kayu kls. II 3,480,000.00 222,720.00
0.5000 Kg Lem Kayu 15,120.00 7,560.00
JUMLAH 230,280.00

K.6 1 m² Daun Pintu Playwood Rangkap Kayu kls. II tertutup


0.7000 Oh Pekerja 96,800.00
2.1000 Oh Tukang Kayu 121,000.00
0.2100 Oh Kepala Tukang 145,200.00
0.0350 Oh Mandor 133,100.00
0.0250 M³ Papan Kayu kls. II 3,480,000.00 87,000.00
0.0300 Kg Paku 1" - 2,5" 23,100.00 693.00
0.5000 Kg Lem Kayu 15,120.00 7,560.00
1.0000 Lbr Playwood 90 x 220cm tebal = 4mm 70,020.16 70,020.16
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

JUMLAH 165,273.16

K.7 1 m² Jalusi Kusen Kayu kls. I


0.6700 Oh Pekerja 96,800.00
2.0000 Oh Tukang Kayu 121,000.00
0.2000 Oh Kepala Tukang 145,200.00
0.3350 Oh Mandor 133,100.00
0.0600 M³ Papan Kayu kls. I 3,900,000.00 234,000.00
0.1500 Kg Paku 1" - 2,5" 23,100.00 3,465.00
JUMLAH 237,465.00

K.7.a 1 m² Jalusi Kusen Kayu kls. II


0.6700 Oh Pekerja 96,800.00
2.0000 Oh Tukang Kayu 121,000.00
0.2000 Oh Kepala Tukang 145,200.00
0.3350 Oh Mandor 133,100.00
0.0600 M³ Papan Kayu kls. II 3,480,000.00 208,800.00
0.1500 Kg Paku 1" - 2,5" 23,100.00 3,465.00
JUMLAH 212,265.00

K.8 1 m² Daun Pintu Playwood Rangkap Kayu kls. I expose


0.8000 Oh Pekerja 96,800.00
2.4000 Oh Tukang Kayu 121,000.00
0.2400 Oh Kepala Tukang 145,200.00
0.0400 Oh Mandor 133,100.00
0.0256 M³ Papan Kayu kls. I 3,900,000.00 99,840.00
0.0300 Kg Paku 1" - 2,5" 23,100.00 693.00
0.5000 Kg Lem Kayu 15,120.00 7,560.00
1.0000 Lbr Playwood 90 x 220cm tebal = 4mm 70,020.16 70,020.16
JUMLAH 178,113.16

K.8.a 1 m² Daun Pintu Playwood Rangkap Kayu kls. II expose


0.8000 Oh Pekerja 96,800.00
2.4000 Oh Tukang Kayu 121,000.00
0.2400 Oh Kepala Tukang 145,200.00
0.0400 Oh Mandor 133,100.00
0.0256 M³ Papan Kayu kls. II 3,480,000.00 89,088.00
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

0.0300 Kg Paku 1" - 2,5" 23,100.00 693.00


0.5000 Kg Lem Kayu 15,120.00 7,560.00
1.0000 Lbr Playwood 90 x 220cm tebal = 4mm 70,020.16 70,020.16
JUMLAH 167,361.16

K.9 1 m² Teakwood Rangkap Kayu kls. I expose


0.8000 Oh Pekerja 96,800.00
2.4000 Oh Tukang Kayu 121,000.00
0.2400 Oh Kepala Tukang 145,200.00
0.0400 Oh Mandor 133,100.00
0.0250 M³ Papan Kayu kls. I 3,900,000.00 97,500.00
0.0300 Kg Paku 1" - 2,5" 23,100.00 693.00
0.3000 Kg Lem Kayu 15,120.00 4,536.00
1.0000 Lbr Teakwood 90 x 220cm tebal = 4mm 99,000.00 99,000.00
JUMLAH 201,729.00

K.10 1 m² Teakwood Rangkap Lapis Formika Kayu kls. II expose


0.8500 Oh Pekerja 96,800.00
2.5500 Oh Tukang Kayu 121,000.00
0.2550 Oh Kepala Tukang 145,200.00
0.0430 Oh Mandor 133,100.00
0.0250 M³ Papan Kayu kls. II 3,480,000.00 87,000.00
0.0300 Kg Paku 1" - 2,5" 23,100.00 693.00
0.8000 Kg Lem Kayu 15,120.00 12,096.00
1.0000 Lbr Teakwood 90 x 220cm tebal = 4mm 99,000.00 99,000.00
0.5000 Lbr Formika 90,000.00 45,000.00
JUMLAH 243,789.00

K.11 1 m³ Konstruksi Kuda-Kuda Konvensional Kayu kls. I bentang = 6 m


4.0000 Oh Pekerja 96,800.00
12.0000 Oh Tukang Kayu 121,000.00
1.2000 Oh Kepala Tukang 145,200.00
0.2000 Oh Mandor 133,100.00
1.1000 M³ Balok Kayu kls. I 3,900,000.00 4,290,000.00
15.0000 Kg Besi Strip 10,800.00 162,000.00
5.6000 Kg Paku Biasa 2"-5" 16,200.00 90,720.00
JUMLAH 4,542,720.00
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

K.11.a 1 m³ Konstruksi Kuda-Kuda Konvensional Kayu kls. II bentang = 6 m


4.0000 Oh Pekerja 96,800.00
12.0000 Oh Tukang Kayu 121,000.00
1.2000 Oh Kepala Tukang 145,200.00
0.2000 Oh Mandor 133,100.00
1.1000 M³ Balok Kayu kls. II 3,300,000.00 3,630,000.00
15.0000 Kg Besi Strip 10,800.00 162,000.00
5.6000 Kg Paku Biasa 2"-5" 16,200.00 90,720.00
JUMLAH 3,882,720.00

K.11.b 1 m³ Konstruksi Kuda-Kuda Konvensional Kayu kls. III bentang = 6 m


4.0000 Oh Pekerja 96,800.00
12.0000 Oh Tukang Kayu 121,000.00
1.2000 Oh Kepala Tukang 145,200.00
0.2000 Oh Mandor 133,100.00
1.1000 M³ Balok Kayu kls. III 2,880,000.00 3,168,000.00
15.0000 Kg Besi Strip 10,800.00 162,000.00
5.6000 Kg Paku Biasa 2"-5" 16,200.00 90,720.00
JUMLAH 3,420,720.00

K.12 1 m³ Konstruksi Kuda-Kuda Expose Kayu kls. I


6.7000 Oh Pekerja 96,800.00
20.1000 Oh Tukang Kayu 121,000.00
2.0100 Oh Kepala Tukang 145,200.00
0.3350 Oh Mandor 133,100.00
1.2000 M³ Balok Kayu kls. I 3,900,000.00 4,680,000.00
15.0000 Kg Besi Strip 10,800.00 162,000.00
5.6000 Kg Paku Biasa 2"-5" 16,200.00 90,720.00
JUMLAH 4,932,720.00

K.12.a 1 m³ Konstruksi Kuda-Kuda Expose Kayu kls. II


6.7000 Oh Pekerja 96,800.00
20.1000 Oh Tukang Kayu 121,000.00
2.0100 Oh Kepala Tukang 145,200.00
0.3350 Oh Mandor 133,100.00
1.2000 M³ Balok Kayu kls. II 3,300,000.00 3,960,000.00
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

15.0000 Kg Besi Strip 10,800.00 162,000.00


5.6000 Kg Paku Biasa 2"-5" 16,200.00 90,720.00
JUMLAH 4,212,720.00

K.13 1 m³ Gording Kayu kls. II


6.7000 Oh Pekerja 96,800.00
20.1000 Oh Tukang Kayu 121,000.00
2.0100 Oh Kepala Tukang 145,200.00
0.3350 Oh Mandor 133,100.00
1.1000 M³ Balok Kayu kls. II 3,300,000.00 3,630,000.00
15.0000 Kg Besi Strip 10,800.00 162,000.00
3.0000 Kg Paku Biasa 2"-5" 16,200.00 48,600.00
JUMLAH 3,840,600.00

K.13.a 1 m³ Gording Kayu kls. III


6.7000 Oh Pekerja 96,800.00
20.1000 Oh Tukang Kayu 121,000.00
2.0100 Oh Kepala Tukang 145,200.00
0.3350 Oh Mandor 133,100.00
1.1000 M³ Balok Kayu kls. III 2,880,000.00 3,168,000.00
15.0000 Kg Besi Strip 10,800.00 162,000.00
3.0000 Kg Paku Biasa 2"-5" 16,200.00 48,600.00
JUMLAH 3,378,600.00

K.14 1 m² Rangka Atap Genteng Keramik Kayu kls. II


0.1000 Oh Pekerja 96,800.00
0.1000 Oh Tukang Kayu 121,000.00
0.0100 Oh Kepala Tukang 145,200.00
0.0050 Oh Mandor 133,100.00
0.0140 M³ Balok Kayu kls. II 3,300,000.00 46,200.00
0.0360 M³ Kayu Reng 2 x 3cm 2,880,000.00 103,680.00
0.2500 Kg Paku Biasa 2"-5" 16,200.00 4,050.00
JUMLAH 153,930.00

K.15 1 m² Rangka Atap Genteng Beton Kayu kls. II


0.1000 Oh Pekerja 96,800.00
0.1000 Oh Tukang Kayu 121,000.00
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

0.0100 Oh Kepala Tukang 145,200.00


0.0050 Oh Mandor 133,100.00
0.0140 M³ Balok Kayu kls. II 3,300,000.00 46,200.00
0.0570 M³ Kayu Reng 3 x 4cm 2,880,000.00 164,160.00
0.2500 Kg Paku Biasa 2"-5" 16,200.00 4,050.00
JUMLAH 214,410.00

K.16 1 m² Rangka Atap Sirap Kayu kls. II


0.1200 Oh Pekerja 96,800.00
0.1200 Oh Tukang Kayu 121,000.00
0.0120 Oh Kepala Tukang 145,200.00
0.0060 Oh Mandor 133,100.00
0.0140 M³ Balok Kayu kls. II 3,300,000.00 46,200.00
0.0570 M³ Paku Biasa 2"-5" 16,200.00 923.40
JUMLAH 47,123.40

K.17 1 m² Rangka Langit-Langit / Plafond = 50 x 100cm Kayu kls. II


0.1500 Oh Pekerja 96,800.00
0.3000 Oh Tukang Kayu 121,000.00
0.0300 Oh Kepala Tukang 145,200.00
0.0750 Oh Mandor 133,100.00
0.0154 M³ Balok Kayu kls. II 3,300,000.00 50,820.00
0.2000 Kg Paku Biasa 2"-5" 16,200.00 3,240.00
JUMLAH 54,060.00

K.17.a 1 m² Rangka Langit-Langit / Plafond = 50 x 100cm Kayu kls. III


0.1500 Oh Pekerja 96,800.00
0.3000 Oh Tukang Kayu 121,000.00
0.0300 Oh Kepala Tukang 145,200.00
0.0750 Oh Mandor 133,100.00
0.0154 M³ Balok Kayu kls. III 2,880,000.00 44,352.00
0.2000 Kg Paku Biasa 2"-5" 16,200.00 3,240.00
JUMLAH 47,592.00

K.18 1 m² Rangka Langit-Langit / Plafond = 60 x 60cm Kayu kls. II


0.2000 Oh Pekerja 96,800.00
0.3000 Oh Tukang Kayu 121,000.00
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

0.0300 Oh Kepala Tukang 145,200.00


0.0100 Oh Mandor 133,100.00
0.0163 M³ Balok Kayu kls. II 3,300,000.00 53,790.00
0.2500 Kg Paku Biasa 2"-5" 16,200.00 4,050.00
JUMLAH 57,840.00

K.18.a 1 m² Rangka Langit-Langit / Plafond 60 x 60cm Kayu kls. III


0.2000 Oh Pekerja 96,800.00
0.3000 Oh Tukang Kayu 121,000.00
0.0300 Oh Kepala Tukang 145,200.00
0.0100 Oh Mandor 133,100.00
0.0163 M³ Balok Kayu kls. III 2,880,000.00 46,944.00
0.2500 Kg Paku Biasa 2"-5" 16,200.00 4,050.00
JUMLAH 50,994.00

K.19 1 m' Lisplank 3 x 20cm Kayu kls. I


0.1000 Oh Pekerja 96,800.00
0.2000 Oh Tukang Kayu 121,000.00
0.0200 Oh Kepala Tukang 145,200.00
0.0050 Oh Mandor 133,100.00
0.0108 M³ Papan Kayu kls. I 3,900,000.00 42,120.00
0.1000 Kg Paku Biasa 2"-5" 16,200.00 1,620.00
JUMLAH 43,740.00

K.19.a 1 m' Lisplank 3 x 20cm Kayu kls. II


0.1000 Oh Pekerja 96,800.00
0.2000 Oh Tukang Kayu 121,000.00
0.0200 Oh Kepala Tukang 145,200.00
0.0050 Oh Mandor 133,100.00
0.0108 M³ Papan Kayu kls. II 3,480,000.00 37,584.00
0.1000 Kg Paku Biasa 2"-5" 16,200.00 1,620.00
JUMLAH 39,204.00

K.20 1 m' Lisplank 3 x 30cm Kayu kls. I


0.1000 Oh Pekerja 96,800.00
0.2000 Oh Tukang Kayu 121,000.00
0.0200 Oh Kepala Tukang 145,200.00
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

0.0050 Oh Mandor 133,100.00


0.0108 M³ Papan Kayu kls. I 3,900,000.00 42,120.00
0.0500 Kg Paku Biasa 2"-5" 16,200.00 810.00
JUMLAH 42,930.00

K.20.a 1 m' Lisplank 3 x 30cm Kayu kls. II


0.1000 Oh Pekerja 96,800.00
0.2000 Oh Tukang Kayu 121,000.00
0.0200 Oh Kepala Tukang 145,200.00
0.0050 Oh Mandor 133,100.00
0.0108 M³ Papan Kayu kls. II 3,480,000.00 37,584.00
0.1000 Kg Paku Biasa 2"-5" 16,200.00 1,620.00
JUMLAH 39,204.00

K.21 1 m² Rangka Dinding Pemisah 60 x 120cm Kayu kls. II


0.1500 Oh Pekerja 96,800.00
0.4500 Oh Tukang Kayu 121,000.00
0.0450 Oh Kepala Tukang 145,200.00
0.0080 Oh Mandor 133,100.00
0.0280 M³ Balok Kayu kls. II 3,300,000.00 92,400.00
0.1500 Kg Paku Biasa 2"-5" 16,200.00 2,430.00
JUMLAH 94,830.00

K.21.a 1 m² Rangka Dinding Pemisah 60 x 120cm Kayu kls. III


0.1500 Oh Pekerja 96,800.00
0.4500 Oh Tukang Kayu 121,000.00
0.0450 Oh Kepala Tukang 145,200.00
0.0080 Oh Mandor 133,100.00
0.0280 M³ Balok Kayu kls. III 2,880,000.00 80,640.00
0.1500 Kg Paku Biasa 2"-5" 16,200.00 2,430.00
JUMLAH 83,070.00

K.22 1 m² Dinding Pemisah dari Teakwood Rangkap Kayu kls. II


0.1500 Oh Pekerja 96,800.00
0.4500 Oh Tukang Kayu 121,000.00
0.0450 Oh Kepala Tukang 145,200.00
0.0080 Oh Mandor 133,100.00
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

0.0280 M³ Kayu Balok kls. II 3,300,000.00 92,400.00


0.1500 Kg Paku Biasa 2"-5" 16,200.00 2,430.00
0.8600 Lbr Teakwood 120 x 240cm tebal = 4mm 118,800.00 102,168.00
0.5600 Kg Lem Kayu 15,120.00 8,467.20
JUMLAH 205,465.20

K.22,a 1 m² Dinding Pemisah dari Teakwood Rangkap Kayu kls. III


0.1500 Oh Pekerja 96,800.00
0.4500 Oh Tukang Kayu 121,000.00
0.0450 Oh Kepala Tukang 145,200.00
0.0080 Oh Mandor 133,100.00
0.0280 M³ Kayu Balok kls. III 2,880,000.00 80,640.00
0.1500 Kg Paku Biasa 2"-5" 16,200.00 2,430.00
0.8600 Lbr Teakwood 120 x 240cm tebal = 4mm 118,800.00 102,168.00
0.5600 Kg Lem Kayu 15,120.00 8,467.20
JUMLAH 193,705.20

K.23 1 m² Dinding Pemisah dari Playwood Rangkap Kayu kls. II


0.2000 Oh Pekerja 96,800.00
0.6000 Oh Tukang Kayu 121,000.00
0.0600 Oh Kepala Tukang 145,200.00
0.0100 Oh Mandor 133,100.00
0.0280 M³ Kayu Balok kls. II 3,300,000.00 92,400.00
0.1500 Kg Paku Biasa 2"-5" 16,200.00 2,430.00
0.8600 Lbr Playwood 120 x 240cm tebal = 4mm 95,700.00 82,302.00
0.5600 Kg Lem Kayu 15,120.00 8,467.20
JUMLAH 185,599.20

K.23.a 1 m² Dinding Pemisah dari Playwood Rangkap Kayu kls. III


0.2000 Oh Pekerja 96,800.00
0.6000 Oh Tukang Kayu 121,000.00
0.0600 Oh Kepala Tukang 145,200.00
0.0100 Oh Mandor 133,100.00
0.0280 M³ Kayu Balok kls. III 2,880,000.00 80,640.00
0.1500 Kg Paku Biasa 2"-5" 16,200.00 2,430.00
0.8600 Lbr Playwood 120 x 240cm tebal = 4mm 95,700.00 82,302.00
0.5600 Kg Lem Kayu 15,120.00 8,467.20
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

JUMLAH 173,839.20

K.24 1 m² Dinding Lambrisering dari Papan Kayu kls. I


0.6000 Oh Pekerja 96,800.00
1.8000 Oh Tukang Kayu 121,000.00
0.1800 Oh Kepala Tukang 145,200.00
0.0300 Oh Mandor 133,100.00
0.0070 M³ Papan Kayu kls. I 3,900,000.00 27,300.00
0.1000 Kg Paku Biasa 2"-5" 16,200.00 1,620.00
0.1500 lbr Paku Sekrup 54,000.00 8,100.00
JUMLAH 37,020.00

K.25 1 m² Dinding Lambrisering dari Plywood 120 x 240cm


0.0250 Oh Pekerja 96,800.00
0.0750 Oh Tukang Kayu 121,000.00
0.0080 Oh Kepala Tukang 145,200.00
0.0010 Oh Mandor 133,100.00
0.4000 Lbr Plywood 120 x 240cm tebal = 4 mm 95,700.00 38,280.00
0.0500 Kg Paku Biasa 2"-5" 16,200.00 810.00
JUMLAH 39,090.00
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

677,600.00
2,541,000.00
304,920.00
46,585.00

3,570,105.00 7,895,475.00

580,800.00
2,178,000.00
261,360.00
39,930.00

3,060,090.00 7,055,460.00

580,800.00
2,178,000.00
261,360.00
39,930.00
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

3,060,090.00 6,551,460.00

96,800.00
363,000.00
43,560.00
6,655.00

510,015.00 656,775.00

96,800.00
363,000.00
43,560.00
6,655.00

510,015.00 609,975.00

77,440.00
290,400.00
34,848.00
5,324.00

408,012.00 506,148.00

77,440.00
290,400.00
34,848.00
5,324.00

408,012.00 496,068.00
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

77,440.00
290,400.00
34,848.00
5,324.00

408,012.00 467,988.00

96,800.00
363,000.00
43,560.00
6,655.00

510,015.00 767,175.00

96,800.00
363,000.00
43,560.00
6,655.00

510,015.00 740,295.00

67,760.00
254,100.00
30,492.00
4,658.50
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

357,010.50 522,283.66

64,856.00
242,000.00
29,040.00
44,588.50

380,484.50 617,949.50

64,856.00
242,000.00
29,040.00
44,588.50

380,484.50 592,749.50

77,440.00
290,400.00
34,848.00
5,324.00

63,654.26
408,012.00 586,125.16

77,440.00
290,400.00
34,848.00
5,324.00
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

408,012.00 575,373.16

77,440.00
290,400.00
34,848.00
5,324.00

408,012.00 609,741.00

82,280.00
308,550.00
37,026.00
5,723.30

433,579.30 677,368.30

387,200.00
1,452,000.00
174,240.00
26,620.00

2,040,060.00 6,582,780.00
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

387,200.00
1,452,000.00
174,240.00
26,620.00

2,040,060.00 5,922,780.00

387,200.00
1,452,000.00
174,240.00
26,620.00

2,040,060.00 5,460,780.00

648,560.00
2,432,100.00
291,852.00
44,588.50

3,417,100.50 8,349,820.50

648,560.00
2,432,100.00
291,852.00
44,588.50
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

3,417,100.50 7,629,820.50

648,560.00
2,432,100.00
291,852.00
44,588.50

3,417,100.50 7,257,700.50

648,560.00
2,432,100.00
291,852.00
44,588.50

3,417,100.50 6,795,700.50

9,680.00
12,100.00
1,452.00
665.50

23,897.50 177,827.50

9,680.00
12,100.00
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

1,452.00
665.50

23,897.50 238,307.50

11,616.00
14,520.00
1,742.40
798.60

28,677.00 75,800.40

14,520.00
36,300.00
4,356.00
9,982.50

65,158.50 119,218.50

14,520.00
36,300.00
4,356.00
9,982.50

65,158.50 112,750.50

19,360.00
36,300.00
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

4,356.00
1,331.00

61,347.00 119,187.00

19,360.00
36,300.00
4,356.00
1,331.00

61,347.00 112,341.00

9,680.00
24,200.00
2,904.00
665.50

37,449.50 81,189.50

9,680.00
24,200.00
2,904.00
665.50

37,449.50 76,653.50

9,680.00
24,200.00
2,904.00
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

665.50

37,449.50 80,379.50

9,680.00
24,200.00
2,904.00
665.50

37,449.50 76,653.50

14,520.00
54,450.00
6,534.00
1,064.80

76,568.80 171,398.80

14,520.00
54,450.00
6,534.00
1,064.80

76,568.80 159,638.80

14,520.00
54,450.00
6,534.00
1,064.80
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

76,568.80 282,034.00

14,520.00
54,450.00
6,534.00
1,064.80

76,568.80 270,274.00

19,360.00
72,600.00
8,712.00
1,331.00

102,003.00 287,602.20

19,360.00
72,600.00
8,712.00
1,331.00
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

102,003.00 275,842.20

58,080.00
217,800.00
26,136.00
3,993.00

306,009.00 343,029.00

2,420.00
9,075.00
1,161.60
133.10

12,789.70 51,879.70
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

L PEKERJAAN KUNCI & KACA

L.1 1 bh Kunci Tanam Antik


0.0600 Oh Pekerja 96,800.00
0.6000 Oh Tukang Kayu 121,000.00
0.0600 Oh Kepala Tukang 145,200.00
0.0030 Oh Mandor 133,100.00
1.0000 Bh Kunci Tanam Antik 450,600.00 450,600.00
JUMLAH 450,600.00

L.2 1 bh Kunci Tanam Biasa


0.0100 Oh Pekerja 96,800.00
0.5000 Oh Tukang Kayu 121,000.00
0.0500 Oh Kepala Tukang 145,200.00
0.0050 Oh Mandor 133,100.00
1.0000 Bh Kunci Tanam Biasa 102,000.00 102,000.00
JUMLAH 102,000.00

L.3 1 bh Kunci Kamar Mandi


0.0050 Oh Pekerja 96,800.00
0.5000 Oh Tukang Kayu 121,000.00
0.0500 Oh Kepala Tukang 145,200.00
0.0030 Oh Mandor 133,100.00
1.0000 Bh Kunci Kamar Mandi 92,400.00 92,400.00
JUMLAH 92,400.00

L.4 1 bh Kunci Silinder


0.0050 Oh Pekerja 96,800.00
0.5000 Oh Tukang Kayu 121,000.00
0.0500 Oh Kepala Tukang 145,200.00
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

0.0030 Oh Mandor 133,100.00


1.0000 Bh Kunci Silinder 84,000.00 84,000.00
JUMLAH 84,000.00

L.5 1 bh Engsel Pintu


0.0150 Oh Pekerja 96,800.00
0.1500 Oh Tukang Kayu 121,000.00
0.0150 Oh Kepala Tukang 145,200.00
0.0008 Oh Mandor 133,100.00
1.0000 Bh Engsel Pintu 24,085.71 24,085.71
JUMLAH 24,085.71

L.6 1 bh Engsel Jendela


0.0100 Oh Pekerja 96,800.00
0.1000 Oh Tukang Kayu 121,000.00
0.0100 Oh Kepala Tukang 145,200.00
0.0005 Oh Mandor 133,100.00
1.0000 Bh Engsel Jendela 17,742.86 17,742.86
JUMLAH 17,742.86

L.7 1 bh Kait Angin


0.0150 Oh Pekerja 96,800.00
0.1500 Oh Tukang Kayu 121,000.00
0.0150 Oh Kepala Tukang 145,200.00
0.0080 Oh Mandor 133,100.00
1.0000 Bh Kait Angin 9,300.00 9,300.00
JUMLAH 9,300.00

L.8 1 bh Door Closer


0.0500 Oh Pekerja 96,800.00
0.5000 Oh Tukang Kayu 121,000.00
0.0500 Oh Kepala Tukang 145,200.00
0.0030 Oh Mandor 133,100.00
1.0000 Bh Door Closer 141,000.00 141,000.00
JUMLAH 141,000.00

L.9 1 bh Kunci Slot


KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

0.0200 Oh Pekerja 96,800.00


0.2000 Oh Tukang Kayu 121,000.00
0.0200 Oh Kepala Tukang 145,200.00
0.0010 Oh Mandor 133,100.00
1.0000 Bh Kunci Slot 12,000.00 12,000.00
JUMLAH 12,000.00

L.10 1 bh Door Holder


0.0500 Oh Pekerja 96,800.00
0.5000 Oh Tukang Kayu 121,000.00
0.0500 Oh Kepala Tukang 145,200.00
0.0030 Oh Mandor 133,100.00
1.0000 Bh Door Holder 141,000.00 141,000.00
JUMLAH 141,000.00

L.11 1 bh Door Stop


0.0100 Oh Pekerja 96,800.00
0.1000 Oh Tukang Kayu 121,000.00
0.0100 Oh Kepala Tukang 145,200.00
0.0050 Oh Mandor 133,100.00
1.0000 Bh Door Stop 18,000.00 18,000.00
JUMLAH 18,000.00

L.12 1 bh Rel Pintu Dorong


0.0600 Oh Pekerja 96,800.00
0.6000 Oh Tukang Kayu 121,000.00
0.0600 Oh Kepala Tukang 145,200.00
0.0030 Oh Mandor 133,100.00
1.0000 Set Rel Pintu Dorong 294,000.00 294,000.00
JUMLAH 294,000.00

L.13 1 bh Kunci Lemari


0.0250 Oh Pekerja 96,800.00
0.2500 Oh Tukang Kayu 121,000.00
0.0250 Oh Kepala Tukang 145,200.00
0.0013 Oh Mandor 133,100.00
1.0000 Set Kunci Lemari 31,800.00 31,800.00
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

JUMLAH 31,800.00

L.14 1 m² Kaca Bening tebal = 3mm


0.0150 Oh Pekerja 96,800.00
0.1500 Oh Tukang Kayu 121,000.00
0.0150 Oh Kepala Tukang 145,200.00
0.0008 Oh Mandor 133,100.00
1.1000 M² Kaca Bening tebal = 3mm 114,000.00 125,400.00
0.0500 Kg Sealant 30,000.00 1,500.00
JUMLAH 126,900.00

L.15 1 m² Kaca Bening tebal = 5mm


0.0150 Oh Pekerja 96,800.00
0.1500 Oh Tukang Kayu 121,000.00
0.0150 Oh Kepala Tukang 145,200.00
0.0008 Oh Mandor 133,100.00
1.1000 M² Kaca Bening tebal = 5mm 159,000.00 174,900.00
0.0500 Kg Sealant 30,000.00 1,500.00
JUMLAH 176,400.00

L.15.a 1 m² Kaca Buram tebal = 5mm


0.0150 Oh Pekerja 96,800.00
0.1500 Oh Tukang Kayu 121,000.00
0.0150 Oh Kepala Tukang 145,200.00
0.0008 Oh Mandor 133,100.00
1.1000 M² Kaca Buram tebal = 5mm 141,600.00 155,760.00
0.0500 Kg Sealant 30,000.00 1,500.00
JUMLAH 157,260.00

L.16 1 m² Kaca Bening tebal = 8mm


0.0170 Oh Pekerja 96,800.00
0.1700 Oh Tukang Kayu 121,000.00
0.0170 Oh Kepala Tukang 145,200.00
0.0009 Oh Mandor 133,100.00
1.1000 M² Kaca Bening tebal = 8mm 168,000.00 184,800.00
0.0700 Kg Sealant 30,000.00 2,100.00
JUMLAH 186,900.00
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

L.17 1 m² Kaca Buram tebal = 12mm


0.0250 Oh Pekerja 96,800.00
0.2500 Oh Tukang Kayu 121,000.00
0.0250 Oh Kepala Tukang 145,200.00
0.0013 Oh Mandor 133,100.00
1.1000 M² Kaca Buram tebal = 12mm 307,200.00 337,920.00
0.0700 Kg Sealant 30,000.00 2,100.00
JUMLAH 340,020.00

L.18 1 m² Kaca Cermin tebal = 5mm


0.0150 Oh Pekerja 96,800.00
0.1500 Oh Tukang Kayu 121,000.00
0.0150 Oh Kepala Tukang 145,200.00
0.0080 Oh Mandor 133,100.00
1.1000 M² Kaca Cermin tebal = 5mm 150,000.00 165,000.00
JUMLAH 165,000.00

L.19 1 m² Kaca Cermin tebal = 8mm


0.0170 Oh Pekerja 96,800.00
0.1700 Oh Tukang Kayu 121,000.00
0.0170 Oh Kepala Tukang 145,200.00
0.0090 Oh Mandor 133,100.00
1.1000 M² Kaca Cermin tebal = 8mm 168,000.00 184,800.00
JUMLAH 184,800.00

L.20 1 m² Kaca Wireglassed tebal = 5mm


0.0150 Oh Pekerja 96,800.00
0.1500 Oh Tukang Kayu 121,000.00
0.0150 Oh Kepala Tukang 145,200.00
0.0080 Oh Mandor 133,100.00
1.1000 M² Kaca Wireglassed tebal = 5mm 682,800.00 751,080.00
JUMLAH 751,080.00

L.21 1 m² Kaca Patri tebal = 5mm


0.0750 Oh Pekerja 96,800.00
0.1500 Oh Tukang Kayu 121,000.00
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

0.0150 Oh Kepala Tukang 145,200.00


0.0040 Oh Mandor 133,100.00
1.1000 M² Kaca Patri tebal = 5mm 682,800.00 751,080.00
0.0500 Kg Sealant 30,000.00 1,500.00
JUMLAH 752,580.00
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

5,808.00
72,600.00
8,712.00
399.30

87,519.30 538,119.30

968.00
60,500.00
7,260.00
665.50

69,393.50 171,393.50

484.00
60,500.00
7,260.00
399.30

68,643.30 161,043.30

484.00
60,500.00
7,260.00
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

399.30

68,643.30 152,643.30

1,452.00
18,150.00
2,178.00
106.48

21,886.48 45,972.19

968.00
12,100.00
1,452.00
66.55

14,586.55 32,329.41

1,452.00
18,150.00
2,178.00
1,064.80

22,844.80 32,144.80

4,840.00
60,500.00
7,260.00
399.30

72,999.30 213,999.30
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

1,936.00
24,200.00
2,904.00
133.10

29,173.10 41,173.10

4,840.00
60,500.00
7,260.00
399.30

72,999.30 213,999.30

968.00
12,100.00
1,452.00
665.50

15,185.50 33,185.50

5,808.00
72,600.00
8,712.00
399.30

87,519.30 381,519.30

2,420.00
30,250.00
3,630.00
173.03
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

36,473.03 68,273.03

1,452.00
18,150.00
2,178.00
106.48

21,886.48 148,786.48

1,452.00
18,150.00
2,178.00
106.48

21,886.48 198,286.48

1,452.00
18,150.00
2,178.00
106.48

21,886.48 179,146.48

1,645.60
20,570.00
2,468.40
119.79

24,803.79 211,703.79
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

2,420.00
30,250.00
3,630.00
173.03

36,473.03 376,493.03

1,452.00
18,150.00
2,178.00
1,064.80

22,844.80 187,844.80

1,645.60
20,570.00
2,468.40
1,197.90

25,881.90 210,681.90

1,452.00
18,150.00
2,178.00
1,064.80

22,844.80 773,924.80

7,260.00
18,150.00
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

2,178.00
532.40

28,120.40 780,700.40
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

M PEKERJAAN PENGECATAN

M.1 1 m² Pengikisan / Pengerokan Permukaan Cat Lama


0.1500 Oh Pekerja 96,800.00
0.0030 Oh Mandor 133,100.00
0.0500 Kg Soda Api 7,680.00 384.00
JUMLAH 384.00

M.2 1 m² Pencucian Bidang Permukaan Tembok Pernah Dicat


0.1500 Oh Pekerja 96,800.00
0.0030 Oh Mandor 133,100.00
0.0500 Kg Sabun 24,000.00 1,200.00
JUMLAH 1,200.00

M.3 1 m² Pengecatan Kayu Baru = 1 lapis plamur, 1 lapis cat dasar, 2 lapis cat penutup
0.0700 Oh Pekerja 96,800.00
0.0090 Oh Tukang Cat 121,000.00
0.0060 Oh Kepala Tukang 145,200.00
0.0030 Oh Mandor 133,100.00
0.2000 Kg Cat Menie 59,400.00 11,880.00
0.1500 Kg Plamur 11,700.00 1,755.00
0.1700 Kg Cat Dasar (Besi) 63,600.00 10,812.00
0.2600 Kg Cat Penutup (Besi) 63,600.00 16,536.00
0.0100 Bh Kuas 36,300.00 363.00
0.0300 Kg Pengencer / Thinner 22,200.00 666.00
0.2000 Lbr Ampelas 4,500.00 900.00
JUMLAH 42,912.00

M.4 1 m² Pengecatan Kayu Baru = 1 lapis plamur, 1 lapis cat dasar, 3 lapis cat penutup
0.0700 Oh Pekerja 96,800.00
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

0.1050 Oh Tukang Cat 121,000.00


0.0040 Oh Kepala Tukang 145,200.00
0.0030 Oh Mandor 133,100.00
0.2000 Kg Cat Menie 59,400.00 11,880.00
0.1500 Kg Plamur 11,700.00 1,755.00
0.1700 Kg Cat Dasar (Besi) 63,600.00 10,812.00
0.3500 Kg Cat Penutup (Besi) 63,600.00 22,260.00
0.0100 Bh Kuas 36,300.00 363.00
0.0300 Kg Pengencer / Thinner 22,200.00 666.00
0.2000 Lbr Ampelas 4,500.00 900.00
JUMLAH 48,636.00

M.5 1 m² Pengecatan Kayu Dengan Teak Oil


0.0400 Oh Pekerja 96,800.00
0.0630 Oh Tukang Cat 121,000.00
0.0630 Oh Kepala Tukang 145,200.00
0.0030 Oh Mandor 133,100.00
0.3600 Ltr Teak Oil 288.00 103.68
JUMLAH 103.68

M.6 1 m² Pengecatan Kayu Dengan Politur


0.0400 Oh Pekerja 96,800.00
0.0600 Oh Tukang Cat 121,000.00
0.0160 Oh Kepala Tukang 145,200.00
0.0030 Oh Mandor 133,100.00
0.1500 Ltr Politur 37,800.00 5,670.00
0.3720 Ltr Politur jadi 37,800.00 14,061.60
2.0000 Lbr Ampelas 4,500.00 9,000.00
JUMLAH 28,731.60

M.7 1 m² Pengecatan Kayu Dengan Cat Residu / Ter


0.1000 Oh Pekerja 96,800.00
0.0060 Oh Mandor 133,100.00
0.3500 Ltr Residu / Ter 15,840.00 5,544.00
JUMLAH 5,544.00

M.8 1 m² Pengecatan Kayu Dengan Vernis


KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

0.1600 Oh Pekerja 96,800.00


0.1600 Oh Tukang Cat 121,000.00
0.0160 Oh Kepala Tukang 145,200.00
0.0030 Oh Mandor 133,100.00
0.1500 Ltr Vernis 51,000.00 7,650.00
0.0500 Kg Dempul 39,000.00 1,950.00
0.1000 Lbr Ampelas 4,500.00 450.00
JUMLAH 10,050.00

M.9 1 m² Pengecatan Tembok Baru = 1 lapis plamur , 1 lapis cat dasar , 2 lapis cat penutup
0.0200 Oh Pekerja 96,800.00
0.0630 Oh Tukang Cat 121,000.00
0.0063 Oh Kepala Tukang 145,200.00
0.0030 Oh Mandor 133,100.00
0.1000 Kg Plamur 11,700.00 1,170.00
0.1000 Kg Cat Dasar (Dinding) 89,928.00 8,992.80
0.2600 Kg Cat Penutup (Dinding) 89,928.00 23,381.28
JUMLAH 33,544.08

M.10 1 m² Pengecatan Tembok Lama = 1 lapis cat dasar , 2 lapis cat penutup
0.0280 Oh Pekerja 96,800.00
0.0420 Oh Tukang Cat 121,000.00
0.0042 Oh Kepala Tukang 145,200.00
0.0030 Oh Mandor 133,100.00
0.1200 Kg Cat Dasar (Dinding) 89,928.00 10,791.36
0.1800 Kg Cat Penutup (Dinding) 89,928.00 16,187.04
JUMLAH 26,978.40

M.11 1 m² Pengecatan Permukaan Baja Dengan Menie Besi


0.0200 Oh Pekerja 96,800.00
0.2000 Oh Tukang Cat 121,000.00
0.0200 Oh Kepala Tukang 145,200.00
0.0025 Oh Mandor 133,100.00
0.1000 Kg Menie Besi 59,400.00 5,940.00
0.0100 Bh Kuas 36,300.00 363.00
JUMLAH 6,303.00
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

M.11.a 1 m² Pengecatan Permukaan Baja Dengan Menie Besi + Perancah


0.2500 Oh Pekerja 96,800.00
0.2250 Oh Tukang Cat 121,000.00
0.0225 Oh Kepala Tukang 145,200.00
0.0075 Oh Mandor 133,100.00
0.1000 Kg Menie Besi 59,400.00 5,940.00
0.0100 Ltr Pengencer / Thinner 22,200.00 222.00
0.0100 Bh Kuas 36,300.00 363.00
0.0020 M² Perancah Kayu 1,980,000.00 3,960.00
JUMLAH 10,485.00

M.12 1 m² Pengecatan Permukaan Baja Galvanis Secara Manual = 3 lapis


0.4000 Oh Pekerja 96,800.00
0.8000 Oh Tukang Cat 121,000.00
0.0800 Oh Kepala Tukang 145,200.00
0.0200 Oh Mandor 133,100.00
0.1100 Kg Cat Dasar (Besi) 63,600.00 6,996.00
0.1700 Bh Cat antara (Besi) 63,600.00 10,812.00
0.0800 Kg Cat Penutup (Besi) 63,600.00 5,088.00
0.0100 Bh Kuas 36,300.00 363.00
0.0100 Ltr Pengencer / Thinner 22,200.00 222.00
JUMLAH 23,481.00

M.13 1 m² Pengecatan Permukaan Baja Galvanis Secara Manual = 4 lapis


0.2500 Oh Pekerja 96,800.00
0.2500 Oh Tukang Cat 121,000.00
0.0250 Oh Kepala Tukang 145,200.00
0.0013 Oh Mandor 133,100.00
0.1000 Kg Menie - A 59,400.00 5,940.00
0.1000 Kg Menie - B 59,400.00 5,940.00
0.0800 Kg Cat Besi 63,600.00 5,088.00
0.0100 Bh Kuas 36,300.00 363.00
0.0100 Ltr Pengencer / Thinner 22,200.00 222.00
JUMLAH 17,553.00

M.14 1 m² Pengecatan Genteng dengan Cat Spesial


0.1000 Oh Pekerja 96,800.00
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

0.1000 Oh Tukang Cat 121,000.00


0.0150 Oh Kepala Tukang 145,200.00
0.0050 Oh Mandor 133,100.00
0.3000 Kg Cat Genteng Special 40,200.00 12,060.00
0.0100 Bh Kuas 36,300.00 363.00
JUMLAH 12,423.00
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

14,520.00
399.30

14,919.30 15,303.30

14,520.00
399.30

14,919.30 16,119.30

6,776.00
1,089.00
871.20
399.30

9,135.50 52,047.50

6,776.00
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

12,705.00
580.80
399.30

20,461.10 69,097.10

3,872.00
7,623.00
9,147.60
399.30

21,041.90 21,145.58

3,872.00
7,260.00
2,323.20
399.30

13,854.50 42,586.10

9,680.00
798.60

10,478.60 16,022.60
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

15,488.00
19,360.00
2,323.20
399.30

37,570.50 47,620.50

1,936.00
7,623.00
914.76
399.30

10,873.06 44,417.14

75
2,710.40
5,082.00
609.84
399.30

8,801.54 35,779.94

1,936.00
24,200.00
2,904.00
332.75

29,372.75 35,675.75
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

24,200.00
27,225.00
3,267.00
998.25

55,690.25 66,175.25

38,720.00
96,800.00
11,616.00
2,662.00

149,798.00 173,279.00

24,200.00
30,250.00
3,630.00
173.03

58,253.03 75,806.03

9,680.00
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

12,100.00
2,178.00
665.50

24,623.50 37,046.50
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

N PEKERJAAN SANITASI

N.1 1 bh Closet Duduk / Monoblock


3.3000 Oh Pekerja 96,800.00
1.1000 Oh Tukang Batu 121,000.00
0.0100 Oh Kepala Tukang 145,200.00
0.1600 Oh Mandor 133,100.00
1.0000 Unit Closet Duduk / Monoblock 4,174,500.00 4,174,500.00
6% x bahan Ls Perlengkapan 4,174,500.00 250,470.00
JUMLAH 4,424,970.00

N.2 1 bh Closet Jongkok Porselin


1.0000 Oh Pekerja 96,800.00
1.5000 Oh Tukang Batu 121,000.00
0.1500 Oh Kepala Tukang 145,200.00
0.1600 Oh Mandor 133,100.00
1.0000 Unit Closet Jongkok Porselin 165,000.00 165,000.00
6.0000 Kg Semen Portland 1,668.00 10,008.00
0.0100 M³ Pasir Pasang 148,179.36 1,481.79
JUMLAH 176,489.79

N.3 1 bh Urinoir
1.0000 Oh Pekerja 96,800.00
1.0000 Oh Tukang Batu 121,000.00
0.1000 Oh Kepala Tukang 145,200.00
0.0500 Oh Mandor 133,100.00
1.0000 Unit Urinoir 1,140,000.00 1,140,000.00
6.0000 Kg Semen Portland 1,668.00 10,008.00
0.0100 M³ Pasir Pasang 148,179.36 1,481.79
30% x bahan Bh Perlengkapan 1,140,000.00 44,453.81
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

JUMLAH 1,195,943.60

N.4 1 bh Wastafel
1.2000 Oh Pekerja 96,800.00
1.4500 Oh Tukang Batu 121,000.00
0.1500 Oh Kepala Tukang 145,200.00
0.0600 Oh Mandor 133,100.00
1.2000 Unit Wastafel 990,000.00 1,188,000.00
6.0000 Kg Semen Portland 1,668.00 10,008.00
0.0100 M³ Pasir Pasang 148,179.36 1,481.79
12% x bahan Bh Perlengkapan 990,000.00 17,781.52
JUMLAH 1,217,271.32

N.5 1 bh Bathcuip Porselen


0.0750 Oh Pekerja 96,800.00
0.7500 Oh Tukang Batu 121,000.00
0.0750 Oh Kepala Tukang 145,200.00
0.0030 Oh Mandor 133,100.00
1.0000 Unit Bathcuip Porselen 3,960,000.00 3,960,000.00
20% x bahan Kg Perlengkapan 3,960,000.00 792,000.00
JUMLAH 4,752,000.00

N.6 1 bh Bak Fibreglass = 1 m³


3.0000 Oh Pekerja 96,800.00
4.5000 Oh Tukang Batu 121,000.00
0.0500 Oh Kepala Tukang 145,200.00
0.9000 Oh Mandor 133,100.00
1.0000 Unit Bak Fibreglass = 1 m³ 518,400.00 518,400.00
12% x bahan Kg Perlengkapan 518,400.00 62,208.00
JUMLAH 580,608.00

N.7 1 bh Bak Mandi Bt. Bata = 0,30 m³


6.0000 Oh Pekerja 96,800.00
3.0000 Oh Tukang Batu 121,000.00
0.3000 Oh Kepala Tukang 145,200.00
0.0300 Oh Mandor 133,100.00
150.0000 M³ Bt. Bata 1,530.00 229,500.00
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

120.0000 Kg Semen Portland 1,668.00 200,160.00


0.3000 M³ Pasir Pasang 148,179.36 44,453.81
360.0000 Bh Porselen 11 x 11cm 1,440.00 518,400.00
6.0000 Kg Semen Warna 14,800.00 88,800.00
JUMLAH 1,081,313.81

N.8 1 bh Bak Mandi Fiber = 0,30 m³


0.3000 Oh Pekerja 96,800.00
0.4500 Oh Tukang Batu 121,000.00
0.0500 Oh Kepala Tukang 145,200.00
0.9000 Oh Mandor 133,100.00
1.0000 Unit Bak Fiber = 0,30 m³ 330,000.00 330,000.00
12% x bahan Ls Perlengkapan 330,000.00 39,600.00
JUMLAH 369,600.00

N.9 1 bh Bak Mandi Fiber = 1 m³


0.3000 Oh Pekerja 96,800.00
0.4500 Oh Tukang Batu 121,000.00
0.0450 Oh Kepala Tukang 145,200.00
0.0150 Oh Mandor 133,100.00
1.0000 Unit Bak Fiber = 1 m³ 518,400.00 518,400.00
12% x bahan Ls Perlengkapan 518,400.00 62,208.00
JUMLAH 580,608.00

N.10 1 bh Bak Cuci Piring


0.0500 Oh Pekerja 96,800.00
0.5000 Oh Tukang Batu 121,000.00
0.0500 Oh Kepala Tukang 145,200.00
0.0250 Oh Mandor 133,100.00
1.0000 Unit Bak Cuci Piring (Stainless steel) 252,000.00 252,000.00
1.0000 Bh Water Drain 24,000.00 24,000.00
20.0000 Kg Semen Portland 1,668.00 33,360.00
0.0500 M³ Pasir Pasang 148,179.36 7,408.97
JUMLAH 316,768.97

N.11 1 bh Floor Drain (PVC)


0.0100 Oh Pekerja 96,800.00
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

0.1000 Oh Tukang Batu 121,000.00


0.0100 Oh Kepala Tukang 145,200.00
0.0050 Oh Mandor 133,100.00
1.0000 Unit Floor Drain (PVC) 28,500.00 28,500.00
JUMLAH 28,500.00

N.11.a 1 bh Floor Drain (Besi)


0.0100 Oh Pekerja 96,800.00
0.1000 Oh Tukang Batu 121,000.00
0.0100 Oh Kepala Tukang 145,200.00
0.0050 Oh Mandor 133,100.00
1.0000 Unit Floor Drain (Besi) 52,800.00 52,800.00
JUMLAH 52,800.00

N.12 1 bh Kran Air dia. 1/2'' atau 3/4''


0.0100 Oh Pekerja 96,800.00
0.4000 Oh Tukang Batu 121,000.00
0.0400 Oh Kepala Tukang 145,200.00
0.0050 Oh Mandor 133,100.00
1.0000 Bh Kran Air dia. 1/2'' atau 3/4'' 29,700.00 29,700.00
0.0250 Ls Seal Tape 3,600.00 90.00
JUMLAH 29,790.00
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

319,440.00
133,100.00
1,452.00
21,296.00
3,795,000

3,795,000
475,288.00 4,900,258.00

96,800.00
181,500.00
21,780.00
21,296.00
165,000

1,668

148,179
321,376.00 497,865.79

96,800.00
121,000.00
14,520.00
6,655.00
1,140,000

1,668

148,179

1,140,000
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

238,975.00 1,434,918.60

116,160.00
175,450.00
21,780.00
7,986.00
990,000

1,668

148,179

990,000
321,376.00 1,538,647.32

7,260.00
90,750.00
10,890.00
399.30
3,300,000

3,300,000
109,299.30 4,861,299.30

290,400.00
544,500.00
7,260.00
119,790.00
528,000

528,000
961,950.00 1,542,558.00

580,800.00
363,000.00
43,560.00
3,993.00
1,530
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

1,668

148,179

1,440

14,800
991,353.00 2,072,666.81

29,040.00
54,450.00
7,260.00
119,790.00
330,000

330,000
210,540.00 580,140.00

29,040.00
54,450.00
6,534.00
1,996.50
528,000

528,000
92,020.50 672,628.50

4,840.00
60,500.00
7,260.00
3,327.50
252,000

24,000

1,668

148,179
75,927.50 392,696.47

968.00
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

12,100.00
1,452.00
665.50
28,500
15,185.50 43,685.50

968.00
12,100.00
1,452.00
665.50
48,000
15,185.50 67,985.50

968.00
48,400.00
5,808.00
665.50
29,700

4,500
55,841.50 85,631.50
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

O PEKERJAAN PIPA

O.1 1 m' Pipa Galvanis dia. 1/2''


0.0540 Oh Pekerja 96,800.00
0.0900 Oh Tukang Pipa 121,000.00
0.0090 Oh Kepala Tukang 145,200.00
0.0270 Oh Mandor 133,100.00
1.2000 M' Pipa Galvanis dia. 1/2'' 26,400.00 31,680.00
35% x bahan Ls Perlengkapan 26,400.00 9,240.00
JUMLAH 40,920.00

O.2 1 m' Pipa Galvanis dia. 3/4''


0.0540 Oh Pekerja 96,800.00
0.0900 Oh Tukang Pipa 121,000.00
0.0090 Oh Kepala Tukang 145,200.00
0.0270 Oh Mandor 133,100.00
1.2000 M' Pipa Galvanis dia. 3/4'' 31,800.00 38,160.00
35% x bahan Ls Perlengkapan 31,800.00 11,130.00
JUMLAH 49,290.00

O.3 1 m' Pipa Galvanis dia. 1''


0.0540 Oh Pekerja 96,800.00
0.0900 Oh Tukang Pipa 121,000.00
0.0090 Oh Kepala Tukang 145,200.00
0.0270 Oh Mandor 133,100.00
1.2000 M' Pipa Galvanis dia. 1'' 37,500.00 45,000.00
35% x bahan Ls Perlengkapan 37,500.00 13,125.00
JUMLAH 58,125.00

O.4 1 m' Pipa Galvanis dia. 1,5''


KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

0.1080 Oh Pekerja 96,800.00


0.1800 Oh Tukang Pipa 121,000.00
0.0180 Oh Kepala Tukang 145,200.00
0.0050 Oh Mandor 133,100.00
1.2000 M' Pipa Galvanis dia. 1,5'' 67,800.00 81,360.00
35% x bahan Ls Perlengkapan 67,800.00 23,730.00
JUMLAH 105,090.00

O.5 1 m' Pipa Galvanis dia. 3''


0.1350 Oh Pekerja 96,800.00
0.2250 Oh Tukang Pipa 121,000.00
0.0230 Oh Kepala Tukang 145,200.00
0.0070 Oh Mandor 133,100.00
1.2000 M' Pipa Galvanis dia. 3'' 96,000.00 115,200.00
35% x bahan Ls Perlengkapan 96,000.00 33,600.00
JUMLAH 148,800.00

O.6 1 m' Pipa Galvanis dia. 4''


0.1350 Oh Pekerja 96,800.00
0.2250 Oh Tukang Pipa 121,000.00
0.0230 Oh Kepala Tukang 145,200.00
0.0070 Oh Mandor 133,100.00
1.2000 M' Pipa Galvanis dia. 4'' 158,400.00 190,080.00
35% x bahan Ls Perlengkapan 158,400.00 55,440.00
JUMLAH 245,520.00

O.7 1 m' Pipa PVC Type AW dia. 1/2''


0.0360 Oh Pekerja 96,800.00
0.0600 Oh Tukang Pipa 121,000.00
0.0060 Oh Kepala Tukang 145,200.00
0.0020 Oh Mandor 133,100.00
1.2000 M' Pipa PVC Type AW dia. 1/2'' 5,800.00 6,960.00
35% x bahan Ls Perlengkapan 5,800.00 2,030.00
JUMLAH 8,990.00

O.8 1 m' Pipa PVC Type AW dia. 3/4''


0.0360 Oh Pekerja 96,800.00
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

0.0600 Oh Tukang Pipa 121,000.00


0.0060 Oh Kepala Tukang 145,200.00
0.0020 Oh Mandor 133,100.00
1.2000 M' Pipa PVC Type AW dia. 3/4'' 7,500.00 9,000.00
35% x bahan Ls Perlengkapan 7,500.00 2,625.00
JUMLAH 11,625.00

O.9 1 m' Pipa PVC Type AW dia. 1''


0.0360 Oh Pekerja 96,800.00
0.0600 Oh Tukang Pipa 121,000.00
0.0060 Oh Kepala Tukang 145,200.00
0.0020 Oh Mandor 133,100.00
1.2000 M' Pipa PVC Type AW dia. 1'' 10,475.00 12,570.00
35% x bahan Ls Perlengkapan 10,475.00 3,666.25
JUMLAH 16,236.25

O.10 1 m' Pipa PVC Type AW dia. 1,5''


0.0540 Oh Pekerja 96,800.00
0.0900 Oh Tukang Pipa 121,000.00
0.0090 Oh Kepala Tukang 145,200.00
0.0030 Oh Mandor 133,100.00
1.2000 M' Pipa PVC Type AW dia. 1,5'' 16,900.00 20,280.00
35% x bahan Ls Perlengkapan 16,900.00 5,915.00
JUMLAH 26,195.00

O.11 1 m' Pipa PVC Type AW dia. 2''


0.0540 Oh Pekerja 96,800.00
0.0900 Oh Tukang Pipa 121,000.00
0.0090 Oh Kepala Tukang 145,200.00
0.0030 Oh Mandor 133,100.00
1.2000 M' Pipa PVC Type AW dia. 2'' 22,250.00 26,700.00
35% x bahan Ls Perlengkapan 22,250.00 7,787.50
JUMLAH 34,487.50

O.12 1 m' Pipa PVC Type AW dia. 3''


0.0810 Oh Pekerja 96,800.00
0.1350 Oh Tukang Pipa 121,000.00
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

0.0135 Oh Kepala Tukang 145,200.00


0.0040 Oh Mandor 133,100.00
1.2000 M' Pipa PVC Type AW dia. 3'' 38,250.00 45,900.00
35% x bahan Ls Perlengkapan 38,250.00 13,387.50
JUMLAH 59,287.50

O.13 1 m' Pipa PVC Type AW dia. 4''


0.0810 Oh Pekerja 96,800.00
0.1350 Oh Tukang Pipa 121,000.00
0.0135 Oh Kepala Tukang 145,200.00
0.0040 Oh Mandor 133,100.00
1.2000 M' Pipa PVC Type AW dia. 4'' 60,300.00 72,360.00
35% x bahan Ls Perlengkapan 60,300.00 21,105.00
JUMLAH 93,465.00

O.14 1 m' Pipa HDPE dia. 63mm


0.0350 Oh Pekerja 96,800.00
0.0170 Oh Tukang Pipa 121,000.00
0.0030 Oh Mandor 133,100.00
1.0000 M' Pipa HDPE ø 63mm 50,160.00 50,160.00
0.0190 Hr Sewa Tripot / Tackel & Handle Crane 2T -
JUMLAH 50,160.00

O.15 1 m' Pipa HDPE dia. 110mm


0.0400 Oh Pekerja 96,800.00
0.0200 Oh Tukang Pipa 121,000.00
0.0040 Oh Mandor 133,100.00
1.0000 M' Pipa HDPE ø 110mm 150,600.00 150,600.00
0.0190 Hr Sewa Tripot / Tackel & Handle Crane 2T -
JUMLAH 150,600.00

O.16 1 m' Pipa HDPE dia. 125mm


0.0450 Oh Pekerja 96,800.00
0.0230 Oh Tukang Pipa 121,000.00
0.0050 Oh Mandor 133,100.00
1.0000 M' Pipa HDPE ø 125mm 195,000.00 195,000.00
0.0190 Hr Sewa Tripot / Tackel & Handle Crane 2T -
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

JUMLAH 195,000.00

O.17 1 m' Pipa HDPE dia. 140mm


0.0620 Oh Pekerja 96,800.00
0.0310 Oh Tukang Pipa 121,000.00
0.0060 Oh Mandor 133,100.00
1.0000 M' Pipa HDPE ø 140mm 243,000.00 243,000.00
0.0190 Hr Sewa Tripot / Tackel & Handle Crane 2T -
JUMLAH 243,000.00

O.18 1 m' Pipa HDPE dia. 200mm


0.1020 Oh Pekerja 96,800.00
0.0510 Oh Tukang Pipa 121,000.00
0.0100 Oh Mandor 133,100.00
1.0000 M' Pipa HDPE ø 200mm 496,800.00 496,800.00
0.0190 Hr Sewa Tripot / Tackel & Handle Crane 2T -
JUMLAH 496,800.00

O.19 1 m' Pipa HDPE dia. 250mm


0.1330 Oh Pekerja 96,800.00
0.0670 Oh Tukang Pipa 121,000.00
0.0130 Oh Mandor 133,100.00
1.0000 M' Pipa HDPE ø 250mm 774,600.00 774,600.00
0.0420 Hr Sewa Tripot / Tackel & Handle Crane 2T -
JUMLAH 774,600.00

O.20 1 m' Pipa HDPE dia. 280mm


0.1700 Oh Pekerja 96,800.00
0.0850 Oh Tukang Pipa 121,000.00
0.0170 Oh Mandor 133,100.00
1.0000 M' Pipa HDPE ø 280mm 969,600.00 969,600.00
0.0650 Hr Sewa Tripot / Tackel & Handle Crane 2T -
JUMLAH 969,600.00

O.21 1 m' Pipa HDPE dia. 400mm


0.2900 Oh Pekerja 96,800.00
0.1450 Oh Tukang Pipa 121,000.00
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

0.0290 Oh Mandor 133,100.00


1.0000 M' Pipa HDPE ø 400mm 1,978,200.00 1,978,200.00
0.1520 Hr Sewa Tripot / Tackel & Handle Crane 2T -
JUMLAH 1,978,200.00

O.22 1 m' Pipa HDPE dia. 450mm


0.3590 Oh Pekerja 96,800.00
0.1800 Oh Tukang Pipa 121,000.00
0.0360 Oh Mandor 133,100.00
1.0000 M' Pipa HDPE ø 450mm 2,505,600.00 2,505,600.00
0.2000 Hr Sewa Tripot / Tackel & Handle Crane 2T -
JUMLAH 2,505,600.00

O.23 1 m' Pipa HDPE dia. 500mm


0.4330 Oh Pekerja 96,800.00
0.2160 Oh Tukang Pipa 121,000.00
0.0430 Oh Mandor 133,100.00
1.0000 M' Pipa HDPE ø 500mm 3,090,960.00 3,090,960.00
0.2510 Hr Sewa Tripot / Tackel & Handle Crane 2T -
JUMLAH 3,090,960.00

O.24 1 m' Pipa HDPE dia. 560mm


0.5120 Oh Pekerja 96,800.00
0.2560 Oh Tukang Pipa 121,000.00
0.0510 Oh Mandor 133,100.00
1.0000 M' Pipa HDPE ø 560mm 3,871,800.00 3,871,800.00
0.3070 Hr Sewa Tripot / Tackel & Handle Crane 2T -
JUMLAH 3,871,800.00

O.25 1 m' Pipa HDPE dia. 800mm


0.8930 Oh Pekerja 96,800.00
0.4460 Oh Tukang Pipa 121,000.00
0.0890 Oh Mandor 133,100.00
1.0000 M' Pipa HDPE ø 800mm 6,270,000.00 6,270,000.00
0.5730 Hr Sewa Tripot / Tackel & Handle Crane 2T -
JUMLAH 6,270,000.00
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

O.26 1 m' Pipa HDPE dia. 900mm


1.3530 Oh Pekerja 96,800.00
0.6770 Oh Tukang Pipa 121,000.00
0.1350 Oh Mandor 133,100.00
1.0000 M' Pipa HDPE ø 900mm 7,897,440.00 7,897,440.00
0.8830 Hr Sewa Tripot / Tackel & Handle Crane 2T -
JUMLAH 7,897,440.00

O.27 1 m' Pipa HDPE dia. 1000mm


1.6590 Oh Pekerja 96,800.00
0.8300 Oh Tukang Pipa 121,000.00
0.1660 Oh Mandor 133,100.00
1.0000 M' Pipa HDPE ø 1000mm 9,802,920.00 9,802,920.00
1.0930 Hr Sewa Tripot / Tackel & Handle Crane 2T -
JUMLAH 9,802,920.00

O.28 1 m' Pipa HDPE dia. 1100mm


1.8180 Oh Pekerja 96,800.00
0.9090 Oh Tukang Pipa 121,000.00
0.1820 Oh Mandor 133,100.00
1.0000 M' Pipa HDPE ø 1100mm -
1.2050 Hr Sewa Tripot / Tackel & Handle Crane 2T -
JUMLAH -

O.29 1 m' Pipa HDPE dia. 1200mm


2.3700 Oh Pekerja 96,800.00
1.1850 Oh Tukang Pipa 121,000.00
0.2370 Oh Mandor 133,100.00
1.0000 M' Pipa HDPE ø 1200mm -
1.5840 Hr Sewa Tripot / Tackel & Handle Crane 2T -
JUMLAH -

O.30 1 m' Pipa GIP dia. 63mm


0.3450 Oh Pekerja 96,800.00
0.1720 Oh Tukang Pipa 121,000.00
0.0340 Oh Mandor 133,100.00
1.0000 M' Pipa GIP ø 63mm -
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

JUMLAH -

O.31 1 m' Pipa GIP dia. 100mm


0.4000 Oh Pekerja 96,800.00
0.2000 Oh Tukang Pipa 121,000.00
0.0400 Oh Mandor 133,100.00
1.0000 M' Pipa GIP ø 100mm -
JUMLAH -

O.32 1 m' Pipa GIP dia. 125mm


0.4480 Oh Pekerja 96,800.00
0.2240 Oh Tukang Pipa 121,000.00
0.0450 Oh Mandor 133,100.00
1.0000 M' Pipa GIP ø 125mm -
JUMLAH -

O.33 1 m' Pipa GIP dia. 150mm


0.5060 Oh Pekerja 96,800.00
0.2530 Oh Tukang Pipa 121,000.00
0.0510 Oh Mandor 133,100.00
1.0000 M' Pipa GIP ø 150mm -
JUMLAH -

O.34 1 m' Pipa GIP dia. 200mm


0.7960 Oh Pekerja 96,800.00
0.3980 Oh Tukang Pipa 121,000.00
0.0800 Oh Mandor 133,100.00
1.0000 M' Pipa GIP ø 200mm -
JUMLAH -

O.35 1 m' Pipa GIP dia. 250mm


0.9490 Oh Pekerja 96,800.00
0.4750 Oh Tukang Pipa 121,000.00
0.0950 Oh Mandor 133,100.00
1.0000 M' Pipa GIP ø 250mm -
JUMLAH -
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

O.36 1 m' Pipa GIP dia. 300mm


0.9580 Oh Pekerja 96,800.00
0.4790 Oh Tukang Pipa 121,000.00
0.0960 Oh Mandor 133,100.00
1.0000 M' Pipa GIP ø 300mm -
JUMLAH -

O.37 1 m' Pipa GIP dia. 400mm


1.2120 Oh Pekerja 96,800.00
0.6060 Oh Tukang Pipa 121,000.00
0.1210 Oh Mandor 133,100.00
1.0000 M' Pipa GIP ø 400mm -
JUMLAH -

O.38 1 m' Pipa GIP dia. 450mm


1.3530 Oh Pekerja 96,800.00
0.6760 Oh Tukang Pipa 121,000.00
0.1350 Oh Mandor 133,100.00
1.0000 M' Pipa GIP ø 450mm -
JUMLAH -

O.39 1 m' Pipa GIP dia. 500mm


1.4690 Oh Pekerja 96,800.00
0.7350 Oh Tukang Pipa 121,000.00
0.1470 Oh Mandor 133,100.00
1.0000 M' Pipa GIP ø 500mm -
JUMLAH -

O.40 1 m' Pipa GIP dia. 600mm


1.3270 Oh Pekerja 96,800.00
0.6640 Oh Tukang Pipa 121,000.00
0.1330 Oh Mandor 133,100.00
1.0000 M' Pipa GIP ø 600mm -
JUMLAH -

O.41 1 m' Pipa GIP dia. 800mm


2.3270 Oh Pekerja 96,800.00
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

1.1630 Oh Tukang Pipa 121,000.00


0.2330 Oh Mandor 133,100.00
1.0000 M' Pipa GIP ø 800mm -
JUMLAH -

O.42 1 m' Pipa GIP dia. 900mm


2.6230 Oh Pekerja 96,800.00
1.3120 Oh Tukang Pipa 121,000.00
0.2620 Oh Mandor 133,100.00
1.0000 M' Pipa GIP ø 900mm -
JUMLAH -

O.43 1 m' Pipa GIP dia. 1000mm


2.9110 Oh Pekerja 96,800.00
1.4560 Oh Tukang Pipa 121,000.00
0.2910 Oh Mandor 133,100.00
1.0000 M' Pipa GIP ø 1000mm -
JUMLAH -

O.44 1 m' Pipa GIP dia. 1100mm


3.2000 Oh Pekerja 96,800.00
1.6000 Oh Tukang Pipa 121,000.00
0.3200 Oh Mandor 133,100.00
1.0000 M' Pipa GIP ø 1100mm -
JUMLAH -

O.45 1 m' Pipa GIP dia. 1200mm


3.4880 Oh Pekerja 96,800.00
1.7440 Oh Tukang Pipa 121,000.00
0.3490 Oh Mandor 133,100.00
1.0000 M' Pipa GIP ø 1200mm -
JUMLAH -

O.46 1 m' Pipa DCI dia. 100mm


0.4890 Oh Pekerja 96,800.00
0.0980 Oh Tukang Pipa 121,000.00
0.0490 Oh Mandor 133,100.00
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

1.0000 M' Pipa DCI ø 100mm -


0.3800 Hr Sewa Tripot / Tackel & Handle Crane 2T -
JUMLAH -

O.47 1 m' Pipa DCI dia. 200mm


0.8550 Oh Pekerja 96,800.00
0.1710 Oh Tukang Pipa 121,000.00
0.0850 Oh Mandor 133,100.00
1.0000 M' Pipa DCI ø 200mm -
0.3800 Hr Sewa Tripot / Tackel & Handle Crane 2T -
JUMLAH -

O.48 1 m' Pipa DCI dia. 250mm


0.9510 Oh Pekerja 96,800.00
0.1900 Oh Tukang Pipa 121,000.00
0.0950 Oh Mandor 133,100.00
1.0000 M' Pipa DCI ø 250mm -
0.0500 Hr Sewa Tripot / Tackel & Handle Crane 2T -
JUMLAH -

O.49 1 m' Pipa DCI dia. 300mm


0.9730 Oh Pekerja 96,800.00
0.1950 Oh Tukang Pipa 121,000.00
0.0970 Oh Mandor 133,100.00
1.0000 M' Pipa DCI ø 300mm -
0.0710 Hr Sewa Tripot / Tackel & Handle Crane 2T -
JUMLAH -

O.50 1 m' Pipa DCI dia. 400mm


1.5450 Oh Pekerja 96,800.00
0.3090 Oh Tukang Pipa 121,000.00
0.0930 Oh Operator Alat Berat 196,200.00
0.1540 Oh Mandor 133,100.00
1.0000 M' Pipa DCI ø 400mm -
0.0230 Hr Sewa Excafator Type 225 kap 0,5 - 1,0m3 -
0.0310 Hr Sewa Tripot / Tackel & Handle Crane 2T -
JUMLAH -
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

O.51 1 m' Pipa DCI dia. 450mm


1.8130 Oh Pekerja 96,800.00
0.3630 Oh Tukang Pipa 121,000.00
0.1430 Oh Operator Alat Berat 196,200.00
0.1810 Oh Mandor 133,100.00
1.0000 M' Pipa DCI ø 450mm -
0.0290 Hr Sewa Excafator Type 225 kap 0,5 - 1,0m3 -
0.0390 Hr Sewa Tripot / Tackel & Handle Crane 2T -
JUMLAH -

O.52 1 m' Pipa DCI dia. 500mm


2.0470 Oh Pekerja 96,800.00
0.4090 Oh Tukang Pipa 121,000.00
0.1930 Oh Operator Alat Berat 196,200.00
0.2050 Oh Mandor 133,100.00
1.0000 M' Pipa DCI ø 500mm -
0.0340 Hr Sewa Excafator Type 225 kap 0,5 - 1,0m3 -
0.0450 Hr Sewa Tripot / Tackel & Handle Crane 2T -
JUMLAH -

O.53 1 m' Pipa DCI dia. 600mm


2.0110 Oh Pekerja 96,800.00
0.4020 Oh Tukang Pipa 121,000.00
0.2930 Oh Operator Alat Berat 196,200.00
0.2010 Oh Mandor 133,100.00
1.0000 M' Pipa DCI ø 600mm -
0.0580 Hr Sewa Excafator Type 225 kap 0,5 - 1,0m3 -
0.0770 Hr Sewa Tripot / Tackel & Handle Crane 2T -
JUMLAH -

O.54 1 m' Pipa DCI dia. 800mm


3.8590 Oh Pekerja 96,800.00
0.7720 Oh Tukang Pipa 121,000.00
0.4930 Oh Operator Alat Berat 196,200.00
0.3860 Oh Mandor 133,100.00
1.0000 M' Pipa DCI ø 800mm -
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

0.0840 Hr Sewa Excafator Type 225 kap 0,5 - 1,0m3 -


0.2250 Hr Sewa Tripot / Tackel & Handle Crane 2T -
JUMLAH -

O.55 1 m' Pipa DCI dia. 900mm


4.9950 Oh Pekerja 96,800.00
0.9990 Oh Tukang Pipa 121,000.00
0.5930 Oh Operator Alat Berat 196,200.00
0.4990 Oh Mandor 133,100.00
1.0000 M' Pipa DCI ø 900mm -
0.0930 Hr Sewa Excafator Type 225 kap 0,5 - 1,0m3 -
0.2480 Hr Sewa Tripot / Tackel & Handle Crane 2T -
JUMLAH -

O.56 1 m' Pipa DCI dia. 1000mm


5.9310 Oh Pekerja 96,800.00
1.1860 Oh Tukang Pipa 121,000.00
0.7930 Oh Operator Alat Berat 196,200.00
0.6930 Oh Mandor 133,100.00
1.0000 M' Pipa DCI ø 1000mm -
0.1120 Hr Sewa Excafator Type 225 kap 0,5 - 1,0m3 -
0.2980 Hr Sewa Tripot / Tackel & Handle Crane 2T -
JUMLAH -

O.57 1 m' Pipa DCI dia. 1100mm


6.9490 Oh Pekerja 96,800.00
1.3900 Oh Tukang Pipa 121,000.00
0.7930 Oh Operator Alat Berat 196,200.00
0.6950 Oh Mandor 133,100.00
1.0000 M' Pipa DCI ø 1100mm -
0.1520 Hr Sewa Excafator Type 225 kap 0,5 - 1,0m3 -
0.3040 Hr Sewa Tripot / Tackel & Handle Crane 2T -
JUMLAH -

O.58 1 m' Pipa DCI dia. 1200mm


8.0560 Oh Pekerja 96,800.00
1.6110 Oh Tukang Pipa 121,000.00
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

0.8930 Oh Operator Alat Berat 196,200.00


0.8060 Oh Mandor 133,100.00
1.0000 M' Pipa DCI ø 1200mm -
0.1800 Hr Sewa Excafator Type 225 kap 0,5 - 1,0m3 -
0.3600 Hr Sewa Tripot / Tackel & Handle Crane 2T -
JUMLAH -

O.59 1 m' Pipa Baja dia. 63mm


0.4990 Oh Pekerja 96,800.00
0.1000 Oh Tukang Pipa 121,000.00
0.0500 Oh Mandor 133,100.00
1.0000 M' Pipa Baja ø 63mm -
0.0040 Hr Sewa Tripot / Tackel & Handle Crane 2T -
JUMLAH -

O.60 1 m' Pipa Baja dia. 100mm


0.5790 Oh Pekerja 96,800.00
0.1160 Oh Tukang Pipa 121,000.00
0.0580 Oh Mandor 133,100.00
1.0000 M' Pipa Baja ø 100mm -
0.0040 Hr Sewa Tripot / Tackel & Handle Crane 2T -
JUMLAH -

O.61 1 m' Pipa Baja dia. 125mm


0.6480 Oh Pekerja 96,800.00
0.1300 Oh Tukang Pipa 121,000.00
0.0650 Oh Mandor 133,100.00
1.0000 M' Pipa Baja ø 125mm -
0.0040 Hr Sewa Tripot / Tackel & Handle Crane 2T -
JUMLAH -

O.62 1 m' Pipa Baja dia. 150mm


0.7060 Oh Pekerja 96,800.00
0.1420 Oh Tukang Pipa 121,000.00
0.0710 Oh Mandor 133,100.00
1.0000 M' Pipa Baja ø 150mm -
0.0040 Hr Sewa Tripot / Tackel & Handle Crane 2T -
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

JUMLAH -

O.63 1 m' Pipa Baja dia. 200mm


1.1130 Oh Pekerja 96,800.00
0.2230 Oh Tukang Pipa 121,000.00
0.1110 Oh Mandor 133,100.00
1.0000 M' Pipa Baja ø 200mm -
0.0040 Hr Sewa Tripot / Tackel & Handle Crane 2T -
JUMLAH -

O.64 1 m' Pipa Baja dia. 250mm


1.3250 Oh Pekerja 96,800.00
0.2650 Oh Tukang Pipa 121,000.00
0.1330 Oh Mandor 133,100.00
1.0000 M' Pipa Baja ø 250mm -
0.0040 Hr Sewa Tripot / Tackel & Handle Crane 2T -
JUMLAH -

O.65 1 m' Pipa Baja dia. 300mm


1.4150 Oh Pekerja 96,800.00
0.2830 Oh Tukang Pipa 121,000.00
0.1410 Oh Mandor 133,100.00
1.0000 M' Pipa Baja ø 300mm -
0.0040 Hr Sewa Tripot / Tackel & Handle Crane 2T -
JUMLAH -

O.66 1 m' Pipa Baja dia. 400mm


2.3660 Oh Pekerja 96,800.00
0.4730 Oh Tukang Pipa 121,000.00
0.2370 Oh Mandor 133,100.00
1.0000 M' Pipa Baja ø 400mm -
0.0270 Hr Sewa Excafator Type 225 kap 0,5 - 1,0m3 -
0.0390 Hr Sewa Tripot / Tackel & Handle Crane 2T -
JUMLAH -

O.67 1 m' Pipa Baja dia. 450mm


2.2310 Oh Pekerja 96,800.00
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

0.4460 Oh Tukang Pipa 121,000.00


0.2230 Oh Mandor 133,100.00
1.0000 M' Pipa Baja ø 450mm -
0.0260 Hr Sewa Excafator Type 225 kap 0,5 - 1,0m3 -
0.0370 Hr Sewa Tripot / Tackel & Handle Crane 2T -
JUMLAH -

O.68 1 m' Pipa Baja dia. 500mm


2.4320 Oh Pekerja 96,800.00
0.4860 Oh Tukang Pipa 121,000.00
0.2430 Oh Mandor 133,100.00
1.0000 M' Pipa Baja ø 500mm -
0.0290 Hr Sewa Excafator Type 225 kap 0,5 - 1,0m3 -
0.0450 Hr Sewa Tripot / Tackel & Handle Crane 2T -
JUMLAH -

O.69 1 m' Pipa Baja dia. 600mm


2.2080 Oh Pekerja 96,800.00
0.4420 Oh Tukang Pipa 121,000.00
0.2210 Oh Mandor 133,100.00
1.0000 M' Pipa Baja ø 600mm -
0.0270 Hr Sewa Excafator Type 225 kap 0,5 - 1,0m3 -
0.0390 Hr Sewa Tripot / Tackel & Handle Crane 2T -
JUMLAH -

O.70 1 m' Pipa Baja dia. 800mm


3.8970 Oh Pekerja 96,800.00
0.7790 Oh Tukang Pipa 121,000.00
0.3000 Oh Mandor 133,100.00
1.0000 M' Pipa Baja ø 800mm -
0.0460 Hr Sewa Excafator Type 225 kap 0,5 - 1,0m3 -
0.0980 Hr Sewa Tripot / Tackel & Handle Crane 2T -
JUMLAH -

O.71 1 m' Pipa Baja dia. 900mm


4.4030 Oh Pekerja 96,800.00
0.0810 Oh Tukang Pipa 121,000.00
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

0.4400 Oh Mandor 133,100.00


1.0000 M' Pipa Baja ø 900mm -
0.0520 Hr Sewa Excafator Type 225 kap 0,5 - 1,0m3 -
0.1150 Hr Sewa Tripot / Tackel & Handle Crane 2T -
JUMLAH -

O.72 1 m' Pipa Baja dia. 1000mm


4.8950 Oh Pekerja 96,800.00
0.9790 Oh Tukang Pipa 121,000.00
0.4890 Oh Mandor 133,100.00
1.0000 M' Pipa Baja ø 1000mm -
0.0580 Hr Sewa Excafator Type 225 kap 0,5 - 1,0m3 -
0.1330 Hr Sewa Tripot / Tackel & Handle Crane 2T -
JUMLAH -

O.73 1 m' Pipa Baja dia. 1100mm


5.3870 Oh Pekerja 96,800.00
1.0770 Oh Tukang Pipa 121,000.00
0.5390 Oh Mandor 133,100.00
1.0000 M' Pipa Baja ø 1100mm -
0.0640 Hr Sewa Excafator Type 225 kap 0,5 - 1,0m3 -
0.1500 Hr Sewa Tripot / Tackel & Handle Crane 2T -
JUMLAH -

O.74 1 m' Pipa Baja dia. 1200mm


5.8970 Oh Pekerja 96,800.00
1.1760 Oh Tukang Pipa 121,000.00
0.5880 Oh Mandor 133,100.00
1.0000 M' Pipa Baja ø 1200mm -
0.0700 Hr Sewa Excafator Type 225 kap 0,5 - 1,0m3 -
0.1670 Hr Sewa Tripot / Tackel & Handle Crane 2T -
JUMLAH -
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

5,227.20
10,890.00
1,306.80
3,593.70

21,017.70 61,937.70

5,227.20
10,890.00
1,306.80
3,593.70

21,017.70 70,307.70

5,227.20
10,890.00
1,306.80
3,593.70

21,017.70 79,142.70
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

10,454.40
21,780.00
2,613.60
665.50

35,513.50 140,603.50

13,068.00
27,225.00
3,339.60
931.70

44,564.30 193,364.30

13,068.00
27,225.00
3,339.60
931.70

44,564.30 290,084.30

3,484.80
7,260.00
871.20
266.20

11,882.20 20,872.20

3,484.80
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

7,260.00
871.20
266.20

11,882.20 23,507.20

3,484.80
7,260.00
871.20
266.20

11,882.20 28,118.45

5,227.20
10,890.00
1,306.80
399.30

17,823.30 44,018.30

5,227.20
10,890.00
1,306.80
399.30

17,823.30 52,310.80

7,840.80
16,335.00
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

1,960.20
532.40

26,668.40 85,955.90

7,840.80
16,335.00
1,960.20
532.40

26,668.40 120,133.40

3,388.00
2,057.00
399.30

5,844.30 56,004.30

3,872.00
2,420.00
532.40

6,824.40 157,424.40

4,356.00
2,783.00
665.50
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

7,804.50 202,804.50

6,001.60
3,751.00
798.60

10,551.20 253,551.20

9,873.60
6,171.00
1,331.00

17,375.60 514,175.60

12,874.40
8,107.00
1,730.30

22,711.70 797,311.70

16,456.00
10,285.00
2,262.70

29,003.70 998,603.70

28,072.00
17,545.00
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

3,859.90

49,476.90 2,027,676.90

34,751.20
21,780.00
4,791.60

61,322.80 2,566,922.80

41,914.40
26,136.00
5,723.30

73,773.70 3,164,733.70

49,561.60
30,976.00
6,788.10

87,325.70 3,959,125.70

86,442.40
53,966.00
11,845.90

152,254.30 6,422,254.30
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

130,970.40
81,917.00
17,968.50

230,855.90 8,128,295.90

160,591.20
100,430.00
22,094.60

283,115.80 10,086,035.80

175,982.40
109,989.00
24,224.20

310,195.60 310,195.60

229,416.00
143,385.00
31,544.70

404,345.70 404,345.70

33,396.00
20,812.00
4,525.40
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

58,733.40 58,733.40

38,720.00
24,200.00
5,324.00

68,244.00 68,244.00

43,366.40
27,104.00
5,989.50

76,459.90 76,459.90

48,980.80
30,613.00
6,788.10

86,381.90 86,381.90

77,052.80
48,158.00
10,648.00

135,858.80 135,858.80

91,863.20
57,475.00
12,644.50

161,982.70 161,982.70
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

92,734.40
57,959.00
12,777.60

163,471.00 163,471.00

117,321.60
73,326.00
16,105.10

206,752.70 206,752.70

130,970.40
81,796.00
17,968.50

230,734.90 230,734.90

142,199.20
88,935.00
19,565.70

250,699.90 250,699.90

128,453.60
80,344.00
17,702.30

226,499.90 226,499.90

225,253.60
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

140,723.00
31,012.30

396,988.90 396,988.90

253,906.40
158,752.00
34,872.20

447,530.60 447,530.60

281,784.80
176,176.00
38,732.10

496,692.90 496,692.90

309,760.00
193,600.00
42,592.00

545,952.00 545,952.00

337,638.40
211,024.00
46,451.90

595,114.30 595,114.30

47,335.20
11,858.00
6,521.90
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

65,715.10 65,715.10

82,764.00
20,691.00
11,313.50

114,768.50 114,768.50

92,056.80
22,990.00
12,644.50

127,691.30 127,691.30

94,186.40
23,595.00
12,910.70

130,692.10 130,692.10

149,556.00
37,389.00
18,246.60
20,497.40

225,689.00 225,689.00
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

175,498.40
43,923.00
28,056.60
24,091.10

271,569.10 271,569.10

198,149.60
49,489.00
37,866.60
27,285.50

312,790.70 312,790.70

194,664.80
48,642.00
57,486.60
26,753.10

327,546.50 327,546.50

373,551.20
93,412.00
96,726.60
51,376.60
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

615,066.40 615,066.40

483,516.00
120,879.00
116,346.60
66,416.90

787,158.50 787,158.50

574,120.80
143,506.00
155,586.60
92,238.30

965,451.70 965,451.70

672,663.20
168,190.00
155,586.60
92,504.50

1,088,944.30 1,088,944.30

779,820.80
194,931.00
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

175,206.60
107,278.60

1,257,237.00 1,257,237.00

48,303.20
12,100.00
6,655.00

67,058.20 67,058.20

56,047.20
14,036.00
7,719.80

77,803.00 77,803.00

62,726.40
15,730.00
8,651.50

87,107.90 87,107.90

68,340.80
17,182.00
9,450.10
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

94,972.90 94,972.90

107,738.40
26,983.00
14,774.10

149,495.50 149,495.50

128,260.00
32,065.00
17,702.30

178,027.30 178,027.30

136,972.00
34,243.00
18,767.10

189,982.10 189,982.10

229,028.80
57,233.00
31,544.70

317,806.50 317,806.50

215,960.80
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

53,966.00
29,681.30

299,608.10 299,608.10

235,417.60
58,806.00
32,343.30

326,566.90 326,566.90

213,734.40
53,482.00
29,415.10

296,631.50 296,631.50

377,229.60
94,259.00
39,930.00

511,418.60 511,418.60

426,210.40
9,801.00
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

58,564.00

494,575.40 494,575.40

473,836.00
118,459.00
65,085.90

657,380.90 657,380.90

521,461.60
130,317.00
71,740.90

723,519.50 723,519.50

570,829.60
142,296.00
78,262.80

791,388.40 791,388.40
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

P PEKERJAAN AKSESORIES PIPA

P.1 1 bh Valve dia. 150mm


1.4290 Oh Pekerja 96,800.00
0.7150 Oh Tukang Pipa 121,000.00
0.1430 Oh Mandor 133,100.00
1.0000 Bh Valve ø 150mm -
0.1000 Hr Sewa Tripot / Tackel & Handle Crane 2T -
JUMLAH -

P.2 1 bh Valve dia. 200mm


1.7140 Oh Pekerja 96,800.00
0.8570 Oh Tukang Pipa 121,000.00
0.1710 Oh Mandor 133,100.00
1.0000 Bh Valve ø 200mm -
0.3000 Hr Sewa Tripot / Tackel & Handle Crane 2T -
JUMLAH -

P.3 1 bh Valve dia. 250mm


1.7140 Oh Pekerja 96,800.00
0.8570 Oh Tukang Pipa 121,000.00
0.1710 Oh Mandor 133,100.00
1.0000 Bh Valve ø 250mm -
0.4000 Hr Sewa Tripot / Tackel & Handle Crane 2T -
JUMLAH -

P.4 1 bh Valve dia. 300mm


2.0000 Oh Pekerja 96,800.00
1.0000 Oh Tukang Pipa 121,000.00
0.2000 Oh Mandor 133,100.00
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

1.0000 Bh Valve ø 300mm -


0.5000 Hr Sewa Tripot / Tackel & Handle Crane 2T -
JUMLAH -

P.5 1 bh Valve dia. 400mm


3.4290 Oh Pekerja 96,800.00
1.7150 Oh Tukang Pipa 121,000.00
0.3430 Oh Mandor 133,100.00
1.0000 Bh Valve ø 400mm -
1.0000 Hr Sewa Tripot / Tackel & Handle Crane 2T -
JUMLAH -

P.6 1 bh Valve dia. 450mm


3.4290 Oh Pekerja 96,800.00
1.7150 Oh Tukang Pipa 121,000.00
0.3430 Oh Mandor 133,100.00
1.0000 Bh Valve ø 450mm -
1.0000 Hr Sewa Tripot / Tackel & Handle Crane 2T -
JUMLAH -

P.7 1 bh Valve dia. 500mm


4.0000 Oh Pekerja 96,800.00
2.0000 Oh Tukang Pipa 121,000.00
0.4000 Oh Mandor 133,100.00
1.0000 Bh Valve ø 500mm -
1.0000 Hr Sewa Tripot / Tackel & Handle Crane 2T -
JUMLAH -

P.8 1 bh Valve dia. 600mm


1.4210 Oh Pekerja 96,800.00
0.7110 Oh Tukang Pipa 121,000.00
0.1420 Oh Mandor 133,100.00
1.0000 Bh Valve ø 600mm -
0.6000 Hr Sewa Tripot / Tackel & Handle Crane 2T -
0.3000 Hr Mobile Crane = < 3 ton -
JUMLAH -
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

P.9 1 bh Valve dia. 700mm


1.4290 Oh Pekerja 96,800.00
0.7150 Oh Tukang Pipa 121,000.00
0.1430 Oh Mandor 133,100.00
1.0000 Bh Valve ø 700mm -
0.5000 Hr Sewa Tripot / Tackel & Handle Crane 2T -
0.5000 Hr Mobile Crane = < 3 ton -
JUMLAH -

P.10 1 bh Valve dia. 800mm


1.7860 Oh Pekerja 96,800.00
0.8930 Oh Tukang Pipa 121,000.00
0.1790 Oh Mandor 133,100.00
1.0000 Bh Valve ø 800mm -
0.5000 Hr Sewa Tripot / Tackel & Handle Crane 2T -
0.5000 Hr Mobile Crane = < 3 ton -
JUMLAH -

P.11 1 bh Valve dia. 900mm


1.7140 Oh Pekerja 96,800.00
0.8570 Oh Tukang Pipa 121,000.00
0.1710 Oh Mandor 133,100.00
1.0000 Bh Valve ø 900mm -
0.7500 Hr Sewa Tripot / Tackel & Handle Crane 2T -
0.7500 Hr Mobile Crane = < 3 ton -
JUMLAH -

P.12 1 bh Valve dia. 1000mm


2.5710 Oh Pekerja 96,800.00
1.2860 Oh Tukang Pipa 121,000.00
0.2570 Oh Mandor 133,100.00
1.0000 Bh Valve ø 1000mm -
1.0000 Hr Sewa Tripot / Tackel & Handle Crane 2T -
1.0000 Hr Mobile Crane = < 3 ton -
JUMLAH -

P.13 1 bh Valve dia. 1100mm


KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

3.0000 Oh Pekerja 96,800.00


1.5000 Oh Tukang Pipa 121,000.00
0.3000 Oh Mandor 133,100.00
1.0000 Bh Valve ø 1100mm -
1.0000 Hr Sewa Tripot / Tackel & Handle Crane 2T -
1.0000 Hr Mobile Crane = < 3 ton -
JUMLAH -

P.14 1 bh Valve dia. 1200mm


3.0000 Oh Pekerja 96,800.00
1.5000 Oh Tukang Pipa 121,000.00
0.3000 Oh Mandor 133,100.00
1.0000 Bh Valve ø 1200mm -
1.0000 Hr Sewa Tripot / Tackel & Handle Crane 2T -
1.0000 Hr Mobile Crane = < 3 ton -
JUMLAH -

P.15 1 bh Tee dia. 150mm


0.1060 Oh Pekerja 96,800.00
0.0530 Oh Tukang Pipa 121,000.00
0.0110 Oh Mandor 133,100.00
1.0000 Bh Tee ø 150mm -
0.0280 Hr Sewa Tripot / Tackel & Handle Crane 2T -
JUMLAH -

P.16 1 bh Tee dia. 200mm


0.2160 Oh Pekerja 96,800.00
0.1080 Oh Tukang Pipa 121,000.00
0.0220 Oh Mandor 133,100.00
1.0000 Bh Tee ø 200mm -
0.0290 Hr Sewa Tripot / Tackel & Handle Crane 2T -
JUMLAH -

P.17 1 bh Tee dia. 250mm


0.3260 Oh Pekerja 96,800.00
0.1630 Oh Tukang Pipa 121,000.00
0.0330 Oh Mandor 133,100.00
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

1.0000 Bh Tee ø 250mm -


0.0390 Hr Sewa Tripot / Tackel & Handle Crane 2T -
JUMLAH -

P.17 1 bh Tee dia. 300mm


0.4360 Oh Pekerja 96,800.00
0.2180 Oh Tukang Pipa 121,000.00
0.0440 Oh Mandor 133,100.00
1.0000 Bh Tee ø 300mm -
0.5000 Hr Sewa Tripot / Tackel & Handle Crane 2T -
JUMLAH -

P.18 1 bh Tee dia. 400mm


0.6560 Oh Pekerja 96,800.00
0.3280 Oh Tukang Pipa 121,000.00
0.0660 Oh Mandor 133,100.00
1.0000 Bh Tee ø 400mm -
0.5000 Hr Sewa Tripot / Tackel & Handle Crane 2T -
JUMLAH -

P.19 1 bh Tee dia. 450mm


0.7660 Oh Pekerja 96,800.00
0.3830 Oh Tukang Pipa 121,000.00
0.0770 Oh Mandor 133,100.00
1.0000 Bh Tee ø 450mm -
0.5000 Hr Sewa Tripot / Tackel & Handle Crane 2T -
JUMLAH -

P.20 1 bh Tee dia. 500mm


0.8760 Oh Pekerja 96,800.00
0.4380 Oh Tukang Pipa 121,000.00
0.0880 Oh Mandor 133,100.00
1.0000 Bh Tee ø 500mm -
0.6000 Hr Sewa Tripot / Tackel & Handle Crane 2T -
JUMLAH -

P.21 1 bh Tee dia. 600mm


KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

1.0960 Oh Pekerja 96,800.00


0.5480 Oh Tukang Pipa 121,000.00
0.1100 Oh Mandor 133,100.00
1.0000 Bh Tee ø 600mm -
0.1930 Hr Sewa Tripot / Tackel & Handle Crane 2T -
0.9600 Hr Mobile Crane = < 3 ton -
JUMLAH -

P.22 1 bh Tee dia. 700mm


1.3160 Oh Pekerja 96,800.00
0.6580 Oh Tukang Pipa 121,000.00
0.1320 Oh Mandor 133,100.00
1.0000 Bh Tee ø 700mm -
0.2250 Hr Sewa Tripot / Tackel & Handle Crane 2T -
0.1130 Hr Mobile Crane = < 3 ton -
JUMLAH -

P.23 1 bh Tee dia. 800mm


1.5360 Oh Pekerja 96,800.00
0.7680 Oh Tukang Pipa 121,000.00
0.1540 Oh Mandor 133,100.00
1.0000 Bh Tee ø 800mm -
0.2570 Hr Sewa Tripot / Tackel & Handle Crane 2T -
0.1290 Hr Mobile Crane = < 3 ton -
JUMLAH -

P.24 1 bh Tee dia. 900mm


1.7560 Oh Pekerja 96,800.00
0.8780 Oh Tukang Pipa 121,000.00
0.1760 Oh Mandor 133,100.00
1.0000 Bh Tee ø 900mm -
0.3210 Hr Sewa Tripot / Tackel & Handle Crane 2T -
0.1610 Hr Mobile Crane = < 3 ton -
JUMLAH -

P.25 1 bh Tee dia. 1000mm


1.9760 Oh Pekerja 96,800.00
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

0.9880 Oh Tukang Pipa 121,000.00


0.1980 Oh Mandor 133,100.00
1.0000 Bh Tee ø 1000mm -
0.3660 Hr Sewa Tripot / Tackel & Handle Crane 2T -
0.1830 Hr Mobile Crane = < 3 ton -
JUMLAH -

P.26 1 bh Tee dia. 1100mm


2.1960 Oh Pekerja 96,800.00
1.0980 Oh Tukang Pipa 121,000.00
0.2200 Oh Mandor 133,100.00
1.0000 Bh Tee ø 1100mm -
0.3860 Hr Sewa Tripot / Tackel & Handle Crane 2T -
0.1930 Hr Mobile Crane = < 3 ton -
JUMLAH -

P.27 1 bh Tee dia. 1200mm


2.4160 Oh Pekerja 96,800.00
1.2080 Oh Tukang Pipa 121,000.00
0.2420 Oh Mandor 133,100.00
1.0000 Bh Tee ø 1200mm -
0.4500 Hr Sewa Tripot / Tackel & Handle Crane 2T -
0.2250 Hr Mobile Crane = < 3 ton -
JUMLAH -
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

138,327.20
86,515.00
19,033.30

243,875.50 243,875.50

165,915.20
103,697.00
22,760.10

292,372.30 292,372.30

165,915.20
103,697.00
22,760.10

292,372.30 292,372.30

193,600.00
121,000.00
26,620.00
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

341,220.00 341,220.00

331,927.20
207,515.00
45,653.30

585,095.50 585,095.50

331,927.20
207,515.00
45,653.30

585,095.50 585,095.50

387,200.00
242,000.00
53,240.00

682,440.00 682,440.00

137,552.80
86,031.00
18,900.20

242,484.00 242,484.00
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

138,327.20
86,515.00
19,033.30

243,875.50 243,875.50

172,884.80
108,053.00
23,824.90

304,762.70 304,762.70

165,915.20
103,697.00
22,760.10

292,372.30 292,372.30

248,872.80
155,606.00
34,206.70

438,685.50 438,685.50
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

290,400.00
181,500.00
39,930.00

511,830.00 511,830.00

290,400.00
181,500.00
39,930.00

511,830.00 511,830.00

10,260.80
6,413.00
1,464.10

18,137.90 18,137.90

20,908.80
13,068.00
2,928.20

36,905.00 36,905.00

31,556.80
19,723.00
4,392.30
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

55,672.10 55,672.10

42,204.80
26,378.00
5,856.40

74,439.20 74,439.20

63,500.80
39,688.00
8,784.60

111,973.40 111,973.40

74,148.80
46,343.00
10,248.70

130,740.50 130,740.50

84,796.80
52,998.00
11,712.80

149,507.60 149,507.60
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

106,092.80
66,308.00
14,641.00

187,041.80 187,041.80

127,388.80
79,618.00
17,569.20

224,576.00 224,576.00

148,684.80
92,928.00
20,497.40

262,110.20 262,110.20

169,980.80
106,238.00
23,425.60

299,644.40 299,644.40

191,276.80
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

119,548.00
26,353.80

337,178.60 337,178.60

212,572.80
132,858.00
29,282.00

374,712.80 374,712.80

233,868.80
146,168.00
32,210.20

412,247.00 412,247.00
DAFTAR ANALISA PEKERJAAN
BIDANG CIPTA KARYA
DINAS PEKERJAAN UMUM KOTA PANGKALPINANG
TAHUN ANGGARAN 2016

KODE HARGA SATUAN (Rp.) JUMLAH (Rp)


URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

Q PEKERJAAN PENGETESAN PIPA

Q.1 1 m' Pengetesan Pipa dia. 50mm


0.0080 Oh Pekerja 96,800.00
0.0008 Oh Mandor 133,100.00
0.0020 M³ Air Test / Air Bersih 240,000.00 480.00
0.0600 Ltr Bahan Bakar 8,340.00 500.40
0.0020 Ltr Minyak Pelumas 39,600.00 79.20
JUMLAH 1,059.60

Q.2 1 m' Pengetesan Pipa dia. 75mm


0.0080 Oh Pekerja 96,800.00
0.0008 Oh Mandor 133,100.00
0.0040 M³ Air Test / Air Bersih 240,000.00 960.00
0.0600 Ltr Bahan Bakar 8,340.00 500.40
0.0020 Ltr Minyak Pelumas 39,600.00 79.20
JUMLAH 1,539.60

Q.3 1 m' Pengetesan Pipa dia. 100mm


0.0080 Oh Pekerja 96,800.00
0.0008 Oh Mandor 133,100.00
0.0080 M³ Air Test / Air Bersih 240,000.00 1,920.00
0.0600 Ltr Bahan Bakar 8,340.00 500.40
0.0020 Ltr Minyak Pelumas 39,600.00 79.20
JUMLAH 2,499.60

Q.4 1 m' Pengetesan Pipa dia. 150mm


0.0080 Oh Pekerja 96,800.00
0.0008 Oh Mandor 133,100.00
0.0180 M³ Air Test / Air Bersih 240,000.00 4,320.00
KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

0.0600 Ltr Bahan Bakar 8,340.00 500.40


0.0020 Ltr Minyak Pelumas 39,600.00 79.20
JUMLAH 4,899.60

Q.5 1 m' Pengetesan Pipa dia. 200mm


0.0080 Oh Pekerja 96,800.00
0.0008 Oh Mandor 133,100.00
0.0310 M³ Air Test / Air Bersih 240,000.00 7,440.00
0.0600 Ltr Bahan Bakar 8,340.00 500.40
0.0020 Ltr Minyak Pelumas 39,600.00 79.20
JUMLAH 8,019.60

Q.6 1 m' Pengetesan Pipa dia. 250mm


0.0080 Oh Pekerja 96,800.00
0.0008 Oh Mandor 133,100.00
0.0490 M³ Air Test / Air Bersih 240,000.00 11,760.00
0.0600 Ltr Bahan Bakar 8,340.00 500.40
0.0020 Ltr Minyak Pelumas 39,600.00 79.20
JUMLAH 12,339.60

Q.7 1 m' Pengetesan Pipa dia. 300mm


0.0080 Oh Pekerja 96,800.00
0.0008 Oh Mandor 133,100.00
0.0710 M³ Air Test / Air Bersih 240,000.00 17,040.00
0.0600 Ltr Bahan Bakar 8,340.00 500.40
0.0020 Ltr Minyak Pelumas 39,600.00 79.20
JUMLAH 17,619.60

Q.8 1 m' Pengetesan Pipa dia. 400mm


0.0080 Oh Pekerja 96,800.00
0.0008 Oh Mandor 133,100.00
0.1260 M³ Air Test / Air Bersih 240,000.00 30,240.00
0.0600 Ltr Bahan Bakar 8,340.00 500.40
0.0020 Ltr Minyak Pelumas 39,600.00 79.20
JUMLAH 30,819.60

Q.9 1 m' Pengetesan Pipa dia. 500mm


KODE HARGA SATUAN (Rp.) JUMLAH (Rp)
URAIAN PEKERJAAN
ANAL BAHAN UPAH BAHAN

0.0080 Oh Pekerja 96,800.00


0.0008 Oh Mandor 133,100.00
0.1580 M³ Air Test / Air Bersih 240,000.00 37,920.00
0.0600 Ltr Bahan Bakar 8,340.00 500.40
0.0020 Ltr Minyak Pelumas 39,600.00 79.20
JUMLAH 38,499.60

Q.10 1 m' Pengetesan Pipa dia. 600mm


0.0080 Oh Pekerja 96,800.00
0.0008 Oh Mandor 133,100.00
0.2830 M³ Air Test / Air Bersih 240,000.00 67,920.00
0.0600 Ltr Bahan Bakar 8,340.00 500.40
0.0020 Ltr Minyak Pelumas 39,600.00 79.20
JUMLAH 68,499.60
PINANG

JUMLAH (Rp) JUMLAH UPAH +


UPAH BAHAN (Rp.)

774.40
106.48

880.88 1,940.48

774.40
106.48

880.88 2,420.48

774.40
106.48

880.88 3,380.48

774.40
106.48
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

880.88 5,780.48

774.40
106.48

880.88 8,900.48

774.40
106.48

880.88 13,220.48

774.40
106.48

880.88 18,500.48

774.40
106.48

880.88 31,700.48
JUMLAH (Rp) JUMLAH UPAH +
UPAH BAHAN (Rp.)

774.40
106.48

880.88 39,380.48

774.40
106.48

880.88 69,380.48
1 PEKERJAAN GALIAN 54 10,000.00 540,000.00
18 5,000.00 90,000.00
PEKERJAAN BETON 0.36 1,048,351.42 377,406.51
PEKERJAAN PAS.BATA 72 64,973.43 4,678,086.95
PEKERJAAN PAS. KERAMIK 101.65 222,998.57 22,667,804.76
28,353,298.22