WO#33 PROVISION OF DEDICATE IRT LINE FROM TK-253 TO MAB-HCR IN MAA

Activity ID Activity Name Original Start Finish 2019


Duration
r Apr May Jun Jul Aug

WO#33 PROVISION
PROVIS OF DEDICATE IRT LINE FROM TK-253 TO MAB- 328 24-Jul-18 A 15-Aug-19

MILESTONES 385 24-Jul-18 A 12-Aug-19

MS100 Commencement of Work Order 0 24-Jul-18 A


MS155 Work Order Completion 0 12-Aug-19

GENERAL ACTIVTIES
AC 85 24-Jul-18 A 05-Nov-18 A

INITIATION 29 24-Jul-18 A 01-Sep-18 A


MOBILIZATION 0 24-Jul-18 A 24-Jul-18 A
A1000 Site Handover Certificate 0 24-Jul-18 A 24-Jul-18 A
SUBMISSIONS OF DOCUMENT 28 25-Jul-18 A 01-Sep-18 A
G-100 Submission of Organization Chart 7 25-Jul-18 A 01-Aug-18 A
G-110 Submission of Key personnel CV 7 25-Jul-18 A 01-Aug-18 A
G-120 Approval of Organisation Chart 21 02-Aug-18 A 01-Sep-18 A
G-130 Approval of Key personnel CV 21 02-Aug-18 A 01-Sep-18 A
PMS 54 04-Sep-18 A 05-Nov-18 A
WORK PROGRAMME
PROGR 33 04-Sep-18 A 11-Oct-18 A
G-140 Preparation & Submission to KNPC 15 04-Sep-18 A 20-Sep-18 A
G-150 Review & approval by KNPC 21 20-Sep-18 A 11-Oct-18 A
PMS & "S" Cu
Curve 21 13-Oct-18 A 05-Nov-18 A
G-160 Preparation & Submission to KNPC 3 13-Oct-18 A 15-Oct-18 A
G-170 Review & approval by KNPC 21 15-Oct-18 A 05-Nov-18 A
METHOD STATEMENTS
STAT & PROCEDURES 58 06-Aug-18 A 17-Oct-18 A
PAINTING & B
BLASTING PROCEDURE 33 04-Sep-18 A 11-Oct-18 A
G-200 Surface & painting Procedure & Submission to KNPC 15 04-Sep-18 A 20-Sep-18 A
G-210 Review & approval by KNPC 21 20-Sep-18 A 11-Oct-18 A
WPS 38 04-Sep-18 A 17-Oct-18 A
G-220 Preparation & Submission to KNPC 20 04-Sep-18 A 26-Sep-18 A
G-230 Review & approval by KNPC 21 26-Sep-18 A 17-Oct-18 A
ITP 33 04-Sep-18 A 11-Oct-18 A
G-240 Preparation & Submission to KNPC 15 04-Sep-18 A 20-Sep-18 A
G-250 Review & approval by KNPC 21 20-Sep-18 A 11-Oct-18 A
HYDROTEST P
PROCEDURE 33 06-Aug-18 A 18-Sep-18 A
G-260 Preparation & Submission to KNPC 15 06-Aug-18 A 28-Aug-18 A
G-270 Review & approval by KNPC 21 28-Aug-18 A 18-Sep-18 A
METHOD STATEMENT
STAT 33 12-Aug-18 A 24-Sep-18 A

Actual Level of Effort Remaining Work Date Revision Checked Approved


Page 1 of 4
07-Jul-19 Revised schedule
Actual Work Critical Remainin...
WO#33 PROVISION OF DEDICATE IRT LINE FROM TK-253 TO MAB-HCR IN MAA
Activity ID Activity Name Original Start Finish 2019
Duration
r Apr May Jun Jul Aug
G-280 Preparation & Submission to KNPC 15 12-Aug-18 A 03-Sep-18 A
G-290 Review & approval by KNPC 21 03-Sep-18 A 24-Sep-18 A

PROCUREMENT
PROCUREME 316 25-Jul-18 A 03-Aug-19

HANDING OVER FREE ISSUE MATERIAL 228 25-Jul-18 A 28-Apr-19 A


A2320 Power Cables ( 500 Mtr) 60 25-Jul-18 A 08-Oct-18 A
A2330 Instrumentation Cables ( 1000 Mtr ) 60 25-Jul-18 A 08-Oct-18 A
A2310 MOV ( 1 No ) 20 31-Mar-19 A 22-Apr-19 A
A2300 Pipes & fittings 50 25-Jul-18 A 28-Apr-19 A
PREFABRICATION
PREFABRICATI 55 27-Sep-18 A 30-Apr-19 A
A2380 Handover Fabrication yard by KNPC 5 27-Sep-18 A 02-Oct-18 A
A2390 Blasting & Pre fabrication of piping material 30 27-Oct-18 A 30-Apr-19 A
KCCEC MATERIAL
MATER 276 16-Sep-18 A 03-Aug-19
OMRON RELAY
RELA 241 09-Oct-18 A 16-Jul-19
P3025 Submission & approval of Data sheets 30 09-Oct-18 A 12-Nov-18 A
P3030 Placement of PO 14 13-Nov-18 A 04-Jul-19
P3040 Manufacturing 5 06-Jul-19 10-Jul-19
P3050 Delivery & Inspection at Site 5 11-Jul-19 16-Jul-19
DCS VENDOR ASSITANCE 276 16-Sep-18 A 03-Aug-19
P3060 Placement of PO 10 16-Sep-18 A 26-Sep-18 A
P3055 Submission & approval of Data sheets 30 30-Jun-19 03-Aug-19

CONSTRUCTION
CONSTRUCTI 255 26-Oct-18 A 11-Aug-19

EXISTING LINE ( NEAR TK 459 TO NEAR TK 511 ) 10 26-Oct-18 A 15-Dec-18 A


A2340 Line Survey & permit issuance 5 26-Oct-18 A 26-Oct-18 A
A2350 Repair / Rectification of pipe supports ( if required ) 1 29-Nov-18 A 02-Dec-18 A
A2360 Hand over line by KNPC for Hydro test 1 03-Dec-18 A 03-Dec-18 A
A2355 Spades instllation / weld blanks 2 02-Dec-18 A 03-Dec-18 A
A2370 Hydrotest 2 06-Dec-18 A 15-Dec-18 A
TIE IN ( Existing Line Tie In ) TK 511 (2 tie in ) 11 30-Jun-19 11-Jul-19
A2550 Site prepration ( permit Authorization , necessary arrangements) 1 30-Jun-19 30-Jun-19
A2560 Fabrication / Testing / Cross check for tie in pipes 2 01-Jul-19 02-Jul-19
A2510 Cold Cutting 3 03-Jul-19 06-Jul-19
A2520 Welding of Tie in pipe 3 07-Jul-19 09-Jul-19
A2530 NDT 2 10-Jul-19 11-Jul-19

Actual Level of Effort Remaining Work Date Revision Checked Approved


Page 2 of 4
07-Jul-19 Revised schedule
Actual Work Critical Remainin...
WO#33 PROVISION OF DEDICATE IRT LINE FROM TK-253 TO MAB-HCR IN MAA
Activity ID Activity Name Original Start Finish 2019
Duration
r Apr May Jun Jul Aug
NEW LINE ( SW
SWITCH GATE TO TK 511) 52 15-May-19 A 14-Jul-19
A1870 Site prepration ( permit Authorization , necessary arrangements) 1 15-May-19 A 15-May-19 A
A1880 Erection of scaffolding 5 15-May-19 A 20-May-19 A
A1900 Installation of prefabricated pipes 5 15-May-19 A 20-May-19 A
A1905 Repair / Rectification of existing pipe supports ( if required ) and Pipe support 6 16-May-19 A 22-May-19 A
A1890 Dismantlle of scaffolding 5 26-May-19 A 30-May-19 A
A1910 Fit-up & welding of field joints ( New line ) 6 16-May-19 A 06-Jul-19
A1930 NDT for field joints 6 02-Jul-19 08-Jul-19
A1940 Paint touch up 5 09-Jul-19 14-Jul-19
NEAR TK 459 TO
T TK 253 64 20-Apr-19 A 07-Aug-19
A1010 Site prepration ( permit Authorization , necessary arrangements) 1 20-Apr-19 A 21-Apr-19 A
A1020 Erection of scaffolding 10 27-Apr-19 A 10-Jul-19
A1040 Installation of prefabricated pipes ( New line ) 15 01-May-19 A 16-Jul-19
A1050 Fit-up & welding of field joints 28 02-May-19 A 31-Jul-19
A1070 NDT for field joints ( New line ) 20 06-May-19 A 01-Aug-19
A1030 Dismantlle of scaffolding 5 03-Aug-19 07-Aug-19
A1100 paint touch up ( New line ) 5 03-Aug-19 07-Aug-19
A1035 Repair / Rectification of existing pipe supports ( if required ) and Pipe support 15 22-Jul-19 07-Aug-19
TIE IN ( new Line
Lin ) 9 01-Aug-19 11-Aug-19
A1765 Site prepration ( permit Authorization , necessary arrangements) 1 01-Aug-19 01-Aug-19
A1770 Fabrication / Testing / Cross check for tie in pipes 2 03-Aug-19 04-Aug-19
A1790 Cold Cutting 1 05-Aug-19 05-Aug-19
A1820 Welding of Tie in pipe 2 06-Aug-19 07-Aug-19
A1830 NDT 1 08-Aug-19 08-Aug-19
A1840 Hydrotest ( Complete line ) 2 10-Aug-19 11-Aug-19
PSV & MOV INSTALLATION
INS 88 13-Feb-19 A 23-Jul-19
A2440 Laying of Cables ( power & Instrumentation ) 5 13-Feb-19 A 01-Jun-19 A
A2450 caution tape, backfilling & Route marker 10 01-Jun-19 A 05-Jun-19 A
A2460 JB Installation ,Cable termination & loop checking 2 30-Jun-19 01-Jul-19
A2470 MOV feed back point & graphic Configuration 2 17-Jul-19 18-Jul-19
A2480 Instllation of MOV 2 20-Jul-19 21-Jul-19
A2410 Bolting & Tightening of flanges 1 22-Jul-19 22-Jul-19
A2490 MOV Testing & Commissioning 2 22-Jul-19 23-Jul-19

Actual Level of Effort Remaining Work Date Revision Checked Approved


Page 3 of 4
07-Jul-19 Revised schedule
Actual Work Critical Remainin...
WO#33 PROVISION OF DEDICATE IRT LINE FROM TK-253 TO MAB-HCR IN MAA
Activity ID Activity Name Original Start Finish 2019
Duration
r Apr May Jun Jul Aug
COMPLETION & HANDOVER 22 24-Jul-19 15-Aug-19

H110 As built and finals issue of documents 14 24-Jul-19 07-Aug-19


H100 Punch Points 5 07-Aug-19 12-Aug-19
H105 Handover 4 11-Aug-19 15-Aug-19

Actual Level of Effort Remaining Work Date Revision Checked Approved


Page 4 of 4
07-Jul-19 Revised schedule
Actual Work Critical Remainin...