Sie sind auf Seite 1von 14

OBLICON CHAPTER II CASE DIGEST be delivered was a controlling motive for the

establishment of the contract


I. SSS vs. Moonwalk Development and Housing
c) When demand would be useless, as when the
Corporation
debtor has rendered it beyond his power to
Facts: perform.

 SSS filed a complaint in the CFI of Rizal against The case does not fall in any of these exceptions
Moonwalk, alleging that they (SSS) committed an therefore, demand was necessary in order for
error in failing to compute 12% interest due on Moonwalk to be considered in delay.
delayed payments on the loan of Moonwalk resulting
II. RCBC v. Court of Appeals
in a chain of errors in the application of payments
made by Moonwalk. Facts:
 CFI dismissed the complaint on the ground that the
 Lustre bought a corolla. He made a down payment of
obligation was already extinguished by the payment
164,620, while the balance will be paid in 24 equal
of Moonwalk of its indebtedness to SSS and by SSS’
monthly installments through RCBC as the financing
act of cancelling the real estate mortgages executed
agent.
in its favor by defendant Moonwalk.
 He issued 24 PDCs amounting to 14,976 pesos each
Issue:  All the checks were encashed except for the payment
for August 1991 because it was unsigned. Because of
1. Is the penalty demandable even after the
this the amount representing said check was recalled
extinguishment of the Principal Obligation?
and re-credited to private respondent’s account.
2. When is default incurred and when is demand
 The recall caused the last two checks of February and
not necessary?
March 1993 to not be presented for payment in
Ruling: conformity to the bank’s procedure.
 It demanded payment of the balance including
1. NO. A penalty is demandable in case of non-
liquidated damages but private respondent refused
performance or late performance of the main
to pay prompting petitioner to file an action for
obligation. In other words there must be a total
replevin and damages.
or partial breach of the obligation. It is important
 RTC and CA both side with private respondent Lustre
to note however that there is no mora or delay
 RCBC contends that the recalled check was not
unless there is demand. In the present case,
encashed such that the installment for August 1991
during the time when the obligation was still
was not paid, hence by virtue of the acceleration
subsisting, although there were late amortization
clause in the chattel mortgage executed by Lustre,
there was no demand made by the creditor,
RCBC was justified in treating the entire balance as
plaintiff appellant for the payment of the penalty.
due and demandable.
Hence up to the time of the letter of the plaintiff
 Despite RCBC’s demand, Lustre refused to pay as
there was no mora in the payment of the penalty.
such RCBC claims Lustre is in delay.
2. Under the civil code, delay begins from the time
the creditor judicially or extra-judicially demands Issue:
from the obligor the performance of the
obligation. There are only three instances when Whether or not Lustre was in delay
demand is not necessary to render the obligor in Ruling:
default: (1169)
a) When the obligation or the law expressly so No. Article 1170 of the New Civil code provides that those
declares who in the performance of their obligations are guilty of
b) When from the nature and the circumstances delay are liable for damages. The delay in the
of the obligation it appears that the performance of the obligation however must be either
designation of the time when the thing is to malicious or negligent. Thus assuming that Lustre was
guilty of delay, in the payment of the value of the
unsigned check, he cannot be held liable for damages.
There is no imputation much less evidence that Lustre immediately deliver the goods otherwise delay would
acted with malice or negligence in failing to sign the attach.
check. It was merely inadvertence in his part. The
IV. Pantaleon v. American Express
invocation of the acceleration clause of the executed
chatter mortgage was unwarranted. Facts:
III. Barzaga v. Court of Appeals  Pantaleon and his family were in a tour of Western
Europe. On the last day of the tour, Mrs. Pantaleon
Facts:
bought a diamond, a pendant and a chain totaling $
 Barzaga’s wife wished to be laid to rest before 13,826.
Christmas day to spare her family’s feelings.  To pay for these, Pantaleon presented his American
 Barzaga set out to arrange for her wife’s interment on express credit card together with his passport to the
the 24th of December. sales clerk. This happened 15 minutes before the
 On December 22, he went to Alviar’s hardware store group was to depart from the store.
and bought materials and told the store employees  10 minutes later, the store clerk informed Pantaleon
that it needs to be delivered at the Memorial that his card had not yet been approved. His son
Cemetery in Dasmarinas Cavite by 8:00 that same informed them that the whole bus was waiting for
morning since his hired workers were already there them so he ordered to cancel the sale
and time was of the essence. Maria Boncales agreed.  The store manager asked the plaintiff to wait and so
 By 8:00 the delivery was not at the site yet, by 9:00 after 15 minutes, the store manager informed
still no delivery so Barzaga went back to the store who Pantaleon that the bank demanded bank references
assured him it will be there in no time. By 10:00 still  The coster decided to release the items even without
no delivery so he went back to the store only to Amex ‘s approval of the purchase.
receive the same answer.  After more incidents of the same nature, Pantaleon
 After hours of waiting, he had to dismiss his workers. sued for damages.
He filed a complaint against Alviar’s hardware store,  RTC sided with Pantaleon while CA reversed their
cancelled his transaction and bought materials decision and sides with Amex
elsewhere. This cause the project to be delayed
further to after Christmas day. Issue:
 Barzaga sued for damages. Whether or not Amex had committed breach of its
obligations to Pantaleon or if not are they liable under
Issue:
article 21 of the civil code.
Whether or not Alviar was negligent and incurred delay in
Ruling:
the performance of his contractual obligation
Yes. There was mora solvendi on the part of Amex.
Ruling:
Although Amex has the right to verify whether the credit
Yes. The law expressly provides that those who in the it is extending upon a particular purchase was indeed
performance of their obligation are guilty of fraud, contracted by the cardholder, the culpable failure of
negligence or delay and those who in any manner Amex is not the failure to timely approve petitioner’s
contravene the tenor thereof are liable for damages. purchase but the failure to timely act on the same
Contrary to the CA’s factual determination there was a whether favorably or unfavorably. They could have
specific time agreed upon for the delivery of the materials promptly informed the petitioners the reason for the
to the cemetery. delay or that said transaction would take some time.
There is finding of bad faith attributable particularly in the
Alviar invokes fortuitous event due to the flat tire of the
dilly-dallying of respondent’s manila credit authorizer.
delivery truck but this event was foreseeable.
V. Lorenzo Shipping Corporation v. BJ Marthel
This is a case of non-performance of a reciprocal
International
obligation. Barzaga in his end, paid the purchase price in
full therefore Alviar is obligated to fulfill his obligation to Facts:
 BJMI supplied LSC with spare parts for the latter’s  Solar harvest deposited $40,150 in DCC Corporation’s
marine engines. Sometime in 1989 LSC asked for a dollar savings account as full payment.
quotation of various machine parts. Thereafter LSC  Despite such payment, they did not receive any boxes
issued a purchase order for the procurement of one from respondent so they wrote a demand letter for
set of cylinder liner (date of delivery not specified). reimbursement of the amount paid.
 Instead of paying 25% DP for the first cylinder liner,  Respondent replied that the boxes has been
LSC issued 10 PDCs representing the full payment of completed and that petitioner failed to pick them up
the aforementioned cylinder liner. from their warehouse 30 days from completion as
 After, LSC issued another purchase order for another agreed upon. They also claim that petitioner even
unit of cylinder liner. Terms of payment are 25% upon placed an additional order of 24,000 boxes out of
delivery, balance payable in 5 bi-monthly equal which 14,000 had been manufactured without any
installments. It also did not state the date of delivery. advance payment from the Solar Harvest.
 BJMI deposited LSC’s check but the same was  Respondent demanded Solar Harvest to remove the
dishonored due to insufficiency of funds. The boxes from their storage warehouse and to pay the
remaining nine were returned by BJMI to LSC. remaining balance of their orders as well as storage
 The ordered cylinders were delivered to LSC’s fees.
warehouse.
Issue:
 LSC refused to pay full price for the cylinders claiming
that BJMI’s delivery was late and due to the scrapping Whether or not Petitioner is entitled to the claim for
of the MV Dadiangas Express, it would have to sell the rescission he is asking for as per Article 1191 of the civil
cylinder and pay the balance from the proceeds of code.
the sale.
Ruling:
Issue:
No. Under 1191 of the NCC, the power to rescind
Whether or not there was delay in delivery of the subjects obligations is implied in reciprocal ones, in case one of the
of the contract of sale to justify the petitioner to disregard obligors should not comply with what is incumbent upon
the terms of the contract considering that time was of the him. In reciprocal obligations, generally demand is not
essence thereof. necessary but when different dates for performance of
the obligations are fixed, the default for each must be
Ruling:
determined by the demand of other party of the
No. There was no actual or apparent intention in the fulfillment of his obligation. In this case, petitioners sent
contract itself or the surrounding circumstance of that a follow up letter and not a demand letter. Also
intention. There was a significant difference between the respondent showed sufficient proof that it was ready to
purchase orders and the quotations. The omission of the comply with its obligation and that even if parties agreed
delivery dates in the purchase order which was in the for respondent to deliver the boxes, they still wouldn’t be
quotation was the doing of LSC and not BJMI. Also, by in delay since there was no demand from the Solar
accepting the cylinder liners when these were delivered Harvest.
to its warehouse, petitioner indisputably waived the
VII. Cathay Pacific Airways LTD v. Sps. Vazquez
claimed delay in the delivery of said items.
Facts:
VI. Solar Harvest v. Davao Corrugated Carton
Corp.  Sps. Vazquez are gold members of CPA. They
went to HK with some other people.
Facts:
 During their boarding time on the flight back to
 Solar Harvest entered into an agreement with DCC Manila, they were told that they have been
Corporation for the purchase of carton boxes upgraded to first class but they refused citing that
specifically for the business of exporting fresh it would be impolite to accept said offer and leave
bananas. Said agreement was not reduced into their guests.
writing.
 The ground stewardess warned them that they Ruling:
would not be allowed to take the flight if they
YES. Meralco is liable for damages under Article 1170 of
refused.
the NCC which provides, those who in the performance of
 Sps. Vazquez sued for damages
their obligation are guilty of fraud, negligence, or delay,
Issue: and those who in any manner contravene the tenor
thereof, are liable for damages. Meralco is required to
1. Whether or not Sps. Vazquez are entitled to exercise utmost care and diligence being a public utility
damages. vested with vital interest. It is guilty of negligence in
2. Whether or not there was breach of obligation on following the court order of MTC. It could have
the part of Cathay Pacific Airways coordinated with the proper court officials in determining
Ruling: the structures covered by the court order before cutting
power supply of Ramoy.
1. Yes to nominal damages but No to moral
damages. There was no bad faith on the part of IX. Areola v. CA and Prudential Guarantee
the ground stewardess. She was honest in saying Insurance
that their seats were given to other passengers Facts:
and that the business class was fully booked.
2. Yes. Sps. Vazquez should have been consulted  7 months after the issuance of Areola’s personal
first whether they wanted to avail the privilege or accident insurance, respondent insurance company
waive it. They had every right to waive it and it unilaterally cancelled the same since the company
should not be imposed on them no matter how records revealed that petitioner-insured failed to pay
seemingly odd it is to deny the upgrade. By his premiums.
insisting on the upgrade, Cathay breached its  Respondent then offered to reinstate the same policy
contract of carriage with the Vazquezes it previously cancelled and even proposed to extend
its lifetime upon finding that the cancellation was
Note** Breach of contract is failure without legal reason
erroneous and that the premiums were paid full but
to comply with the terms of a contract.
not remitted by the insurance company’s branch
VIII. Meralco v. Ramoy manager.

Facts: Issue:

 The electric service connection of Ramoy and his 1. Did the erroneous act of cancelling subject
wife were disconnected pursuant to a court order insurance policy entitle petitioner to payment of
acquired by NPC for ejectment of settlers damages due to breach of obligation
occupying their property. They sought the help of 2. Did the subsequent act of reinstating the
Meralco in doing this. wrongfully cancelled insurance policy obliterate
 Ramoy reasoned with the Meralco foreman that liability for damages of the insurance company?
he was the registered owners of a parcel of land Ruling:
covered by a TCT and that his property was
outside NPC’s property coverage. Yes. Article 1191 grants the injured party a choice
 During the ocular inspection ordered by the between rescission and fulfillment of the obligation in
court, it was found that Ramoy’s property was case the debtor fails to comply with what is incumbent
indeed outside the property of NPC. upon him. In any case, the payment of damages is proper
regardless whether he chooses fulfillment or rescission.
Issue:
Only nominal damages since no actual or substantial
Whether or not Meralco acted in bad faith in the damage or injury was inflicted on petitioner and the
disconnection of the electric services of Ramoy and his respondent insurance company rectified its error
wife. immediately after its realization of said mistake.
Whether or not Meralco is guilty of breach of contract X. Tanguilig v. Court of Appeals
Facts: Inc. while the plans and specifications for the building
were prepared by Nakpil and Sons
 Tanguilig proposed to Herce to construct a windmill
 On August 2, 1968, a strong earthquake hit Manila
system for him for 60,000 with a one-year guarantee
and its environs and the building in question
from date of completion and acceptance of Herce of
sustained major damages.
the project.
 As a temporary remedial measure, the building was
 Tanguilig paid Herce 30,000 with an installment
shored up by United Construction Inc. for 13,661.28
payment of 15,000 leaving a balance of 15,000
pesos.
 Thereafter, due to refusal and failure of respondent
 The PBA sued United Construction claiming defects in
to pay the balance, Herce filed a complaint to collect
construction while Unite Construction sued Nakpil
the amount
and Sons claiming defects in the design and
 Petitioner denied the claim saying he already paid this
specifications.
amount to SPGMI which constructed the ell to which
the windmill system was to be connected. Further, he Issue:
said that assuming he does have unpaid balance, it
Whether or not the substantial damage of the building
should be offset by defects in the windmill which
was attributable to a fortuitous event.
caused the structure to collapse after a strong wind
hit their place. Ruling:
Issue: No. The facts determined by the lower courts indicate
wanton negligence off both the defendant and the third
Whether or not the claim of respondent of force majeure
party defendants in effecting the plans, designs,
should be appreciated
specifications, and construction of the PBA building. Their
Ruling: negligence is equivalent to bad faith in the performance
of their respective tasks.
No. To invoke fortuitous event, four requisites must
concur: Note** Instances where rule on fortuitous event does not
apply: If upon the happening of a fortuitous event, or an
a) Cause of the breach of the obligation must be
act of God there concurs a corresponding fraud,
independent of the will of the debtor
negligence, delay or contravention in any manner of the
b) The event must be either unforeseeable or
tenor of the obligation.
unavoidable
c) The event must be such as to render it impossible XII. Republic v. Luzon Stevedoring
for the debtor to fulfill his obligation in a normal
Facts:
manner.
d) Debtor must be free from any participation in or  In the early afternoon of August 17, 1960, a barge
aggravation of the injury to the creditor. owned by respondents was being towed down the
Pasig River by tugboats belonging to the same
Herce failed to show that the collapse of the windmill was
corporation.
due solely to a fortuitous event. Interestingly the
 The barge rammed against one of the wooden piles
evidence does not disclose that a typhoon transpired but
of Nagtahan Bailey bridge, smashing the posts and
rather only a strong wind. But a strong wind in this case
causing the bridge to list.
cannot be fortuitous. On the contrary a strong wind
should be present in places where windmills are  The river at the time was swollen due to the heavy
constructed, otherwise the windmills will not turn. downpour recently.
 The Republic is suing Luzon Stevedoring for actual
XI. Nakpil and Sons v. Court of Appeals and consequential damages while LS contends they
exercised due diligence in the selection and
Facts:
supervision of its employees and that the damages to
 The Philippine Bar Association decided to construct the bridge were caused by force majeure.
an office building in Intramuros, Manila, The
Issue:
construction was undertaken by United Construction
Whether or not the collision of the appellant’s barge with XIV. Salugada v. FEU
the supports of the bridge was cause by a fortuitous event
Facts:
Ruling:
 Saludaga was a sophomore law student of
No. fortuitous events are extraordinary events not respondent FEU when he was shot by Rosete, one of
foreseeable or avoidable. Events that could not be the security guards on duty at the school premises.
foreseen or though which foreseen, were inevitable. It is  He was rushed to FEU-NRMF due to the wound he
therefore not enough that the event should not have sustained.
been foreseen or anticipated, as is commonly believed it  Petitioner filed a complaint against respondent
must be one that is impossible to foresee or avoid. Mere school on the grounds of breach of obligation to
difficulty to see the happening is not impossibility to provide students with a safe and secure environment
foresee the same. The very measures adopted by the and an atmosphere conducive to learning.
appellant prove that the possibility of danger is not only  Respondent school filed a third party complaint with
foreseeable but actually foreseen. They should have the Security Agency to indemnify them with whatever
exercised a higher level of care and diligence knowing the would be adjudged in favor of petitioner.
possibility of such event in happening.  Respondent school invoke fortuitous event reasoning
XIII. Far East Bank and Trust Co. v. CA that they could not have reasonably foreseen nor
avoided the accident caused by Rosete since he was
Facts: not their employee.
 Luna applied for and was accorded a FAR EAST CARD Issue:
issued by petitioner bank. He also requested a
Whether or not defense of fortuitous event should be
supplemental card for Clarita Luna
appreciated.
 Clarita lost her card and FEBTC was informed. In order
for it to be replaced Clarita submitted an affidavit of Ruling:
loss.
 Luis Luna’s card was not honored when he tried No. In order for force majeure to be considered,
paying for a despedida lunch for a close friend respondents must show that no negligence or
misconduct was committed that may have occasioned
 Luis Luna sued for damages
the loss. In this case FEU was negligent by not using a
Issue: higher level of scrutiny in checking the qualifications of
the security guards being given to them by the agency.
Whether FEBTC is liable for damages
XV. Fil Estate Properties Inc. v. Sps. Ronquillo
Ruling:
Facts:
No. In culpa contractual, moral damages may be
recovered where the defendant is shown to have acted in  Sps. Ronquillo purchased from petitioners an 82 sqm.
bad faith or with malice in the breach of the contract. The Condo for 5.1 million.
bank was remiss in indeed neglecting to personally inform  Upon learning that the construction works had
Luis of his own card’s cancellation. However, nothing in stopped, respondents likewise stopped paying the
the findings of the trial court and appellate court can monthly amortization. They then demanded full
sufficiently indicate deliberate intent on the part of FEBTC refund which the petitioners refuse to do.
to cause harm to respondent.
Issue:
Nominal Damages may be recovered. Article 2221 of NCC:
Is the breach of obligation due to economic hardships a
“Nominal damages are adjudicated in order that a right fortuitous event?
of the plaintiff which has been violated or invaded by the
defendant may be vindicated or recognized and not for Ruling:
the purpose of indemnifying the plaintiff for any loss No. the Asian financial crisis is not a fortuitous event that
suffered by him” would excuse petitioners from performing their
contractual obligation. Because of the Petitioner’s breach Issue:
they are ordered to refund the amount paid and to
Whether or not the loan obligations incurred by the
rescind the contract.
petitioners under the subject promissory note and
XVI. Metro Concast Steel Corp. v. Allied Bank various trust receipts have already been extinguished due
Corp. to force majeure or fortuitous event.

Facts: Held:

On various dates and for different amounts, Metro No. The loan obligation was not extinguished.
Concast, a corporation duly organized and existing under
Article 1231 of the Civil Code states that obligations are
and by virtue of Philippine laws and engaged in the
extinguished either by payment or performance, the loss
business of manufacturing steel, through its officers
of the thing due, the condonation or remission of the
obtained several loans from Allied Bank. These loan
debt, the confusion or merger of the rights of creditor and
transactions were covered by a promissory note and
debtor, compensation or novation.
separate letters of credit/trust receipts.
In the present case, petitioners argued that their loan
Petitioners failed to settle their obligations under the
obligations to Allied Bank had already been extinguished
aforementioned promissory note and trust receipts,
due to Peakstar’s failure to perform its own obligations to
hence, Allied Bank, through counsel, sent them demand
Metro Concast pursuant to the MoA.
letters,20 all dated December 10, 1998, seeking payment
but to no avail. Thus, Allied Bank was prompted to file a Petitioners classify Peakstar’s default as a form of force
complaint for collection of sum of money against majeure in the sense that they have, beyond their control,
petitioners before the RTC. lost the funds they expected to have received from the
Peakstar which they would, in turn, use to pay their own
The petitioners purported that the economic reverses
loan obligations to Allied Bank.
suffered by the economy and the devaluation of the peso
against the US dollar contributed to the downfall of the While it may be argued that Peakstar’s breach of the MoA
steel industry, directly affecting the business of Metro was unforseen by petitioners, the same us clearly not
Concast and eventually leading to its cessation. “impossible”to foresee or even an event which is
independent of human will.” Neither has it been shown
Petitioners offered the sale of Metro Concast’s remaining
that said occurrence rendered it impossible for
assets, consisting of machineries and equipment, to Allied
petitioners to pay their loan obligations to Allied Bank and
Bank, which the latter refused. Instead, Allied Bank
thus, negates the former’s force majeure theory
advised them to sell the equipment and apply the
altogether.
proceeds of the sale to their outstanding obligations.
Petitioners offered the equipment for sale, but there XVII. Seoane v. Franco
were no takers, and it was reduced into scrap metal.
Facts:
Peakstar Oil Corporation (Peakstar), represented by one
Crisanta Camiling (Camiling), expressed interest in buying  A mortgage was executed on October 13, 1884 to
the scrap metal. A Memorandum of Agreement dated secure the payment of the sum of4876.01, the
November 8, 2002 (MoA) was drawn between Metro mortgagor agreeing to pay the sum little by little
Concast, represented by petitioner Jose Dychiao, and  The claim appears to have been presented to the
Peakstar, through Camiling, under which Peakstar plaintiff’s intestate on August 8, 1911. Nothing has
obligated itself to purchase the scrap metal. been paid either of principal or of interest.

Unfortunately, Peakstar defaulted on all its obligations This is an appeal from a judgment of the Court of First
under the MoA. In this regard, petitioners averred that Instance of Zamboanga in favor of the plaintiff, holding
their failure to pay their outstanding loan obligations to that the right of action upon the mortgage debt which
Allied Bank must be considered as force majeure, and was the basis of the claim presented against the plaintiffs
therefore extinguished. estate had prescribed.
The mortgage in question was executed on the 13th of desired without other formality than that of giving a
October, 1884, to secure the payment of the sum of month's notice. The owners of the land undertake to
P4,876.01, the mortgagor agreeing to pay the sum "little maintain the club as tenant as long as the latter shall see
by little," The claim appears to have been presented to fit."
the plaintiff's intestate on the 8th of August, 1911.
Considering the case the court said (p. 314):
Nothing has been paid either of principal or of interest.
"The Civil Code has made provision for such a case in all
We are of the opinion that this case falls within the
kinds of obligations. In speaking in general of obligations
provisions of article 1128 of the Civil Code, which reads as
with a term it has supplied the deficiency of the former
follows:
law with respect to the 'duration of the term when it has
"1128. When the obligation does not fix a term, but it can been left to the will of the debtor and provides that in this
be inferred from its nature and circumstance that there case the term shall be fixed by the courts. (Art. 1128, sec.
was an intention of granting it to the debtor, the courts 2.) In every contract, as laid down by the authorities,
shall fix the duration of such a term. there is always a creditor who is entitled to demand the
performance, and a debtor upon whom rests the
"The courts shall also fix the duration of a term when it
obligation to perform the undertaking. In bilateral
may have been left at the will of the debtor."
contracts the contracting parties are mutually creditors
The obligation in question seems to leave the duration of and debtors. Thus, in this contract of lease, the lessee is
the period for the payment thereof to the will of the the creditor with respect to the rights enumerated in
debtor. It appears also that it was the intention of the article 1554, and is the debtor with respect to the
instrument to give the debtor time within which to pay obligations imposed by articles 1555 and 1561. The term
the obligation. In such cases this court has held, on within which performance of the latter obligation is due
several occasions, that the obligation is not due and is what has been left to the will of the debtor. This term
payable until an action has been commenced by the it is which must be fixed by the courts,
mortgagee against the mortgagor for the purpose of
"The only action which can be maintained under the
having the court fix the date on and after which the
terms of the contract is that by which it is sought to obtain
instrument shall be payable and the date of maturity is
from the judge the determination of this period, and not
fixed in pursuance thereof. The case of Eleizegui vs. The
the unlawful detainer action which has been brought-an
Manila Lawn Tennis Club (2 Phil Rep., 309), in which the
action which presupposes the expiration of the term and
opinion was written by the Chief Justice of the court, is
makes it the duty of the judge to simply decree an
the leading case upon the subject. In that case the
eviction. To maintain the latter action it is sufficient to
question was over the duration of a lease concerning "a
show the expiration of the term of the contract, whether
piece of land for a fixed consideration and to endure at
conventional or legal; in order to decree the relief to be
the will of the lessee." In discussing the question the court
granted in the former action it is necessary for the judge
said (p. 310):
to look into the character and conditions of the mutual
"With respect to the term of the lease the present undertakings with a view to supplying the lacking element
question has arisen. In its discussion three theories have of a time at which the lease is to expire."
been presented: One which makes the duration depend
The case of Barretto vs. The City of Manila (7 Phil. Rep.,
upon the will of the lessor, who, upon one month's notice
416) dealt with a case where the terms of a donation did
given to the 'lessee, may terminate the lease so
not fix the time of the performance of the condition
stipulated; another which, on the contrary, makes it
placed upon the donation, and the court held that the
dependent upon the will of the lessee, as stipulated; and
period must be determined by the court in a proper
the third, in accordance with which the right is reserved
action in accordance with article 1128 of the Civil Code,
to the court to fix the duration of the term."
saying (p. 420):
The clause on which the case turns is as follows (p. 312):
"The contract having fixed no period in which the
"Mr. Williamson, or whoever may succeed him as condition should be fulfilled, the provisions of article 1128
secretary of the club, may terminate this lease whenever of the Civil Code are applicable and it is the duty of the
court to fix a suitable time for its fulfillment. Eleizegui vs. prosecuted no suit could be brought for the recovery of
The Manila Lawn Tennis Club, 2 Phil. Rep., 309' (11 Phil. the amount named in the instrument. It is, therefore,
Rep., 624.[1]) clear that this action is premature. The instrument has
been sued upon before it is due. The action must
In the case of Levy Hermanos vs. Paterno (18 Phil. Rep.,
accordingly be dismissed.
353) the court said (p. 355):
Ordinarily, when an action of this sort is dismissed the
"The defendant having bound himself to pay his debt to
plaintiff may at once begin his action for the purpose of
the plaintiffs in partial payments, as set forth in the note
fixing a date upon which the instrument shall become
in question, it is seen that the obligation is one of
due. From the undisputed facts in this case and from the
payment by installments, since its fulfillment cannot be
facts and conditions that very probably cannot be
required immediately nor does its existence depend upon
charged hereafter, it is our present opinion that such
the happening of any particular event. But, though the
action is itself prescribed. Section 38 of the Code of Civil
obligation is one of payment by installments,
Procedure reads as follows:
nevertheless no fixed day was specified for its fulfillment,
so that the period for payment is undetermined or was "SEC. 38. To what this chapter does not apply. This
not fixed by the parties when they executed the contract. chapter shall not apply to actions already commenced, or
Besides, it is evident that the term for payment was to cases wherein the right of action has already accrued;
granted for the exclusive benefit of the defendant and for but the statutes in force when the action or right of action
his own convenience, as by the language of the accrued shall be applicable to such cases according to the
document, the plaintiffs gained nothing by the fact that subject of the action and without regard to the form; nor
the debt was not immediately demandable. Nor was any shall this chapter apply in the case of a continuing and
interest stipulated on the debt during the time that it subsisting trust, nor to an action by the vendee of real
should remain unpaid by the defendant. For the property in possession thereof to obtain the conveyance
foregoing reasons, and in whatever manner this case be of it: Provided, nevertheless, That all rights of action
considered, it is unquestionable that it falls within the which have already accrued, except those named in the
provisions of article 1128 of the Civil Code. * * * last preceding paragraph, must be vindicated by the
commencement of an action or proceeding to enforce
"The obligation being manifestly defective with regard to
the same within ten years after this Act comes into
the duration of the period granted to the debtor, that is,
effect."
to the defendant, that defect must be cured by the courts
through judicial decision which shall determine the said This section evidently covers all rights of action of
duration, under the power expressly granted them for whatever kind or nature, except those which have special
such purpose by the legal provisions just above limitations and are referred to in subsequent sections. A
transcribed. right of action to fix a day for the determination of the
time of payment is included within the terms of this
"The trial court, therefore, acted in accordance with the
section. The mortgage in question having left the period
law in exercising the said power in the present case, by
of payment to the will of the mortgagor, an action could
fixing the duration of the period on the basis that the
have been maintained by the mortgagee at any time after
payment of the debt should be made at the rate of P200
its execution for the naming of a date on which the
a month; and we see no abuse of judicial discretion in
instrument must be paid in full. That right of action
fixing such a rate, considering the importance of the
accrued as soon as the instrument was executed. Such
obligation and the absence of any stipulation of interest
action, therefore, falls within the provisions of section 38,
in favor of the creditors."
and not having been, commenced within the ten years
From these decisions it is clear that the instrument sued next following the 1st day of October, 1901, such action
upon in the case at bar is one which leaves the period of cannot, under the facts as they now appear, be
payment at the will of the mortgagor. Such being the maintained.
case, an action should have been brought for the purpose
While the expression of an opinion as to the prescription
of having the court set a date on which the instrument
of the action to fix a date for the maturity of the obligation
should become due and payable. Until such action was
in question is unnecessary for a complete resolution of
the case before us, still we do not hesitate to express that Whether or not carnapping constitute as a fortuitous
opinion for the reasons which we have heretofore given event.
in one or two other cases, particularly that of Lichauco vs.
Ruling:
Limjuco (19 Phil. Rep., 12). That case went off upon the
finding of the court that the action could not be No. carnapping is not a fortuitous event. It must be
maintained by the plaintiff, Lichauco, on behalf of his proved and established that the event was an act of god
brothers and sisters and upon that finding the complaint or was done solely by third persons and that neither
was dismissed. While the merits in that case were not claimant nor the person alleged to be negligent has any
necessarily before us, we nevertheless took up the facts participation.
as they appeared and expressed our opinion of what the
result of the case would be upon the merits if it Even assuming arguendo that carnapping was duly
subsequently came before us upon the same facts. In established as a fortuitous event, still private respondent
that case we said (p. 17): cannot escape liability. Article 1165 of the NCC makes an
obligor who is guilty of delay responsible even for a
"We believe, however, that, for the information of the fortuitous event until he has effected the delivery.
parties interested in the subject matter of this action and
to the end that unnecessary litigation may be avoided, XIX. Sicam v. Jorge
the opinion of the court should be given upon the facts Facts:
presented in this case. Knowing what our opinion is upon
these facts it is probable that the heirs will not care to  Jorge pawned several pieces of jewelry with Sicam to
pursue the litigation further unless, which is somewhat secure a loan of 59,500
unlikely, they are able to present new facts. We,  On October 19, 1987, two armed men entered the
therefore, proceed to a consideration of the case upon pawnshop and took away whatever cash and jewelry
the merits as presented by the record." were found in the pawnshop vault.
 Sicam sent Jorge a informing her of the loss of her
The judgment is affirmed, with costs against the jewelry due to robbery
appellant. So ordered.  Jorge requested Sicam to prepare the pawned
XVIII. Jimmy Co v. Court of Appeals jewelry for withdrawal but Sicam failed to do so.
 Jorge and her husband filed with the RTC a case for
Facts: damages
 Co entrusted his car to BMSC for some repair  Sicam in his defense stated that he exercised due care
including battery replacement with BMSC and diligence in the safekeeping of the articles
undertaking to return the vehicle on July 21, 1990 pledged with it and it could not be made liable for
fully serviced and supplied in accordance with the job event that is fortuitous.
contract. Issue:
 When the due date came, the battery was weak and
not yet replaced so Co had no choice to buy a new Whether or not the robbery that transpired is a fortuitous
battery and deliver it to BMSC for installation on the event.
same day. Ruling:
 The battery was still not installed so it was
rescheduled to July 24, 1990 No. Article 1174 provides: Except in cases by the law or
 When Co arrived on July 24 he was told that it was when it is declared by stipulation, or when the nature of
carnapped on the same day while being road-tested the obligation requires the assumption of risk, no person
an employee of private respondent. shall be responsible for those events which not be
 Petitioner filed a suit for damages against private foreseen or which though foreseen were inevitable.
respondent. The RTC found for the petitioner while Fortuitous events must be one that is impossible to
upon appeal the CA found for the respondent on the foresee or to avoid. The mere difficulty to foresee the
ground of fortuitous event. happening is not impossibility to foresee the same. The
Issue: testimony of Sicam of the measures he adopted to safe
keep those that are pawned in his shop shows that the  He then filed a request for relief from money
possibility of robbery was not only foreseeable but accountability under section 638 of the Revised
actually foreseen and anticipated. Furthermore there was Administration Code.
negligence on Sicam’s part.  The Chairman of COA denied the petitioner’s request.
XX. Austria v. CA (1971) Issue:
Facts: Whether or not petitioner should be absolved of money
accountability.
 Abad received from Austria a pendant with diamonds
to be sold on commission basis or to be returned on Ruling:
demand.
Yes. Applying the letter and spirit of the above-mentioned
 Abad while walking home, her purse was snatched by
laws and after considering the established facts in light of
two men among those taken was the consigned
the arguments of the parties, the court inclined in favor
pendant.
of the petitioner.
 Austria sued for damages while Abad interposed the
defense of fortuitous event. XXII. Yobido v. CA
Issue: Facts:
Whether or not the defense of fortuitous should be  The Tumboy family boarded a Yobido bus bound for
appreciated. Davao City.
 While in transit, the front tire of the bus exploded and
Ruling:
the bus fell into a ravine and struck a tree which
No. Abad was negligent. The requisites of a fortuitous caused the death of Tito Tumboy and physical injuries
event are as follows. to other passengers.
 Leny Tumboy filed a complaint for breach of contract
a) The event must be independent of the human
of carriage against the owner of the bus company and
will
its driver.
b) The occurrence must render it impossible for the
debtor to fulfill the obligation in a normal manner Issue:
c) The obligor must be free of participation in or
aggravation of the injury to the creditor. Is the tire explosion a fortuitous event?

**Abad’s negligence aggravated the injury to the Ruling:


creditor. No. it is settled that an accident caused either by defects
XXI. Hernandez v. Chairman of COA in the automobile or through the negligence of its driver
is not a fortuitous event that would exempt the carrier
Facts: from liability for damages.
 Hernandez is the officer in charge of the Ternate When a passenger dies while travelling, the carrier is
Beach Project of the Philippine Tourism Authority in presumed to have been at fault or acted negligently. It
Cavite. may only be overcome by evidence that the carrier had
 He went to the main office in Manila to encash two observed extraordinary diligence as prescribed by 1733,
checks covering the wages of the employes and the 1755 and 1756 or that the death was due to a fortuitous
operating expense of the project but it was delayed event.
and so it was released on the same day at night.
XXIII. Juntilla v. Fontanar
 He took the cash with him home in Marilao Bulacan
but while in transit. The bus he was riding was robbed Facts:
and the money with him was stolen.
 Juntilla was a passenger of a PUJ from Danao City to
Cebu City
 When the jeepney reached Mandaue city the right • Criminal complaint for Reckless Imprudence Resulting
rear tire exploded causing the vehicle to turn turtle. to Damage in Property was filed against petitioner
In the process, Junitlla who was in the front seat was Pascual. On the other hand, petitioner-corporation was
thrown out of the vehicle. asked to pay the amount of P7,992,350, inclusive of the
 He sustained injuries and lost his watch. value of the commercial building

Issue: • Respondents later on filed a civil complaint based on


quasi-delict against petitioners for a sum of money and
Whether or not the explosion of the tire was a fortuitous damages, alleging that Pascual acted with gross
event. negligence while petitioner-corporation lacked the
Ruling: required diligence in the selection and supervision of
Pascual as its employee
No. The cause of the unforeseen and unexpected
occurrence was not independent of the human will. The • The court a quo declared that, although the
accident was cause either through negligence of the respondents failed to prove the precise cause of the fire
driver or because of mechanical defects in the tire. that engulfed the garage, Pascual was nevertheless
negligent based on the doctrine of res ipsa loquitur.
XXIV. Perla Compania de Seguros v. Sarangay
Issue: WON the court erred in applying the doctrine of
FACTS: RES IPSA LOQUITOR
• Respondent spouses Gaudencio Sarangaya III and Held:
Primitiva Sarangaya erected a semi-concrete, semi-narra,
one-storey commercial building, subdivided into three • To sustain the allegation of negligence based on the
doors, each of which was leased out. doctrine of res ipsa loquitur, the following requisites must
concur:
• Perla Compania de Seguros, Inc. leased the first door
renovated its rented space and divided it into two, left 1) The accident is of a kind which does not ordinarily
side as an office while the right was used by Pascual as a occur unless someone is negligent;
garage. 2) The cause of the injury was under the exclusive control
• On July 7, 1988, after checking his appointments the of the person in charge and
next day, decided to warm up the car. When he pulled up 3) The injury suffered must not have been due to any
the handbrake and switched on the ignition key, the voluntary action or contribution on the part of the person
engine made an odd sound and did not start. injured.
• Thinking it was just the gasoline percolating into the • Under the first requisite, the occurrence must be one
engine, he again stepped on the accelerator and started that does not ordinarily occur unless there is negligence.
the car. This revved the engine but petitioner again heard Flames spewing out of a car engine, when it is switched
an unusual sound. He then saw a small flame coming out on, is obviously not a normal event. Neither does an
of the engine. explosion usually occur when a car engine is revved.
• Startled, he turned it off, alighted from the vehicle and Hence, in this case, without any direct evidence as to the
started to push it out of the garage when suddenly, fire cause of the accident, the doctrine of res ipsa loquitur
spewed out of its rear compartment and engulfed the comes into play. Under the second requisite, the
whole garage. Pascual was trapped inside and suffered instrumentality or agency that triggered the occurrence
burns on his face, legs and arms. must be one that falls under the exclusive control of the
person in charge thereof. In this case, the car where the
• Meanwhile, respondents were busy watching television fire originated was under the control of Pascual. Under
when they heard two loud explosions and, in no time, fire the third requisite, there is nothing in the records to show
spread inside their house, destroying all their belongings, that respondents contributed to the incident
furniture and appliances.
• The relationship between the two petitioners was based
on the principle of pater familias according to which the
employer becomes liable to the party aggrieved by its XXV. Fil-Estate Properties v. Go
employee if he fails to prove due diligence of a good
Facts
father of a family in the selection and supervision of his
employees. The burden of proof that such diligence was Fil-Estate Properties, Inc. (petitioner) entered into a
observed devolves on the employer who formulated the contract to sell a condominium unit to respondent
rules and procedures for the selection and hiring of his spouses Gonzalo and Consuelo Go at “Eight Sto. Domingo
employees. In the selection of prospective employees, Place,” a condominium project of petitioner located on
employers are required to examine them as to their Sto. Domingo Avenue, Quezon City on December 29,
qualifications, experience and service records. While the 1995. The spouses paid a total of P3,439,000.07 of the
petitioner-corporation does not appear to have erred in full contract price set at P3,620,000.00.
considering Pascual for his position, its lack of supervision
over him made it jointly and solidarily liable for the fire. Petitioner failed to develop the condominium project so
on August 4, 1999, the spouses demanded the refund of
When there is caso fortuito: the amount they paid, plus interest. When petitioner did
not refund the spouses, the latter filed a complaint
(a) The cause of the unforeseen and unexpected
against petitioner for reimbursement of P3,620,000
occurrence was independent of the human will
representing the lump sum price of the condominium
human agency must be entirely excluded as the unit, plus interest,P100,000 attorney’s fees, and expenses
proximate cause or contributory cause of the injury or of litigation before the Housing and Land Use Regulatory
loss -Not because car not maintained Board (HLURB). In response, petitioner claimed that
respondents had no cause of action since the delay in the
(b) It was impossible to foresee the event which
construction of the condominium was caused by the
constituted the caso fortuito or, if it could be foreseen, it
financial crisis that hit the Asian region, a fortuitous event
was impossible to avoid - NOT under the control of
over which petitioner had no control. The HLURB Regional
Pascual
Director approved the decision of the Housing and Land
(c) The occurrence must be such as to render it impossible Use Arbiter in favor of the spouses Go on July 18, 2000
to perform an obligation in a normal manner - Spouses ordering the petitioner to refund to the complainants,
had no access nor obligation for the maintenance P3,439,000.07 (the amount proved) plus 12% interest
thereon reckoned from 09 August 1999 (the date the
(d) The person tasked to perform the obligation must not respondent received the demand letter) until the same is
have participated in any course of conduct that fully paid and pay P25,000.00 attorney’s fees as and by
aggravated the accident way of damages.
2. YES. The Board of Commissioners of the HLURB denied
Perla did not include any rule or regulation that Pascual petitioner’s petition for review and consequent motion
should have observed in performing his functions for reconsideration. The Office of the President dismissed
petitioner’s appeal and denied its motion for
There was no guidelines for the maintenance and upkeep reconsideration.
of company property like the vehicle that caught fire
On appeal, asserting that both the HLURB and the Office
Did not require periodic reports on or inventories of its of the President committed reversible errors, Fil-Estate
properties asked the Court of Appeals to set aside the orders it is
Article 2180 of the Civil Code states that employers shall appealing. The Court of Appeals affirmed the actions
be liable for the damage caused by their employees. The taken by the HLURB and the Office of the President and
liability is imposed on all those who by their industry, denied petitioner’s motion for reconsideration.
profession or other enterprise have other persons in their Issue
service or supervision
Whether or not the financial crisis that hit the Asian
Nowhere does it state that the liability is limited to region is considered a fortuitous event which caused the
employers in the transportation business.
delay in fulfilling the petitioner’s obligation to the
respondent.

Held

The Court had said that the 1997 financial crisis that
ensued in Asia did not constitute a valid justification to
renege on obligations and that is not among the
fortuitous events contemplated under Article 1174 of the
Civil Code. The Court does not generalize that the Asian
financial crisis in 1997 was unforeseeable and beyond the
control of a business corporation. However, a real estate
enterprise engaged in the pre-selling of condominium
units is concededly a master in projections on
commodities and currency movements and business
risks. The fluctuating movement of the Philippine peso in
the foreign exchange market is an everyday occurrence,
and fluctuations in currency exchange rates happen
everyday, thus, not an instance of caso fortuito. Following
Article 1475 of the Civil Code, upon perfection of the
contract, the parties, may demand performance. And
under Article 1191 of the same code, should one of the
parties, in this instance Fil-Estate, fail to comply with the
obligation, the aggrieved party may choose between
fulfillment or rescission of the obligation, with damages in
either case. Inasmuch as Fil-Estate could no longer fulfill
its obligation, the spouses Go may ask for rescission of the
contract with damages.

The Court DENIED the petition for lack of merit and ruled
to award only P3,439,000.07, representing the sum of
their actual payments plus amortization interests and
interest at legal rate which is 6% per annum from the date
of demand on August 4, 1999 and conformed with the
ruling in Eastern Shipping Lines, Inc. v. Court of Appeals,
the award of 12% interest on the amount of refund must
be reduced to 6%. Also the Court modified the Court of
Appeals’ grant of attorney’s fees from P25,000 to
P100,000 as just and equitable since respondents were
compelled to secure the services of counsel over eight
years to protect their interest due to petitioner’s delay in
the performance of their clear obligation. Costs against
petitioner.

Das könnte Ihnen auch gefallen