Sie sind auf Seite 1von 105

Name of Work: Urgent Maintenance and Special repairs for a period of One

Year of Chandikhole – Paradip Stretch (Km.0.000 to Km.76.588) Section of NH –


5A (New NH53) in the State of Odisha

ABSTRACT

BILL NO. DESCRIPTION AMOUNT

BILL NO. 1 ROAD MAINTENANCE 191979872


ROAD PROPERTY MANAGEMENT AND
BILL NO. 2 60438896
OTHER MAINTENANCE
RENEWAL AND ENGINEERING
Bill No. 3
IMPROVEMENT
78726659

BILL NO. 4 INCIDENT MANAGEMENT 9203152


BILL NO. 5 MISCELLANEOUS 2522181
TOTAL Rs 342870759

Project Director
PIU- Bhubaneswar
National Highways Authority Of India Cost Estimate Page 1 of 10

Summary Of Cost Estimate


BILL NO-1 (ROAD MAINTENANCE)
Item Estimated
Description of Items Unit Rate Amount
No. Quantity
Blading/grading the unpaved shoulder and slopes using
motor grader/power roller/plate compactor at the required
1.01 camber as directed by the Engineer in charge conforming to Sqm 45,934.80 9 413,413.20
Technical Specification clause no. 3003. The work also
includes disposal of surplus materials.
Providing spot reconditioning, reconstruction and regravelling
to repair specific erosion or other damages for restoring the
1.02 eroded area to originally constructed cross section on cuts Cum 2,296.74 445 1,021,860.66
and fills slopes/shoulders conforming to Technical
Specification claus
Providing repair to grouted stone pitching with 1:3 cement
sand mortar over the already prepared surface/slopes of
1.03 guide bunds, rivers training works, and road embankments
as per MORTH section 2500 complete in all respect as
directed by Engineer.
(a) Using Boulders available at site Cum 25.00 133 3,325.00
(b) Using Procured material(Granite) Cum 10.00 895 8,950.00
Clearing, cleaning, depending and reshaping of road site
unlined/kaccha drains and making shallow kaccha lateral
1.04 drains on shoulders wherever required, including removal
and disposal of sediments, extraneous debris and vegetation
growth blocking the free
(a) Drains having depth upto 0.6 meter Rm 96,000 11 1,056,000.00
(b) Drais having depth more than 0.6 meter Rm 8000.00 23 185,648.28
Cleaning road side/Median open lined/puca drains to bring
them to original shape, drainage capacity including disposal
1.05 of sediments, extraneous debaris & vegetation growth
blocking the free flow from site out side ROW with all leads
and lifts complete in
(a) Drains having cross sectional area upto 0.3 Sqm Rm 5000 14 69,193.28

(b) Drains having cross sectional area more than upto 0.3 Sqm Rm 6000 38 229,672.52
Clearing, longitudinal and transverse covered drains and pipe
drains including manholes, gratings, channels and gullies etc.
1.06 & bringing them to original drainage capacity, including Rm 1600.00 150 240,000.00
disposal of sediments, extraneous debaris & vegetation
growth blocking th
Clearing slab/box type culverts and pipe culverts including
clearing, cleaning and reshaping of upstream and down
1.07 stream faces of these culverts with in right way. The job also
includes disposal of excess material recovered from site
including vegetation
(a) Slab/Box type Culverts No. 46.00 910 41,860.00
(b) Pipe Culverts No. 28.00 644 18,032.00
Carrying out proper cleaning of carriageways, footpaths,
verges, expansion joints (for free movement), drainage Rmtr of
1.08 spouts of bridge including removal and disposal of trash, Bridge 13600.00 173 2,352,800.00
plastic, vegetation etc. from site out side ROW complete as
per direction of Engineer
Loading, unloading, transportation & disposal of surplus
material left over by accidental vehicle or otherwise lying on
1.09 Cum 720.00 88 63,100.42
road (on carriageway) with all lead & lifts complete as
directed by Engineer in Charge.
Carrying out proper cleaning and removing of
dust/silt/thrash/plastic/rubbish/garbage/waste from the
1.10 carriageway, footpaths, verges(excluding the verges of
central median) by mechanical means and from shoulders
upto Toe line of the embackment including si

(a) Urban area (Frequency of cleaning to One time in a month) Per Km 96.00 7346.00 705,216.00

(b) Rural area (Frequency of cleaning will be quarterly). Per Km 274.23 7346.00 2,014,508.27
Removal of rank vegetation/weeds and undesirable
vegetation from shoulders, embankment slopes upto ROW
1.11 (both side) complete in all respect including breaking of
colds, rough dressing disposal of waste material and
vegetation at a place outside ROW as per
National Highways Authority Of India Cost Estimate Page 2 of 10

Item Estimated
Description of Items Unit Rate Amount
No. Quantity
Shoulders including side slopes of embankment up to toe line
on both side of the carriageway. (Frequency of cleaning will
(a) Sqm. 456176.00 5.00 2,280,880.00
be four times in year however limited to only areas prone to
growth of rank/undesirable vegetation and weeds).

From Toe line of embankment slopes to ROW on both sides


of the carriageway(Frequency of cleaning will be two times in
(b) Sqm. 173120.00 5.00 865,600.00
a year however limited to only areas prone to growth of
rank/undesirable vegetation and weeds.

Providing localized repair to rutted portion or bituminous


surface at scattered location by applying tack coat as per
technical specification Clause 503 and then filling the
1.12 Cum 14.38 9324.00 134,124.69
depression with bituminous concrete by using paving grade
bitumen conforming to technical specification clause no. 509,
complete in all respect as directed by the Engineer.
Providing localized repair to broken edges of carriageway at
scattered location by applying tack coat as per technical
1.13 specification Clause 503 and then repairing the broken edges Cum 0.00 9324.00 -
with bituminous concrete by using paving grade bitumen
conforming to techn
Providing sealing to closely spreader cracks at scattered
location after sweeping the surface clean and dry, applying
1.14 tack coat of emulsified bitumen @ 0.15 ltr/sqm followed by Sqm 0.00 72.00 -
distributing slurry evenly in 5mm thickness prepared by
mixing emulsified bit
Providing and applying low viscosity bitumen emulsion for
sealing cracks less then 3mm wide or incipient fretting or
1.15 disintegration in an existing bituminous surfacing complete as Sqm 0.00 27.00 -
per MORTH specification Section 518 and as per direction of
the Engineer in
Providing sealing cracks wider then 3mm using slow curing
bitumen emulsen @ 0.66 kg per 10 mtrs of the cracks and
1.16 Rmt 0.00 3.00 -
stone crusher screening @ 0.0004 cum/10 mtrs complete as
per direction of the engineer incharge.
Providing treatment to bleeding bituminous surface by
uniform spreading of crusher screening/other fine graded
1.17 material @ 2.5 Kg per Sqm, properly rolled as per clause Sqm 0.00 71.00 -
3004.4 of Technical Specification complete in all respect and
as p[er direction of Engi
Providing treatment and repair to pot holes/patch repair of all
1.18 types of bitumen pavement complete as per technical
specification clause 3004.2,and as per direction of Engineer.
Carrying out patch repair with bituminous concrete up to 25
mm thickness after removal of all failed material, trimming of
(a) completed excavation to provide firm vertical faces, cleaning Sqm 0.00 154.00 -
of surface, painting of tack coat on the sides & base of
excavation as
Carrying out patch repair with bituminous concrete up to 40
mm thickness after removal of all failed material, trimming of
(b) completed excavation to provide firm vertical faces, cleaning Sqm 0.00 379.00 -
of surface, painting of tack coat on the sides & base of
excavation as
Filling potholes and patch repair beyond 40 mm thickness
after removal of all failed material, trimming of completed
(c) excavation to provide firm vertical faces cleaning of surface, Sqm 0.00 816.00 -
painting of tack coat on the sides & base of excavation as
per clause no. 5
Cement concrete of specified mix as under with stone
aggregates 20mm nominal size mechanically mixed and
1.19 vibrated in foundation, sub-structure and superstructure
including shuttering/ form work conforming to MORTH
specification Clause no. 1000, 1500 & 1700
(a) Cement concrete M 15 grade Cum 68.00 4852.00 329,936.00
(b) Cement concrete M 20 grade Cum 87.00 5341.00 464,667.00
National Highways Authority Of India Cost Estimate Page 3 of 10

Item Estimated
Description of Items Unit Rate Amount
No. Quantity
Reinforced Cement concrete of specified mix as under with
stone aggregates 20 mm nominal size mechanically mixed
1.20 and vibrated in foundation, substructure and superstructure
for thin as well as thick section including shuttering/formwork
conforming to MORTH
(a) M 20 Grade Cum 36.48 5341.00 194,839.68
(b) M 25 Grade Cum 41.00 5708.00 234,028.00
(c) M 30 Grade Cum 26.00 6650.00 172,900.00
Providing and fixing position HYSD reinforcement in
abutment, pier, superstructure, crash barrier and in other
1.21 MT 2.00 72877.00 145,754.00
structure complete as per technical specification Section
1600 and as directed by the Engineer.
Dismantling structure and pavement including disposal of
1.22 resultant materials and salvaging the useful material -
complete in all respect as per direction of the Engineer.
a) Plain concrete Cum 25.00 352.00 8,800.00
RCC including clearing, straightening and cutting of bars and
(b) Cum 20.00 616.00 12,320.00
separating out of RCC
Dismantling of road including wearing courses, base
courses, and sub base courses including stacking of old
1.23
serviceable material complete in all respect as per direction
of Engineer.
Dismantling of bituminous wearing courses, including
(a) disposal of the waste material out side ROW as per direction Cum 96.00 548.00 52,608.00
of Engineer.
Dismantling of base courses, including stacking of useful
(b) material at proper location and disposal of unserviceable Cum 87.00 548.00 47,676.00
material out side ROW as per direction of Engineer.

Dismantling of sub base courses, including stacking of useful


(c) material at proper location and disposal of unserviceable Cum 85.00 391.00 33,235.00
material out side ROW as per direction of Engineer.

Earthwork in excavation necessary for construction of


roadway / structures including all leads and lifts completes as
1.24
per Technical specification clause 301 and 304 duly watered,
rolled & compacted as per direction of Engineer in charge.

(a) All type of soil Cum 67.00 152.00 10,184.00

Construction of embankment with approved borrow material


brought from location out side ROW with all leads and lifts
1.25 Cum 65.00 296.00 19,240.00
complete in all respect as per Technical specification clause
no. 305 duly watered, rolled & compacted.
Construction of embankment with suitable material obtained
from roadway, drainage excavation, and pavement
1.26 dismantling etc, with all leads and lifts complete in all respect Cum 41.00 96.00 3,936.00
as per Technical specification clause no. 305 duly watered,
rolled & compacted.
Scarifying existing road surface including bitumenous surface
complete as per Technical Specification clause no. 501,
1.27 including disposal of unserviceable material out side ROW Sqm 1110.09 3.00 3,330.27
with all leads and lifts complete in all respect as pe direction
of Engineer-In
Construction of sub grade and earthen shoulders with
approved material satisfying the requirement of minimum
1.28 soaked CBR value brought from borrow areas located Cum 17.23 306.00 5,271.02
outside ROW with all leads and lifts transporting to site,
laying and compacting as per Technic

Providing, Laying and compacting granular sub base (GSB)


with approved materials complete as per Technical
1.29 Cum 13006.50 1939.00 25,219,603.50
specification clause 401 conforming to grade I Table
400.1/400.2 as per approval of Engineer in charge.

Providing, Laying and compacting wet mix macadam (WMM)


1.30 base course with approved materials complete as per Cum 12292.38 2503.00 30,767,814.63
Technical specification Clause no. 406 of MORTH.
Providing, Laying and compacting dense graded bituminous
macadam complete as per Technical specification Clause
1.31 Cum 3661.88 8489.00 31,085,656.88
no. 507. Including tack coat as per Technical specification
Clause no. 503.
Providing, Laying and compacting bituminous concrete as
1.32 per Technical specification clause 509. Including tack coat as
per Technical specification Clause no. 503.
(a) Using paving grade bitumen 60/70 Cum 7997.50 9223.00 73,760,942.50

Providing, Laying and compacting bituminous concrete as


(b) per Technical specification clause 509. Including tack coat as Cum 970.20 9223.00 8,948,154.60
per Technical specification Clause no. 503. (for service road)
Providing,laying bituminous primer coat over granular
surface with bituminous emulsion complete as per Technical
1.33 Sqm 48825.00 23.00 1,122,975.00
specification Clause no 502@7.5 kg/10sqm and as per
direction of Engineer.
National Highways Authority Of India Cost Estimate Page 4 of 10

Item Estimated
Description of Items Unit Rate Amount
No. Quantity
Providing and applying tack coat with bitumen emulsion using
emulsion pressure distributir at the rate of 0.20 Kg per Sqm
1.34 Sqm 199937.50 8.00 1,599,500.00
on the prepared bituminous/granular surface cleaned with
mechnical as per technical specification 503.

Sealing of crack/porous concrete with Epoxy grout by


1.35 injection through nipples complete as per Clause 2803 of Sqm 145.00 2728.00 395,560.00
Technical specification and as per approval of Engineer.
Applying Epoxy motar over leached honey combed and
spalled concrete surface and exposed steel reinforcement
1.36 Sqm 69.00 349.00 24,081.00
complete as per Technical specification Clause no. 2804 and
as per approval of Engineer.
Cement Pointing of any design/repair to existing pointing,
with cement motar 1:3 on all types of masonry work
1.37 Sqm 280.00 45.00 12,600.00
excluding stone masonary in superstructure/ substructure as
per MORTH specification clause no. 1000 & 1300 .
Cement Pointing of any design/repair to existing pointing,
with cement motar 1:3 on stone masonary work in
1.38 Sqm 185.00 59.00 10,915.00
superstructure/ substructure as per MORTH specification
clause no. 1000 & 1300.
Cement plaster/ repair to cement plaster in thickness 12-20
mm in cement motar 1:4 on all types of masonary work in
1.39 Sqm 250.00 62.00 15,500.00
superstructure/ substructure at any height as per MORTH
clause no. 1000 , 1300 & 1400.
Repair of all types of damaged stone/ brick masonry work in
superstructure and substructure of bridges/ CD works
1.40
including dismantling of damaged portion and reconstructing
to match with existing pattern without causing any damage to
(a) Stone Masonary work in cement morter 1:3 for substructure Cum 1270.00 2244.00 2,849,880.00

(b) Repair ro the all types of damged stone/brick masonry work Cum 132.00 3574.00 471,768.00
Construction of Footpaths/ separators/ traffic Islands by
Providing 150 mm thick compacted GSB as per MORTH
Section 401 & 25 mm thick cement concrete grade M-15
1.41 base over laid with 25 mm thick M-20 precast cement Sqm 1360.00 1046.00 1,422,560.00
concrete chequred titles in cement mortar 1:3 cement sand
mortar. The joint of the tiles to be bonded & finished with neat
cement slurry etc.complite in all respect.
Replacement of damaged cement concrete chequred tiles
with new 25mm thick M-20 precast cement concrete
1.42 chequrred tiles on the already prepared/existing base with Sqm 68.00 301.00 20,468.00
1:3 cement sand mortar. The joint of the tiles to be bonded &
finished with neat cement slurry
Dismantling of existing damaged Expansion joints and
providing and fixing of a new strip seal expansion joint
1.43 catering to maximum horizontal movement up to 70 mm Rmt 55.30 14629.00 808,983.70
complete and to be installed by the
manufacture/supplier/their authorised representative complite
as per engineer in charge.
Sub Total 191,979,872

Summary Of Cost Estimate


National Highways Authority Of India Cost Estimate Page 5 of 10

Item Estimated
Description of Items Unit Rate Amount
No. Quantity

BILL NO -2 (ROAD PROPERTY MANAGEMENT AND OTHER MAINTENANCE

Providing, planting healthy/ well-developed spalling of


ornamental/flowering shrubs of specified species and
2.01 varieties, 1-2 years of age in 25cm-30cm poly bags or pots, No. 1100.00 62 68,200.00
height and spread 0.60mt-0.90mt above ground, with 3-4
branches, in well prepared pits
Maintenance of new plants(item no-2.01) by basin
making,weeding,hoeling,cleaning,levelling,and dressing of
2.02 median,uprooting,and removal of weeds,cuting
grass,disposal of all muck outside ROW regularly to keep the
median clean and plantation.
Watering of each plant as and when required depending
upon the climatic conditions of the locality/region/season/
(a) strictly as per direction of engineer in charge.Km length of
maintenance will be decided considering density of plants as
666 per km.actually
Application of FYM or Sludge @ 1/2 cuft or 10 kg/Plant two
times a year during February / March and October / No 1100.00 24 26,400.00
(b)
November plus 20 grams of NPK(12:32:16) or bonemeal per
plants two times a year as detailed above.
Application of insecticide / pesticide / fungicide etc. for
(c) control of insect’s pests and diseases as and when required
as per direction of Engineer.
Trimming and pruning of all shrubs / plants as and when
(d)
required to give them required shape, size and spread.
Replacement of deed , damaged plants from the median by
healthy & well developed plant of similar species, varieties,
(e)
age and size etc. within 10 days of occurrence of causality as
noticed/ reported or as directed by the Engineer.
Maintenance of median and the exiting plants in it (with a
density of 666 plants per km.) by basin making, weding-
2.03 holeing, cleaning, leveling and dressing of median, uprooting
and removal of weeds, cutting grass, disposal of all muck
outside ROW regularly
Watering of each plant as and when required depending
upon the climatic conditions of the locality/region/season/
(a) strictly as per direction of engineer in charge.Km length of
maintenance will be decided considering density of plants as
666 per km.actually
Application of FYM or Sludge @ 1/2 cuft or 10 kg/Plant two
times a year during February / March and October / Km/mont 756.76 15006 11,355,891.89
(b) h
November plus 20 grams of NPK(12:32:16) or bonemeal per
plants two times a year as detailed above.
Application of insecticide / pesticide / fungicide etc. for
(c) control of insect’s pests and diseases as and when required
as per direction of Engineer.
Trimming and pruning of all shrubs / plants as and when
(d)
required to give them required shape, size and spread.

Replacement of deed , damaged plants from the median by


healthy & well developed plant of similar species, varieties,
(e)
age and size etc. within 10 days of occurrence of causality as
noticed/ reported or as directed by the Engineer.
Supplying and turfing with live and perennial turf forming
grass on embankment slopes, verges, medians and other
2.04 location confirming to Technical specification Clause 307 Sqm. 225.00 34 7,650.00
including watering and maintaining for entire contract period
with periodical mowing
White wash / cement paint/ snowcem in two or more coats to
give an even shade and smooth surface for protection of
2.05 exposed concrete/ masonry portion of bridges/ CD works,
kerb and wheel guard including scraping of damage paint
from old surface and repairi
(a) White washing two coats on existing surface Sqm 10000.00 8 80,000.00
Finishing walls with exterior decorative cement based paint
such as snowcern on old work , two coats to give an even
(b) Sqm 0.00 35 -
shade after repairing of defects so as to achieve smooth and
defects free surface.
National Highways Authority Of India Cost Estimate Page 6 of 10

Item Estimated
Description of Items Unit Rate Amount
No. Quantity
Painting with higloss synthetic enamel paint two coats to give
an even and smooth surface for protection of exposed
2.06 concrete/ masonry portion of Bridges/CD works/ parapet,
kerb painting and repairing wherever necessary, complete as
per approval of Enginee
(a) Old existing surface Sqm 124000.00 52 6,448,000.00
New surface after applying priming coat with cement primer
(b) Sqm 0.00 64 -
(two coats) of approved quality.
Painting all types of M.S/GI railing as when required with two
coats of synthetic enamel paint of approved brand after
2.07
cleaning the surface complete in all respect as directed by
the Engineer.
Per rmt
of Full
(a) On existing Railing. 3600.00 45 162,000.00
height of
railing
Per rmt
On new surface after applying two coat of metallic primer of of Full
(b) 3200.00 81 259,200.00
approved quality and make. height of
railing
Paining two coats of ready mixed paint of approved brand as
2.08 steel structure to give an even shade and smooth surface as
per direction of engineer in charge.
(a) On existing surface. Sqm 0.00 45 -
On new surface after applying two coat of metallic primer of
(b) Sqm 0.00 81 -
approved quality and make.
Cleaning, removing, clearing of dust dirt from the existing
2.09 metal crash barrier and pedestrian guard rail by washing with
water & detergent etc. complete as directed by Engineer.

(a) MBCB Rm 10000.00 5 50,000.00

Carrying out routine maintenance to all types of road signs


2.10 complete as directed by the Engineer and as per Additional
Maintenance standard clause 5.5.3 the bid document.

(a) Road sign Boards mounted on single post. No. 52.00 33 1,716.00
(b) Road sign Boards mounted on double post. No. 18.00 50 900.00
(c) Overhead gantry road sign boards. No. 3.00 837 2,511.00
Carrying out of repair signs including strengthing resetting or
otherwise repairing signs made out of Retro Reflective sheet,
2.11 job includes patch repair to aluminum sheet, posts, signs/
script and repainting of posts at damaged location / position
with app
(a) Road sign Boards mounted on single post. No. 62.00 399.00 24,738.00
(b) Road sign Boards mounted on double post. No. 27.00 682.00 18,414.00
Painting two coats on old surface after miner repairs to give
an even and smooth surface and printing letters and figures
2.12 with first quality synthetic enamel paint of approved brand
and manufacture complete in all respect confirming to
respective IRC spec
(a) Hectometer stones No 25.00 19.00 475.00
(b) Kilometer stones No 130.00 43.00 5,590.00
(c) 5th Kilometer stones No 15.00 89.00 1,335.00
(d) Boundary Stones No 82.00 22.00 1,804.00
Providing and fixing reinforced cement concrete M-15 grade
5th kilometer stones, kilometer stones and hectometer
2.13 stones of standard design as per IRC-8-1980 & MORTH
specification clause 804 including two coat painting with
synthetic enamel paint after app
(a) Hectometer stones No 60.00 367.00 22,020.00
(b) Kilometer stones No 54.00 1440.00 77,760.00
(c) 5th Kilometer stones No 6.00 2346.00 14,076.00

Paining two coats with first quality enamel paint of approved


2.14 make & quality to give an even shade including writing, letter
7 figure etc. Complete in all respect as per IRC standard.

(a) Printing letters of CD nos No 50.00 7.00 350.00


Strengthening and repairing of partiality damaged M.S
pedestrian Railing/pipe railing complete including welding,
2.15 repairing/replacement of damaged parts/ portions (salvage Per Rmt. 6000.00 2781 16,683,714.95
material will be contractors property ) as per existing pattern
complete in all res
Replacement of damaged single faced W-beam metal crash
barrier made out of members.Job includes repair of old
2.16 damaged member by strengthening the member and
removing and repairing all the existing dents as well as other
defects and neatly refixing the repaired
Beam made out of cold rolled steel strip W profile of 3 mm
thick having a minimum of yield strength 2400 kg/sqcm
(a) Rmt 6000.00 660.00 3,960,000.00
having width of 313 mm and depth of corrugation as 83mm
hot dip galvanised of zinc coating @550gm/sqm
National Highways Authority Of India Cost Estimate Page 7 of 10

Item Estimated
Description of Items Unit Rate Amount
No. Quantity
Post consisting of colled rolled channel 150x75x5 mm having
minimum yield strength of 2400 kg/sqcm.The total lengyh of
(b) post shal be 1900 mm and minimum height of post above M No 3000.00 1944.00 5,832,000.00
20 concrete foundation shall be 800 mm hot dip galvanized
of zinc coating of 55
Space chanels or brackets made out of CRP steel channel
section 150x75x5 mm having an yield strength of
(c) No 3000.00 490.00 1,470,000.00
2400kg/sqcm .The length of spacer channel shall be 330 mm
and hot dip galvanised having zinc coating @550gm/sqm.
Fasteners button head bolts 16x40 mm long with nut and
(d) No 6000.00 17.00 102,000.00
washer hot dipped galvanized.
Replacing damaged / broken railing with new precast / cast
in situ, concrete railing to match with existing design and
2.17 pattern , made out of cement concrete of appropriate grade
and required reinforcement including proper curing, painting
and complete in
(a) New Bridges and old bridges in RCC M 30 Rmt. 8650.00 1591.00 13,762,150.00
Sub Total 60,438,896
National Highways Authority Of India Cost Estimate Page 8 of 10

Item Estimated
Description of Items Unit Rate Amount
No. Quantity
Summary Of Cost Estimate

BILL NO -3 (ENGINEERING IMPROVEMENT)

Replacement of stolen / missing retro-reflectorised traffic


sign boards by providing and fixing new retro-reflectorised
3.01 cautionary , mandatory and informatory sign as per ASTM D
4956-04 made of high intensity grade Micro prismatic
sheeting Type-IV, fixed
i) Advance Direction, Destination, Reassurance and place
indification sign ( size 2100 mm x 1700 mm ) as per drawing
(a) Sqm 89.61 27,682 2,480,721.35
with two vertical posts embedded in M 15 cement concrete
details as per description given above and as per drawing.

(a) ii) Facility information Sign 800 x 600 No 65.00 5,683 369,395.00

(b) Cautionary / Warning Sign

i) Triangular 900 mm side No 135.00 4,185 564,975.00

(c) Mandatory / Regulatory Sign


i) Octagon “STOP” Sign No 82.00 5,868 481,176.00
ii) 600 mm Dia Circular Sign No 67.00 3,337 223,579.00
Supplying and installation of delineators ( Roadway indicators
) 95 cm high above ground level of total length 135 cm.
3.02 painted black and white in 15 cm wide strips fitted with 3 nos. No 540.00 1,055 569,700.00
rectangular micro prismatic reflective sheeting fixed on 2 mm
thick alum
P/F Cats Eye/ Pavement Marker ( NMC nail Less ) :- Made
out of Acryliv-strene-Acrylonitril or Hi-Impact polystyrene
3.03 fitted with Moulded of Methacrylate (NMC) reflector cube No 5500.00 398 2,186,808.53
corner reflector design; Filled with tightly adhering potting
compound as per ASTM
Providing and fixing retro-reflective stickers (Engineering
grade) of size 10 cm x 5 cm on MBCBs and other structures
3.04 No 14000.00 15 209,704.57
as per the MORTH CI No. 801 and as per approval of
Engineer in charge,
Providing and marking of hot applied thermoplastic
compound 2.05 mm thick including refloctorising glass beads
3.05 @ 250 gms/ sqm area, thickness of 2.5 mm is exclusive of Sqm 51748.50 520 26,921,053.48
surface applied glass beads as per IRC 35. The finished
surface to be level, uniform an
Providing and fixing new MS railing/ pipe railing for medians /
horizontal curves including foundation concrete 45 cm x 30
3.07 cm x 30cm in M-15 ) and two coat painting with first quality Rm 6500.00 3235 21,024,673.08
synthetic enamel paint after applying two coat metallic primer
of
Construction and laying Cast in situ cement concrete kerb in
M 20 grade and matching with the existing kerb section
3.08 complete including dismantling and disposal of existing Rm 3500.00 434 1,519,047.14
damaged broken kerbs as per technical specification clause
408 for kerbs ( M-20 gra
Repairing of damaged kerb after dismantling of the kerb up
to minimum of 100 mm and making good the section with M-
3.09 20 concrete to match with the existing section including form Rm 1800.00 143 257,400.00
work, curing, painting with two coats of first quality synthetic
enamel paint
Providing and fixing single faced W-beam crash barrier (W
profile safety guard Rails) made out of the following
3.10 members.job includes erection complete in all respect
including end anchorage as per most clause 811 and using
m-20 grade cement concrete whereever required as
directedby the Engineer.
length of new MBCB Rm 5600.00 3672 20,562,274.84
Removal of unauthorized boards within ROW and stacking
etc. complete in all respect including transportation from site
3.11
to the nearest store / suitable location as per direction of
Engineer in charge.
(a) Single Post. No 62.00 134.00 8,308.00
(b) Double Post ( Post width less than 2 m.) No 46.00 211.00 9,706.00
(c) Double/multi Post ( Post Width grater than 2 m.) No 23.00 239.00 5,497.00
Removal of encroachment of ROW including cost of
3.12 dismantaling,liasioning with local authorities,transportation of Sqm 2800.00 77.00 215,600.00
debries etc complete
Providing and erecting overhead sign boards (Gantry Board
of size 14.1mtx2.1mt) with a corrosion resistant 2mm thick
aluminium alloy sheet reflectorised with high intensity retro-
reflective sheeting of encapsulated lense type with vertical
3.13 No 2.00 558,519.96 1,117,039.91
and lateral clearance given in clause 802.2 and 802.3 and
installed as per clause 802.7 over a designed support
system of aluminium alloy or galvanised steel trestles and
trusses of sections and type as per structural design
Sub Total 78,726,658.91
Summary Of Cost Estimate
National Highways Authority Of India Cost Estimate Page 9 of 10

Item Estimated
Description of Items Unit Rate Amount
No. Quantity
BILL NO-4 (INCIDENT MANAGEMENT)

Removing all types of broken down / vehicles which have


met with accidents from the carriage way and toeing the Per
4.1 36.00 116659 4,199,733.88
same to proper location i.e. nearest police stations or some Month
suitable location by using 15 tones or of more capacity.

Providing and supply of following manpower for misc. work


4.2
as and when required basis as per instruction of Engineer.

(a) Mate/Supervisor Per Day 96.00 244.3 23,452.80


(b) Helper / Beldar / Coolie. Per Day 324.00 224.3 72,673.20
(c) Security Guard Per Day 120.00 244.3 29,316.00
Patrolling by route patrol vehicle as per Clause 6.4 of scope Each
of work and as per clause 6.8 and 6.8.3 of performance Vehicle
4.3 standard of scope of work. The route patrol vechile shall be 12.00 181,807 2,181,688.63
per
equipped with precise vechile tracking system (VTS) (of Month
reputed ISO 9001 comp
Each
Provision of Ambulance as per clause 6.4 of scope of work
Vehicle
4.4 and as per clause 6.8 ‘Performance Standard’ of scope of 12.00 182,871 2,194,447.46
per
work.
Month
Removing the dead animals lying on the Highway and
burying them at proper safe locations outside ROW complete Per
4.5 in all respect with all lead and lifts as per Clause 6.8 Month 12.00 41520 498,240.00
‘Performance Standard’ of scope of work and as per
direction of the Engineer.
Supply of color photographs in three copies and two CDs
4.6 Per Set 12.00 300 3,600.00
complete as per technical specification clause 125 .

Supply of Video ( CD ) in three copies including vediography


4.7 of complete stretch at three stages in O&M period complete Per Set 0.00 20000 -
as per Technical specification clause 126 .
Sub Total 9,203,152
National Highways Authority Of India Cost Estimate Page 10 of 10

Item Estimated
Description of Items Unit Rate Amount
No. Quantity

Summa

BILL NO -5 (MISCELLANEOUS)

Dismantaling of Structure and pavement and disposal of


unserviceable material at suitable place out side ROW with
5.01
all lead and lifts complete in all respect as per approval of
Engineer
a) Dry stone masonary Cum 15.00 166.00 2,490.00

b) Stone masonary/Brick masonary in mud mortar Cum 18.00 227.00 4,086.00

c) Rigid pavement Cum 5.00 735.00 3,675.00

Suplying and fixing of cement concrete precast slab M20


5.02 grade excluding the cost of HYSD reinforcement complete Cum 68.00 1046.00 71,128.00
as per drawing and technical spesification section 1200.
Providing & laying RCC NP-4 / prestressed concrete pipe of
various dia meters ( as per details given below ) for culverts
5.03 on first class bedding of granular material in single ROW
including fixing collar with cement mortar 1:2 but excluding
2900 of Techni
(a) 1000 mm dia Rmt 60.00 7569.00 454,140.00

Providing following equipments in running condition on hire


basis including running and maintenance charges as per
5.04
instruction of the Engineer including P.O.L. complete as per
specification. ( Rate for net working hours at site )

(a) Tipper 6 Cum. Capacity. Per hour 900.00 506.09 455,481.00

(b) JCB Per hour 900.00 730.43 657,387.00

(c) Excavator Per hour 450.00 730.43 328,693.50

(d) Tractor with trolly Per hour 900.00 289.00 260,100.00


Providing and placing in proper position empty cement bags
filled with local earth to control erosion / damage of the side
5.05 of the road or bank of the river / nallha at required locations Nos 15000.00 19.00 285,000.00
including cost of material, labour equipment transporation
etc. comp
5.05 Repairing of Gantry Board at Km 311 (Totapara) including Nos 0.00 45000.00 -

Sub Total 2,522,180.50

Project Director
PIU- Bhubaneswar
National Highway Authority Of India Details of Quantities
BILL NO-1 (ROAD MAINTENANCE)

Item Location Measurements


Description of Items No
No. Unit Side Chainage L B D Qnty Remarks

Blading/grading the unpaved shoulder and slopes using


motor grader/power roller/plate compactor at the required
Tentative 5% only for shoulders
1.01 camber as directed by the Engineer in charge conforming Sqm B/S Km. 0.000 to Km. 76.558 1 11483.7 45934.8
to Technical Specification clause no. 3003. The work also per year
includes disposal of surplus materials.

B/S Km. 0.000 to Km. 76.558 2 76558 1.5 229674

Total Provisional Quantity For One year 45,934.80

Providing spot reconditioning, reconstruction and


regravelling to repair specific erosion or other damages
for restoring the eroded area to originally constructed
1.02 cross section on cuts and fills slopes/shoulders Cum B/S Km. 0.000 to Km. 76.558 1 15311.6 1.5 0.1 2,296.74 Frequency once in a year
conforming to Technical Specification clause no.305
waterd and well compacted with all leads & lifts as
directed by the engineer.-in-charge.

Tentative 20% length both side


B/S Km. 0.000 to Km. 76.558 1 76558 15311.6
considered
Total Qty.For One year Total QTY 2,296.74

Providing repair to grouted stone pitching with 1:3 cement


sand mortar over the already prepared surface/slopes of
1.03 guide bunds, rivers training works, and road
embankments as per MOST section 2500 complete in all
respect as directed by Engineer.

(a) Using Boulders available at site Cum

For Existing work 25.00

Provisional Qty. for One year B/S Km. 0.000 to Km. 76.558 25.00

1 Total QTY 25.00

(b) Using Procured material(Granite) Cum

For Existing work 1 20.00 5.00 0.30 10.00

Provisional Qty. for One year B/S Km. 0.000 to Km. 76.558 10.00

Total Qty.For One year 1 Total QTY 10.00

Clearing, cleaning, depending and reshaping of road site


unlined/kaccha drains and making shallow kaccha lateral
drains on shoulders wherever required, including removal
1.04
and disposal of sediments, extraneous debris and
vegetation growth blocking the free flow site outside Row
with all leads & lifts complete in all respect.

Urban Area length = 2000 m four


(a) Drains having depth upto 0.6 meter Rm B/S Km. 0.000 to Km. 76.558 4 2000 8,000.00
times a year
Total Provisional Quantity For One year Total QTY 8000.00

(b) Drais having depth more than 0.6 meter Rm B/S Km. 0.000 to Km. 76.558 2 1511.16 3022.32

Total Provisional Quantity For One year Rm B/S Km. 0.000 to Km. 76.558 Total Qty 3022.32

Cleaning road side/Median open lined/puca drains to bring


them to original shape, drainage capacity including
1.05 disposal of sediments, extraneous debaris & vegetation
growth blocking the free flow from site out side ROW with
all leads and lifts complete in all respect.

50% of Urban Area length four


(a) Drains having cross sectional area upto 0.3 Sqm Rm B/S Km. 0.000 to Km. 76.558 4 2500 5,000
times a year
Drains having cross sectional area more than upto 0.3 50% of Urban Area length four
(b) Rm B/S Km. 0.000 to Km. 76.558 4 3000 6,000
Sqm times a year
Total Provisional Quantity For One year Total Qty 11,000

Clearing, longitudinal and transverse covered drains and


pipe drains including manholes, gratings, channels and
gullies etc. & bringing them to original drainage capacity,
1.06 Rm B/S Km 0.000 -76.558
including disposal of sediments, extraneous debaris &
vegetation growth blocking as directed by the engineer.-in-
charge.

Provisional Qty. for One year Rm B/S Km. 0.000 to Km. 76.558 2 800 1,600.00 15% of Urban length considered
Total Qty.For One year Total Qty 1600.00
Clearing slab/box type culverts and pipe culverts including
clearing, cleaning and reshaping of upstream and down
stream faces of these culverts with in right way. The job
1.07
also includes disposal of excess material recovered from
site including vegetation as directed by the engineer.-in-
charge.

(a) Slab/Box type Culverts No. B/S Km. 0.000 to Km. 76.558 1 46 46.00 To be operated once in a Year

Total Provisional Quantity For One year Total Qty 46.00


(b) Pipe Culverts No. B/S Km. 0.000 to Km. 76.558 1 28 28.00 To be operated once in a Year
Total Provisional Quantity ForOne year Total Qty 28.00

CMEC Consulting Engineers Pvt. Ltd. , Bhubaneswar-751002


National Highway Authority Of India Details of Quantities
Item Location Measurements
Description of Items No
No. Unit Side Chainage L B D Qnty Remarks

Carrying out proper cleaning of carriageways, footpaths,


verges, expansion joints (for free movement), drainage Footpath in all major and minor
Rmtr of
1.08 spouts of bridge including removal and disposal of trash,
Bridge
B/S Km. 0.000 to Km. 76.558 2 6800 13600.00 bridges to be cleaned two times
plastic, vegetation etc. from site out side ROW complete a year
as per direction of Engineer-in-charge.

Total Provisional Quantity For One year Total Qty 13600.00

Loading, unloading, transportation & disposal of surplus


material left over by accidental vechile or otherwise lying
1.09 Cum B/S Km. 0.000 to Km. 76.558 12 60 720.00 Assuming 60 cum per month
on road (on carriageway) with all lead & lifts complete as
directed by Engineer in charge.

Total Provisional Quantity For One year Total Qty 720.00

Carrying out proper cleaning and removing of


dust/silt/thrash/plastic/rubbish/garbage/waste from the
carriageway, footpaths, verges(excluding the verges of
1.10
central median) by mechanical means and from shoulders
upto Toe line of the embackment including side slopes as
directed by Engineer- in- Charge.

(a) Urban area (Frequency of cleaning one time in a month) Per Km B/S

Km. 13.000 to Km. 14.000 1

Km. 33.000 to Km. 34.000 1.00

Km. 38.000 to Km. 39.000 1.00

Km. 71.000 to Km. 76.000 5.00

12 8 96.00
(b) Rural area (Frequency of cleaning will be quarterly). Per Km B/S Km. 0.000 to Km. 76.558 4 68.56 274.23

Removal of rank vegetation/weeds and undesirable


vegetation from shoulders, embankment slopes upto
ROW (both side) complete in all respect including
1.11
breaking of colds, rough dressing disposal of waste
material and vegetation at a place outside ROW as per
technical specification.

Shoulders including side slopes of embankment up to toe


line on both side of the carriageway. (Frequency of
About 10% length both side
(a) cleaning will be four times in year however limited to only Sqm. B/S Km. 0.000 to Km. 76.558 4 28511 4 456,176
areas prone to growth of rank/undesirable vegetation and considered
weeds).

Total Provisional Quantity For One year Total Qty 456176.00


From Toe line of embankment slopes to ROW on both
About 10% length both side
sides of the carriageway(Frequency of cleaning will be two
(b)
times in a year however limited to only areas prone to
Sqm B/S Km. 0.000 to Km. 76.558 2 17312 5 173,120 considered for average width of
growth of rank/undesirable vegetation and weeds. 5m.

Total Provisional Quantity For One year Total Qty 173,120

Providing localized repair to rutted portion or bituminous


surface at scattered location by applying tack coat as per
technical specification Clause 503 and then filling the
5% length both side considered
1.12 depression with bituminous concrete by using paving Cum Km. 0.000 to Km. 76.558 1 7655.8 7.25 0.05 13.88
grade bitumen conforming to technical specification for average width of 7.25m.
clause no. 509, complete in all respect as directed by the
Engineer-In-Charge.

5% of total service road length


In Service Roads 1 1850 5.5 0.05 0.51 (1850m) considered for average
width of 5.5m.
Total Qty.For One year Total QTY 14.38

Providing localized repair to broken edges of carriageway


at scattered location by applying tack coat as per
technical specification Clause 503 and then repairing the
broken edges with bituminous concrete by using paving
1.13 grade bitumen conforming to technical specification Cum
Clause 503 and then filling the depression with bituminous
concrete by using paving grade bitumen conforming to
technical specification clause no. 509, complete in all
respect as directed by the Engineer-in-Charge.

Km. 0.000 to Km. 76.558 Provisional 0


Total Qty.For One year Total Qty 0.00

Providing sealing to closely spreader cracks at scattered


location after sweeping the surface clean and dry,
applying tack coat of emulsified bitumen @ 0.15 ltr/sqm
followed by distributing slurry evenly in 5mm thickness
prepared by mixing emulsified bitumen 6.0 liter with clean/
dry sand/crusher dust 20 litre & water mixed to such
1.14 Sqm
consistencies that it can be satisfactorly laid. Proper
rolling & compacting after sitting of the slurry sufficiently,
complete in all respect as directed by Engineer-in-Charge.
The work is to be carried out as per the additional
maintenance standard clause no.6.12.6 & performance
standrad 6.8.1.

CMEC Consulting Engineers Pvt. Ltd. , Bhubaneswar-751002


National Highway Authority Of India Details of Quantities
Item Location Measurements
Description of Items No
No. Unit Side Chainage L B D Qnty Remarks

1% length exluding length of


Provisional Qty. for One year Km. 0.000 to Km. 76.558 1 0 7.25 0.00 overlaying both side considered
for average width of 7.25m.

For One year Total Qty 0.00

Providing and applying low viscosity bitumen emulsion for


sealing cracks less then 3mm wide or incipient fretting or
1.15 disintegration in an existing bituminous surfacing Sqm
complete as per MORTH specification Section 518 and as
per direction of the Engineer-in-Charge(Fog spray).

2% length exluding length of


Provisional Qty. for One year Km. 0.000 to Km. 76.558 1 0 7.25 0.00 overlaying both side considered
for average width of 7.25m.

For One year Total Qty 0

Providing sealing cracks wider then 3mm using slow


curing bitumen emulsen @ 0.66 kg per 10 mtrs of the
1.16 Sqm
cracks and stone crusher screening @ 0.0004 cum/10
mtrs complete as per direction of the engineer incharge.

1.5% length exluding length of


For Existing work Km. 0.000 to Km. 76.558 1 0 7.25 0.00 overlaying both side considered
for average width of 7.25m.

For One year Total Qty 0

Providing treatment to bleeding bituminous surface by


uniform spreading of crusher screening/other fine graded
1.17 material @ 2.5 Kg per Sqm, properly rolled as per clause Sqm
3004.4 of Technical Specification complete in all respect
and as p[er direction of Engineer-in-Charge.

For Existing work 0


Provisional
Provisional Qty. for One year 0

For One year Total Qty 0

Providing treatment and repair to pot holes/patch repair of


all types of bitumen pavement complete as per technical
1.18 specification clause 3004.2,and as per direction of
Engineer and as per additional maintenance standard
6.12.9. and performance standard 6.8.1.

Carrying out patch repair with bituminous concrete up to


25 mm thickness after removal of all failed material,
trimming of completed excavation to provide firm vertical 1% length exluding length of
faces, cleaning of surface, painting of tack coat on the
overlaying both side & including
(a) sides & base of excavation all as per clause no. 503 back Sqm B/S Km. 0.000 to Km. 76.558 1 0 7.25 0.00
filling the patch with hot bituminous concrete as per service road considered for
clause no.509. Compacting trimming & finishing the average width of 7.25m.
surface to from a smooth continuous technical
Specification.

Total Provisional Quantity For One year Total Qty 0.00

Carrying out patch repair with bituminous concrete up to


40 mm thickness after removal of all failed material,
trimming of completed excavation to provide firm vertical 0.5% length exluding length of
faces, cleaning of surface, painting of tack coat on the
overlaying including service
(b) sides & base of excavation as all as per clause no. 503 Sqm B/S Km. 0.000 to Km. 76.558 1 76558 7.25 2775.23
back filling the patch with hot bituminous concrete as per road both side considered for
clause no.509. Compacting trimming & finishing the average width of 7.25m.
surface to from a smooth continuous technical
Specification.

Total Provisional Quantity For One year Total Qty 2775.23


Filling potholes and patch repair beyond 40 mm thickness
after removal of all failed material, trimming of completed 0.5% length exluding length of
excavation to provide firm vertical faces cleaning of
overlaying including service
(c) surface, painting of tack coat on the sides & base of Sqm B/S Km. 0.000 to Km. 76.558 1 76558 7.25 1387.61
excavation as per clause no. 509. Compacting trimming & road both side considered for
finishing the surface to from a smooth continuous average width of 7.25m.
technical Specification.

Total Provisional Quantity For One year Total Qty 1387.61

Construction of dry lean cement concrete Sub- base over


a prepared sub-grade with coarse and fine aggregate
conforming to IS: 383, the size of coarse aggregate not
exceeding 25 mm, aggregate cement ratio not to exceed
15:1, aggregate gradation after blending to be as per table
600-1, cement content not to be less than 150 kg/ cum,
1.19
optimum moisture content to be determined during trial
length construction, concrete strength not to be less than
10 Mpa at 7 days, mixed in a batching plant, transported
to site, laid with a paver with electronic sensor,
compacting with 8-10 tonnes vibratory roller, finishing and
curing.

(a) Cement concrete M 15 grade Cum B/S Provisional 68.00


CMEC Consulting Engineers Pvt. Ltd. , Bhubaneswar-751002
National Highway Authority Of India Details of Quantities
Item Location Measurements
Description of Items No
No. Unit Side Chainage L B D Qnty Remarks

For One year Total Qty 68.00

(b) Cement concrete M 20 grade Cum Provisional

For Existing work 87.00

Provisional Qty. for One year Provisional 87.00

Reinforced Cement concrete of specified mix as under


with stone aggregates 20 mm nominal size mechanically
mixed and vibrated in foundation, substructure and
1.20 superstructure for thin as well as thick section including
shuttering/formwork conforming to MOST specification
clause no.1000,1500 & 1700 but excluding cost of
reinforcement.

(a) M 20 Grade Cum

RCC Covered drain RHS Km. 0.000 to Km. 76.558 95 0.32 30.40
Provisional 6.08
Total Qty 36.48
(b) M 25 Grade Cum Km. 0.000 to Km. 76.558
Provisional 41.00
Total Qty 41.00
(c) M 30 Grade Cum B/S Km. 0.000 to Km. 76.558 Provisional Total Qty 26.00
Providing and fixing position HYSD reinforcement in
abutment, pier, superstructure, crash barrier and in other
1.21
structure complete as per technical specification Section
MT B/S Km. 0.000 to Km. 76.558 Provisional Total Qty 2.00
1600 and as directed by the Engineer.

Dismataling structure and pavement including disposal of


1.22 resultant materials and salvaging the useful material
complete in all respect as per direction of the Engineer.

a) Plain concrete Cum B/S Km. 0.000 to Km. 76.558 Provisional 25.00
RCC including clearing, straightening and cutting of bars
(b) Cum B/S Km. 0.000 to Km. 76.558 Provisional 20.00
and separating out of RCC
Dismantling of road including wearing courses, base
courses, and sub base courses including stacking of old Removal of Un authorised
1.23
serviceable material complete in all respect as per approaches
direction of Engineer.
Dismantling of bituminous wearing courses, including
(a) disposal of the waste material out side ROW as per Cum B/S Km. 0.000 to Km. 76.558 Provisional Total Qty 96.00
direction of Engineer.

Dismantling of base courses, including stacking of useful


(b) material at proper location and disposal of unserviceable Cum B/S Km. 0.000 to Km. 76.558 Provisional Total Qty 87.00
material out side ROW as per direction of Engineer.

Dismantling of sub base courses, including stacking of


useful material at proper location and disposal of
(c)
unserviceable material out side ROW as per direction of
Cum B/S Km. 0.000 to Km. 76.558 Provisional Total Qty 85.00
Engineer.
Earthwork in excavation necessary for construction of
roadway / structures including all leads and lifts completes
1.24 as per Technical specification clause 301 and 304 duly
watered, rolled & compacted as per direction of Engineer
in charge.

Removal of Un authorised
(a) All type of soil Cum B/S Km. 0.000 to Km. 76.558 Provisional 67.00
approaches &Road construction

Total Qty 67.00


Construction of embankment with approved borrow
material brought from location out side ROW with all leads
1.25 and lifts complete in all respect as per Technical
specification clause no. 305 duly watered, rolled &
compacted.

Provisional Qty. forOne year Cum B/S Km. 0.000 to Km. 76.558 Provisional 65.00
Total Qty.For One year Total QTY 65.00

Construction of embankment with suitable material obtain


from roadway, drainage excavation ,and pavment
1.26 dismantling etc.with all leads and lifts complete in all Cum B/S Km. 0.000 to Km. 76.558 Provisional 41.00
respect as per Technical specification clause no. 305 duly
watered, rolled & compacted.

Total Qty.For One year Total QTY 41.00

Scarifying existing road surface including bitumenous


surface complete as per Technical Specification clause
1.27 no. 501, including disposal of unserviceable material out Sqm B/S Km. 0.000 to Km. 76.558 1 153.116 7.25 1,110.09 For Bridge approaches
side ROW with all leads and lifts complete in all respect
as pe direction of Engineer-In-Charge.

CMEC Consulting Engineers Pvt. Ltd. , Bhubaneswar-751002


National Highway Authority Of India Details of Quantities
Item Location Measurements
Description of Items No
No. Unit Side Chainage L B D Qnty Remarks

Construction of sub grade and earthen shoulders with


approved material satisfying the requirement of minimum
soaked CBR value brought from borrow areas located
1.28 outside ROW with all leads and lifts transporting to site, Cum
laying and compacting as per Technical specification
clause no. 305 complete in all respect as per direction of
Engineer-In-Charge.

Provisional Qty. for One year B/S Km. 0.000 to Km. 76.558 1 38.279 1.5 0.3 17.23

Total Qty.For One year Total QTY 17.23

Providing, Laying and compacting granular sub base


(GSB) with approved materials complete as per Technical
1.29
specification clause 401 conforming to grade I Table
400.1/400.2 as per approval of Engineer in charge.

Provisional Qty. for One year B/S Km. 0.000 to Km. 76.558 1 8970 7.25 0.2 13,006.50 Lump sum length taken
Total Qty.For One year Total QTY 13,006.50

Providing, Laying and compacting wet mix macadam


1.30 (WMM) base course with approved materials complete as Cum B/S Km. 0.000 to Km. 76.558 1 6782 7.25 0.25 12,292.38 Lump sum length taken
per Technical specification Clause no. 406 of MORTH.

Total Provisional Quantity For One year Total QTY 12,292.38


Providing, Laying and compacting dense graded
bituminous macadam complete as per Technical
1.31 Cum
specification Clause no. 507. Including tack coat as per
Technical specification Clause no. 503.

Provisional Qty. for One year B/S Km. 0.000 to Km. 76.558 1 5580 8.75 0.075 3661.875
Total Qty.For One year Total QTY 3,661.88

Providing, Laying and compacting bituminous concrete as


1.32 per Technical specification clause 509. Including tack coat
as per Technical specification Clause no. 503.

A major maintenance is required


Wearing Course for DBM Base course.
(a) Cum B/S Km. 0.000 to Km. 76.558 1 22850 8.75 0.04 7,997.50 after 9 yr of the road
Using paving grade bitumen 60/70
construction
Total Provisional Quantity For One year Total QTY 7997.50

Providing, Laying and compacting bituminous concrete as


per Technical specification clause 509. Including tack coat
(b)
as per Technical specification Clause no. 503. (for service
road)

(a) Using paving bitumen VG-30 Cum All service road 1 3528 5.5 0.05 970.2
Total QTY 970.20
Providing,laying biytuminous primer coat over granular
surface with bituminous emulsion complete as per
1.33 Sqm
Technical specification Clause no 502@7.5 kg/10sqm and
as per direction of Engineer.

Provisional Qty. for One year B/S Km. 0.000 to Km. 76.558 1 5,580 8.75 48,825.00
Total Qty.For One year Total QTY 48,825.00

Providing and applying tack coat with bitumen emulsion


using emulsion pressure distributir at the rate of 0.20 Kg
1.34 Sqm
per Sqm on the prepared bituminous/granular surface
cleaned with mechnical as per technical specification 503.

Providing in full width on Rutted surface. LHS Km. 0.000 to Km. 76.558 1 22850 8.75 0 199937.50
Total Qty.For One year Total QTY 199,937.50

Sealing of crack/porous concrete with Epoxy grout by May be necessary for


1.35 injection through nipples complete as per Clause 2803 of Sqm B/S Km 0.000 to Km.76.558 Provisional Total Qty 145.00 rehabilitation of the Bridge
Technical specification and as per approval of Engineer. existing over Creek.

Applying Epoxy motar over leached honey combed and


spalled concrete surface and exposed steel reinforcement
1.36
complete as per Technical specification Clause no. 2804
Sqm B/S Km 0.000 to Km.76.558 Provisional Total Qty 69.00
and as per approval of Engineer.

Cement Pointing of any design/repair to existing pointing,


with cement motar 1:3 on all types of masonry work
1.37
excluding stone masonary in superstructure/ substructure
Sqm B/S Km 0.000 to Km.76.558 Provisional Total Qty 280.00
as per MOST specification clause no. 1000 & 1300 .

Cement Pointing of any design/repair to existing pointing,


with cement motar 1:3 on stone masonary work in
1.38
superstructure/ substructure as per MOST specification
Sqm B/S Km 0.000 to Km.76.558 Provisional Total Qty 185.00
clause no. 1000 & 1300.

Cement plaster/ repair to cement plaster in thickness 12-


20 mm in cement motar 1:4 on all types of masonary work
1.39
in superstructure/ substructure at any height as per MOST
Sqm Km 0.000 to Km.76.558 Provisional Total Qty 250.00 For all gantry board
clause no. 1000 , 1300 & 1400.

Repair of all types of damaged stone/ brick masonry work


in superstructure and substructure of bridges/ CD works
1.40 including dismantling of damaged portion and
reconstructing to match with existing pattern without
causing any damage to the structure in ceme
CMEC Consulting Engineers Pvt. Ltd. , Bhubaneswar-751002
National Highway Authority Of India Details of Quantities
Item Location Measurements
Description of Items No
No. Unit Side Chainage L B D Qnty Remarks
(a) Repair of Stone Masonry in CM 1:3 Cum B/S Km 0.000 to Km.76.558 Provisional Total Qty 1270.00
(b) Repair of Brick Masonry in CM 1:3 Cum B/S Km 0.000 to Km.76.558 Provisional Total Qty 132.00

Construction of Footpaths/ separators/ traffic Islands by


Providing 150 mm thick compacted GSB as per MORTH Provision of 5% length of the
Section 401 & 25 mm thick cement concrete grade M-15 Footpaths in all major and minor
1.41 base over laid with 25 mm thick M-20 precast cement Sqm B/S Km 0.000 to Km.76.558 1 57 1.5 1360.00 bridges kept for
concrete chequred titles in cement mortar 1:3 cement repair,(Including Luna bridge Ch-
sand mortar. The joint of the tiles to be bonded & finished 52+300 RHS)
with neat cement slurry etc.complite in all respect.

Replacement of damaged cement concrete chequred tiles


with new 25mm thick M-20 precast cement concrete
chequrred tiles on the already prepared/existing base with
1.42
1:3 cement sand mortar. The joint of the tiles to be
Sqm B/S Km. 0.000 to Km. 76.558 Provisional Total Qty 68.00
bonded & finished with neat cement slurry etc. complete
in all respect,

Dismantling of existing damaged Expansion joints and


providing and fixing of a new strip seal expansion joint
catering to maximum horizontal movement up to 70 mm
1.43 Rmt B/S
complete and to be installed by the
manufacture/supplier/their authorised representative
complite as per Engineer in charge.

Km 64 1 28.5 28.50
1 26.8 26.80
For Existing work 55.30
For One year Total Qty 55.30

CMEC Consulting Engineers Pvt. Ltd. , Bhubaneswar-751002


National Highway Authority Of India Details of Quantities
Item Location Measurements
Description of Items No
No. Unit Side Chainage L B D Qnty Remarks

BILL NO -2 (ROAD PROPERTY MANAGEMENT AND OTHER MAINTENANCE

Providing, planting healthy/ well-developed spalling


of ornamental/flowering shrubs of specified species
and varieties, 1-2 years of age in 25cm-30cm poly
2.01 No. median Km. 0.000 to Km. 76.558 Provisional Total Qty 1100.00
bags or pots, height and spread 0.60mt-0.90mt
above ground, with 3-4 branches, in well prepared
pits.
Maintenance of new plants(item no-2.01) by basin
making,weeding,hoeling,cleaning,levelling,and
dressing of median,uprooting,and removal of
2.02 No. median Km. 0.000 to Km. 76.558 1 3500 1100.00
weeds,cuting grass,disposal of all muck outside
ROW regularly to keep the median clean and
plantation.

Watering of each plant as and when required depending


upon the climatic conditions of the locality/region/season/
(a) strictly as per direction of engineer in charge.Km length of
maintenance will be decided considering density of plants
as 666 per km.actually.

Application of FYM or Sludge @ 1/2 cuft or 10 kg/Plant


two times a year during February / March and October /
(b)
November plus 20 grams of NPK(12:32:16) or bonemeal
per plants two times a year as detailed above.

Application of insecticide / pesticide / fungicide etc. for


(c) control of insect’s pests and diseases as and when
required as per direction of Engineer.

Trimming and pruning of all shrubs / plants as and when


(d)
required to give them required shape, size and spread.

Replacement of deed , damaged plants from the median


by healthy & well developed plant of similar species,
(e) varieties, age and size etc. within 10 days of occurrence
of causality as noticed/ reported or as directed by the
Engineer.

Maintenance of median and the exiting plants in it (with a


density of 666 plants per km.) by basin making, weding-
2.03 holeing, cleaning, leveling and dressing of median,
uprooting and removal of weeds, cutting grass, disposal
of all muck outside ROW regularly.

Watering of each plant as and when required depending


upon the climatic conditions of the locality/region/season/
(a) strictly as per direction of engineer in charge.Km length of
maintenance will be decided considering density of plants
as 666 per km.actually

Application of FYM or Sludge @ 1/2 cuft or 10 kg/Plant Km/mo Total Plants=42000 (approx.)
two times a year during February / March and October / nth
median Km. 0.000 to Km. 76.558 12 63.06 756.76
(b) Equivalent Km.=63.06
November plus 20 grams of NPK(12:32:16) or bonemeal
per plants two times a year as detailed above.

Application of insecticide / pesticide / fungicide etc. for


(c) control of insect’s pests and diseases as and when
required as per direction of Engineer.

Trimming and pruning of all shrubs / plants as and when


(d)
required to give them required shape, size and spread.

Replacement of deed , damaged plants from the median


by healthy & well developed plant of similar species,
(e) varieties, age and size etc. within 10 days of occurrence
of causality as noticed/ reported or as directed by the
Engineer.
756.76

Supplying and turfing with live and perennial turf forming


grass on embankment slopes, verges, medians and other
2.04 location confirming to Technical specification Clause 307 Sqm.
including watering and maintaining for entire contract
period with periodical mowing.

50m length of Median to be


Provisional Qty. for One year B/s Km. 0.000 to Km. 76.558 0 50 4.5 225.00 turfed at 10nos of median
opening locations.

For One year Total Qty 225.00

White wash / cement paint/ snowcem in two or more


coats to give an even shade and smooth surface for
protection of exposed concrete/ masonry portion of
2.05
bridges/ CD works, kerb and wheel guard including
scraping of damage paint from old surface and repairing
of the old surface as directed Engineer in charge.

(a) White washing two coats on existing surface Sqm B/S Km. 0.000 to Km. 76.558 Provisional 10000.00
Finishing walls with exterior decorative cement
based paint such as snowcern on old work , two
(b) coats to give an even shade after repairing of Sqm
defects so as to achieve smooth and defects free
surface.
B/s Ch.13.230 1 20 5 180.00 Underpass
B/s Ch.21.250 1 20 5 180.00 Underpass
CMEC Consulting Engineers Pvt. Ltd. , Bhubaneswar-751002 B/s Ch.23.400 1 20 5 180.00 Underpass
National Highway Authority Of India Details of Quantities
Item Location Measurements
Description of Items No
No. Unit Side Chainage L B D Qnty Remarks

B/s Ch.28.650 1 20 5 210.00 Underpass

Ch.33.500 1 20 5 200.00 Underpass

Ch.36.200 1 20 5 150.00 Underpass

Ch.67.800 1 20 5 180.00 Underpass


For Existing work 0.00
For One year 0.00

Painting with higloss synthetic enamel paint two coats to


give an even and smooth surface for protection of
2.06 exposed concrete/ masonry portion of Bridges/CD works/
parapet, kerb painting and repairing wherever necessary,
complete as per approval of Engineer in charge.

(a) Old existing surface Sqm B/s Km. 0.000 to Km. 76.558 2 62000 124000.00 2 times in 3 years
Total Qty.For One year Total Qty 124000.00
Painting all types of M.S/GI railing as when required with
two coats of synthetic enamel paint of approved brand
2.07
after cleaning the surface complete in all respect as
directed by the Engineer.
Per rmt of Full On all existing Pedestrian M.S.
(a) On existing Railing.
height of railing
Km. 0.000 to Km. 76.558 3600.00
Guard rail
For Existing work 3600.00
For One year 3600.00
Per rmt
of Full
On new surface after applying two coat of metallic primer On new Pedestrian M.S. Guard
(b)
of approved quality and make.
height B/S Km. 0.000 to Km. 76.558 Total Qty 3200.00
of rail
railing
Cleaning, removing, clearing of dust dirt from the existing
metal crash barrier and pedestrian guard rail by washing
2.09
with water & detergent etc. complete as directed by
Engineer.
(a) MBCB Rm Km. 0.000 to Km. 76.558 1 10000.00 Total Qty 10000.00 2 times in 3 years
Carrying out routine maintenance to all types of road signs
complete as directed by the Engineer and as per
2.10
Additional Maintenance standard clause 5.5.3 the bid
document.
(a) Road sign Boards mounted on single post. No. B/S Km. 0.000 to Km. 76.558 Provisional Total Qty 52
(b) Road sign Boards mounted on double post. No. B/S Km. 0.000 to Km. 76.558 Provisional Total Qty 18
(c) Overhead gantry road sign boards. No. B/S Km. 0.000 to Km. 76.558 Provisional Total Qty 3
Carrying out of repair signs including strengthing resetting
or otherwise repairing signs made out of Retro Reflective
sheet, job includes patch repair to aluminum sheet, posts,
signs/ script and repainting of posts at damaged location /
2.11
position with approved quality of enamel paint complete in
all repect confirming to respectitive IRC/MOST
specification and as per additional maintenance clause
6.12.4.

(a) Road sign Boards mounted on single post. No. B/S Km 0.000-76.588 Provisional Total Qty 62.00
(b) Road sign Boards mounted on double post. No. B/S Km 0.000-76.588 Provisional Total Qty 27.00
Painting two coats on old surface after miner repairs to
give an even and smooth surface and printing letters and
2.12 figures with first quality synthetic enamel paint of
approved brand and manufacture complete in all respect
confirming to respective IRC specification.

(a) Hectometer stones No B/S Km 0.000-76.588 Provisional Total Qty 25.00


(b) Kilometer stones No B/S Km 0.000-76.588 Provisional Total Qty 130.00
(c) 5th Kilometer stones No B/S Km 0.000-76.588 Provisional Total Qty 15.00
(d) Boundary Stones No B/S Km 0.000-76.588 Provisional Total Qty 82.00

Providing and fixing reinforced cement concrete M-15


grade 5th kilometer stones, kilometer stones and
2.13 hectometer stones of standard design as per IRC-8-1980
& MORTH specification clause 804 including two coat
painting with synthetic enamel paint.

(a) Hectometer stones No B/S Km. 0.000 to Km. 76.558 Provisional Total Qty 60.00
(b) Kilometer stones No B/S Km. 0.000 to Km. 76.558 Provisional Total Qty 54.00
(c) 5th Kilometer stones No B/S Km. 0.000 to Km. 76.558 Provisional Total Qty 6.00
Paining two coats with first quality enamel paint of
approved make & quality to give an even shade including
2.14
writing, letter 7 figure etc. Complete in all respect as per
IRC standard.

(a) Printing letters of CD nos No B/S Km. 0.000 to Km. 76.558 1 28 Total Qty 50.00

CMEC Consulting Engineers Pvt. Ltd. , Bhubaneswar-751002


National Highway Authority Of India Details of Quantities
Item Location Measurements
Description of Items No
No. Unit Side Chainage L B D Qnty Remarks

Strengthening and repairing of partiality damaged M.S


pedestrian Railing/pipe railing complete including welding,
repairing/replacement of damaged parts/ portions Per
2.15
(salvage material will be contractors property ) as per Rmt.
existing pattern complete in all respect as per IRC
standard specification.

For Existing work 3200.00


Provisional Qty. for One year
For One year Total Qty 3200.00

Replacement of damaged single faced W-beam metal


crash barrier made out of members.Job includes repair of
old damaged member by strengthening the member and
removing the old unused member by replacing with new
2.16
member and repairing all the existing dents as well as
other defects and neatly refixing the repaired including
provision of new MBCB at specified locations as directed
by the Engineer-in-charge.

Beam made out of cold rolled steel strip W profile of 3 mm


thick having a minimum of yield strength 2400 kg/sqcm
(a)
having width of 313 mm and depth of corrugation as
Rmt B/S Km. 0.000 to Km. 76.558 1 6000 6000.00
83mm hot dip galvanised of zinc coating @550gm/sqm

Total Qty.For One year Total Qty 6000.00

Post consisting of colled rolled channel 150x75x5 mm


having minimum yield strength of 2400 kg/sqcm.The total
(b) length of post shal be 1900 mm and minimum height of No B/S Km. 0.000 to Km. 76.558 1 3000 3000.00 1 post/2 rmt of beam
post above M 20 concrete foundation shall be 800 mm hot
dip galvanized of zinc coating of 55

Total Qty.For One year Total Qty 3000.00


Space chanels or brackets made out of CRP steel
channel section 150x75x5 mm having an yield strength of
(c) 2400kg/sqcm .The length of spacer channel shall be 330 No 1 channel/2 rmt of beam
mm and hot dip galvanised having zinc coating
@550gm/sqm.
B/S Km. 0.000 to Km. 76.558 1 3000 3000.00
Total Qty.For One year Total Qty 3000.00
Fasteners button head bolts 16x40 mm long with nut and
(d) No
washer hot dipped galvanized.
B/S Km. 0.000 to Km. 76.558 1 6000 6000.00 14 fasteners/ rmtof beam
Total Qty.For One year Total Qty 6000.00
Replacing damaged / broken railing with new precast /
cast in situ, concrete railing to match with existing design
2.17 and pattern , made out of cement concrete of appropriate
grade and required reinforcement including proper curing,
painting and complete in all respect.

(a) New Bridges and Old bridges in RCC M 30 Rmt.

For Existing work Km. 0.000 to Km. 76.558 8650.00


For One year Total Qty 8650.00

BILL NO -3 (ENGINEERING IMPROVEMENT)

Replacement of stolen / missing retro-reflectorised traffic


sign boards by providing and fixing new retro-reflectorised
3.01 cautionary , mandatory and informatory sign as per ASTM
D 4956-04 made of high intensity grade Micro prismatic
sheeting Type-IV.

i) Advance Direction, Destination, Reassurance and place


indification sign ( size 2100 mm x 1700 mm ) as per
(a) drawing with two vertical posts embedded in M 15 cement Sqm B/S Km. 0.000 to Km. 76.558
concrete details as per description given above and as
per drawing.
Helpline board B/S Km. 0.000 to Km. 76.558 8 2.1 1.7 28.56
Advance direcction,and place identification B/S Km. 0.000 to Km. 76.558 6 2.1 1.7 21.42
Gantry board B/S Km. 0.000 to Km. 76.558 2 11.657 1.7 39.63

Total Qty.For Three Months Total Qty 89.61


ii) Facility information Sign 800 x 600 No B/S Km. 0.000 to Km. 76.558 Provisional Total Qty 65.00
(b) Cautionary / Warning Sign
i) Triangular 900 mm side No B/S Km 0+000 -76+588 Provisional Total Qty 135.00
(c) Mandatory / Regulatory Sign
i) Octagon “STOP” Sign No B/S Km. 0.000 to Km. 76.558 Provisional Total Qty 82.00
ii) 600 mm Dia Circular Sign No B/S Km. 0.000 to Km. 76.558 Provisional Total Qty 67.00

CMEC Consulting Engineers Pvt. Ltd. , Bhubaneswar-751002


National Highway Authority Of India Details of Quantities
Item Location Measurements
Description of Items No
No. Unit Side Chainage L B D Qnty Remarks

Supplying and installation of delineators ( Roadway


indicators ) 95 cm high above ground level of total length
135 cm. painted black and white in 15 cm wide strips
fitted with 3 nos. rectangular micro prismatic reflective
sheeting fixed on 2 mm thick aluminium sheet of size
3.02
80mmx 100mm one in each black strip duly riveted in the
No B/S Km. 0.000 to Km. 76.558 Provisional Total Qty 540.00
rectangular tubular section facing direction of traffic. The
delinator is embedded in M-15 cement concrete in pit size
300mmx 300mmx 450mm. The rate quoted is further
complete job as directed by the Engineer - In- Charge.

P/F Cats Eye/ Pavement Marker ( NMC nail Less ) :-


Made out of Acryliv-strene-Acrylonitril or Hi-Impact
3.03 polystyrene fitted with Moulded of Methacrylate (NMC) No B/S Km. 0.000 to Km. 76.558 Provisional Total Qty 5500.00
reflector cube corner reflector design; Filled with tightly
adhering potting compound as per ASTM.

Providing and fixing retro-reflective stickers (Engineering


grade) of size 10 cm x 5 cm on MBCBs and other
3.04
structures as per the MORTH CI No. 801 and as per
No B/S Km. 0.000 to Km. 76.558 Provisional Total Qty 14000.00
approval of Engineer in charge,

Providing and marking of hot applied thermoplastic


compound 2.05 mm thick including refloctorising glass
beads @ 250 gms/ sqm area, thickness of 2.5 mm is
3.05 exclusive of surface applied glass beads as per IRC 35.
The finished surface to be level, uniform and free from
streaks and holes complete in all respect and as per
approval of Engineer in charge.

At median openings and at junctions for black spots


/zebra crossings
Sqm Provisional 1200.00
For lane marking B/S Km. 0.000 to Km. 76.558
b) Edge marking of Carriageway : continious 150 mm
wide

Total Length of Project Road where edge marking to be


provided in median 22850
Edge marking on carriageway 4 72000 0.15 43200.00
(ii) Centre lane marking : 100mm wide
Total Length of Project Road 22850.00
Deduction of Horizontal Curves portion length 713.88
Straight length of Road. 22136.12
For straight portion centre line marking will be 3000mm
continious with 6000mm intreval. 2 72000.00 0.15 0.33 7128.00
For curves portion center line marking will be 3000mm
continious with 3000mm interval 2 1470.00 0.15 0.5 220.50
Total Center line marking for main carrigeway 7348.50

Net edge and Center line marking for main carrigeway 50548.50
Total Provisional Quantity For One year 51748.50

Providing and fixing new MS railing/ pipe railing for


medians / horizontal curves including foundation concrete
3.07 45 cm x 30 cm x 30cm in M-15 ) and two coat painting RMT
with first quality synthetic enamel paint after applying two
coat metallic primer of Engineer in charge.

Provisinal Qty.Replacement of
stolen / missing /Damage by
Provisional Qty. for One year Km. 0.000 to Km. 76.558 6500.00 accidents for Two Years.and newly
closed unauthrised median opening
where required.
For One year Total Qty 6500.00
Construction and laying Cast in situ cement concrete kerb
in M 20 grade and matching with the existing kerb section
complete including dismantling and disposal of existing
3.08 Rmt
damaged broken kerbs as per technical specification
clause 408 for kerbs ( M-20 graade) as per existing
pattern.

For Existing work B/s Km. 0.000 to Km. 76.558


Provisional Qty. for One year 3500.00
For One year Total Qty 3500.00
Repairing of damaged kerb after dismantling of the kerb
up to minimum of 100 mm and making good the section
with M-20 concrete to match with the existing section
3.09
including form work, curing, painting with two coats of first
Rmt B/S Km. 0.000 to Km. 76.558 Provisional Total Qty 1800.00
quality synthetic enamel paint etc as per direction of
Engineer in charge.

Providing and fixing single faced W-beam crash barrier


(W profile safety guard Rails) made out of the following
members.job includes erection complete in all respect
3.10 Rmt Km. 0.000 to Km. 76.558
including end anchorage as per most clause 811 and
using m-20 grade cement concrete whereever required as
directedby the Engineer.

(a) length of new MBCB Rmt B/S Km. 0.000 to Km. 76.558 1 5600 5600.00

CMEC Consulting Engineers Pvt. Ltd. , Bhubaneswar-751002


National Highway Authority Of India Details of Quantities
Item Location Measurements
Description of Items No
No. Unit Side Chainage L B D Qnty Remarks

Four spacings considered for 8


(b) Terminal Anchorage Nos B/S Km. 0.000 to Km. 76.558 1 16 2 32.00 locations in one side. Two end
anchorage per location is taken.

Removal of unauthorized boards within ROW and


stacking etc. complete in all respect including
3.11
transportation from site to the nearest store / suitable
location as per direction of Engineer in charge.

Total Provisional Quantity


(a) Single Post. No B/S Km. 0.000 to Km. 76.558 Provisional 62.00
For One year

Total Provisional Quantity


(b) Double Post ( Post width less than 2 m.) No B/S Km. 0.000 to Km. 76.558 Provisional 46.00
For One year

Total Provisional Quantity


(c) Double/multi Post ( Post Width grater than 2 m.) No B/S Km. 0.000 to Km. 76.558 Provisional 23.00
For One year
Removal of encroachment of ROW including cost of
dismantaling,liasioning with local authorities,transportation
3.12
of debries etc complete as per direction of Engineer in
Sqm B/S Km. 0.000 to Km. 76.558 Provisional Total Qty 2800.00
charge.
3.13 Providing and Fixing Gantry Board Nos B/S Km. 0.000 to Km. 76.558 2.00
Supplying & Fixing LED Solar Blinker mounted on
a steel poles to guide and warn various vehicle
drivers of a forthcoming flyovers, crossover,
underpass and other intersections and accident
prone region. Manufactured using superior grade
battery, solar panel and other components, clearly
visibile for enhancing road safety during fog, rain Total Provisional Quantity Median opening & Major
3.46 Nos B/S Km. 0.000 to Km. 76.558
For One year
64.00
and other adverse weather condition as per Clause Junction area
6.15 of Performance Standards of Scope of Work
including maintenance and replacement of the
same and as directed by the Engineer-in-charge.
The warranty so provided by the Supplier will be in
the name of NHAI.

BILL NO-4 (INCIDENT MANAGEMENT)

Removing all types of broken down/vehicles which have


met with accidents from the carriageway and toeing the
same to proper locations i.e. nearest Police stations or
some suitable location by using 15 tonne or of more
capacity pick and carry crane, as per the requirement of
the incident and as per clause 6.4 of Scope of Work and
as per Clause 6.8 'Performance Standard' of scope of Per Total Provisional Quantity
4.1
work. The crane shall be equipped with precise vehicle Month
B/S Km. 0.000 to Km. 76.558 12
For One year
36.00
tracking system (VTS) (of reputed ISO 9001 company)
based on Global provision system (GPS) and GSM /
GPRMS technology. The system shall include micro, live,
real time tracking web based software through which use
of GIS maps and transit, stoppage idle, over speed
reports of vehicle shall be obtained.

Providing and supply of following manpower for misc.


4.2 work as and when required basis as per instruction of
Engineer.
Total Provisional Quantity
(a) Mate/Supervisor Per Day Km. 0.000 to Km. 76.558 12 8 For One year
96.00 Provisional

Total Provisional Quantity


(b) Helper / Beldar / Coolie. Per Day Km. 0.000 to Km. 76.558 12 27 For One year
324.00 Provisional

Total Provisional Quantity


(c) Security Guard Per Day Km. 0.000 to Km. 76.558 12 10 For One year
120.00 Provisional

Patrolling by route patrol vechile as per Clause 6.4 of


Each
scope of work and as per clause 6.8 and 6.8.3 of
Vehicle Total Provisional Quantity
4.3 performance standard of scope of work. The route patrol
per
B/S Km. 0.000 to Km. 76.558 12
For One year
12.00
vechile shall be equipped with precise vechile tracking
Month
system (VTS) (of reputed ISO 9001 comp

Each
Provision of Ambulance as per clause 6.4 of scope of
Vehicle Total Provisional Quantity
4.4 work and as per clause 6.8 ‘Performance Standard’ of
per
B/S Km. 0.000 to Km. 76.558 12
For One year
12.00
scope of work.
Month
Removing the dead animals lying on the Highway and
burying them at proper safe locations outside ROW
Per Total Provisional Quantity
4.5 complete in all respect with all lead and lifts as per Clause
Month
B/S Km. 0.000 to Km. 76.558 12
For One year
12.00
6.8 ‘Performance Standard’ of scope of work and as per
direction of the Engineer.

Supply of color photographs in three copies and two CDs Total Provisional Quantity
4.6
complete as per technical specification clause 125 .
Per Set B/S Km. 0.000 to Km. 76.558 12
For One year
12.00

BILL NO -5 (MISCELLANEOUS)

Dismantaling of Structure and pavement and disposal of


unserviceable material at suitable place out side ROW
5.01
with all lead and lifts complete in all respect as per
approval of Engineer

a) Dry stone masonary Cum B/S Km. 0.000 to Km. 76.558 Provisional Total Qty 15.00
CMEC Consulting Engineers Pvt. Ltd. , Bhubaneswar-751002
National Highway Authority Of India Details of Quantities
Item Location Measurements
Description of Items No
No. Unit Side Chainage L B D Qnty Remarks

b) Stone masonary/Brick masonary in mud mortar Cum B/S Km. 0.000 to Km. 76.558 Provisional Total Qty 18.00

c) Rigid pavement Cum B/S Km. 0.000 to Km. 76.558 Provisional Total Qty 5.00

Suplying and fixing of cement concrete precast slab M20


5.02 grade excluding the cost of HYSD reinforcement complete Cum B/S Km. 0.000 to Km. 76.558 Provisional Total Qty 68.00
as per drawing and technical spesification section 1200.

Providing & laying RCC NP-4 / prestressed concrete pipe


of various dia meters ( as per details given below ) for
5.03 culverts on first class bedding of granular material in
single ROW including fixing collar with cement mortar 1:2
but excluding 2900 of Technical specification

For the existing loops at junction


(a) 1200 mm dia Rmt B/S Km. 0.000 to Km. 76.558 Provisional Total Qty 60.00
of NH-5 & NH-5A

Providing following equipments in running condition on


hire basis including running and maintenance charges as
5.04
per instruction of the Engineer including P.O.L. complete
as per specification. ( Rate for net working hours at site )

Per Total Provisional Quantity


(a) Tipper 6 Cum. Capacity. B/S Km. 0.000 to Km. 76.558 Provisional 900.00 Assuming 25 hours/month
hour For One year
Per Total Provisional Quantity
(b) JCB B/S Km. 0.000 to Km. 76.558 Provisional 900.00 Assuming 25 hours/month
hour For One year
Per Total Provisional Quantity
(c) Excavator B/S Km. 0.000 to Km. 76.558 Provisional 450.00
hour For One year
Per Total Provisional Quantity
(d) Tractor with trolly B/S Km. 0.000 to Km. 76.558 Provisional 900.00 Assuming 25 hours/month
hour For One year

Providing and placing in proper position empty cement


bags filled with local earth to control erosion / damage of
Total Provisional Quantity
5.05 the side of the road or bank of the river / nallha at required Nos B/S Km. 0.000 to Km. 76.558 Provisional 15000.00
For One year
locations including cost of material, labour equipment
transporation etc.
5.1
5.17 Sets

Project Director
PIU- Bhubaneswar

CMEC Consulting Engineers Pvt. Ltd. , Bhubaneswar-751002


RATE ANALLYSIS
BILL No 1: Road Maintenance
Ref. to Unit Quantity Rate Cost Remarks/In
MOST
S.No MoRT Description Rs Rs put
Data No
H reference
1.01 2.3 201

Blading/grading the unpaved shoulder and slopes manually at


the required camber as directed by the Engineer in charge
confirming to Technical Specifications clause no. 3003. The
work also include disposal of surplus material and addition of
suitable earth

Unit = Sqm
Taking output = 100 Sqm
Assuming average depth of stripping as 75 mm
Quantity of earth cutting involved = 7.5 cum
a) Labour
Mate day 0.1 244.30 24.43 L-10
Mazdoor day 2.5 224.30 560.75 L-01
b) Machinery
Plate compactor@25Sqm per hour hour 4 100.00 400.00 P&M-086
c) Overhead charges @ 8% on (a+b) 78.8144
d) Contractor's profit @ 10% on (a+b+c) 106.40
Rate per Sqm = (a+b+c+d)/100 11.70
say 9

Providing spot reconditioning, reconstruction and regravelling


to repair specific erosion or other damages for restoring the
1.02 3.1 3002 eroded area to originally constructed cross section on cuts
and fills sloped/ shoulders confirming to Technical
Specifications cla
Unit = cum
Taking output = 10 cum
a) Labour
Mate day 0.08 244.30 19.54 L-10
Mazdoor day 2.00 224.30 448.60 L-01
b) Machinery
Excavator 1.0 cum bucket capacity @ 60 cum per hour hour 0.13 730.43 94.96 P&M-026
Tipper ( L is average lead in km for borrow earth) t.km 450.00 2.17 976.50 P&M-047

Add 10 percent of cost of carriage towards loading and 97.65


unloading charges.
Plate compactor hour 0.50 100.00 50.00 P&M-086
c)Morrum Cum 7.50 274.38 2057.85 M-007
3745.10
d) Overhead charges @ 8 % on (a+b) 299.61
e) Contractor's profit @ 10 % on (a+b+c) 404.47
4449.18
Cost of 10 cum = a+b+c+d 4449.18
Rate per cum = (a+b+c+d)/10 444.92
say 445

Providing repair to grouted stone pitching with 1:3 cement


sand mortar over the already prepared surface/slopes of
1.03 15.4 2504 guide bunds, river training works and road embankments as
per MOST section 2500 complete in all respects as directed
by the engineer
a) Using stone availble at site (The job include removal
cleaning and stackiing of stone from the damge
locations) and using the same
Unit = cum
Taking output = 1 cum
a a) Labour
Mate day 0.04 244.30 9.77 L-10
Mason day 0.35 264.30 92.51 L-25
Mazdoor day 0.75 224.30 168.23 L-01
Total 270.50
b) Overhead charges @ 8% on (a) 21.64
c) Contractor's profit @ 10% on (a+b) 1.73

Page1of 23
BILL No 1: Road Maintenance
Ref. to Unit Quantity Rate Cost Remarks/In
MOST
S.No MoRT Description Rs Rs put
Data No
H reference
Cost for 1 cum = a+b+c 0.14
Rate per cum = (a+b+c) 133

b Stone/Boulder (Using procurred materials)


Unit = Cum
Taking output = 1 Cum
a) Material
Stone weighing not less than 40kg Cum 1.00 933.88 933.88 M-003
Stone spalls of minimum 25 mm size Cum 0.20 933.88 186.78 M-003
b) Labour
Mate Day 0.04 244.30 9.77 L-10
Masson Day 0.35 264.30 92.51 L-25
Mazdoor Day 0.75 224.30 168.23 L-01
Total 1391.16
c) Overhead chages @ 8% on (a+b) 111.29
d) Contractor's profit @ 10% input on (a+b+c) 150.25
Rate per cum(a+b+c+d) 1652.70
Rate per Cum 895

Clearing, cleaning, deepening and reshaping of roadside


unlined/kaccha drains and making shallow kaccha lateral
1.04 drains on shoulders wherever required, including removal and
disposal of sediments, extraneous debris and vegetation
growth blocking the free f
a) Drains having depth upto 0.6 meter RM
Unit = running metre
Taking output = 1000 metres
Assuming muck causing choking of drain to be 0.2 cum per
metre, quantity of earth to be removed for 10 metres = 2 cum

a) Labour
Mate day 3.00 244.30 732.90 L-10
Mazdoor day 50.00 224.30 11215.00 L-01
b) Machinery
Tractor Trolly hour 4.00 289.00 1156.00 P&M-053
TOTAL 13103.90
c) overhead charge @ 8% i.e on (a+b) 1048.31
d) Add contractor's profit @ 10% i.e on (a+b+c) 1415.22
Cost for 1000 metres = a+b+c+d 15567.43
Rate per metre = (a+b+c+d)/1000 15.57
11
b) Drains having depth more than 0.6 meter RM
Unit = running metre
consider 1000m
a) Labour
Mate Day 4.00 244.30 977.20 L-10
Mazdoor Day 75.00 224.30 16822.50 L-01
b) Machinery
Tractor Trolly hour 6.00 289.00 1734.00 P&M-053
TOTAL 19533.70
c) overhead charge @ 8% i.e on (a+b) 1562.70
d) Add contractor's profit @ 10% i.e on (a+b+c) 2109.64
Cost for 10 metres = a+b+c+d 23206.04
Rate per metre = (a+b+c+d)/1000 23.21
23

Clearing road side/Median open lined/ pucca drains to bring


them to original shape, drainage capacity incuding
1.05 0 305 disposal of sediments, extraneous debris & vegetation
growth blocking the free flow from site outside ROW with
all leads and lifts complete in a
A Drains having cross sectional area upto 0.3 Sqm RM
Consider 1000m
a) Labour
Mate day 4.00 244.30 977.20 L-10
Mazdoor Nos 45.00 224.30 10093.50 L-01
b) Machinery Tractor trolley Hrs 2.00 289.00 578.00 P&M-053

Page2of 23
BILL No 1: Road Maintenance
Ref. to Unit Quantity Rate Cost Remarks/In
MOST
S.No MoRT Description Rs Rs put
Data No
H reference
Total 11648.70
c) overhead charges @ 8% i.e on (a+b) 931.90
d) Add Profit 10% on ( a+b+c) 1258.06
13838.66
Total cost per Rmtr 13.84
14
B Drains having cross sectional area more than 0.3 Sqm RM
Out put per day = 150 Rmt
a) Labour
Mate Nos 0.32 244.30 78.18 L-10
skilled Nos 5.00 264.30 1321.50
unskilled Nos 5.00 224.30 1121.50 L-01
b) Machinery Tractor trolley Hrs 8.00 289.00 2312.00 P&M-053
4833.18
c) Add OH 8% on (a+b) 386.65
d) Add Profit 10% on ( a+b+c) 521.98
For 150 Rmt 5741.81
for Rmt 38

Clearing, longitudinal and transverse covered drains and pipe RM


drains including manholes, gratings, channels and gullies
1.06 etc. & bringing them to original drainage capacity, including
disposal of sediments, extraneous debris & vegetation
growth blocking t
unit=Rmt
Taking output =100Rmt
a) Labour
Mate day 4.00 244.30 977.20 L-10
Mazdoor day 30.00 224.30 6729.00 L-01
b) Machinery
Sluge suction tanker capacity 3 cum (Rate of Bhadrak Cum 45.00 211.86 9533.70 Market rate
municipal)
Total (a+b) 17239.90
d) overhead charges @ 8% i.e on (a+b) 1379.19
e) Add Profit 10% on ( a+b) 1861.91
20481.00
for Rmt 204.81
Say 150

Clearing slab/ box type culverts and pipe culverts including


clearing, cleaning and reshapping of upstream and down
1.07 stream faces of these culverts with in right of way. The job
includes disposal of excess material recovered from site
including vegetation
A) slab / box type culverts
Cleaning up stream & D/stream
Down Stream for 100m each side

a) Labour
Mate Day 0.50 244.30 122.15 L-10
Mazdoor Day 5.00 224.30 1121.50 L-01
b) Machinery
Tractor Hour 1.00 289.00 289.00 P&M-053
Total 1532.65
c) Add OH 8% on (a+b) 122.61
d) Add Profit 10% on ( a+b+c) 165.53
1820.8
Total cost per No / Time 910.39
Say 910
B) Pipe Culverts
Cleaning up Stream & D/stream
Down stream for 100m each side
consider 2 no per/ time
a) Labour
Mate Day 0.50 244.30 122.15 L-10
Mazdoor Day 3.00 224.30 672.90 L-01

Page3of 23
BILL No 1: Road Maintenance
Ref. to Unit Quantity Rate Cost Remarks/In
MOST
S.No MoRT Description Rs Rs put
Data No
H reference
b) Machinery
Tractor Hour 1.00 289.00 289.00 P&M-053
Total (a+b) 1084.05
C) Overhead charges @ 8% i.e on (a+b) 86.72
d) Add Profit 10% on ( a+b+c) 117.08
Total( a+b+c+d) 1287.85
Total cost per No / Time 643.93
Say 644

Carrying out proper cleaning of carriageways, footpaths,


verges, expansion joints (for free movement), drainage spouts
1.08 of bridge including removal and disposal of trash, plastic,
vegetation etc. from site outside ROW complete as per
direction of Engineer.
ROB / Flyover /Bridges
Consider 10m/ Per time
a) Labour
Mate Day 1.00 244.30 244.30 L-10
Mazdoor Day 5.00 224.30 1121.50 L-01
b) Machinery
Air compressor Hrs 0.50 179.13 89.57 P & M-001
Total(a+b) 1455.37
C ) Overhead charges @ 8% i.e on (a+b) 116.43
d) Add Contractor's Profit @ 10% i.e on (a+b+c) 157.18
1728.97
Total cost per m/ time 172.90
Say 173

Loading, unloading, transportation & disposal of surplus Cum.


material left over by accidental vehicle or otherwise lying on
1.09
road (on carriageway) with all lead & lifts complete as directed
by Engineer in Charge.
Taking = cum
Tking output = 5.5 cum
Time required for
i) Poisitioning of tipper at loading point 1Min
ii) Loading by front end loader 1 cum bucket capacity @ 25 13 Min
cum per hour
iii) Maneuvering, revrsig , dumpint and turning for return 2 Min
Total 20Min
a) Machinery
Tipper 5.5 tons capacity Hour 0.33 506.09 167.01 P&M-048
Front end-loader 1 Cum bucket capacity @ 25 cum/ hour Hour 0.33 452.17 149.22 P&M-017
Transpotation assume lead 5Km And density of material 1.5 T.km 41.25
89.51
ton/m3 2.17
Total 405.74
b) Overhead charges @ 8% i.e on (a) 32.46
c) Add Contractor's profit @ 10% i.e on (a+b) 43.82
Total(a+b+c+d) 482.02 87.64
Total cost per cum say 88

Carrying out proper cleaning & removal of dust / silt / thrash /


plastic / rubbish / garbage / waste from the carriageways,
1.10 footpaths, verges (excluding the verges of central median) by
mechanical means and from shoulders up to toe line of the
embankment
A Urban Area (Frequency of cleaning will be monthly)
B Rural Area (Frequency of cleaning will be quarterly)
A) Urban area ( Frequency of cleaning once in a month)

Unit = Per km Km.


Taking Output = 5000sqm
a) Labour
Mate Day 0.20 244.30 48.86 L-10

Page4of 23
BILL No 1: Road Maintenance
Ref. to Unit Quantity Rate Cost Remarks/In
MOST
S.No MoRT Description Rs Rs put
Data No
H reference
Mazdoor Day 2.50 224.30 560.75 L-01
b) Machinery
Machanical broom @ 1250sqm per hour Hour 4.00 230.00 920.00 P & M-031
Tractor Trolly Hour 1.00 289.00 289.00 P&M-053
Total (a+b) 1818.61
c) Overhead charges @ 8% i.e on (a+b) 145.49
d) Add contractor's profit @ 10% i.e on (a+b+c) 196.41
Total (a+b+c+d) 2160.51
For 1 Sqm = Total(a+b+c+d)/5000 0.43
cost per km (B/S) = 2*1000*8.5*0.38 7345.73
Say 7346.00
B) Rural Area ( Frequency of cleaning will be quaterly
Unit = Per km Km.
Taking Output = 5000sqm
a) Labour
Mate Day 0.20 244.30 48.86 L-10
Mazdoor Day 2.50 224.30 560.75 L-01
b) Machinery
Machanical broom @ 1250sqm per hour Hour 4.00 230.00 920.00 P & M-031
Tractor Trolly Hour 1.00 289.00 289.00 P&M-053
Total (a+b) 1818.61
c) Overhead charges @ 8% i.e on (a+b) 145.49
d) Add contractor's profit @ 10% i.e on (a+b+c) 196.41
Total (a+b+c+d) 2160.51
For 1 Sqm = Total(a+b+c+d)/5000 0.43
cost per km (B/S) = 2*1000*8.5*0.38 7345.73
Say 7346.00

Removal of rank vegetation/weeds and undesirable


vegetation from shoulders, embankment slopes upto ROW
1.11 (both sides) complete in all respect including breaking of
clods,rough dressing and disposal of waste material and
vegetation at a place outside ROW as
Shoulders including side slopes of embankment up to toe line Sqm.
on both sides of the carriageway. (Frequency of cleaning will
be four times in a year however limited to only areas prone to
a growth of rank / undesirable vegetation and weeds).
By manual means
Taking aoutput = 8000sqm
a) Labour
Mate Day 6.00 244.30 1465.80 L-10
Mazdoor Day 150.00 224.30 33645.00 L-01
b) Machinery
Tractor - Trolley Hrs 1.00 289.00 289.00 P&M-053
Total (a+b) 35399.80
c) Over head charges @ 8% i.e on ( a+b) 2831.98
D) Add contractor's profit @ 10% i.e on (a+b+c) 3823.18
42054.96
Rate per sqm 5.26
Say 5.00
From Toe line of embankment slopes to ROW on both sides Sqm.
of the carriageway (Frequency of cleaning will be two times in
a year however limited to only areas prone to growth of rank /
b undesirable vegetation and weeds).
By manual means
Taking aoutput = 8000sqm
a) Labour
Mate Day 6.00 244.30 1465.80 L-10
Mazdoor Day 150.00 224.30 33645.00 L-01
b) Machinery
Tractor - Trolley Hrs 1.00 289.00 289.00 P&M-053
Total (a+b) 35399.80
c) Over head charges @ 8% i.e on ( a+b) 2831.98

Page5of 23
BILL No 1: Road Maintenance
Ref. to Unit Quantity Rate Cost Remarks/In
MOST
S.No MoRT Description Rs Rs put
Data No
H reference
D) Add contractor's profit @ 10% i.e on (a+b+c) 3823.18
42054.96
Rate per sqm 5.26
Say 5.00

Providing localized repair to rutted portion or bituminous surface Cum


at scattered location by applying tack coat as per technical
specification Clause 503 and then filling the depression with
1.12
bituminous concrete by using paving grade bitumen conforming
to technical specification clause no. 509, complete in all respect
as directed by the Engineer.
Tack Coat
Taking Output = 3500 Sqm
a) Material
Emulsion @ 0.2 Kg Per Sqm ton 0.70 29860.70 20902.49 M-077
b) Labour
Mate Day 0.08 244.30 19.54 L-10
Mazdoor Day 2.00 224.30 448.60 L-01
c) Machinery
Mechanical broom @ 1250 Sqm per hour Hrs 2.80 230.00 644.00 P&M-031
Air compressor 250cfm Hrs 2.80 179.13 501.56 P&M001
Emulsion pressure distributor @ 1750sqm per hour Hrs 2.00 601.74 1203.48 P&M004
Total (a+b+c) 23719.68
d) overhead charges @8% i.e on (a+b+c) 1897.57
e) Add contractor's profit @ 10% i.e on (a+b+c+d) 2561.73
28178.98
8.05
8.00
Bituminous Concrete cum
Taking out put= 191 Cum (450 tons)
a) Labour
Mate day 0.84 244.30 205.21 L-10
Mazdoor working with HMP,mechanical broom, paver, roller, day 16.00 224.30 3588.80 L-01
skilled mazdoor for checking line and levels day 5.00 264.30 1321.50 L-26
b) Machinery 0.00
Batch Mix HMP @ 75 ton per hour Hrs 6.00 7765.22 46591.32 P&M-023
Paver finisher hydrostatic with sensor control @75 cum per hrs 6.00 1500.00 9000.00 P&M-034
Generator 250kva Hrs 6.00 1125.00 6750.00 P&M-081
Front end loader 1cum bucket capacity Hrs 6.00 452.17 2713.02 P&M-017
Tipper 10ton capacity Ton .Km 450.00 1.74 783.00 P&M-058
Add 10% cost of carriage to cover cost of loading and 78.30
Smooth wheeled roller 8-10 ton for initial breakdown rolling Hrs 3.90 294.78 1149.64 P&M-044
Vibratory roller 8 ton for intermediate rolling Hrs 3.90 864.50 3371.55 P&M-059
Finish rolling with 6-8 ton smooth wheeled tandem roller Hrs 3.90 294.78 1149.64 P&M-044
c) Material
i)Bitumein @ 5% of weight of mix (60 / 70) Ton 22.50 41294.90 929135.25 M-074
ii) Aggregate Total weight of mix = 450 tons
weight of bitumein = 22.5 tons
weight of Aggregate = 450-22.50 =427.50tons
Taking density of aggregate = 1.5 ton/ cum
Volume of Aggregate = 285cum
Grading 1 (19mm nominal size)
20-10mm 35% Cum 99.75 1790.07 178559.48 M-045
10 -5 mm 23% Cum 65.55 1437.69 94240.58 M-040
5mm and below 40% Cum 114.00 1506.26 171713.64 M-030
Filler @ 2% of weight of Aggregate Cum 8.62 5500.00 47410.00 M-188

d) Over head charges @ 8% i.e on ( a+b+c) 119820.88


e) Add contractor's profit @ 10% i.e on (a+b+c+d) 161758.18
1779339.99
Rate per Cum 9315.92
Rate including Tack Coat 9323.92
Say 9324.00

1.13 Same as Item No-1.12 Say 9324.00

Page6of 23
BILL No 1: Road Maintenance
Ref. to Unit Quantity Rate Cost Remarks/In
MOST
S.No MoRT Description Rs Rs put
Data No
H reference

Providing sealing to closely spreaded cracks at scattered Sqm.


locations after sweeping the surface clean and dry, applying
1.14 tack coat of emulsified bitumen @ 0.15 ltr/sqm followed by
distributing slurry evenly in 5mm thickness prepared by mixing
emulsified bit
Slurry Seal
5 mm thickness
Unit = sqm
Taking output = 16000 sqm (80 cum)
Taking density of 2.2 tons per cum
weight of mix = 176 tons
a) Labour
Mate day 0.24 244.30 58.63 L-10
Mazdoor day 6.00 224.30 1345.80 L-01
b) Machinery
Mechanical broom Hrs 6.00 230.00 1380.00 P&M-031
Air compressor 250 cfm Hrs 6.00 179.13 1074.78 P&M-001
Mobile slurry seal equipment Hrs 6.00 565.22 3391.32 P&M-033
Front end loader 1 cum bucket capacity Hrs 6.00 452.17 2713.02 P&M-017
Tipper 5.5 cum capacity for carriage of aggregate from Hrs 6.00 506.09 3036.54 P&M-048
stockpile on road side to slurry equipment, bitumen emulsion
and filler.
Pneumatic tyred roller with individual wheel load not Hrs 6.00 697.39 4184.34 P&M-037
exceeding 1.5 tons
Water tanker 6 KL capacity Hrs 6.00 690.00 4140.00 P&M-060
c) Material
Residual Binder @ 11 per cent of mix 80 x 2.2 x 0.11 ton 19.36 41294.90 799469.26 P&M-074
Fine aggregate 4.75 mm and below 87 per cent of total Cum 102.08 1437.69 146759.40 M-040
Filler @ 2 per cent of total mix = 80 x 2.2 x 0.02 ton 1.16 5500.00 6380.00 M-188
Cost of water KL 12.00 125.00 1500.00 M-189
d) Overhead charges @ 8 % on (a+b+c) 78034.65
e) Contractor's profit @ 10 % on (a+b+c+d) 105346.77
Cost for 16000 sqm = a+b+c+d+e 1158814.51
Rate per sqm = (a+b+c+d+e)/16000 72.43
say 72.00

Providing and applying low viscosity bitumen emulson for


sealing cracks less then 3mm wide or incipient fretting or
1.15 disintigration in an exiting bitumenious surfacing complete as
per MORTH specification section 518 and as per direction of
the engineer in
unit = Sqm
Taking output = 10500sqm
a) Labour
Mate Day 0.12 244.30 29.32 L-10
Mazdoor Day 3.00 224.30 672.90 L-01
b) Machinery
Mechanical broom @ 1250 Sqm per hour Hrs 6.00 230.00 1380.00 P&M-031
Air compressor 250 cfm Hrs 6.00 179.13 1074.78 P&M-001
BitumenEmulsion pressure distributor @ 1750 sqm per hour ton 6.00 601.74 3610.44 P&M-004
c) Material
Bitumen emulsion @ 0.75 kg per sqm ton 7.88 29860.70 235302.32 M-077
Total 242069.75
d) Overhead charges @ 8 % on (a+b+c) 19365.58
e) Contractor's profit @ 10 % on (a+b+c+d) 26143.53
Total (a+b+c+d+e) 287578.87
Rate per sqm= (a+b+c+d+e)/10500 27.39
say 27.00

Providing sealing cracks wider than 3mm using slow curing Rmt
bitumen emulsen @ 0.66 kg per 10 mtrs of the cracks and
1.16
stone crusher screening @ 0.0004 cum/10 mtrs complete as
per direction of the engineer incharge.
Unit = Rmt

Page7of 23
BILL No 1: Road Maintenance
Ref. to Unit Quantity Rate Cost Remarks/In
MOST
S.No MoRT Description Rs Rs put
Data No
H reference
Taking output = 500m
a) Labour
Mate Day 0.04 244.30 9.77 L-10
Mazdoor Day 1.00 224.30 224.30 L-01
b) Material
Slow curing bitumen emulsion kg 33.00 29.86 985.40 M-073
Stone Crusher dust cum 0.02 776.02 15.52 M-021
Total (a+b) 1235.00
c) Over head charges @ 8% i.e on (a+b) 98.80
d) Add contractor's profit @ 10% i.e on (a+b+c) 133.38
Total (a+b+c+d) 1467.17
2.93
say 3.00

Providing treatment to bleeding bituminous surface by uniform


spreading of crusher dust/other fine graded material @ 2.5 kg
1.17 per sqm, properly rolled as per clause 3004.4 of technical
specification complete in all respect and as per direction of
Engineer-i
Unit = Sqm
Taking output 100 Sqm
a) Labour
Mate Day 0.30 244.30 73.29 L-10
Plant Mazdoor Day 6.00 224.30 1345.80 L-01
b) Material
5.6 mm stone aggregate Cum 1.50 1506.26 2259.39 M-050
Bitumen @ 15 Kg/Sqm Mt 0.02 41294.90 825.90 M-074
C) Machinery
Tractor - Trolly Hrs 2.00 289.00 578.00 M-053
Roller Hrs 2.00 294.78 589.56 P&M-044
Boiler Hrs 2.00 111.30 222.60 P&M-005
Sundries Ls 100.00
Total 5994.54
d) Overhead chages @8% i.e on (a+b+c) 479.56
e) Add Contractro's profit @ 10% i.e. on (a+b+c+d) 647.41
7121.51
Rate per Sqm 71.22
say 71.00

Providing treatment and repair to pot holes and patch repairs


of all types of bitumen pavement complete as per technical
1.18
specification Clause 3004.2 and as per the direction of
Engineer.
a Carrying out patchrepair with bitumenious concret up to 25 Sqm.
unit = sqm
Taking output = 10250sqm (256cum) (506 tonnes)
a) Labour
Mate Day 3.76 244.30 918.57 L-10
Mazdoor Day 90.00 224.30 20187.00 L-01
Mazdoor skilled Day 4 264.30 1057.20
b) Machinery
Air compressor 250 cfm Hrs 6.00 179.13 1074.78 P&M-001
HMP 100-110 TPH CAPACITY Hrs 6.00 9710.43 58262.58 P&M-022
Tipper 10 ton Capacity Hrs 45.00 484.35 21795.75 P&M-057
Smooth Wheeled roller 8-10 ton Hrs 12.00 294.78 3537.36 P&M-044
c) Material
Crushed stone aggregates nominal size 13.2mm @ cum 230.50 1838.64 423806.52
Crushed stone aggregates nominal size 11.2mm @0.112 cum 115.31 937.00 108045.47 M-041
Bitumen 60/70 @14.6 Kg/10sqm Ton 14.97 41294.90 618184.65 M-074
Bitumen emulsion emulsion for tack coat including vertical ton 2.46 29860.70 73457.32 M-077
1330327.20
d) overhead charges @ 8% on (a+b+c) 106426.18
e) Contractor's profit @ 10% on (a+b+c+d) 143675.34
cost for 10250 Sqm = a+b+c+d+e 1580428.72
Rate per sqm = (a+b+c+d+e)/10250 154.19

Page8of 23
BILL No 1: Road Maintenance
Ref. to Unit Quantity Rate Cost Remarks/In
MOST
S.No MoRT Description Rs Rs put
Data No
H reference
say 154.00

Carrying out patch repairs with bitumenious concrete up to 40


mm thickness after removal of all failed material, trimming of
completed excavation to provide firm vertical faces, cleaning
surfaces, painting of tack coat on the sides & base of
b excavation a
Taking output = 4800sqm(196 cum)( 450ton)
a)Labour
Mate Day 2.92 244.30 713.36 L-10
Mazdoor Day 70.00 224.30 15701.00 L-01
Mazdoor Skilled Day 3.00 264.30 792.90
b) Machinery
Air compressor 250 cfm Hrs 6 179.13 1074.78 P&M-001
HMP 100-110 TPH CAPACITY Hrs 6.00 9710.43 58262.58 P&M-022
Tipper 10tons capacity Hrs 45.00 484.35 21795.75 P&M-057
Smooth Wheeled roller 8-10 ton Hrs 12.00 294.78 3537.36 P&M-044
c) Material
Bitumen 60-70 ton 22.50 41294.90 929135.25 M-074
Bitumen emulsion for tack coat ton 1.18 29860.70 35235.63 M-077
Aggregates
i) Grading - II 13mm (nominal size)
13.2 - 10 mm 30% cum 85.5 1838.64 157203.72 M-044
10-5mm 25% cum 71.25 1437.69 102435.41
5mm and below 43% cum 122.55 1506.26 184592.16
Filler 2% cum 8.55 3.85 32.88
Add 5% for wastage 22213.21
Total 1532725.99
i)for grading II Material
d) overhead charges @ 8% on (a+b+c) 122618.08
e) Contractor's profit @ 10% on (a+b+c+d) 165534.41
Cost for 4800cum= a+b+c+d+e 1820878.48
rate per sqm= (a+b+c+d+e)/4800 379.35
say 379.00

Filling pot holes and patch repairs beyound 40 mm thickness Sqm.


after removal of all failed materials trimming of completed
excavation to provide firm vertical faces cleaning of surfaces
painting of tack coat on the sides & base of excavation as per
c the claus
Taking output = 4800sqm(367.5 cum)(
848ton)
a)Labour
Mate Day 3.92 244.30 957.66 L-10
Mazdoor Day 140.00 224.30 31402.00 L-01
Mazdoor Skilled Day 5.00 264.30 1321.50
b) Machinery
Air compressor 250 cfm Hrs 7 179.13 1253.91 P&M-001
HMP 100-110 TPH CAPACITY Hrs 7.00 9710.43 67973.01 P&M-022
Tipper 10tons capacity Hrs 90.00 484.35 43591.50 P&M-057
Smooth Wheeled roller 8-10 ton Hrs 24.00 294.78 7074.72 P&M-044
c) Material
Bitumen 60-70 ton 42.18 41294.90 1741818.88 M-074
Bitumen emulsion for tack coat ton 2.21 29860.70 65992.15 M-077
Aggregates
i) Grading - II 13mm (nominal size)
13.2 - 10 mm 30% cum 282.04 1838.64 518570.03 M-044
10-5mm 25% cum 185.33 1437.69 266447.09
5mm and below 43% cum 322.33 1506.26 485512.79
Filler 2% cum 16.11 3.85 61.96 M-188
Add 5% for wastage 63529.59
Total 3295506.78
i)for grading II Material
d) overhead charges @ 8% on (a+b+c) 263640.54
e) Contractor's profit @ 10% on (a+b+c+d) 355914.73

Page9of 23
BILL No 1: Road Maintenance
Ref. to Unit Quantity Rate Cost Remarks/In
MOST
S.No MoRT Description Rs Rs put
Data No
H reference
Cost for 4800cum= a+b+c+d+e 3915062.05
rate per sqm= (a+b+c+d+e)/4800 815.64
say 816.00

Cement concrete of specified mix as under with stone


aggregates 20mm nominal size mechanically mixed and
1.19 vibrated in foundation, sub-structure and superstructure
including shuttering/ formwork conforming to MOST
Specification Clause no. 1000, 1500 & 1700
a) Cement Concrete M15 Grade
PCC Grade M15
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 4.13 5500.00 22715.00 M-081
Coarse sand cum 6.75 638.04 4306.77 M-005
20 mm Aggregate cum 8.10 1790.07 14499.57 M-045
10 mm Aggregate cum 5.40 1838.64 9928.66 M-044
b) Labour
Mate day 0.86 244.30 210.10 L-10
Mason day 1.50 264.30 396.45 L-25
Mazdoor day 20.00 224.30 4486.00 L-01
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 153.91 923.46 P&M-009
Generator 33 KVA hour 6.00 240.00 1440.00 P&M-079
Per Cum Basic Cost of Labour, Material & Machinery 58906.00
(a+b+c)
d) Formwork @ 4 per cent on cost of concrete i.e. 2356
cost of material, labour and machinery
e) Overhead charges @ 8% on (a+b+c+d) 4900.98
f) Contractor's profit @ 10% on (a+b+c+d+e) 6616.32
Cost for 15 cum = a+b+c+d+e+f 72779.54
Rate per cum = (a+b+c+d+e+f)/15 4851.97
say 4852.00

b) PCC M20
Unit : cum
Taking output = 15 cum
a)Material
Cement tonne 5.21 5500.00 28655.00 M-081
Coarse sand cum 6.75 638.04 4306.77 M-005
20 mm Aggregate cum 8.10 1790.07 14499.57 M-045
10 mm Aggregate cum 5.40 1838.64 9928.66 M-044
b) Labour
Mate day 0.86 244.30 210.10 L-10
Mason day 1.50 264.30 396.45 L-25
Mazdoor day 20.00 224.30 4486.00 L-01
c)Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 153.91 923.46 P&M-009
Generator 33 KVA hour 6.00 240.00 1440.00 P&M-079
Per Cum Basic Cost of Labour, Material & Machinery 64846.00
(a+b+c)
d)Formwork @ 4 per cent on cost of concrete i.e. cost 2593.84
of material, labour and machinery
67439.84
e) Overhead charges @ 8% on (a+b+c+d) 5395.19
f)Contractor's profit @ 10% on (a+b+c+d+e) 7283.50
Cost for 15 cum = a+b+c+d+e+f 80118.53
Rate per cum = (a+b+c+d+e+f)/15 5341.24
say 5341.00

Reinforced Cement concret of specified mix as under


with storage aggregates 20 mm nominal size
mechanically mixed and vibrates in foundation,
1.20
substructure and superstructure and superstructure for
thin as well as thick section including shuttering /form

a) RCC M20

Page10of 23
BILL No 1: Road Maintenance
Ref. to Unit Quantity Rate Cost Remarks/In
MOST
S.No MoRT Description Rs Rs put
Data No
H reference
Unit : cum
Taking output = 15 cum
a)Material
Cement tonne 5.21 5500.00 28655.00 M-081
Coarse sand cum 6.75 638.04 4306.77 M-005
20 mm Aggregate cum 8.10 1790.07 14499.57 M-045
10 mm Aggregate cum 5.40 1838.64 9928.66 M-044
b) Labour
Mate day 0.86 244.30 210.10 L-10
Mason day 1.50 264.30 396.45 L-25
Mazdoor day 20.00 224.30 4486.00 L-01
c)Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 153.91 923.46 P&M-009
Generator 33 KVA hour 6.00 240.00 1440.00 P&M-079
Per Cum Basic Cost of Labour, Material & Machinery 64846.00
(a+b+c)
d)Formwork @ 4 per cent on cost of concrete i.e. cost 2593.84
of material, labour and machinery
67439.84
e) Overhead charges @ 8% on (a+b+c+d) 5395.19
f)Contractor's profit @ 10% on (a+b+c+d+e) 7283.50
Cost for 15 cum = a+b+c+d+e+f 80118.53

Rate per cum = (a+b+c+d+e+f)/15 5341.24


say 5341.00

b) RCC Grade M25


Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 6.05 5500.00 33275.00 M-081
Coarse sand cum 6.75 638.04 4306.77 M-005
20 mm Aggregate cum 8.10 1790.07 14499.57 M-045
10 mm Aggregate cum 5.40 1838.64 9928.66 M-044
b) Labour
Mate day 0.86 244.30 210.10 L-10
Mason day 1.50 264.30 396.45 L-25
Mazdoor day 20.00 224.30 4486.00 L-01
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 153.91 923.46 P&M-009
Generator 33 KVA hour 6.00 240.00 1440.00 P&M-079
Per Cum Basic Cost of Labour, Material & Machinery 69466.00
d) Formwork @ 3.75 per cent of a+b+c. 2604.98
e) Overhead charges @ 8% on (a+b+c+d) 5765.68
f) Contractor's profit @ 10% on (a+b+c+d+e) 7783.67
85620.32
cost of 15 cum = a+b+c+d+e+f 85620.32
Rate per cum (a+b+c+d+e+f )/15 5708.02
say 5708.00

RCC M 30 Grade
c) Unit : cum
Taking output = 15 cum
Material
Cement tonne 6.10 5500.00 33550.00 M-081
Coarse sand cum 6.75 638.04 4306.77 M-005
20 mm Aggregate cum 8.10 1790.07 14499.57 M-045
10 mm Aggregate cum 5.40 1838.64 9928.66 M-044
Labour
Mate day 0.90 244.30 219.87 L-10
Mason day 1.50 264.30 396.45 L-25
Mazdoor day 21.00 224.30 4710.30 L-01
Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 153.91 923.46 P&M-009
Generator 33 KVA hour 6.00 240.00 1440.00 P&M-079
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 69975.07
Formwork @ 20 per cent on cost of concrete i.e. cost of material, labour and machinery 13995.01
83970.09
Overhead charges @ 8% on (a+b+c+d) 6717.61

Page11of 23
BILL No 1: Road Maintenance
Ref. to Unit Quantity Rate Cost Remarks/In
MOST
S.No MoRT Description Rs Rs put
Data No
H reference
Contractor's profit @ 10% on (a+b+c+d+e) 9068.77
Cost for 15 cum = a+b+c+d+e+f 99756.46
Rate per cum = (a+b+c+d+e+f)/15 6650.43
say 6650.00

Providing Tor steel reinforcement as per approved design and


drawing including carriage of reinforcement to work site
1.21 ,cutting, bending and binding with annealed wire with cost of
wire, removal of rust ,placing the rod in position all complete
as per TSC.
unit = 1 MT
Taking output = 1MT
a)Material
HYSD bars including 5 per cent overlaps and wastage MT 1.05 55983.00 58782.15
b)Labour for cutting, bending, shifting to site, tying and placing
in position including binding wire
Mate Nos 0.44 244.30 107.49 L-10
Black Smith Nos 3.00 264.30 792.90 L-26
Mazdoor Nos 8.00 224.30 1794.40 L-01
c)Add OH 8% on ( a to b ) 4774.60
d)Add Profit 10% on ( a to c) 6625.15
72876.70
say 72877.00

Dismentaling structure and pavement including disposal of


resultant material and/ salvaging the use of ful material
1.22
complete as per tech specification clause No 202 complete in
all respect as per the direction of the engineer.
a) Plain Concrete
Unit = Cum
Taking Output = 1.25 cum
Dismantling Work

a) Labour
Mate Day 0.05 244.30 12.22 L-10
Mazdoor for dismantling,loading and unloading Day 1.25 224.30 280.38 L-01
b) Machinery
Tractor - Trolly Hrs 0.27 289.00 78.03 P&M-053
Total 370.62
c) Overhead Charges @8% on (a+b) 29.65
d) Contractor'sprofit @ 10% on (a+b+c) 40.03
440.30
352.24
say 352.00
RCC including clearing, straightening and cutting of bars
b)
and separating out of Rcc
Unit = Cum
Taking Output = 1.25 cum
Dismantling Work

a) Labour
Mate Day 0.05 244.30 12.22 L-10
Mazdoor for dismantling,loading and unloading Day 0.25 224.30 56.08 L-01
Blacksmith Day 0.66 264.30 174.44 L-26
Mazdoor with pnematic breaker Day 0.66 224.30 148.04 L-01
b) Machinery
Air compressor 250cfm Hrs 1.00 179.13 179.13 P&M-001
Tractor - Trolly Hrs 0.27 289.00 78.03 P&M-053
Total 647.93
c) Overhead Charges @8% on (a+b) 51.83
d) Contractor'sprofit @ 10% on (a+b+c) 69.98
769.74
615.79
say 616.00

Dismantling of road including wearing courses, basw


courses and sub base courses including stacking of old
1.23
serviceable material complete in all respect as per
direction of engineer

Page12of 23
BILL No 1: Road Maintenance
Ref. to Unit Quantity Rate Cost Remarks/In
MOST
S.No MoRT Description Rs Rs put
Data No
H reference
Dismantling of bitumenous wearing courses includiing
a disposal of the waste material outside ROW as per direction of
Engineer
Unit = Cum
Taking Output = 1 Cum
Bituminous courses
a) Labour
Mate Day 0.06 244.30 14.66 L-10
Mazdoor for dismantling,loading and unloading Day 1.50 224.30 336.45 L-01
b) Machinery
Tractor - Trolly hour 0.38 289.00 109.82 P&M-053
460.93
c) Overhead Charges @8% on (a+b) 36.87
d) Contractor'sprofit @ 10% on (a+b+c) 49.78
547.58
say 548.00
Dismantling of base courses, including stacking of useful
b material at proer location and disposal of unserviceable
material outside ROW as per direction of engineer
Unit = Cum
Taking Output = 1 Cum
Bituminous courses
a) Labour
Mate Day 0.06 244.30 14.66 L-10
Mazdoor for dismantling,loading and unloading Day 1.50 224.30 336.45 L-01
b) Machinery
Tractor - Trolly hour 0.38 289.00 109.82 P&M-053
460.93
c) Overhead Charges @8% on (a+b) 36.87
d) Contractor'sprofit @ 10% on (a+b+c) 49.78
547.58
say 548.00
Dismantling of subbase courses, including stacking of useful
c material at proper location and disposal of unserviceable
material outside ROW as per direction of Engineer
Unit = Cum
Taking Output = 1 Cum
Bituminous courses
a) Labour
Mate Day 0.04 244.30 9.77 L-10
Mazdoor for dismantling,loading and unloading Day 1.00 224.30 224.30 L-01
b) Machinery
Tractor - Trolly hour 0.33 289.00 95.37 P&M-053
329.44
c) Overhead Charges @8% on (a+b) 26.36
d) Contractor'sprofit @ 10% on (a+b+c) 35.58
391.38
say 391.00

Earthwork in excavation necessary for construction of


roadway ,drain including all leads and lifts complet as per
1.24
Technical Specifications Clause No. 305 in ordinary and hard
soil as directed by the Engineer .
Unit = cum
Taking output = 120 cum
a) Labour
Mate day 1.80 244.30 439.74 L-10
Mazdoor day 45.00 224.30 10093.50 L-01
b) Machinery
Truck 5.5 cum capacity hour 10.00 484.35 4843.50 P&M-057
15376.74
c) Overhead charges @ 8 % on (a+b) 1230.14
d) Contractor's profit @ 10 % on (a+b+c) 1660.69
18267.57
Cost of 120 cum = a+b+c+d 18267.57
Rate per cum = (a+b+c+d)/120 152.23
say 152.00

Construction of Embankment with Material obtained from


Borrowpits

Page13of 23
BILL No 1: Road Maintenance
Ref. to Unit Quantity Rate Cost Remarks/In
MOST
S.No MoRT Description Rs Rs put
Data No
H reference
Construction of embankment with approved material obtained
from borrow pits with all lifts and leads, transporting to site,
1.25
spreading, grading to required slope and compacting to meet
requirement of table 300-2.
Unit = cum
Taking output = 100 cum
a) Labour
Mate day 0.04 244.30 9.77 L-10
Mazdoor day 1.00 224.30 224.30 L-01
b) Machinery
Hydraulic Excavator1 cum bucket capacity @ 60 cum per hour 1.67 730.43 1219.82 P&M-026
Tipper 10 tonne capacity tonne.km 160 x L 2.17 5200.00 Lead =13 km
& P&M-058
Add 10 per cent of cost of carriage to cover cost of loading 520.00
Dozer 80 HP for spreading @ 200 cum per hour hour 0.50 1592.17 796.09 P&M-015
Motor grader for grading @ 100 cum per hour hour 1.00 1343.48 1343.48 P&M-032
Water tanker6 KL capacity hour 4.00 690.00 2760.00 P&M-060
Vibratory roller 8 -10 tonnes @ 100 cum per hour hour 1.00 864.50 864.50 P&M-059
c) Material
Cost of water KL 24 125.00 3000 M-189
Compensation for earth taken from private land cum 100 80.00 8000 M-092
Add for seinarage charges cum 100 10 1000
d) Overhead charges @ 8% on (a+b+c) 1995.04
e) Contractor's profit @ 10% on (a+b+c+d) 2693.30
Cost for 100 cum = a+b+c+d+e 29626.29
Rate per cum = (a+b+c+d+e)/100 296.26
say 296.00

Construction of embankment with suitable material obtained


from roadway , drainage excavation, and pavement
1.26 dismantalling etc.. With all leads and lifts complete in all
respect as per Technical specificaations clause no .305 duly
watered, rolled and compa
Unit = Cum
Taking Output = 100 cum
Labour
Mate day 0.02 244.30 4.89 L-10
Mazdoor day 0.50 224.30 112.15 L-01
Machinery
Dozer 80 HP for spreading @ 200 cum per hour hour 0.50 1343.48 671.74 P&M-015
Motor grader for grading @ 100 cum per hour hour 1.00 690.00 690.00 P&M-032
Water tanker 6 KL capacity hour 4.00 690.00 2760.00 P&M-060
Vibratory roller 8 - 10 tonnes @ 100 cum per hour hour 1.00 864.50 864.50 P&M-059
Material
Cost of water KL 24.00 125.00 3000 M-189
8103.28
Overhead charges @ 8% on (a+b+c) 648.26
Contractor's profit @ 10% on (a+b+c+d) 875.15
Cost for 100 cum = (a+b+c+d+e) 9626.69
Rate per Cum = (a+b+c+d+e)/100 96.27
say 96.00

Scarifying existing road surface including bitumenous surface


complete as per Technical Specification clause no. 501,
1.27 including disposal of unserviceable material out side ROW
with all leads and lifts complete in all respect as pe direction of
Engineer-In
Unit = Sqm
Taking Output = 100 Sqm
Labour
Mate day 0.01 244.30 2.44 L-10
Mazdoor day 0.25 224.30 56.08 L-01
Machinery
Tractor with ripper attachment @ 60 Cum per hour hour 0.08 251.30 20.10 P&M-055
Front end laider 1 cum bucket capacity @ 25 cum per hour hour 0.20 452.17 90.43 P&M-017
Tipper 5.5 cum capacity, 4 tips per hour hour 0.23 484.35 111.40 P&M-057
280.46
Overhead charges @ 8% on (a+b+c) 22.44
Contractor's profit @ 10% on (a+b+c+d) 30.29
Cost for 100 cum = (a+b+c+d+e) 333.18
Rate per Cum = (a+b+c+d+e)/100 3.33

Page14of 23
BILL No 1: Road Maintenance
Ref. to Unit Quantity Rate Cost Remarks/In
MOST
S.No MoRT Description Rs Rs put
Data No
H reference
say 3.00

Construction of sub-grade with approved material obtained


from borrow pits with all lifts & leads, transporting to site,
1.28 a
spreading, grading to required slope and compacted to meet
requirement of table No. 300-2
Unit = cum
Taking output = 100 cum
a) Labour
Mate day 0.04 244.30 9.77 L-10
Mazdoor day 1.00 224.30 224.30 L-01
b) Machinery
Hydraulic excavator1 cum bucket capacity @ 60 cum per hour hour 1.67 730.43 1219.82 P&M-026
Tipper 10 tonne capacity tonne.km 175xL 1.74 4550.00 Lead =13km
Add 10 per cent of cost of carriage to cover cost of loading 455.00
Dozer 80 HP for spreading @ 200 cum per hour hour 0.50 1592.17 796.09 P&M-015
Motor grader for grading @ 50 cum per hour hour 2.00 1343.48 2686.96 P&M-032
Water tanker with 6 km lead hour 4.00 690.00 2760.00 P&M-060
Vibratory roller 8-10 tonnes @ 80 cum per hour hour 1.25 864.50 1080.63 P&M-059
c) Material
Cost of water KL 24.00 125.00 3000.00 M-189
Compensation for earth taken from private land cum 100.00 80.00 8000.00 M-092
Add for seinarage charges cum 100.00 10.00 1000.00
25782.56
d) Overhead charges @ 8 % on (a+b+c) 2062.60
e) Contractor's profit @ 10 % on (a+b+c+d) 2784.52
Cost for 100 cum = a+b+c+d+e 30629.68
Rate per cum = (a+b+c+d+e)/100 306
say 306.00

Construction of earthen shoulders with approved


1.28 b
material obtained from borrow pits
Same as that for Subgrde ( Item NO.3.04) cum 306

Providing, laying and compacting granular sub-base (GSB)


1.29 complete as per drawing and Technical specifications clause
401 grading I table 400-1
Unit = cum
Taking output = 300 cum
a) Labour
Mate day 0.48 244.30 117.26 L-10
Mazdoor skilled day 2.00 264.30 528.60 L-C
Mazdoor unskilled day 10.00 224.30 2243.00 L-01
b) Machinery
Motor Grader 110 HP @ 50 cum hour 6.00 1343.48 8060.88 P&M-032
Vibratory roller 8 -10 tonne hour 6.00 864.50 5187.00 P&M-059
Tractor - Rotavator hour 12.00 249.20 2990.40 P&M-054
Water tanker 6 KL capacity hour 3.00 690.00 2070.00 P&M-060
c) Material
Close graded Granular sub-base Material as per table 400-1
For Grading-I Material
53 mm to 9.5 mm @ 50 per cent cum 192.00 1401.50 269088.00 M-013
9.5 mm to 2.36 mm @ 20 per cent cum 76.00 1418.64 107816.64 M-025
2.36 mm below @ 30 per cent cum 115.20 776.02 89397.50 M-021
Cost of water KL 18.00 125.00 2250.00 M-189
489749.29
d) Overhead charges @ 8 % on (a+b+c) 39179.94
e) Contractor's profit @ 10 % on (a+b+c+d) 52892.92
581822.15
Cost for 300 cum = a+b+c+d+e 581822.15
Rate per cum = (a+b+c+d+e)/300

1939.41

Page15of 23
BILL No 1: Road Maintenance
Ref. to Unit Quantity Rate Cost Remarks/In
MOST
S.No MoRT Description Rs Rs put
Data No
H reference
say 1939.00

1.30 Wet Mix Macadam


Providing, laying, spreading and compacting graded stone
aggregate to wet mix macadam specification including
premixing the Material with water at OMC in mechanical mix
plant carriage of mixed Material by tipper to site, laying in
uniform layers with pave
Unit = cum
Taking output = 225 cum (495 tonnes)
a) Labour
Mate day 0.48 244.30 117.26 L-10
Mazdoor skilled day 2.00 264.30 528.60 L-C
Mazdoor day 10.00 224.30 2243.00 L-01
b) Machinery
Wet mix plant of 75 tonne hourly capacity hour 6.60 289.00 1907.40 P&M-094
Electric generator 125 KVA hour 6.00 786.96 4721.76 P&M-018
Front end loader 1 cum capacity hour 6.00 452.17 2713.02 P&M-017
Paver finisher hour 6.00 642.61 3855.66 P&M-035
Vibratory roller 8 - 10 tonne hour 6x0.65 864.50 3371.55 P&M-059
or
Smooth 3 wheeled steel roller @ 8-10 tonnes. hour 12.00
Water tanker 6 KL capacity hour 3.00 690.00 2070.00 P&M-060
Tipper tonne.km 495 x L 1.74 31680.00 Lead =30 km
Add 10 per cent of cost of carriage to cover cost of loading 3168.00
c) Material ( Table 400-11)
45 mm to 22.4 mm@ 30 per cent cum 89.10 1499.59 133613.47 M-034
22.4 mm to 2.36 mm @ 40 per cent cum 118.80 1790.07 212660.32 M-031
2.36 mm to 75 micron@ 30 per cent cum 89.10 776.02 69143.38 M-022
Cost of water KL 18.00 125.00 2250.00 M-189
474043.42
d) Overhead charges @ 8% on (a+b+c) 37923.47
e) Contractor's profit @ 10% on (a+b+c+d) 51196.69
Cost for 225 cum = a+b+c+d+e 563163.58
Rate per cum = (a+b+c+d+e)/225 2502.95
say 2503.00

1.31 Dense Graded Bituminous Macadam


Providing and laying dense graded bituminous
macadam with 100-120 TPH batch type HMP producing
an average output of 75 tonnes per hour using crushed
aggregates of specified grading, premixed with
bituminous binder @ 4.0 to 4.5 per cent by weight of
total
Unit = cum
Taking output = 195 cum (450 tonnes)
a) Labour
Mate day 0.840 244.30 205.21 L-10
Mazdoor working with HMP, mechanical broom, paver, day 16.000 224.30 3588.80 L-13
Skilled mazdoor for checking line & levels day 5.000 264.30 1321.50 L-15
b) Machinery
Batch mix HMP @ 75 tonne per hour hour 6.000 7765.22 46591.32 P&M-023
Paver finisher hydrostatic with sensor control @ 75 cum hour 6.000 1500.00 9000.00 P&M-034
Generator 250 KVA hour 6.000 1125.00 6750.00 P&M-081
Front end loader 1 cum bucket capacity hour 6.000 452.17 2713.02 P&M-017
Tipper 10 tonne capacity tonne.k 450 x L 1.74 28800.00 Lead =32
Add 10 per cent of cost of carriage to cover cost of 2880.00
smooth wheeled roller 8-10 tonnes for initial break down hour 6.00x0.65 294.78 1149.64 P&M-044
Vibratory roller 8 tonnes for intermediate rolling. hour 6.00x0.65 864.50 3371.55 P&M-059
Finish rolling with 6-8 tonnes smooth wheeled tandem hour 6.00x0.65 641.74 2502.79 P&M-045
c) Materials
Bitumen @ 4.25 per cent of weight of mix tonne 19.130 41294.90 789971.44 M-074
Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 19.13 tonnes
Weight of aggregate = 450 -19.13 = 430.87 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 287.25 cum

Grading - II19 mm (Nominal Size)


25 - 10 mm 30 per cent cum 86.160 1838.64 158417.22 M-046

Page16of 23
BILL No 1: Road Maintenance
Ref. to Unit Quantity Rate Cost Remarks/In
MOST
S.No MoRT Description Rs Rs put
Data No
H reference
10 - 5 mm 28 per cent cum 80.430 1437.69 115633.41 M-040
5 mm and below 40 per cent cum 114.900 1506.26 173069.27 M-030
Filler @ 2 per cent of weight of aggregates. tonne 8.620 5500.00 47410.00 M-188
1393375.17
d) Overhead charges @ 8% on (a+b+c) 111470.01
e) Contractor's profit @ 10% on (a+b+c+d) 150484.52
Cost for 205 cum = a+b+c+d+e 1655329.70
Rate per cum = (a+b+c+d+e)/195 (For Grading-II) 8488.87
say 8489.00

Providing laying and compacting bituminous concrete as per


1.32 technical specification clause no 509 Including tack coat as
per technical specification clause no 503
Bituminious Concrete
Unit = Cum
Taking Output = 191 Cum (450 tonnes)
a) Labour
Mate day 0.84 244.30 205.21 L-10
Mazdoor working with HMP, mechanical broom, paver, roller, day 16.00 224.30 3588.80 L-01
Skilled mazdoor for checking line & levels day 5.00 264.30 1321.50
b) Machinery
Batch mix HMP @ 75 tonne per hour hour 6.00 7765.22 46591.32 P&M-023
Paver finisher hydrostatic with sensor control @ 75 cum per hour 6.00 1500.00 9000.00 P&M-034
Generator 250 KVA hour 6.00 1125.00 6750.00 P&M-081
Front end loader 1 cum bucket capacity hour 6.00 452.17 2713.02 P&M-017
Tipper 10 tonne capacity tonne. 450.00 1.74 28800.00 Lead =32
Add 10 per cent of cost carriage to cover cost of loading and 2880.00
Smooth wheeled roller 8-10 tonnes for initial break down hour 3.90 294.78 1149.64 P&M-044
Vibratory roller 8 tonnes for intermediate rolling hour 3.90 864.50 3371.55 P&M-059
Finish rolling with 6-8 tonnes smooth wheeled tandem roller hour 3.90 641.74 2502.79 P&M-045
c) Material
Bitumen @ 5 per cent of weight of mix tonne 22.50 41294.90 929135.25 M-074
Grading - II 19mm(nominal size)
20-10 mm 35% cum 99.75 1790.07 178559.48 M-045
10 - 5 mm 23% cum 65.55 1437.69 94240.58 M-040
5 mm and below 40 % cum 114.00 1506.26 171713.64 M-030
Filler @ 2 per cent of weight of aggregates tonne 5.70 5500.00 31350.00 M-188
1513872.78
d) Overhead charges @ 8% on (a+b+c) 121109.82
e) Contractor's profit @ 10% on (a+b+c+d) 163498.26
Cost for 195 Cum = (a+b+c+d+e) 1798480.87
Rate per Cum = (a+b+c+d+e)/191 9222.98
say 9223.00

Providing and laying Semi Dense Bituminous Concrete


Extra complete as directed by the Engineers per technical
specification Clause 508
Unit = cum
Taking output = 195 cum (450 tonnes)
a) Labour
Mate day 0.840 244.30 205.21 L-10
Mazdoor working with HMP, mechanical broom, paver, roller, day 16.000 224.30 3588.80 L-01
Skilled mazdoor for checking line & levels day 5.000 190.00 950.00
b) Machinery
Batch mix HMP @ 75 tonne per hour hour 6.000 7765.22 46591.32 P&M-023
Paver finisher hydrostatic with sensor control @ 75 cum per hour 6.000 1500.00 9000.00 P&M-034
Generator 250 KVA hour 6.000 1125.00 6750.00 P&M-081
Front end loader 1 cum bucket capacity hour 6.000 452.17 2713.02 P&M-017
Tipper 10 tonne capacity tonne.km 450 x L 0.00 28800.00 Lead =32
Add 10 per cent of cost of carriage to cover cost of loading 2880.00
Smooth wheeled roller 8-10 tonnes for initial break down hour 6.00x0.65* 294.78 1149.64 P&M-044
Vibratory roller 8 tonnes for intermediate rolling. hour 6.00x0.65* 864.50 3371.55 P&M-059
Finish rolling with 6-8 tonnes smooth wheeled tandem roller hour 6.00x0.65* 641.74 2502.79 P&M-045
c) Material
* Grading I: 13 mm (Nominal Size)
i) Bitumen@ 4.5 per cent of weight of mix tonne 20.250 41294.90 836221.73 M-074
ii) Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 20.25 tonnes
Weight of aggregate = 450-20.25 = 429.75 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 286.5 cum

Page17of 23
BILL No 1: Road Maintenance
Ref. to Unit Quantity Rate Cost Remarks/In
MOST
S.No MoRT Description Rs Rs put
Data No
H reference
13.2 - 10 mm20 per cent cum 57.300 1838.64 105354.07 M-044
10 - 5 mm 38 per cent cum 108.870 1437.69 156521.31 M-040
5 mm and below 40 per cent cum 114.600 1506.26 172617.40 M-030
Filler @ 2 per cent of weight of aggregates. tonne 8.620 5500.00 47410.00 M-188
d) Overhead charges @ 8% on (a+b+c) 114130.15
e) Contractor's profit @ 10% on (a+b+c+d) 154075.70
Cost for 205 cum = a+b+c+d+e 1694832.68
Rate per cum = (a+b+c+d+e)/195 (For Grading I) 8691.45
say 8691.00
Providing and laying bituminous primer coat over granular
surface with bituminous emulsion complete as per technical
1.33
specification clause no.502 @ 7.5 kg/10 sqm as per the
direction of Engineer
Unit = Sqm.
Taking Output = 3500 Sqm.
Labour
Mate day 0.08 244.30 19.54 L-10
Mazdoor day 2.00 224.30 448.60 L-01
Machinery
Mechanical broom @ 1250 sqm per hour hour 2.80 230.00 644.00 P&M-031
Air compressor 250 cfm hour 2.80 179.13 501.56 P&M-001
Bitumen pressure distributor @ 1750 sqm per hour hour 2.00 601.74 1203.48 P&M-004
Water tanker 6 KL capacity @ 1 trip per hour hour 1.00 690.00 690.00 P&M-060
Material
Bitumen emulsion SS grade @ 0.6 kg per sqm tonne 2.10 29860.70 62707.47 M-077
Cost of water KL 6.00 125.00 750.00 M-189
66964.66
Overhead charges @ 8% on (a+b+c) 5357.17
Contractor's profit @ 10% on (a+b+c+d) 7232.18
Cost for 3500 sqm = (a+b+c+d+e) 79554.01
Rate per Sqm = (a+b+c+d+e)/3500 22.73
say 23.00

Providing and applying tack coat with bitumen emulsion using


emulsion pressure distributir at the rate of 0.20 Kg per Sqm on
1.34 5.2 503
the prepared bituminous/granular surface cleaned with
mechnical as per technical specification 503.
Unit = sqm
Taking output = 3500 sqm
a) Labour
Mate day 0.08 244.30 19.54 L-10
Mazdoor day 2.00 224.30 448.60 L-01
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 2.80 230.00 644.00 P&M-031
Air compressor 250 cfm hour 2.80 179.13 501.56 P&M-001
Emulsion pressure distributor @ 1750 sqm per hour hour 2.00 601.74 1203.48 P&M-016
c) Material
Bitumen emulsion @ 0.2 kg per sqm tonne 0.70 29860.70 20902.49 M-077
23719.68
d) Overhead charges @ 8 % on (a+b+c) 1897.57
e) Contractor's profit @ 10 % on (a+b+c+d) 2561.73
28178.98
Cost for 3500 sqm = a+b+c+d+e 28178.98
Rate per sqm = (a+b+c+d+e)/3500 8.05
say 8.00

Sealing of crack/porous concrete with Epoxy grout by injection


1.35 through nipples complete as per Clause 2803 of Technical
specification and as per approval of Engineer.
Epoxy Resin
unit = sqm
Taking output = 1sqm
Assuming thickness 25mm
a) Material
Cement kg 25.60 5.50 140.80 M-081
Graded Sand cum 0.06 638.04 38.28 M-005
Wire mesh 50mm X 50mm size of 3mm wire kg 3.20 48.00 153.60 M-192
Epoxy kg 1.07 1550.00 1658.50 Market Rate

Page18of 23
BILL No 1: Road Maintenance
Ref. to Unit Quantity Rate Cost Remarks/In
MOST
S.No MoRT Description Rs Rs put
Data No
H reference
Accelerator compound for guniting @4% weight of cement kg 1.03 142.00 146.26 Market Rate
Add @ 2% cost of material 42.75
b)Labour
Mate Day 0.02 244.30 4.89 L-10
Mason Day 0.06 264.30 15.86 L-25
Mazdor Day 0.22 224.30 49.35 L-01
c)Machinery
Compressor with guniting equipment along with accessories Hrs 0.16 285.00 45.60 P&M-063
Total 2295.88
d) Overheads @ 8% (a+b+c) 183.67
e) contractor's Profit @10% on (a+b+c+d) 247.96
2727.51
say 2728.00

Applying Epoxy mortar over leached honey combad and


spalled concrete surface and spalled concrete surface and
1.36
exposed steel reinforcement complete as per Technical
specification clause 2804 and as per approval of Engineer.
Unit = sqm
Taking output = 10sqm
Assume average 10mm Thickness of epoxy mortar
a) Material
Epoxy resin- hardner mix for prime coat Kg 2.50 310 775.00 Market Rate
Epoxy Mortar Kg 2.20 550 1210.00 Market Rate
Epoxy resin-hardner mix for seal coat Kg 2.00 310 620.00 Market Rate
Add 3% cost of material 78.15
b) Labour
Mate Day 0.04 244.30 9.77 L-10
Skilled Labour Day 0.50 264.30 132.15 L-25
Unskilled Labour Day 0.50 224.30 112.15 L-01
Total(a+b) 2937.22
c) Overhead Charges @8% on (a+b) 234.98
d) contractors Profit @10% on (a+b+c) 317.22
3489.42
348.94
say 349.00

Cement pointing of any design/repair to existing pointing,with


cement mortar1:3 on all types of masonary work in super
1.37
structure/substructure as per MOST specification clause No
1000 & 1300
Cement Mortar 1:3
Unit = 1 Cum
Taking output = 1 Cum
a) Material
Cement Tonne 0.51 5500.00 2805.00 M-081
Sand Cum 1.05 638.04 669.94 M-005
b) Labour
Mate Day 0.04 244.30 9.77 L-10
Mazdoor Day 0.90 224.30 201.87 L-01
Total Material and Labour = (a+b) 3686.58
say 3687.00
ii) pointing on Masonary Work
Unit = 10 Sqm
Taking output = 10 Sqm
a) Material
Cement morter 1:3 Cum 0.03 3687.00 110.61
b) Labour
Mate Day 0.04 244.30 9.77 L-10
Masson Day 0.50 264.30 132.15 L-25
Mazdoor Day 0.50 224.30 112.15 L-01
364.68
Add 5 % of cost of above for scaffolding 18.23
c) Overhead Charges @ 8% i.e on (a+b) 30.63
d) Add contracotr profit @ 10 % i.e (a+b+c) 41.35

Page19of 23
BILL No 1: Road Maintenance
Ref. to Unit Quantity Rate Cost Remarks/In
MOST
S.No MoRT Description Rs Rs put
Data No
H reference
454.90
Rate per Sqm 45.49
say 45.00

Cement pointing of any design/repair to existing pointing,with


cement mortar1:3 on Sone masonary work in super
1.38
structure/substructure as per MOST specification clause No
1000 & 1300
Unit = 10 Sqm
Taking output = 10 Sqm
a) Material
Cement mortar 1:3 Cum 0.06 3687.00 221.22
b) Labour
Mate Day 0.04 244.30 9.77 L-10
Mazdoor Day 0.50 224.30 112.15 L-01
Masson Day 0.50 264.30 132.15 L-25
Total(a+b) 475.29
Add 5% of cost of above for scaffolding 23.76
c) over head charges @ 8% i.e. on (a+b) 39.92
d) Add contracotr profit @ 10 % i.e (a+b+c) 53.90
Total (a+b+c+d) 592.88
Rate per Sqm 59.29
say 59.00

Cement plaster / Repairs to cement plaster in thickness 12-20


mm in cement mortar 1.4 on all types of masonry work in
1.39 Sqm.
suoper structure /substructure at any height as per MOST
clause No 1000 , 1300, ND 1400
a Cement Mortar 1:4 ( 1Cement : 4sand)
unit=1cum
Taking output = 1cum
a)Materials
Cement Ton 0.40 5500.00 2200.00 M-081
sand cum 1.12 638.04 714.60 M-005
b) Labour
Mate Day 0.04 244.30 9.77 L-10
Mazddor Day 0.90 224.30 201.87 L-01
Total (a+b) 3126
Add for scafloding @ 5% of cost of (a+b) 156
c) Overhead Charges @8% on (a+b) 263
d) Add contractor's profit @ 10% i.e. on (a+b+c) 354.516
Total (a+b+c+d) 3899.680
say 3900.00
Rate of 12mm thickness (83.34 Sqm) 46.796
Rate of 20mm thickness (50 SQm) 78.000
Rate for average thickness 62.398
say 62.00

Repair to all types of damaged stone / brick masonry work in


superstructure and superstructure and superstructure
1.40 bridges/ CD works including dismentalling of demaged portion
and reconstructing to match with existing pattern with out
b damaging to the stru
(a) Repair to stone masonry in 1:3 cement sand mortar
I) Dismantling of Brick/Rubble stone Masonry in Cement
Morter
in cement morter
Unit = Cum
Taking output = 1.25 Cum
a) Labour
Mate Day 0.03 244.30 7.33 L-10
Mazdoor for dismantling loading and un loading Day 0.75 224.30 168.23 L-01
b) Machinery
Tractor-Trolly Hour 0.27 289.00 78.03 P&M-053
253.58
c) Over head charges @ 8% i.e on (a+b) 20.29
d) Add Contractor's profit @ 10% i.e on (a+b+c) 27.39

Page20of 23
BILL No 1: Road Maintenance
Ref. to Unit Quantity Rate Cost Remarks/In
MOST
S.No MoRT Description Rs Rs put
Data No
H reference
301.26
241.01
say 241.00
II)Repair ro the all types of damged stone/brick masonry
work
Unit= Cum
Taking output = 1 Cum
a) Material
Brick First Class Each 500.00 3.15 1575.00
Cement Morter 1:3 Cum 0.24 3687.00 884.88 1.37
b) Labour
Mate Day 0.06 244.30 14.66 L-10
Masson Day 0.80 264.30 211.44 L-25
Mazdoor Day 0.80 224.30 179.44 L-01
Total (a+b) 2865.42
Add for scafolding @ 5% of cost of material and labour 143.27
3008.69
c) Overhead charges @ 8% i.e on (a+b) 240.70
d) Add contractor's profit @ 10% i.e on (a+b+c) 324.94
Total (a+b+c+d) 3574.32
say 3574.00
III) Stone Masonary work in cement morter 1:3 for
substructure
Ashlar masory (First Sort)
Plain ashlar
Unit = Cum
Taking output = 1 Cum
a) material
Stone Cum 1.11 933.88 1036.61 M-002
Through and bond stone each 7.00 40.00 280.00 M-182
Cement morter 1:3 Cum 0.33 3687.00 1216.71 1.37
b) Labour for masonry work
Mate Day 0.20 244.30 48.86 L-10
Masson Day 2.50 264.30 660.75 L-25
mazdoor Day 2.50 224.30 560.75 L-01
Total (a+b) 3803.68
Add for scafolding @ 5 % of cost of (a+b) 190.18
3993.86
c) Overhead charges @ 8% i.e on (a+b) 319.51
d) Add contractor's profit @ 10% i.e on (a+b+c) 431.34
say 431.00
Say 2243.50
Rate for Repair and dismantling = (II + III)/2 + I say 2244.00

Construction of Footpaths/ separators/ traffic Islands by


Providing 150 mm thick compacted GSB as per MORTH
5.02 Section 401 & 25mm thick cement concrete grade M-15 base Sqm.
over laid with 25 mm thick M-20 precast cement concrete
chequred tiles in cement mortar 1
Taking output = 300 sqm
a) Labour
Mate Nos 1.36 244.30 332.25 L-10
Mason Nos 4.00 264.30 1057.20 L-25
Mazdoor Nos 30.00 224.30 6729.00 L-01
b) Machinery
Vibratory road roller 8 - 10 tonne @ 60 cum per hour Hrs 0.75 864.50 648.38 P&M-059
Water tanker 6 Kl Capacity @ 1 trip per hour Hrs 2.00 690.00 1380.00 P&M-060
Concrete mixer 0.4/0.28 cum per hour Hrs 6.00 153.91 923.46 P&M-009
c) Material
i) for Granular sub-base material
53 mm to 26.5 mm @ 35% Cum 20.79 1499.59 31176.48
26.5mm to 4.75 mm @ 45% Cum 26.73 1838.64 49146.85
2.36mm below @ 20% Cum 11.88 1506.26 17894.37
ii) For cemnet concrete grade M 15, 7.5 cum
Aggregate 12mm crushed @ 0.9 cum of Concrete Cum 6.75 1790.07 12082.97
Sand @ 0.45 Cum/Cum of Concrete Cum 3.38 638.04 2156.58
Cement Cum 1.88 5500.00 10340.00 M-081

Page21of 23
BILL No 1: Road Maintenance
Ref. to Unit Quantity Rate Cost Remarks/In
MOST
S.No MoRT Description Rs Rs put
Data No
H reference
iii) For Cement Plaster 1:3
Sand Cum 3.84 638.04 2450.07 M-005
Cement Tonne 1.83 5500.00 10065.00 M-081
iv) Pre-cast cement concrete tiles
Tiles size 300 x 300 mm and 25 mm thick Sqm 315.00 355.00 111825.00
V) RCC Pipes
Pipes 200 mm dia 2.5m long for drainage Mtr 22.50 200.00 4500.00
vi) Cost of water KL 12.00 125.00 1500.00
c) Overhead charges @ 8% i.e on (a+b+c) 21136.61
d) Add contractor's profit @ 10% i.e on (a+b+c+d) 28534.42
Cost for 300 sqm = a+b+c+d+e 313878.62
Rate per sqm = (a+b+c+d+e)/300 1046.26
say 1046.00

Replacement of damaged cement concrete chequred tiles


with new 25mm thick M-20 precast cement concrete
1.42 chequrred tiles on the already prepared/existing base with 1:3
cement sand mortar. The joint of the tiles to be bonded &
finished with neat cement slurr
i) Dismantling of Cement concrete tiles
in cement morter
Unit = Sqm
Taking Out put = 50 Sqm
a) Labour
Mate Day 0.03 244.30 7.33 L-10
Mazdoor for dismantling, loading and unloading Day 0.75 224.30 168.23 L-01
b) Machinery
Tractor - trolly Hour 0.27 289.00 78.03 P&M-053
Total (a+b) 253.58
c) Overhead charges @ 8% i.e. on (a+b) 20.29
d) Add contractor's profit @ 10% i.e on (a+b+c) 27.39
Total (a+b+c+d) 301.26
Rate per Sqm 6.03
say 6.00
Replacement of chequred tiles
Unit = Sqm
Taking output = 300 Sqm
a) Labour
Mate Day 1.36 244.30 332.25 L-10
Mason Day 4.00 264.30 1057.20 L-25
Mazdoor Day 30.00 224.30 6729.00 L-01
b) Material
iii) For Cement Plaster 1:3
Sand Cum 3.84 638.04 2450.07 M-005
Cement Tonne 1.83 5500.00 10065.00 M-081
iv) Pre-cast cement concrete chequred tiles
Tiles size 300 x 300 mm and 25 mm thick Sqm 315.00 170.87 53824.05
Cost of water KL 12.00 125.00 1500.00 M-189
75957.57
c) Over head charges @ 8% i.e. on (a+b) 6076.61
d) Contractors profit @ 10% on (a+b+c) 8203.42
Total 90237.60
Rate per SQm = (a+b+c+d)/300 300.79
say 301.00

Dismantaling of existing damaged Expansion joints and


providing and fixing of a new strip seal expansion joint
1.43 catering to maximum horizontal movement up to 70 mm
complete and to be installed by the manufacture/supplier/their
authorised representative ens
Replacement of Expansion joints
Unit = 1Rmt
Taking out put = 12 Rmt
a) Material
Epoxy for bonding new concrete to old concrete @ 0.8 kg/sqm 14880.00
kg 9.6 1550
Concrete M 30 Cum 3.6 6650.00 23940.00 1.20©
b) Labour

Page22of 23
BILL No 1: Road Maintenance
Ref. to Unit Quantity Rate Cost Remarks/In
MOST
S.No MoRT Description Rs Rs put
Data No
H reference
Removal of old expansion joint including breaking of
concrete,cutting of lugs and shifting of broken materials etc
Mate Day 0.26 244.30 63.52 L-10
Mazdoor Day 6 224.30 1345.80 L-01
Mazdoor (skilled) Day 0.5 264.30 132.15 L-25
40361.47
c) Over head charges @ 8% i.e. on (a+b) 3228.92
d) Contractor profits @ 10% on (a+b+c) 4359.04
Total 47949.42
Per Rmt 3995.79
Strip seal Expansion joint
unit = Rmt
Taking out put = 12 m
a) Labour
Mate day 0.05 244.30 12.22 L-10
Mazdoor Day 1 224.30 224.30 L-01
Mazdoor (skilled) Day 0.25 264.30 66.08 L-25
b) Material
Supply of complete assembly of strip seal expansion joint
comprising of edge beams,anchorage,strip seal elements and
RM 12 8500.00 102000.00
complete accessories as per approved specification and
drawings. M-178
Add 5% of cost of material for anchorage 5100.00
reinforcement,welding and other incedents
107402.59
c) Over head charges @ 8% i.e. on (a+b) 8592.21
d) Contractor profits @ 10% on (a+b+c) 11599.48
Total 127594.28
Per Rmt 10632.86
Total cost of Replacement=(dismantaling+Fixing) 14628.64
say 14629.00

Page23of 23
NATIONAL HIGHWAYS AUTHORITY OF INDIA RATE ANALYSIS

BILL NO - 2
ROAD PROPERTY MANAGEMANT AND OTHER MAINTENANCE
Sr No Ref. to Description Unit Quantity Rate Cost Remarks/ Input
MoRTH Rs Rs ref.
Spec.
2.01 124 Providing planting healthy well developed saplings of ornaments
flowering shurbs of specified species and varities 1-2 years of
No
age in 25 c m- 30 cm poly bags or pots,height and spread 0.60
mt-0.90 mt above ground,with 3-4 branches,in well prepared pit
Unit = Each
Taking output =666Nos
a) Labour
Mate day 1.20 244.30 293.16 L-10
Mazdoor day 12.00 224.30 2691.60 L-01
b) Machinery
Water Tanker 6Kl Capacity Hour 6.00 690.00 4140.00 P&M-060
C) Material
Plant Each 666.00 25.00 16650.00 M-100
Manure Sludge / Farm yard manure cum 63.64 100.00 6364.00
Pesticide Kg 0.50 136.00 68.00 M-136
Cost of Water KL 36.00 125.00 4500.00 M-189
Total (a+b+c) 34706.76
d) Overhead charges @ 8% i.e. on (a+b+c) 2776.54
e) Add contractor's profit @10% i.e on (a+b+c+d) 3748.33
41231.63
61.91
Say 62.00

2.02 Maintenance of new plantation (Item no 2.1) by basin making


weeding- Hoeing, cleaning , levelling and dressing of median
uprooting and removal ROW regularly to keep the median clean
and plantation in healthy and good condition. The job also
includes the
a) Watering of each plants as and when required depending
upon the climatic conditionsof the locality / region / season /
strictly as per direction of engineer in charge. Km.Length of
maintenance will be decided considering density of existing
plants as 6
b)Application of FYM or sludge @ 1/2 cuft or 10 Kg/plant two
times a yearduring february / march and October / November
plus 20 grams of NPK(12:32:16) or Bonemeal per plants two
times a year as detailed above.
c)Application of insecticide / pesticide / fungicide etc for control of
insects pests and diseases as and when required as per
direction of engineer.
d)Trimming and pruning of all shurbs / plants as and when
required to give them required shape , size and spread.
e) Replacement of dead , damaged plants from the median by
healthy & well developed plant of similar species , varieties , age
and size etc within 10 days of occurrence of casuality as noticed
/ reported or as directed by the engineer.
Note: The quoted rates shall be adjusted as per actual density of
plants per km.at site or alternatively the maintenance of newly
planted plants shall be accounted for under this item.
Unit = per month
Taking output = 12 month
a) Labour
Mate Day 36.00 244.30 8794.80 L-10
Mazdoor Day 365.00 224.30 81869.50 L-01
b) Machinery
Water Tanker 6Kl Capacity Hour 90.00 690.00 62100.00 P&M-060
C) Material
Manure Sludge / Farm yard manure cum 18.85 100.00 1885.00
Cost of Water Kl 36.00 125.00 4500.00 M-189
Replacement of casualities @ 10%

Bill No.A2
1
NATIONAL HIGHWAYS AUTHORITY OF INDIA RATE ANALYSIS

Sr No Ref. to Description Unit Quantity Rate Cost Remarks/ Input


MoRTH Rs Rs ref.
Spec.
Shrubs each 67.00 15.00 1005.00
Pesticide Kg 1.50 136.00 204.00 M-136
Total (a+b+c) 160358.30
d) Overhead charges @ 8% i.e. on (a+b+c) 12828.66
e) Add contractor's profit @10% i.e on (a+b+c+d) 17318.70
190505.66
15875.47
Say 15875.00
Amount @ no. of plants 23.84
Say 24.00

2.03 Maintenance of median and the existing plants In it (with a


density of 666 plants per Km ) by basin making weeding- Hoeing,
cleaning , levelling and dressing of median uprooting and
removal ROW regularly to keep the median clean and plantation
in healthy
a) Watering of each plants as and when required depending
upon the climatic conditionsof the locality / region / season /
strictly as per direction of engineer in charge. Km.Length of
maintenance will be decided considering density of existing
plants as 6
b)Application of FYM or sludge @ 1/2 cuft or 10 Kg/plant two
times a yearduring february / march and October / November
plus 20 grams of NPK(12:32:16) or Bonemeal per plants two
times a year as detailed above.
c)Application of insecticide / pesticide / fungicide etc for control of
insects pests and diseases as and when required as per
direction of engineer.
d)Trimming and pruning of all shurbs / plants as and when
required to give them required shape , size and spread.
e) Replacement of dead , damaged plants from the median by
healthy & well developed plant of similar species , varieties , age
and size etc within 10 days of occurrence of casuality as noticed
/ reported or as directed by the engineer.
Note: The quoted rates shall be adjusted as per actual density of
plants per km.at site or alternatively the maintenance of newly
planted plants shall be accounted for under this item.
Unit = per month
Taking output = 12 month
a) Labour
Mate Day 36.00 244.30 8794.80 L-10
Mazdoor Day 365.00 224.30 81869.50 L-01
b) Machinery
Water Tanker 6Kl Capacity Hour 90.00 582.00 52380.00 P&M-060
C) Material
Manure Sludge / Farm yard manure cum 18.85 150.00 2827.50
Cost of Water Kl 36.00 125.00 4500.00 M-189
Replacement of casualities @ 10%
Shrubs each 67.00 15.00 1005.00
Pesticide Kg 1.50 136.00 204.00 M-136
Total (a+b+c) 151580.80
d) Overhead charges @ 8% i.e. on (a+b+c) 12126.46
e) Add contractor's profit @10% i.e on (a+b+c+d) 16370.73
Total(a+b+c+d+e) 180077.99
Total per month 15006.50
Say 15006.00

2.04 Supplying and turfing with live ande perinnal turforming grass on
embankment slopes, verges medians and other locations
conforming to Technical Specification clause 307 including
watering and maintaining for entire contract period with periodical
mowing c
A) Maintenance of Truffing of slopes

Bill No.A2
2
NATIONAL HIGHWAYS AUTHORITY OF INDIA RATE ANALYSIS

Sr No Ref. to Description Unit Quantity Rate Cost Remarks/ Input


MoRTH Rs Rs ref.
Spec.
Unit = Sqm
Taking Output = 100 Sqm
a) Labour
Mali Day 0.12 264.30 31.72 L-38

b) Machinery
Water tanker 6 KL capacity hour 2.00 690.00 1380.00 P&M-060
c) Material
Cost of water KL 12.00 125.00 1500.00 M-189
2911.72
d) Overhead charges @ 8% i.e. on (a+b+c) 232.94
e) Add contractors profit @ 10% i.e. on (a+b+c+d) 291.17
3435.82
Rate per Sqm 34.36
Say 34.00

2.05 a White wash/ cement paint/ snowcem in two or more coats to give
an even shade and smooth surface for protection of exposed
concrete/masonary portion of Bridges/CD works, kerb and wheel
guard including scraping of damage paint from old surface and
repairin
White washing two coats on existing surface
Unit = Sqm
Taking output = 93 Sqm
a) Material
Shell lime unsoaked Kg 23.32 14.00 326.48
b) Labour
Painter(Semi Skilled) Day 1.50 0.00 0.00 L-11
Man mulia Day 1.00 224.30 224.30 L-01
550.78
Add 10% of cost of material and labour 55.08
605.86
c) Overhead charges @ 8% on (a+b) 48.47
d) contractors profit @ 10 % on (a+b+c) 65.43
Total (a+b+c+d) 719.76
7.74
Rate per Sqm Say 8.00
b Finishing walls with exterior decorative cement based paint such
as snowcern on old work, two coats to give an even shade after
Sqm
repairing of defects so as to achieve smooth and defects free
surface.
Water proofing cement paint of approved brand and
manufacture
Out put 10 sqm,unit 1 sqm
a) Material
Water proofing Paint lit 2.00 47.50 95.00
b) Labour
Mate No 0.03 244.30 7.33 L-10
Painter No 0.50 264.30 132.15 L-29
unskilled No 0.25 224.30 56.08 L-01
290.55
c ) Add OH 8% on (a+b) 23.24
d ) Add Profit 10% on ( a+b+c) 31.38
Total for 10 sqm 345.18
For 1 sqm 34.52
Say 35.00

Bill No.A2
3
NATIONAL HIGHWAYS AUTHORITY OF INDIA RATE ANALYSIS

Sr No Ref. to Description Unit Quantity Rate Cost Remarks/ Input


MoRTH Rs Rs ref.
Spec.
2.06 a Painting with higloss synthetic enemal paint two coats to give an
even and smooth surface for protection of exposed
concrete/masonary portion of Bridges/CD works/ parapet, kerb
painting and repairing wherever necessary, complete as per
approval of Enginee
Old existing surface Sqm
Unit = Sqm
Taking output = 40 Sqm
a) Labour
Mate day 0.12 244.30 29.32 L-10
Painter day 2.00 264.30 528.60 L-29
Mazdoor day 1.00 224.30 224.30 L-01
b) Material
Paint conforming to requirement of clause 803.3 litre 6.00 145.00 870.00 M-131
Add @ 1% on cost of material for scaffolding 8.70
Total (a+b) 1660.92
Add @ 5% cost of labour and materials to prepare the surface by 83.05
filling putty roughness on the surface and priming the surface
before laying 2 coats of painting
c) Overheads @ 8% on (a+b) 139.52
d) Contractor's profit @ 10% on (a+b+c) 188.35
Cost for 40 Sqm = a+b+c+d 2071.83
Rate per Sqm = (a+b+c+d)/40 51.80
Rate per Sqm Say 52.00

b New Surface after applying priming coat with cement primer


(two coat) of approved Quality
Unit = Sqm
Taking output = 40 Sqm
a) Labour
Mate Day 0.12 244.30 29.32 L-10
Painter Day 2.00 264.30 528.60 L-29
mazdoor Day 1.00 224.30 224.30 L-01
b) Material
paint conforming to requirement of clause 803.3 Litre 7.25 145.00 1051.25 M131
Add for scaffolding @ 1% of labour cost where required 10.51

Total (a+b) 1843.98


Add @ 5% cost of labour and materials to prepare the surface by 92.20
filling putty roughness on the surface and priming the surface
before laying 2 coats of painting
c) Overhead Charges @ 8% on (a+b) 154.89
d) Contractor's Profit @ 10% on (a+b+c) 209.11
2300.18
Rate Per Sqm 57.50
Say 58.00
Rate for Bridge Railling Painting (Add 10% for Scaffolding) Say 63.80

Say 64.00

2.07 Painting all types of M.S/G.I railling as when required with two
coats of synthetic enamel paint of approved brand after cleaning
the surface complete in all respect as directed by the Engineer
On Existing Railling
painting on steel surface
Providing and applying two coats of ready mix paint of approved
brand on steel surface after through cleaning of surface to give
and even shade
Unit = Sqm
Taking output = 10 Sqm
a) Labour

Bill No.A2
4
NATIONAL HIGHWAYS AUTHORITY OF INDIA RATE ANALYSIS

Sr No Ref. to Description Unit Quantity Rate Cost Remarks/ Input


MoRTH Rs Rs ref.
Spec.
Mate Day 0.03 244.30 7.33 L-10
Painter Day 0.45 264.30 118.94 L-29
Mazdoor Day 0.25 224.30 56.08 L-01
b) Material
paint ready mixed approved brand litre 1.25 145.00 181.25 M131
Add @ 8% on cost of material for scaffolding and brushes 14.50
etc.
Total (a+b) 378.09
c) overhead chrge @ 8% on (a+b) 30.25
d) Contractor's Profit @ 10% on (a+b+c) 40.83
449.17
Rate per Sqm 44.92
Say 45.00
B on new surface after applying two coat of metallic primer of
approved quality and make
Metallic Primer
Unit = Sqm
Taking output = 10 Sqm
a) Labour
Mate Day 0.03 244.30 7.33 L-10
Painter Day 0.45 264.30 118.94 L-29
Mazdoor Day 0.25 224.30 56.08 L-01
b)Material
paint ready mixed approved brand litre 1.25 98.00 122.50 M198
Add @ 5% on cost of material for scaffolding and brushes etc. 6.13

Total (a+b) 310.96


c) overhead chrge @ 8% on (a+b) 24.88
d) Contractor's Profit @ 10% on (a+b+c) 33.58
369.43
Rate per Sqm 36.94
Say 37.00
Enamel Paint
Unit = Sqm
Taking Output = 10 Sqm
a) Labour
Mate Day 0.03 244.30 7.33 L-10
Painter Day 0.45 264.30 118.94 L-29
Mazdoor Day 0.25 224.30 56.08 L-01
b)Material
paint ready mixed approved brand litre 1.25 145.00 181.25 M131
Add @ 5% on cost of material for scaffolding and brushes etc. 9.06

Total (a+b) 372.65


c) overhead chrge @ 8% on (a+b) 29.81
d) Contractor's Profit @ 10% on (a+b+c) 40.25
442.71
Rate per Sqm 44.27
Say 44.00
Rate with Metallic Primer and Enamel Paint Say 81.00

2.08 Painting two coats on steel structure to give and even shade and
smooth surface as per direction of Engineer-In-Charge
a) Old Existing Surface
Painting on steel surface
Providing and applying two coats of ready mix paint of approved
brand on steel surface after through cleaning of surface to give
and even shade
Unit = Sqm
Taking output = 10 Sqm

Bill No.A2
5
NATIONAL HIGHWAYS AUTHORITY OF INDIA RATE ANALYSIS

Sr No Ref. to Description Unit Quantity Rate Cost Remarks/ Input


MoRTH Rs Rs ref.
Spec.
a) Labour
Mate Day 0.03 244.30 7.33 L-10
Painter Day 0.45 264.30 118.94 L-29
Mazdoor Day 0.25 224.30 56.08 L-01
b) Material
paint ready mixed approved brand litre 1.25 145.00 181.25 M131
Add @ 8% on cost of material for scaffolding and brushes 14.50
etc.
Total (a+b) 378.09
c) overhead chrge @ 8% on (a+b) 30.25
d) Contractor's Profit @ 10% on (a+b+c) 40.83
449.17
Rate per Sqm 44.92
Say 45.00
b)New surface after applying two coat of metallic primer of
approved quality and make
Metallic Primer
Unit = Sqm
Taking output = 10 Sqm
a) Labour
Mate Day 0.03 244.30 7.33 L-10
Painter Day 0.45 264.30 118.94 L-29
Mazdoor Day 0.25 224.30 56.08 L-01
b)Material
paint ready mixed approved brand litre 1.25 98.00 122.50 M198
Add @ 5% on cost of material for scaffolding and brushes etc. 6.13

Total (a+b) 310.96


c) overhead chrge @ 8% on (a+b) 24.88
d) Contractor's Profit @ 10% on (a+b+c) 33.58
369.43
Rate per Sqm 36.94
Say 37.00
Enamel Paint
Unit = Sqm
Taking Output = 10 Sqm
a) Labour
Mate Day 0.03 244.30 7.33 L-10
Painter Day 0.45 264.30 118.94 L-29
Mazdoor Day 0.25 224.30 56.08 L-01
b)Material
paint ready mixed approved brand litre 1.25 145.00 181.25 M131
Add @ 5% on cost of material for scaffolding and brushes etc. 9.06

Total (a+b) 372.65


c) overhead chrge @ 8% on (a+b) 29.81
d) Contractor's Profit @ 10% on (a+b+c) 40.25
442.71
Rate per Sqm 44.27
Say 44.00
Rate with Metallic Primer and Enamel Paint Say 81.00

2.09 Cleaning, removing, clearing of dust and dirt from the existing
metal crash barrier and pedestrian guard rail by washing with
water & detergent etc. complete as directed by Engineer.

Output - 1000m per day


A) Labour
I) Mate: Nos 0.50 244.30 122.15 L-10
ii) Semi Skilled Nos 2.00 244.30 488.60 L-19

Bill No.A2
6
NATIONAL HIGHWAYS AUTHORITY OF INDIA RATE ANALYSIS

Sr No Ref. to Description Unit Quantity Rate Cost Remarks/ Input


MoRTH Rs Rs ref.
Spec.
ii) Unskilled Nos 4.00 224.30 897.20 L-01

B) Material
Chemical cleaner for Removal of posters L.S 400.00
C) Machinery
i) Water Tanker Hrs 3.00 690.00 2070.00 P&M-060
Total of (A + B + C) 3977.95
Add overhead 8% on Total of ( a + b + c) 318.24
Contractor profit 10% on Total of ( a to d ) 429.62
4725.80
4.73
Rate per Metre Say 5.00

2.10 Carrying out routine maintenance to all types of road signs


complete as directed by the Engineer and as per Additional
Maintenance Standard clause 5.5.3 of the bid documents.
Road sign marked - Single post
Output - 25 Nos per day
a) Labour
I) Mate: Nos 0.10 244.30 24.43 L-10
Mazdoor Nos 3.00 224.30 672.90 L-01
sundries @ 1% 6.97
704.30
b) overhead 8% on Total of ( a ) 56.34
c) Contractor profit 10% on Total of ( a + b) 76.06
836.71
33.47
Rate per No. / month Say 33.00
Road sign marked - Double post
Rate for double posts = 1.5 X13 Nos 1.50 33.00 49.50
Say 50.00
Overhead gantry road sign boards
Unit = Per no/Month
Tking output = 1Nos
a) Labour
Mate Day 0.10 244.30 24.43 L-10
Mazdoor Day 3.00 224.30 672.90 L-01
sundries @ 1% 6.97
704.30
b) Overhead Charge @ 8% on (a) 56.34
c) Contractor's Profit @ 10% on (a+b) 76.06
836.71
Say 837.00

2.11 Carrying out repair to road signs including strengthening


resetting or otherwise repairing signs made out of retro reflective
sheets. Job includes patch repair to aluminium sheet , R R sheet
, posts , signs / scripts and repainting of posts at damaged loc
a) Road sign Boards mounted onsingle post
unit = No
Taking output = 3nos
a) Labour
Mate day 0.01 244.30 2.44 L-10
Mazdoor day 0.50 224.30 112.15 L-01
Blacksmith day 0.50 264.30 132.15 L-26
b) Material
Angle 1.5m kg 10.20 51.54 525.73 M-126
Paint 3 nos Sqm 1.28 45.00 57.60 Item-2.08

Bill No.A2
7
NATIONAL HIGHWAYS AUTHORITY OF INDIA RATE ANALYSIS

Sr No Ref. to Description Unit Quantity Rate Cost Remarks/ Input


MoRTH Rs Rs ref.
Spec.
c) Machinery
Tractor Trolly Hour 0.25 289.00 72.25 P&M-053
Welding transformer Hour 0.25 112.00 28.00 Market rate
Generator 33kva Hour 0.25 240.00 60.00 P&M-079
990.32
b) Overhead Charge @ 10% on (a) 99.03
c) Contractors Profit @ 10% on (a+b+c+d) 108.94
1198.29
399.43
Rate Per No say 399.00
b) Road Sign Boards Mounted on double post
Taking output = 3nos
a) Labour
Mate day 0.02 244.30 4.89 L-10
Mazdoor day 0.80 224.30 179.44 L-01
Blacksmith day 0.80 264.30 211.44 L-26
b) Material
Angle 1.5m kg 20.40 51.54 1051.46 M-126
Paint 3 nos Sqm 2.56 45.00 115.20 Item-2.08
c) Machinery
Tractor Trolly Hour 0.25 289.00 72.25 P&M-053
Welding transformer Hour 0.25 112.00 28.00 Market rate
Generator 33kva Hour 0.25 240.00 60.00 P&M-079
1722.67
b) Overhead Charge @ 8% on (a) 137.81
c) Contractors Profit @ 10% on (a+b+c+d) 186.05
2046.54
682.18
Rate Per No say 682.00

2.12 Painting two coats on old surface after minor repairs to give an
even and smooth surface and printing letters and figures with 1st
quality synthetic enamel paint of approved brand and
manufacture complete in all respect conforming to respective
IRC specif
A) Hectometer Stones
unit = Sqm
Taking output = 40sqm
a) Labour
Mate Day 0.12 244.30 29.32 L-10
Painter Day 2.00 264.30 528.60 L-29
Mazdoor Day 1.00 224.30 224.30 L-01
b)Material
Paint conforming to requirement of clause 803.3 Litre 6.00 145.00 870.00 M131
Add for scafolding @ 20% cost of albour where required and for 156.44
letter writing
Total 1808.66
c) Overhead Charge @ 8% on (a+b) 144.69
d) Contractor's Profit @ 10% on ( a+b+c) 195.34
2148.69
53.72
say 54.00
Hectometer Stones area of 0.35sqm 18.90
say 19.00
B) Kilometer Stones
Kilometer stones area of 0.8 sqm sqm 0.80 54.00 43.20
say 43.00
C)5th Kilometer stones
5th kilometer stones area of 1.65 sqm sqm 1.65 54.00 89.10

Bill No.A2
8
NATIONAL HIGHWAYS AUTHORITY OF INDIA RATE ANALYSIS

Sr No Ref. to Description Unit Quantity Rate Cost Remarks/ Input


MoRTH Rs Rs ref.
Spec.
say 89.00
D) Boundary Stones
Boundary stones Area of 0.4Sqm Sqm 0.40 54.00 21.60
say 22.00

2.13 Providing and fixing reinforced cement concrete M-15 grade and
5th kilometer stones and hectometer stones of standard desing
as per IRC -8-1980 & MORTH specification clause 804 including
two coat painting with synthetic enamel paint after applying
approve
a) Hectometre Stones
Unit = Nos
Taking Output = 33 Nos
a) M 15 Grade of concrete Cum 1.58 4852.00 7666.16 1.19(a)
b) Steel reinforcement @ 5 Kg per Sqn(basic rate of 2.08) Kg 66.00 55.98 3694.88
c) Excavation in soil for foundation Cum 1.39 152.00 211.28 1.24
d) Painting two coats on concrete surface Sqm 6.27 81.00 507.87 Item-2.08(b)
Per
e) Lettering on Km Post(average 1 letter of 10 cm height 330.00 0.47 155.10
Cm/letter
Transportation and fixing
f) Labour
mate Day 0.34 244.30 83.06 L-10
Mason Day 1.50 264.30 396.45 L-25
Mazdoor Day 7.00 224.30 1570.10 L-01
g) Machinery
Tractor- Trolly Hour 6.00 200.87 1205.22 P&M-053

h) Overhead @ 8% on (f+g) 260.39


i) Contractor's profit @ 10% on (f+g+h) 26.04
Cost of 33 nos hectometer stone = (a+b+c+d+e+f+g+h+i) 15776.55
Rate of each hectometer stone = (a+b+c+d+e+f+g+h+i)/33 478.08
Per Nos say 478.00
b) Kilometer Stones
Unit = Nos
Taking Output = 14 Nos
a) M 15 Grade of concrete Cum 3.77 4852.00 18292.04 1.19(a)
b) Steel reinforcement @ 5 Kg per Sqn(basic rate of 2.08) Kg 26.32 55.98 1473.47
c) Excavation in soil for foundation Cum 2.77 152.00 421.04 1.24
d) Painting two coats on concrete surface Sqm 11.41 81.00 924.21 Item-2.08(b)
Per
e) Lettering on Km Post(average 12 letter of 10 cm height 1680.00 0.47 789.60
Cm/letter
Transportation and fixing
f) Labour
mate Day 0.32 244.30 78.18 L-10
Mason Day 1.00 264.30 264.30 L-25
Mazdoor Day 7.00 224.30 1570.10 L-01
g) Machinery
Tractor- Trolly Hour 6.00 289.00 1734.00 P&M-053

h) Overhead @ 8% on (f+g) 291.73


i) Contractor's profit @ 10% on (f+g+h) 393.83
Cost of 14nos Kilometer stone = (a+b+c+d+e+f+g+h+i) 26232.49
Rate for each KM stone = (a+b+c+d+e+f+g+h+i)/14 1873.75
say 1874.00
C) 5th Kilometere stones
Unit = Nos
Taking Output = 6 Nos
a) M 15 Grade of concrete Cum 2.35 4852.00 11402.20 1.19(a)
b) Steel reinforcement @ 5 Kg per Sqn(basic rate of 2.08) Kg 22.08 55.98 1236.10

Bill No.A2
9
NATIONAL HIGHWAYS AUTHORITY OF INDIA RATE ANALYSIS

Sr No Ref. to Description Unit Quantity Rate Cost Remarks/ Input


MoRTH Rs Rs ref.
Spec.
c) Excavation in soil for foundation Cum 1.68 152.00 255.36 1.24
d) Painting two coats on concrete surface Sqm 9.85 81.00 797.85 Item-2.08(b)
Per
e) Lettering on Km Post(average 1 letter of 10 cm height 1800.00 0.47 846.00
Cm/letter
Transportation and fixing
f) Labour
mate Day 0.26 244.30 63.52 L-10
Mason Day 0.60 264.30 158.58 L-25
Mazdoor Day 6.00 224.30 1345.80 L-01
g) Machinery
Tractor- Trolly Hour 6.00 289.00 1734.00 P&M-053
3301.90
h) Overhead @ 8% on (f+g) 264.15
i) Contractor's profit @ 10% on (f+g+h) 356.60
Cost of 6 nos 5th Kilometer stone = (a+b+c+d+e+f+g+h+i) 18460.17
Rate for each 5th KM stone = (a+b+c+d+e+f+g+h+i)/6 3076.69
say 3077.00
d) Boundary stones
Unit = Nos
Taking Output = 57 Nos
a) M 15 Grade of concrete Cum 1.25 4852.00 6065.00 1.19(a)
b) Steel reinforcement Kg 79.80 55.98 4467.44
c) Excavation in soil for foundation Cum 10.72 152.00 1629.44 1.24
Per
d) Lettering on Km Post(average 1 letter of 10 cm height 2280.00 0.47 1071.60
Cm/letter
Transportation and fixing
e) Labour
mate Day 0.57 244.30 139.25 L-10
Mazdoor Day 14.25 224.30 3196.28 L-01
f) Machinery
Tractor- Trolly Hour 6.00 289.00 1734.00 P&M-053
g) Material
Stone spall Cum 11.97 933.88 11178.54 M-008

h) Overhead @8% on (a+b+c+d+e+f+g) 2358.52


i) Contractor's profit @ 10% on (a+b+c+d+e+f+g+h) 3184.01
31840.08
Rate for each Boundary stone = (a+b+c+d+e+f+g+h+i)/57 558.60
say 559.00

2.14 Painting two coats with first quality enamel paint of approved
make & quality to give an even shade including writing , letter &
figure etc.complete in all respect as per IRC standard.
A printing letters of CD nos. No
I) Hindi
Details for 100 letters of 16 cm height i.e 1600 cm
unit = per cm height per letter
a) Labour
Mate Day 0.12 244.30 29.32 L-10
Painter Day 2.00 264.30 528.60 L-29
Mazdoor Day 1.00 224.30 224.30 L-01
b)Material
Paint Litre 0.70 145.00 101.50 M131
Total (a+b) 883.72
c) Overhead Charge @ 8% on (a+b) 70.70
d) Contractor's Profit @ 10% on ( a+b+c) 95.44
1933.57
Per cm height per letter 1.21
II) engilish and Roman

Bill No.A2
10
NATIONAL HIGHWAYS AUTHORITY OF INDIA RATE ANALYSIS

Sr No Ref. to Description Unit Quantity Rate Cost Remarks/ Input


MoRTH Rs Rs ref.
Spec.
Hypens and the like not to be measured and paid for details for
100 letters of 16cm height i.e. 1600cm
unit = per cm height per letter
a) Labour
Mate Day 0.07 244.30 17.10 L-10
Painter Day 1.25 264.30 330.38 L-29
Mazdoor Day 0.50 224.30 112.15 L-01
b) Material
Paint Litre 0.50 145.00 72.50 M131
Total (a+b)
c) Overhead Charge @ 8% on (a+b) 42.57
d) Contractor's Profit @ 10% on ( a+b+c) 4.26
578.95
Per cm height per letter 0.36
Average rate of english And Hindi 1.57
Painting of surface area Sqm 0.09 50.00 4.50
Letter Writing No. 4.00 0.54 2.16
6.66
say 7.00

2.15
Strengthening and repairing of partially damaged M.S pedestrian
Railling / pipe railing complete including welding , repairing /
Rmt
replacement of damaged parts / portions (salvage material will be
controctors property) as per existing pattern complete in al

Unit = Rmt
Taking output = 1.95rmt
a) Labour
Mate Day 0.48 244.30 117.26 L-10
Mazdoor Day 6.00 224.30 1345.80 L-01
Blacksmith Day 2.00 264.30 528.60 L-26
b) Material
M.S.Pipe / angle/ Squarbar(l/s) Kg 44.16 51.54 2276.09 M-126
C) Machinery
Tractor -Trolly hour 1.50 289.00 433.50 P&M-053
Welding Transformer hour 2.00 112.00 224.00 Market Rate
Total (a+b+c) 4925.26
d) Over head charge @ 8% on (a+b+c) 394.02
e)contractor's profit @ 10% on (a+b+c+d) 531.93
5851.21
3000.62
2780.6
assume 25% scrap material after accident 11Kg X Rs20 = 220 say
2186.0
2.16 Replacement of damaged single faced W- Beam metal crash
barrier made out of the following members. Job includes taking
out old damged member and neatly refixing the new member
(with cement concrete foundation in M-20 for post complete in all
respects as p
(A)Beam made out of cold rolled steel strip W profile of 3 mm
thick having a minimum yield strength of 2400 kg/sqcm having
width of 313 mm and depth of corrugation as 83 mm hot dip
galvanized of zinc coating @ 550 gm/sqm.
Unit = Rmt
Taking output = 4.5m
a) Labour
Mate day 0.06 244.30 14.66 L-10
Blacksmith day 0.50 264.30 132.15 L-01
Mazdoor day 1.00 224.30 224.30 L-26
b) Machinery
Tractor - trolly hrs 0.10 289.00 28.90 P&M-053

Bill No.A2
11
NATIONAL HIGHWAYS AUTHORITY OF INDIA RATE ANALYSIS

Sr No Ref. to Description Unit Quantity Rate Cost Remarks/ Input


MoRTH Rs Rs ref.
Spec.
c)Material
Corrugated sheet 3 mm thick W beam section railling 4.5 m in 2101.71 M-088
Kg 41.21 51.00
length

d) overhead charge @ 8% on (a+b+c) 200.14


e)contractor's profit @ 10% on (a+b+c+d) 270.19
2972.04
660.45
Rate per Rmt say 660.00

(B)Post consisting of cold rolled channel 150 x 75 x 5 mm having


minimum yield strength of 2400 kg/sqcm.The total length of post
shall be 1900 mm and minimum height of post above M 20
concrete foundation shall be 800 mm hot dip galvanized of zinc
coating

Taking output = 3No


a) Labour
Mate day 0.06 244.30 14.66 L-10
Blacksmith day 0.50 264.30 132.15 L-01
Mazdoor day 1.00 224.30 224.30 L-26
b) Machinery
Tractor - trolly hrs 0.10 289.00 28.90 P&M-053
c)Material
Channel post 150x75x5 mm 1.9 m long 3 nos @16.4 kg per 4818.15 M-126
Kg 93.48 51.54
meter
d) Earth work excavation
Earth work excavation for the size of (0.35 x0.35x1.10) Cum 0.40 152.00 60.80 1.24

c) overhead charge @ 8% on (a+b) 32.00


d)contractor's profit @ 10% on (a+b+c) 521.82
5832.77
1944.26
Rate per No say 1944.00

(C )Space channels or brackets made out of CRP steel channel


section 150 x 75 x 5 mm having an yield strength of 2400
Nos
kg/sqcm.The length of spacer channel shall be 330 mm and hot
dip galvanized having zinc coating @ 550 gm/sqm.

Taking output = 3No


a) Labour
Mate day 0.06 244.30 14.66 L-10
Blacksmith day 0.50 264.30 132.15 L-01
Mazdoor day 1.00 224.30 224.30 L-26
b) Machinery
Tractor - trolly hrs 0.10 289.00 28.90 P&M-053
c)Material
Spacer 150x75x5 mm channel 0.33 m long 3 nos @ 16.4 kg per 837.04 M-126
Kg 16.24 51.54
meter

c) overhead charge @ 8% on (a+b+c) 98.96


d) Contractor's Profit 133.60
1469.62
489.87
Rate per Rmt say 490.00
(D)Fasteners button head bolts 16 x 40 mm long , with nut and
washer hot dipped galvanized. Required reinforcement including Nos
proper curing , painting and complete in all respect.
Taking output = 25No
a) Labour

Bill No.A2
12
NATIONAL HIGHWAYS AUTHORITY OF INDIA RATE ANALYSIS

Sr No Ref. to Description Unit Quantity Rate Cost Remarks/ Input


MoRTH Rs Rs ref.
Spec.
Mate day 0.02 244.30 4.89 L-10
Blacksmith day 0.10 264.30 26.43 L-01
Mazdoor day 0.50 224.30 112.15 L-26
b)Material
Nuts and bolts Kg 3.50 60.00 210.00 M-130
353.47
c) overhead charge @8% on (a+b) 28.28
d) Contractor's Profit 38.17
419.92
16.80
Rate per Rmt say 17.00

Bill No.A2
13
NATIONAL HIGHWAYS AUTHORITY OF INDIA RATE ANALYSIS

Sr No Ref. to Description Unit Quantity Rate Cost Remarks/ Input


MoRTH Rs Rs ref.
Spec.
2.17 Replacing damaged / broken railing with new precast / cast in
situ, concrete railing to match with existing design and pattern ,
made out of cement concrete of appropriate grade and required
reinforcement including proper curing, painting and complete in

i) Replacement of Damaged Concrete Railing


Unit =Rmt
Taking out put = 10 Rmt
a) Labour
Mate day 0.2 244.30 48.86 L-10
Mazdoor day 5 224.30 1121.5 L-01
b) Machinary
Tractor trolly for disposal of dismantaled material hour 1 200.87 200.87 P&M-053
1371.23
c) over head charges @ 8% on (a+b) 109.6984
d) Add contractor profit @ 10% on (a+b+c) 148.09284
Total (a+b+c+d) 1629.02124
Rate per Rmt 162.902124
ii) RCC M 30 say 163
unit = Rmt
Taking output = 48 mt
a) Material
M 30 grade RCC Cum 4.49 6650.00 29858.5 1.20©
b) HYSD bar reinforcement tonne 0.895 55983.00 50104.785
79963.285
c) over head charges @ 8% on (a+b) 6397.06
d) Add Contractors profit @ 10 % on (a+b+c) 8636.03
Total 79963.29
Rate per Rmt 1665.90
Rate per Rmt(i+ii) 1828.90
say 1829

Bill No.A2
14
BILL No 3: Engineering Improvements
Ref. to Unit Quantity Rate Cost Remarks/I
MOST
S.No MoRTH Description Rs Rs nput
Data No
Spec. reference
BILL No 3: Engineering Improvements
Replacement of stolen/missing retro-reflectorised traffic
sign boards by providing and fixing new retro-
3.01 reflectorised cautionary, mandatory and informatory sign
as per ASTM D 4956-04 made of High intensity grade
Microprismatic sheeting Type-IV, fixed over
(A) 8.4 801 Informatory sign
i) Advance direction, Destination , Reassurance and
place identification sign (size 2100mm x 1700mm) as
per deawing with two vertical posts embeded in M15
Cement concrete details as per description given above
and as per drawing.
Unit= Nos
Taking output=one traffic sign
i)Excavation for foundation cum 0.43 152.23 65.46 A1
ii)Cement Concrete M15 grade cum 0.24 4851.97 1164.47 A2
iii)Painting angle iron post two coats sqm 0.86 49.07 42.20
. 1272.13
a)Labour( For fixing at site)
Mate day 0.01 244.30 2.44 L-10
Mazdoor day 0.30 224.30 67.29 L-01
69.73
b)Machinery
Tractor-trolley hour 0.02 289.00 5.78 P&M-053
c)Material

Mild steel angle iron 75 mm x 75 mm x 6 mm , 3.1 metres


kg long 47.60 51.54 2453.40 M-126/1000
Add 2 per cent of cost of materials for drilling
holes,nuts,bolts ,fabrication etc. 49.07
Aluminium PVC composite sheeting fixed with
encapsulated lens type reflective sheeting
including angle iron frame.lettering & signs as As aproved
applicable. sqm 3.57 5505.00 19652.85 By NHAI
22155.32
Total of a+b+c = 22230.83
d)Overheads @ 8% on (a+b+c) 1778.47
e)Contractor's Profit @ 10% on (a+b+c+d) 2400.93
Cost for one board= i+ii+iii+a+b+c+d+e 27682.36
say 27,682
ii) Facility Information sign 800 X 600
Taking output = One traffic sign
i) Excavation for foundation cum 0.22 152.23 32.88 A1
ii) cement concrete M15 grade cum 0.12 4851.97 582.24 A2
iii) Painting angle iron post two coats sqm 0.43 49.07 21.10
636.22
a)Labour (for fixing at site)
Mate Day 0.01 244.30 2.44 L-10
Mazdoor Day 0.25 224.30 56.08 L-01
58.52
b) Material
Mild Steek angle iron 75 X75 X 6mm
Kg 23.80 51.54 1226.70 M-126/1000
Aluminum sheeting fixed with encapsulated lens
type reflective sheeting of size including lettering As aproved
and signs as apllicable Sqm 0.48 5505.00 2642.40 By NHAI
Add 2% of cost of angle iron towards cost of
drilling holes , nuts bolts etc. 24.53
c) Machinery
Tractor- trolly Hour 0.01 289.00 2.89 P&M-053

b) Overhead charges @ 8% on (a) 4.68


c) Contractors Profit @ 10% on (a+b) 392.76
5683.44
Say 5,683
b Cationary / Warning sign
BILL No 3: Engineering Improvements
Ref. to Unit Quantity Rate Cost Remarks/I
MOST
S.No MoRTH Description Rs Rs nput
Data No
Spec. reference
i) triangular 900mm side
Unit= Nos
Taking output=0.35 sqm
i)Excavation for foundation cum 0.22 152.23 32.88 A1
ii)Cement Concrete M15 grade cum 0.12 4851.97 582.24 A2
iii)Painting angle iron post two coats sqm 0.43 49.07 21.10
. 636.22
a)Labour( For fixing at site)
Mate day 0.01 244.30 2.44 L-10
Mazdoor day 0.25 224.30 56.08 L-01
58.52
b)Machinery
Tractor-trolley hour 0.01 289.00 2.89 P&M-053
c)Material
Mild steel angle iron 75 mm x 75 mm x 6 mm , 3.1 metres long kg 19.00 51.54 979.30
Add 2 per cent of cost of materials for drilling holes,nuts,bolts
,fabrication etc. 19.59
Aluminium sheeting fixed with encapsulated lens type
reflective sheeting including angle iron frame.lettering & signs As aproved
as applicable. sqm 0.35 5505.00 1926.75 By NHAI
2925.63
Total of a+b+c = 2987.04
d)Overheads @ 8% on (a+b+c) 238.96
e)Contractor's Profit @ 10% on (a+b+c+d) 322.60
Cost for one board= i+ii+iii+a+b+c+d+e 4184.82
Say 4,185

c Mandatory / Regulatory sign


i) octagon STOP SIGN
i) triangular 900mm side
unit = each
Taking Output = one traffic sign
i) Excavation for foundation cum 0.216 152.23 32.88 A1
ii) cement concrete M15 grade cum 0.12 4851.97 582.24 A2
iii) Painting angle iron post two coats cum 0.43 49.07 21.10
. 636.22
a)Labour (for fixing at site)
Mate Day 0.01 244.30 2.44 L-10
BILL No 3: Engineering Improvements
Ref. to Unit Quantity Rate Cost Remarks/I
MOST
S.No MoRTH Description Rs Rs nput
Data No
Spec. reference
Mazdoor Day 0.25 224.30 56.08 L-01
58.52
c) Machinery
Tractor- trolly Hour 0.01 289.00 2.89 P&M-053

b) Material
Mild Steel angle iron 75 X75 X 6mm Kg 23.8 51.54 1226.70
Add 2% of cost of angle iron towards cost of drilling holes ,
nuts bolts etc. 24.53
Aluminum sheeting fixed with encapsulated lens type
reflective sheeting of size including lettering and signs as As aproved
apllicable Sqm 0.67 5505.00 3688.35 By NHAI
4939.58
Total of a+b+c = 4939.58
d)Overheads @ 8% on (a+b+c) 395.17
e)Contractor's Profit @ 10% on (a+b+c+d) 533.48
Cost for one board= i+ii+iii+a+b+c+d+e 5868.23
Say 5,868
ii) 600mm dia circular sign
unit = each
Taking Output = one traffic sign
i) Excavation for foundation cum 0.22 152.23 32.88 A1
ii) cement concrete M15 grade cum 0.12 4851.97 582.24 A2
iii) Painting angle iron post two coats Sqm 0.43 49.07 21.10
. 636.22
a)Labour (for fixing at site)
Mate Day 0.01 244.30 2.44 L-10
Mazdoor Day 0.25 224.30 56.08 L-01
58.52
c) Machinery
Tractor- trolly Hour 0.01 289.00 2.89 P&M-053

b) Material
Mild Steelangle iron 75 X75 X 6mm Kg 23.80 51.54 1226.70
Add 2% of cost of angle iron towards cost of drilling
holes , nuts bolts etc. 24.53
Aluminum sheeting fixed with encapsulated lens type
reflective sheeting of size including lettering and signs as Sqm 0.28
apllicable 5505.00 1557.92
2809.15
Total of a+b+c = 2809.15
d)Overheads @ 8% on (a+b+c) 224.73
e)Contractor's Profit @ 10% on (a+b+c+d) 303.39
Cost for one board= i+ii+iii+a+b+c+d+e 3337.27
Say 3,337

Supplying and installation of delineators (Roadway


indicators) 95 cm high above ground level of total length
3.02 135 cm. painted black and white in 15cm wide strips Nos. 1.00
fitted with 3 nos. rectangular microprismatic reflective
sheeting fixed on 2 mm thick aluminum
Unit = Each
Taking output= 30 Nos.
a) Labour
Mate Nos 0.04 244.30 9.77 L-10
Mazdoor for fixing Nos 1.00 224.30 224.30 L-01
b) Material
Cost of approved type of delineators from ISI certified firm as
Each 30.00 800.00
per the standard drawing given in IRC - 79 24000.00 M-091
Add 10 per cent cost of material for installation 2400.00
c) Over head Chage @ 8 % on (a+b) 2130.73
d) Contractor's profit @ 10 % on (a+b+c) 2876.48
Cost for 30 Nos. delineators = (a+b+ c+d) 31641.28
Rate per delineators = (a+b+c+d) /30 1,054.71
Say 1,055.00
BILL No 3: Engineering Improvements
Ref. to Unit Quantity Rate Cost Remarks/I
MOST
S.No MoRTH Description Rs Rs nput
Data No
Spec. reference

Cats Eye/pavement Marker (NMC nail lens:- Made out


of Acrylic-strene-Acrylonitril of Hi Impact polystrene fitted
3.03 with moulded of methacrylate (NMC ) rflector cube
corner reflector design; filled with tightly adhering potting
compund as per ASTM D 788 size
Unit = Nos
Taking out put = 50 nos
a) Labour
Mate Day 0.04 244.30 9.77 L-10
Mazdoor Day 1.00 224.30 224.30 L-01
b) Material
Cats Eye Nos 50 300.00 15000.00 Market Rate
Add 10 % of cost of material for fixing and installation 1500.00
16734.07
c) Over head Chage @ 8 % on (a+b) 1338.72576
d) Contractor's Profit @ 10 % on (a+b+c) 1807.279776
Total 19880.08
397.60
say 398

Providing and fixing retro-reflective stickers (Engineering


grade) of size 10cmx5cm on MBCBs and other structures as
3.04 Nos
per MoST Cl No. 801 and as per approval of Engineer in
charge,
unit = sqm
Taking output = 0.005 sqm
a) Materials
Tape including fixing of size 10cm Dia Sqm 0.005 727.3 3.6365
b)Labour hr 0.04 224.30 8.972
c) Overhead charges @ 8% on (a+b) 1.009
c) Contractors Profit @ 10% on (a+b+c) 1.362
Total cost =(a+b+c) 14.979
2995.7796
Rate per sqm Say 2996
Rate per no.of size 0.1x0.05 14.98
Say 15

Providing and marking of hot applied thermoplastic compound


2.5 mm thick including reflectorising glass beads @ 250 gms/
3.05 8.13 803 sqm area, thickness of 2.5 mm is exclusive of surface applied
glass beads as per IRC 35. The finished Surface to be level,
uniform and
Unit= sqm
Taking output= 600 sqm
a)Labour
Mate day 0.03 244.30 7.33 L-10
Mazdoor day 0.75 224.30 168.23 L-01
175.55
b)Material
Hot applied thermoplastic compound Litre 1500.00 169.00 253500.00 M-118
Reflectorising glass beads kg 150.00 56.00 8400.00 M-152
261900.00
c)Machinery
Road Marking machine @ 60 sqm per hour hour 10.00 52.17 521.70 P&M-043
Tractor- trolley hour 0.50 289.00 144.50 P&M-054
666.20
Total of a+b+c 262741.75
d)Overheads @ 8% on (a+b+c) 21019.34
e)Contractor's Profit @ 10% on (a+b+c+d) 28376.11
Cost for 600 sqm=(a+b+c+d+e) 312137.20
Rate per sqm say 520
Lane/ Center/ edge marking /transverse marking and any
other marking
BILL No 3: Engineering Improvements
Ref. to Unit Quantity Rate Cost Remarks/I
MOST
S.No MoRTH Description Rs Rs nput
Data No
Spec. reference

Providing Random Rubble masonary in cement mortar 1:3 for cum


drains, protection walls, boundary wall etc complete in all
3.06
respect as per technical specification clause 309 & 1400 and
as per directions of Engineer in charge.
Unit = Cum
Taking output = 1 Cum
a) Material
Stone Cum 1.00 933.88 933.88 M-001
Through and bond stone Nos. 7.00 40.00 280.00 M-182
(7 No x 0.24m x 0.24m x 0.39m = 0.16 Cum)
Cement mortar 1:3 (Rate as in item 12.6) Cum 0.33 3687.00 1216.71 Item-1.37
b) Labour
Mate Nos. 0.10 244.30 24.43 L-10
Mason Nos. 1.20 264.30 317.16 L-25
Mazdoor Nos. 1.00 224.30 224.30 L-01
Add for scaffolding @ 5 per cent of cost of a material and b
Labour 149.82
c) Overheads @ 8% on (a+b) 251.70
d) Contractor's profit @ 10% on (a+b+c) 339.80
Rate per cum = (a+b+c+d) Say 3,738

Providing & fixing New MS railing/pipe railing in medians / Per


horizontal curves including foundation concrete (45 cm x 45
cm x 75 cm in M-15) and two coat painting after
3.07
applying two coat mettalic primer of
approved quality. The job includes
dismantling of....... Meter
Taking output = 3.0 metres
i) Excavation for foundation (3 x 0.45 x 0.3 x 0.3) cum 0.12 152.23 18.57 A1
ii) Foundation concrete M-15 grade PCC 3 x0.45 x 0.3 x cum
0.3 0.12 4851.97 591.94 A2
iii) Painting of Angle SA 50x50 sqm 2.16 58.00 125.28
iv) Painting of 20mmx20mm bars sqm 2.20 58.00 127.31
a) Labour (For fixing at site)
Mate day 0.01 244.30 2.44 L-10
Mazdoor day 0.25 224.30 56.08 L-01
Plumber day 0.01 264.30 2.64 L-31
b) Material
Angle & MS bar & Plate kg 140.32 51.54 7232.27 M-126
c) Machinery
Tractor-trolley hour 0.04 289.00 11.56 P&M-053
8,168
d) Overheads @ 8% on (a+b) 653.45
d) Contractor's profit @ 10% on (a+b+c) 882.15
Cost for 3 metre =i+ii+iii+iv+ a+b+c+d 9,704
Rate per metre = (i+ii+iii+iv+a+b+c+d)/3 3,235

Construction and laying Cast in situ cement concrete kerb in


M 20 grade and matching with the existing kerb section
3.08 complete including dismantling and disposal of existing No
damaged broken kerbs as per technical Specifications Clause
408 for kerbs (M-20 Grade)
A)unit = Rmt
Taking output = 10Rmt
a) Labour
Mate Day 0.02 244.30 4.89 L-10
Mazdoor Day 0.23 224.30 51.59 L-01
b) Machinery
Tractor Trolly Hour 0.30 289.00 86.70 P&M-053
143.18
c) Overhead Charge @ 8% on (a+b) 11.45
BILL No 3: Engineering Improvements
Ref. to Unit Quantity Rate Cost Remarks/I
MOST
S.No MoRTH Description Rs Rs nput
Data No
Spec. reference
d) Contractor's Profit @ 10% on (a+b+c) 15.46
17.01
Rate per Rmt Say 17

B)Unit = Running metre


Taking output = 300metre length
Cement Concrete
Cement Concrete of grade M 20 cum 17.48 5341.24 93364.79 A3
a) Labour
Mate Day 0.72 244.30 175.90 L-10
Masson Day 2.00 264.30 528.60 L-25
Mazdor Day 16.00 224.30 3588.80 L-01
b) Machinery
Kerb casting machine @ 50metre /hour laying kerb and hour
casting 6.00 173.91 1043.46 P&M-029
Concrete mixer 0.48/0.28 hour 16.00 153.91 2462.56 P&M-009
Water Tanker 6Kl capacity hour 6.00 690.00 4140.00
105,304.11
c) Overhead Charge @ 10% on (a+b) 8,424
d) Contractor's Profit @ 10% on (a+b+c) 11,373
125,101
417.00
Say 417
Say 434

Repairing of damaged kerb after dismantling of the kerb upto RM


minimum of 100mm and making good the section with M-20
3.09 concrete to match with the existing section including form
work , curing , painting with two coats of first quality synthetic
enamel paint
Unit = Running metre
Taking output = 360 metre
Using Concrete Mixer
Cement Concrete
Cement concrete of grade M20 = 12.60 cum
Total Concrete = 12.60 Cum
a) Labour
Mate Nos 0.72 244.30 175.90 L-10
Mason Nos 2.00 264.30 528.60 L-25
Mazdoor Nos 16.00 224.30 3588.80 L-01
b) Machinery 0.00
Kerb casting machine @ 60 metres/hour Hrs 3.00 173.91 521.73 P&M-029
Concrete mixer 0.48/0.28 cum capacity Hrs 6.00 153.91 923.46
Water tanker 6 KL capacity Hrs 3.00 690.00 2070.00
c) Material 0.00
Crushed stone aggregate 20 mm nominal size 59 per cent Cum 7.43 1790.07 13307.38 M-053
Coarse sand 30 per cent Cum 3.78 638.04 2411.79 M-005
Cement 11 per cent Tonne 1.39 5500.00 7623.00 M-081
Cost of water KL 30.00 125.00 3750.00 M-189
d) Overhead charges @8%on (a+b+c) 2,792
e) Contractor's profit @10%on (a+b+c+d) 3,769
I) Breaking of damaged kerb Cum 24.21 235.00 5689.35
2) painting, primer etc Sqm 90.00 49.07 4416.37 A7
51,568
Cost for 360 meter = a+b+c+d+e 143.24
Rate per metre = (a+b+c+d+e)/360 Say 143.00

G.I.Barbed Wire Fencing 1.8 High


3.10 8.18 807
Providing and fixing 1.8 metres high GI barbed wire fencing
with 2.4m angle iron posts 50mm x 50mm x 6mm placed
every 3 metres center to center founded in M15 grade cement
concrete,in pit size of 225 mmx225 mmx600 mm below
ground level, every 15th post, l
Unit= per running metre
Taking output= 30 m
BILL No 3: Engineering Improvements
Ref. to Unit Quantity Rate Cost Remarks/I
MOST
S.No MoRTH Description Rs Rs nput
Data No
Spec. reference
a)Labour
Mate day 0.12 244.30 29.32 L-10
Mazdoor day 2.50 224.30 560.75 L-01
Blacksmith day 0.40 264.30 105.72 L-26
695.79
b)Material
Barbed wire 428 m length @9.38 kg per 100 metre kg 40.15 50.00 2007.50 M-063
MS angle iron 50 mm x 50 mm x 6 mm, 33.8metre in length
@ 4.5kg per metre kg 152.00 43.70 6641.94
Add for GI staple,binding wire,drilling holes etc. @ 2 per cent
of the cost of material 124.28
6338.18
c)Painting
Applying two coats of painting on exposed surface of angle
iron posts sqm 3.96 34.00 134.64
Total of a+b+c = 7168.61
d)Overheads @ 8% on (a+b+c) 573.49
e)Contractor's Profit @ 10% on (a+b+c+d) 774.21
Cost for 30 m=(a+b+c+d+e) 8516.30
Rate per running metre say 284

Providing and Fixing Metal Beam Crash Barrier( W


profile safety guard rails)made out of following
members.Job includes fixing new post in cement
3.10 8.23 (A) 810
concrete of M-20grade foundation (0.35m x 0.35m x
0.95m) complete in all respects as fasteners and fixing
etc
Metal Beam Crash Barrier
Type - A, "W" : Metal Beam Crash Barrier
Providing and erecting a "W" metal beam crash barrier
comprising of 3 mm thick corrugated sheet metal beam
rail, 70 cm above road/ground level, fixed on ISMC
series channel vertical post, 150 x 75 x 5 mm spaced 2
m centre to centre, 1.8 m high, 1.1 m belo
Unit = Running metre
Taking output = 4.5 metre length
a) Labour
Mate day 0.06 244.30 14.66 L-10
Blacksmith day 0.50 264.30 132.15 L-26
Mazdoor day 1.00 224.30 224.30 L-01
b) Machinery
Tractor-trolley hour 0.10 289.00 28.90 P&M-053
c) Material
Corrugated sheet,3 mm thick, "W" beam section kg 41.21 55.98 2307.06 M-179
railing,4.5 m in length including Galvansing @ Rs12/Kg /1000

Channel post 150 x 75 x 5 mm,1.8 m long,3 Nos @ 16.4 kg 73.80 55.98 4131.55 M-179
kg per metre /1000
Spacer 150 x 75 x 5 mm channel 0.33 m long,3 Nos @ kg 16.24 55.98 909.16 M-179
16.4 kg per metre /1000
Nuts and bolts kg 20.00 60.00 1200.00 M-130
Add for Galvansation kg 151.25 12.00 1815.00
Add 15 per cent of the cost of material for fabrication, 1554.42
nuts, bolts and washers etc.)
12317.19
d) Overhead charges @ 8% on (a+b+c) 985.38
e) Contractor's profit @ 10% on (a+b+c+d) 1330.26
f)Excavation for foundation of vertical posts
3X0.35X0.35X0.95=0.35 cum cum 0.35 60.00 21.00
g)M 20 Concrete for foundation of vertical post
3X0.35X0.35X0.95=0.35 cum cum 0.35 5341.24 1869.43 A3
Cost for 4.5 metre = a+b+c+d+e+f+g 16523.26
Rate per metre = (a+b+c+d+e+f+g)/4.5 3671.83
say 3672
BILL No 3: Engineering Improvements
Ref. to Unit Quantity Rate Cost Remarks/I
MOST
S.No MoRTH Description Rs Rs nput
Data No
Spec. reference
Removal of unauthorised boards within ROW and
stacking etc complete in all respect including
3.11
transportation from site to the nearst store / suitable
location as per direction of engineer in charge
Single Post
Unit = Each
Taking output 30nos
a) Labour
Mate Day 0.48 244.30 117.26 L-10
Mazdoor Day 10.00 224.30 2243.00 L-01
b) Machinery
Tractor -Trolly Hour 1.50 289.00 433.50 P&M-053
Gas Cutter Hour 3.00 200.00 600.00 Market rate

Total 3393.76
c) Overhead Charge @ 8% on (a+b) 271.50
d) Contractor's Profit @ 10% on (a+b+c 366.53
4031.79
134.39
Say 134.00
Double Post (Post width less than 2 m.)
b
Unit = Each
Taking output 30nos
a) Labour
Mate Day 0.50 244.30 122.15 L-10
Mazdoor Day 14.00 224.30 3140.20 L-01
b) Machinery
Tractor -Trolly Hour 3.00 289.00 867.00 P&M-053
Gas Cutter Hour 6.00 200.00 1200.00 Market rate
Total 5329.35
c) Overhead Charge @ 10% on (a+b) 426.35
d) Contractor's Profit @ 10% on (a+b+c 575.57
6331.27
211.04
Say 211.00

C Double / Multi post (Post width grater than 2


Unit = Each
Taking output 30nos
a) Labour
Mate Day 1.00 264.30 264.30 L-10
Mazdoor Day 10.00 244.30 2443.00 L-01
b) Machinery
Tractor -Trolly Hour 6.00 289.00 1734.00 P&M-053
Gas Cutter Hour 8.00 200.00 1600.00 Market rate
Total 6041.30
c) Overhead Charge @ 8% on (a+b) 483.30
d) Contractor's Profit @ 10% on (a+b+c 652.46
7177.06
239.24
Say 239.00
Removal of encroachment of ROW including cost of
dismantaling,liasioning with local authorities,transportation of
3.12 debries etc complete
Unit=sqm
Taking out put=1550 sqm
a) Labour
Mate day 4.00 284.30 1137.20 L-10
Mazdoor Day 40.00 264.30 10572.00 L-01
b) Machinery
Hydrulic Excavator of 1 cum bucket Hour 64.00 730.43 46747.52 P&M-026
Tipper Hour 64.00 506.09 32389.76 P&M-048
Add 10 % of cost of labour and machinary of unforeseen 9084.65
problems during evictions
BILL No 3: Engineering Improvements
Ref. to Unit Quantity Rate Cost Remarks/I
MOST
S.No MoRTH Description Rs Rs nput
Data No
Spec. reference
c) Overhead Charge @ 8% on (a+b) 7994.49
d) Contractor's Profit @ 10% on (a+b+c 10792.56
118718.18
76.59
Rate per sqm Say 77.00
NATIONAL HIGHWAYS AUTHORITY OF INDIA RATE ANALYSIS

CHAPTER - 4
INCIDENT MANAGEMENT
Provision of15 Tonnes capacity Pick & Carry Cranes
with required staff and Equipment for removing all types of
4.1 4.02 broken down vehicles which have met with accidents, from
the carriageway and toeing the same to proper locations i.e
nearest Police stations or
A For buses and lories and other heavy vehicles
Out put = 01 vehicles per mothn
a) Labour
Labour no/month 3 no x 30 days 244.30 21987.00 L-10
Skilled no/month 3 no x 30 days 264.30 23787.00 L-35
Driver no/month 3 no x 30 days 284.30 25587.00 L-01

b) Machinery
Towaway crane (Hire Charge) month 1.00 13200.00 13200.00 Market Rate
c) ii) Diesel liters 260.000 55.63 Do
14463.80
Market Rate 1.00 1024.00
d) Provision of GPS & GIS for vehicle tracking System
1024.00
e) Overhead charges @ 8% on (a+b+c) 8003.90
f) Contractor's profit @ 10% on (a+b+c+d) 8606.57
Total rate per vehicle per month (a+b+c+d+e) 116659

Providing and supply of following manpower for misc. work as


4.2 4.05 and when required basis as per instruction of Engineer.

Unit = hour
Mate/Supervisor day 244.30 244.30 L-10
Helper / Beldar / Coolie. day 224.30 224.30 L-01
Security Guard day 244.30 244.30 L-22

Providing, running and maintaining route patrol


vehicle as per clause 4.4 of scope of work and as per
4.3 4.03 clause 4.8 'Performance Standard' of scope of work
with provision of GPS & GIS for vehicle tracking
system as per NHAI Circular No.15/2008,
I) One vehicle considering to run 6 trips in each direction
(3LCW+3RCW)(77*6)=462 km / day ie monthly running
Unit = months
a) Labour
Supervisor/Route Patrol Incharge no/month 3 no x 30 days 284.3 25587.00 L-58
Patrol Asst. no/month 3 no x 30 days 244.3 21987.00 L-22
Driver no/month 3 no x 30 days 284.3 25587.00
b) Vehicle
I) Four wheeler(trax/Maxx) including maintenance month 1.000 30000 30000.00 Market Rate
ii) Diesel liters 804.000 55.63 44726.52 Do
Market Rate 1.000 1024.00 Do
c) Provision of GPS & GIS for vehicle tracking System
1024.00
d) Patrol Equipment per month 1.000 4125 4125.00
153036.52
d) Add 8% overhead 12242.92
165279.44
e) Add 10% profit 16527.94
Per month for one Vehciles per month 181807

Provision of Air conditioned Ambulance with paramedical


staff as per clause 4.4 of scope of work and as per clause
4.4 4.04
6.8 "Performance Standard" of scope of work complete as
directed by the Engineer.
Unit = Per month / per vehicles
a)
I) One Air conditioned ambulance considered 1.000 30000 30000.00 Market Rate
ii) Disel for ambulance 100 km / day running liters 450.000 55.63 25033.50 Do
iii) Maintenance 1.000 1500 1500.00 Do
iv) First Aid kit & Equpment 1.000 5000 5000.00

b) I) Para medical staff per month 3.000 9000 27000.00 Market Rate
ii) Helper no 3 no x 30 days 244 21987.00
iii) Driver no 3 no x 30 days 284 25587.00
iv) Nursing Staff per month 3 no x 30 days 170 15300.00 Market Rate
Market Rate 1.000 1024.00
c) Provision of GPS & GIS for vehicle tracking System
1024.00
c) Mobile phones no 1.000 1500 1500.00
153931.50
e) Add 8% over head 12314.52
f) Add 10 % contractor profit 16624.60
Total rate per month (a+b+c+d+e) 182870.62

Bill No.A4
1
NATIONAL HIGHWAYS AUTHORITY OF INDIA RATE ANALYSIS

Say 182871

Removing the dead animals / birds lying on the highway,


and burring them at proper safe locations complete in all
4.5 4.01
respect with all lead and lifts as per clause 4.8 "Performance
Standard" of scope of work, as directed by the Engineer.
Unit = 1 Nos
Output = 01 Nos.
a) Labour
Mate day 1.00 244.30 244.30 L-10
Mazdoor( unskilled) day 2.00 224.30 448.60 L-01
b) Machienenry
Tractor Trolly hrs 2.00 289.00 578.00 P&M-053
c) Tools and tackles 10% including burning 127.09
1397.99
d) Overhead charges @ 8% on (a+b+c) 111.84
e) Contractor's profit @ 10% on (a+b+c+d) 150.98
Rate per no. = a+b+c+d+e 1660.81
Assuming per month 15 cow dead animals 24912.18
Assuming per month dog50 dead animals(20% of unit 16608.12
rate)
Say 41520

Supply of colour photographs in three copies and two CDs


4.6 complete as per Technical specification clause 125

As per market rate No 300.00

Supply of Vedio Cassette (CD) in three copies including


videography of complete stretch at three stages in O&M
4.7
period complete as per Technical specification clause
126
Per set 1 Provisional 20000.00

Bill No.A4
2
NATIONAL HIGHWAYS AUTHORITY OF INDIA RATE ANALYSIS

BILL NO - 5
MISCLLANEOUS
Sr No Ref. to Description Unit Quantity Rate Cost Remarks/ Input
MoRTH Rs Rs ref.
Spec.
5.01 124 Dismantling of structures and pavement and disposal of
unserviceable material at suitable place outside ROW with
all lead and lifts complete in all respect as per
approval of Engineer. The rate quoted should be
inclusive of salvage value of the servicable
A) Dry stone masonary Cum
Taking output = 1.25 Cum
a) Labour
Mate Nos 0.014 244.30 3.42 L-10
Mazdoor Skilled Nos 0.35 224.30 78.51 L-01
b) Machinery
Tractor-Trolley Hr. 0.27 289.00 78.03 P&M-053
c) Overhead @ 8% on (a+b) 12.80
d) Contractor's profit @ 10% on (a+b+c) 17.28
Cost for 1.25 Cum = a+b+c+d 190.03
Rate per Cum = (a+b+c+d)/1.25 165.84
165.84
Say 166.00

b) Stone masonary/Brick masonary in Mud


mortar
Taking output = 1.25 Cum
a) Labour
Mate Nos 0.024 244.30 5.86 L-10
Mazdoor Skilled Nos 0.6 224.30 134.58 L-01
b) Machinery
Tractor-Trolley Hr. 0.27 289.00 78.03 P&M-053
c) Overhead @ 8% on (a+b) 17.48
d) Contractor's profit @ 10% on (a+b+c) 23.60
Cost for 1.25 Cum = a+b+c+d 259.55
Rate per Cum = (a+b+c+d)/1.25 226.51
Say 227.00
c) Rigid Pavement
Taking output = 1.25 Cum
a) Labour
Mate Nos 0.15 244.30 36.65 L-10
Blacksmith Nos 0.25 264.30 0.00 L-45
Mazdoor Skilled Nos 3.50 224.30 350.00 L-10
b) Machinery
Tractor-Trolley Hr. 0.27 289.00 386.65 P&M-053
c) Overhead @ 10% on (a+b) 61.86
d) Contractor's profit @ 10% on (a+b+c) 83.52
Cost for 1.25 Cum = a+b+c+d 918.67
Rate per Cum = (a+b+c+d)/1.25 734.93
Say 735.00

5.03 Providing and lying RCC NP-4 /Prestressed concrete pipe


at various dia meter (as per detail given below) for culvert
on culverts on first class bedding of granular materials
materials in single ROW including fixing collar with
cement mortar 1:2 but excluding
A)1200 mm dia
unit = Metre
Taking output = 12.5 metre
a) Labour
Mate Day 0.28 244.30 68.40 L-10

Bill No.A5
1
NATIONAL HIGHWAYS AUTHORITY OF INDIA RATE ANALYSIS

Sr No Ref. to Description Unit Quantity Rate Cost Remarks/ Input


MoRTH Rs Rs ref.
Spec.
Masson Day 1.00 264.30 264.30 L-25
Mazdoor Day 6.00 224.30 1345.80 L-01
b) material
Sand at site cum 0.09 638.04 57.42 M-005
cement at site ton 0.07 5500.00 385.00 M-081
RCC pipe NP-4/ prestressed concrete pipe metre 12.50 6201.60 77520.00 M-149
Total 79640.93
c) overhead charges @ 8% i.e on (a+B) 6371.27
d) Add contractors profit @ 10% i.e on (a+b+C) 8601.22
94613.42
7569.07
Say 7569.00

5.04 Providing following equipments in running condition on hire basis


including running and maintenance charges as per instruction of
the Engineer including P.O.L. complete as per specification. ( Rate
for net working hours at site )

a Tipper 5Cum. Capacity. hour 506.09 P&M-048


b JCB hour 730.43 P&M-026
c Excavator hour 730.43 P&M-026
d Tractor with trolly hour 289.00 P&M-053

5.05
Providing and placing in proper position empty cement bags filled
with local earth to control erosion / damage of the side of the road
or bank of the river / nallha at required locations including cost of
material, labour equipment transporation etc. comp

Taking output=750bags
a) Labour
Mate Nos 0.40 244.30 97.72 L-10
Mazdoor Nos 15.00 224.30 3364.50 L-01
b) material
Cement Bags including sand Nos 750.00 6.00 4500.00 M-159
c) Machinery
Crane Hr 20.00 200.00 4000.00 P&M-013
d) Over head charges@8% on (a+b+c) 956.98
d) Contractor profit @10% on (a+b+c+d) 1291.92
Rate for 750 No=(a+b+c+d+e) 14211.12
Rate for each No=(a+b+c+d+e)/750 18.95
Say 19.00

Project Director
PIU- Bhubaneswar

Bill No.A5
2
NATIONAL HIGHWAYS AUTHORITY OF INDIA RATE ANALYSIS

Hire Charges of Plant and Machineries


(As per Scheduled of Rates, 2014(Post GST), Public Works Department)
Output of Rate
Sl. No. Description of Machine Activity Output Unit
Machine (Rs.)
P&M-001 Air Compressor General Purpose capacity in cfm 170/250 hour 179.13
P&M-002 Batching and Mixing Plant (a) 30 cum capacity Concrete Mixing cum/hour 20 hour 1252.17

P&M-003 Batching and Mixing Plant (b) 15 - 20 cum capacity Concrete Mixing cum/hour 13 hour 1043.48

P&M-004 Bitumen Pressure Distributor Applying bitumen tack coat sqm/hour 1750 hour 601.74
P&M-005 Bitumen Boiler oil fired Bitumen Spraying capacity in litre 1500 hour 111.30
P&M-006 Concrete Paver Finisher with 40 HP Motor Paving of concrete surface cum / hour 20 hour 1608.70

P&M-007 Concrete Pump of 45 & 30 cum capacity Pumping of concrete cum / hour 33 / 22 hour 143.48
P&M-008 Concrete Bucket For Pouring concrete capacity in cum 1 hour 8.70
P&M-009 Concrete Mixer (a) 0.4/0.28 cum Concrete Mixing cum/hour 2.5 hour 153.91
P&M-010 Concrete Mixer (b) 1 cum Concrete Mixing cum/hour 7.5 hour 153.91
P&M-011 Crane (a) 80 tonnes Lifting Purpose hour 717.39
P&M-012 Cranes b) 35 tonnes Lifting Purpose hour 478.26
P&M-013 Cranes c) 3 tonnes Lifting Purpose hour 200.00
P&M-014 Dozer D - 80 - A 12 Spreading /Cutting / Clearing cum/hour 300/ 150/250 hour 2190.43
P&M-015 Dozer D - 50 - A 15 Spreading /Cutting / Clearing cum/hour 200/ 100/150 hour 1592.17
P&M-016 Emulsion Pressure Distributor Applying emulsion tack coat sqm/hour 1750 hour 448.70
P&M-017 Front End loader 1 cum bucket capacity Soil loading / Aggregate loading cum/hour 60 /25 hour 452.17
P&M-018 Generator (a) 125 KVA Genration of electric Energy KVA 100 hour 786.96
P&M-019 Generator( b) 63 KVA Genration of electric Energy KVA 50 hour 393.48

P&M-020 GSB Plant 50 cum Producing GSB cum/hour 40 hour 582.61


P&M-021 Hotmix Plant - 120 TPH capacity DBM/BM/SDC/ Premix cum/hour 40 hour 13130.43
P&M-022 Hotmix Plant - 100 TPH capacity DBM/BM/SDC/ Premix cum/hour 30 hour 9710.43
P&M-023 Hotmix Plant - 60 to 90 TPH capacity DBM/BM/SDC/ Premix cum/hour 25 hour 7765.22
P&M-024 Hotmix Plant - 40 to 60 TPH capacity DBM/BM/SDC/ Premix cum/hour 17 hour 6217.39
P&M-025 Hydraulic Chip Spreader Surface Dressing sqm/hour 1500 hour 1478.26
P&M-026 Hydraulic Excavator of 1 cum bucket Soil Ordinary/Soil Marshy / Soil cum/hour 60 /60 /60 hour 730.43
Unsuitable
P&M-027 Integrated Stone Crusher 100THP Crushing of Spalls TPH 100 hour 1860.87
P&M-028 Integrated Stone Crusher 200 HP Crushing of Spalls TPH 200 hour 10226.09
P&M-029 Kerb Casting Machine Kerb Making Rm/hour 80 hour 173.91
P&M-030 Mastic Cooker Mastic Wearing coat capacity in tonne 1 hour 1379.13
P&M-031 Mechanical Broom Hydraulic Surface Cleaning sqm/hour 1250 hour 230.00
P&M-032 Motor Grader 3.35 mtr blade Clearing /Spreading /GSB /WBM cum/hour 200/200/50/50 hour 1343.48
P&M-033 Mobile slurry seal equipment Mixing and laying slurry seal sqm/hour 2700 hour 565.22
P&M-034 Paver Finisher Hydrostatic with sensor control 100 TPH Paving of DBM/ BM/SDC/ Premix cum/hour 40 hour 1500.00

P&M-035 Paver Finisher Mechanical 100 TPH Paving of WMM /Paving of DLC cum/hour 40/30 hour 642.61
P&M-036 Piling Rig with Bantonite Pump 0.75 m dia to 1.2 m dia Boring Rm/hour 2 to 3 hour 3065.22
attachment
P&M-037 Pneumatic Road Roller Rolling of Asphalt Surface cum/hour 25 hour 697.39
P&M-038 Pneumatic Sinking Plant Pneumatic Sinking of wells cum/hour 1.5 to 2.00 hour 2690.00
P&M-039 Pot Hole Repair Machine Repair of potholes cum/hour 4 hour 508.70
P&M-040 Prestressing Jack with Pump & access Stressing of steel wires/stands hour 72.17
INPUT
4
P&M-041 Ripper Scarifying cum/hour 60 hour 18.00
NATIONAL HIGHWAYS AUTHORITY OF INDIA RATE ANALYSIS

P&M-042 Rotavator Scarifying cum/hour 25 hour 11.00


P&M-043 Road marking machine Road marking Sqm/hour 100 hour 52.17
P&M-044 Smooth Wheeled Roller 8 tonne Soil Compaction /BM Compaction cum/hour 70/25 hour 294.78
P&M-045 Tandem Road Roller Rolling of Aspalt Surface cum/hour 30 hour 641.74
P&M-046 Tipper - 5 cum Transportation of soil, GSB, WMM, Capacity in cum 5.5 km 20.87
Hotmix etc.
P&M-047 Tipper - 5 cum Transportation of soil, GSB, WMM, Capacity in cum 5.5 tonne.km 2.17
Hotmix etc.
P&M-048 Tipper - 5 cum Transportation of soil, GSB, WMM, Capacity in cum 5.5 hour 506.09
Hotmix etc.
P&M-049 Transit Mixer 4.0/4.5 cum Transportation of Concrete Mix to site cum/hour 4.5 hour 521.74

P&M-050 Transit Mixer 4/4.5 cum Transportation of Concrete Mix to site cum/hour 4.5 tonne.km 4.00

P&M-051 Transit Mixer 3.0 cum Transportation of Concrete Mix to site cum/hour 3 hour 478.26

P&M-052 Transit Mixer 3.0 cum Transportation of Concrete Mix to site cum/hour 3 tonne.km 4.00

P&M-053 Tractor Pulling capacity in HP 50 hour 200.87


P&M-054 Tractor with Rotevator Rate of Tractor + Rotevator hour 249.20
P&M-055 Tractor with Ripper Rate of Tractor + Ripper hour 251.30
P&M-056 Truck 5.5 cum per 10 tonnes Material Transport capacity/cum 4.5 km 17.39
P&M-057 Truck 5.5 cum per 10 tonnes Material Transport capacity/cum 4.5 hour 484.35
P&M-058 Truck 5.5 cum per 10 tonnes Material Transport capacity/cum 4.5 tonne.km 1.74
P&M-059 Vibratory Roller 8 tonne Earth or soil / GSB / WBM cum/hour 100/60/60 hour 864.50
P&M-060 Water Tanker Water Transport capacity in KL 6 hour 690.00
P&M-061 Water Tanker Water Transport capacity in KL 6 km 52.00
P&M-062 Wet Mix Plant 60 TPH Wet Mix cum/hour 25 hour 675.65
P&M-063 Compressor with gunting equipment along with Hour hour 285.00
accessories
Sl. No. Description of Machine Unit Rate
(Rs.)
P&M-063 Air compressor with pneumatic chisel attachment for cutting hard clay. hour input
P&M-064 Batch type cold mixing plant 100-120 TPH capacity producing an average output of 75 tonne per hour hour input
P&M-065 Belt conveyor system hour input
P&M-066 Boat to carry atleast 20 persons hour input
P&M-067 Cement concrete batch mix plant @ 175 cum per hour (effective output) hour 5160.00
P&M-068 Cement concrete batch mix plant @ 75 cum per hour hour 2760.00
P&M-070 Crane 5 tonne capacity hour 200.00

P&M-071 Crane 10 tonne capacity hour 300.00

P&M-072 Crane 15 tonne capacity hour 400.00


P&M-073 Crane 20 tonne capacity hour 450.00

P&M-074 Crane 40 T capacity hour 526.09

P&M-077 Drum mix plant for cold mixes of appropriate capacity but not less than 75 tonnes/hour. hour 289.00

P&M-079 Generator 33 KVA hour 240.00


P&M-080 Generator 100 KVA hour 450.00
P&M-081 Generator 250 KVA hour 1125.00
P&M-083 Joint Cutting Machine with 2-3 blades (for rigid pavement) hour 281.00
P&M-085 Piling rig Including double acting pile driving hammer (Hydraulic rig) hrs 3525.00
P&M-086 Plate compactor hour 100.00
P&M-088 Texturing machine (for rigid pavement) hour 281.00

P&M-093 Wet Mix Plant 100 TPH hour 384.37

P&M-094 Wet Mix Plant 75 TPH hour 1036.00


P&M-095 Tractor with Trolly hour 289.00

INPUT
5
NATIONAL HIGHWAYS AUTHORITY OF INDIA RATE ANALYSIS

(B) Labour
Sl. No. Description of Labour Unit Rate
(Rs.)
A Category Unskilled
L-01 Male mulia day 224.30
L-02 Female mulia day 224.30
L-03 Survey Khalasi / Chain man day 224.30
L-04 Scavanger day 224.30
B Category Semiskilled
L-05 Mulia working in water or arduous nature of work day 244.30
L-06 Night mulia or attendent working in floodand other emergent work day 244.30
L-07 Mulia for handling hot binder and Tar boiler men day 244.30
L-08 Sangi mulia day 244.30
L-09 pile driving mate ( Guide man) day 244.30
L-10 Mate day 244.30
L-11 Helper to carpenter or Blacksmith/Painter/Blaster/Plumber/Eltrician/fitter/Welder day 244.30
L-12 Hammer man day 244.30
L-13 Thatcher / Gharami day 244.30
L-14 Tile turner day 244.30
L-15 Boat man day 244.30
L-16 Bhisti day 244.30
L-17 Well sinker day 244.30
L-18 Rod binder and bender day 244.30
L-19 Cleaner / Sweeper day 244.30
L-20 Stone packer day 244.30
L-21 Pump helper day 244.30
L-22 Watch man ( Store) / Gurkha / Security Guard day 244.30
L-23 Bellow man day 244.30
C Category Skilled
L-24 Blaster ( Second Class) day 264.30
L-25 Mason ( Second Class) day 264.30
L-26 Black smith ( Second Class) day 264.30
L-27 Carpenter ( Second Class) day 264.30
L-28 Fitter ( Second Class) day 264.30
L-29 Painter / Polisher ( Second Class) day 264.30
L-30 Welder ( Second Class) day 264.30
L-31 Plumber ( Second Class) day 264.30
L-32 Driller ( Second Class) day 264.30
L-33 Stone dresser / Cutter ( Second Class) day 264.30
L-34 Cobbler with toolsr ( Second Class) day 264.30
L-35 Wire man / Lift operator / Diesel pump driver / Telephone operator ( Second Class) day 264.30
L-36 Boring mistry / Pipe driver ( Second Class) day 264.30
L-37 Electrician / Rigger / Line man / Telephone attendant ( Second Class) day 264.30
L-38 Gardener day 264.30
L-39 Amin day 264.30
L-40 Tracer day 264.30
L-41 Jr. progress recorder day 264.30
L-42 Store keeper Gr - II / Store Asst./ Account clerk / Clerk / Typist / Toolkeeper / Time keeper / Munsi day 264.30
D Category Highly Skilled
L-42 Blaster ( licensed) day 284.30
L-43 Mason ( Special) day 284.30
L-44 Carpenter ( Special) day 284.30
L-45 Blacksmith ( Special) day 284.30
L-46 Fitter ( Special) day 284.30
L-47 Painter / Polisher ( Special) day 284.30
L-48 Welder ( Special) day 284.30
L-49 Plumber ( Special) day 284.30
L-50 Driller ( Special) day 284.30
L-51 Stone dresser / Cutter ( Special) day 284.30
L-52 Diver for well sinking in bridge( per shift of four hours) day 284.30
L-53 Electrician / Airconditioned plant operator / wire man / Lift operator / Diesel pump operator( Special) day 284.30
L-54 Jeep driver / Tractor driver / Truck driver / Dozer driver / Roller driver / Concrete mixture operator / Crane operator day 284.30
L-55 Auto eleectrician day 284.30
L-56 Guiniting Machine operator day 284.30
L-57 Senior Accountant / Stenographor day 284.30
L-58 Supervisor / Manager day 284.30
L-59 Testing Laboratory Assistant / Instrument Mechanic / Telephone Mechanic day 284.30
L-60 Rigger and Cobbler with Tools Driver ( Heavy Vehicle) day 284.30
E Other Category
L-60 Boring Mistry ( Special) day 284.30
L-61 Winch Operator day 284.30
INPUT
L-62 Well sinker ( Special) day 284.306
L-63 Helper to Well sinker day 264.30
L-64 Computer Programmer / Analyzer day 7000.00
NATIONAL HIGHWAYS AUTHORITY OF INDIA RATE ANALYSIS

L-65 Computer Operator day 5200.00


L-66 Helper to operator of Heavy construction Machineries day 5000.00
L-67 Mechanic for Heavy construction day 6000.00
L-68 Helper to mechanic of Heavy construction Machineries day 5000.00
L-69 operator for Heavy construction day 6000.00
L-70 Junior Research Assistant ( Technical Assistant) day 5200.00

INPUT
7
NATIONAL HIGHWAYS AUTHORITY OF INDIA RATE ANALYSIS

(C) Materials
Sl. No. Description Unit Rate
(Rs.)
M-001 Stone Boulder of size 150 mm and below at Cruser Plant cum 933.88
M-002 Supply of quarried stone 150 - 200 mm size for Hand Broken at site cum 933.88
M-003 Boulder with minimum size of 300 mm for Pitching at Site cum 933.88
M-004 Coarse sand at Mixing Plant cum 638.04
M-005 Coarse sand at Site (Baitarini) cum 638.04
M-006 Fine sand at Site (Baitarini) cum 632.33
M-007 Moorum at Site cum 274.38
M-008 Gravel/ Quarry spall at Site cum 933.88
M-009 Granular Material or hard murrum for GSB works at Site cum 274.38
M-010 Granular Material or hard murrum for GSB works at Mixing Plant cum 274.38
M-011 Fly ash conforming to IS: 3812 ( Part II & I) atHMP Plant / Batching Plant / Crushing Plant cum 50.00
M-012 Filter media/ Filter Material as per Table 300-3 (MoRT&H Specification) cum 1499.59
M-013 Close graded Granular sub-base Material 53 mm to 9.5 mm cum 1401.50 1463.50
M-014 Close graded Granular sub-base Material 37.5 mm to 9.5 mm cum 767.00 829.00
M-015 Close graded Granular sub-base Material 26.5 mm to 9.5 mm cum 767.00 829.00
M-016 Close graded Granular sub-base Material 9.5 mm to 4.75 mm cum 937.00 999.00
M-017 Close graded Granular sub-base Material 9.5 mm to 2.36 mm cum 937.00 999.00
M-018 Close graded Granular sub-base Material 4.75mm to 2.36 mm cum 793.00 855.00
M-019 Close graded Granular sub-base Material 4.75mm to 75 micron mm cum 793.00 855.00
M-020 Close graded Granular sub-base Material 2.36 mm cum 793.00 855.00
M-021 Stone crusher dust finer than 3mm with not more than 10% passing 0.075 sieve. cum 776.02 838.02
M-022 Coarse graded Granular sub-base Material 2.36 mm & below cum 1418.64 1480.64
M-023 Coarse graded Granular sub-base Material 4.75mm to 75 micron mm cum 793.00 855.00
M-024 Coarse graded Granular sub-base Material 4.75 mm to 2.36 mm cum 793.00 855.00
M-025 Coarse graded Granular sub-base Material 9.5 mm to 4.75 mm cum 1861.50 1923.50
M-026 Coarse graded Granular sub-base Material 26.5 mm to 4.75 mm cum 767.00 829.00
M-027 Coarse graded Granular sub-base Material 26.5 mm to 9.5 mm cum 767.00 829.00
M-028 Coarse graded Granular sub-base Material 37.5 mm to 9.5 mm cum 767.00 829.00
M-029 Coarse graded Granular sub-base Material 53 mm to 26 .5mm cum 1499.59 1561.59
M-030 Aggregates below 5.6 mm cum 1506.26 1568.26
M-031 Aggregates 22.4 mm to 2.36 mm cum 1790.07 1852.07
M-032 Aggregates 22.4 mm to 5.6 mm cum 922.00 984.00
M-033 Aggregates 45 mm to 2.8 mm cum 767.00 829.00
M-034 Aggregates 45 mm to 22.4 mm cum 1499.59 1561.59
M-035 Aggregates 53 mm to 2.8 mm cum 767.00 829.00
M-036 Aggregates 53 mm to 22.4 mm cum 767.00 829.00
M-037 Aggregates 63 mm to 2.8 mm cum 725.00 787.00
M-038 Aggregates 63 mm to 45 mm cum 1401.50 1463.50
M-039 Aggregates 90 mm to 45 mm cum 995.60 1057.60
M-040 Aggregates 4.75mm cum 1437.69 1499.69
M-041 Aggregates 11.2 mm to 0.09 mm cum 937.00 999.00
M-042 Aggregates 13.2 mm to 0.09 mm cum 922.00 984.00
M-043 Aggregates 13.2 mm to 5.6 mm cum 922.00 984.00
M-044 Aggregates 13.2 mm to 10 mm cum 1838.64 1900.64
M-045 Aggregates 20 mm to 10 mm cum 1790.07 1852.07
M-046 Aggregates 25 mm to 10 mm cum 1838.64 1900.64
M-047 Aggregates 19 mm to 6 mm cum 1823.40 1885.40
M-048 Aggregates 37.5 mm to 19 mm cum 767.00 829.00
M-049 Aggregates 37.5 mm to 25 mm cum 767.00 829.00
M-050 Aggregates 6 mm nominal size cum 1506.26 1568.26
M-051 Aggregates 10 mm nominal size cum 1861.50 1923.50
M-052 Aggregates 13.2/12.5 mm nominal size cum 922.00 984.00
M-053 Aggregates 20 mm nominal size cum 1790.07 1852.07
M-054 Aggregates 25 mm nominal size cum 922.00 984.00
M-055 Aggregates 40 mm nominal size cum 1499.59 1561.59

M-056 AC pipe 100 mm dia metre 30.00


M-058 Alluminium Paint litre 130.00
M-059 Aluminium alloy plate 2mm Thick sqm 4800.00
M-060 Aluminium alloy/galvanised steel tonne 80000.00
M-061 Aluminium sheeting fixed with encapsulated lens type reflective sheeting including 2% towards lettering, cost of angle iron, cost of drilling sqm 4800.00
holes, nuts, bolts etc.and signs as applicable
M-062 Aluminium studs 100 x 100 mm fitted with lense reflectors nos 275.00
M-063 Barbed wire kg 50.00
M-071 Bentonite kg 2.23
M-072 Binding wire kg 60.00
M-073 Bitumen ( Cationic Emulsion ) tonne 29860.70
INPUT
M-074 Bitumen (60-70 grade) tonne 41294.908
M-075 Bitumen (80-100 grade ) tonne 35477.50
NATIONAL HIGHWAYS AUTHORITY OF INDIA RATE ANALYSIS

M-077 Bitumen (emulsion) tonne 29860.70


M-078 Bitumen (CRMB-60) tonne 34509.90
M-079 Brick each 5.99
M-081 Cement tonne 5500.00
M-082 Cold twisted bars (HYSD Bars) tonne 41269
M-083 Coller for joints 300 mm dia nos 20.00
M-086 Copper Plate(12m long x 250mmwide) kg 1200
M-087 Corrosion resistant Structural steel tonne 34526.00
M-088 Corrugated sheet, 3 mm thick, "Thrie" beam section railing kg 51.00
M-089 Credit for excavated rock found suitable for use cum 100.00
M-090 Curing compound liter 150.00
M-091 Delineators from ISI certified firm as per the standard drawing given in IRC - 79 each 800.00
M-092 Earth Cost or compensation for earth taken from private land cum 80.00
M-093 Elastomeric slab seal expansion joint assembly manufactured by using chloroprene, elastomer for elastomeric slab unit conforming to metre 10000.00
M-094 Electric Detonators @ 1 detonator for 1/2 gelatin stick of 125 gms each 100 nos 1500.00
M-097 Epoxy primer kg 4.50
M-100 Flowering Plants each 25.00
M-101 Galvanised MS flat clamp nos 20.00
M-103 Galvanised structural steel plate 200 mm wide, 6 mm thick, 24 m long kg 40.00
M-104 Gelatin 80% kg 20.00
M-110 GI bolt 10 mm Dia nos 0.75
M-111 Grouting pump with agitator hour 206.00
M-112 Grass (Doob) kg 10.00
M-113 Grass (Fine) kg 10.00
M-118 Hot applied thermoplastic compound litre 169.00
M-119 HTS strand tonne 37000.00
M-120 Joint Sealant Compound kg 50.00
M-121 Jute netting, open weave, 2.5 cm square opening for seeding and Mulching sqm 30.00
M-123 M.S. Clamps nos 90.00
M-124 M.S. Clamps kg 45.00
M-126 Mild Steel bars/Angle/Channel tonne 51542.00
M-130 Nuts and bolts kg 60.00
M-131 Paint litre 145.00
M-132 Pavement Marking Paint litre 200.00
M-136 Pesticide kg 136.00
M-137 Pipes 200 mm dia, 2.5 m long for drainage metre 1181.00
M-138 Plastic sheath, 1.25 mm thick for dowel bars sqm 5.00
M-141 Pre moulded Joint filler,25 mm thick for expansion joint. sqm 200.00
M-142 Pre-coated stone chips of 13.2 mm nominal size cum 1649.66
M-144 Pre-moulded asphalt filler board sqm 200.00
M-148 Random Rubble Stone cum 395.00
M-149 RCC Pipe NP 4 heavy duty non presure pipe 1000 mm dia metre 5116.00
M-150 RCC Pipe NP 4 heavy duty non presure pipe 1200 mm dia metre 6201.60
M-151 RCC Pipe NP 3 heavy duty non presure pipe 300 mm dia metre 1772.00
M-152 Reflectorising glass beads kg 56.00
M-153 Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. (Copper Strips) metre 35.00
M-154 Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. (Galvanised carbon steel strips) metre 25.00
M-155 Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. (Glass reinforced polymer/ fibre reinforced polymer / polymeric strips) metre 20.00
M-156 Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. (Stainless steel strips) metre 30.00
M-157 Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. Aluminium strips) metre 20.00
M-158 Rivets each 2.00
M-159 Sand bags (Cost of sand and Empty cement bag) nos 6.00
M-160 Sapling 2 m high 25 mm dia each 80.00
M-161 Scrap tyres of size 900 x 20 nos 40.00
M-162 Seeds kg 100.00
M-163 Selected earth cum 73.00
M-164 Separation Membrane of impermeable plastic sheeting 125 micron thick sqm 4.00
M-165 Sheathing duct metre 80.00
M-166 Shrubs each 15.00
M-167 Sludge / Farm yard manure @ 0.18 cum per 100 sqm at site of work for turfing cum 150.00
M-172 Steel drum 300 mm dia 1.2 m high/empty bitumen drum nos 100.00
M-174 Steel pipe 25 mm external dia as per IS:1239 metre 123.16
M-175 Steel pipe 50 mm external dia as per IS:1239 metre 302.31
M-178 Strip seal expansion joint metre 8500.00
M-179 Structural Steel tonne 55983.00
M-180 Super plastisizer admixture IS marked as per 9103-1999 kg 56.00
M-181 Synthetic Geogrids as per clause 3102.8 and approved design and specifications. sqm 425
M-182 Through and bond stone each 40.00
M-183 Tie rods 20mm diameter nos 365
M-184 Tiles size 300 x 300 mm and 25 mm thick each 15.88
M-185 Timber cum 780
M-186 Traffic cones with 150 mm reflective sleeve nos 375
INPUT
M-187 Tube anchorage set complete with bearing plate, permanent wedges etc nos 3450.00 9
M-188 Unstaked lime (filler) may be Cement tonne 5500.00
M-189 Water KL 125.00
NATIONAL HIGHWAYS AUTHORITY OF INDIA RATE ANALYSIS

M-190 Water based cement paint litre 35.00


M-191 Welded steel wire fabric kg 85
M-192 Wire mesh 50mm x 50mm size of 3mm wire kg 48
M-193 Wooden ballies 2" Dia for bracing each 150
M-194 Wooden ballies 8" Dia and 9 m long each 85
M-195 Wooden packing cum 875
M-196 Wooden staff for fastening of flag 25 mm dia, one m long each 245
M-197 Gunny Bags each 3.00
M-198 Redoxide Primer Kl 98.00

INPUT
10
NATIONAL HIGHWAYS AUTHORITY OF INDIA RATE ANALYSIS

ORISSA Government Labour Rates

Unit rate Unit Rate per


Sl. No. Type of Labour per Month. Day.
(Rs.) (Rs.)

1 Highly Skilled 8529.00 284.30

2 Skilled 7929.00 264.30

3 Semi Skilled 7329.00 244.30

4 Un Skilled 6729.00 224.30

Bitumen Rates (IOCL) Ex- Haladia w.e.f 01.09.2018

Education
Rate @ Haladia Unit Rate Cost of Haulage Excluding Cost
Sl. No. Type of Bitumen Unit Basic GST @ 18% Cess @ 3% on Ex-MI Price CST @ 2% Entry Tax @ 2%
(Rs.) (Rs.) Loading and Unloading (Rs.)
ED

Lead From Haladia = 232 km Surfaced Road tonne.km 4.10

1 VG30 grade (packed) tonne 30140.00 5425.20 0.00 0.00 0.00 0.00 0.00 35565.20 3027.50 38592.70
2 VG30 grade (bulk) tonne 32430.00 5837.40 0.00 0.00 0.00 0.00 0.00 38267.40 3027.50 41294.90

3 80/100 grade (packed) tonne 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3027.50 3027.50

4 VG40 grade (bulk) tonne 27500.00 4950.00 0.00 0.00 0.00 0.00 0.00 32450.00 3027.50 35477.50
5 Emulsion (M) bulk tonne 22740.00 4093.20 0.00 0.00 0.00 0.00 0.00 26833.20 3027.50 29860.70
6 CRMB-60 bulk tonne 26680.00 4802.40 0.00 0.00 0.00 0.00 0.00 31482.40 3027.50 34509.90
7 CRMB-55 bulk tonne 28960.00 5212.80 0.00 0.00 0.00 0.00 0.00 34172.80 3027.50 37200.30

This Price includes 18% GST.

Market Rate
Chandikhol - Paradip Section (NH-5A) 9
NATIONAL HIGHWAYS AUTHORITY OF INDIA RATE ANALYSIS

Aggregate Cost
Sl. No Description Unit Cost at Royalty Total Cost Cost of Haulage Excluding Total Cost
Quarry site (Rs.) (Rs.) Loading and Unloading per cum
(Rs.) (Rs.)

Royalty = Rs 130/ per Cum


1 Stone Boulder of size 150mm and below at cu m 143.81 130.00 273.81 660.07 933.88
Crusher plant
2 Aggregate of size 63 mm and below at Crusher cu m 611.43 130.00 741.43 660.07 1401.50
plant
3 Aggregate of size 40 mm and below at Crusher cu m 709.52 130.00 839.52 660.07 1499.59
plant
4 Aggregate of size 20 mm and below at Crusher cu m 1000.00 130.00 1130.00 660.07 1790.07
plant
5 Aggregate of size 16 mm and below at Crusher cu m 1033.33 130.00 1163.33 660.07 1823.40
plant
6 Aggregate of size 12 mm and below at Crusher cu m 1048.57 130.00 1178.57 660.07 1838.64
plant
7 Aggregate of size 10 mm and below at Crusher cu m 1071.43 130.00 1201.43 660.07 1861.50
plant
8 Aggregate of size 6 mm and below at Crusher cu m 716.19 130.00 846.19 660.07 1506.26
plant
Aggregate of size4.75 mm and below at Crusher cu m 647.62 130.00 777.62 660.07 1437.69
plant
Aggregate of size2.36 mm and below at Crusher cu m 628.57 130.00 758.57 660.07 1418.64
plant
9 Aggregate of size Dust at Crusher plant cu m 80.95 35.00 115.95 660.07 776.02

Sand Cost
Sl. No Description Unit Cost at Royalty Total Cost Cost of Haulage Including Total Cost 187.5
Quarry site (Rs.) (Rs.) Loading and Unloading per cum
(Rs.) (Rs.)

Royalty = Rs 35/ per Cum

1 Mortar Sand Cost at baitarini Cum 48.57 35.00 83.57 554.47 638.04

2 Fillng Sand Cost at Batarini cu m 42.86 35.00 77.86 554.47 632.33

Moorum Cost

Cost at Total Cost


Royalty Total Cost Cost of Haulage Including
Sl. No Description Unit Quarry site per cum
(Rs.) (Rs.) Loading and Unloading
(Rs.) (Rs.)

Royalty = Rs 35/ per Cum

1 Moorum Cost cu m 45.71 35.00 80.71 193.67 274.38

Market Rate
Chandikhol - Paradip Section (NH-5A) 10
NATIONAL HIGHWAYS AUTHORITY OF INDIA RATE ANALYSIS

Reinforcement Cost at BBSR


Sl. No Description Unit Ex BBSR Entry Tax @ Amount VAT @ 4% Total Amount Average Cost
Price per MT 1% (Rs.) (Rs.) (Rs.) (Rs.)
(Rs.) (Rs.) Not
Applicable
Steel Owner: SAIL; Rate as on January 2018
HYSD Bars/ TMT Bar
3 25mm tonne 55300.00 0.00 55300.00 0.00 55300.00
4 20mm tonne 55300.00 0.00 55300.00 0.00 55300.00
5 16mm tonne 55300.00 0.00 55300.00 0.00 55300.00 41269
55983.00
6 12mm tonne 55300.00 0.00 55300.00 0.00 55300.00
7 10mm tonne 56500.00 0.00 56500.00 0.00 56500.00
8 8mm tonne 58200.00 0.00 58200.00 0.00 58200.00
Structural Steel 0.00
9 Angle tonne 49560.00 0.00 49560.00 1982.40 51542.40 51542.00
10 Channel tonne 49560.00 0.00 49560.00 1982.40 51542.40
Mild Steel Bar 51542.00
11 HYSD Bars/ TMT Bar tonne 55983.00

RCC Hume Pipe Cost at Chandikhole


Sl. No Description Unit Cost at 18% GST Total Amount Cost of Haulage Including Average Cost
Factory (Rs.) (Rs.) Loading and Unloading per Lm
(Rs.) (Rs.)

NP-4 RCC Pipes


1 300 mm dia. 2.5 Lm 3500.00 630.00 4130.00 300.00 1772.00
2 600 mm dia. 2.5 Lm 6000.00 1080.00 7080.00 350.00 2972.00 6000
3 900 mm dia. 2.5 Lm 9800.00 1764.00 11564.00 400.00 4785.60 9800
4 1000 mm dia. 2.5 Lm 10500.00 1890.00 12390.00 400.00 5116.00 10500
5 1200 mm dia. 2.5 Lm 12800.00 2304.00 15104.00 400.00 6201.60 12800

Market Rate
Chandikhol - Paradip Section (NH-5A) 11
NATIONAL HIGHWAYS AUTHORITY OF INDIA RATE ANALYSIS

RATES OF MATERIALS

Sl No Name of items Unit for Cuttack


Adopted Rate in Rs. in
District
SOR - 2014 (Post GST) , Govt. of
7500 Orissa , w.e.f. 01.07.2017
Well burnt clamp burnt bricks(25cmx12cmx8cm) having
crushing strength not less than 35 Kg/ Cm2 with dimensional 1000 Nos 3089.36
1 tolerance +8percent
Well burnt clamp burnt bricks(23cmx11cmx8cm) having
crushing strength not less than 35 Kg/ Cm2 with dimensional 1000 Nos 2780.43
2 tolerance +8percent

K.B bricks(25cmx12cmx8cm) having crushing strength not 1000 Nos 4844.26


3 less than 75 Kg/ Cm2 with dimensional tolerance +8percent

K.B bricks(23cmx11cmx8cm) having crushing strength not 1000 Nos 4119.15


4 less than 75 Kg/ Cm2 with dimensional tolerance +8percent

Flyash bricks (25cmx12cmx8cm) having crushing strength not 1000 Nos 4144.68
5 less than 75 Kg/ Cm2 with dimensional tolerance +2percent

Flyash bricks (23cmx11cmx8cm) having crushing strength not 1000 Nos 3529.36
6 less than 75 Kg/ Cm2 with dimensional tolerance +2percent
Flyash bricks (30cmx20cmx15cm) having crushing strength
not less than 75 Kg/ Cm2 with dimensional tolerance Each 12.77
7 +2percent
Cemen concrete solid Block machine mixed and Hydraulic
compressed having crushing strength not less than 75 Kg/
8 Cm2
Each 22.05
a 400mmx 200mmx 200mm size
Each 17.32
b 400mmx 150mmx 200mm size
Each 11.81
c 400mmx 100mmx 150mm size
Each 13.39
d 300mmx200mmx 150mm size
Each 11.02
e 300mmx150mmx 150mm size
Each 9.45
f 300mmx100mmx 150mm size
Cemen concrete Hollow Block machine mixed and Hydraulic
compressed having crushing strength not less than 70 Kg/
9 Cm2
Each 19.69
a 400mmx 200mmx 200mm size
Each 14.96
b 400mmx 150mmx 200mm size
Each 11.02
c 400mmx 100mmx 200mm size

Chandikhol - Paradip Section (NH-5A)


NATIONAL HIGHWAYS AUTHORITY OF INDIA RATE ANALYSIS

RATES OF MATERIALS

Sl No Name of items Unit Rate in Rs.


Each 11.02
d 300mmx200mmx 150mm size
Each 10.24
e 300mmx150mmx 150mm size
Each 7.87
f 300mmx100mmx 150mm size
1 Cum 298.72
10 K. B. bricks Khoa 4Cm. Size
1 Cum 257.02
11 Clamp burnt bricks Khoa 4Cm. Size
1 Cum 357.45
12 Surkhi of Clamp burnt bricks
1 Cum 371.06
13 Surkhi of Klin burnt bricks
1 Cum 138.10
14 Screen washed gravel for concrete ( 12mm - 20 mm)

1 Cum 45.71
15 Gravel or moorum
Stone Screned Dust passing through 2.36 mm sieve and 1 Cum 80.95
16 retained on 0.075mm sieve
1 Cum 92.38
17 River single or bajri ( 12 mm - 20 mm)
1 Cum 48.57
18 Screened and washed sharp sand for mortar
1 Cum 42.86
19 Sand for filling and road blinding
1 Cum 47.62
20 Clay mortar for masonary work with admixture of sand.
1 Kg 13.33
21 Stone lime unslaked.
1 Kg 18.10
22 Ghooting lime unslaked
1 Kg 16.19
23 Shell lime unslaked.

24
1 Cum 206.11
a Granite broken stone not less than 0.0025 Cum Stacked
1 Cum 179.91
b Granite broken stone not less than 0.0025 Cum Picked up.
Stone other than granite quarried, broken and stacked 0.0015
1 Cum 184.76
25 Cum to 0.003 Cum
Stone other than granite picked up, broken and stacked
1 Cum 161.90
26 0.0015 Cum to 0.003 Cum
Stone other than granite quarried, broken and stacked above
1 Cum 173.33
27 0.003 Cum
Stone other than granite picked up, broken and stacked
1 Cum 161.90
28 above 0.003 Cum

Chandikhol - Paradip Section (NH-5A)


NATIONAL HIGHWAYS AUTHORITY OF INDIA RATE ANALYSIS

RATES OF MATERIALS

Sl No Name of items Unit Rate in Rs.


Granite Stone broken metal 63mm size passing through
29 90mm Sieve retained on 53mm sieve
1 Cum 611.43
a) Crusher broken
1 Cum 492.38
b) Hand broken
Granite Stone broken metal 45mm size passing through
30 53mm Sieve retained on 26mm sieve
1 Cum 633.33
a) Crusher broken
1 Cum 191.43
b) Hand broken

31 Granite Stone broken metal 40mm size


1 Cum 709.52
a) Crusher broken
1 Cum 566.67
b) Hand broken
Granite Stone broken metal 26.5mm size( Passing through
32 45mm sieve & retained on 22.4 mm)
1 Cum 747.62
a) Crusher broken
1 Cum 569.52
b) Hand broken
Granite Stone broken metal 25mm size( Passing through
33 40mm sieve & retained on 20 mm)
1 Cum 761.90
a) Crusher broken
1 Cum 580.95
b) Hand broken
Granite Stone broken metal 22mm size( Passing through
34 26.5mm sieve & retained on11.2 mm)
1 Cum 790.48
a) Crusher broken
1 Cum 605.71
b) Hand broken
Granite Stone broken metal 20mm size( Minium 65% by Wt.
Passing through 19 mm sieve & retained on 13.2 mm sieve.
35 But whole should pass 26.5 mm sieve))
1 Cum 1000.00
a) Crusher broken
1 Cum 784.76
b) Hand broken
Granite Stone broken chips 13.2 mm size( Passing through
36 22.4 mm sieve & retained on 11.2 mm sieve.)
1 Cum 1033.33
a) Crusher broken
1 Cum 797.14
b) Hand broken

Chandikhol - Paradip Section (NH-5A)


NATIONAL HIGHWAYS AUTHORITY OF INDIA RATE ANALYSIS

RATES OF MATERIALS

Sl No Name of items Unit Rate in Rs.


Granite Stone broken chips 12mm size( Minium 65% by Wt.
Passing through 13.2 mm sieve & retained on 9.5 mm sieve.
37 But whole should pass 19 mm sieve))
1 Cum 1048.57
a) Crusher broken
1 Cum 810.48
b) Hand broken
Granite Stone broken chips 11.2 mm size( Passing through
38 13.2 mm sieve & retained on 5.6 mm sieve.)
1 Cum 1072.38
a) Crusher broken
1 Cum 828.57
b) Hand broken
Granite Stone broken chips 10mm size( Minium 65% by Wt.
Passing through 9.5 mm sieve & retained on 6.3 mm sieve.
39 But whole should pass 13.2 mm sieve)
1 Cum 1071.43
a) Crusher broken
1 Cum 823.81
b) Hand broken
Granite Stone broken chips 6.7 mm size( Passing through 1 Cum 716.19
(A) 11.2 mm sieve & retained on 2.8 mm sieve.)
Granite Stone Screening ( Passing through 2.36 mm sieve & 1 Cum 628.57
(B) retained on 180 micron sieve.)
Granite Stone broken chips 4.7 mm size( Passing through 1 Cum 647.62
40 6.7 mm sieve & retained on 2.36 mm sieve.)
1 Cum 241.90
41 Stone other than granite broken to 5 Cm size
1 Cum 247.62
42 Stone other than granite broken to 4 Cm size
1 Cum 264.76
43 Stone other than granite broken to 2 Cm size
1 Cum 276.19
44 Stone other than granite broken to 1 Cm size
stone boulder 15 cm & above size picked up and nullah 1 Cum 143.81
45 boulders
Soilling stone boulder 15 cm & above size picked up nullah 1 Cum 149.52
46 boulder broken
Stone boulder 15 cm & above size other than granite or 1 Cum 115.24
47 laterite picked up and nullah boulders
Soilling stone boulder 15 cm & above other than granite or
1 Cum 126.67
48 laterite picked up nullah boulder broken

1 Cum 115.24
49 Soling stone boulder 10 cm size picked up other than granite

Chandikhol - Paradip Section (NH-5A)


NATIONAL HIGHWAYS AUTHORITY OF INDIA RATE ANALYSIS

RATES OF MATERIALS

Sl No Name of items Unit Rate in Rs.


1 Cum 184.76
50 Hard broken soling stone other than granite ( 40mm to 90mm)
1 Cum 599.05
51 I.R.C Grade I ( 90mm-45mm)
1 Cum 668.57
52 I.R.C Grade II ( 63mm-45mm)
1 Cum 714.29
53 I.R.C Grade III ( 53mm-22.4mm)
1 Cum 97.14
54 Laterite soling stone 23 cm.size
1 Cum 538.10
55 Laterite Stone rough dressed
1 Sqm 100.41
56 Bamboo mat or talai
1 Sqm 110.37
57 Bamboo 1st class 7 cm to 10 cm dia & above 63. Long

58
1 Sqm 24.90
a) Belongi Bamboo 2.51 cm to 4 cm dia & above 5 cm long
1 Sqm 33.20
b) Belongi Bamboo above 4 cm to 7 cm dia & above 5 cm long
1 Mtr. 83.82
59 Sal bullahs 75 mm to 120mm dia up to 5.5 n. long
1 Mtr. 93.78
60 Sal bullahs 150 mm to 200mm dia up to 5.5 n. long
Sal bullahs above 200mm & upto 250mm dia up to 2.75 m.
1 Cum 7264.73
61 long
Sal bullahs above 200mm & upto 250mm dia up to 2.75 m.
1 Cum 8234.02
62 long & upto 4.75 long
Sal bullahs above 200mm & upto 250mm dia above 4.75 m.
1 Cum 9235.68
63 long
Sal bullahs above 250mm & upto 380mm mean dia up to
1 Cum 10594.19
64 2.75 m. long
Sal bullahs above 250mm & upto 380mm mean dia & above
1 Cum 13154.36
65 2.75 m.long up to 4.75 m. long
Sal bullahs above 250mm & upto 380mm dia above 4.75 m.
1 Cum 14131.95
66 long
1 Mtr. 39.83
67 Non-sal bullahs 75mm mean dia of any length
1 Mtr. 52.28
68 Non-sal bullahs 100mm mean dia of any length
1 Mtr. 60.58
69 Non-sal bullahs 125mm mean dia of any length
1 Mtr. 73.86
70 Non-sal bullahs 150mm to 200mm mean dia of any length
Non-sal bullahs above 200mm &upto 250mm mean dia upto 1 Cum 5199.17
71 2.5m long

Chandikhol - Paradip Section (NH-5A)


NATIONAL HIGHWAYS AUTHORITY OF INDIA RATE ANALYSIS

RATES OF MATERIALS

Sl No Name of items Unit Rate in Rs.


Non-sal bullahs above 200mm &upto 250mm mean dia above
1 Cum 5774.27
72 2.5m long
Seasoned rough dressed sawn Sal wood having min. 1 Cum 27212.45
73 dimension 50mm to 150mm & up to 2.75m. Long
Seasoned rough dressed sawn Sal wood having min. 1 Cum 29702.07
74 dimension 50mm to 150mm & above 2.75m. Long
Seasoned Sal wood beam of cross sectional area not less
than 150 Sq cm & least lateral dimension 100 mm & above 1 Cum 29952.70
75 2.75m. Long.

Seasoned Sal wood planks not more than 75mm thick & not 1 Cum 26698.76
76 less than 200mm width

1 Cum 43079.67
77 Seasoned Piasal wood planks for shutters
1 Cum 56688.80
78 Seasoned Teak wood planks for shutters
Non Sal wood scantling & plants ( Tentera,Kasi,Gamhari,
1 Cum 16421.58
79 Kuruma)
1 Cum 9987.55
80 Non-Sal reapers.
424.00
81 Fire wood 1 Qtl.
714.96
82 1st class Raniganj or Mangalore pattern tiles 100 Nos
1126.77
83 Ridges of Raniganj or Mangalore pattern tiles. 100 Nos
228.35
84 Flat tiles ( 14 Cmx 14 Cmx 1Cm) 1000 Nos
245.67
85 Flat tiles ( 15 Cmx 15 Cmx 1.2Cm) 1000 Nos
962.99
86 Flat tiles ( 30 Cmx 15 Cmx 2.5Cm) 1000 Nos
1124.41
87 Flat tiles ( 30 Cmx 30 Cmx 2.5Cm) 1000 Nos
240.94
88 Pan tiles 1000 Nos
503.15
89 Nuria tiles ( 20cm to 25 cm) 1000 Nos
593.70
90 Nuria tiles ( 20cm to 30 cm) 1000 Nos
730.71
91 Ridge tiles 1000 Nos

92 Marble Tiles of minimum 16mm thick, dunguri variety


428.35
(a) Upto 0.10 Sqm. 1 Sqm
523.62
(b) Above 0.10 Sqm. To 0.40 Sqm. 1 Sqm

Chandikhol - Paradip Section (NH-5A)


NATIONAL HIGHWAYS AUTHORITY OF INDIA RATE ANALYSIS

RATES OF MATERIALS

Sl No Name of items Unit Rate in Rs.


590.55
© Above 0.4 Sqm. To 1.00 Sqm 1 Sqm

93 Kota Tiles of minimum 16mm thick


316.54
(a) Upto 0.10 Sqm. 1 Sqm
386.61
(b) Above 0.10 Sqm. 1 Sqm
248.03
94 Khandolites ( Up to 0.06 Sqm.) 1 Sqm

95 Granite Tiles
923.62
(a) Upto 0.10 Sqm.( 10 mm thick) 1 Sqm

(b) Above 0.10 Sqm 1 Sqm


1048.03
I) Above 0.10 Sqm & up to 0.4 Sqm ( 10mm thick) 1 Sqm
1645.67
ii) Above 0.40 Sqm ( 20mm thick) 1 Sqm

96 Kodappa Tiles of 10mm thick


237.80
(a) Above 0.1 Sqm & upto 0.40 Sqm 1 Sqm
285.83
(b) Above 0.40 Sqm. 1 Sqm
314.17
97 Dholpuri Stone Tiles 1 Sqm
( A) Ceramic wall tiles of premium grade having thickness
98 6.5mm to 6.7mm confirming to IS 13753 of following sizes

304.72
( I ) 30cmx20cm/20cmx20cm special plain / printed series 1 Sqm
( B) Ceramic wall tiles of premium grade having thickness
7mm to 8mm confirming to IS 13755 of following sizes
326.77
( I ) 30cmx30cm/40cmx20cm special plain / printed series 1 Sqm
( C) Vitrified floorl tiles of premium grade having thickness
8mm to 10mm confirming to IS 13756 of following sizes
( i ) 60cmx60cm plain ( Ivory) 1 Sqm 514.17
( ii ) 60cmx60cm coloured / Printed series 1 Sqm 559.06
( C) Vitrified industrial floorl tiles of premium grade having
thickness 8mm to 10mm confirming to IS 4457 of following
467.72
( i ) 30cmx30cm plain 1 Sqm
170.87
99 Chequred Tiles 1 Sqm

100 Terrazo Tiles

Chandikhol - Paradip Section (NH-5A)


NATIONAL HIGHWAYS AUTHORITY OF INDIA RATE ANALYSIS

RATES OF MATERIALS

Sl No Name of items Unit Rate in Rs.


195.28
( a) With grey cement 1 Sqm
231.50
(b) With white cement 1 Sqm
101.57
101 Red oxide primer 1 Litre
114.17
102 Wood Primer do
125.20
103 Wood shine paint do
196.06
104 Plastic Emulsion Paint do
149.61
105 Enamel Paint do
51.97
106 Distemper 1 KG
36.22
107 cement Paint do
90.55
108 Red Oxide power do
129.92
109 French Polish 1 Litre
125.20
110 Varnish do
9.45
111 Plaster of Paris do
37.45
112 Coal Tar do

113 G.C.I Sheet


239.15
a) 0.30mm thick 1 Sqm
240.85
b) 0.40mm thick 1 Sqm
146.46
114 A.C Sheet do
148.03
115 A.C. ridges 1 pair
181.89
116 6mm thick plain A.C. Sheet 1 Sqm
14.47
117 Tar paper do
22.05
118 Putty ( wood) 1 KG
77.95
119 Putty ( iron) do
51.06
120 Wire nails do
5900.00
121 M.S. Angle 1 Qtl.

Chandikhol - Paradip Section (NH-5A)


NATIONAL HIGHWAYS AUTHORITY OF INDIA RATE ANALYSIS

RATES OF MATERIALS

Sl No Name of items Unit Rate in Rs.


5900.00
122 M.S. Channel do
60.63
123 Bolt, Nut & Washers 1 KG
Holding down bolts minimum 60 Cm. Long with 15 Cmx 15
58.27
124 Cmx 6 Cm size washer plate do
67.23
125 Binding wire do
43.40
126 Coir String do
313.01
127 Empty cement bags ( HDPE) by lot & not shorted out 100
313.01
b) Empty Cement gunny bags by lot & not shorted out 100 nos
107.32
c) Empty Bitumen Drum Each
205.69
d) Empty Bitumen Emulsion Drum Each
223.58
128 Straw in Bundle 100 nos
528.38
129 Marble Chips 1 Qtl.
307.42
130 Marble Power do

131 Cement
568.00
a) 33 Grade do
568.00
b) 43 Grade do
568.00
c) 53 Grade do
1515.75
132 White Cement do

133 Steel do
6200.00
a) Plain do
6200.00
b) HYSD ( FE-415) do
4699.57
134 " Z " type Steel Sheet Piles do
257.64
135 Bentonite Power do

136 Butt hinges ( ISI)


4.72
a) 50mmx37mmx1.5mm Each
6.30
b) 75mmx47mmx0.70mm Each

Chandikhol - Paradip Section (NH-5A)


NATIONAL HIGHWAYS AUTHORITY OF INDIA RATE ANALYSIS

RATES OF MATERIALS

Sl No Name of items Unit Rate in Rs.


11.02
c) 100x58x1.90mm Each
17.32
d) 125x65x2.12mm Each

137 M.S.Aldrop ( ISI )


72.44
a) 250x16mm Each
77.95
b) 300x16mm Each

138 M.S.Handle ( ISI )


11.02
a) 100mm Each
12.60
b) 125mm Each
15.75
c) 150mm Each

139 M.S.Tower Bolt ( ISI )


13.39
a) 100x10mm Each
20.47
b) 150x10mm Each
26.77
c) 200x10mm Each

140 M.S.Screw ( ISI )


22.83
a) 12x3mm 100 pcs
25.98
b) 12x4mm 100 pcs
29.13
c) 20x4mm 100 pcs
30.71
d) 20x5mm 100 pcs
32.28
e) 25x4mm 100 pcs
37.01
f) 25x5mm 100 pcs
38.58
g) 30x4mm 100 pcs
40.16
h) 30x5mm 100 pcs
43.31
I) 30x6mm 100 pcs
45.67
j) 35x6mm 100 pcs
48.03
k) 35x7mm 100 pcs

Chandikhol - Paradip Section (NH-5A)


NATIONAL HIGHWAYS AUTHORITY OF INDIA RATE ANALYSIS

RATES OF MATERIALS

Sl No Name of items Unit Rate in Rs.


55.91
l) 35x8mm 100 pcs
59.84
m) 50x7mm 100 pcs
63.78
n) 50x8mm 100 pcs

141 Steel window stay bar (ISI)


19.69
a) 200mm Each
23.62
b) 250mm Each
29.13
c) 300mm Each

142 Steel window handle including Nut, bolt & washer ( ISI)
15.75
a) 100mm Each
20.47
b) 150mm Each

143 Welded mesh


151.49
a) 25mmx25mmx11 gauge Sqm
141.28
b) 25mmx25mmx13 gauge Sqm
141.28
c) 50mmx25mmx11 gauge Sqm
128.51
d) 50mmx25mmx13 gauge Sqm
54.47
144 G.I. " L" & "J" hook Kg
58.27
145 W.I.clamp Kg

Aluminium Fittings

146 Butt hinges ( ISI)


51.97
a) 125mmx75mmx4mm Each
43.31
b) 125mmx63mmx4mm Each
40.16
c) 100mmx75mmx4mm Each
38.58
d) 100mmx63mmx4mm Each
25.98
e) 75mmx63mmx4mm Each
10.24
f) 50mmx35mmx3.2mm Each

Chandikhol - Paradip Section (NH-5A)


NATIONAL HIGHWAYS AUTHORITY OF INDIA RATE ANALYSIS

RATES OF MATERIALS

Sl No Name of items Unit Rate in Rs.

147 Aluminium Handle ( ISI)


22.05
a) 150mm with 175mmx40mm flat Each
22.05
b) 125mm with 175mmx40mm flat Each
21.26
c) 100mm with 150mmx33mm flat Each
20.47
d) 75mm with 118mmx33mm flat Each

148 Aluminium Tower bolt ( barrel type) ( ISI)


50.39
a) 300mmx10mm Each
47.24
b) 250mmx10mm Each
42.52
c) 200mmx10mm Each
36.22
d) 150mmx10mm Each
29.13
e) 100mmx10mm Each

149 Sliding door bolt ( Aldrop) ( ISI)


170.08
a) 300mmx16mm Each
161.42
b) 250mmx16mm Each
Brass Fittings

150 Butt hinges light/ordinary ( ISI)


54.47
a) 125mmx70mmx4mm Each
41.70
b) 100mmx70mmx4mm Each
30.64
c) 75mmx40mmx2.5mm Each
15.32
d) 50mmx40mmx2.5mm Each

151 Butt hinges ( Heavy type)( ISI)


171.06
a) 125mm x 85mm x 5.5mm (0.07 kg) Each
155.74
b) 100mm x 85mm x 5.5mm (0.056 kg ) Each
65.53
c) 75mm x 65mm x 4mm ( 0.02 kg) Each

152 Brass tower bolt ( Barrel type) ( ISI)

Chandikhol - Paradip Section (NH-5A)


NATIONAL HIGHWAYS AUTHORITY OF INDIA RATE ANALYSIS

RATES OF MATERIALS

Sl No Name of items Unit Rate in Rs.


167.66
a) 250mm x 10mm Each
141.28
b) 200mm x 10mm Each
105.53
c) 150mm x 10mm Each
78.30
d) 100mm x 10mm Each

153 Brass Screws ( ISI)


148.94
a) 50mm 100 Nos
134.47
b) 40mm 100 Nos
114.89
c) 30mm 100 Nos
104.68
d) 25mm 100 Nos
77.45
e) 20mm 100 Nos

154 Chromium plated fittings ( Brass) (ISI) handle


123.40
a) 125mm with 175 x 32 mm plate Each
106.38
b) 100mm with 150 x 25mm plate Each
92.77
c) 75mm with 125 x 25mm plate Each

155 Wall cement Primer ( ISI)


90.55
a) Oil Bound 1 Litre
115.75
b) Water Bound 1 Litre
125.98
156 Aluminium paint ( ISI) 1 Litre
146.46
157 Weather seal coat 1 Litre
163.78
158 Adhesive ( ISI) Kg
159 Bituminous expansion joint board ( ISI)
589.08
a) 12mm thick Sqm
815.13
b) 16mm thick Sqm
1065.55
c) 25mm thick Sqm
56.17
160 Barbed wire ( ISI) Kg

Chandikhol - Paradip Section (NH-5A)


NATIONAL HIGHWAYS AUTHORITY OF INDIA RATE ANALYSIS

RATES OF MATERIALS

Sl No Name of items Unit Rate in Rs.

161 Glass Plain ( ISI)


287.66
a) 3mm Sqm
323.40
b) 4mm Sqm
442.55
c) 5mm Sqm
497.87
d) 6mm Sqm
765.96
e) 8mm Sqm
960.85
f) 10mm Sqm
1132.77
g) 12mm Sqm

162 Glass pin headed ( ISI)


259.57
a) 4mm Sqm
329.36
b) 5mm Sqm

163 Black Glass ( ISI)


444.26
a) 4mm Sqm
526.81
b) 5mm Sqm
636.60
c) 6mm Sqm
1005.96
d) 8mm Sqm
1595.74
e) 12mm Sqm

164 Frostee glass ( ISI)


437.45
a) 4mm Sqm
468.94
b) 5mm Sqm
537.02
165 Wire glass - 6mm ( ISI) Sqm

166 Sun-control film ( ISI)


485.11
a) Reflective Sqm
344.68
b) Non- reflective Sqm

167 Prelaminated Particle board ( Novapan standard type) ( ISI )

Chandikhol - Paradip Section (NH-5A)


NATIONAL HIGHWAYS AUTHORITY OF INDIA RATE ANALYSIS

RATES OF MATERIALS

Sl No Name of items Unit Rate in Rs.


511.49
a) 9mm Sqm
571.06
b) 12mm Sqm
623.83
c) 18mm Sqm
685.96
d) 25mm Sqm

168 BWR ply wood ( ISI)


252.77
a) 3mm Sqm
285.96
b) 4mm Sqm
408.51
c) 6mm Sqm
504.68
d) 9mm Sqm
655.32
e) 12mm Sqm
768.51
f) 16mm Sqm
910.64
g) 19mm Sqm
1300.43
h) 25mm Sqm

169 BWR Block Board ( ISI)


687.66
a) 16mm Sqm
774.47
b) 19mm Sqm
859.57
c) 25mm Sqm
1081.70
d) 32mm Sqm

170 Vinyl Floorig ( ISI)

( A) Homogenious range ( ISI)


233.86
I) PVC ( MF) Classic Roll - 1.00mm thick Sqm
275.59
ii) PVC ( MF) Classic tilel - 1.00mm thick Sqm
317.32
iii) PVC ( MF) impress Roll - 1.50mm thick Sqm
366.14
iv) PVC ( MF) impress tile - 1.50mm thick Sqm
411.81
v) PVC ( MF) Super Roll - 2.00mm thick Sqm

Chandikhol - Paradip Section (NH-5A)


NATIONAL HIGHWAYS AUTHORITY OF INDIA RATE ANALYSIS

RATES OF MATERIALS

Sl No Name of items Unit Rate in Rs.


478.74
vi) PVC ( MF) Super tile - 2.00mm thick Sqm
( B) Heterogenious range ( ISI)
439.37
I) PVC ( MF) Hetero Roll - 2.00mm thick Sqm
488.98
ii) PVC ( MF) Hetero tile - 2.00mm thick Sqm
216.17
171 Aluminium extruded section Kg
Roll formed sections made of pre-painted steel ( base steel as
per IS - 513 of 0.6 mm thick " D" quality, galvanised as per IS -
172 277 with zinc of 120 gm/sqm)
a) Outer frames Po-527 mtr 286.81

b) Intermediate mullion Po-528 mtr 310.64

c) Shutter frame Po-153 mtr 242.55

d) Fixed beeding Po-179 mtr 125.11

e) Sliding shutter Po-254 mtr 149.79

f) Outer frames (side/top) Po-255 mtr 180.43

g) Outer frames (bottom) Po-256 mtr 125.96

h) Sliding track (SS) Po-257 mtr 466.38

I) Sashbar Po-101 mtr 440.00

j) Sashbar at shutter Po-107 mtr 222.98

k) Louvered horizontal ( Top / bottom) Po-193A mtr 125.96

l) 33 x 57 Box Section mtr 190.21

m) 100x50mm Box Sction mtr 431.49

n) Small Z Section mtr 212.77

o) Extendec Z Section mtr 285.11

p) Cover Profile mtr 102.98


Acessories

a) Sliding outer frame assembly / pc Each 227.23

b) Sliding shutter / pc Each 192.34

c) Sashbar Each 15.32


d) Wall fixing with polymide anchor at every 600mm c/c of
24.68
outer frame Each
e) Outer frame corner Each 37.45

f) Top hung shutter /pc Each 302.13

Chandikhol - Paradip Section (NH-5A)


NATIONAL HIGHWAYS AUTHORITY OF INDIA RATE ANALYSIS

RATES OF MATERIALS

Sl No Name of items Unit Rate in Rs.


g) Fixed mullion Each 46.81

h) Fixed galzing Each 93.62

I ) Louvered blade Each 24.68

j) Side hung door /pc Each 346.38

k) Door lock / pc Each 311.49

l) Swing door shutter / pc Each 174.47

m) Floor Spring ( Godrej Make) Each 2664.68


Gasket
a) For Shutter Po-153 mtr 34.89
b) For beading Po-179 mtr 46.81
c) For Sashbar Po-101 mtr 97.02

Chandikhol - Paradip Section (NH-5A)


II - RATE OF LABOUR (As per SOR 2014 (Post GST))

Sl No DESCRIPTION UNIT RATE IN RS.


1 2 3 4
A Category Unskilled
1 Male mulia Per day 224.30
2 Female mulia Per day 224.30
3 Survey Khalasi / Chain man Per day 224.30
4 Scavanger Per day 224.30
B Category Semi skilled
1 Mulia working in water or arduous nature of work Per day 244.30
Night mulia or attendent working in floodand other
2 emergent work Per day 244.30
3 Mulia for handling hot binder and Tar boiler men Per day 244.30
4 Sangi mulia Per day 244.30
5 pile driving mate ( Guide man) Per day 244.30
6 Mate Per day 244.30
Helper to carpenter or
Blacksmith/Painter/Blaster/Plumber/Eltrician/fitter/
7 Welder Per day 244.30
8 Hammer man Per day 244.30
9 Thatcher / Gharami Per day 244.30
10 Tile turner Per day 244.30
11 Boat man Per day 244.30
12 Bhisti Per day 244.30
13 Well sinker Per day 244.30
14 Rod binder and bender Per day 244.30
15 Cleaner / Sweeper Per day 244.30
16 Stone packer Per day 244.30
17 Pump helper Per day 244.30
18 Watch man ( Store) / Gurkha / Security Guard Per day 244.30
19 Bellow man Per day 244.30
C Category Skilled
1 Blaster ( Second Class) Per day 264.30
2 Mason ( Second Class) Per day 264.30
3 Black smith ( Second Class) Per day 264.30
4 Carpenter ( Second Class) Per day 264.30
5 Fitter ( Second Class) Per day 264.30
6 Painter / Polisher ( Second Class) Per day 264.30
7 Welder ( Second Class) Per day 264.30
8 Plumber ( Second Class) Per day 264.30
9 Driller ( Second Class) Per day 264.30
10 Stone dresser / Cutter ( Second Class) Per day 264.30
11 Cobbler with toolsr ( Second Class) Per day 264.30
Wire man / Lift operator / Diesel pump driver /
12 Telephone operator ( Second Class) Per day 264.30
13 Boring mistry / Pipe driver ( Second Class) Per day 264.30
Electrician / Rigger / Line man / Telephone
14 attendant ( Second Class) Per day 264.30
15 Gardener Per day 264.30
16 Amin Per day 264.30
Sl No DESCRIPTION UNIT RATE IN RS.
17 Tracer Per day 264.30
18 Jr. progress recorder Per day 264.30

Store keeper Gr - II / Store Asst./ Account clerk /


19 Clerk / Typist / Toolkeeper / Time keeper / Munsi Per day 264.30
D Category Highly Skilled
1 Blaster ( licensed) Per day 284.30
2 Mason ( Special) Per day 284.30
3 Carpenter ( Special) Per day 284.30
4 Blacksmith ( Special) Per day 284.30
5 Fitter ( Special) Per day 284.30
6 Painter / Polisher ( Special) Per day 284.30
7 Welder ( Special) Per day 284.30
8 Plumber ( Special) Per day 284.30
9 Driller ( Special) Per day 284.30
10 Stone dresser / Cutter ( Special) Per day 284.30
Diver for well sinking in bridge( per shift of four
11 hours) Per day 284.30

Electrician / Airconditioned plant operator / wire


12 man / Lift operator / Diesel pump operator( Special) Per day 284.30
Jeep driver / Tractor driver / Truck driver / Dozer
driver / Roller driver / Concrete mixture operator /
13 Crane operator Per day 284.30
14 Auto eleectrician Per day 284.30
15 Guiniting Machine operator Per day 284.30
16 Senior Accountant / Stenographor Per day 284.30
17 Supervisor / Manager Per day 284.30
Testing Laboratory Assistant / Instrument
18 Mechanic / Telephone Mechanic Per day 284.30
Rigger and Cobbler with Tools Driver ( Heavy
19 Vehicle) Per day 284.30
E Other Category
1 Boring Mistry ( Special) Per day 284.30
2 Winch Operator Per day 284.30
3 Well sinker ( Special) Per day 284.30
4 Helper to Well sinker Per day 264.30
5 Computer Programmer / Analyzer Per Month 7000.00
6 Computer Operator Per Month 5200.00
Helper to operator of Heavy construction
7 Machineries Per Month 5000.00
8 Mechanic for Heavy construction Per Month 6000.00
Helper to mechanic of Heavy construction
9 Machineries Per Month 5000.00
10 operator for Heavy construction Per Month 6000.00

11 Junior Research Assistant ( Technical Assistant) Per Month 5200.00


Lead in Km
Average Project Length=78/2 =39 km
From Road to Quarry =24 km
Total Lead =63. km
Lead Statement
Stone Aggregate
Distance from NH-
Sl.no Name of Quarry Average Lead in km Total Lead in Km
5A
1 Chadheidhara 24 39 63.00

Rate for conveyance of materials (Aggregate)


Distance to be
cost per 1 cum Amount
carried
Up to 5 km 149.67 149.67

Every extra km beond


8.80 510.40
5 km and up to 50 km

Total 660.1

Sand
Distance from NH-
Sl.no Name of Quarry Average Lead in km Total Lead in Km
5A
1 Mahanadi river 12.0 39 51.00

Rate for conveyance of materials (Sand)


Distance to be
cost per 1 cum Amount
carried
Up to 5 km 149.67 149.67

Every extra km beond


8.80 404.80
5 km and up to 50 km

Total 554.47

Bricks
Distance from NH-
Sl.no Name of Quarry Average Lead in km Total Lead in Km
5A
1 Near River bank 4.0 39 43.00

Rate for conveyance of materials (Bricks)


Distance to be
cost per 2500 no Amount
carried
Up to 5 km 967.27 967.27
Every extra km beond
39.62 1505.56
5 km and up to 50 km
Total 2472.83
Per 1000 no 989.13
Cement
Distance from NH-
Sl.no Name of Quarry Average Lead in km Total Lead in Km
5A
1 Local Market 0.0 39 39.00

Rate for conveyance of materials (Cement)


Distance to be
cost per 1000 kg Amount
carried
Up to 5 km 161.72 161.72

Every extra km beond


8.23 279.82
5 km and up to 50 km

Total 441.54

Rate for conveyance of materials (R.R stone)

Distance to be
cost per 1 cum Amount
carried
Up to 5 km 149.67 149.67

Every extra km beyond


8.80 325.60
5 km and up to 50 km

Total 475.27
Gravel/Morum
Distance from NH-
Sl.no Name of Quarry Average Lead in km Total Lead in Km
5A
1 Marshaghai 3.0 7 10.00

Rate for conveyance of materials (Gravel)


Distance to be
cost per 1 cum Amount
carried
Up to 5 km 149.67 149.67

Every extra km beond


8.80 44.00
5 km and up to 50 km

Total 193.67

HYSD steel
Distance from NH-
Sl.no Name of Place Average Lead in km Total Lead in Km
5A
1 Local Market 0.0 39 39.00

Rate for conveyance of materials (HYSD Steel)


Distance to be
cost per1000 kg Amount
carried
Up to 5 km 161.72 161.72
Every extra km beond
8.23 279.82
5 km and up to 50 km
Total 441.54
Bitumen

Distance from NH-6


Sl.no Name of Place
towards Kolkota+NH 5
Average Lead in km Total Lead in Km

1 Haladia 368 39 407

Rate for conveyance of materials (Bitumen)


Distance to be
cost per1000 kg Amount
carried
Up to 5 km 161.72 161.72
Every extra km beond
8.23 370.35
5 km and up to 50 km
Every extra km beyond
6.99 2495.43
50 km
Total 3027.50

Das könnte Ihnen auch gefallen