Beruflich Dokumente
Kultur Dokumente
ABSTRACT
Project Director
PIU- Bhubaneswar
National Highways Authority Of India Cost Estimate Page 1 of 10
(b) Drains having cross sectional area more than upto 0.3 Sqm Rm 6000 38 229,672.52
Clearing, longitudinal and transverse covered drains and pipe
drains including manholes, gratings, channels and gullies etc.
1.06 & bringing them to original drainage capacity, including Rm 1600.00 150 240,000.00
disposal of sediments, extraneous debaris & vegetation
growth blocking th
Clearing slab/box type culverts and pipe culverts including
clearing, cleaning and reshaping of upstream and down
1.07 stream faces of these culverts with in right way. The job also
includes disposal of excess material recovered from site
including vegetation
(a) Slab/Box type Culverts No. 46.00 910 41,860.00
(b) Pipe Culverts No. 28.00 644 18,032.00
Carrying out proper cleaning of carriageways, footpaths,
verges, expansion joints (for free movement), drainage Rmtr of
1.08 spouts of bridge including removal and disposal of trash, Bridge 13600.00 173 2,352,800.00
plastic, vegetation etc. from site out side ROW complete as
per direction of Engineer
Loading, unloading, transportation & disposal of surplus
material left over by accidental vehicle or otherwise lying on
1.09 Cum 720.00 88 63,100.42
road (on carriageway) with all lead & lifts complete as
directed by Engineer in Charge.
Carrying out proper cleaning and removing of
dust/silt/thrash/plastic/rubbish/garbage/waste from the
1.10 carriageway, footpaths, verges(excluding the verges of
central median) by mechanical means and from shoulders
upto Toe line of the embackment including si
(a) Urban area (Frequency of cleaning to One time in a month) Per Km 96.00 7346.00 705,216.00
(b) Rural area (Frequency of cleaning will be quarterly). Per Km 274.23 7346.00 2,014,508.27
Removal of rank vegetation/weeds and undesirable
vegetation from shoulders, embankment slopes upto ROW
1.11 (both side) complete in all respect including breaking of
colds, rough dressing disposal of waste material and
vegetation at a place outside ROW as per
National Highways Authority Of India Cost Estimate Page 2 of 10
Item Estimated
Description of Items Unit Rate Amount
No. Quantity
Shoulders including side slopes of embankment up to toe line
on both side of the carriageway. (Frequency of cleaning will
(a) Sqm. 456176.00 5.00 2,280,880.00
be four times in year however limited to only areas prone to
growth of rank/undesirable vegetation and weeds).
Item Estimated
Description of Items Unit Rate Amount
No. Quantity
Reinforced Cement concrete of specified mix as under with
stone aggregates 20 mm nominal size mechanically mixed
1.20 and vibrated in foundation, substructure and superstructure
for thin as well as thick section including shuttering/formwork
conforming to MORTH
(a) M 20 Grade Cum 36.48 5341.00 194,839.68
(b) M 25 Grade Cum 41.00 5708.00 234,028.00
(c) M 30 Grade Cum 26.00 6650.00 172,900.00
Providing and fixing position HYSD reinforcement in
abutment, pier, superstructure, crash barrier and in other
1.21 MT 2.00 72877.00 145,754.00
structure complete as per technical specification Section
1600 and as directed by the Engineer.
Dismantling structure and pavement including disposal of
1.22 resultant materials and salvaging the useful material -
complete in all respect as per direction of the Engineer.
a) Plain concrete Cum 25.00 352.00 8,800.00
RCC including clearing, straightening and cutting of bars and
(b) Cum 20.00 616.00 12,320.00
separating out of RCC
Dismantling of road including wearing courses, base
courses, and sub base courses including stacking of old
1.23
serviceable material complete in all respect as per direction
of Engineer.
Dismantling of bituminous wearing courses, including
(a) disposal of the waste material out side ROW as per direction Cum 96.00 548.00 52,608.00
of Engineer.
Dismantling of base courses, including stacking of useful
(b) material at proper location and disposal of unserviceable Cum 87.00 548.00 47,676.00
material out side ROW as per direction of Engineer.
Item Estimated
Description of Items Unit Rate Amount
No. Quantity
Providing and applying tack coat with bitumen emulsion using
emulsion pressure distributir at the rate of 0.20 Kg per Sqm
1.34 Sqm 199937.50 8.00 1,599,500.00
on the prepared bituminous/granular surface cleaned with
mechnical as per technical specification 503.
(b) Repair ro the all types of damged stone/brick masonry work Cum 132.00 3574.00 471,768.00
Construction of Footpaths/ separators/ traffic Islands by
Providing 150 mm thick compacted GSB as per MORTH
Section 401 & 25 mm thick cement concrete grade M-15
1.41 base over laid with 25 mm thick M-20 precast cement Sqm 1360.00 1046.00 1,422,560.00
concrete chequred titles in cement mortar 1:3 cement sand
mortar. The joint of the tiles to be bonded & finished with neat
cement slurry etc.complite in all respect.
Replacement of damaged cement concrete chequred tiles
with new 25mm thick M-20 precast cement concrete
1.42 chequrred tiles on the already prepared/existing base with Sqm 68.00 301.00 20,468.00
1:3 cement sand mortar. The joint of the tiles to be bonded &
finished with neat cement slurry
Dismantling of existing damaged Expansion joints and
providing and fixing of a new strip seal expansion joint
1.43 catering to maximum horizontal movement up to 70 mm Rmt 55.30 14629.00 808,983.70
complete and to be installed by the
manufacture/supplier/their authorised representative complite
as per engineer in charge.
Sub Total 191,979,872
Item Estimated
Description of Items Unit Rate Amount
No. Quantity
Item Estimated
Description of Items Unit Rate Amount
No. Quantity
Painting with higloss synthetic enamel paint two coats to give
an even and smooth surface for protection of exposed
2.06 concrete/ masonry portion of Bridges/CD works/ parapet,
kerb painting and repairing wherever necessary, complete as
per approval of Enginee
(a) Old existing surface Sqm 124000.00 52 6,448,000.00
New surface after applying priming coat with cement primer
(b) Sqm 0.00 64 -
(two coats) of approved quality.
Painting all types of M.S/GI railing as when required with two
coats of synthetic enamel paint of approved brand after
2.07
cleaning the surface complete in all respect as directed by
the Engineer.
Per rmt
of Full
(a) On existing Railing. 3600.00 45 162,000.00
height of
railing
Per rmt
On new surface after applying two coat of metallic primer of of Full
(b) 3200.00 81 259,200.00
approved quality and make. height of
railing
Paining two coats of ready mixed paint of approved brand as
2.08 steel structure to give an even shade and smooth surface as
per direction of engineer in charge.
(a) On existing surface. Sqm 0.00 45 -
On new surface after applying two coat of metallic primer of
(b) Sqm 0.00 81 -
approved quality and make.
Cleaning, removing, clearing of dust dirt from the existing
2.09 metal crash barrier and pedestrian guard rail by washing with
water & detergent etc. complete as directed by Engineer.
(a) Road sign Boards mounted on single post. No. 52.00 33 1,716.00
(b) Road sign Boards mounted on double post. No. 18.00 50 900.00
(c) Overhead gantry road sign boards. No. 3.00 837 2,511.00
Carrying out of repair signs including strengthing resetting or
otherwise repairing signs made out of Retro Reflective sheet,
2.11 job includes patch repair to aluminum sheet, posts, signs/
script and repainting of posts at damaged location / position
with app
(a) Road sign Boards mounted on single post. No. 62.00 399.00 24,738.00
(b) Road sign Boards mounted on double post. No. 27.00 682.00 18,414.00
Painting two coats on old surface after miner repairs to give
an even and smooth surface and printing letters and figures
2.12 with first quality synthetic enamel paint of approved brand
and manufacture complete in all respect confirming to
respective IRC spec
(a) Hectometer stones No 25.00 19.00 475.00
(b) Kilometer stones No 130.00 43.00 5,590.00
(c) 5th Kilometer stones No 15.00 89.00 1,335.00
(d) Boundary Stones No 82.00 22.00 1,804.00
Providing and fixing reinforced cement concrete M-15 grade
5th kilometer stones, kilometer stones and hectometer
2.13 stones of standard design as per IRC-8-1980 & MORTH
specification clause 804 including two coat painting with
synthetic enamel paint after app
(a) Hectometer stones No 60.00 367.00 22,020.00
(b) Kilometer stones No 54.00 1440.00 77,760.00
(c) 5th Kilometer stones No 6.00 2346.00 14,076.00
Item Estimated
Description of Items Unit Rate Amount
No. Quantity
Post consisting of colled rolled channel 150x75x5 mm having
minimum yield strength of 2400 kg/sqcm.The total lengyh of
(b) post shal be 1900 mm and minimum height of post above M No 3000.00 1944.00 5,832,000.00
20 concrete foundation shall be 800 mm hot dip galvanized
of zinc coating of 55
Space chanels or brackets made out of CRP steel channel
section 150x75x5 mm having an yield strength of
(c) No 3000.00 490.00 1,470,000.00
2400kg/sqcm .The length of spacer channel shall be 330 mm
and hot dip galvanised having zinc coating @550gm/sqm.
Fasteners button head bolts 16x40 mm long with nut and
(d) No 6000.00 17.00 102,000.00
washer hot dipped galvanized.
Replacing damaged / broken railing with new precast / cast
in situ, concrete railing to match with existing design and
2.17 pattern , made out of cement concrete of appropriate grade
and required reinforcement including proper curing, painting
and complete in
(a) New Bridges and old bridges in RCC M 30 Rmt. 8650.00 1591.00 13,762,150.00
Sub Total 60,438,896
National Highways Authority Of India Cost Estimate Page 8 of 10
Item Estimated
Description of Items Unit Rate Amount
No. Quantity
Summary Of Cost Estimate
(a) ii) Facility information Sign 800 x 600 No 65.00 5,683 369,395.00
Item Estimated
Description of Items Unit Rate Amount
No. Quantity
BILL NO-4 (INCIDENT MANAGEMENT)
Item Estimated
Description of Items Unit Rate Amount
No. Quantity
Summa
BILL NO -5 (MISCELLANEOUS)
Project Director
PIU- Bhubaneswar
National Highway Authority Of India Details of Quantities
BILL NO-1 (ROAD MAINTENANCE)
Provisional Qty. for One year B/S Km. 0.000 to Km. 76.558 25.00
Provisional Qty. for One year B/S Km. 0.000 to Km. 76.558 10.00
(b) Drais having depth more than 0.6 meter Rm B/S Km. 0.000 to Km. 76.558 2 1511.16 3022.32
Total Provisional Quantity For One year Rm B/S Km. 0.000 to Km. 76.558 Total Qty 3022.32
Provisional Qty. for One year Rm B/S Km. 0.000 to Km. 76.558 2 800 1,600.00 15% of Urban length considered
Total Qty.For One year Total Qty 1600.00
Clearing slab/box type culverts and pipe culverts including
clearing, cleaning and reshaping of upstream and down
stream faces of these culverts with in right way. The job
1.07
also includes disposal of excess material recovered from
site including vegetation as directed by the engineer.-in-
charge.
(a) Slab/Box type Culverts No. B/S Km. 0.000 to Km. 76.558 1 46 46.00 To be operated once in a Year
(a) Urban area (Frequency of cleaning one time in a month) Per Km B/S
12 8 96.00
(b) Rural area (Frequency of cleaning will be quarterly). Per Km B/S Km. 0.000 to Km. 76.558 4 68.56 274.23
RCC Covered drain RHS Km. 0.000 to Km. 76.558 95 0.32 30.40
Provisional 6.08
Total Qty 36.48
(b) M 25 Grade Cum Km. 0.000 to Km. 76.558
Provisional 41.00
Total Qty 41.00
(c) M 30 Grade Cum B/S Km. 0.000 to Km. 76.558 Provisional Total Qty 26.00
Providing and fixing position HYSD reinforcement in
abutment, pier, superstructure, crash barrier and in other
1.21
structure complete as per technical specification Section
MT B/S Km. 0.000 to Km. 76.558 Provisional Total Qty 2.00
1600 and as directed by the Engineer.
a) Plain concrete Cum B/S Km. 0.000 to Km. 76.558 Provisional 25.00
RCC including clearing, straightening and cutting of bars
(b) Cum B/S Km. 0.000 to Km. 76.558 Provisional 20.00
and separating out of RCC
Dismantling of road including wearing courses, base
courses, and sub base courses including stacking of old Removal of Un authorised
1.23
serviceable material complete in all respect as per approaches
direction of Engineer.
Dismantling of bituminous wearing courses, including
(a) disposal of the waste material out side ROW as per Cum B/S Km. 0.000 to Km. 76.558 Provisional Total Qty 96.00
direction of Engineer.
Removal of Un authorised
(a) All type of soil Cum B/S Km. 0.000 to Km. 76.558 Provisional 67.00
approaches &Road construction
Provisional Qty. forOne year Cum B/S Km. 0.000 to Km. 76.558 Provisional 65.00
Total Qty.For One year Total QTY 65.00
Provisional Qty. for One year B/S Km. 0.000 to Km. 76.558 1 38.279 1.5 0.3 17.23
Provisional Qty. for One year B/S Km. 0.000 to Km. 76.558 1 8970 7.25 0.2 13,006.50 Lump sum length taken
Total Qty.For One year Total QTY 13,006.50
Provisional Qty. for One year B/S Km. 0.000 to Km. 76.558 1 5580 8.75 0.075 3661.875
Total Qty.For One year Total QTY 3,661.88
(a) Using paving bitumen VG-30 Cum All service road 1 3528 5.5 0.05 970.2
Total QTY 970.20
Providing,laying biytuminous primer coat over granular
surface with bituminous emulsion complete as per
1.33 Sqm
Technical specification Clause no 502@7.5 kg/10sqm and
as per direction of Engineer.
Provisional Qty. for One year B/S Km. 0.000 to Km. 76.558 1 5,580 8.75 48,825.00
Total Qty.For One year Total QTY 48,825.00
Providing in full width on Rutted surface. LHS Km. 0.000 to Km. 76.558 1 22850 8.75 0 199937.50
Total Qty.For One year Total QTY 199,937.50
Km 64 1 28.5 28.50
1 26.8 26.80
For Existing work 55.30
For One year Total Qty 55.30
Application of FYM or Sludge @ 1/2 cuft or 10 kg/Plant Km/mo Total Plants=42000 (approx.)
two times a year during February / March and October / nth
median Km. 0.000 to Km. 76.558 12 63.06 756.76
(b) Equivalent Km.=63.06
November plus 20 grams of NPK(12:32:16) or bonemeal
per plants two times a year as detailed above.
(a) White washing two coats on existing surface Sqm B/S Km. 0.000 to Km. 76.558 Provisional 10000.00
Finishing walls with exterior decorative cement
based paint such as snowcern on old work , two
(b) coats to give an even shade after repairing of Sqm
defects so as to achieve smooth and defects free
surface.
B/s Ch.13.230 1 20 5 180.00 Underpass
B/s Ch.21.250 1 20 5 180.00 Underpass
CMEC Consulting Engineers Pvt. Ltd. , Bhubaneswar-751002 B/s Ch.23.400 1 20 5 180.00 Underpass
National Highway Authority Of India Details of Quantities
Item Location Measurements
Description of Items No
No. Unit Side Chainage L B D Qnty Remarks
(a) Old existing surface Sqm B/s Km. 0.000 to Km. 76.558 2 62000 124000.00 2 times in 3 years
Total Qty.For One year Total Qty 124000.00
Painting all types of M.S/GI railing as when required with
two coats of synthetic enamel paint of approved brand
2.07
after cleaning the surface complete in all respect as
directed by the Engineer.
Per rmt of Full On all existing Pedestrian M.S.
(a) On existing Railing.
height of railing
Km. 0.000 to Km. 76.558 3600.00
Guard rail
For Existing work 3600.00
For One year 3600.00
Per rmt
of Full
On new surface after applying two coat of metallic primer On new Pedestrian M.S. Guard
(b)
of approved quality and make.
height B/S Km. 0.000 to Km. 76.558 Total Qty 3200.00
of rail
railing
Cleaning, removing, clearing of dust dirt from the existing
metal crash barrier and pedestrian guard rail by washing
2.09
with water & detergent etc. complete as directed by
Engineer.
(a) MBCB Rm Km. 0.000 to Km. 76.558 1 10000.00 Total Qty 10000.00 2 times in 3 years
Carrying out routine maintenance to all types of road signs
complete as directed by the Engineer and as per
2.10
Additional Maintenance standard clause 5.5.3 the bid
document.
(a) Road sign Boards mounted on single post. No. B/S Km. 0.000 to Km. 76.558 Provisional Total Qty 52
(b) Road sign Boards mounted on double post. No. B/S Km. 0.000 to Km. 76.558 Provisional Total Qty 18
(c) Overhead gantry road sign boards. No. B/S Km. 0.000 to Km. 76.558 Provisional Total Qty 3
Carrying out of repair signs including strengthing resetting
or otherwise repairing signs made out of Retro Reflective
sheet, job includes patch repair to aluminum sheet, posts,
signs/ script and repainting of posts at damaged location /
2.11
position with approved quality of enamel paint complete in
all repect confirming to respectitive IRC/MOST
specification and as per additional maintenance clause
6.12.4.
(a) Road sign Boards mounted on single post. No. B/S Km 0.000-76.588 Provisional Total Qty 62.00
(b) Road sign Boards mounted on double post. No. B/S Km 0.000-76.588 Provisional Total Qty 27.00
Painting two coats on old surface after miner repairs to
give an even and smooth surface and printing letters and
2.12 figures with first quality synthetic enamel paint of
approved brand and manufacture complete in all respect
confirming to respective IRC specification.
(a) Hectometer stones No B/S Km. 0.000 to Km. 76.558 Provisional Total Qty 60.00
(b) Kilometer stones No B/S Km. 0.000 to Km. 76.558 Provisional Total Qty 54.00
(c) 5th Kilometer stones No B/S Km. 0.000 to Km. 76.558 Provisional Total Qty 6.00
Paining two coats with first quality enamel paint of
approved make & quality to give an even shade including
2.14
writing, letter 7 figure etc. Complete in all respect as per
IRC standard.
(a) Printing letters of CD nos No B/S Km. 0.000 to Km. 76.558 1 28 Total Qty 50.00
Net edge and Center line marking for main carrigeway 50548.50
Total Provisional Quantity For One year 51748.50
Provisinal Qty.Replacement of
stolen / missing /Damage by
Provisional Qty. for One year Km. 0.000 to Km. 76.558 6500.00 accidents for Two Years.and newly
closed unauthrised median opening
where required.
For One year Total Qty 6500.00
Construction and laying Cast in situ cement concrete kerb
in M 20 grade and matching with the existing kerb section
complete including dismantling and disposal of existing
3.08 Rmt
damaged broken kerbs as per technical specification
clause 408 for kerbs ( M-20 graade) as per existing
pattern.
(a) length of new MBCB Rmt B/S Km. 0.000 to Km. 76.558 1 5600 5600.00
Each
Provision of Ambulance as per clause 6.4 of scope of
Vehicle Total Provisional Quantity
4.4 work and as per clause 6.8 ‘Performance Standard’ of
per
B/S Km. 0.000 to Km. 76.558 12
For One year
12.00
scope of work.
Month
Removing the dead animals lying on the Highway and
burying them at proper safe locations outside ROW
Per Total Provisional Quantity
4.5 complete in all respect with all lead and lifts as per Clause
Month
B/S Km. 0.000 to Km. 76.558 12
For One year
12.00
6.8 ‘Performance Standard’ of scope of work and as per
direction of the Engineer.
Supply of color photographs in three copies and two CDs Total Provisional Quantity
4.6
complete as per technical specification clause 125 .
Per Set B/S Km. 0.000 to Km. 76.558 12
For One year
12.00
BILL NO -5 (MISCELLANEOUS)
a) Dry stone masonary Cum B/S Km. 0.000 to Km. 76.558 Provisional Total Qty 15.00
CMEC Consulting Engineers Pvt. Ltd. , Bhubaneswar-751002
National Highway Authority Of India Details of Quantities
Item Location Measurements
Description of Items No
No. Unit Side Chainage L B D Qnty Remarks
b) Stone masonary/Brick masonary in mud mortar Cum B/S Km. 0.000 to Km. 76.558 Provisional Total Qty 18.00
c) Rigid pavement Cum B/S Km. 0.000 to Km. 76.558 Provisional Total Qty 5.00
Project Director
PIU- Bhubaneswar
Unit = Sqm
Taking output = 100 Sqm
Assuming average depth of stripping as 75 mm
Quantity of earth cutting involved = 7.5 cum
a) Labour
Mate day 0.1 244.30 24.43 L-10
Mazdoor day 2.5 224.30 560.75 L-01
b) Machinery
Plate compactor@25Sqm per hour hour 4 100.00 400.00 P&M-086
c) Overhead charges @ 8% on (a+b) 78.8144
d) Contractor's profit @ 10% on (a+b+c) 106.40
Rate per Sqm = (a+b+c+d)/100 11.70
say 9
Page1of 23
BILL No 1: Road Maintenance
Ref. to Unit Quantity Rate Cost Remarks/In
MOST
S.No MoRT Description Rs Rs put
Data No
H reference
Cost for 1 cum = a+b+c 0.14
Rate per cum = (a+b+c) 133
a) Labour
Mate day 3.00 244.30 732.90 L-10
Mazdoor day 50.00 224.30 11215.00 L-01
b) Machinery
Tractor Trolly hour 4.00 289.00 1156.00 P&M-053
TOTAL 13103.90
c) overhead charge @ 8% i.e on (a+b) 1048.31
d) Add contractor's profit @ 10% i.e on (a+b+c) 1415.22
Cost for 1000 metres = a+b+c+d 15567.43
Rate per metre = (a+b+c+d)/1000 15.57
11
b) Drains having depth more than 0.6 meter RM
Unit = running metre
consider 1000m
a) Labour
Mate Day 4.00 244.30 977.20 L-10
Mazdoor Day 75.00 224.30 16822.50 L-01
b) Machinery
Tractor Trolly hour 6.00 289.00 1734.00 P&M-053
TOTAL 19533.70
c) overhead charge @ 8% i.e on (a+b) 1562.70
d) Add contractor's profit @ 10% i.e on (a+b+c) 2109.64
Cost for 10 metres = a+b+c+d 23206.04
Rate per metre = (a+b+c+d)/1000 23.21
23
Page2of 23
BILL No 1: Road Maintenance
Ref. to Unit Quantity Rate Cost Remarks/In
MOST
S.No MoRT Description Rs Rs put
Data No
H reference
Total 11648.70
c) overhead charges @ 8% i.e on (a+b) 931.90
d) Add Profit 10% on ( a+b+c) 1258.06
13838.66
Total cost per Rmtr 13.84
14
B Drains having cross sectional area more than 0.3 Sqm RM
Out put per day = 150 Rmt
a) Labour
Mate Nos 0.32 244.30 78.18 L-10
skilled Nos 5.00 264.30 1321.50
unskilled Nos 5.00 224.30 1121.50 L-01
b) Machinery Tractor trolley Hrs 8.00 289.00 2312.00 P&M-053
4833.18
c) Add OH 8% on (a+b) 386.65
d) Add Profit 10% on ( a+b+c) 521.98
For 150 Rmt 5741.81
for Rmt 38
a) Labour
Mate Day 0.50 244.30 122.15 L-10
Mazdoor Day 5.00 224.30 1121.50 L-01
b) Machinery
Tractor Hour 1.00 289.00 289.00 P&M-053
Total 1532.65
c) Add OH 8% on (a+b) 122.61
d) Add Profit 10% on ( a+b+c) 165.53
1820.8
Total cost per No / Time 910.39
Say 910
B) Pipe Culverts
Cleaning up Stream & D/stream
Down stream for 100m each side
consider 2 no per/ time
a) Labour
Mate Day 0.50 244.30 122.15 L-10
Mazdoor Day 3.00 224.30 672.90 L-01
Page3of 23
BILL No 1: Road Maintenance
Ref. to Unit Quantity Rate Cost Remarks/In
MOST
S.No MoRT Description Rs Rs put
Data No
H reference
b) Machinery
Tractor Hour 1.00 289.00 289.00 P&M-053
Total (a+b) 1084.05
C) Overhead charges @ 8% i.e on (a+b) 86.72
d) Add Profit 10% on ( a+b+c) 117.08
Total( a+b+c+d) 1287.85
Total cost per No / Time 643.93
Say 644
Page4of 23
BILL No 1: Road Maintenance
Ref. to Unit Quantity Rate Cost Remarks/In
MOST
S.No MoRT Description Rs Rs put
Data No
H reference
Mazdoor Day 2.50 224.30 560.75 L-01
b) Machinery
Machanical broom @ 1250sqm per hour Hour 4.00 230.00 920.00 P & M-031
Tractor Trolly Hour 1.00 289.00 289.00 P&M-053
Total (a+b) 1818.61
c) Overhead charges @ 8% i.e on (a+b) 145.49
d) Add contractor's profit @ 10% i.e on (a+b+c) 196.41
Total (a+b+c+d) 2160.51
For 1 Sqm = Total(a+b+c+d)/5000 0.43
cost per km (B/S) = 2*1000*8.5*0.38 7345.73
Say 7346.00
B) Rural Area ( Frequency of cleaning will be quaterly
Unit = Per km Km.
Taking Output = 5000sqm
a) Labour
Mate Day 0.20 244.30 48.86 L-10
Mazdoor Day 2.50 224.30 560.75 L-01
b) Machinery
Machanical broom @ 1250sqm per hour Hour 4.00 230.00 920.00 P & M-031
Tractor Trolly Hour 1.00 289.00 289.00 P&M-053
Total (a+b) 1818.61
c) Overhead charges @ 8% i.e on (a+b) 145.49
d) Add contractor's profit @ 10% i.e on (a+b+c) 196.41
Total (a+b+c+d) 2160.51
For 1 Sqm = Total(a+b+c+d)/5000 0.43
cost per km (B/S) = 2*1000*8.5*0.38 7345.73
Say 7346.00
Page5of 23
BILL No 1: Road Maintenance
Ref. to Unit Quantity Rate Cost Remarks/In
MOST
S.No MoRT Description Rs Rs put
Data No
H reference
D) Add contractor's profit @ 10% i.e on (a+b+c) 3823.18
42054.96
Rate per sqm 5.26
Say 5.00
Page6of 23
BILL No 1: Road Maintenance
Ref. to Unit Quantity Rate Cost Remarks/In
MOST
S.No MoRT Description Rs Rs put
Data No
H reference
Providing sealing cracks wider than 3mm using slow curing Rmt
bitumen emulsen @ 0.66 kg per 10 mtrs of the cracks and
1.16
stone crusher screening @ 0.0004 cum/10 mtrs complete as
per direction of the engineer incharge.
Unit = Rmt
Page7of 23
BILL No 1: Road Maintenance
Ref. to Unit Quantity Rate Cost Remarks/In
MOST
S.No MoRT Description Rs Rs put
Data No
H reference
Taking output = 500m
a) Labour
Mate Day 0.04 244.30 9.77 L-10
Mazdoor Day 1.00 224.30 224.30 L-01
b) Material
Slow curing bitumen emulsion kg 33.00 29.86 985.40 M-073
Stone Crusher dust cum 0.02 776.02 15.52 M-021
Total (a+b) 1235.00
c) Over head charges @ 8% i.e on (a+b) 98.80
d) Add contractor's profit @ 10% i.e on (a+b+c) 133.38
Total (a+b+c+d) 1467.17
2.93
say 3.00
Page8of 23
BILL No 1: Road Maintenance
Ref. to Unit Quantity Rate Cost Remarks/In
MOST
S.No MoRT Description Rs Rs put
Data No
H reference
say 154.00
Page9of 23
BILL No 1: Road Maintenance
Ref. to Unit Quantity Rate Cost Remarks/In
MOST
S.No MoRT Description Rs Rs put
Data No
H reference
Cost for 4800cum= a+b+c+d+e 3915062.05
rate per sqm= (a+b+c+d+e)/4800 815.64
say 816.00
b) PCC M20
Unit : cum
Taking output = 15 cum
a)Material
Cement tonne 5.21 5500.00 28655.00 M-081
Coarse sand cum 6.75 638.04 4306.77 M-005
20 mm Aggregate cum 8.10 1790.07 14499.57 M-045
10 mm Aggregate cum 5.40 1838.64 9928.66 M-044
b) Labour
Mate day 0.86 244.30 210.10 L-10
Mason day 1.50 264.30 396.45 L-25
Mazdoor day 20.00 224.30 4486.00 L-01
c)Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 153.91 923.46 P&M-009
Generator 33 KVA hour 6.00 240.00 1440.00 P&M-079
Per Cum Basic Cost of Labour, Material & Machinery 64846.00
(a+b+c)
d)Formwork @ 4 per cent on cost of concrete i.e. cost 2593.84
of material, labour and machinery
67439.84
e) Overhead charges @ 8% on (a+b+c+d) 5395.19
f)Contractor's profit @ 10% on (a+b+c+d+e) 7283.50
Cost for 15 cum = a+b+c+d+e+f 80118.53
Rate per cum = (a+b+c+d+e+f)/15 5341.24
say 5341.00
a) RCC M20
Page10of 23
BILL No 1: Road Maintenance
Ref. to Unit Quantity Rate Cost Remarks/In
MOST
S.No MoRT Description Rs Rs put
Data No
H reference
Unit : cum
Taking output = 15 cum
a)Material
Cement tonne 5.21 5500.00 28655.00 M-081
Coarse sand cum 6.75 638.04 4306.77 M-005
20 mm Aggregate cum 8.10 1790.07 14499.57 M-045
10 mm Aggregate cum 5.40 1838.64 9928.66 M-044
b) Labour
Mate day 0.86 244.30 210.10 L-10
Mason day 1.50 264.30 396.45 L-25
Mazdoor day 20.00 224.30 4486.00 L-01
c)Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 153.91 923.46 P&M-009
Generator 33 KVA hour 6.00 240.00 1440.00 P&M-079
Per Cum Basic Cost of Labour, Material & Machinery 64846.00
(a+b+c)
d)Formwork @ 4 per cent on cost of concrete i.e. cost 2593.84
of material, labour and machinery
67439.84
e) Overhead charges @ 8% on (a+b+c+d) 5395.19
f)Contractor's profit @ 10% on (a+b+c+d+e) 7283.50
Cost for 15 cum = a+b+c+d+e+f 80118.53
RCC M 30 Grade
c) Unit : cum
Taking output = 15 cum
Material
Cement tonne 6.10 5500.00 33550.00 M-081
Coarse sand cum 6.75 638.04 4306.77 M-005
20 mm Aggregate cum 8.10 1790.07 14499.57 M-045
10 mm Aggregate cum 5.40 1838.64 9928.66 M-044
Labour
Mate day 0.90 244.30 219.87 L-10
Mason day 1.50 264.30 396.45 L-25
Mazdoor day 21.00 224.30 4710.30 L-01
Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 153.91 923.46 P&M-009
Generator 33 KVA hour 6.00 240.00 1440.00 P&M-079
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) 69975.07
Formwork @ 20 per cent on cost of concrete i.e. cost of material, labour and machinery 13995.01
83970.09
Overhead charges @ 8% on (a+b+c+d) 6717.61
Page11of 23
BILL No 1: Road Maintenance
Ref. to Unit Quantity Rate Cost Remarks/In
MOST
S.No MoRT Description Rs Rs put
Data No
H reference
Contractor's profit @ 10% on (a+b+c+d+e) 9068.77
Cost for 15 cum = a+b+c+d+e+f 99756.46
Rate per cum = (a+b+c+d+e+f)/15 6650.43
say 6650.00
a) Labour
Mate Day 0.05 244.30 12.22 L-10
Mazdoor for dismantling,loading and unloading Day 1.25 224.30 280.38 L-01
b) Machinery
Tractor - Trolly Hrs 0.27 289.00 78.03 P&M-053
Total 370.62
c) Overhead Charges @8% on (a+b) 29.65
d) Contractor'sprofit @ 10% on (a+b+c) 40.03
440.30
352.24
say 352.00
RCC including clearing, straightening and cutting of bars
b)
and separating out of Rcc
Unit = Cum
Taking Output = 1.25 cum
Dismantling Work
a) Labour
Mate Day 0.05 244.30 12.22 L-10
Mazdoor for dismantling,loading and unloading Day 0.25 224.30 56.08 L-01
Blacksmith Day 0.66 264.30 174.44 L-26
Mazdoor with pnematic breaker Day 0.66 224.30 148.04 L-01
b) Machinery
Air compressor 250cfm Hrs 1.00 179.13 179.13 P&M-001
Tractor - Trolly Hrs 0.27 289.00 78.03 P&M-053
Total 647.93
c) Overhead Charges @8% on (a+b) 51.83
d) Contractor'sprofit @ 10% on (a+b+c) 69.98
769.74
615.79
say 616.00
Page12of 23
BILL No 1: Road Maintenance
Ref. to Unit Quantity Rate Cost Remarks/In
MOST
S.No MoRT Description Rs Rs put
Data No
H reference
Dismantling of bitumenous wearing courses includiing
a disposal of the waste material outside ROW as per direction of
Engineer
Unit = Cum
Taking Output = 1 Cum
Bituminous courses
a) Labour
Mate Day 0.06 244.30 14.66 L-10
Mazdoor for dismantling,loading and unloading Day 1.50 224.30 336.45 L-01
b) Machinery
Tractor - Trolly hour 0.38 289.00 109.82 P&M-053
460.93
c) Overhead Charges @8% on (a+b) 36.87
d) Contractor'sprofit @ 10% on (a+b+c) 49.78
547.58
say 548.00
Dismantling of base courses, including stacking of useful
b material at proer location and disposal of unserviceable
material outside ROW as per direction of engineer
Unit = Cum
Taking Output = 1 Cum
Bituminous courses
a) Labour
Mate Day 0.06 244.30 14.66 L-10
Mazdoor for dismantling,loading and unloading Day 1.50 224.30 336.45 L-01
b) Machinery
Tractor - Trolly hour 0.38 289.00 109.82 P&M-053
460.93
c) Overhead Charges @8% on (a+b) 36.87
d) Contractor'sprofit @ 10% on (a+b+c) 49.78
547.58
say 548.00
Dismantling of subbase courses, including stacking of useful
c material at proper location and disposal of unserviceable
material outside ROW as per direction of Engineer
Unit = Cum
Taking Output = 1 Cum
Bituminous courses
a) Labour
Mate Day 0.04 244.30 9.77 L-10
Mazdoor for dismantling,loading and unloading Day 1.00 224.30 224.30 L-01
b) Machinery
Tractor - Trolly hour 0.33 289.00 95.37 P&M-053
329.44
c) Overhead Charges @8% on (a+b) 26.36
d) Contractor'sprofit @ 10% on (a+b+c) 35.58
391.38
say 391.00
Page13of 23
BILL No 1: Road Maintenance
Ref. to Unit Quantity Rate Cost Remarks/In
MOST
S.No MoRT Description Rs Rs put
Data No
H reference
Construction of embankment with approved material obtained
from borrow pits with all lifts and leads, transporting to site,
1.25
spreading, grading to required slope and compacting to meet
requirement of table 300-2.
Unit = cum
Taking output = 100 cum
a) Labour
Mate day 0.04 244.30 9.77 L-10
Mazdoor day 1.00 224.30 224.30 L-01
b) Machinery
Hydraulic Excavator1 cum bucket capacity @ 60 cum per hour 1.67 730.43 1219.82 P&M-026
Tipper 10 tonne capacity tonne.km 160 x L 2.17 5200.00 Lead =13 km
& P&M-058
Add 10 per cent of cost of carriage to cover cost of loading 520.00
Dozer 80 HP for spreading @ 200 cum per hour hour 0.50 1592.17 796.09 P&M-015
Motor grader for grading @ 100 cum per hour hour 1.00 1343.48 1343.48 P&M-032
Water tanker6 KL capacity hour 4.00 690.00 2760.00 P&M-060
Vibratory roller 8 -10 tonnes @ 100 cum per hour hour 1.00 864.50 864.50 P&M-059
c) Material
Cost of water KL 24 125.00 3000 M-189
Compensation for earth taken from private land cum 100 80.00 8000 M-092
Add for seinarage charges cum 100 10 1000
d) Overhead charges @ 8% on (a+b+c) 1995.04
e) Contractor's profit @ 10% on (a+b+c+d) 2693.30
Cost for 100 cum = a+b+c+d+e 29626.29
Rate per cum = (a+b+c+d+e)/100 296.26
say 296.00
Page14of 23
BILL No 1: Road Maintenance
Ref. to Unit Quantity Rate Cost Remarks/In
MOST
S.No MoRT Description Rs Rs put
Data No
H reference
say 3.00
1939.41
Page15of 23
BILL No 1: Road Maintenance
Ref. to Unit Quantity Rate Cost Remarks/In
MOST
S.No MoRT Description Rs Rs put
Data No
H reference
say 1939.00
Page16of 23
BILL No 1: Road Maintenance
Ref. to Unit Quantity Rate Cost Remarks/In
MOST
S.No MoRT Description Rs Rs put
Data No
H reference
10 - 5 mm 28 per cent cum 80.430 1437.69 115633.41 M-040
5 mm and below 40 per cent cum 114.900 1506.26 173069.27 M-030
Filler @ 2 per cent of weight of aggregates. tonne 8.620 5500.00 47410.00 M-188
1393375.17
d) Overhead charges @ 8% on (a+b+c) 111470.01
e) Contractor's profit @ 10% on (a+b+c+d) 150484.52
Cost for 205 cum = a+b+c+d+e 1655329.70
Rate per cum = (a+b+c+d+e)/195 (For Grading-II) 8488.87
say 8489.00
Page17of 23
BILL No 1: Road Maintenance
Ref. to Unit Quantity Rate Cost Remarks/In
MOST
S.No MoRT Description Rs Rs put
Data No
H reference
13.2 - 10 mm20 per cent cum 57.300 1838.64 105354.07 M-044
10 - 5 mm 38 per cent cum 108.870 1437.69 156521.31 M-040
5 mm and below 40 per cent cum 114.600 1506.26 172617.40 M-030
Filler @ 2 per cent of weight of aggregates. tonne 8.620 5500.00 47410.00 M-188
d) Overhead charges @ 8% on (a+b+c) 114130.15
e) Contractor's profit @ 10% on (a+b+c+d) 154075.70
Cost for 205 cum = a+b+c+d+e 1694832.68
Rate per cum = (a+b+c+d+e)/195 (For Grading I) 8691.45
say 8691.00
Providing and laying bituminous primer coat over granular
surface with bituminous emulsion complete as per technical
1.33
specification clause no.502 @ 7.5 kg/10 sqm as per the
direction of Engineer
Unit = Sqm.
Taking Output = 3500 Sqm.
Labour
Mate day 0.08 244.30 19.54 L-10
Mazdoor day 2.00 224.30 448.60 L-01
Machinery
Mechanical broom @ 1250 sqm per hour hour 2.80 230.00 644.00 P&M-031
Air compressor 250 cfm hour 2.80 179.13 501.56 P&M-001
Bitumen pressure distributor @ 1750 sqm per hour hour 2.00 601.74 1203.48 P&M-004
Water tanker 6 KL capacity @ 1 trip per hour hour 1.00 690.00 690.00 P&M-060
Material
Bitumen emulsion SS grade @ 0.6 kg per sqm tonne 2.10 29860.70 62707.47 M-077
Cost of water KL 6.00 125.00 750.00 M-189
66964.66
Overhead charges @ 8% on (a+b+c) 5357.17
Contractor's profit @ 10% on (a+b+c+d) 7232.18
Cost for 3500 sqm = (a+b+c+d+e) 79554.01
Rate per Sqm = (a+b+c+d+e)/3500 22.73
say 23.00
Page18of 23
BILL No 1: Road Maintenance
Ref. to Unit Quantity Rate Cost Remarks/In
MOST
S.No MoRT Description Rs Rs put
Data No
H reference
Accelerator compound for guniting @4% weight of cement kg 1.03 142.00 146.26 Market Rate
Add @ 2% cost of material 42.75
b)Labour
Mate Day 0.02 244.30 4.89 L-10
Mason Day 0.06 264.30 15.86 L-25
Mazdor Day 0.22 224.30 49.35 L-01
c)Machinery
Compressor with guniting equipment along with accessories Hrs 0.16 285.00 45.60 P&M-063
Total 2295.88
d) Overheads @ 8% (a+b+c) 183.67
e) contractor's Profit @10% on (a+b+c+d) 247.96
2727.51
say 2728.00
Page19of 23
BILL No 1: Road Maintenance
Ref. to Unit Quantity Rate Cost Remarks/In
MOST
S.No MoRT Description Rs Rs put
Data No
H reference
454.90
Rate per Sqm 45.49
say 45.00
Page20of 23
BILL No 1: Road Maintenance
Ref. to Unit Quantity Rate Cost Remarks/In
MOST
S.No MoRT Description Rs Rs put
Data No
H reference
301.26
241.01
say 241.00
II)Repair ro the all types of damged stone/brick masonry
work
Unit= Cum
Taking output = 1 Cum
a) Material
Brick First Class Each 500.00 3.15 1575.00
Cement Morter 1:3 Cum 0.24 3687.00 884.88 1.37
b) Labour
Mate Day 0.06 244.30 14.66 L-10
Masson Day 0.80 264.30 211.44 L-25
Mazdoor Day 0.80 224.30 179.44 L-01
Total (a+b) 2865.42
Add for scafolding @ 5% of cost of material and labour 143.27
3008.69
c) Overhead charges @ 8% i.e on (a+b) 240.70
d) Add contractor's profit @ 10% i.e on (a+b+c) 324.94
Total (a+b+c+d) 3574.32
say 3574.00
III) Stone Masonary work in cement morter 1:3 for
substructure
Ashlar masory (First Sort)
Plain ashlar
Unit = Cum
Taking output = 1 Cum
a) material
Stone Cum 1.11 933.88 1036.61 M-002
Through and bond stone each 7.00 40.00 280.00 M-182
Cement morter 1:3 Cum 0.33 3687.00 1216.71 1.37
b) Labour for masonry work
Mate Day 0.20 244.30 48.86 L-10
Masson Day 2.50 264.30 660.75 L-25
mazdoor Day 2.50 224.30 560.75 L-01
Total (a+b) 3803.68
Add for scafolding @ 5 % of cost of (a+b) 190.18
3993.86
c) Overhead charges @ 8% i.e on (a+b) 319.51
d) Add contractor's profit @ 10% i.e on (a+b+c) 431.34
say 431.00
Say 2243.50
Rate for Repair and dismantling = (II + III)/2 + I say 2244.00
Page21of 23
BILL No 1: Road Maintenance
Ref. to Unit Quantity Rate Cost Remarks/In
MOST
S.No MoRT Description Rs Rs put
Data No
H reference
iii) For Cement Plaster 1:3
Sand Cum 3.84 638.04 2450.07 M-005
Cement Tonne 1.83 5500.00 10065.00 M-081
iv) Pre-cast cement concrete tiles
Tiles size 300 x 300 mm and 25 mm thick Sqm 315.00 355.00 111825.00
V) RCC Pipes
Pipes 200 mm dia 2.5m long for drainage Mtr 22.50 200.00 4500.00
vi) Cost of water KL 12.00 125.00 1500.00
c) Overhead charges @ 8% i.e on (a+b+c) 21136.61
d) Add contractor's profit @ 10% i.e on (a+b+c+d) 28534.42
Cost for 300 sqm = a+b+c+d+e 313878.62
Rate per sqm = (a+b+c+d+e)/300 1046.26
say 1046.00
Page22of 23
BILL No 1: Road Maintenance
Ref. to Unit Quantity Rate Cost Remarks/In
MOST
S.No MoRT Description Rs Rs put
Data No
H reference
Removal of old expansion joint including breaking of
concrete,cutting of lugs and shifting of broken materials etc
Mate Day 0.26 244.30 63.52 L-10
Mazdoor Day 6 224.30 1345.80 L-01
Mazdoor (skilled) Day 0.5 264.30 132.15 L-25
40361.47
c) Over head charges @ 8% i.e. on (a+b) 3228.92
d) Contractor profits @ 10% on (a+b+c) 4359.04
Total 47949.42
Per Rmt 3995.79
Strip seal Expansion joint
unit = Rmt
Taking out put = 12 m
a) Labour
Mate day 0.05 244.30 12.22 L-10
Mazdoor Day 1 224.30 224.30 L-01
Mazdoor (skilled) Day 0.25 264.30 66.08 L-25
b) Material
Supply of complete assembly of strip seal expansion joint
comprising of edge beams,anchorage,strip seal elements and
RM 12 8500.00 102000.00
complete accessories as per approved specification and
drawings. M-178
Add 5% of cost of material for anchorage 5100.00
reinforcement,welding and other incedents
107402.59
c) Over head charges @ 8% i.e. on (a+b) 8592.21
d) Contractor profits @ 10% on (a+b+c) 11599.48
Total 127594.28
Per Rmt 10632.86
Total cost of Replacement=(dismantaling+Fixing) 14628.64
say 14629.00
Page23of 23
NATIONAL HIGHWAYS AUTHORITY OF INDIA RATE ANALYSIS
BILL NO - 2
ROAD PROPERTY MANAGEMANT AND OTHER MAINTENANCE
Sr No Ref. to Description Unit Quantity Rate Cost Remarks/ Input
MoRTH Rs Rs ref.
Spec.
2.01 124 Providing planting healthy well developed saplings of ornaments
flowering shurbs of specified species and varities 1-2 years of
No
age in 25 c m- 30 cm poly bags or pots,height and spread 0.60
mt-0.90 mt above ground,with 3-4 branches,in well prepared pit
Unit = Each
Taking output =666Nos
a) Labour
Mate day 1.20 244.30 293.16 L-10
Mazdoor day 12.00 224.30 2691.60 L-01
b) Machinery
Water Tanker 6Kl Capacity Hour 6.00 690.00 4140.00 P&M-060
C) Material
Plant Each 666.00 25.00 16650.00 M-100
Manure Sludge / Farm yard manure cum 63.64 100.00 6364.00
Pesticide Kg 0.50 136.00 68.00 M-136
Cost of Water KL 36.00 125.00 4500.00 M-189
Total (a+b+c) 34706.76
d) Overhead charges @ 8% i.e. on (a+b+c) 2776.54
e) Add contractor's profit @10% i.e on (a+b+c+d) 3748.33
41231.63
61.91
Say 62.00
Bill No.A2
1
NATIONAL HIGHWAYS AUTHORITY OF INDIA RATE ANALYSIS
2.04 Supplying and turfing with live ande perinnal turforming grass on
embankment slopes, verges medians and other locations
conforming to Technical Specification clause 307 including
watering and maintaining for entire contract period with periodical
mowing c
A) Maintenance of Truffing of slopes
Bill No.A2
2
NATIONAL HIGHWAYS AUTHORITY OF INDIA RATE ANALYSIS
b) Machinery
Water tanker 6 KL capacity hour 2.00 690.00 1380.00 P&M-060
c) Material
Cost of water KL 12.00 125.00 1500.00 M-189
2911.72
d) Overhead charges @ 8% i.e. on (a+b+c) 232.94
e) Add contractors profit @ 10% i.e. on (a+b+c+d) 291.17
3435.82
Rate per Sqm 34.36
Say 34.00
2.05 a White wash/ cement paint/ snowcem in two or more coats to give
an even shade and smooth surface for protection of exposed
concrete/masonary portion of Bridges/CD works, kerb and wheel
guard including scraping of damage paint from old surface and
repairin
White washing two coats on existing surface
Unit = Sqm
Taking output = 93 Sqm
a) Material
Shell lime unsoaked Kg 23.32 14.00 326.48
b) Labour
Painter(Semi Skilled) Day 1.50 0.00 0.00 L-11
Man mulia Day 1.00 224.30 224.30 L-01
550.78
Add 10% of cost of material and labour 55.08
605.86
c) Overhead charges @ 8% on (a+b) 48.47
d) contractors profit @ 10 % on (a+b+c) 65.43
Total (a+b+c+d) 719.76
7.74
Rate per Sqm Say 8.00
b Finishing walls with exterior decorative cement based paint such
as snowcern on old work, two coats to give an even shade after
Sqm
repairing of defects so as to achieve smooth and defects free
surface.
Water proofing cement paint of approved brand and
manufacture
Out put 10 sqm,unit 1 sqm
a) Material
Water proofing Paint lit 2.00 47.50 95.00
b) Labour
Mate No 0.03 244.30 7.33 L-10
Painter No 0.50 264.30 132.15 L-29
unskilled No 0.25 224.30 56.08 L-01
290.55
c ) Add OH 8% on (a+b) 23.24
d ) Add Profit 10% on ( a+b+c) 31.38
Total for 10 sqm 345.18
For 1 sqm 34.52
Say 35.00
Bill No.A2
3
NATIONAL HIGHWAYS AUTHORITY OF INDIA RATE ANALYSIS
Say 64.00
2.07 Painting all types of M.S/G.I railling as when required with two
coats of synthetic enamel paint of approved brand after cleaning
the surface complete in all respect as directed by the Engineer
On Existing Railling
painting on steel surface
Providing and applying two coats of ready mix paint of approved
brand on steel surface after through cleaning of surface to give
and even shade
Unit = Sqm
Taking output = 10 Sqm
a) Labour
Bill No.A2
4
NATIONAL HIGHWAYS AUTHORITY OF INDIA RATE ANALYSIS
2.08 Painting two coats on steel structure to give and even shade and
smooth surface as per direction of Engineer-In-Charge
a) Old Existing Surface
Painting on steel surface
Providing and applying two coats of ready mix paint of approved
brand on steel surface after through cleaning of surface to give
and even shade
Unit = Sqm
Taking output = 10 Sqm
Bill No.A2
5
NATIONAL HIGHWAYS AUTHORITY OF INDIA RATE ANALYSIS
2.09 Cleaning, removing, clearing of dust and dirt from the existing
metal crash barrier and pedestrian guard rail by washing with
water & detergent etc. complete as directed by Engineer.
Bill No.A2
6
NATIONAL HIGHWAYS AUTHORITY OF INDIA RATE ANALYSIS
B) Material
Chemical cleaner for Removal of posters L.S 400.00
C) Machinery
i) Water Tanker Hrs 3.00 690.00 2070.00 P&M-060
Total of (A + B + C) 3977.95
Add overhead 8% on Total of ( a + b + c) 318.24
Contractor profit 10% on Total of ( a to d ) 429.62
4725.80
4.73
Rate per Metre Say 5.00
Bill No.A2
7
NATIONAL HIGHWAYS AUTHORITY OF INDIA RATE ANALYSIS
2.12 Painting two coats on old surface after minor repairs to give an
even and smooth surface and printing letters and figures with 1st
quality synthetic enamel paint of approved brand and
manufacture complete in all respect conforming to respective
IRC specif
A) Hectometer Stones
unit = Sqm
Taking output = 40sqm
a) Labour
Mate Day 0.12 244.30 29.32 L-10
Painter Day 2.00 264.30 528.60 L-29
Mazdoor Day 1.00 224.30 224.30 L-01
b)Material
Paint conforming to requirement of clause 803.3 Litre 6.00 145.00 870.00 M131
Add for scafolding @ 20% cost of albour where required and for 156.44
letter writing
Total 1808.66
c) Overhead Charge @ 8% on (a+b) 144.69
d) Contractor's Profit @ 10% on ( a+b+c) 195.34
2148.69
53.72
say 54.00
Hectometer Stones area of 0.35sqm 18.90
say 19.00
B) Kilometer Stones
Kilometer stones area of 0.8 sqm sqm 0.80 54.00 43.20
say 43.00
C)5th Kilometer stones
5th kilometer stones area of 1.65 sqm sqm 1.65 54.00 89.10
Bill No.A2
8
NATIONAL HIGHWAYS AUTHORITY OF INDIA RATE ANALYSIS
2.13 Providing and fixing reinforced cement concrete M-15 grade and
5th kilometer stones and hectometer stones of standard desing
as per IRC -8-1980 & MORTH specification clause 804 including
two coat painting with synthetic enamel paint after applying
approve
a) Hectometre Stones
Unit = Nos
Taking Output = 33 Nos
a) M 15 Grade of concrete Cum 1.58 4852.00 7666.16 1.19(a)
b) Steel reinforcement @ 5 Kg per Sqn(basic rate of 2.08) Kg 66.00 55.98 3694.88
c) Excavation in soil for foundation Cum 1.39 152.00 211.28 1.24
d) Painting two coats on concrete surface Sqm 6.27 81.00 507.87 Item-2.08(b)
Per
e) Lettering on Km Post(average 1 letter of 10 cm height 330.00 0.47 155.10
Cm/letter
Transportation and fixing
f) Labour
mate Day 0.34 244.30 83.06 L-10
Mason Day 1.50 264.30 396.45 L-25
Mazdoor Day 7.00 224.30 1570.10 L-01
g) Machinery
Tractor- Trolly Hour 6.00 200.87 1205.22 P&M-053
Bill No.A2
9
NATIONAL HIGHWAYS AUTHORITY OF INDIA RATE ANALYSIS
2.14 Painting two coats with first quality enamel paint of approved
make & quality to give an even shade including writing , letter &
figure etc.complete in all respect as per IRC standard.
A printing letters of CD nos. No
I) Hindi
Details for 100 letters of 16 cm height i.e 1600 cm
unit = per cm height per letter
a) Labour
Mate Day 0.12 244.30 29.32 L-10
Painter Day 2.00 264.30 528.60 L-29
Mazdoor Day 1.00 224.30 224.30 L-01
b)Material
Paint Litre 0.70 145.00 101.50 M131
Total (a+b) 883.72
c) Overhead Charge @ 8% on (a+b) 70.70
d) Contractor's Profit @ 10% on ( a+b+c) 95.44
1933.57
Per cm height per letter 1.21
II) engilish and Roman
Bill No.A2
10
NATIONAL HIGHWAYS AUTHORITY OF INDIA RATE ANALYSIS
2.15
Strengthening and repairing of partially damaged M.S pedestrian
Railling / pipe railing complete including welding , repairing /
Rmt
replacement of damaged parts / portions (salvage material will be
controctors property) as per existing pattern complete in al
Unit = Rmt
Taking output = 1.95rmt
a) Labour
Mate Day 0.48 244.30 117.26 L-10
Mazdoor Day 6.00 224.30 1345.80 L-01
Blacksmith Day 2.00 264.30 528.60 L-26
b) Material
M.S.Pipe / angle/ Squarbar(l/s) Kg 44.16 51.54 2276.09 M-126
C) Machinery
Tractor -Trolly hour 1.50 289.00 433.50 P&M-053
Welding Transformer hour 2.00 112.00 224.00 Market Rate
Total (a+b+c) 4925.26
d) Over head charge @ 8% on (a+b+c) 394.02
e)contractor's profit @ 10% on (a+b+c+d) 531.93
5851.21
3000.62
2780.6
assume 25% scrap material after accident 11Kg X Rs20 = 220 say
2186.0
2.16 Replacement of damaged single faced W- Beam metal crash
barrier made out of the following members. Job includes taking
out old damged member and neatly refixing the new member
(with cement concrete foundation in M-20 for post complete in all
respects as p
(A)Beam made out of cold rolled steel strip W profile of 3 mm
thick having a minimum yield strength of 2400 kg/sqcm having
width of 313 mm and depth of corrugation as 83 mm hot dip
galvanized of zinc coating @ 550 gm/sqm.
Unit = Rmt
Taking output = 4.5m
a) Labour
Mate day 0.06 244.30 14.66 L-10
Blacksmith day 0.50 264.30 132.15 L-01
Mazdoor day 1.00 224.30 224.30 L-26
b) Machinery
Tractor - trolly hrs 0.10 289.00 28.90 P&M-053
Bill No.A2
11
NATIONAL HIGHWAYS AUTHORITY OF INDIA RATE ANALYSIS
Bill No.A2
12
NATIONAL HIGHWAYS AUTHORITY OF INDIA RATE ANALYSIS
Bill No.A2
13
NATIONAL HIGHWAYS AUTHORITY OF INDIA RATE ANALYSIS
Bill No.A2
14
BILL No 3: Engineering Improvements
Ref. to Unit Quantity Rate Cost Remarks/I
MOST
S.No MoRTH Description Rs Rs nput
Data No
Spec. reference
BILL No 3: Engineering Improvements
Replacement of stolen/missing retro-reflectorised traffic
sign boards by providing and fixing new retro-
3.01 reflectorised cautionary, mandatory and informatory sign
as per ASTM D 4956-04 made of High intensity grade
Microprismatic sheeting Type-IV, fixed over
(A) 8.4 801 Informatory sign
i) Advance direction, Destination , Reassurance and
place identification sign (size 2100mm x 1700mm) as
per deawing with two vertical posts embeded in M15
Cement concrete details as per description given above
and as per drawing.
Unit= Nos
Taking output=one traffic sign
i)Excavation for foundation cum 0.43 152.23 65.46 A1
ii)Cement Concrete M15 grade cum 0.24 4851.97 1164.47 A2
iii)Painting angle iron post two coats sqm 0.86 49.07 42.20
. 1272.13
a)Labour( For fixing at site)
Mate day 0.01 244.30 2.44 L-10
Mazdoor day 0.30 224.30 67.29 L-01
69.73
b)Machinery
Tractor-trolley hour 0.02 289.00 5.78 P&M-053
c)Material
b) Material
Mild Steel angle iron 75 X75 X 6mm Kg 23.8 51.54 1226.70
Add 2% of cost of angle iron towards cost of drilling holes ,
nuts bolts etc. 24.53
Aluminum sheeting fixed with encapsulated lens type
reflective sheeting of size including lettering and signs as As aproved
apllicable Sqm 0.67 5505.00 3688.35 By NHAI
4939.58
Total of a+b+c = 4939.58
d)Overheads @ 8% on (a+b+c) 395.17
e)Contractor's Profit @ 10% on (a+b+c+d) 533.48
Cost for one board= i+ii+iii+a+b+c+d+e 5868.23
Say 5,868
ii) 600mm dia circular sign
unit = each
Taking Output = one traffic sign
i) Excavation for foundation cum 0.22 152.23 32.88 A1
ii) cement concrete M15 grade cum 0.12 4851.97 582.24 A2
iii) Painting angle iron post two coats Sqm 0.43 49.07 21.10
. 636.22
a)Labour (for fixing at site)
Mate Day 0.01 244.30 2.44 L-10
Mazdoor Day 0.25 224.30 56.08 L-01
58.52
c) Machinery
Tractor- trolly Hour 0.01 289.00 2.89 P&M-053
b) Material
Mild Steelangle iron 75 X75 X 6mm Kg 23.80 51.54 1226.70
Add 2% of cost of angle iron towards cost of drilling
holes , nuts bolts etc. 24.53
Aluminum sheeting fixed with encapsulated lens type
reflective sheeting of size including lettering and signs as Sqm 0.28
apllicable 5505.00 1557.92
2809.15
Total of a+b+c = 2809.15
d)Overheads @ 8% on (a+b+c) 224.73
e)Contractor's Profit @ 10% on (a+b+c+d) 303.39
Cost for one board= i+ii+iii+a+b+c+d+e 3337.27
Say 3,337
Channel post 150 x 75 x 5 mm,1.8 m long,3 Nos @ 16.4 kg 73.80 55.98 4131.55 M-179
kg per metre /1000
Spacer 150 x 75 x 5 mm channel 0.33 m long,3 Nos @ kg 16.24 55.98 909.16 M-179
16.4 kg per metre /1000
Nuts and bolts kg 20.00 60.00 1200.00 M-130
Add for Galvansation kg 151.25 12.00 1815.00
Add 15 per cent of the cost of material for fabrication, 1554.42
nuts, bolts and washers etc.)
12317.19
d) Overhead charges @ 8% on (a+b+c) 985.38
e) Contractor's profit @ 10% on (a+b+c+d) 1330.26
f)Excavation for foundation of vertical posts
3X0.35X0.35X0.95=0.35 cum cum 0.35 60.00 21.00
g)M 20 Concrete for foundation of vertical post
3X0.35X0.35X0.95=0.35 cum cum 0.35 5341.24 1869.43 A3
Cost for 4.5 metre = a+b+c+d+e+f+g 16523.26
Rate per metre = (a+b+c+d+e+f+g)/4.5 3671.83
say 3672
BILL No 3: Engineering Improvements
Ref. to Unit Quantity Rate Cost Remarks/I
MOST
S.No MoRTH Description Rs Rs nput
Data No
Spec. reference
Removal of unauthorised boards within ROW and
stacking etc complete in all respect including
3.11
transportation from site to the nearst store / suitable
location as per direction of engineer in charge
Single Post
Unit = Each
Taking output 30nos
a) Labour
Mate Day 0.48 244.30 117.26 L-10
Mazdoor Day 10.00 224.30 2243.00 L-01
b) Machinery
Tractor -Trolly Hour 1.50 289.00 433.50 P&M-053
Gas Cutter Hour 3.00 200.00 600.00 Market rate
Total 3393.76
c) Overhead Charge @ 8% on (a+b) 271.50
d) Contractor's Profit @ 10% on (a+b+c 366.53
4031.79
134.39
Say 134.00
Double Post (Post width less than 2 m.)
b
Unit = Each
Taking output 30nos
a) Labour
Mate Day 0.50 244.30 122.15 L-10
Mazdoor Day 14.00 224.30 3140.20 L-01
b) Machinery
Tractor -Trolly Hour 3.00 289.00 867.00 P&M-053
Gas Cutter Hour 6.00 200.00 1200.00 Market rate
Total 5329.35
c) Overhead Charge @ 10% on (a+b) 426.35
d) Contractor's Profit @ 10% on (a+b+c 575.57
6331.27
211.04
Say 211.00
CHAPTER - 4
INCIDENT MANAGEMENT
Provision of15 Tonnes capacity Pick & Carry Cranes
with required staff and Equipment for removing all types of
4.1 4.02 broken down vehicles which have met with accidents, from
the carriageway and toeing the same to proper locations i.e
nearest Police stations or
A For buses and lories and other heavy vehicles
Out put = 01 vehicles per mothn
a) Labour
Labour no/month 3 no x 30 days 244.30 21987.00 L-10
Skilled no/month 3 no x 30 days 264.30 23787.00 L-35
Driver no/month 3 no x 30 days 284.30 25587.00 L-01
b) Machinery
Towaway crane (Hire Charge) month 1.00 13200.00 13200.00 Market Rate
c) ii) Diesel liters 260.000 55.63 Do
14463.80
Market Rate 1.00 1024.00
d) Provision of GPS & GIS for vehicle tracking System
1024.00
e) Overhead charges @ 8% on (a+b+c) 8003.90
f) Contractor's profit @ 10% on (a+b+c+d) 8606.57
Total rate per vehicle per month (a+b+c+d+e) 116659
Unit = hour
Mate/Supervisor day 244.30 244.30 L-10
Helper / Beldar / Coolie. day 224.30 224.30 L-01
Security Guard day 244.30 244.30 L-22
b) I) Para medical staff per month 3.000 9000 27000.00 Market Rate
ii) Helper no 3 no x 30 days 244 21987.00
iii) Driver no 3 no x 30 days 284 25587.00
iv) Nursing Staff per month 3 no x 30 days 170 15300.00 Market Rate
Market Rate 1.000 1024.00
c) Provision of GPS & GIS for vehicle tracking System
1024.00
c) Mobile phones no 1.000 1500 1500.00
153931.50
e) Add 8% over head 12314.52
f) Add 10 % contractor profit 16624.60
Total rate per month (a+b+c+d+e) 182870.62
Bill No.A4
1
NATIONAL HIGHWAYS AUTHORITY OF INDIA RATE ANALYSIS
Say 182871
Bill No.A4
2
NATIONAL HIGHWAYS AUTHORITY OF INDIA RATE ANALYSIS
BILL NO - 5
MISCLLANEOUS
Sr No Ref. to Description Unit Quantity Rate Cost Remarks/ Input
MoRTH Rs Rs ref.
Spec.
5.01 124 Dismantling of structures and pavement and disposal of
unserviceable material at suitable place outside ROW with
all lead and lifts complete in all respect as per
approval of Engineer. The rate quoted should be
inclusive of salvage value of the servicable
A) Dry stone masonary Cum
Taking output = 1.25 Cum
a) Labour
Mate Nos 0.014 244.30 3.42 L-10
Mazdoor Skilled Nos 0.35 224.30 78.51 L-01
b) Machinery
Tractor-Trolley Hr. 0.27 289.00 78.03 P&M-053
c) Overhead @ 8% on (a+b) 12.80
d) Contractor's profit @ 10% on (a+b+c) 17.28
Cost for 1.25 Cum = a+b+c+d 190.03
Rate per Cum = (a+b+c+d)/1.25 165.84
165.84
Say 166.00
Bill No.A5
1
NATIONAL HIGHWAYS AUTHORITY OF INDIA RATE ANALYSIS
5.05
Providing and placing in proper position empty cement bags filled
with local earth to control erosion / damage of the side of the road
or bank of the river / nallha at required locations including cost of
material, labour equipment transporation etc. comp
Taking output=750bags
a) Labour
Mate Nos 0.40 244.30 97.72 L-10
Mazdoor Nos 15.00 224.30 3364.50 L-01
b) material
Cement Bags including sand Nos 750.00 6.00 4500.00 M-159
c) Machinery
Crane Hr 20.00 200.00 4000.00 P&M-013
d) Over head charges@8% on (a+b+c) 956.98
d) Contractor profit @10% on (a+b+c+d) 1291.92
Rate for 750 No=(a+b+c+d+e) 14211.12
Rate for each No=(a+b+c+d+e)/750 18.95
Say 19.00
Project Director
PIU- Bhubaneswar
Bill No.A5
2
NATIONAL HIGHWAYS AUTHORITY OF INDIA RATE ANALYSIS
P&M-003 Batching and Mixing Plant (b) 15 - 20 cum capacity Concrete Mixing cum/hour 13 hour 1043.48
P&M-004 Bitumen Pressure Distributor Applying bitumen tack coat sqm/hour 1750 hour 601.74
P&M-005 Bitumen Boiler oil fired Bitumen Spraying capacity in litre 1500 hour 111.30
P&M-006 Concrete Paver Finisher with 40 HP Motor Paving of concrete surface cum / hour 20 hour 1608.70
P&M-007 Concrete Pump of 45 & 30 cum capacity Pumping of concrete cum / hour 33 / 22 hour 143.48
P&M-008 Concrete Bucket For Pouring concrete capacity in cum 1 hour 8.70
P&M-009 Concrete Mixer (a) 0.4/0.28 cum Concrete Mixing cum/hour 2.5 hour 153.91
P&M-010 Concrete Mixer (b) 1 cum Concrete Mixing cum/hour 7.5 hour 153.91
P&M-011 Crane (a) 80 tonnes Lifting Purpose hour 717.39
P&M-012 Cranes b) 35 tonnes Lifting Purpose hour 478.26
P&M-013 Cranes c) 3 tonnes Lifting Purpose hour 200.00
P&M-014 Dozer D - 80 - A 12 Spreading /Cutting / Clearing cum/hour 300/ 150/250 hour 2190.43
P&M-015 Dozer D - 50 - A 15 Spreading /Cutting / Clearing cum/hour 200/ 100/150 hour 1592.17
P&M-016 Emulsion Pressure Distributor Applying emulsion tack coat sqm/hour 1750 hour 448.70
P&M-017 Front End loader 1 cum bucket capacity Soil loading / Aggregate loading cum/hour 60 /25 hour 452.17
P&M-018 Generator (a) 125 KVA Genration of electric Energy KVA 100 hour 786.96
P&M-019 Generator( b) 63 KVA Genration of electric Energy KVA 50 hour 393.48
P&M-035 Paver Finisher Mechanical 100 TPH Paving of WMM /Paving of DLC cum/hour 40/30 hour 642.61
P&M-036 Piling Rig with Bantonite Pump 0.75 m dia to 1.2 m dia Boring Rm/hour 2 to 3 hour 3065.22
attachment
P&M-037 Pneumatic Road Roller Rolling of Asphalt Surface cum/hour 25 hour 697.39
P&M-038 Pneumatic Sinking Plant Pneumatic Sinking of wells cum/hour 1.5 to 2.00 hour 2690.00
P&M-039 Pot Hole Repair Machine Repair of potholes cum/hour 4 hour 508.70
P&M-040 Prestressing Jack with Pump & access Stressing of steel wires/stands hour 72.17
INPUT
4
P&M-041 Ripper Scarifying cum/hour 60 hour 18.00
NATIONAL HIGHWAYS AUTHORITY OF INDIA RATE ANALYSIS
P&M-050 Transit Mixer 4/4.5 cum Transportation of Concrete Mix to site cum/hour 4.5 tonne.km 4.00
P&M-051 Transit Mixer 3.0 cum Transportation of Concrete Mix to site cum/hour 3 hour 478.26
P&M-052 Transit Mixer 3.0 cum Transportation of Concrete Mix to site cum/hour 3 tonne.km 4.00
P&M-077 Drum mix plant for cold mixes of appropriate capacity but not less than 75 tonnes/hour. hour 289.00
INPUT
5
NATIONAL HIGHWAYS AUTHORITY OF INDIA RATE ANALYSIS
(B) Labour
Sl. No. Description of Labour Unit Rate
(Rs.)
A Category Unskilled
L-01 Male mulia day 224.30
L-02 Female mulia day 224.30
L-03 Survey Khalasi / Chain man day 224.30
L-04 Scavanger day 224.30
B Category Semiskilled
L-05 Mulia working in water or arduous nature of work day 244.30
L-06 Night mulia or attendent working in floodand other emergent work day 244.30
L-07 Mulia for handling hot binder and Tar boiler men day 244.30
L-08 Sangi mulia day 244.30
L-09 pile driving mate ( Guide man) day 244.30
L-10 Mate day 244.30
L-11 Helper to carpenter or Blacksmith/Painter/Blaster/Plumber/Eltrician/fitter/Welder day 244.30
L-12 Hammer man day 244.30
L-13 Thatcher / Gharami day 244.30
L-14 Tile turner day 244.30
L-15 Boat man day 244.30
L-16 Bhisti day 244.30
L-17 Well sinker day 244.30
L-18 Rod binder and bender day 244.30
L-19 Cleaner / Sweeper day 244.30
L-20 Stone packer day 244.30
L-21 Pump helper day 244.30
L-22 Watch man ( Store) / Gurkha / Security Guard day 244.30
L-23 Bellow man day 244.30
C Category Skilled
L-24 Blaster ( Second Class) day 264.30
L-25 Mason ( Second Class) day 264.30
L-26 Black smith ( Second Class) day 264.30
L-27 Carpenter ( Second Class) day 264.30
L-28 Fitter ( Second Class) day 264.30
L-29 Painter / Polisher ( Second Class) day 264.30
L-30 Welder ( Second Class) day 264.30
L-31 Plumber ( Second Class) day 264.30
L-32 Driller ( Second Class) day 264.30
L-33 Stone dresser / Cutter ( Second Class) day 264.30
L-34 Cobbler with toolsr ( Second Class) day 264.30
L-35 Wire man / Lift operator / Diesel pump driver / Telephone operator ( Second Class) day 264.30
L-36 Boring mistry / Pipe driver ( Second Class) day 264.30
L-37 Electrician / Rigger / Line man / Telephone attendant ( Second Class) day 264.30
L-38 Gardener day 264.30
L-39 Amin day 264.30
L-40 Tracer day 264.30
L-41 Jr. progress recorder day 264.30
L-42 Store keeper Gr - II / Store Asst./ Account clerk / Clerk / Typist / Toolkeeper / Time keeper / Munsi day 264.30
D Category Highly Skilled
L-42 Blaster ( licensed) day 284.30
L-43 Mason ( Special) day 284.30
L-44 Carpenter ( Special) day 284.30
L-45 Blacksmith ( Special) day 284.30
L-46 Fitter ( Special) day 284.30
L-47 Painter / Polisher ( Special) day 284.30
L-48 Welder ( Special) day 284.30
L-49 Plumber ( Special) day 284.30
L-50 Driller ( Special) day 284.30
L-51 Stone dresser / Cutter ( Special) day 284.30
L-52 Diver for well sinking in bridge( per shift of four hours) day 284.30
L-53 Electrician / Airconditioned plant operator / wire man / Lift operator / Diesel pump operator( Special) day 284.30
L-54 Jeep driver / Tractor driver / Truck driver / Dozer driver / Roller driver / Concrete mixture operator / Crane operator day 284.30
L-55 Auto eleectrician day 284.30
L-56 Guiniting Machine operator day 284.30
L-57 Senior Accountant / Stenographor day 284.30
L-58 Supervisor / Manager day 284.30
L-59 Testing Laboratory Assistant / Instrument Mechanic / Telephone Mechanic day 284.30
L-60 Rigger and Cobbler with Tools Driver ( Heavy Vehicle) day 284.30
E Other Category
L-60 Boring Mistry ( Special) day 284.30
L-61 Winch Operator day 284.30
INPUT
L-62 Well sinker ( Special) day 284.306
L-63 Helper to Well sinker day 264.30
L-64 Computer Programmer / Analyzer day 7000.00
NATIONAL HIGHWAYS AUTHORITY OF INDIA RATE ANALYSIS
INPUT
7
NATIONAL HIGHWAYS AUTHORITY OF INDIA RATE ANALYSIS
(C) Materials
Sl. No. Description Unit Rate
(Rs.)
M-001 Stone Boulder of size 150 mm and below at Cruser Plant cum 933.88
M-002 Supply of quarried stone 150 - 200 mm size for Hand Broken at site cum 933.88
M-003 Boulder with minimum size of 300 mm for Pitching at Site cum 933.88
M-004 Coarse sand at Mixing Plant cum 638.04
M-005 Coarse sand at Site (Baitarini) cum 638.04
M-006 Fine sand at Site (Baitarini) cum 632.33
M-007 Moorum at Site cum 274.38
M-008 Gravel/ Quarry spall at Site cum 933.88
M-009 Granular Material or hard murrum for GSB works at Site cum 274.38
M-010 Granular Material or hard murrum for GSB works at Mixing Plant cum 274.38
M-011 Fly ash conforming to IS: 3812 ( Part II & I) atHMP Plant / Batching Plant / Crushing Plant cum 50.00
M-012 Filter media/ Filter Material as per Table 300-3 (MoRT&H Specification) cum 1499.59
M-013 Close graded Granular sub-base Material 53 mm to 9.5 mm cum 1401.50 1463.50
M-014 Close graded Granular sub-base Material 37.5 mm to 9.5 mm cum 767.00 829.00
M-015 Close graded Granular sub-base Material 26.5 mm to 9.5 mm cum 767.00 829.00
M-016 Close graded Granular sub-base Material 9.5 mm to 4.75 mm cum 937.00 999.00
M-017 Close graded Granular sub-base Material 9.5 mm to 2.36 mm cum 937.00 999.00
M-018 Close graded Granular sub-base Material 4.75mm to 2.36 mm cum 793.00 855.00
M-019 Close graded Granular sub-base Material 4.75mm to 75 micron mm cum 793.00 855.00
M-020 Close graded Granular sub-base Material 2.36 mm cum 793.00 855.00
M-021 Stone crusher dust finer than 3mm with not more than 10% passing 0.075 sieve. cum 776.02 838.02
M-022 Coarse graded Granular sub-base Material 2.36 mm & below cum 1418.64 1480.64
M-023 Coarse graded Granular sub-base Material 4.75mm to 75 micron mm cum 793.00 855.00
M-024 Coarse graded Granular sub-base Material 4.75 mm to 2.36 mm cum 793.00 855.00
M-025 Coarse graded Granular sub-base Material 9.5 mm to 4.75 mm cum 1861.50 1923.50
M-026 Coarse graded Granular sub-base Material 26.5 mm to 4.75 mm cum 767.00 829.00
M-027 Coarse graded Granular sub-base Material 26.5 mm to 9.5 mm cum 767.00 829.00
M-028 Coarse graded Granular sub-base Material 37.5 mm to 9.5 mm cum 767.00 829.00
M-029 Coarse graded Granular sub-base Material 53 mm to 26 .5mm cum 1499.59 1561.59
M-030 Aggregates below 5.6 mm cum 1506.26 1568.26
M-031 Aggregates 22.4 mm to 2.36 mm cum 1790.07 1852.07
M-032 Aggregates 22.4 mm to 5.6 mm cum 922.00 984.00
M-033 Aggregates 45 mm to 2.8 mm cum 767.00 829.00
M-034 Aggregates 45 mm to 22.4 mm cum 1499.59 1561.59
M-035 Aggregates 53 mm to 2.8 mm cum 767.00 829.00
M-036 Aggregates 53 mm to 22.4 mm cum 767.00 829.00
M-037 Aggregates 63 mm to 2.8 mm cum 725.00 787.00
M-038 Aggregates 63 mm to 45 mm cum 1401.50 1463.50
M-039 Aggregates 90 mm to 45 mm cum 995.60 1057.60
M-040 Aggregates 4.75mm cum 1437.69 1499.69
M-041 Aggregates 11.2 mm to 0.09 mm cum 937.00 999.00
M-042 Aggregates 13.2 mm to 0.09 mm cum 922.00 984.00
M-043 Aggregates 13.2 mm to 5.6 mm cum 922.00 984.00
M-044 Aggregates 13.2 mm to 10 mm cum 1838.64 1900.64
M-045 Aggregates 20 mm to 10 mm cum 1790.07 1852.07
M-046 Aggregates 25 mm to 10 mm cum 1838.64 1900.64
M-047 Aggregates 19 mm to 6 mm cum 1823.40 1885.40
M-048 Aggregates 37.5 mm to 19 mm cum 767.00 829.00
M-049 Aggregates 37.5 mm to 25 mm cum 767.00 829.00
M-050 Aggregates 6 mm nominal size cum 1506.26 1568.26
M-051 Aggregates 10 mm nominal size cum 1861.50 1923.50
M-052 Aggregates 13.2/12.5 mm nominal size cum 922.00 984.00
M-053 Aggregates 20 mm nominal size cum 1790.07 1852.07
M-054 Aggregates 25 mm nominal size cum 922.00 984.00
M-055 Aggregates 40 mm nominal size cum 1499.59 1561.59
INPUT
10
NATIONAL HIGHWAYS AUTHORITY OF INDIA RATE ANALYSIS
Education
Rate @ Haladia Unit Rate Cost of Haulage Excluding Cost
Sl. No. Type of Bitumen Unit Basic GST @ 18% Cess @ 3% on Ex-MI Price CST @ 2% Entry Tax @ 2%
(Rs.) (Rs.) Loading and Unloading (Rs.)
ED
1 VG30 grade (packed) tonne 30140.00 5425.20 0.00 0.00 0.00 0.00 0.00 35565.20 3027.50 38592.70
2 VG30 grade (bulk) tonne 32430.00 5837.40 0.00 0.00 0.00 0.00 0.00 38267.40 3027.50 41294.90
3 80/100 grade (packed) tonne 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3027.50 3027.50
4 VG40 grade (bulk) tonne 27500.00 4950.00 0.00 0.00 0.00 0.00 0.00 32450.00 3027.50 35477.50
5 Emulsion (M) bulk tonne 22740.00 4093.20 0.00 0.00 0.00 0.00 0.00 26833.20 3027.50 29860.70
6 CRMB-60 bulk tonne 26680.00 4802.40 0.00 0.00 0.00 0.00 0.00 31482.40 3027.50 34509.90
7 CRMB-55 bulk tonne 28960.00 5212.80 0.00 0.00 0.00 0.00 0.00 34172.80 3027.50 37200.30
Market Rate
Chandikhol - Paradip Section (NH-5A) 9
NATIONAL HIGHWAYS AUTHORITY OF INDIA RATE ANALYSIS
Aggregate Cost
Sl. No Description Unit Cost at Royalty Total Cost Cost of Haulage Excluding Total Cost
Quarry site (Rs.) (Rs.) Loading and Unloading per cum
(Rs.) (Rs.)
Sand Cost
Sl. No Description Unit Cost at Royalty Total Cost Cost of Haulage Including Total Cost 187.5
Quarry site (Rs.) (Rs.) Loading and Unloading per cum
(Rs.) (Rs.)
1 Mortar Sand Cost at baitarini Cum 48.57 35.00 83.57 554.47 638.04
Moorum Cost
Market Rate
Chandikhol - Paradip Section (NH-5A) 10
NATIONAL HIGHWAYS AUTHORITY OF INDIA RATE ANALYSIS
Market Rate
Chandikhol - Paradip Section (NH-5A) 11
NATIONAL HIGHWAYS AUTHORITY OF INDIA RATE ANALYSIS
RATES OF MATERIALS
Flyash bricks (25cmx12cmx8cm) having crushing strength not 1000 Nos 4144.68
5 less than 75 Kg/ Cm2 with dimensional tolerance +2percent
Flyash bricks (23cmx11cmx8cm) having crushing strength not 1000 Nos 3529.36
6 less than 75 Kg/ Cm2 with dimensional tolerance +2percent
Flyash bricks (30cmx20cmx15cm) having crushing strength
not less than 75 Kg/ Cm2 with dimensional tolerance Each 12.77
7 +2percent
Cemen concrete solid Block machine mixed and Hydraulic
compressed having crushing strength not less than 75 Kg/
8 Cm2
Each 22.05
a 400mmx 200mmx 200mm size
Each 17.32
b 400mmx 150mmx 200mm size
Each 11.81
c 400mmx 100mmx 150mm size
Each 13.39
d 300mmx200mmx 150mm size
Each 11.02
e 300mmx150mmx 150mm size
Each 9.45
f 300mmx100mmx 150mm size
Cemen concrete Hollow Block machine mixed and Hydraulic
compressed having crushing strength not less than 70 Kg/
9 Cm2
Each 19.69
a 400mmx 200mmx 200mm size
Each 14.96
b 400mmx 150mmx 200mm size
Each 11.02
c 400mmx 100mmx 200mm size
RATES OF MATERIALS
1 Cum 45.71
15 Gravel or moorum
Stone Screned Dust passing through 2.36 mm sieve and 1 Cum 80.95
16 retained on 0.075mm sieve
1 Cum 92.38
17 River single or bajri ( 12 mm - 20 mm)
1 Cum 48.57
18 Screened and washed sharp sand for mortar
1 Cum 42.86
19 Sand for filling and road blinding
1 Cum 47.62
20 Clay mortar for masonary work with admixture of sand.
1 Kg 13.33
21 Stone lime unslaked.
1 Kg 18.10
22 Ghooting lime unslaked
1 Kg 16.19
23 Shell lime unslaked.
24
1 Cum 206.11
a Granite broken stone not less than 0.0025 Cum Stacked
1 Cum 179.91
b Granite broken stone not less than 0.0025 Cum Picked up.
Stone other than granite quarried, broken and stacked 0.0015
1 Cum 184.76
25 Cum to 0.003 Cum
Stone other than granite picked up, broken and stacked
1 Cum 161.90
26 0.0015 Cum to 0.003 Cum
Stone other than granite quarried, broken and stacked above
1 Cum 173.33
27 0.003 Cum
Stone other than granite picked up, broken and stacked
1 Cum 161.90
28 above 0.003 Cum
RATES OF MATERIALS
RATES OF MATERIALS
1 Cum 115.24
49 Soling stone boulder 10 cm size picked up other than granite
RATES OF MATERIALS
58
1 Sqm 24.90
a) Belongi Bamboo 2.51 cm to 4 cm dia & above 5 cm long
1 Sqm 33.20
b) Belongi Bamboo above 4 cm to 7 cm dia & above 5 cm long
1 Mtr. 83.82
59 Sal bullahs 75 mm to 120mm dia up to 5.5 n. long
1 Mtr. 93.78
60 Sal bullahs 150 mm to 200mm dia up to 5.5 n. long
Sal bullahs above 200mm & upto 250mm dia up to 2.75 m.
1 Cum 7264.73
61 long
Sal bullahs above 200mm & upto 250mm dia up to 2.75 m.
1 Cum 8234.02
62 long & upto 4.75 long
Sal bullahs above 200mm & upto 250mm dia above 4.75 m.
1 Cum 9235.68
63 long
Sal bullahs above 250mm & upto 380mm mean dia up to
1 Cum 10594.19
64 2.75 m. long
Sal bullahs above 250mm & upto 380mm mean dia & above
1 Cum 13154.36
65 2.75 m.long up to 4.75 m. long
Sal bullahs above 250mm & upto 380mm dia above 4.75 m.
1 Cum 14131.95
66 long
1 Mtr. 39.83
67 Non-sal bullahs 75mm mean dia of any length
1 Mtr. 52.28
68 Non-sal bullahs 100mm mean dia of any length
1 Mtr. 60.58
69 Non-sal bullahs 125mm mean dia of any length
1 Mtr. 73.86
70 Non-sal bullahs 150mm to 200mm mean dia of any length
Non-sal bullahs above 200mm &upto 250mm mean dia upto 1 Cum 5199.17
71 2.5m long
RATES OF MATERIALS
Seasoned Sal wood planks not more than 75mm thick & not 1 Cum 26698.76
76 less than 200mm width
1 Cum 43079.67
77 Seasoned Piasal wood planks for shutters
1 Cum 56688.80
78 Seasoned Teak wood planks for shutters
Non Sal wood scantling & plants ( Tentera,Kasi,Gamhari,
1 Cum 16421.58
79 Kuruma)
1 Cum 9987.55
80 Non-Sal reapers.
424.00
81 Fire wood 1 Qtl.
714.96
82 1st class Raniganj or Mangalore pattern tiles 100 Nos
1126.77
83 Ridges of Raniganj or Mangalore pattern tiles. 100 Nos
228.35
84 Flat tiles ( 14 Cmx 14 Cmx 1Cm) 1000 Nos
245.67
85 Flat tiles ( 15 Cmx 15 Cmx 1.2Cm) 1000 Nos
962.99
86 Flat tiles ( 30 Cmx 15 Cmx 2.5Cm) 1000 Nos
1124.41
87 Flat tiles ( 30 Cmx 30 Cmx 2.5Cm) 1000 Nos
240.94
88 Pan tiles 1000 Nos
503.15
89 Nuria tiles ( 20cm to 25 cm) 1000 Nos
593.70
90 Nuria tiles ( 20cm to 30 cm) 1000 Nos
730.71
91 Ridge tiles 1000 Nos
RATES OF MATERIALS
95 Granite Tiles
923.62
(a) Upto 0.10 Sqm.( 10 mm thick) 1 Sqm
304.72
( I ) 30cmx20cm/20cmx20cm special plain / printed series 1 Sqm
( B) Ceramic wall tiles of premium grade having thickness
7mm to 8mm confirming to IS 13755 of following sizes
326.77
( I ) 30cmx30cm/40cmx20cm special plain / printed series 1 Sqm
( C) Vitrified floorl tiles of premium grade having thickness
8mm to 10mm confirming to IS 13756 of following sizes
( i ) 60cmx60cm plain ( Ivory) 1 Sqm 514.17
( ii ) 60cmx60cm coloured / Printed series 1 Sqm 559.06
( C) Vitrified industrial floorl tiles of premium grade having
thickness 8mm to 10mm confirming to IS 4457 of following
467.72
( i ) 30cmx30cm plain 1 Sqm
170.87
99 Chequred Tiles 1 Sqm
RATES OF MATERIALS
RATES OF MATERIALS
131 Cement
568.00
a) 33 Grade do
568.00
b) 43 Grade do
568.00
c) 53 Grade do
1515.75
132 White Cement do
133 Steel do
6200.00
a) Plain do
6200.00
b) HYSD ( FE-415) do
4699.57
134 " Z " type Steel Sheet Piles do
257.64
135 Bentonite Power do
RATES OF MATERIALS
RATES OF MATERIALS
142 Steel window handle including Nut, bolt & washer ( ISI)
15.75
a) 100mm Each
20.47
b) 150mm Each
Aluminium Fittings
RATES OF MATERIALS
RATES OF MATERIALS
RATES OF MATERIALS
RATES OF MATERIALS
RATES OF MATERIALS
RATES OF MATERIALS
Total 660.1
Sand
Distance from NH-
Sl.no Name of Quarry Average Lead in km Total Lead in Km
5A
1 Mahanadi river 12.0 39 51.00
Total 554.47
Bricks
Distance from NH-
Sl.no Name of Quarry Average Lead in km Total Lead in Km
5A
1 Near River bank 4.0 39 43.00
Total 441.54
Distance to be
cost per 1 cum Amount
carried
Up to 5 km 149.67 149.67
Total 475.27
Gravel/Morum
Distance from NH-
Sl.no Name of Quarry Average Lead in km Total Lead in Km
5A
1 Marshaghai 3.0 7 10.00
Total 193.67
HYSD steel
Distance from NH-
Sl.no Name of Place Average Lead in km Total Lead in Km
5A
1 Local Market 0.0 39 39.00