Sie sind auf Seite 1von 5

UDC 621.311.25: 621.

317
Indexing Terms: Nuclear reactors, Power stations, Measurements,
Control equipment

Updating the control and


instrumentation systems on an
operational nuclear power station
C. F. UNSWORTH, BA, CEng, MIERE'

SUMMARY
The problems of and the procedures for planning the
replacement of the control and instrumentation equipment on
an operational nuclear power station are outlined. The major
refurbishments carried out at the Hinkley Point 'A' station are
described. These include replacement of the burst can
detection and reactor temperature monitoring equipment,
turbine instrumentation, boiler drum level control and stack
* 1 Mount Road, Nether Stowey, Nr Bridgwater, Somerset TA5 1LU monitoring equipment.

1 Introduction signal was available. Answers of 'for a few seconds' were


The instrumentation and control systems on a modern not accepted and in fact it was only available for 400 ms, a
power station are very extensive and complex and on a fact not known during the previous 12 years of use.
nuclear power station they are even more so. The life of Another major problem when doing any modification
electronic equipment (determined mostly by how long work on a nuclear power station is the very strict
spares are available) is about 10-15 years. Consequently, modification procedure. This is designed to ensure that all
as power stations have an expected life of 25-35 years, at modifications are correctly and safely engineered.
least one major instrument and control refit is expected A paper is prepared, detailing the proposed changes and
during the life of the station. In the case of nuclear stations the reasons for them. Also included are the proposed
which operate as base load stations (at full load for testing procedures and commissioning details along with
24 hours per day, 365 days per year) this imposes any changes needed in the station operating rules both
considerable constraints on what can be done and how. during and after the proposed modification. This paper (or
This paper describes briefly the instrument and control series of papers) is considered by a number of independent
refurbishment of the Hinkley Point 'A' nuclear power assessors who report their findings to the Safety
station. Hinkley Point 'A' is a 'Magnox' reactor station Committee. This consists of senior members of the nuclear
which was commissioned in 1965 and which has an output side of the Central Electricity Generating Board (CEGB)
of approximately 450 MW from its two reactors. It is along with external experts in various nuclear related
situated in West Somerset, on the Bristol Channel coast. fields. Only when this committee is satisfied that a
proposal is satisfactory is it allowed to proceed, and
2 Preparation several submissions to the committee may be necessary
To replace control and instrumentation equipment on depending on the type of modification.
operational plant requires the full co-operation of The three categories of modification are:
contractors, operators and maintenance staff. In general, (1) Category 1—A modification affecting nuclear safety
change is not welcome and great care needs to be given to which, if inadequately conceived or executed, might lead to
presenting data in as similar manner as possible to the old a serious increase in the risk of a radiological hazard or
equipment. Change will be accepted only if the new which involves significant alteration to the principles on
presentation is obviously clearer and better. Analogue is which safety arguments have been based. This is the most
usually preferred to digital display. stringent category.
Before replacing a system it is necessary to know exactly (2) Category 2 is similar to Category 1 but there is a less
how it works. This may seem obvious but many problems serious risk.
arise when changing a system without considering its (3) Category 3 is defined as a modification which could not
effects on other systems. For example, in one case a lead to a significant increase in the risk of radiological
ratemeter counted pulses for 30 seconds and then sent a hazard.
signal representing the total count to a dedicated recorder; A further constraint on updating control and instru-
in the new system it sent the signal to a computer which mentation equipment in an operational nuclear station is
was performing many other tasks and had to be the lack of space. The new equipment has to go into
programmed to look at the ratemeter output at just the existing equipment rooms before the old equipment is
right time. Thus, problems of timing became important. removed. This presents some difficult problems, in cabling,
The computer programmer wanted to know how long the positioning and testing of the new equipment.
Journal of the Institution of Electronic and Radio Engineers, Vol. 57, No. 4, pp. 156-160, July/August 1987 ©1987 IERE
I 1/3
reactor reactor reactor reactor reactor reactor reactor reactor
1 2 1 2 2 1 1 2
alarms alarms
J 1 1 i J I
Thermocouples b.s.d.

Input
data

rri dig tD digVO dig 1/0


control
reader panel
punch
disc
teletype I — PDP111 computer store

watch dog
DEC- DEC- digital
alarm writer writer output
temperature b.s.d. temperature b.s.d.
data data data data
station chart . station chart
Reactor 1 System alarm recorder Reactor 2 System alarm recorder

Fig. 1. Burst fuel can detection and reactor temperature monitoring systems.

3 Systems Replaced temperature contour map is displayed when required.


3.1 Burst Can Detection Equipment and Reactor The system consists of three scanning units each with
Temperature Monitoring (Fig. 1) 360 channels of 3-pole mercury-wetted reed relays.
There is a requirement to monitor 700 thermocouples Mercury-wetted reeds were chosen for their ability to
every 2 minutes and to retain this information for 1 hour. handle higher common mode voltages than dry reeds; also,
This task had been performed by a specially designed data the average expected number of operations is 109, two
logger, commissioned in 1963 and with a memory drum orders of magnitude better than for dry reeds.
which was becoming unmaintainable. A modern scanning The measuring system comprises a programmable-gain-
system controlled by a mini-computer was proposed to range amplifier with 16 ranges from + 10mV to ±372 V
replace it. It was seen that this system would be full scale, a 12-bit analogue to digital converter and full
underemployed and it was decided to put the Burst Can series-mode integrating and phase-lock control system.
Detection (BCD) system onto the same logging system. The system is controlled by a mini-computer (PDP11/40)
The BCD system monitors the fuel cans for leaks. There with a 32K RAM and a memory disc of 1-2 M words.
are 4500 fuel channels in each of the Hinkley Point Each reactor has its own system but the facility is also
Magnox reactors, each channel containing 8 fuel elements. provided that in the event of a failure the other system will
The uranium metal used as fuel is enclosed in Magnox monitor both reactors' inputs.
cans. If these cans leak, the CO 2 coolant can come in Commissioning this system had a number of problems.
contact with the uranium and cause oxidation, releasing The new equipment had to be fitted in alongside the
radioactive fission products into the coolant gas. The existing and connected in parallel without disturbing the
oxide could cause swelling that may block the flow of CO 2 original system which was in use. The two sets of readings
up the channel and cause overheating. It is therefore were carefully compared (always a dangerous procedure)
important to detect leaks as early as possible. The and eventually the old system was closed down and
requirement is to monitor each of the 4500 channels every removed.
20 minutes. This is done in the following manner. A
3/8 inch pipe samples the channel gas at the top of each of 3.2 Safety Lines (Fig. 2)
the 4500 channels. These pipes come out of the reactor and Each reactor has three independent lines of protection. If
are passed to a valve where groups of four are commoned any parameter goes into alarm a relay opens in the safety
together. These are fed to a multiway valve with 72 inputs line and releases an end relay. If only one of the three
and one output. This valve connects each of its 72 inputs safety lines goes into a trip condition an alarm is given in
in turn every 30 seconds to its output and thence to a the main control room. If two out of the three lines trip,
radiation detector. There are sixteen of these 72-way valves then the reactor control rods drop into the reactor and
and sixteen detectors. This arrangement can handle cause it to shut down. It is not possible for the operator to
1 6 x 7 2 x 4 ( = 4608) channels and is more than adequate override this system.
for monitoring 4500 channels in 20 minutes. The output The parameters measured are
from the detectors is fed to sixteen 72-point recorders
neutron flux,
(working on an 8 x 9 matrix) for display to the operators.
The computer has to recognize which of the detectors is rate of change of flux,
sending it data and also which position the 72-way valve is fuel-channel gas outlet temperature,
in. When measured values are in an alarm condition they fuel element temperature (on selected elements),
are automatically printed. Logs, etc. are also printed on rate of change of reactor pressure,
demand. reactor over-pressure,
The scanning of 700 chromel/alumel thermocouples, loss of 11 kV power to the reactor gas circulators.
linearization of the inputs and print-out of results when in The original equipment was based on thermionic valves
alarm or on demand is also performed. A reactor and was becoming difficult to maintain. Also the
C. F. UNSWORTH: UPDATING THE CONTROL AND INSTRUMENTATION SYSTEMS ON A NUCLEAR POWER STATION 157
emergency differencial thermocouples delayed auxiliary circuit
push-buff on pressure in reactor core neutron monitoring aux.
on main switches in protection motor field supply
control desk coolant and main control relay
gas duct

under voltage Ion chambers in ion chambers thermocouples auxiliary cct


relay in 11 kV reactor monitoring in reactor in reactor monitoring
supply to 1. low log excess flux monitoring (fuel element) gas valves and
blowers 2. low log doubling time high power blower circuit
3. high log doubling time flux levels breaker
3 groups

end push blower rate of neutron shut-down channel fuel d.ap. _ blower pony end

I relay button no volts change


of press
flux amp. outlet
temps.
element
temps.
aux.
circuits
motor
circuits
relay

safety line'A1 ('B'or'O


broken CCT factor alarm contactor
circuits
contactor

contactor contactor

contacts contacts

from safety line 'B' from safety line B'


contacts contacts

from safety line'C from safety line 'C


contacts contacts

Fig. 2. Block diagram of safety line. (The contacts operate in a two out of three co-incidence to disconnect the 110 V supply
from the control rod motor contactors, thus allowing the control rods to 'drop in', tripping the reactor.)

temperature trip amplifiers were magnetic amplifiers and flows,


insulation failures were becoming a problem after twenty, speed,
years in service. Consequently, new solid state equipment, vibrations,
designed for a 'box' for box' replacement, was ordered and eccentricity,
is being installed. expansion,
The method of installation is to replace each amplifier in dissolved oxygen,
turn in one safety line with the reactor at full power. This conductivity,
means that for some periods one line is 'tripped' and any condition of valves, etc.
other spurious alarm will cause the reactor to shut down.
A total of 1000 inputs are scanned and displayed. Both
However, the method avoids changing all the equipment at
graphical and alphanumeric displays in colour are
once during a reactor outage and returning to power with
available at fixed VDUs in the control room and on
a complete set of new equipment.
portable VDUs at up to thirty positions in the Turbine
When the system is completed, a full set of radio Hall. Full colour VDUs are used and over one hundred
interference checks will be carried out to demonstrate that formats are available.
it is free from radio frequency interference, which can be a
Plant inputs enter the system through one of four
problem on modern solid-state equipment with low input
microprocessor units. Here they are converted to
signals. For example, the inputs to the temperature
engineering units and passed along a serial link to the
amplifiers are 10-30 mV and to the flux instruments
main computer. This is a DEC11/34 with two RLO1 disc
10" 5 A to 10" 3 A. Until these tests are completed the use
drives plus a 128K RAM.
of RF equipment in the vicinity of the safety line
Again the system was designed to run in parallel with
equipment is banned.
the original installed equipment.
3.3 Turbine Computer System 3.4 Boiler Drum Level Control (Fig. 3)
The Turbine Hall contains nine turbines—six 95 MW sets Each Reactor has six boilers, each with two steam loops (a
and three 33 MW variable-frequency sets. high pressure loop and a low pressure loop). Each loop
The original design was to have the measured has its own steam drum and the water level in this is
parameters displayed at local gauge boards on indicators maintained by a feed regulating valve.
and charts. It became necessary to change the chart The original control system was a pneumatic, 3-element
recorders (ninety-five in all) due to age and to satisfy a (steam flow, feed flow, drum level), single-term system. It
changed operations requirement for the information from needed replacing because spares were not available and
any turbine to be displayed at any other turbine and in the also the range of control was limited at the lower end due
control room. The obvious solution was to put in a to steam and feed-flow measurements being part of the
computer logging system. control function.
The parameters measured include the following:
It was decided to try a control system with one control
pressures (steam and oil), element only—drum level, as this would remove the
temperatures (steam, oil, gas), inaccuracies of steam and feed flow measurements at low
158 J. IERE, Vol. 57, No. 4, July/August 1987
Repear of I.p. diagram for h.p.

h.p. feed reg.


valve

feed
line

Drum level control system


single element"/ rwo rerm control Feed flow
ho m.c.r. records

Fig. 3. Feed water control system.

flows. A problem in measuring drum level accurately is the The drum level control is better under all conditions and
variation in density. If the steam pressure varies, as it does the maintenance effort is considerably reduced.
under certain operating conditions, the density of the
steam and water (due to steam bubbles) varies, producing 3.5 Stack Monitoring (Fig. 4)
large errors in the level signal. To counteract these errors, All effluent discharged from a nuclear power station has to
density compensation must be applied. be monitored in order that prescribed limits are not
The differential pressure across the drum and the steam exceeded. Air from the reactor shield cooling and CO 2
pressure are fed into a device known as a 'density discharges are particularly important. A representative
compensator'. This has a built-in algorithm and the output sample, proportional to the discharge is required and as
signal is an accurate measure of the drum level. this will contain both gaseous and particulate components,
The true drum level signal from the density compensator therefore isokinetic sampling conditions are essential. A
is fed directly into a microprocessor-based controller single probe is used in each of the two stacks. The probe in
which operates as a conventional incremental controller the CO2 stack (18 inch diameter) is placed in the centre
with raise/lower output to change the position of the valve. while the probe in the air stack (11 feet diameter) is
Manual, automatic, remote or ratio modes are selectable positioned so as to be in the maximum flow. Variable
via front panel pushbuttons. A bar graph display shows speed pumps are used to draw samples from the probes at
the position of the control valve. rates which maintain the isokinetic condition, i.e. maintain
The density compensator is very quick acting and the velocity along the same probe equal to the velocity of
enables control of these particular boilers to be undertaken the sampled gas passing the probe. Each sample system
successfully with a single-element system. Tests using uses a differential pressure transmitter, a 3-term controller
single-element control, pseudo 3-element control and full and a variable speed pump to ensure the correct conditions
3-element cascaded control showed that for a steady drum are met.
level, the single-element control was the best. Each probe consists of effectively two pitot tubes
The transmitters have an overall accuracy of ±05% at measuring the flow velocities up the stack. The pressure
reference temperature, which results in an overall system outputs from these pitot tubes are connected across a
accuracy of approximately 1-3%. differential pressure transmitter so that any difference in
The replacement control system differs from the original flow velocity between the two will produce a signal from
in the following ways: the differential transmitter which is used to adjust the
pump speed. The sample gas is fed through a particulate
(1) Electronic not pneumatic filter which is changed regularly and the accumulated
(2) Single element, not 3-element activity is measured in the laboratory. The I 131 is collected
(3) Two term not single term in a charcoal filter pack and a separate tapping point is
(4) More indications for the operator provided for S35, C 14 and H 3 analysis. The sample is
The new system was phased in gradually, first on one drawn off and heated in a furnace to 1100°C to convert, it
boiler where it was rigorously tested, and then on a further to oxides, and is then collected by bubbling through catch
two boilers on the same reactor. The modification was pots containing different chemicals. The solutions
then carried out on all the boilers and is now working well. produced are then analysed by appropriate radioactive
C. F. UNSWORTH: UPDATING THE CONTROL AND INSTRUMENTATION SYSTEMS ON A NUCLEAR POWER STATION 159
The pressure in this leg is
GAS FLOW proportional to gas velocity
up the stack

-•if*- VOiam.
AIR

t 7
The pressure in this leg is
AIR SAMPLE proportional to the gas To dp Cell
GAS FLOW
velocity up the sample line
CO2 SAMPLE

Sample gas to the pump

(a) (b)

Air Flow CO, Flow


6000mVmin 0-100lbs/sec.

AIR SAMPLE

C0 2 SAMPLE

POSITION OF SAMPLE PROBES Fig. 4. Stack monitoring system, (a) Position of sample
IN THE TWO STACKS probes in the two stacks, (b) Section through the isokinetic
sampling probe.

counting techniques. The air sampling is relatively changes have taken place such as new recorders, new
straightforward as the air flow up the stack remains fairly chemical instrumentation, level indication, more and
constant but the CO2 flow varies from a few pounds per improved health physics instrumentation. In the future
hour to several tons per hour. This very wide range of there will be a need to improve the fuelling machine logic,
flows requires the addition of an extra pump to cope with new turbovisory on all the turbines and a new station
the maximum flow. telephone system.
As the rate of change in electronics and instrumentation
3.6 Wind Speed and Direction increases the need to change the control and
A requirement of nuclear power stations is to measure instrumentation systems on major plant will increase. It is
wind speed and direction at two heights (32 ft and 105 ft). an aspect that should be taken more fully into account
With large buildings on the site ('A' Station Reactor during the design of all major industrial plants that have
buildings are 180 ft high and 'B' Station is 250 ft high) the an expected life in excess of ten years. ,
location of suitable sites for wind measurement that would
not be affected by these buildings was a problem. 5 Acknowledgments
Eventually a computer model of the site and measurement The author would like to thank the Central Electricity
requirements provided the correct locations. New towers Generating Board for permission to publish this paper.
were constructed and the equipment installed and
commissioned.

4 Conclusions Manuscript first received by the Institution on 9th April 1986, and in revised
The major refurbishments carried out to date at Hinkley form on 1st December 1986
Point have been described. In addition, many other minor Paper No. 2286/MI43

The Author
Charles Unsworth studied Electrical Engineer-
ing and Earth Sciences at the University
College of Swansea and the Open University
respectively. After training in telecommuni-
cations with the Automatic Telephone and
Electric Company in Liverpool, he worked as a
Development Engineer for the English Electric
Company and for BICC. In 1967 he joined the
Instrumentation Department at the CEGB's
Trawsfynydd Nuclear Power Station and in
1970 transferred to the Hinkley Point Power
Station as the Control and Instrumentation
Development Engineer. Mr Unsworth is active
in the public debate on nuclear power and now
lectures on the subject on behalf of the CEGB.
C. F. Unsworth

160 J. IERE, Vol. 57, No. 4, July/August 1987

Das könnte Ihnen auch gefallen