MGMT 3000 Assignment Semester 2 - 2017

Proposed Freight Link Project

Freight Link Project


This would be a significant road infrastructure project to be undertaken in Western Australia and
includes a Heavy Vehicle Toll Charge. The Freight Link is 14km in length and is expected to cost $1b.

It will provide the 'missing link' in the Perth Urban Transport Corridor, through a dedicated, East-West
freight connection between Perth's heartland industrial areas, such as Kewdale and Welshpool, and
Fremantle Port. Current stop-start traffic would be replaced with free-flowing vehicle movements
yielding environmental, safety and productivity benefits for the Western Australian community. The
freight link will also have a rail track built to be used for cargo trains for ship loading at Fremantle port.

Imagine that you are employed with the Mainroads Department and you have been assigned to work
with the engineering planning team on the proposed new Freight Link Project.
The estimated total cost of the Freight Link Project is estimated to be $1 billion in today’s dollars.
It is expected that a total of 25,000 vehicles per day will use the new freight link.
You have been told that 45% of the total number of vehicles that will use the Freight Link will fall
under the Heavy Vehicle category thus attracting the toll charge.

Revenue will be generated via toll charges and from the bill board advertising along the route.

Expected Revenue from billboard advertising 20 cents / vehicle *

Table 1a

*Note this is a one way flat rate applicable to all vehicles independent of distance
travelled and category type.

Engineering Management 3000 - Semester 2 2017 Assignment Page 1


There will be three types of Heavy Vehicle toll charges that will apply.
The charges will vary depending on the length of your journey. The distance is made up of
three segments. Refer to Table 1b below.

Distance Travelled Expected Percentage of Toll Charges


(One way) Population Usage (One way)

>= 10km 56% $3*N


>5 km and < 10 km 28% $2*N
< = 5km 16% $N
Table 1b

Financing Structure of the Project

Funding for the project is expected to come from the State Government using a mix of existing and
borrowed funds. The government has $550m in cash already allocated for this project, thus the $550m is
not to be considered as part of this analysis.

The state government intends to make up the shortfall by borrowing the $450m with an annual interest
rate of 2.5% to finance the project. The borrowed funds will help cover the cost of the preparation of all
the documentation, contracts, public consultation, the tendering process, the actual construction and
commissioning. It is envisaged that some of the borrowed funds will also in part cover, staff wages and the
ongoing operation and maintenance costs.

The proposed financing arrangement for the loan is to be financed over a 45 year period.
The government has stipulated that if the project was to go ahead, the initial project scoping must start
on the 1st of Jan 2018 and has stated that the project is to break even at the end of the 45 year period.
This goal is to be achieved from revenue generated via toll charges along the 14km route and from
roadside billboard advertising while also taking into account expected annual ongoing maintenance and
operational and costs.

The Government requires that the toll charge has to set at a reasonable value and has stipulated a
constraint that a one way toll charge must be set to less than or equal to $2 per road segment as defined
in Table 1b. A second constraint stipulates that the project must break even in less than or equal to 45
years.

Note that the loan drawdown profile of the borrowed $450m total, follows the typical project lifecycle “S
curve” expenditure distribution as given in Table 2 below.

Year of Loan Drawdown Expected Loan Drawdown Profile


By the end of 1st Year Expected drawdown is 16% of total loan amount.
By the end of 2nd Year Expected drawdown is 25% of total loan amount.
By the end of 3rd Year Expected drawdown is 37% of total loan amount.
By the end of 4th Year Expected drawdown is 15% of total loan amount.
By the end of 5th Year Expected drawdown is 7% of total loan amount.
Table 2

Note that the revenue stream can only start once the road link is built, commissioned and handed over.

Engineering Management 3000 - Semester 2 2017 Assignment Page 2


Operations and Maintenance Costs
The expected costs associated with the ongoing maintenance and operational cost (in today’s dollars)
is listed in Table 3 below. Maintenance costs commence only once the Freight Link is commissioned.

Operations and Maintenance Expected Costs


Ongoing Maintenance 30 cents / vehicle*
Table 3

*Note that this is a flat rate applicable to all vehicles for each time any segment of the Freight Link is used
independent of distance travelled and category type.

Appendix Information
In the appendix you have been given tables of the work breakdown structures covering the expected
Electrical, Mechanical and the Communications / IT engineering scope of works.
You have also been given a table of the Master Plan for the project.

Task List

Your team has been asked to determine what a one way toll charge needs to be set to, in order to be
able to break even at the end of a 45 year time frame.

To help you to provide a response to this request you are required to present the following in your formal
report to the government:

Task 1. Draw the Gantt charts pertaining to each of the Work Breakdown Structures for the Mechanical,
Communication / IT and Electrical scope of work components as per Tables 5, 6 and 7 respectively.
(Note: The Gantt charts can be hand drawn but no free hand drawings are acceptable as this is a
formal report. All charts are to be clearly labelled showing total time duration in weeks. )
[24 Marks]
Task 2. Draw an AOA diagram for the of the Electrical Engineering scope of works, starting from and
including activity “AE” up to and including activity “QE”. Refer to Table 7. [10 Marks]

a. Find and state the critical path and determine its duration. [2 Marks]

b. State by how many weeks the termination of the primary incoming 66kV overhead
feeders could be delayed by, without affecting the completion time of the overall
Electrical Engineering component of the project. [2 Marks]

c. State by how many weeks the installation of the lightning and surge protection could be
delayed by, without affecting the completion time of the overall Electrical Engineering
component of the project. [2 Marks]

d. State by how many weeks the installation of the substation protection equipment could
be delayed by, without affecting the completion time of the overall Electrical
Engineering component of the project. [2 Marks]

e. State by how many weeks the testing of the boom gates primary and secondary power
supply could be delayed by, without affecting the completion time of the overall
Electrical Engineering component of the project. [2 Marks]

Engineering Management 3000 - Semester 2 2017 Assignment Page 3


Your Tasks List Continued …….

Task 3. Using the data given in Table 4 of the Appendix and incorporating information attained from
question 1, draw the complete Gantt chart of the “Master Plan” for this project. [8 Marks]

Task 4. Using the now completed Table 4 determine the overall expected project completion time from
the initial tender, “Activity A” to the commissioning and handover of the complete project,
“Activity K ”. Clearly state how many weeks in total it will take to build and commission the
Freight Link project. This is a critical number as it will determine when the project can commence
earning revenue. Derive also the total revenue equation. [8 Marks]

Task 5. Draw and clearly label the pre-tax cash flow diagram for the total project taking into account all
relevant cash inflows and outflows. [10 Marks]

Task 6. Given that the project is to break even at the end of 45 years, determine the value of a one way
toll charge, $N if the government can negotiate an interest rate of 2.5%. (Show your working) Is
this in breach of a government constraint for the project? [20 Marks]

Task 7. Alternative Scenario: Assume the government at short notice, can at best negotiate to borrow the
funds at an interest rate of 3%. By setting the price of a one way toll charge to $N = $2, calculate
how many years it would take to break even. (Show your working) Is this in breach of a
government constraint for the project? [20 Marks]

Task 8. You are asked to look at a further scenario, where the government wants to set the price of a one
way toll charge to $N = $1.80 Given that the project must break even at the end of 45 years,
calculate what interest rate must be negotiated, to achieve this. Give your answer to an accuracy
of seven significant figures. (Show your working) [20 Marks]

Task 9. Part of your role is to select the engineering contracting company to carry out the build of the
Electrical, Mechanical and Comms IT construction work. The list of accredited tenderers has been
narrowed down to two companies. Both companies have provided their respective financial
statements for the past two fiscal years. Refer to Appendix 2. Calculate the solvency, liquidity and
profitability ratios for each company (for both financial years) and display your workings. Based
on your calculations in about 500 words make your recommendation as to which company would
be better placed to undertake this project. In your own words clearly explain your reasoning.
[35 Marks]

Task 10. Team Formation. [10 Marks]


• Form your own team of three people that you wish to work with.
• Refer to the notes on Team Development and Organising teams. In particular the “five stage
group model” of team formation and “leadership” respectively.
• Elect a team leader. It is the team leader’s role to ensure that all team members hand in their
assignment on time.
• Define clearly amongst yourselves who is doing what and by when.
• If you are the team leader: In your own words write a short paragraph (about 100 words) on
the power tactics that you used to motivate and influence your group’s behaviour. Highlight
which tactic worked best for you.

Engineering Management 3000 - Semester 2 2017 Assignment Page 4


Task 10 Continued …….

• If you are a team member: In your own words write a short paragraph (about 100 words) on the
power tactics that your team leader used to motivate and influence the group’s behaviour.
Comment on the tactic’s effectiveness. Also comment on if you had been the team leader, if you
would have used the same or a different tactic to motivate the team.

Assignment Requirements
1. The Assignment is due COB 4:00pm Friday the 22rd of September 2017.
2. The Assignment is worth 20% of the total MGMT 3000 unit mark.
3. It is to be handed in to the assignment office and later collected from the assignment office.
4. Your report must have a signed cover sheet from the assignment office.
5. Each team member is to hand in a complete report in his/her own name with its own cover page.
Each report will be marked individually. It is quite OK to have your own independent views. You
don’t have to agree with your team member’s view(s).
6. As this is a professional report for the government, nothing in the report is to be drawn free hand.
All diagrams must be either printed of ruled up and/or stencilled. Only ink pen is to be used.
All charts and diagrams are to be clearly labelled.
7. All text must be typed and in you own words. No paragraphs of text can be the same as a team
member’s.
8. Calculations can be typed or hand written (neatly) and must be shown.
9. Label which task you are answering.
10. A total of 13 marks will be allocated for the overall presentation of the assignment.
11. Late assignments – will incur a daily 10% penalty deduction off the total mark.

Report Format and Mark Breakdown

1. A signed Assignment Office Registration Cover Page


2. A Cover page – With Name and student ID numbers of all team members and who the leader was.
3. Introductory paragraph (in your own words) outlining what this report will address. (about100 words)
[6 Marks]
4. Your answers to each of the ten tasks. Include all charts and calculations. Each task you are answering
must be numbered. [175 Marks - For tasks 1 to 10. Refer to task list for breakdown]
5. Concluding paragraph (in your own words) summarising your results. (about 100 -200words) [6 Marks]
6. Assignment Presentation [13 Marks] (Remember this is a formal report)
Total possible assignment marks = [200 Marks]
When handing in your report:
• Your reports must be handed in together with your other team members reports. Place the team
leader’s report on top. This can be done by either of two ways:
o You may have all three reports inserted in the one plastic sleeve, or,
o You can have three plastic sleeves all tied together in one corner.
o When collecting your reports from the assignment office you will need to know your team
leaders name as they will be catalogued under your team leader’s name.

Engineering Management 3000 - Semester 2 2017 Assignment Page 5


Appendix 1

The Master Plan - Construction of the Freight Link project

Activity Description Predecessors Weeks*

A Prepare concept plan broad scope of the project Start 14


1/Jan/2018
B Seek Public Consultation and stakeholder engagement A 7
C Prepare Business Case and Obtain Environmental Approvals B 10
D Commence and Close the Tender Period C 9
E Analyse and award contract to the winning tenderer. D 13
F Finalise and submit the detailed design of the Civil, Electrical, E 20
Mechanical and the Comms IT engineering works and wait for
final approvals.
G Ordering of all materials required for the Civil, Electrical, F 25
Mechanical and the Comms IT engineering works
H Ordering of the carriages for the light rail project F 14
I Completion of the Construction Phase – for all the Civil scope G 45
of works
J Completion of the Construction Phase – for all Electrical, I TBD^
Mechanical and the Comms IT engineering scope of works
K Final Commissioning and Project Handover of the total project J 10
and commemorate with the Premier at a ribbon cutting
ceremony
Table 4

TBD^ - To be determined from the WBS tables 5, 6 & 7 in appendix

Engineering Management 3000 - Semester 2 2017 Assignment Page 6


WBS Mechanical Engineering Scope of Works
Activity Description Predecessors Weeks*

AM Confirm order all materials from the design bill of quantities I (Master Plan) 2
BM Catalogue and deliver all materials to appropriate sites AM 1
CM Mobilise personnel to site office(s) BM 2
DM Install the rail tracks to specifications CM 13
EM Install rail sidings and all fire hydrant infrastructure CM 6
FM Install track interchange infrastructure DM 7
GM Install all control and signalling equipment along the rail line DM,EM,FM 11
HM Install all the boom gates as per the design DM 8
IM Install the required control and signalling software for HM 12
the master control room
JM Test the rail tracks under load with actual carriage GM 4
KM Confirm max carriage speed allowable along the rail route JM 6
LM Test fire hydrant infrastructure ensuring water comes out at KM 4
the required pressure.
NM Final testing commissioning and formal handover LM 5
Table 5

WBS Communications and IT Engineering Scope of Works


Activity Description Predecessors Weeks*

AT Confirm order all materials from the design bill of quantities I (Master Plan) 2
BT Catalogue and deliver all materials to appropriate sites AT 1
CT Mobilise personnel to site office(s) BT 2
DT Relocate all existing telecommunications infrastructure along CT 14
the proposed rail route as required by the design
ET Install optic fibre along the route and connect to the Telstra DT 6
network
FT Install the router system enabling wireless internet access ET 9
and the toll sensors along the route
GT Installation of mobile towers and antennas as required ET 10
HT Install GSM4 mobile equipment racks as existing Telstra GT,ET 4
exchanges and the mobile towers
IT Setup the backup comms network for the train drivers to talk to HT 2
the main control room
JT Install the security microphone and speaker system at the ET 7
stopping stations
KT Install the remotely controlled security cameras with live feed IT 3
back to the control room.
LT Final testing commissioning and formal handover KT 4
Table 6
Engineering Management 3000 - Semester 2 2017 Assignment Page 7
WBS Electrical Engineering Scope of Works

Activity Description Predecessors Weeks*

AE Confirm order all materials from the design bill of quantities I (Master Plan) 2
and deliver all materials to site
BE Prepare final Design drawings and documentation AE 8
CE Mobilise personnel to site office(s) AE 2
DE Relocate all existing electrical infrastructure along the proposed AE 5
route as required by the design
EE Build a 66kV substation along the route as per the design CE,DE 9
FE Terminate the primary incoming 66kV overhead feeders from EE 4
Western Power to the new substation
GE Terminate the second 66kV cable for from Western Power for DE 3
power robustness. This diverse cable is for power reliability in
the event of a fault on the primary cable
HE Equip the switch room with the main switchboard and GE 7
protection fuses and circuit breakers at the sub stations
IE Install all sub switchboards HE 4
JE Install the uninterruptable power supply equipment in the main FE,IE 6
switch room
KE Install all the wiring reticulation along the route for supply to FE,IE 9
the boom gates and signalling controls
LE Install the protection equipment at the sub station JE,KE 5
ME Install all lighting poles and globes along the highway and rail LE 10
line including security lighting
NE Install lightning and surge protection LE 6

OE Test primary and secondary power supply for the boom gates DE 5

PE Test that all road lighting and security lighting meets the BE,ME,NE,OE 4
Australian Standards
QE Final testing commissioning and formal handover PE 5
Table 7

*Assume 52 weeks per year (i.e. no holiday gaps due to shift work arrangements). Also one work
week is equal to seven days i.e. no week ends. Also assume one year is equal to 365 days exactly.

Also for simplicity assume all expenditures land at the end of each year. For example, assume all
maintenance costs are incurred at the end of each year (even though in practice maintenance costs are
incurred throughout a given year).

Engineering Management 3000 - Semester 2 2017 Assignment Page 8


Appendix 2

Creative Contractors AAA - Income Statement ($AUD x 1000)

Fiscal Year ending 30-Jun-16 30-Jun-15

Net Revenue 34,575 30,102

Cost of Good Sold 28,500 25,786

Gross Margin 6,075 4,316

Other Income
Investment A 31 25

Investment B 64 52

Investment C 58 19

Total Income from Investments 153 96

Operating Expenses

Selling, General & Admin 2,794 2,294

R&D and Engineering 345 419

Special Charges 7 45

Total Operating Expenses 3,146 2,758

EBITDA 2,929 1,558

Depreciation and Amortisation 110 235

EBIT 2,819 1,323

Interest 75 98

Provision for Income Tax 450 502

Net Profit / Income 2,447 819

Engineering Management 3000 - Semester 2 2017 Assignment Page 9


Creative Contractors AAA - Cash Flow Statement ($AUD x 1000)

Fiscal Year ending 30-Jun-16 30-Jun-15

Cash flow from Operating Activities

Net Income 2,447 819


Depreciation and Amortisation 110 235
Changes in Working Capital 901 893
Changes in Non-Current Assets & Liabilities 108 87
Special charges and other adjustments -98 635

Net cash provided by Operating Activities 3,468 2,669

Cash flow from Investing Activities

Marketable Securities
Purchases -4,006 -4,736
Sales 3,642 2,956
Capital Expenditure -154 -152

Net Cash Used in Investing Activities -518 -1,932

Cash flow from Financing Activities

Purchase of Common Stock -1135 -1935


Issuance of Common Stock to
Staff 245 265

Net Cash Used in Investing Activities -890 -1670

Effect of exchange rate changes in cash -120 60

Net Increase in Cash 1,940 -873

Cash at the beginning of the period 469 1,342

Cash at the end of the period 2,409 469

Engineering Management 3000 - Semester 2 2017 Assignment Page 10


Creative Contractors AAA - Balance Sheet ($AUD x 1000)

Fiscal Year ending 30-Jun-16 30-Jun-15

Current Assets
Cash (at end of period) 2,409 469
Short Term Investments 205 154
Accounts Receivable 1208 987
Inventories 139 127
Other 950 801

Total Current Assets 4,911 2,538

Non - Current Assets

Property, Plant & Equipment 850 980


Long Term Investments 3209 2897
Other 148 256

Total Non Current Assets 4,207 4,133

Total Assets 9,118 6,671

Current Liabilities

Accounts Payable 1500 1807


Accrued and other 2500 1306

Total Current Liabilities 4,000 3,113

Non - Current Liabilities

Long Term Debt 1131 989

Total Non Current Liabilities 1,131 989

Total Liabilities 5,131 4,102

Equity

Preferred stock 703 440


Common Stock and Capital 1788 1253
Retained Earning 1496 876

Total Equity 3987 2569

Engineering Management 3000 - Semester 2 2017 Assignment Page 11


Total Contractors BBB - Income Statement ($AUD x 1000)

Fiscal Year ending 30-Jun-16 30-Jun-15

Net Revenue 34,564 29,845

Cost of Good Sold 29,105 24,538

Gross Margin 5,459 5,307

Other Income
Investment A 31 20

Investment B 64 41

Investment C 23 16

Total Income from Investments 118 77

Operating Expenses

Selling, General & Admin 2,894 2,500

R&D and Engineering 425 419

Special Charges 7 3

Total Operating Expenses 3,326 2,922

EBITDA 2,133 2,385

Depreciation and Amortisation 198 480

EBIT 1,935 1,905

Interest 39 45

Provision for Income Tax 975 502

Net Profit 1,039 1,435

Engineering Management 3000 - Semester 2 2017 Assignment Page 12


Total Contractors BBB - Cash Flow Statement ($AUD x 1000)

Fiscal Year ending 30-Jun-16 30-Jun-15

Cash flow from Operating Activities

Net Income 1,039 1,435


Depreciation and Amortisation 198 480
Changes in Working Capital 901 893
Changes in Non-Current Assets & Liabilities 108 87
Special charges and other adjustments -98 635

Net cash provided by Operating Activities 2,148 3,530

Cashflow from Investing Activities

Marketable Securities
Purchases -4,006 -4,736
Sales 3,642 2,956
Capital Expenditure -154 -152

Net Cash Used in Investing Activities -518 -1,932

Cash flow from Financing Activities

Purchase of Common Stock -1135 -1935


Issuance of Common Stock to Staff 245 265

Net Cash Used in Investing Activities -890 -1670

Effect of exchange rate changes in cash -120 60

Net Increase in Cash 620 -12

Cash at the beginning of the period 1,330 1,342

Cash at the end of the period 1,950 1,330

Engineering Management 3000 - Semester 2 2017 Assignment Page 13


Total Contractors BBB - Balance Sheet ($AUD x 1000)

Fiscal Year ending 30-Jun-16 30-Jun-15

Current Assets
Cash (at end of period) 1,950 1,330
Short Term Investments 205 154
Accounts Receivable 1208 987
Inventories 142 131
Other 0 600

Total Current Assets 3,505 3,202

Non - Current Assets

Property, Plant & Equipment 850 980


Long Term Investments 3209 2897
Other 148 256

Total Non Current Assets 4,207 4,133

Total Assets 7,712 7,335

Current Liabilities

Accounts Payable 2089 2000


Accrued and other 1456 1400

Total Current Liabilities 3,545 3,400

Non - Current Liabilities

Long Term Debt 1250 1000

Total Non Current Liabilities 1,250 1,000

Total Liabilities 4,795 4,400

Equity

Preferred stock 452 806


Common Stock and Capital 969 1253
Retained Earning 1496 876

Total Equity 2917 2935

Engineering Management 3000 - Semester 2 2017 Assignment Page 14