Beruflich Dokumente
Kultur Dokumente
AT NEW DELHI
VERSUS
INDEX
PLAINTIFF
THROUGH COUNSEL
ABHINAY/UTSAV TRIVEDI/HIMANSHU
COUNSEL FOR THE PLAINTIFF
P-2A, JANGPURA EXTENSION,
NEW DELHI – 110014
9205137094
PLACE: NEW DELHI
DATE: __.09.2019
BEFORE THE LEARNED DISTRICT JUDGE, SAKET COURTS
AT NEW DELHI
VERSUS
COURT FEES
BEFORE THE LEARNED DISTRICT JUDGE, SAKET COURTS
AT NEW DELHI
VERSUS
SYNOPSIS
It is the case of the Plaintiff that as per the terms of the Work Order, the
Bank Guarantee ought to have been released by the Defendant No. 2.
However, the same was continuously renewed by the Defendant No. 2
year after year on the pretext of its impending Arbitration with a third
party, with whom the plaintiff has no privity of contract.
However, the Defendant has not acceded to the multiple requests made
by the Plaintiff. Currently, the claim period of this Bank Guarantee is
expiring on 15.09.2019. Instead of releasing the same, the Defendant No.
2 has sent a communication to the Defendant No. 1 to either extend the
Bank Guarantee or encash the same if the Plaintiff fails to extend it by
10.09.2019.
Therefore, left with no option, your humble plaintiff has approached this
Ld. Court seeking an injunction against the Defendants from
encashing/invoking the Bank Guarantee furnished by Defendant No. 1
to Defendant No. 2 for and on behalf of the Plaintiff add further seeking
refund of the Bank charges paid by the Plaintiff for renewals of the Bank
Guarantee after 15.08.2011 along with interest.
LIST OF DATES
PLAINTIFF
THROUGH COUNSEL
ABHINAY/UTSAV TRIVEDI/HIMANSHU
COUNSEL FOR THE PLAINTIFF
P-2A, JANGPURA EXTENSION,
NEW DELHI – 110014
9205137094
PLACE: NEW DELHI
DATE: __.09.2019
BEFORE THE LEARNED DISTRICT JUDGE, SAKET COURTS
AT NEW DELHI
CS(Comm.) No. ____ 2019
IN THE MATTER OF:
VERSUS
MEMO OF PARTIES
M/S CICO TECHNOLOGIES LIMITED
THROUGH ITS AUTHORIZED REPRESENTATIVE
MR. SUKANTA MALIK
HAVING ITS OFFICE AT.
C-44/2, 1ST & 2ND FLOORS,
OKHLA INDUSTRIAL AREA PHASE-II,
NEW DELHI 110020 …. PLAINTIFF
VERSUS
1. KOTAK MAHINDRA BANK LTD
THROUGH ITS BRANCH MANAGER
HAVING ITS CONCERNED BRANCH AT:
GROUND FLOOR, SHOP NO. 1, 2, 3, 6 AND 6A,
BASEMENT FLOOR, SHOP NO. B-1,
DEENAR BHAVAN, 44, NEHRU PLACE,
NEW DELHI – 110 019
THROUGH COUNSEL
ABHINAY/UTSAV TRIVEDI/HIMANSHU
COUNSEL FOR THE PLAINTIFF
P-2A, JANGPURA EXTENSION,
PLACE: NEW DELHI NEW DELHI – 110014
DATE: __.09.2019 9205137094
BEFORE THE LEARNED DISTRICT JUDGE, SAKET COURTS
AT NEW DELHI
CS(COMM.) No. ____ 2019
2. That the Defendant No. 1, i.e. Kotak Mahindra Bank Ltd. is the
bank, which has issued the Bank Guarantee in favour of the
Defendant No. 2, for and on behalf of the Plaintiff. The
Defendant No. 1 has issued the said Bank Guarantee from its
branch situated at Ground Floor, Shop No. 1, 2, 3, 6 and 6A,
Basement Floor, Shop No. B-1, Deenar Bhavan, 44, Nehru Place,
New Delhi – 110 019.
6. That as per the terms of the Work Order issued in its favour, the
Plaintiff was under an obligation to furnish a Performance
Guarantee in the form of a Bank Guarantee in your favour, for
an amount of Rs. 10,61,610/- i.e. 10% of the total value of the
work to be done by CICO, i.e. Rs. 1,06,16,109/-.
9. That the Plaintiff changed its banker in the year 2010, the old
Bank Guarantee by Bank of India was replaced by a new Bank
Guarantee dated 24.12.2010, bearing Bank Guarantee No.
205B215103580005, which was issued by the Defendant No. 1 at
the request of and for the account of the Plaintiff for a value of
Rs. 10,61,610/- (Rupees Ten lakh Sixty One Thousand Six
Hundred and Ten only).
12. That as per the terms of the Work Order, the defects liability
period was for a period of one year from the completion of work
and issue of final payment certificate.
13. That since the final payment certificate was issued on
15.08.2010, the defects liability period stood lapsed on
15.08.2011, i.e. one year after the issuance of the defects liability
period.
17. That the Plaintiff has also furnished a Guarantee Bond dated
10.02.2014 as per the terms of the Work Order. The relevant
Clause is extracted hereunder for ready reference:
18. This Guarantee Bond is valid for a period of ten years, i.e. till
10.02.2024.
19. That the Bank Guarantee No. 205B215103580005 dated
24.12.2010, which was issued by the Defendant No. 1 at the
request of and for the account of the Plaintiff for a value of Rs.
10,61,610/- was initially valid till 15.03.2011, with claim period
upto 15.09.2011.
36. The reason for this extension was alleged to be that the “Bank
Guarantee is required to be extend MCD/Client has not
certified/finalized the final bills.”
39. The reason for this extension was alleged to be that the “Bank
Guarantee is required to be extend MCD/Client has not
certified/finalized the final bills.”
42. The reason for this extension was alleged to be that the “Bank
Guarantee is required to be extend MCD/Client has not
certified/finalized the final bills.”
45. The reason for this extension was alleged to be that the “Bank
Guarantee is required to be extend MCD/Client has not
certified/finalized the final bills.”
47. That on 06.03.2019 the Defendant No. 2, for the first time
informed the Plaintiff that there is currently an Arbitration
going on between the Defendant No. 2 and MCD regarding
some leakage issue in the project. Therefore till the time that
arbitration is not finished, the Bank Guarantee will be kept alive
by the Defendant No. 2.
51. That the Plaintiff states that the claim being put up by the
Defendant No. 2 is baseless and devoid of any merit insofar as
the Plaintiff is not responsible for any leakage that may or may
not have taken place at the project site. The plaintiff states that if
anyone is responsible for the leakage, if there is any, it is the
Defendant No. 2 itself.
52. The plaintiff further avers that it has no liability under the Work
Order to make good any deficiency in service.
53. That the Work order specifically provided that the defects
liability period under the same would be for a period of one
year from the completion of work and issue of final payment
certificate, i.e. 15.08.2011. Thus, the plaintiff is not liable for any
defects that may have taken place after 15.08.2011.
54. For all the defects, if any, which took place before 15.08.2011, the
Defendant No. 2 cannot claim any amount from the Plaintiff
since such a claim would be barred by laws of limitation.
56. That the Bank Guarantee, which was furnished by the Plaintiff
to the Defendant No. 2 clearly mentioned that the Defendant
No. 1 will pay an amount to the Defendant No. 2 merely on a
demand stating that there are recoveries due or likely to be due
from the Plaintiff. Since there is no liability on the part of the
Plaintiff, there can be no recoveries that are due or that may
likely to be due from the Plaintiff to the Defendant No. 2. In
such a case, the Defendant No. 1 is under no obligation to make
good any amount to the Defendant No. 2.
57. Thus, the request to extend the bank guarantee beyond the
present claim period till 15.09.2019, is completely unjustified
and falls foul of the settled principles of law.
59. That the Plaintiff states that till date, it has incurred a total
amount of Rs. 1,63,457/- towards Bank Charges after 15.08.2011,
i.e. after the time that the Plaintiff was under no contractual
obligation to extend the Bank Guarantee.
60. That apart from the Bank charges paid till now, the Plaintiff
states that it is also entitled to interest amount on these Bank
charges calculated at the rate of 18% per annum is Rs. 1,28,137/-
as per the general market/commercial practice.
61. That the cause of action arose on 16.11.2005 when the Work
Order was issued by the Defendant No. 2 to the Plaintiff,
24.12.2010 when the BG was given by the Defendant No. 1 to the
Defendant No. 2 at the instance of the Plaintiff, 08.09.2011,
09.03.2012, 14.03.2013, 09.09.2013, 10.03.2014, 04.03.2015,
14.09.2015, 05.03.2016, 06.09.2016, 06.09.2017, 04.09.2018 when
the Defendant No. 1 extended the expiry period of the Bank
Guarantee No. 205B215103580005 dated 24.12.2010 and then on
27.08.2019 when the Defendant No. 2 sent a letter to extend (or
encash) the expiry period of the Bank Guarantee No.
205B215103580005 dated 24.12.2010 and then on 05.09.2019
when the Defedant No. 2 reiterated its stand to renew the BG
and send us the our office by 10th of September 2019. Therefore
the present suit is under the limitation period of 3 years from
the date of last cause of action.
63. That for the purposes of jurisdiction and court fee, the suit is
being valued at Rs. 13, 53 ,204/- including the amount of Bank
Guarantee and charges incurred in keeping the Bank Guarantee
alive plus interest at 18% from 15.08.2011 until the date of filing
the present suit i.e. 06.09.2019 and court fee of __________ is
affixed thereon.
PRAYER
THROUGH COUNSEL
ABHINAY/UTSAV TRIVEDI/HIMANSHU
COUNSEL FOR THE PLAINTIFF
TAS LAW
P-2A, JANGPURA EXTENSION,
NEW DELHI – 110014
9205137094
PLACE: NEW DELHI
DATE: 06.09.2019
VERIFICATION:
PLAINTIFF
BEFORE THE LEARNED DISTRICT JUDGE, SAKET COURTS
AT NEW DELHI
CS(COMM.) No. ____ 2019
IN THE MATTER OF:
M/S CICO TECHNOLOGIES LIMITED …. PLAINTIFF
VERSUS
KOTAK MAHINDRA BANK LTD. AND ANR. …DEFENDANTS
AFFIDAVIT
DEPONENT
VERIFICATION:
Verified at New Delhi on this 6th Day of September, 2019 that the
contents of the above affidavit are true and correct, and no part of it is
false and nothing has been concealed therefrom.
DEPONENT
BEFORE THE LEARNED DISTRICT JUDGE, SAKET COURTS
AT NEW DELHI
CS(COMM.) No. ____ 2019
IN THE MATTER OF:
M/S CICO TECHNOLOGIES LIMITED …. PLAINTIFF
VERSUS
KOTAK MAHINDRA BANK LTD. AND ANR. …DEFENDANTS
STATEMENT OF TRUTH
DEPONENT
VERIFICATION:
Verified at New Delhi on this 6th day of September, 2019 that the
contents of my above affidavit are correct and true to the best of my
knowledge and belief and no part of it is false and nothing material has
been concealed there from.
DEPONENT
BEFORE THE LEARNED DISTRICT JUDGE, SAKET COURTS
AT NEW DELHI
VERSUS
Copy of the
Board Resolution
dated 02.09.2019
in favour of the
Authorised
Signatory
2. DOCUMENT -2 Both the Photocopy By hand Both the
Parties Parties
Copy of the work
order dated
16.11.2005 issued
by Defendant
No. 2 in favour of
the Plaintiff
3. DOCUMENT -3 Both the Photocopy Receipt Both the
parties parties
Copy of the Final
Payment
Certificate dated
24.11.2010 issued
by the Defendant
No. 2 in favour of
the Plaintiff
4. DOCUMENT -4 Both the Photocopy Receipt Defendant
Parties No. 2
Copy of the
original Bank
Guarantee
(replaced) dated
24.12.2010 issued
by the Defendant
No.1 in favour of
Defendant No.2
5. DOCUMENT -4 Both the Photocopy Receipt Both the
parties parties
Copy of the Final
Payment
Certificate dated
24.11.2010 issued
by the Defendant
No. 2 in favour of
the Plaintiff
6. DOCUMENT -5 Both the Photocopy Receipt Both the
parties Parties
Copy of the letter
dated 03.09.2011
issued by the
Defendant No. 2
to Defendant No.
1 seeking
extension of the
Bank Guarantee
7. DOCUMENT -6 Both the Photocopy Receipt Defendant
parties No. 2
Copy of the
extended Bank
Guarantee dated
08.09.2011 issued
by Defendant
No. 2 extending
the Bank
Guarantee
8. DOCUMENT -7 Both the Photocopy Receipt Both the
parties Parties
Copy of the letter
dated 01.03.2012
issued by the
Defendant No. 2
to Defendant No.
1 seeking
extension of the
Bank Guarantee
9. DOCUMENT -8 Both the Photocopy Receipt Defendant
parties No. 2
Copy of the
extended Bank
Guarantee dated
09.03.2012 issued
by Defendant
No. 2 extending
the Bank
Guarantee
10. DOCUMENT -9 Both the Photocopy Receipt Both the
parties Parties
Copy of the letter
dated 13.03.2013
issued by the
Defendant No. 2
to Defendant No.
1 seeking
extension of the
Bank Guarantee
11. DOCUMENT -10 Both the Photocopy Receipt Defendant
parties No. 2
Copy of the
extended Bank
Guarantee dated
14.03.2013 issued
by Defendant
No. 2 extending
the Bank
Guarantee
12. DOCUMENT -11 Both the Photocopy Receipt Both the
parties Parties
Copy of the letter
dated 03.09.2013
issued by the
Defendant No. 2
to Defendant No.
1 seeking
extension of the
Bank Guarantee
13. DOCUMENT -12 Both the Photocopy Receipt Defendant
parties No. 2
Copy of the
extended Bank
Guarantee dated
09.09.2013 issued
by Defendant
No. 2
14. DOCUMENT -13 Both the Photocopy Receipt Defendant
parties No. 2
Copy of the
Corporate
Guarantee dated
10.02.2014 issued
by the Plaintiff in
favour of
Defendant No. 2
15. DOCUMENT -13 Both the Photocopy Receipt Defendant
parties No. 2
Copy of the
extended Bank
Guarantee dated
10.03.2014 issued
by Defendant
No. 2
16. DOCUMENT -14 Both the Photocopy Receipt Both the
parties Parties
Copy of the letter
dated 27.02.2015
issued by the
Defendant No. 2
to Defendant No.
1 seeking
extension of the
Bank Guarantee
17. DOCUMENT -15 Both the Photocopy Receipt Defendant
parties No. 2
Copy of the
extended Bank
Guarantee dated
04.03.2015 issued
by Defendant
No. 2 extending
the Bank
Guarantee
18. DOCUMENT -16 Both the Photocopy Receipt Defendant
parties No. 2
Copy of the
extended Bank
Guarantee dated
14.09.2015 issued
by Defendant
No. 2 extending
the Bank
Guarantee
19. DOCUMENT -17 Both the Photocopy Receipt Both the
parties Parties
Copy of the letter
dated 03.03.2016
issued by the
Defendant No. 2
to Defendant No.
1 seeking
extension of the
Bank Guarantee
20. DOCUMENT -18 Both the Photocopy Receipt Defendant
parties No. 2
Copy of the
extended Bank
Guarantee dated
05.03.2016 issued
by Defendant
No. 2 extending
the Bank
Guarantee
21. DOCUMENT -19 Both the Photocopy Receipt Both the
parties Parties
Copy of the letter
dated 01.09.2016
issued by the
Defendant No. 2
to Defendant No.
1 seeking
extension of the
Bank Guarantee
22. DOCUMENT -20 Both the Photocopy Receipt Defendant
parties No. 2
Copy of the
extended Bank
Guarantee dated
06.09.2016 issued
by Defendant
No. 2 extending
the Bank
Guarantee
23. DOCUMENT -21 Both the Photocopy Receipt Both the
parties Parties
Copy of the letter
dated 31.08.2017
issued by the
Defendant No. 2
to Defendant No.
1 seeking
extension of the
Bank Guarantee
24. DOCUMENT -22 Both the Photocopy Receipt Defendant
parties No. 2
Copy of the
extended Bank
Guarantee dated
06.09.2017 issued
by Defendant
No. 2 extending
the Bank
Guarantee
25. DOCUMENT -23 Both the Photocopy Receipt Both the
parties Parties
Copy of the letter
dated 31.08.2018
issued by the
Defendant No. 2
to Defendant No.
1 seeking
extension of the
Bank Guarantee
26. DOCUMENT -24 Both the Photocopy Receipt Defendant
parties No. 2
Copy of the
extended Bank
Guarantee dated
04.09.2018 issued
by Defendant
No. 2 extending
the Bank
Guarantee
27. 2DOCUMENT -25 Both the Photocopy Receipt Both the
. parties Parties
Copy of the letter
dated 27.08.2019
issued by the
Defendant No. 2
to Defendant No.
1 seeking
extension of the
Bank Guarantee
3. DOCUMENT -25 Both the Photocopy Receipt Both the
PLAINTIFF
THROUGH COUNSEL
ABHINAY/UTSAV TRIVEDI/HIMANSHU
COUNSEL FOR THE PLAINTIFF
P-2A, JANGPURA EXTENSION,
NEW DELHI – 110014
9205137094
PLACE: NEW DELHI
DATE: 06.09.2019
BEFORE THE LEARNED DISTRICT JUDGE, SAKET COURTS
AT NEW DELHI
I.A. No. _____ of 2019
CS(Comm.) No. ____ 2019
IN THE MATTER OF:
M/S CICO TECHNOLOGIES LIMITED …. PLAINTIFF
VERSUS
KOTAK MAHINDRA BANK LTD. AND ANR. …DEFENDANTS
The Plaintiff abovenamed
1. That the Plaintiff herein, i.e. CICO Technologies Ltd. has filed the
accompanying suit for Injunction, Declaration and Recovery of Dues
amounting to Rs. 2,91,594/- along with interest at the rate of 18% per
annum.
2. That the Plaintiff craves liberty of this Ld. Court to refer to and rely
upon the facts and averments made in the plaint and the same are
not repeated herein for the sake of brevity, unless so required.
3. That under the Work Order, Plaintiff’s scope of work consisted only
of the following:
7. That as per the terms of the Work Order, the defects liability period
was for a period of one year from the completion of work and issue
of final payment certificate.
8. That since the final payment certificate was issued on 15.08.2010, the
defects liability period stood lapsed on 15.08.2011, i.e. one year after
the issuance of the defects liability period.
10. That in response to the letter dated 04.09.2019, the Defendant No. 2,
vide its email dated 05.09.2019 at 15:08 hours has stated as under:
13. For all the defects, if any, which took place before 15.08.2011, the
Defendant No. 2 cannot claim any amount from the Plaintiff since
such a claim would be barred by laws of limitation.
14. The Plaintiff further avers that neither is it under any contractual
liability to make good any deficiency in service nor such a request
has ever been made by the Defendant No. 2.
15. That the Bank Guarantee, which was furnished by the Plaintiff to the
Defendant No. 2 clearly mentioned that the Defendant No. 1 will pay
an amount to the Defendant No. 2 merely on a demand stating that
there are recoveries due or likely to be due from the Plaintiff. Since
there is no liability on the part of the Plaintiff, there can be no
recoveries that are due or that may likely to be due from the Plaintiff
to the Defendant No. 2. In such a case, the Defendant No. 1 is under
no obligation to make good any amount to the Defendant No. 2.
BALANCE OF CONVENIENCE
18. This amount of Rs. 7,82,635 will be retained by the Defendant No. 2
till 15.09.2021, i.e. ten years from the date of expiry of maintenance
period under the agreement, which is 15.09.2011.
19. That the Plaintiff has also furnished a Guarantee Bond dated
10.02.2014 as per the terms of the Work Order. The relevant Clause is
extracted hereunder for ready reference:
20. This Guarantee Bond is valid for a period of ten years, i.e. 10.02.2024.
21. That in response to the letter dated 04.09.2019, the Defendant No. 2,
vide its email dated 05.09.2019 at 15:08 hours has stated as under:
22. That the Defendant No. 2 has a security deposit of Rs. 7,82,635 and
also a guarantee bond valid till 10.02.2024. Thus, the above concern is
also addressed.
23. That the ground that an Arbitration is pending between MCD and
the Defendant No. 2 can also not be invoked to extend the bank
guarantee since the Plaintiff is neither a party to such an Arbitration,
nor has it ever been produced any orders/pleadings, etc. with
respect to this alleged Arbitration. Therefore, there is no reason that
the Plaintiff should extend the bank guarantee beyond the present
claim period and bear additional charges.
24. That the Plaintiff states that till date, it has incurred a total amount of
Rs. 1,63,457/- towards Bank Charges after 15.08.2011, i.e. after the
time that the Plaintiff was under no contractual obligation to extend
the Bank Guarantee.
25. The Plaintiff has done the present Contract on a very low profit
margin. If the plaintiff is forced to continue paying charges, specially
when it is not liable and the Defendant No. 2 is well protected, the
profit margin will come even lower.
26. Apart from the above, the Plaintiff is also exposed to an amount of
Rs. 10,61,610/- which it is under no responsibility to pay. If the
injunction is not granted, the Defendant No. 1 will remit the amount
of Bank Guarantee to the Defendant No. 2.
27. Once the amount is remitted to the Defendant No. 1, the Plaintiff will
have to undergo another round of litigation for getting refund of the
amount that should never have been released to the Defendant No. 2.
PRAYER
28. In the aforesaid premises, the Plaintiff most respectfully prays that
this Hon’ble Court may be pleased to:
PLAINTIFF
THROUGH COUNSEL
ABHINAY/UTSAV TRIVEDI/HIMANSHU
COUNSEL FOR THE PLAINTIFF
P-2A, JANGPURA EXTENSION,
NEW DELHI – 110014
9205137094
PLACE: NEW DELHI
DATE: 06.09.2019
BEFORE THE LEARNED DISTRICT JUDGE, SAKET COURTS
AT NEW DELHI
I.A. No. _____ of 2019
CS(Comm.) No. ____ 2019
IN THE MATTER OF:
M/S CICO TECHNOLOGIES LIMITED …. PLAINTIFF
VERSUS
KOTAK MAHINDRA BANK LTD. AND ANR. …DEFENDANTS
AFFIDAVIT
DEPONENT
VERIFICATION:
Verified at New Delhi on this 6th Day of September, 2019 that the
contents of the above affidavit are true and correct, and no part of it is
false and nothing has been concealed therefrom.
DEPONENT