Sie sind auf Seite 1von 8

.

NDT examination shall be conducted for a

axadasdfjsaofns
dskdsiaidfmsa
 PIPE SUPPORT DRAWINGS

Dsfdjfiajrfs
Samufsna
rwamirsa

1. Scope of work for Prefab Contractor


The main scope of work for the CONTRACTOR is as follows:

Spools shall undergo surface preparation before

fhfd Complete Piping Fabrication, Pressure and NDT testing, Cleaning and Painting
CONTRACTOR shall fabricate piping spools in accordance with the attached
piping isometric drawings. Piping shall be 100% prefabricated, there shall be no
field welds.
CLIENT shall free issue the pipe, fittings and flanges to the CONTRACTOR
CONTRACTOR to supply remaining materials to complete the work
(consumables, hydro test materials - plugs, gaskets, stud bolts etc)
Pressure testing by water shall be conducted for all spools.

Ngvngjtdjgmncvmgjg
Fskfaifmns
fsmaifmsa
Complete Piping Fabrication, Pressure and NDT testing, Cleaning and Painting
CONTRACTOR shall fabricate piping spools in accordance with the attached
piping isometric drawings. Piping shall be 100% prefabricated, there shall be no
field welds.fsfasfnjfz
CLIENT shall free issue the pipe, fittings and flanges to the CONTRACTOR
of spools

Trial Assembly of all spool and supports for dimensional verification


As part of the final inspection, a trial fit-up and thorough dimensional verification
shall be conducted by the CONTRACTOR with the assistance of a qualified
surveyor and witnessed by the CLIENT as part of the acceptance criteria.
Temporary supports shall be used during the trial fit-up

Fegdhfffhdfdf helloe
 Liquid Penetrant – 10% of all fillet welds, plus one weld from each heat
Piping spools shall be cleaned by acid cleaning process before sealing the spools
for transport.
CONTRACTOR to supply remaining materials to complete the work
(consumables, hydro test materials - plugs, gaskets, stud bolts etc)
Pressure testing by water shall be conducted for all spools.
NDT examination shall be conducted for a percentage
sfsamfkosamfksafa

free from dirt, dust or grease before painting.


fhfdhfdhfdd
2. adajdiasnfjwrw The associated requirements (ie QAQC, Fabrication requirements and
documentation etc) to complete this scope of work are described in more detail in the
attached specif ocumentation
QAQC

 ITP
 WPS
 PQR
 Equipment & Material (Consumables & Paint) Test Certs
 Brief Description of Project
The Fuel Gas Tree Project is being implemented to improve control and stabilize
the fuel gas supply pressures to the CAT engine generators on the
This involves the replacement of the existing fuel supply lines to each generator
to include a larger fuel filter housing and additional instrumentation and valves.
 painting. Spools shall be SPECIFICATION FOR PREFABRICATION, TESTING, CLEANING
AND PAINTING OF PIPING SPOOLS AND PIPING SUPPORTSdffdsfgmkeotjdskge
 ISOMETRIC DRAWINGS PACKAGE
 Visual Inspection – 100%
 Radiography – 10%, as per specification
 Liquid Penetrant – 10% of all fillet welds, plus one weld from each heat
 Final Inspection Procedure and Close-Out Report
ication. Packing for transport to protect against damage to paintwork.
CONTRACTOR shall be responsible for the proper packing of the finished spools
and pipe supports for transport to site.
CONTRACTOR shall be responsible for any damages caused due to improper
packing.
Pipe ends, flanges, threaded ends (male and female) shall be adequately
covered to protect against ingress of material after cleaning and transport.
Fsafsm,akfmskafsfxz

. Pipe Support Material Supply, Fabrication, Testing and Cleaning and Painting
CONTRACTOR shall supply the pipe support materials based on the
requirements from the attached piping support drawings.
CONTRACTOR shall fabricate the pipe supports in accordance with the attached
specification (AFE361318-ENG-PIP-SPC-0001-R0)
Pipe supports shall be supplied with loose shimming plates for shimming on site.
Pipe supports shall be attached to existing structures by bolting
percentage of spools
 Visual Inspection – 100%
 Radiography – 10%, as per specification
Piping spools shall be cleaned by acid cleaning process before sealing the spools
for transport.
Spools shall undergo surface preparation before painting. Spools shall be free
from dirt, dust or grease before painting.
 Fit-up / Welding Certs
 NDT / Hydro Certs
 Cleaning / Painting Certs
Fawfsiafjawkfwmn,fasf
CONTRACTOR shall not use chain blocks / lifting hooks to support the piping to
avoid damage to the finished paintwork
Engineering

 Marked up Fabrication Isometrics (Weld No’s, Spool IDs, Heat Nos etc)
Project Management / Planning

 Fabrication Schedule
 Weekly Progress Reports (including, but not limited to: % Complete, Photos,
Schedule)

3. Attachments
pleasnfswiabnfjnfunafsbfaifbuwafrwaf

Trial Assembly of all spool and supports for dimensional verification


As part of the final inspection, a trial fit-up and thorough dimensional verification
shall be conducted by the CONTRACTOR with the assistance of a qualified
surveyor and witnessed by the CLIENT as part of the acceptance criteria.
Temporary supports shall be used during the trial fit-up
Engineering

 Marked up Fabrication Isometrics (Weld No’s, Spool IDs, Heat Nos etc)
Project Management / Planning

 Fabrication Schedule
 Weekly Progress Reports (including, but not limited to: % Complete, Photos,
Schedule)

NDT examination shall be conducted for a

Ngvngjtdjgmncvmgjg
Fskfaifmns
fsmaifmsa
axadasdfjsaofns
dskdsiaidfmsa
 PIPE SUPPORT DRAWINGS
Complete Piping Fabrication, Pressure and NDT testing, Cleaning and Painting
CONTRACTOR shall fabricate piping spools in accordance with the attached
piping isometric drawings. Piping shall be 100% prefabricated, there shall be no
field welds.
CLIENT shall free issue the pipe, fittings and flanges to the CONTRACTOR
CONTRACTOR to supply remaining materials to complete the work
(consumables, hydro test materials - plugs, gaskets, stud bolts etc)
Pressure testing by water shall be conducted for all spools.
NDT examination shall be conducted for a percentage of spools
Dsfdjfiajrfs
Samufsna
rwamirsa

4. Scope of work for Prefab Contractor


The main scope of work for the CONTRACTOR is as follows:

Spools shall undergo surface preparation before

fhfd Complete Piping Fabrication, Pressure and NDT testing, Cleaning and Painting
CONTRACTOR shall fabricate piping spools in accordance with the attached
piping isometric drawings. Piping shall be 100% prefabricated, there shall be no
field welds.
CLIENT shall free issue the pipe, fittings and flanges to the CONTRACTOR
CONTRACTOR to supply remaining materials to complete the work
(consumables, hydro test materials - plugs, gaskets, stud bolts etc)
Pressure testing by water shall be conducted for all spools.
fegdhfffhdfdf
 Liquid Penetrant – 10% of all fillet welds, plus one weld from each heat
Piping spools shall be cleaned by acid cleaning process before sealing the spools
for transport.

sfsamfkosamfksafa

5. Brief Description of Project


The Fuel Gas Tree Project is being implemented to improve control and stabilize
the fuel gas supply pressures to the CAT engine generators on the
This involves the replacement of the existing fuel supply lines to each generator
to include a larger fuel filter housing and additional instrumentation and valves.
painting. Spools shall be free from dirt, dust or grease before painting.
fhfdhfdhfdd
6. adajdiasnfjwrw The associated requirements (ie QAQC, Fabrication requirements and
documentation etc) to complete this scope of work are described in more detail in the
attached specif ocumentation
QAQC Fsafsm,akfmskafsfxz
scsafsfasfxzf
. Pipe Support Material Supply, Fabrication, Testing and Cleaning and Painting
CONTRACTOR shall supply the pipe support materials based on the
requirements from the attached piping support drawings.

 ITP
 WPS
 PQR
 Equipment & Material (Consumables & Paint) Test Certs

 SPECIFICATION FOR PREFABRICATION, TESTING, CLEANING AND PAINTING OF PIPING


SPOOLS AND PIPING SUPPORTSdffdsfgmkeotjdskge
 ISOMETRIC DRAWINGS PACKAGE
 Visual Inspection – 100%
 Radiography – 10%, as per specification
 Liquid Penetrant – 10% of all fillet welds, plus one weld from each heat
 Final Inspection Procedure and Close-Out Report
ication. Packing for transport to protect against damage to paintwork.
CONTRACTOR shall be responsible for the proper packing of the finished spools
and pipe supports for transport to site.
CONTRACTOR shall be responsible for any damages caused due to improper
packing.
Pipe ends, flanges, threaded ends (male and female) shall be adequately
covered to protect against ingress of material after cleaning and transport.
CONTRACTOR shall fabricate the pipe supports in accordance with the attached
specification (AFE361318-ENG-PIP-SPC-0001-R0)
Pipe supports shall be supplied with loose shimming plates for shimming on site.
Pipe supports shall be attached to existing structures by bolting
percentage of spools
 Visual Inspection – 100%
CONTRACTOR shall not use chain blocks / lifting hooks to support the piping to
avoid damage to the finished paintwork
Engineering

 Marked up Fabrication Isometrics (Weld No’s, Spool IDs, Heat Nos etc)
Project Management / Planning

 Fabrication Schedule
 Weekly Progress Reports (including, but not limited to: % Complete, Photos,
Schedule)

7. Attachments
pleasnfswiabnfjnfunafsbfaifbuwafrwaf

 Radiography – 10%, as per specification


Piping spools shall be cleaned by acid cleaning process before sealing the spools
for transport.
Spools shall undergo surface preparation before painting. Spools shall be free
from dirt, dust or grease before painting.
 Fit-up / Welding Certs
 NDT / Hydro Certs
 Cleaning / Painting Certs
Fawfsiafjawkfwmn,fasf

D
D
Pipe Support Material Supply, Fabrication, Testing and Cleaning and Painting
CONTRACTOR shall supply the pipe support materials based on the
requirements from the attached piping support drawings.
CONTRACTOR shall fabricate the pipe supports in accordance with the attached
specification (AFE361318-ENG-PIP-SPC-0001-R0)
Pipe supports shall be supplied with loose shimming plates for shimming on site.
Pipe supports shall be attached to existing structures by bolting.

8.

Das könnte Ihnen auch gefallen