Sie sind auf Seite 1von 9

EARTHWORKS

I. Actual Volume
Vactual = ( 33 x 18 ) ( 0.35 ) = 207.9 m³
II. Volume of Excavation
Volume of Footing 1 = 28.67 m³
Volume of Footing 2 = 8.06 m³
Volume of Column 1 Partial = 12. 032 m³
Volume of Column 2 Partial = 3.384 m³

Vexc = 28.67 + 12.032 + 1.89 = 42.592 m³


Vexc = 8.06 + 3.384 + 1.89 = 13.334 m³
= 55.926 m³
III. Volume Required
Note: Additional 20% for compaction

Vreq = ( 207.9 - 55.926 ) ( 2.4 )= 364.7376 m³

CONCRETE WORKS
I. Footing
Volume of Footing 1 = 28.67 m³
Volume of Footing 2 = 8.06 m³
Total Volume = 36.736 m³
Using Class AA (1 : 1 1/2 : 3) (40 kgs Bag of Cement)
Cement = 36.736 x 12 = 441 Bags
Sand = 36.736 x 0.5 = 18.368 m³
Gravel = 36.736 x 1 = 36.736 m³

II. Footing Tie Beam


FTB1 = 14.7
FTB2 = 10.44
Total Volume = 25.14 m³
Using Class AA (1 : 1 1/2 : 3) (40 kgs Bag of Cement)
Cement = 25.14 x 12 = 302 Bags
Sand = 25.14 x 0.5 = 12.57 m³
Gravel = 25.14 x 1 = 25.14 m³

III. Column
Vc1 = 93.184
Vc2 = 26.208
Total Volume = 119.392 m³
Using Class AA (1 : 1 1/2 : 3) (40 kgs Bag of Cement)
Cement = 119.392 x 12 = 1433 Bags
Sand = 119.392 x 0.5 = 59.696 m³
Gravel = 119.392 x 1 = 119.392 m³

IV. Beam
FB1 = 36.72
FB2 = 41.76
FB3 = 1.6384
Total Volume = 80.1184 m³
Using Class AA (1 : 1 1/2 : 3) (40 kgs Bag of Cement)
Cement = 80.1184 x 12 = 961 Bags
Sand = 80.1184 x 0.5 = 40.0592 m³
Gravel = 80.1184 x 1 = 80.1184 m³

V. Slab
Slab on Fill Total = 89.1
Cement = 89.1 x 12 = 1069 Bags
Sand = 89.1 x 0.5 = 44.55 m³
Gravel = 89.1 x 1 = 89.1 m³

Suspended Slab Total = 276.4


Cement = 276.4 x 12 = 3317 Bags
Sand = 276.4 x 0.5 = 138.2 m³
Gravel = 276.4 x 1 = 276.4 m³

MASONRY WORK
I. First Floor
a. Exterior Wall

No. oh CHB = ( 102 )( 4.3 ) - ( 142.4 )= 296.2

( 296.2 ) ( 12.5 )= 3703 Pcs of 6" CHB


b. Interior Wall
No. oh CHB = ( 132 )( 4.3 ) - ( 59.64 )= 507.96

( 507.96 ) ( 12.5 )= 6350 Pcs of 6" CHB

II. Second Floor


a. Exterior Wall

No. oh CHB = ( 102 )( 4.3 ) - ( 135.75 )= 302.85

( 302.85 ) ( 12.5 )= 3786 Pcs of 6" CHB


b. Interior Wall
No. oh CHB = ( 108 )( 4.3 ) - ( 45.36 )= 419.04

( 419.04 ) ( 12.5 )= 5238 Pcs of 6" CHB

III. Third Floor


a. Exterior Wall

No. oh CHB = ( 102 )( 3.3 ) - ( 117.89 )= 218.71

( 218.71 ) ( 12.5 )= 2734 Pcs of 6" CHB


b. Interior Wall
No. oh CHB = ( 178.5 )( 3.3 ) - ( 32.13 )= 556.92
( 556.92 ) ( 12.5 )= 6962 Pcs of 6" CHB

IV. Fourth Floor


a. Exterior Wall

No. oh CHB = ( 102 )( 3.3 ) - ( 117.89 )= 218.71

( 218.71 ) ( 12.5 )= 2734 Pcs of 6" CHB


b. Interior Wall
No. oh CHB = ( 178.5 )( 3.3 ) - ( 32.13 )= 556.92

( 556.92 ) ( 12.5 )= 6962 Pcs of 6" CHB

IV. Roof Deck


a. Exterior Wall

No. oh CHB = ( 80 )( 1.2 ) = 96

( 96 ) ( 12.5 )= 1200 Pcs of 6" CHB


b. Interior Wall
No. oh CHB = ( 52 )( 2.7 ) - ( 5.04 )= 135.36

( 135.36 ) ( 12.5 )= 1692 Pcs of 6" CHB

STEEL REINFORCEMENT (COLUMN AND TIES)


I. Total Length of Bar
a. Footing
T.L. F1 = 32 [( 12 )( 1.6 )+ ( 12 )( 1.6 )] = 1228.8
T.L. F2 = 16 [( 8 )( 1.2 )+ ( 8 )( 1.2 )] = 307.2
= 1536
Pcs. Of Bars = 1536 / 6= 256 Pcs. Of 16 mm diameter x 6 m for footing

b. Footing Tie Beam


T.L. FTB 1 = ( 168 )( 6 )( 1.1 )= 1108.8

Pcs. Of Bars = 1108.8 / 6 = 184.8 Pcs. Of 16 mm diameter x 6 m for footing

T.L. FTB 2 = ( 174 )( 6 )( 1.1 )= 1148.4

Pcs. Of Bars = 1148.4 / 6 = 191.4 Pcs. Of 16 mm diameter x 6 m for footing

c. Column
Total Length of Vertical Bar
C1 = 32 ( 6 )( 20.85 )= 4002.2 m
C1 (Roof Deck) = 8( 6 )( 45.3 ) = 2174.4

C2 = 16 ( 6 )( 20.85 )= 2001.1 m
C2 (Roof Deck) = 7( 6 )( 15.9 ) = 667.8
Ties
a. No. of Ties for Column
No. of Ties C1 = ( 63.85 ) / ( 0.2 )= 319 Pcs / column
No. of Ties C2 = ( 79.75 ) / ( 0.2 )= 399 Pcs / column
b. Length of Ties
L.T. C1 = 2( 0.4 ) + 2( 0.4 ) = 1.6 m
L.T. C2 = 2( 0.3 ) + 2( 0.3 ) = 1.2 m

c. T.L. Ties
T.L. C1 = 32 ( 319.25 ) ( 1.6 )= 16345.6 m
T.L. C1 = 16 ( 398.75 ) ( 1.2 )= 7656 m
= 24001.6 m
d. Pcs of Bar
Pcs. Of Bar = ( 24001.6 )/ ( 6 )= 4000.27
Say 40001 pcs of 16 mm diameter x6 m for ties

STEEL REINFORCEMENT (BEAM)


I. Total Length (T.L.)
a. Second Floor to Roof Deck Note: 10% Splice
T.L. B1 = 102 ( 12 )( 1.1 )= 1346.4 m
T.L. B1 = 174 ( 12 )( 1.1 )= 2296.8 m
T.L. B3 = 8( 10 )( 1.1 )= 88 m
Pcs of Bar
B1 = 1346.4 / 6 = 224.4 Pcs of 16 mm diameter x 6 m for top and bottom bar
B2 = 2296.8 / 6 = 382.8 Pcs of 16 mm diameter x 6 m for top and bottom bar
B2 = 88 / 6 = 15 Pcs of 16 mm diameter x 6 m for top and bottom bar
Typical to Roof Deck
B1 = 224.4 ( 4 )= 897.6 Pcs of 16 mm diameter x 6 m for top and bottom bar
B2 = 382.8 ( 4 )= 1531 Pcs of 16 mm diameter x 6 m for top and bottom bar
B3 = 15 ( 4 )= 59 Pcs of 16 mm diameter x 6 m for top and bottom bar

II. Stirrups
B1 = 102 / 0.13 = 784.6 Pcs.
B2 = 174 / 0.13 = 1338 Pcs.
B3 = 8/ 0.13 = 62 Pcs.

Length of Stirrups
PB1 = 2( 0.2 )+ 2 ( 0.45 )= 1.3 m
PB2 = 2( 0.2 )+ 2 ( 0.3 )= 1m
PB3 = 2( 0.2 )+ 2 ( 0.4 )= 1.2 m

T.L. B1= 785 ( 1.3 ) = 1020 m


T.L. B2= 1338 ( 1 ) = 1338 m
T.L. B3= 62 ( 1.2 ) = 73.85 m

Pcs. Of Bar
B1 = 785 / 6 = 130.8 Pcs of 16 mm diameter x 6 m for Stirrups
B2 = 1338 / 6 = 223.1 Pcs of 16 mm diameter x 6 m for Stirrups
B3 = 62 / 6 = 11 Pcs of 16 mm diameter x 6 m for Stirrups
STEEL REINFORCEMENT (CHB and SLAB)
I. Slab on Fill
a. Along Short Distance
S1 No. of bars = 33 / 0.4 = 82.5 Pcs
Total Length = 82.5 ( 18 )( 1.15 )= 1707.75 m

Pcs of Bar= 1707.8 / 6= 285


b. Along Long Distance Pcs of 12 mm diameter x 6 for short distance
S1 No. of bars = 18 / 0.4 = 45 Pcs
Total Length = 45 ( 33 )( 1.15 )= 1707.75 m

Pcs of Bar= 1707.8 / 6= 285


Pcs of 12 mm diameter x 6 for short distance
II. Suspended Slab
a. Along Short Distance
S1 No. of bars = 33 / 0.4 = 82.5 Pcs
Total Length = 82.5 ( 11 )( 1.15 )= 1043.625 m

Pcs of Bar= 1043.6 / 6= 174 Pcs of 12 mmØ x 6 for short distance


Typical to Roofdeck = 174 x 4= 695.75 pcs
S2 No. of bars = 25 / 0.4 = 62.5 Pcs
Total Length = 62.5 ( 7 )( 1.15 )= 503.125 m

Pcs of Bar= 503.13 / 6= 84 Pcs of 12 mm Ø x 6 for short distance


Typical to Roofdeck = 84 x 4= 335.42 pcs
S3 No. of bars = 8/ 0.4 = 20 Pcs
Total Length = 20 ( 2 )( 1.15 )= 46 m

Pcs of Bar= 46 / 6= 8 Pcs of 12 mmØ x 6 for short distance


Typical to Roofdeck = 8x 4= 30.667 pcs
b. Along Long Distance
S1 No. of bars = 11 / 0.4 = 27.5 Pcs
Total Length = 27.5 ( 33 )( 1.15 )= 1043.625 m

Pcs of Bar= 1043.6 / 6= 174 Pcs of 12 mm Øx 6 for short distance


Typical to Roofdeck = 174 x 4= 695.75 pcs
S2 No. of bars = 7/ 0.4 = 17.5 Pcs
Total Length = 17.5 ( 25 )( 1.15 )= 503.125 m

Pcs of Bar= 503.13 / 6= 84 Pcs of 12 mm Ø x 6 for short distance


Typical to Roofdeck = 84 x 4= 335.42 pcs
S3 No. of bars = 2/ 0.4 = 5 Pcs
Total Length = 5( 8 )( 1.15 )= 46 m

Pcs of Bar= 46 / 6= 8 Pcs of 12 mm Ø x 6 for short distance


Typical to Roofdeck = 8x 4= 30.667 pcs
CHB Vertical Bar
I. First Floor
P= 226
No. Of bars = 226 / 0.6 = 376.67 Pcs
Length of bar = 6x 1.1 = 6.6 m
Total Length = 376.67 x 6.6 = 2486 m
Pcs. Of bar = 2486 / 6 = 415 pcs of 12mm diameter x 6 m V.B for CHB

II. Second Floor


P= 210
No. Of bars = 210 / 0.6 = 350 Pcs
Length of bar = 4.3 x 1.1 = 4.73 m
Total Length = 350 x 4.73 = 1655.5 m
Pcs. Of bar = 1655.5 / 6 = 276 pcs of 12mm diameter x 6 m V.B for CHB

III. Typical Third to Fourth Floor


P= 280.5
No. Of bars = 280.5 / 0.6 = 467.5 Pcs
Length of bar = 3.3 x 1.1 = 3.63 m
Total Length = 467.5 x 3.63 = 1697 m
Pcs. Of bar = 1697 / 6 = 283 x 2= 565.68
1029 pcs of 12mm diameter x 6 m V.B for CHB
IV. Roof Deck
P= 102
No. Of bars = 102 / 0.6 = 170 Pcs
Length of bar = 1.2 x 1.1 = 1.32 m
Total Length = 170 x 1.32 = 224.4 m
Pcs. Of bar = 224.4 / 6 = 37 pcs of 12mm diameter x 6 m V.B for CHB

P= 33.4
No. Of bars = 33.4 / 0.6 = 55.667 Pcs
Length of bar = 2.7 x 1.1 = 2.97 m
Total Length = 55.667 x 2.97 = 165.33 m
Pcs. Of bar = 165.33 / 6 = 28 pcs of 12mm diameter x 6 m V.B for CHB

CHB Horizontal Bar


I. First Floor H= 6
No. Of bars = 6 / 0.6 = 10 Pcs
Length of bar = 226 x 1.1 = 248.6 m
Total Length = 10 x 248.6 = 2486 m
Pcs. Of bar = 2486 / 6 = 415 pcs of 12mm diameter x 6 m V.B for CHB

II. Second Floor H = 4.3


No. Of bars = 4.3 / 0.6 = 7.1667 Pcs
Length of bar = 210 x 1.1 = 231 m
Total Length = 7.1667 x 231 = 1655.5 m
Pcs. Of bar = 1655.5 / 6 = 276 pcs of 12mm diameter x 6 m V.B for CHB
III. Typical Third to Fourth Floor H = 3.3
No. Of bars = 3.3 / 0.6 = 5.5 Pcs
Length of bar = 280.5 x 1.1 = 308.55 m
Total Length = 5.5 x 308.6 = 1697 m
Pcs. Of bar = 1697 / 6 = 283 x 2= 565.68
1029 pcs of 12mm diameter x 6 m V.B for CHB

IV. Roof Deck H= 1.2 , 2.7


No. Of bars = 1.2 / 0.6 = 2 Pcs
Length of bar = 102 x 1.1 = 112.2 m
Total Length = 2x 112.2 = 224.4 m
Pcs. Of bar = 224.4 / 6 = 37 pcs of 12mm diameter x 6 m V.B for CHB

No. Of bars = 2.7 / 0.6 = 4.5 Pcs


Length of bar = 33.4 x 1.1 = 36.74 m
Total Length = 4.5 x 36.74 = 165.33 m
Pcs. Of bar = 165.33 / 6 = 28 pcs of 12mm diameter x 6 m V.B for CHB

FORMS AND SCAFFOLDING


Second to Roof Deck
No. of Plywood = 594 / 2.88 = 206.25
207 pcs 1/2 x 4 x 8 Marine Plywood
Frame 2" x 3"
S.F. = 12" = .30
S= 1.2 / 0.3 = 4 pcs 2 x 3 x 12
= 207 ( 4 )= 828 pcs 2 x 3 x 12
VOLUME OF CONCRETE
I. Footing
F1 = 32 ( 1.6 x 1.6 x 0.35 ) = 28.672 m³
F2 = 16 ( 1.2 x 1.2 x 0.35 ) = 8.064 m³
= 36.736 m³
II. Footing Tie Beam
FTB1 = 168 ( 0.25 x 0.35 ) = 14.7 m³
FTB2 = 174 ( 0.2 x 0.3 ) = 10.44 m³
= 25.14 m³
III. Column
Vc1 = 32 ( 18.2 x 0.4 x 0.4 ) = 93.184 m³
Vc2 = 16 ( 18.2 x 0.3 x 0.3 ) = 26.208 m³
= 119.392 m³
IV. Beam
FB1 = 2 ( 33 ) ( 0.2 ) ( 0.45 ) = 5.94 m³
FB1 = 2 ( 18 ) ( 0.2 ) ( 0.45 ) = 3.24 m³
= 9.18 ( 4 ) = 36.72 m³
FB2 = 6 ( 18 ) ( 0.2 ) ( 0.3 ) = 6.48
FB2 = 2 ( 33 ) ( 0.2 ) ( 0.3 ) = 3.96
= 10.44 ( 4 ) = 41.76 m³
FB3 = 2 ( 4 ) ( 0.2 ) ( 0.4 ) = 0.64 ( 4 ) = 1.6384 m³
= 80.1184 m³

V. Slab
Slab on Fill = 33 x 18 x 0.15 = 89.1 m³
Suspended = 33 x 18 x 0.15 - 20 = 69.1 m³
Typical to Roof Deck = 69.1 x 4= 276 m³