Mencari Dimensi Balok
Mencari Dimensi Balok
NIM : 5160811314
Lx = 3750 mm
= 3.75 m
TEBAL PLAT
Berdasarkan SNI 2847:2013 tergolong komponen struktur plat
satu arah dengan tumpuan sederhana.
hmin = 182.143 mm
hpakai = 25 cm
PEMBEBANAN UNTUK BALOK
QDL 19.53
QLL 1.8375
COMB 1 = 1,4.DL
= 27.342 kN/m
COMB 2 = 1,2.DL + 1,6L.L + 0,5.R1
= 26.376 kN/m
QU = 26.376 kN/m diambil nilai yang terbesar
123.638 61.819
Mu¯
46.158 kN
= 1/2×𝑄𝑢×�
=Mu-/L
16.485
+
Vu +
46.158 kN
Vu+
123.638
Mu¯
Mu⁺
46.158 kN
16.485 kN
Vu-
46.158 kN
DAERAH TUMPUAN
A. Tulangan Tumpuan
RASIO TULANGAN
(0.85*β*f'c/f'y)*(600/(600+f'y)
ϼb = 0.0325125
0.75*ϼb
ϼ maks = 0.024384375
0.5*ϼb
ϼ= 0.01625625
f'y/(0.85*f'c)
m= 15.6862745098
GAYA PERLAWANAN
( ϼ*f'y*(1-(0.5* ϼ*m)))
R₁ = 5.67343125
MOMEN NOMIAL
(Mu-/0.8)*1000000
Mn = 154546875
Mn/R1
bd² = 27240459.6424783
D PERLU
(bd²/b)^0.5
d perlu = 330.093682
selimut tulangan+10+(0.5*d tul)
ds = 62.5
selimut tulangan+10+(0.5*d tul)
d' = 62.5
d perlu+ds
h perlu = 392.593682
min(d perlu, h)
h pakai = 500
TINGGI EFEKTIF
h pakai-ds
d desak = 437.5
h pakai-d'
d tarik = 438
B. Tulangan Desak
KONTROL PERENCANAAN
(Σc *Es*d desak)/(Σc *Es)+(f'y)
Cb = 837.5
0.75*β*Cb
a maks = 533.906250
154546875 =
154546875 =
48485.2941 =
0 =
((-I45)-((I45^2)-(4*K45*F45))^0.5)/2*K45)
a₁ = 815.5488802818
a₂ = 59.4511197182
min(a1,a2)
a pakai = 59.4511197182
OK
GAYA PERLAWANAN
0.5*R1
R₂ = 2.836715625
R2*B*d desak^2
m₁ = 135741275.024414
Mn-m1
m₂ = 18805599.9755859
TULANGAN TEKAN 1
C. Tulangan Tarik
LUAS TULANGAN TARIK
0.5* ϼ
ϼb = 0.008128125
(ϼb*b*d tarik)+As'
As = 1014.3843383789
JUMLAH TULANGAN
As/As' d tul
n= 2.0675349572
n pakai = 3
n pakai*As'd tul
As ada = 1471.875
OK
TULANGAN TARIK 3
DATA MATERIAL
f'c = 30 Mpa
f'y ulir = 400 MPa
f'y polos = 240 Mpa
ß= 0.85
Σc = 0.003
Es = 200000
Pb = 40
Sb = 25
Ɣ= 0.5
d tul = 25 mm
d tul susut = 10 mm
d tul sengkang = 10 mm
s= 300 mm
Mpa
Nmm
mm
mm
mm
mm
mm
mm
mm
mm
mm
mm
6375 a x
2789062.5 a - 3187.5 a²
875 a - 1 a²
-48485.2941 + 875 a -1 a²
mm
mm
mm
Mpa
Nmm
Nmm
mm²
mm²
buah
buah
mm²
D 25
mm²
buah
mm²
D 25
Kontrol Momen Tersedia (Mg-)
As' ada = 490.6 mm²
As ada = 1471.875 mm²
As'ada*Σc*Es
Cs = 294375 (c - 62,5)/c
0.85*f'c*b*ß
Cc= 5418.75 c
As ada*f'y
Ts = 588750
5418.75 c +
5418.75 c² +
5418.75 c² +
1 c² +
c₁ = 91.4521092632 mm
c₂ = -37.1268497477 mm
max(c1:c2)
c pakai = 91.4521092632 mm
0.85*c pakai
a= 77.7342928738 mm
(c pakai-d')/c pakai)*Σc*Es
fs' = 189.9493155258 Mpa
(0.85*f'c*a*b*(d desak-(a/2)))+(As'ada*fs'*(d desak-d'))
Mg- = 232492655 MPa
0.8*Mg-
0,8Mg- = 185.994124 MPa
OK
Kontrol Rasio
As'ada/(b*d desak)
ϼ' ada = 0.0044857143
As ada/(b*d tarik)
ϼ ada = 0.0134571429
ϼ ada -ϼ' ada
∆ϼ = 0.0089714286
OK
5418.75 c +
5418.75 c² +
5418.75 c² +
1 c² +
c₁ = 49.9144888707 mm
c₂ = -68.0229087093 mm
max(D55:D56)
c pakai = 49.9144888707 mm
0.85*c pakai
a= 42.4273155401 mm
(c pakai-d')/c pakai)*Σc*Es
fs' = -151.284864343 Mpa
(0.85*f'c*a*b*(d desak-(a/2)))+(As'ada*fs'*(d desak-d'))
Mg+ = 84760637.7667 MPa
0.8*Mg-
0,8Mg+ = 67.8085102134 MPa
OK
(c - 62,5)/c
77273437.5 =
77273437.5 =
22727.48162 =
0 =
a₁ = 766.6691014169
a₂ = 29.6444470967
a pakai = 29.6444470967
OK
GAYA PERLAWANAN
R₂ = 5.67343125
R2*b*d desak
m₁ = 620531.5430
Mn-m1
m₂ = 76652905.95703
B. Tulangan Tarik
LUAS TULANGAN TARIK
0.5* ϼ
ϼb = 0.008128125
(0.85*f'c*a2*b)/fy ulir
As = 472.458375604
JUMLAH TULANGAN
As/As' d tulangan
n= 0.9629724853
n pakai = 1
n pakai*As' d tulangan
As ada = 490.625
OK
TULANGAN TEKAN 1
D. Tulangan Susut
0.002*b*h
As st = 250.0000
0.25*Phi*10^2
As tul = 78.500
As st/As tul
n= 3.1847133758
n pakai = 4
TULANGAN SUSUT 4
kNm
Nmm
mm
mm
6800 a x
2707466.06 a - ### a²
796 a - 1 a²
-22727.4816 + 796 a -1 a²
mm
mm
mm
Nmm
Nmm
mm²
mm²
buah
buah
mm²
D 22
mm²
buah
mm²
D 22
mm²
mm²
mm
Nmm
Nmm
mm²
mm²
buah
buah
D 22
Kontrol Momen Kapasitas Positif (Mpr+)
As' ada = 1962.50 mm²
As ada = 490.625 mm²
0.85*f'c*b*ß
Cc = 1530000 c
As'ada*Σc*Es
Cs = 1177500.000 (c - 62,5)/c
As'ada*f'y*1.25
Ts = 245312.5000 Mpa
1530000.00 c +
1530000.00 c² +
1530000.00 c² +
1 c² +
c₁ = 15.6369911332 mm
c₂ = -16.246264009 mm
MAX(D17:D18)
c pakai = 15.6369911332 mm
0.85*c pakai
a= 13.2914424632 mm
(c pakai-d')/c pakai)*Σc*Es
fs' = -12065.8771637208 Mpa
(0.85*f'c*a*b*(d tarik-(a/2)))+(As'ada*fs'*(d tarik-ds))
Mpr+ = 45634787.8237 MPa
0.8*Mpr+/1000000
0,8Mpr+ = 36507830.2590 MPa
OK
5418.75 c +
5418.75 c² +
5418.75 c² +
1 c² +
c₁ = 180.7171347011 mm
c₂ = -99.2292454277 mm
MAX(D46:D47)
c pakai = 180.7171347011 mm
0.85*c pakai
a= 153.6095644959 mm
(c pakai-d')/c pakai)*Σc*Es
fs' = 392.4933899 Mpa
(0.85*f'c*fs'*b*(d desak-(fs'/2)))+(As'ada*fs'*(d desak-ds))
Mpr- = 675863489.0186 MPa
0.8*Mpr-/1000000
0,8Mpr- = 540.6907912149 MPa
OK
- 62,5)/c
1177500 (c - 62,5-245312.5 = 0
1177500 c -388685310 -245312.5 c = 0
932187.500 c -388685310 = 0
0.6093 c -254.0427 = 0
- 62,5)/c
294375 (c - 62,5-735937.5 = 0
294375 c -97171327 -735937.50 c = 0
-441562.500 c -97171327 = 0
-81.4879 c -17932.4249 = 0
SENGKANG
A. Perhitungan Gaya Ultimit
GAYA GESER AKIBAT GEMPA
((Mpr+ + Mpr-)/L)/1000
Ve = 96.1997702456 kN
SPESI MAKSIMUM
s =1172132052756 mm
d desak/4
a= 99.5392 mm
d tul*8
b= 200 mm
d tul sengkang*24
c= 240 mm
s pakai = 50 mm
TUMPUAN SENGKANG 2D10 - 50
355894.4256 = 4000
y = 88.973606404
PERLU
(y/0.75)-Vc
Vs = -0.075939854 kN
x = 142.35777 x
x + -142.358 x
x
y
PLAT LANTAI
A. Rasio Plat
ly/lx
Ly : Lx = 2.142857143
1 ARAH
(ly-(2*(0,5*lebar balok)))/(lx-(2*(0,5*lebar balok)))
ß = 2.230769231
C. Pembebanan
BEBAN MATI
Beton = 3.36 kN/m²
Pasir 5 cm = 0.8 kN/m²
Spesi 2 cm = 0.42 kN/m²
Keramik = 0.0024 kN/m²
Plafon dan Penggantung = 0.117 kN/m²
MEE = 0.25 kN/m²
SUM(beton:mee)
DL = 4.9494 kN/m²
LL = 7.18 kN/m²
BEBAN HIDUP
(1,2*DL)+(1,6*LL)
Qu = 17.42728 kN/m²
MENCARI NOMINAL
(mu*1000000)/0,8
Mn = 2.42561E+13 Nmm
24256100380591.50 = 25500 a
24256100380591.50 = 2613750.00 a
1902439245.53659 = 205 a
0 = ###
a₁ = -22809.4605 mm
a₂ = -22809.4605 mm
a pakai = -22809.4605 mm
TULANGAN POKOK
(0,85*f'c*b plat*a pakai)/f'polos
As ada = -2423505.18 mm²
1/4*3,14*(d tul susut)^2
As D10 = 78.5 mm²
JARAK TULANGAN
(As D10*b plat)/As ada
s = -0.0323911 mm
2*h pakai
s max = 280 mm
s pakai = mm
TULANGAN SUSUT
0,002*b plat*h pakai
As st = 280 mm²
1/4*3,14*(d tul susut)^2
As D10 = 78.5 mm²
JARAK TULANGAN
(Asd10*b plat)/As st
s = 280.3571429 mm
2*h pakai
s max = 280 mm
s pakai = 280.3571429 mm