DETAIL DESAIN JEMBATAN RANGKA 60-M

Struktur : PELAT LANTAI Bagian : Penulangan


Penanggung jawab: Taufiq Rochman, ST, MT Lembar : 1/2
Momen X: Tumpuan dan Lapangan no. 400

Data - data fc 22.5 Mpa


fy 400 Mpa
Mu 2630 kgm
26.3 kNm
26,300,000 Nmm

β1 0.85
ρb 0.02438438
Dimensi balok/plat
b 1000 mm
h 200 mm
d' 30 mm
d 170
2
Asmax = 0.75 ρb.b.d = 3109.00781 mm
Asmin = 1.4 /fy .b.d = 595 mm2

Cc= 0.85 fc'.ab


a
h = d - a/2

Ts= As.fy

Kopel Tekan Beton - Tarik Baja

Coba As = 521 mm2/m

Dari Kesetimbangan, a = As1.fy = 10.89673203 < 170 mm OK


0.85 fc'.b
MR = 0.85 fc' a.b (d-a/2) = 27,434,048 Nmm > 26,300,000
OK
Karena MR > Mu, maka As coba-coba boleh digunakan
2
Jadi As = 521.00 mm /m pakai D 10 - 150
DETAIL DESAIN JEMBATAN RANGKA 60-M
Struktur : PELAT LANTAI Bagian : Penulangan
Penanggung jawab: Taufiq Rochman, ST, MT Lembar : 2/2
Momen Y: Tumpuan dan Lapangan no. 399

Data - data fc 22.5 Mpa


fy 400 Mpa
Mu 3120.9 kgm
31.209 kNm
31,209,000 Nmm

β1 0.85
ρb 0.02438438
Dimensi balok/plat
b 1000 mm
h 200 mm
d' 30 mm
d 170
2
Asmax = 0.75 ρb.b.d = 3109.00781 mm
Asmin = 1.4 /fy .b.d = 595 mm2

Cc= 0.85 fc'.ab


a
h d - a/2
=
Ts= As.fy

Kopel Tekan Beton - Tarik Baja

Coba As = 880 mm2/m

Dari Kesetimbangan, a = As1.fy = 18.40522876 < 170 mm OK


0.85 fc'.b
MR = 0.85 fc' a.b (d-a/2)= 45,280,544 Nmm > 31,209,000
OK
Karena MR > Mu, maka As coba-coba boleh digunakan
2
Jadi As = 880.00 mm /m pakai D 13 - 150