ENERCON CASE STUDY :

RISK RISK DRIVERS RISK MITIGATORS

a) Armed guards available on time


b) Hike in compensation for lending the
Villagers interruptions plot
c) Reallocation bonus to the villagers

Shortage of Particular capacity of


Use crane of 80 tonnes in hour of need so as
crane (220 tonnes crane used at
to reduce wastage of time and resources.
Nawapur Site)

Remoteness of the area Company owned transportation

Company could provide base camps on the


Distance of Nawapur Site
location of site.
a) Efficiency increment of existing cranes
b) Supplier change
Poor Printed Circuit board (PCB)
Work will not be c) Efficiency measurement of new
completed on time products
Heavy rainfall witnessed by this year
monsoon season.
Nothing can be done.
Restricted hours of work because of
high winds
Non availability of raw materials
(Out of the 14 (WECs) to be Change suppliers to receive material on time,
erected at the Nawapur site, improve transportation facility to decrease
materials for only ten had been the delay of raw materials.
received)

New roads to be build, Changes in


government policy for betterment of
Poor Infrastructure infrastructure, can extent private
partnerships for focussed approach

Centralization of power Decentralized system


Impact Identification Impact Drivers Impact Mitigation

Wheeling charge of 4% Reduce the charge by equally dividing


the expense between the company
and the client

Clientele Base is Lost Improper maintenance of Wind Energy EIL to offer a guarantee of 95 per cent
Converters (WEC) uptime subject to grid availability from
EB.

Proper land area to be given to villagers


Stay Order from Court (EIL and Villagers)
for reallocation.

Impact Identification Impact Drivers Impact Mitigation

Immense Competition Better results from our own product

a) More interconnected
Hierarchy in structure (gap in time taken
communication system
Market Share is Lost between decision making body and acting
b) Delayering and simplified
body on field)
management structures

Proper Planning, Early start of Project


Postponement of Tax Benefits
work to meet the expected targets.