Sie sind auf Seite 1von 5

TAT PHASE 2

SCHEDULE OF BUDGETARY PRICES - FIRE SERVICES INSTALLATION

Description Plot 3 DVP


(RM) (RM)

Preliminaries
1.00
(Tenderers to submit breakdown prices)

Stamp duty
a) -
(0.1% of contract sum)
b) Shop drawings, catalogues & samples -
c) Insurances -
d) Documentations -
e) Preliminaries -
f) Tender Deposit -
g) Shop drawings, as-built drawings, O&M manuals -
h) Mobilization, insurance, workmen compensation, etc. -

Total for Item 1.00 15,000.00


TAT PHASE 2
SCHEDULE OF BUDGETARY PRICES - FIRE SERVICES INSTALLATION

Description Plot 3 DVP


(RM) (RM)

2.00 Wet Riser System Installation

2.01 Wet riser duty / standby pumps and motors c/w valves etc.
(i) Single stage - 2 Sets 100,000.00

Sub-Total 100,000.00
2.02 Jockey pump and motors c/w valves etc. (1 Lot)
(i) Single stage - 2 Sets 20,000.00

Sub-Total 20,000.00
Wet riser water storage tank c/w stainless steel cat ladders
2.03 (internal & external), level indicator, level alarm, puddle flange,
valves, vortex inhabitor, fittings, pipework and accessories
(i) 1st stage - 2 Sets (RC tank by others) 60,000.00

Sub-Total 60,000.00
Wet riser piping reticulation including mechanical joint, fittings,
2.04
pipe hangers, motorised valves, etc. painting and accessories.
(i) Tower 312,000.00

Sub-Total 312,000.00
Self Regulating wet riser landing valve c/w 2 sets of Wet Riser
2.05
hoses, hose cradles and 1 set of Nozzle and hose coupling
(i) Tower (168 nos.) 1,500.00 252,000.00
(ii) 3 way valve (12 nos.) 3,000.00 36,000.00

Sub-Total 288,000.00
Fire brigade breeching inlets c/w box, pipe, fittings, painting
2.06 8,000.00
and accessories - 2 Sets

Wet Riser System starter panel including power & control


2.07
wiring, accessories, etc
(i) 1st stage - 2 Sets 42,000.00

Sub-Total 50,000.00

Total for Item 2.00 830,000.00


TAT PHASE 2
SCHEDULE OF BUDGETARY PRICES - FIRE SERVICES INSTALLATION

Description Plot 3 DVP


(RM) (RM)

3.00 Hose Reel Installaion

Hose Reel duty and Standby pumps and motors c/w valves,
3.01
etc
(i) Single stage - 2 Sets 35,000.00

Sub-Total 35,000.00
Hose Reel Pump panel c/w pump power & control wirings and
3.02
accessories (Fire rate cables for pumps)
(i) Single stage - 2 Sets 10,000.00

Sub-Total 10,000.00
Hose reel water storage tank c/w stainless steel cat ladders
3.03 (internal & external), level indicator, level alarm, puddle flange,
valves and fittings, pipework and accessories
(i) HDGI Pressed Steel tank - 2 Sets 40,000.00

Sub-Total 40,000.00
Hose Reel piping reticulating including mechanical joints,
3.04 pressure reducing valves, flow sitch, fittings, pipe hangers,
pressure gauge, painting and accessories, etc.
(i) Tower 152,100.00
(ii) Carpark 74,700.00

Sub-Total 226,800.00
3.05 Hose Reel c/w nozzle key box, hose and accessories

(ii) With nozzle key box (335 nos.) 500.00 167,500.00

Sub-Total 167,500.00

Total for Item 3.00 479,300.00


TAT PHASE 2
SCHEDULE OF BUDGETARY PRICES - FIRE SERVICES INSTALLATION

Description Plot 3 DVP


(RM) (RM)

4.00 Fire Alarm Installation

4.01 Smoke Detector (20 nos.) 450.00 9,000.00

4.02 Heat Detector (2 nos.) 450.00 900.00

4.03 Manual call points and alarm bells (335 nos.) 550.00 184,250.00

Sub-Total 194,150.00
Fire Alarm wiring point including conduits, fittings, junction
4.03
boxes, brackets, painting and accessories (1 lot)

(i) Smoke detectors (20 nos.) 800.00 16,000.00

(i) Heat detectors (2 nos.) 800.00 1,600.00

(ii) Break glass and alarm bells (335 nos.) 800.00 268,000.00

(iii) Flow switch, pressure switch, sensors, etc 30,000.00

Sub-Total 315,600.00
Addressable Fire Alarm Panel c/w Mimic Diagram, standby
4.04
battery, etc.

(i) Main panel in Guard House 75,000.00

Sub-Total 75,000.00

Total for Item 4.00 584,750.00


TAT PHASE 2
SCHEDULE OF BUDGETARY PRICES - FIRE SERVICES INSTALLATION

Description Plot 3 DVP


(RM) (RM)

CO2 and Clean Agent Fire Extinguishing System (TNB


approved brand only) c/w Jabatan Bomba Malaysia approved
5.00
curtain, smoke and heat detector, alarm bell, piping nozzle,
control panel, etc

5.01 Clean Agent System

(i) Double Chamber TNB Sub-station (2 Sets) 125,000.00

5.02 CO2 System

(i) LV Room - MSCP (2 Sets) 35,000.00

(ii) LV Room - Tower (4 Sets) 40,000.00

(iii) Genset Room (2 Set) 25,000.00

Total for Item 5.00 225,000.00

6.00 Portable Fire Extinguishers

(i) 4 kg Dry powder (436 nos.) 125.00 54,500.00

(i) 9 kg Dry powder (141 nos.) 150.00 21,150.00

(ii) 2.3 kg CO2 (8 nos.) 175.00 1,400.00

(iii) Cabinet c/w key box (141 nos.) 150.00 21,150.00

Total for Item 6.00 98,200.00

Testing, commissioning and twenty-four (24) months service


7.00 and maintenance including all authorities inspection and test 10,000.00
fees

8.00 Propriety make fire seal for all floor and wall penetrations 8,000.00

TOTAL BUDGETARY PRICES 2,250,250.00