PROJECT CC 50 : Part design and construction of elevated viaduct, elevated ramp and 2 elevated stations viz Dwarka and

Najafgarh Depot inluding architectural finishing, water supply, sanitary installation and drainage works

ID Task Name Duration Start Finish 2014 2015


A S O N D J F M A M J J A S O N D J F M A M J J A S O
0 DMRC CC50 CONSTRUCTION PROGRAMME 628 days Fri 06-09-13 Tue 08-09-15
1 1 Preconstruction Activities 621 days Fri 06-09-13 Mon 31-08-15
2 1.1 Contractual Activities 29 days Fri 06-09-13 Wed 09-10-13
3 1.1.1 Issue of LOI by DMRC 0 days Fri 06-09-13 Fri 06-09-13
4 1.1.2 Notice to Proceed 0 days Mon 09-09-13 Mon 09-09-13
5 1.1.3 Commencement of Work 0 days Mon 09-09-13 Mon 09-09-13
6 1.1.4 Submission of Performance BG 0 days Thu 19-09-13 Thu 19-09-13
7 1.1.5 Submission of Power of Attorney 0 days Thu 19-09-13 Thu 19-09-13
8 1.1.6 Signing of Contract Agreement 0 days Wed 09-10-13 Wed 09-10-13
9 1.2 Client Deliverables 90 days Mon 09-09-13 Mon 23-12-13
10 1.2.1 Handover of Casting Yard/Contractor's Working Area 0 days Mon 09-09-13 Mon 09-09-13
11 1.2.2 Handover of un obstructed Working Area for Viaduct, station & interconnecting structure, 90 days Tue 10-09-13 Mon 23-12-13
12 1.2.3 Handover of Final Alignment Drawings 0 days Wed 11-09-13 Wed 11-09-13
13 1.2.4 Handover of Architectural Plan & Drawings -Stations 0 days Wed 11-09-13 Wed 11-09-13
14 1.2.5 Handing over of Survey Bench Mark & Issue of Co-ordinates 0 days Mon 09-09-13 Mon 09-09-13
15 1.2.6 Permission for Tree Cutting / transplantation within alignment 57 days Tue 10-09-13 Thu 14-11-13
16 1.2.7 Permission for Dismantling of structures within alignment 0 days Tue 17-09-13 Tue 17-09-13
17 1.2.8 Clearance of HT Line by concerned auth. Within the alignment 30 days Wed 23-10-13 Tue 26-11-13
18 1.3 Contractual Submittals 618 days Tue 10-09-13 Mon 31-08-15
19 1.3.1 Preparation & Submission of Quality Plan 0 days Mon 07-10-13 Mon 07-10-13
20 1.3.2 Preparation & Submission of Safety and Environment Management Plan 0 days Mon 07-10-13 Mon 07-10-13
21 1.3.3 Submission of Quarterly audit report of safety,quality and environment 204 days Tue 10-09-13 Mon 31-08-15
22 1.4 Submission of Construction programme, Establishing site office KD-01 0 days Wed 09-10-13 Wed 09-10-13
23 1.5 Survey & Set out Works 129 days Thu 12-09-13 Sat 08-02-14
24 1.5.1 Initial Survey and set out, fixing of coordinates 40 days Thu 12-09-13 Mon 28-10-13
25 1.5.2 Survey of Charted Utility (Tree , Electrical Post , HT Line , Building etc.) & sub of report 30 days Wed 18-09-13 Tue 22-10-13
26 1.5.3 Utility Identification & Submission of Report 60 days Mon 02-12-13 Sat 08-02-14
27 1.6 Soil Investigation 85 days Wed 11-09-13 Wed 18-12-13
28 1.6.1 Soil Investigation -From.Dwarka & Najafgar Depot 30 days Wed 11-09-13 Tue 15-10-13
29 1.6.2 Labr. Testing and submission of reports 70 days Sat 28-09-13 Wed 18-12-13
30 1.7 Mobilization and Setup 90 days Tue 10-09-13 Mon 23-12-13
31 1.7.1 Initial Staff Mobilization 30 days Tue 10-09-13 Mon 14-10-13
32 1.7.2 Finalize Casting Yard Layout 3 days Tue 10-09-13 Thu 12-09-13
33 1.7.3 Set Up of Site office, Laboratory , Store, cement godown 70 days Fri 13-09-13 Tue 03-12-13
34 1.7.4 Civil Wrks , Erec & Commission 1st batching Plant 45 days Fri 20-09-13 Mon 11-11-13
35 1.7.5 Civil Wrks , Erec & Commission 2nd batching Plant 50 days Sat 26-10-13 Mon 23-12-13
36 1.7.6 Set up of casting yard (Civil & Mechanical Works) 75 days Sat 21-09-13 Tue 17-12-13
37 1.7.7 Fabrication of 1st Segment/ I Girder Formwork 40 days Thu 24-10-13 Mon 09-12-13
38 1.8 Commission 1st batching Plant KD-02 (11-Nov-13) 0 days Mon 11-11-13 Mon 11-11-13
39 1.9 Commission 2nd batching Plant - KD-04 (23-Dec-13) 0 days Mon 23-12-13 Mon 23-12-13
40 1.10 Completion of 1st Formwork of segment production line for 0 days Mon 09-12-13 Mon 09-12-13
41 1.11 Design & Drawings 386 days Tue 10-09-13 Wed 03-12-14
42 1.11.1 Finalize Detailed Design Consultant 15 days Tue 10-09-13 Thu 26-09-13
43 1.11.2 Approval of Detailed Design Consultant 10 days Fri 27-09-13 Tue 08-10-13
44 1.11.3 Proposal of Proof Check consultant for checking of I girder design 0 days Sat 26-10-13 Sat 26-10-13
45 1.11.4 Approval of Proof Check consultant for checking of I girder design 0 days Wed 20-11-13 Wed 20-11-13
46 1.11.5 Submission of DBR - Viaduct 15 days Fri 27-09-13 Mon 14-10-13
47 1.11.6 Approval of DBR - Viaduct 7 days Tue 15-10-13 Tue 22-10-13
48 1.11.7 Submission of DBR - Stations 15 days Fri 27-09-13 Mon 14-10-13
49 1.11.8 Approval of DBR - Stations 7 days Tue 15-10-13 Tue 22-10-13
50 1.11.9 Submission of Span Arrangement Drawing (Based on Alignment GAD) 15 days Thu 12-09-13 Sat 28-09-13
51 1.11.10 Approval of Span Arrangement Drawing (Based on Alignment GAD) 7 days Mon 30-09-13 Mon 07-10-13
52 1.11.11 Initial Pile Design/Drg 52 days Wed 16-10-13 Sat 14-12-13
53 1.11.11.1 Submission of Design /Drg of Test Pile 45 days Wed 16-10-13 Fri 06-12-13
54 1.11.11.2 Approval of Design /Drg of Test Pile 7 days Sat 07-12-13 Sat 14-12-13
55 1.11.12 Pile /Pile Cap /Pier Design/Drg -Viaduct 140 days Mon 16-12-13 Tue 27-05-14
56 1.11.12.1 Submission Design / Drg Wrk Pile/ -Viaduct 75 days Mon 16-12-13 Wed 12-03-14
57 1.11.12.2 Approval Design / Drg Wrk Pile -Viaduct 75 days Tue 24-12-13 Thu 20-03-14
58 1.11.12.3 Submission Design / Pile Cap/Pier -Viaduct 100 days Thu 23-01-14 Mon 19-05-14
59 1.11.12.4 Approval Design / Pile Cap/Pier -Viaduct 100 days Fri 31-01-14 Tue 27-05-14
60 1.11.13 I-Girder, Parapet Design/Drg -Viaduct 57 days Wed 27-11-13 Fri 31-01-14
61 1.11.13.1 Submission Design / Drg I-Girder & Parapet -Viaduct 50 days Wed 27-11-13 Thu 23-01-14
62 1.11.13.2 Approval Design / Drg I-Girder & Parapet -Viaduct 50 days Thu 05-12-13 Fri 31-01-14
63 1.11.14 Super str. Works (Cross Girder, Pier Cap & Deck slab) Design/Drg -Viaduct 82 days Sat 18-01-14 Wed 23-04-14

BASELINE PROGRAMME (R2 dt 30-JANUARY-2014)

Page 1 of 5

ITD CEMENTATION INDIA LTD


PROJECT CC 50 : Part design and construction of elevated viaduct, elevated ramp and 2 elevated stations viz Dwarka and Najafgarh Depot inluding architectural finishing, water supply, sanitary installation and drainage works

ID Task Name Duration Start Finish 2014 2015


A S O N D J F M A M J J A S O N D J F M A M J J A S O
64 1.11.14.1 Submission Design / Drg Sup.str works -Viaduct 75 days Sat 18-01-14 Tue 15-04-14
65 1.11.14.2 Approval Design / Drg sup. Str works -Viaduct 75 days Mon 27-01-14 Wed 23-04-14
66 1.11.15 Ramp 40 days Sat 14-12-13 Wed 29-01-14
67 1.11.15.1 Submission Design / Drg for Ramp 30 days Sat 14-12-13 Fri 17-01-14
68 1.11.15.2 Approval Design / Drg for Ramp 10 days Sat 18-01-14 Wed 29-01-14
69 1.11.16 Pile / Pile Cap/Footing /Pier & Column Design & Drg -Stations 141 days Wed 27-11-13 Fri 09-05-14
70 1.11.16.1 Submission of Framing Plan - Dwarka Station 15 days Wed 27-11-13 Fri 13-12-13
71 1.11.16.2 Approval of Framing Plan - Dwarka Station 7 days Sat 14-12-13 Sat 21-12-13
72 1.11.16.3 Submission Pile / Pile Cap/Footing /Pier & Column Design & Drg -Dwarka Station 90 days Tue 31-12-13 Mon 14-04-14
73 1.11.16.4 Approval Pile / Pile Cap/Footing /Pier & Column Design & Drg -Dwarka Station 90 days Wed 08-01-14 Tue 22-04-14
74 1.11.16.5 Submission of Framing Plan - Najafgarh Station 15 days Sat 14-12-13 Tue 31-12-13
75 1.11.16.6 Approval of Framing Plan - Najafgarh Station 7 days Wed 01-01-14 Wed 08-01-14
76 1.11.16.7 Submission Pile / Pile Cap/Footing /Pier & Column Design & Drg -Najafgarh Station 90 days Fri 17-01-14 Thu 01-05-14
77 1.11.16.8 Approval Pile / Pile Cap/Footing /Pier & Column Design & Drg -Najafgarh Station 90 days Sat 25-01-14 Fri 09-05-14
78 1.11.17 Superstructure Design & Drg -Stations 200 days Tue 15-04-14 Wed 03-12-14
79 1.11.17.1 Submission Superstr. Design & Drg -Dwarka Station 90 days Tue 15-04-14 Mon 28-07-14
80 1.11.17.2 Approval Superstr. Design & Drg -Dwarka Station 60 days Tue 29-07-14 Mon 06-10-14
81 1.11.17.3 Submission Superstr. Design & Drg -Najafgarh Station 120 days Fri 02-05-14 Thu 18-09-14
82 1.11.17.4 Approval Superstr. Design & Drg -Najafgarh Station 65 days Fri 19-09-14 Wed 03-12-14
83 1.12 Mix Design 90 days Fri 27-09-13 Thu 09-01-14
84 1.12.1 Finalize Mix Design for Piling 40 days Fri 27-09-13 Tue 12-11-13
85 1.12.2 Finalize Mix Design for-Precast 40 days Wed 09-10-13 Sat 23-11-13
86 1.12.3 Finalize Mix Design for Cast-in-situ 40 days Mon 25-11-13 Thu 09-01-14
87 1.13 Work Methodology 276 days Tue 08-10-13 Mon 25-08-14
88 1.13.1 Submission of Methodology for Piling by Rotary Piling Rig 15 days Tue 08-10-13 Thu 24-10-13
89 1.13.2 Approval of Methodology for Piling by Rotary Piling Rig 5 days Fri 25-10-13 Wed 30-10-13
90 1.13.3 Submission of Methodology for Pile Cap /Pier/Piercap 15 days Wed 25-12-13 Fri 10-01-14
91 1.13.4 Approval of Methodology for Pile Cap /Pier/Piercap 5 days Sat 11-01-14 Thu 16-01-14
92 1.13.5 Submission of Methodology for I Girder Casting & Stressing 15 days Tue 03-12-13 Thu 19-12-13
93 1.13.6 Approval of Methodology for I Grder Casting & Stressing 5 days Fri 20-12-13 Wed 25-12-13
94 1.13.7 Submission of Methodology for I Girder erection 15 days Fri 14-02-14 Mon 03-03-14
95 1.13.8 Approval of Methodology for I Girder erection 5 days Tue 04-03-14 Sat 08-03-14
96 1.13.9 Submission of Methodology for Parapet erection 15 days Fri 28-03-14 Mon 14-04-14
97 1.13.10 Approval of Methodology for Parapet erection 5 days Tue 15-04-14 Sat 19-04-14
98 1.13.11 Submission of Methodology for Initial Pile Load Test 15 days Thu 10-10-13 Sat 26-10-13
99 1.13.12 Approval of Methodology for Initial Pile Load Test 5 days Mon 28-10-13 Fri 01-11-13
100 1.13.13 Submission of Methdology for Cast insitu deck slab at Viaduct 15 days Thu 16-01-14 Sat 01-02-14
101 1.13.14 Approval of Methdology for Cast insitu deck slab at Viaduct 5 days Mon 03-02-14 Fri 07-02-14
102 1.13.15 Submission of Methdology for Construction of Ramp 15 days Sat 30-11-13 Tue 17-12-13
103 1.13.16 Approval of Methdology for Construction of Ramp 5 days Wed 18-12-13 Mon 23-12-13
104 1.13.17 Submission of Methdology for RCC works at Stations 15 days Tue 28-01-14 Thu 13-02-14
105 1.13.18 Approval of Methdology for RCC works at Stations 5 days Fri 14-02-14 Wed 19-02-14
106 1.13.19 Submission of Methdology for Construction of Substructures at Najafgarh Drain Portion 15 days Wed 18-12-13 Fri 03-01-14
107 1.13.20 Approval of Methdology for Construction of Substructures at Najafgarh Drain Portion 5 days Sat 04-01-14 Thu 09-01-14
108 1.13.21 Submission of Methdology for Integration of old and new viaduct at Dwarka Station 15 days Sat 02-08-14 Tue 19-08-14
109 1.13.22 Approval of Methdology for Integration of old and new viaduct at Dwarka Station 5 days Wed 20-08-14 Mon 25-08-14
110 1.13.23 Submission of Methdology for Casting of Precast parapet 15 days Tue 28-01-14 Thu 13-02-14
111 1.13.24 Approval of Methdology for Casting of Precast parapet 5 days Fri 14-02-14 Wed 19-02-14
112 1.13.25 Submission of Methdology for tests to be performed at Site Lab 15 days Thu 12-12-13 Sat 28-12-13
113 1.13.26 Approval of Methdology for tests to be performed at Site Lab 5 days Mon 30-12-13 Fri 03-01-14
114 1.13.27 Submission of Methdology for Load Test on I-girder 15 days Tue 28-01-14 Thu 13-02-14
115 1.13.28 Approval of Methdology for Load Test on I-girder 5 days Fri 14-02-14 Wed 19-02-14
116 1.13.29 Submission of Methdology for Load Test on Span 15 days Tue 08-04-14 Thu 24-04-14
117 1.13.30 Approval of Methdology for Load Test on Span 5 days Fri 25-04-14 Wed 30-04-14
118 1.14 Traffic Management 618 days Tue 10-09-13 Mon 31-08-15
119 1.14.1 Prepare traffic management plan -In Phases 40 days Fri 27-09-13 Tue 12-11-13
120 1.14.2 Submission of Plan -In phases 40 days Wed 09-10-13 Sat 23-11-13
121 1.14.3 Approval of Traffic Management Plan -In phases 40 days Mon 21-10-13 Thu 05-12-13
122 1.14.4 Making New Road/Strengthning of Existing Roads 618 days Tue 10-09-13 Mon 31-08-15
123 1.15 Test Pile Installation & Reports 116 days Mon 14-10-13 Wed 26-02-14
124 1.15.1 Mobilize Rig for Test Pile 0 days Mon 14-10-13 Mon 14-10-13
125 1.15.2 Install Initial Test Pile 20 days Mon 02-12-13 Tue 24-12-13
126 1.15.3 Pile Load Test & Submission of Report 50 days Tue 31-12-13 Wed 26-02-14
127 2 Casting of Precast Elements 443 days Mon 30-09-13 Fri 27-02-15
128 2.1 Submission of design of Thrust Block & Bed for Precast I-Girder 0 days Mon 30-09-13 Mon 30-09-13
129 2.2 Approval of design of Thrust Block & Bed for Precast I-Girder 3 days Mon 30-09-13 Wed 02-10-13
130 2.3 Casting of I - Girder 250 days Mon 13-01-14 Thu 30-10-14
131 2.4 Casting of Precast Parapet 320 days Thu 20-02-14 Fri 27-02-15

BASELINE PROGRAMME (R2 dt 30-JANUARY-2014)

Page 2 of 5

ITD CEMENTATION INDIA LTD


PROJECT CC 50 : Part design and construction of elevated viaduct, elevated ramp and 2 elevated stations viz Dwarka and Najafgarh Depot inluding architectural finishing, water supply, sanitary installation and drainage works

ID Task Name Duration Start Finish 2014 2015


A S O N D J F M A M J J A S O N D J F M A M J J A S O
132 3 Casting of 1st Girder Segment- KD-06 (13-Jan-14) 0 days Mon 13-01-14 Mon 13-01-14
133 4 Construction of Viaduct 603 days Sat 05-10-13 Tue 08-09-15
134 4.1 Preparatory Works 265 days Sat 05-10-13 Sat 09-08-14
135 4.1.1 Barricading of Area 220 days Wed 27-11-13 Sat 09-08-14
136 4.1.2 Uncharted Utility Trenching & Detection 75 days Thu 05-12-13 Sat 01-03-14
137 4.1.3 Approval for removal/relocation of uncharted utilities 75 days Mon 23-12-13 Wed 19-03-14
138 4.1.4 Removal of Uncharted utility 90 days Tue 31-12-13 Mon 14-04-14
139 4.1.5 Tree Cutting & Transplantation 75 days Fri 15-11-13 Mon 10-02-14
140 4.1.6 Dismantling of structures/obstruction 60 days Sat 05-10-13 Fri 13-12-13
141 4.2 Mainline Viaduct - Piling 321 days Mon 06-01-14 Wed 14-01-15
142 4.2.1 Piling Z2 P5 & P4 - R1 10 days Fri 18-04-14 Tue 29-04-14
143 4.2.2 Piling Z3 P3 (Start of Dwarka Station) to P5A-R1 25 days Mon 26-05-14 Mon 23-06-14
144 4.2.3 Piling Z4 CP36 to P45 -R1 30 days Fri 27-06-14 Thu 31-07-14
145 4.2.4 Piling Z5 PP35 to P21 -R1 50 days Tue 05-08-14 Wed 01-10-14
146 4.2.5 Piling Z6 PP90B to P63 - R2 80 days Mon 06-01-14 Tue 08-04-14
147 4.2.6 Piling Z7 PP51 to P 46 - R2 20 days Mon 14-04-14 Tue 06-05-14
148 4.2.7 Piling Z8 PP91 to P 97-R2 25 days Fri 09-05-14 Fri 06-06-14
149 4.2.8 Piling Z9 P13 to P 6 -R3 25 days Fri 16-05-14 Fri 13-06-14
150 4.2.9 Piling Z11 P62 to P52-R3 30 days Tue 17-06-14 Mon 21-07-14
151 4.2.10 Piling Z12 P14 to P18 (Nallah Ph-1) -R1 20 days Fri 02-05-14 Sat 24-05-14
152 4.2.11 Piling Z13 P19 to P20 (Nallah Ph-2) -R4 10 days Sat 03-01-15 Wed 14-01-15
153 4.3 Completion of 1st Working Pile - KD-05 (06-Jan-14) 0 days Mon 06-01-14 Mon 06-01-14
154 4.4 Mainline Viaduct - Pile Cap 316 days Tue 04-02-14 Fri 06-02-15
155 4.4.1 Pile Cap Z2 P5 & P4 (3rd & 4th Set) (1st & 2nd set) 10 days Wed 04-06-14 Sat 14-06-14
156 4.4.2 Pile Cap Z3 P3 (Start of Dwarka Station) to P5A (1st & 2nd set) 30 days Mon 16-06-14 Sat 19-07-14
157 4.4.3 Pile Cap Z4 & Z7- P51 to CP36 (1st & 2nd set) 55 days Wed 23-07-14 Wed 24-09-14
158 4.4.4 Pile Cap Z8 PP91 to P 97 (1st & 2nd set) 30 days Fri 26-09-14 Thu 30-10-14
159 4.4.5 Pile Cap Z6 PP90B to P 63 (1st & 2nd Set) 100 days Tue 04-02-14 Fri 30-05-14
160 4.4.6 Pile Cap Z11 P62 to P52 (3rd & 4th set) 40 days Thu 03-07-14 Mon 18-08-14
161 4.4.7 Pile Cap Z9 P13 to P 6 (3rd & 4th set) 30 days Tue 19-08-14 Mon 22-09-14
162 4.4.8 Pile Cap Z5 PP35 to P21 (3rd & 4th set) 60 days Tue 23-09-14 Mon 01-12-14
163 4.4.9 Pile Cap Z12 P14 to P18 (Nallah Ph-1) (3rd & 4th set) 25 days Tue 20-05-14 Tue 17-06-14
164 4.4.10 Pile Cap Z13 P19 to P20 (Nallah Ph-2) 15 days Wed 21-01-15 Fri 06-02-15
165 4.5 Mainline Viaduct - Pier 324 days Wed 12-02-14 Tue 24-02-15
166 4.5.1 Pier P5 & P4 (3rd & 4th Set) (1st & 2nd set) 10 days Sat 21-06-14 Wed 02-07-14
167 4.5.2 Pier P3 (Start of Dwarka Station) to P5A (1st & 2nd set) 30 days Thu 03-07-14 Wed 06-08-14
168 4.5.3 Pier P51 to CP36 (1st & 2nd set) 55 days Sat 09-08-14 Sat 11-10-14
169 4.5.4 PierPP91 to P 97 (1st & 2nd set) 30 days Tue 14-10-14 Mon 17-11-14
170 4.5.5 Pier Z6 PP90B to P 63 (1st & 2nd Set) 100 days Wed 12-02-14 Sat 07-06-14
171 4.5.6 Pier Z11 P62 to P52 (3rd & 4th set) 40 days Mon 21-07-14 Thu 04-09-14
172 4.5.7 Pier Z9 P13 to P 6 (3rd & 4th set) 30 days Fri 05-09-14 Thu 09-10-14
173 4.5.8 Pier Z5 PP35 to P21 (3rd & 4th set) 60 days Fri 10-10-14 Thu 18-12-14
174 4.5.9 Pier Z12 P14 to P18 (Nallah Ph-1) (3rd & 4th set) 25 days Fri 06-06-14 Fri 04-07-14
175 4.5.10 Pier Z13 P19 to P20 (Nallah Ph-2) 15 days Sat 07-02-15 Tue 24-02-15
176 4.6 Mainline Viaduct - Pier Cap & Fixing of Bearings 325 days Sat 22-02-14 Sat 07-03-15
177 4.6.1 Pier Cap Z2 P5 & P4 (3rd & 4th Set) (1st & 2nd set) 10 days Sat 12-07-14 Wed 23-07-14
178 4.6.2 Pier Cap Z3 P3 (Start of Dwarka Station) to P5A (1st & 2nd set) 40 days Thu 24-07-14 Mon 08-09-14
179 4.6.3 Pier Cap Z4 & Z7- P51 to CP36 (1st & 2nd set) 65 days Tue 09-09-14 Sat 22-11-14
180 4.6.4 Pier Cap Z8 PP91 to P 97 (1st & 2nd set) 40 days Mon 24-11-14 Thu 08-01-15
181 4.6.5 Pier Cap Z6 PP90B to P 63 (1st & 2nd Set) 120 days Sat 22-02-14 Fri 11-07-14
182 4.6.6 Pier Cap Z11 P62 to P52 (3rd & 4th set) 45 days Fri 01-08-14 Mon 22-09-14
183 4.6.7 Pier Cap Z9 P13 to P 6 (3rd & 4th set) 35 days Tue 23-09-14 Sat 01-11-14
184 4.6.8 Pier Cap Z5 PP35 to P21 (3rd & 4th set) 70 days Mon 03-11-14 Thu 22-01-15
185 4.6.9 Pier Cap Z12 P14 to P18 (Nallah Ph-1) (3rd & 4th set) 35 days Wed 18-06-14 Mon 28-07-14
186 4.6.10 Pier Cap Z13 P19 to P20 (Nallah Ph-2) 15 days Thu 19-02-15 Sat 07-03-15
187 4.7 Mainline Viaduct "I" Girder Erection 337 days Sat 08-03-14 Mon 06-04-15
188 4.7.1 Mobilize Erection Crane 0 days Sat 08-03-14 Sat 08-03-14
189 4.7.2 I - Girder Erection PP90 to P63 125 days Mon 10-03-14 Fri 01-08-14
190 4.7.3 I - Girder Erection by P62 to CP36 70 days Sat 20-09-14 Wed 10-12-14
191 4.7.4 I - Girder Erection PP35 to P 21 & P13 to P6 55 days Thu 11-12-14 Thu 12-02-15
192 4.7.5 I - Girder Erection P5 & P4 (2) 6 days Fri 13-02-15 Thu 19-02-15
193 4.7.6 I - Girder Erection P3 (Start of Dwarka Station) to P5A 20 days Fri 20-02-15 Sat 14-03-15
194 4.7.7 I - Girder Erection P91 to P 97 20 days Sat 02-08-14 Mon 25-08-14
195 4.7.8 I - Girder Erection P14 to P18 (Nallah Ph-1) 30 days Fri 15-08-14 Thu 18-09-14
196 4.7.9 I - Girder Erection P19 to P20 (Nallah Ph-2) 10 days Thu 26-03-15 Mon 06-04-15
197 4.8 Start of Erection of I-Girder - KD-07 (10-Mar-14) 0 days Mon 10-03-14 Mon 10-03-14

BASELINE PROGRAMME (R2 dt 30-JANUARY-2014)

Page 3 of 5

ITD CEMENTATION INDIA LTD


PROJECT CC 50 : Part design and construction of elevated viaduct, elevated ramp and 2 elevated stations viz Dwarka and Najafgarh Depot inluding architectural finishing, water supply, sanitary installation and drainage works

ID Task Name Duration Start Finish 2014 2015


A S O N D J F M A M J J A S O N D J F M A M J J A S O
198 4.9 Mainline Viaduct In-Situ Deck Slab 373 days Wed 26-03-14 Wed 03-06-15
199 4.9.1 In-situ Deck - PP-90B to P-63 115 days Wed 26-03-14 Wed 06-08-14
200 4.9.2 In-situ Deck - P62 to CP36 100 days Wed 15-10-14 Sat 07-02-15
201 4.9.3 In-situ Deck - PP35 to P 21 & P13 to P6 80 days Mon 05-01-15 Tue 07-04-15
202 4.9.4 In-Situ Deck - P4 (End of Dwarka Stn to Pier 36 of Viaduct) 30 days Tue 10-03-15 Mon 13-04-15
203 4.9.5 In-situ Deck - P3 (Start of Dwarka Station) to P5A 35 days Tue 17-03-15 Sat 25-04-15
204 4.9.6 In-situ Deck - P91 to P 97 30 days Wed 27-08-14 Tue 30-09-14
205 4.9.7 In-situ Deck P14 to P18 (Nallah Ph-1) 60 days Wed 01-10-14 Tue 09-12-14
206 4.9.8 In-situ Deck P19 to P20 (Nallah Ph-2) 30 days Thu 30-04-15 Wed 03-06-15
207 4.10 Mainline Parapet Erection 371 days Mon 21-04-14 Fri 26-06-15
208 4.10.1 Parapet Erection - PP90B (Ch:2348) to P63 (Ch:1672) 100 days Mon 21-04-14 Thu 14-08-14
209 4.10.2 Parapet Erection - P62 (Ch:1533) to CP36 (Ch:889.8) 100 days Sat 08-11-14 Wed 04-03-15
210 4.10.3 Parapet Erection - PP35 (Ch:844) to P 21 & P13 to P6 80 days Thu 29-01-15 Fri 01-05-15
211 4.10.4 Parapet Erection- P5(Ch:95) & P4(Ch:70) 15 days Fri 03-04-15 Mon 20-04-15
212 4.10.5 Parapet Erection - P3 (Ch:-70) (Start of Dwarka Station) to P5A (Ch:-250.497) 30 days Fri 10-04-15 Thu 14-05-15
213 4.10.6 Parapet Erection - P91 (Ch:2374.41) to P 97 (Ch:2524.41) 30 days Sat 20-09-14 Fri 24-10-14
214 4.10.7 Parapet Erection (Ch:320) to P18 (Ch:420) (Nallah Ph-1) -R3 30 days Sat 25-10-14 Fri 28-11-14
215 4.10.8 Parapet Erection Z14 P19 to P20 (Nallah Ph-2) -R3 10 days Tue 16-06-15 Fri 26-06-15
216 4.11 Start of Launching of Parapets - KD-08 (21-Apr-14) 0 days Mon 21-04-14 Mon 21-04-14
217 4.12 Partial access of the viaduct(minimum 1.5 km in one stretch for 0 days Mon 23-03-15 Mon 23-03-15
218 4.13 Full Access of Mainline Viaduct and ramps, for laying of track and 0 days Fri 26-06-15 Fri 26-06-15
219 4.14 Fix Expansion Joint & Railing /Misc Works 110 days Mon 04-05-15 Tue 08-09-15
220 4.14.1 Fixing of Expansion Joint 110 days Mon 04-05-15 Tue 08-09-15
221 4.15 Ramp Construction (220m length) 428 days Thu 30-01-14 Fri 12-06-15
222 4.15.1 Excavation 120 days Thu 30-01-14 Wed 18-06-14
223 4.15.2 Raft Construction 120 days Thu 06-03-14 Wed 23-07-14
224 4.15.3 Wall construction 120 days Thu 10-04-14 Wed 27-08-14
225 4.15.4 Deck Slab Construction 230 days Thu 15-05-14 Fri 06-02-15
226 4.15.5 Parapet Erection 230 days Thu 19-06-14 Fri 13-03-15
227 4.15.6 Misc Finishing Works 220 days Tue 30-09-14 Fri 12-06-15
228 4.16 Finishing Works 428 days Mon 28-04-14 Tue 08-09-15
229 4.16.1 R.C.C crash barrier around Pier 250 days Mon 28-04-14 Thu 12-02-15
230 4.16.2 Rain Water Harvesting pit & manhole constr. 250 days Mon 02-06-14 Thu 19-03-15
231 4.16.3 MS Railing and walkways on the both sides 300 days Fri 15-08-14 Thu 30-07-15
232 4.16.4 All other Balance Works reladed to Viaduct and elevated ramp 285 days Sat 11-10-14 Tue 08-09-15
233 4.17 Completion of entire viaduct work as per the contract -KD-11 (08-Sep-15) 0 days Tue 08-09-15 Tue 08-09-15
234 5 Construction of Stations 565 days Tue 19-11-13 Tue 08-09-15
235 5.1 Dwarka Station 489 days Fri 17-01-14 Mon 10-08-15
236 5.1.1 R.C.C Frame Works 394 days Fri 17-01-14 Tue 21-04-15
237 5.1.1.1 Z1 Station Piling (Dwarka Stn) - R1 75 days Fri 17-01-14 Mon 14-04-14
238 5.1.1.2 Pile Cap & Tie Beam Network 90 days Thu 27-02-14 Wed 11-06-14
239 5.1.1.3 Column upto bottom of Track Level Beam 118 days Sat 22-03-14 Wed 06-08-14
240 5.1.1.4 Backfilling PCC & Gradeslab 90 days Sat 22-03-14 Fri 04-07-14
241 5.1.1.5 Beams & Slab at Track Level 170 days Wed 09-04-14 Thu 23-10-14
242 5.1.1.6 Beams & Slab at Platform Level 100 days Wed 26-11-14 Sat 21-03-15
243 5.1.1.7 Track Supporting Structure 90 days Tue 06-01-15 Mon 20-04-15
244 5.1.1.8 Lift shaft , escalator pit 220 days Thu 07-08-14 Mon 20-04-15
245 5.1.1.9 Stair case from Concourse Level to Platform Level 120 days Sat 05-07-14 Fri 21-11-14
246 5.1.1.10 Interconnecting structure between old and new station 120 days Wed 03-12-14 Tue 21-04-15
247 5.1.2 Ancillary Building, Architectural & Finishing Works 318 days Tue 05-08-14 Mon 10-08-15
248 5.1.2.1 Masonary works for Operational , Signalling , telecommunication room, station control 150 days Wed 27-08-14 Tue 17-02-15
249 5.1.2.2 Architectural & Finishing works for Operational , Signalling , telecommunication room, 100 days Thu 27-11-14 Mon 23-03-15
250 5.1.2.3 Masonary Works for TOM Room & flooring with reqd cutting of raceways for fixing AFC 150 days Wed 10-12-14 Tue 02-06-15
251 5.1.2.4 Architectural & Finishing of TOM Room & flooring with reqd cutting of raceways for fixing AFC 120 days Tue 17-02-15 Mon 06-07-15
252 5.1.2.5 Masonary, Architectural & Finishing works for other area at concourse level & Platform Level 140 days Sat 28-02-15 Mon 10-08-15
253 5.1.2.6 RCC/Masonary of UG Tank , pump & Generator room 140 days Tue 05-08-14 Wed 14-01-15
254 5.1.2.7 Finishing works of UG Tank , pump & Generator room 70 days Thu 15-01-15 Mon 06-04-15
255 5.1.2.8 Site Development Works 130 days Tue 10-03-15 Fri 07-08-15
256 5.1.3 KD-01 - Partial access to E & M contractor (09-Feb-15) 0 days Mon 09-02-15 Mon 09-02-15
257 5.1.4 KD-02.1 - Completion of operartional rooms i.e. signaling room 0 days Mon 23-03-15 Mon 23-03-15
258 5.1.5 KD-03.1 - Completion of TOM room & flooring with required 0 days Mon 06-07-15 Mon 06-07-15
259 5.1.6 KD-04.1 - Completion of lift shaft & escalator pit (20-Apr-15) 0 days Mon 20-04-15 Mon 20-04-15
260 5.1.7 KD-05.1 - Completion of UG Tank , pump & generator room (06-Apr-15) 0 days Mon 06-04-15 Mon 06-04-15
261 5.1.8 KD-06.1 - Track supporting structure including track bed in station 0 days Mon 20-04-15 Mon 20-04-15
262 5.2 Najafgarh Depot Station 565 days Tue 19-11-13 Tue 08-09-15

BASELINE PROGRAMME (R2 dt 30-JANUARY-2014)

Page 4 of 5

ITD CEMENTATION INDIA LTD


PROJECT CC 50 : Part design and construction of elevated viaduct, elevated ramp and 2 elevated stations viz Dwarka and Najafgarh Depot inluding architectural finishing, water supply, sanitary installation and drainage works

ID Task Name Duration Start Finish 2014 2015


A S O N D J F M A M J J A S O N D J F M A M J J A S O
263 5.2.1 R.C.C Frame Works 389 days Wed 05-03-14 Mon 01-06-15
264 5.2.1.1 Z10- Station Piling (Najafgarh Stn.)-R3 60 days Wed 05-03-14 Tue 13-05-14
265 5.2.1.2 Pile Cap / Footing 50 days Wed 09-04-14 Thu 05-06-14
266 5.2.1.3 Column upto Concourse Level 50 days Wed 14-05-14 Thu 10-07-14
267 5.2.1.4 Stair case from Ground Floor to Concourse Level 75 days Fri 11-07-14 Mon 06-10-14
268 5.2.1.5 Beams & Slab at Concourse Level 200 days Wed 18-06-14 Thu 05-02-15
269 5.2.1.6 Stair case from Concourse Level to Platform Level 75 days Fri 06-02-15 Mon 04-05-15
270 5.2.1.7 Column upto track level 130 days Wed 23-07-14 Sat 20-12-14
271 5.2.1.8 Beams & Slab at Track Level 200 days Fri 08-08-14 Sat 28-03-15
272 5.2.1.9 Beams & Slab at Platform Level 150 days Wed 29-10-14 Tue 21-04-15
273 5.2.1.10 Track Supporting Structure 90 days Tue 17-02-15 Mon 01-06-15
274 5.2.1.11 R.C.C lift shaft, escalator pit 220 days Thu 04-09-14 Mon 18-05-15
275 5.2.2 Ancillary Buildings, Architectural & Finishing Works 310 days Wed 27-08-14 Sat 22-08-15
276 5.2.2.1 Masonary works for Operational , Signalling , telecommunication room, station control 150 days Wed 01-10-14 Tue 24-03-15
277 5.2.2.2 Architectural & Finishing works for Operational , Signalling , telecommunication room, 120 days Tue 13-01-15 Mon 01-06-15
278 5.2.2.3 Masonary Works for TOM Room & flooring with reqd cutting of raceways for fixing AFC 150 days Wed 10-12-14 Tue 02-06-15
279 5.2.2.4 Architectural & Finishing of TOM Room & flooring with reqd cutting of raceways for fixing AFC120 days Tue 24-03-15 Mon 10-08-15
280 5.2.2.5 Masonary, Architectural & Finishing works for other area at concourse level & Platform Level 150 days Sat 24-01-15 Fri 17-07-15
281 5.2.2.6 RCC/Masonary of UG Tank , pump & Generator room 140 days Wed 27-08-14 Thu 05-02-15
282 5.2.2.7 Finishing works of UG Tank , pump & Generator room 75 days Fri 06-02-15 Mon 04-05-15
283 5.2.2.8 Site Development Works 70 days Wed 03-06-15 Sat 22-08-15
284 5.2.3 KD-01 - Partial access to E & M contractor (09-Feb-15) 0 days Mon 09-02-15 Mon 09-02-15
285 5.2.4 KD-02.2 - Completion of operartional rooms i.e. signaling room 0 days Mon 01-06-15 Mon 01-06-15
286 5.2.5 KD-03.2 - Completion of TOM room & flooring with required 0 days Mon 10-08-15 Mon 10-08-15
287 5.2.6 KD-04.2 - Completion of lift shaft & escalator pit (18-May-15) 0 days Mon 18-05-15 Mon 18-05-15
288 5.2.7 KD-05.2 - Completion of UG Tank , pump & generator room (04-May-15) 0 days Mon 04-05-15 Mon 04-05-15
289 5.2.8 KD-06.2 - Track supporting structure including track bed in station 0 days Mon 01-06-15 Mon 01-06-15
290 5.2.9 Miscellaneous Works 565 days Tue 19-11-13 Tue 08-09-15
291 5.2.9.1 Finishing Works (Stone, Tile works, Flooring, etc.) 80 days Mon 08-06-15 Tue 08-09-15
292 5.2.9.2 Plumbing Works (Water Supply, Drainage Sanitary etc.) 80 days Mon 08-06-15 Tue 08-09-15
293 5.2.9.3 Fire Doors 80 days Mon 08-06-15 Tue 08-09-15
294 5.2.9.4 Misc Works & Diversion of Unchartered Utilities & Other Arch Finishing Works 560 days Tue 19-11-13 Wed 02-09-15
295 5.2.10 KD-07 - Completion of Entire Works as per the Contract (08-Sep-15) 0 days Tue 08-09-15 Tue 08-09-15

BASELINE PROGRAMME (R2 dt 30-JANUARY-2014)