MINUTES FOR PROJECTS PROGRESS

SOLIDUS ENGINEERING SOLUTIONS:


MEETINGS
Minutes for Projects Progress Meetings

Minutes for Projects Progress Meeting

Venue Date Time


Solidus Boardroom 23 July 2015 03h30

Chairperson Apologies
Kesia Chigwida Mrs Maposa
Nhlanhla Sibambo

Task Responsible Reported Action Date


Person Date

1. Evacuation Procedure
1.1 Ms Chairperson explained the evacuation procedure Info

2. Hendrina Sluice Range


2.1 We stopped work because of Safety issues.
2.2 We sent a new quotation and drawings to the client as per EM 23/07/15 31/07/15
agreement, no response yet.
2.3 We will also install the valves that are outstanding when we go
back on site.

3. Arnot Refurbishment of Electronic Equipment Rooms


3.1 Probes were removed today by New Horizons.
3.2 We are left with electrical installation, casting of concrete on the Site 23/07/15 30/07/15
floor and painting the ceiling. Manager
3.3 We have until the 5th of August to finish all the works, the client
have an updated program. 23/07/15 05/08/15

4.Alstom – Kusile Construction of Masonry Walls


4.1The project is 90% done.
4.2 5% left for plastering and 5% for painting. Info 23/07/15 31/07/15
4.2 We will be out of site on the 31st of July. 31/07/15
23/07/15
4.4 The container will be taken out of the station one to Matla and
another one to Arnot for safe keeping.
4.5 Housekeeping in progress
23/07/15 31/07/15
5. Kendal- ESP Manufacture and install By-Pass Chuters and
Launders Replacement

1
MINUTES FOR PROJECTS PROGRESS
SOLIDUS ENGINEERING SOLUTIONS:
MEETINGS
Minutes for Projects Progress Meetings

5.1 The safety file and documents requested were submitted to SM 23/07/15 24/07/15
the client and they are happy with them.
5.2 The site Manager will be meeting the Client tomorrow to
discuss the Launders and the acceptance of the scope 24/07/15
SM/Safety 23/07/15
(24/07/14).
5.3 We will be replacing all the Launders according to the Info 23/07/15 31/07/15
scope.
5.6 We are waiting for the access permit from the client. SM 23/07/15 31/07/15
5.7 Fabrication of ESP bypass in progress at the workshop.

6. Pipe Line Technology


6.1 Pipe sealing – we received 5 orders and 4 were successfully info 23/07/15 23/07/15
done. One is still outstanding at Samancor. One was done today as
a matter of emergency. Info 27/07/15 23/07/15
6.2 Pipe Freezing – 1 was successfully done at Tutuka Power Station.
Info 23/07/15
6.3 We need to improve our communication channel and do a 23/07/15
thorough job as a marketing strategy.
6.4 PLT Sales must buy their tools and equipment and keep them in
the office in case of emergency call outs. PLT 23/07/15 30/07/15

7.CONSTRUCTION OF CW BOOSTER PUMPS


7.1 We were delayed for two weeks due to the container issue and
the core drilling in the concrete. Info 23/07/15 23/07/15
7.2 We are now within the program and we are targeting to finish on
Info 23/07/15
the 29th of July. 29/07/15
7.3 Laser alignment and coupling will be done on Wednesday the
29th of July.
7.4 Written communication is still a problem on the Clients side, they Supervisor 23/07/15 23/07/15
like saying things verbally. (QCPs are signed at very stage).
Info 23/07/15
7.5 We using tools and equipment from Hendrina project as a cost 29/07/15
cutting measure. 23/07/15
7.6 We now know the quantities of grout to use per base since us no 23/07/15
longer using concrete as before. Supervisor 23/07/15
7.7 Welding is supposed to be done well because it will be 29/07/15
inspected by the client. Info 23/07/15
7.8 Hired tools are returned soon after use.

Meeting Adjourned at 16h55

Minutes Approved by: Date: 23/07/15


Chairperson