Beruflich Dokumente
Kultur Dokumente
Lal C. Jayakody
February 1995
161t7o qre..As
Ei-CS 1 ()is'
27J"
' ORARY
ABSTRACT
Construction industry presents some unique challenges and opportunities for Total
Quality Management ( TQM ). Construction process is non repetitive and generally the
workforce is not stable. A given project is dependent upon numerous parties and
influenced by social, political, legal and environmental conditions. Construction projects
are increasingly complex. Each project represents a unique design, where the location,
construction personnel, material, cost and time are variables.
Industry needs to fmd more efficient and effective ways to satisfy it's clients needs and
expectations. This report provides an overview of the construction industry and
promotes a discussion of real problems in the industry. Further it reviews Quality
Management principles and practices adopted by construction and other industries.
This study had been conducted by surveys of seven large and medium construction
companies and interviews with five project management consultants. Results showed
that nearly all companies received financial or some other benefits from QM programs,
and had recognized the need for a continuous improvement process. All consultants
emphasized the difficulty of applying TQM in construction. However one described a
possibility of applying TQM principles in a project specific level. Lack of commitment
and difficulty in cultural change were reported as main obstacles. Variations were seen
as the major reason for cost overruns and delays of projects. Apparently subcontracting
system also creates some problems.
Out of seven, five companies had experience with partnering projects. All companies
highlighted the better environment for continuous improvement process created by
partnering. However only two companies had "relatively" long term partnering
relationships, where characteristics of TQM were found. Other three relationships
studied were short term focused and limited to project by project basis, which had been
established following tender procedures. This reflects the necessity of changing the
structure and documents of project contracts to facilitate partnering. Nevertheless
partnering projects had shown impressive results, such as reduction of project costs,
schedules, increase of profits and so on. Two consultants positively commented about
partnering while other, three expressed their concerns.
More information and application experience is required to further evaluate the success
of partnering. It can be considered that a long term relationship provides maximum
benefits of partnering, while creating an ideal environment for continuous
improvement process, i.e. TQM.
ii
STATEMENT OF ORIGINALITY
I hereby declare that all the following work has been originated and compiled by the
undersigned, unless otherwise referenced.
Lal C. Jayakody
February 1995
ACKNOWLEDGMENTS
First of all I would like to thank to my supervisor, Mr. Barry Phillis who provided
guidance and gave helpful comments and encouragement throughout my work. My
gratitude is due to Prof A. C. Sidwell for generous support and for providing valuable
materials in the initial stage of the study.
Also I wish to thank to Mr. Denis Wilson, Director of Training of Master Builders
Association, the staff of Master Builders Association of SA, and Construction Policy
Steering Committee of NSW, for providing materials for the research.
I am also greatly indebted to the personnel interviewed and to the respondents to the
questionnaire for their support and valuable information.
iv
TABLE OF CONTENTS
Abstract
Statement of Originality
Acknowledgments
Table of Contents
List of Figures
List of Tables
CHAPTER 1: Introduction
1.0 Background of the Study 1
2.0 Introduction 10
2.1 History of Quality 11
2.2 What is Quality ? 11
2.3 The Evolution of Quality Management 13
2.3.1 Inspection 14
2.3.2 Quality Control 14
2.3.3 Quality Assurance 15
2.3.4 Total Quality Management ( TQM ) 15
2.4 Quality Assurance 17
2.5 Quality Audit 19
2.6 Quality Manual, System and Plan 19
2.7 Quality Systems ( ISO 9000 Series ) 20
2.8 Starting TQM from ISO 9000 23
Appendix 1 - Questionnaire
Appendix 2 - Statistical Process Control ( SPC ) - ( An Introduction )
Appendix 3 - T-Distribution ( An introduction )
ix
LIST OF FIGURES
CHAPTER 1 : Introduction
Sir John Holland, Chairman of the John Holland Construction quoted the following
reasons for inefficiencies and poor productivity in construction industry.
Too low tender prices.
Incompetent management.
Hostile on-site relationships.
Poor quality of materials and workmanships.
Inadequate site investigation.
( Holland 1988)
The findings of the NSW Royal Commission in to Productivity show a range of specific
problem areas such as : industrial disputes, substantial cost and time overruns, poor
employer-employee relationships and contractual disputes as having negative effect on
productivity in the industry.
According to Uher ( 1993 ) these are not the main causes of problems, rather that they
are the symptoms of "mismanagement" at all levels of the industry and the excessive
reliance on "subcontracting". Dombkins ( 1993 ) also contends that the Australian
subcontract system is over specialized and it is a major factor in limiting effective
communication. As fmdings of Uher ( 1993 ) provide an insight of the today's
industry, it is worthwhile to mention here briefly.
2
Excessive risk transfer : Although construction activities are subject to a variety of risk
and uncertainties, little or no attempt has been made to manage such risks efficiently.
The lack of training : There are serious problems with recommitment and training,
especially at the tradesman level.
Poor industrial relations : The larger proportion of the industry is substantially free from
industrial conflicts. However serious industrial problems have been experienced on
large projects in the central business district of major cities.
The lack of investment in research and development : While there has been an increase
in privately funded research, there is no firm in the industry that maintains a permanent
research department.
A reduced capacity of general contractors to grow : Without direct labour the potential
for the growth of the contractors has substantially been reduced as the contractors no
longer develop and retain important skills.
Keeping in mind these problem areas let us now examine, the requirements of clint's
and other project participant's of the industry. Time , cost and quality are the three
main constraints which determine the success of a project by clients. Irrespective of
size, nature or complexity of a project, the ultimate goal of any client is to achieve a
"quality constructed project" : a project completed within the budget and the schedule,
to the required quality standards and to the full satisfaction of the client. American
Society of Civil Engineer's Manual defmes the word of "quality" as 'quality is meeting
the agreed upon requirements' ( ASCE Manual ). In simple terms the "quality" is
meeting the owner's requirements. Then to say in other words "budget" and "schedule"
are also parameters of "quality".
Ensuring complete satisfaction of the customer with the goods or services provided by
the supplier is the ultimate purpose of the quality system ( Stebing 1993 ). Kanji and
Asher ( 1992 ) refer to this as "not only to satisfy but to delight the customer".
Customer only delights when his or her all requirements are satisfied. Then from a view
point of a customer it is a good job. What are the requirements of other project
participants ? Can they be satisfied until their objectives are achieved ?
US based FM! Consultancy Group tried to compare the answers to the question of
"What does a good job like ?" given by it's clients and developed a list of common
goals and objectives.
"A good job for most people is one that gets completed within budget, within
schedule and in conformance with the specs; it has a safe working
environment; workers on the site enjoy what they are doing; consultants make
profit ( Probably not only consultants, but also other project participants! ), and
the completed building meets the needs of its occupants" - Lou Bainbridge
(Director, FM! Consulting Group, US).
4
Most construction projects are developed by a project team consisting of owner, design
personnel, contractor and subcontractor. There are of course many other professionals
who play a more significant but more limited role within the overall project ( ASCE
Manual ). These various professionals aim to "satisfy" the basic requirements of
performance specifications. These are set by client needs, by laws or statutory
requirement and building codes. When individual requirements are satisfied, and a
consensus among participants reached, the process is assumed to have reached a
successful end ( Mathur and McGeorge 1991).
Satisfying the owner is only one part of quality performance, just as the owner is only
one member of the project team. Besides meeting the owner's requirement, quality
work must meet the requirements of the design professional, contractor, and regulatory
agencies or more correctly the public requirements for safe environment* conscious
and socially responsible projects ( Poirot 1990 ). This means a quality constructed
project should satisfy the requirement of all the project participants as well as public.
Total Quality Management ( TQM ) goes well beyond the traditional limits of Quality
Control and Quality Assurance. TQM is both an operational philosophy and a
methodology in which there is a strong commitment to customers, employment and
improvement ( Chase 1993 ). There is no universally accepted method to the TQM
approach. It is an ongoing process with continuous improvement, without an end.
Burati ( 1993 ) and Oswald ( 1993 ) describe TQM as a "journey", not a destination.
Peters ( 1987 ) comments that the quality can happen only if it is on behalf of client
and the people are committed to providing quality products and services. To be client
based and staying close requires, time, trust, caring and communication. The key
5
ingredient becoming client based is believing in and trusting the people who work with
you. Trust is required for open communication. Trust is also necessary to risk and risk
is necessary for innovation. Open communication is possible because the time invested
in relationship, because of trust and care about each other. With open communication it
is possible for each side of the relationship to ensure that the other side wins. This is the
philosophy of "partnering concept".
Much is said nowadays about the concept of partnering, between owner and contractor,
between contractor and supplier. The partnering concept is a way of overcoming the
traditional adversarial and litigious nature of the construction industry. It is a process of
improving relationships among those involved on a construction project to the benefit
of all .The essence of partnering is based on the fundamental human value concepts of
common sense, trust and commitment ( CPSC 1993 ). In establishing working
relationships through mutually developed strategies of commitment to the project and
communication within the team environment, partnering is attempting to create an
environment where trust and team work prevent disputes and conflicts for the benefit of
all stakeholders involved.
Brown and Beaton ( 1989 ) further iterate that anything that reduces the contentious
atmosphere or improves the adversarial relationships that develop during contracting is
well wort attention. This would be quality management in grand scale. Partnering
provides an ideal environment for TQM as it focuses on a long term approach of
improving ongoing processes rather than emphasizing individual projects or tasks (
1991).
Although there is quite a lot of material in relation to partnering and its applications in
US, only a few found in respect to the construction industry in Australia. It was
observed that partnering can be used on a project by project basis ( common method in
Australia and public sector in US ) or as a long term relationship ( used by Japanese
contractors, private sector in US and probably very few Australian firms ). Accordingly
there are some differences found between these two approaches of "partnering" ( as
defmed by Partnering Task Force of US and The Construction Policy Steering
7
Under the third phase, interviews were conducted with five Adelaide based project
management consultants with the objective of finding their views in respect to the
application of Quality Management principles and partnering to the construction
projects.
8
Phase!
Six replies were received; giving a response rate of 24%. Only 3 companies had
responded to the questionnaire. The balance three were unanswered.
One company had informed that they are in liquidation.
The second company expressed their inability to assist in research.
No remarks were found in the third questionnaire.
Phase 2:
In September 1994 same set of questionnaire was sent to some other 25 construction
companies in across the Australia, which were selected on the same basis and sources
as mentioned earlier.
At this time also six replies were received but two of them were unanswered
questionnaires.
One company expressed their inability to assist in research.
No remarks were found in the second questionnaire.
At the end of first two phases altogether seven answered questionnaires were available
for analysis. The details of findings are given in Section 12.1.
Phase 3
The comments given by project management consultants are reported in Section 12.3.
The structure of the report is illustrated in a form of flow chart in Figure 1.0.
Structure of the Report
5 10
Contra- Applic
ct Strat- of Part.
egies Japan
USA
1 4 6 7 8 9 12
Introdu Nature/ Quality TQM Partner- Part. Res.
-ction Compl- Man. in in ing Process Find.
exity of Constr- Const- Conce- Bene. &
Con. uction. ruction pt Challa- Discus-
Ind. nges sion
2 3 11
Backgr- Total Applic.
ound of Quality of Part
Quality/ Man. Austra-
Quality (TQM ) lia.
Man.
2.0 Introduction
Quality is a familiar word to all of us. However it has a variety of uses and meanings.
"The attributes of a product and / or service which, as perceived by the customer, make
the product / service attractive to them and gives them satisfaction"- is perhaps the
simplest of definitions examined ( Dale and Cooper 1992). Deming ( 1986 ) quoted
that the quality should be aimed at the needs a the customer, present and future.
According to Wallace and Vallence (1993 ) complete definition of quality will define a
product or service in terms of a customer's stated needs, unstated needs and future
needs.
More and more companies are now organaized internationally. Operational, marketing,
product design and thus quality decisions are integrated internationally. Parts, materials
and services are now routinely sourced worldwide. Inter-governmental negotiations are
increasingly concerned with product liability and quality. The philosophies, systems,
and techniques of quality management are becoming common language of government
and international trade ( Macdonald and Piggot 1993 ).
In this chapter, the definitions of quality, its evolution, and brief explanations of quality
audits, quality manuals, systems and plans are discussed. Following this is a review of
ISO 9000 series and an approach to TQM using ISO as a starting point. In fact, a
quality system provides a sound basis for further development of TQM ( National
Industry Extension Service of Australia - NIES 1990).
11
The group of scientist who developed quality control at AT&T in the first quarter are
often cited as the originators of quality. This may be true of 20th centaury US, but it is
not true world wide. The written history provides a grand procession of characters and
legends. Some of the known historical masters are:
Sun-Tzu lived sometimes during the warring states period ( 480-221 B.C.) in China
developed a set of principles that embodies the principles of Quality Management
(QM).
Aesop, a Greek slave who lived in the 6th century prepared a small sample of QM
related to the morale of people.
Number of QM concepts can be found in the various Socratic dialogues ( Socrates-
470BC to 399BC ) .
( Brocka and Brocka 1992).
To day Japanese are perhaps the most well known implementers of Quality
Management tools and techniques. Juran and Deming were the major contributors to
the Japanese revolution and the modem era of continuously improving quality.
The word quality has number of meninges. Some widely used definitions are :
"Conformance to requirements" - which is measured by the cost of
nonconformance. Poor quality or high quality has no meaning, only
12
"One form of quality is income oriented, and consists of those features of the
product which meet customer needs and thereby produce income. In this sense
higher quality costs more.
A second form of quality is cost oriented and consists of freedom from failures
and deficiencies. In this sense higher quality usually costs less"( Juran, cited in
Brocka and Brocka 1992).
The standard definition of quality used by Juran and adopted and described in ISO
8402 is:
"Fitness for purpose or use" ( cited in Fox 1993, Schmidt and Finningen 1992,
Dale and Cooper 1992).
given used : fitness for purpose. It is usually referenced to and measured by the
degree of conformance to a predetermined standard of performance".
The attributes of a product and / or service which, as perceived by the customer, make
the product / service attractive to them and gives them satisfaction is perhaps the
simplest defmition of quality. It focuses on adding value to the product /service.
From all these defmitions it is understood that the customer is the arbitrator of quality
of product or service. Most producers, customers and consumers consider quality is
more important than ever in their manufacturing, service and purchasing strategies.
In todays market customer requirements are becoming increasingly more rigorous and
their expectations of the product, service in terms of its conformance, reliability,
durability, interchangeability, performance, features, appearance, serviceability,
environment and user friendliness, safety etc, are also increasing. At the same time, it is
likely that the existing competition will be improving and new and lower cost
competitors, emerge in the market price; consequently the process of quality
improvement needs to be continuous and involve everyone in the company.
Quality is a way of organizational and everyday life, a way of doing business, living
and conducting one's personal affairs. What ever each of us does in what ever situation,
the task(s) must be undertaken in a quality conscious way. Quality is driven by our
internal mechanisms, our personal beliefs ( Dale and Cooper 1992).
The quality functions in modern organizations have evolved through four stages.
Inspection
Quality Control
Quality Assurance
Total Quality Management
2.3.1. Inspection
ISO 8402 defines "inspection" as follows :
"Activities such as measuring, examining, testing, gauging, one or more
characteristics of a product or service and comparing these with specified
requirements to determine conformity" ( cited in Fox 1993).
In 1920's QM started with the simple inspection base systems where traditionally a
company would employ teams of inspectors to examine measure or test a product and
compare it with a product standard. The basis of the system was that poor quality
product found by the inspectors would be segregated from that of good quality. This
would then be scrapped, reworked or sold as lower quality.
The inspection often failed to find the poor quality items and the customers were left
with the consequences. Later it was realized that inspection based system was:
Costly : after all someone was paid to look for bad work and someone to repair it ;
Inefficient : it often simply was not successful;
Wrong headed : in that it tended to remove the responsibility for quality away from
inspectors towards inspection ( Kanji and Asher 1993).
During the second world war when air craft technology became more complex and the
costs in both people and equipment of retying on inspection based system for such
15
things as military aircrafts were seen to be unacceptable. The change was to a system of
Quality Control ( QC).
Under such a system, control systems, product testing and documentation control
became the ways to ensure greater process control and reduced nonconformance. Also
typical of such systems were performance data collection, feed back to earlier stages in
the process and self inspection. Final inspection is still regarded as the customer's fmal
safe gn-H ( Kanji and Asher 1993).
The third stage came with the change away with the product quality towards systems
quality. The company sets in a place a system for controlling what is done and the
system is audited to ensure that it is adequate both in design and use. Typical of this
stage were quality manuals, quality planning and advanced document control, i.e.
Quality Assurance ( QA ). The fundamental difference is that QA is prevention based
system while QC is inspection based ( Kanji and Asher 1993).
The fourth stage of development remedied this by applying the concepts of Total
Quality Management ( TQM ) to all parts of the business. Typical of a company going
through a total quality process would be a clear and unambiguous vision, few
interdependent bathers, time spent on training, excellent customer relations and the
realization that quality was not just product quality but the quality of the company as a
whole i.e. TQM ( Kanji and Asher 1993).
The following model ( developed from Dale & Plunkett ) shows one representation of
this development through the phases of inspection, Quality Control, Quality Assurance
& TQM QC embraces inspection, QA embraces QC and like wise, TQM embraces
.
Quality assurance
Third-party approvals, systems audits, quality
planning, quality manuals, quality cost, process
control, FMEA, non-production operations
Quality control
Quality manual, performance data, self-inspection,
product testing, quality planning, use of statistics,
paper work control
Inspection
Salvage, sorting, corrective action, identify sources
of non-conformance
Figure 2.1 Historical development from inspection to TQM. ( Source : Kanji and
:
Asher 1993)
17
A similar model ( developed from Dale and Plunkett ) shows the four levels in the
evolution of TQM.
Policy deployment
Involve suppliers and customers
Total Involve all operations
TOM quality Process management
management Performance measurement
Teamwork
1 Employee involvement
r Quality systems ri.v.oprn.nt
QA quality planning
Quality Comprehensive quality manuals
QC
z OA
TOM
assurance Use of quality costs
Involvement of non-production operations
Failure mode and effects analysis
IAdvanced
Statistical process control
Develop quality manual
QC Process performance data
Quality Self-inspection
Inspection control Product testing
Basic quality planning
Use of basic statistics
Paperwork controls
{ Salvage
Sorting, grading, reblending
Inspection Corrective actions
Identify sources of non-conformance
For natural products, QA is attained through direct sensory examination of the product
( e.g. : freshness of the vegetables ). For manufactured product of a simple short lived
18
nature, the sensory evidence must usually be supplemented by laboratory testing. For
longer life products, more elaborate testing ( e.g. : environment, life ) is needed.
Assurance forms such as the manufacture's quality reputation, test by independent
laboratories or warrants are commonly used by manufactures.
For complex products, even data obtain from sophisticated environmental and life tests
do not provide full QA, since they fail to guard against inadequate product designs,
process designs and quality planning. They also fail to deal with those aspects of
quality performance which show up after fmal testing ( e.g. : packaging, transport,
storage, usage, and maintenance ).
To meet this added needs of QA, the manufacturer must not only produce the product
but also prepare and make available to the customer the proof that the product is fit for
use ( Juran and Gryna ).
Dale and Cooper ( 1992 ) emphasize, the objective of QA that should be for every
person to take personal responsibility for the QA of the processes for which he or she is
accountable. This includes treating later processes as customers and endeavouring to
transfer conforming products, services and documents to those customers, monitoring
quality performance, analysing nonconformance and taking corrective action to prevent
repetition of mistakes, and feeding data backward and forward. The emphasis should be
on pursuing thoroughly corrective action procedures and nonconformance investigation
with closed loop effectiveness. Tasks must be performed by as defined by the "quality
system".
The main objective of QA is to build quality in to the product / service during the
upstream design and planning processes. Quality Function Deployment ( QFD ),
Failure Mode and Effective Analysis ( FMEA ), design of experiments, design reviews,
design for manufacturability and quality audits are of considerable assistance in
pursuing this goal ( Dale and Cooper 1992).
19
The usual purposes of quality audits are to provide independent assurance that :
Plans for attaining quality are such that, if followed, the intended quality will, in fact
be attained.
Products are fit for use and safe for the user.
Laws and regulations are being followed.
There is conformance to specifications.
Procedures are adequate and are being followed.
The data system provides accurate and adequate information on quality to all
concerned.
Deficiencies are identified and corrective action is taken.
Opportunities for improvement are identified and the appropriate personnel are
alerted ( Juran and (hyna 1988).
The quality manual plus the supporting detailed procedures comprise the company's
quality system. A quality manual is a document, setting out the general quality policies,
procedures, and practices of an organization. Generally it contains a policy statement,
authority and responsibilities, organization, system element out lines and a procedure
index.
When the company's quality system is applied to a given project there is invariably the
requirement for some form of adjustment or modification ( either additions to, or
reductions in, the corporate system ) to suit that particular project. Manual plus the
supporting procedures becomes the project quality plan ( Stebbing 1993).
In evaluation of overall quality system, use is often made of reference standards issued
by regulatory bodies. Examples are MIL - Q - 9858 A ( quality program requirements),
BS 5750 ( quality systems ) and ISO 9000 / AS 3900 series ( quality systems ).
Such standards provide important benefits. They help to define the activities that are
needed to achieve quality objectives, provide criteria for evaluation and thereby increase
the objectivity of audits, and are useful during bidding on contacts by providing a
common understanding of the activities required of all bidders.
On the other hand, it has not been proved that surveys based on such standards are
good predictors of subsequent quality performance. Another caution is that some
standards omit such important elements as process capability, training, fitness for use
considerations, quality of previous products delivered etc, ( Juran and (hyna 1988).
Many companies are or will be under pressure from their customers to show proof that
they have implemented management systems complying with one or another of the
current quality assurance standards or certification schemes. This approach is now
international, as the International Standards Organization chart illustrates.
Table 2.1: International Quality Standards. ( Source : Macdonald and Piggot 1993)
22
The ISO 9000 series consists of five documents numbered ISO 9000 to ISO 9004
ISO 9000 : Quality Management and Quality Assurance Standards - Guide lines for
selection and use.
ISO 9001 Quality Systems - Model for Quality Assurance in design /
:
On the other hand number of difficulties and problems have been reported and
discussed
Whether to apply for ISO 9001 or 9002 registration, and whether it should be
sought for the whole company or just one unit / division / site.
Interpretations of various sections of the standard.
23
guidelines provided in ISO 9001 are aids in developing and maintaining the procedures
controls and disciplines required to TQM. The system should help to bring more people
in the organization in contact with quality and thus raise quality awareness. Dale and
Cooper ( 1992 ) observed that the ISO 9000 series tend to encourage the separation of
a business in to areas that complete the recording of requirements and those which do
not. Finance, management information systems and human resources are little affected,
except for training requirements. It is TQM that stimulates the business by creating the
understanding that all the component parts have customers.
The procedure suggested by Braddy ( 1994 ), illustrates how ISO 9000 series can
assist to approach to TQM.
ISO 9000 starts with a requirement for a statement on the quality policy of the
organization. This can be interpreted as a requirement for management to state the aim
or purpose of its system. This is the first step in aligning ISO 9000 with TQM.
ISO 9000 requires everyone in the company to know and understand the quality policy
and his / her contribution towards achieving it. TQM goes further and requires
management to ensure that everyone shares the aim.
24
ISO 9000 is about achieving management's quality policy. It divides naturally, but not
explicitly into three sections.
Management's role.
Operation of major processes.
Control of processes.
Management's Role
Appoint a management representative : Management is not required to delegate quality,
but ISO 9000 requires many activities to be carried out that form part of the
management of the system. It is the responsibility of the management representative that
these are carried out in the manner specified in the written description of the system.
Establish and maintain a documented quality system : In TQM, the quality system is a
statement of the means by which the quality policy i.e. the system aim is to be achieved.
ISO 9000 says that the system is the means of ensuring that out put product confirms to
specified requirements. This is not sufficient today. The system must be the means for
ensuring those customer needs and expectations are achieved, or more that customers
are delighted ( Kanji and Asher 1993 ). ISO 9000 requires the system to be
documented and effectively implemented ( Standardaization ).
Defme responsibility of people who work and manage in the system : It is important
that everyone should know his or her responsibilities within the system.
Review the system regularly for suitability and effectiveness : Management needs to
exercise continual concern about the performance of its system and to realise that it
"owns" the system. That is, only it is empowered to change the system. Management
review of the system can be the formal process of enabling change. But it needs the
help of everyone to enable it to optimise its system to achieve its aim.
The key to the start of TQM lies in what management perceives its role to be. The
description of its role in its quality system defines the style of leadership to be used and
can encourage every one to seek pride in his or her work. Management needs to realize
that most of the problems are caused by the system and not by individuals (Deming
1986).
25
Design : The purpose is to ensure that the completed design meets and has been
verified to meet specified requirements. ISO 9000 has some good requirements to
ensure that the design process produces designs that confirm and have been verified to
conform to specification. There is no acknowledgment of the need to encourage
innovation. This is a vital issue in TQM and must be addressed in all operations. ISO
9000 does not require the marketing process to be described. TQM needs to include the
marketing process as part of the system.
Product and Installation : The purpose is to ensure that the production and installation
processes are "controlled" by what ISO 9000 calls work instructions and planned
arrangements. This is an excellent starting point for continual improvement. TQM
advises that the wealth of knowledge and experience of all those involved with these
processes should be used to improve them continually using the PDCA cycle thus
reducing variations.
PDCA cycle
Plan : to make decisions about what is required to be done : to set an objective and
standard.
Do : to act or to put the plan into effect using worker's input ( e.g. : knowledge, skills
and comments ).
Check : to see that the results of doing match what was planned i.e. to evaluate.
Act : to build on successful changes so that continuous improvement occurs.
26
Figure 2.3 : PDCA cycle - The Shewhart cycle and Deming cycle. ( Source : Wallace
and Vallence 1993)
NIES ( 1990 ) observes that the QA can be used to underpin the Deming cycle to
provide continuous improvement. This means to improve in a series of small steps using
the company's quality systems to make sure that the standard of products or services is
maintained and does not go back wards ( cited in Wallace and Vallence 1993).
quality
assurance
continuous
imcremental improvement
Inspection and Testing : ISO 9000 lays great emphasis on inspection and testing and
requires that all the planned tests have been completed before product is released.
Progress towards TQM begins when inspection is seen to be wasteful, since it adds cost
but not value. More important, the process itself is wasteful if it produces non
conforming products. The way ahead is to improve the process so that it will produce
progressively less non conforming product and eventually none. This is the objective of
continual improvement, which can be achieved by using PDCA cycle over and over
again.
Control of process
Corrective action : There are several requirements of this clause in ISO 9000.
Investigate cause of nonconforming product and the corrective action needed to
prevent recurrence - TQM uses PDCA cycle.
Analyse all processes, concessions, quality records, service reports and customer
complaints to detect and eliminate potential causes of nonconforming products - It
is the process for the collection of the feed back information on how effectively the
processes, making up the system, is working and is thus the start of TQM process
of continual improvement.
Initiate preventive action to deal with problems - TQM embraces this requirement.
Plan and undertake audits : ISO 9000 requires that audits be undertaken aimed at
establishing whether processes are being run in the way described in the written
procedures. TQM points out that most of the problems are due to the systems rather
than to individuals and therefore require management to work on the system to resolve
them.
Plan & provide training : ISO 9000 requires the company to ensure that people are
trained to undertake the tasks to which they are assigned. TQM points out that training
must be planned to meet both the needs of the company and the individual is developed
and the necessary skills are available to the company when needed. This implies long
term planning.
28
Calibrate inspection and test equipment : ISO 9000 requires that measuring equipment
be regularly calibrated. TQM endorses the implied needs for adequate accuracy of
measurement, but point out that the precautions listed by ISO 9000 may not be
exhaustive.
Statistical techniques : This clause is not mandatory. There is a little to point the
company in the direction of statistical process control, which is considered by Deming
1104K
kxt...... 1 to be a powerful tool in analysing the performance of the system and its
processes
The performance of the system and its processes in achieving these aims of the system
has to be continually fed back and used to indicate where improvements are required.
The following recommendations are made by Bradely ( 1994 )
The ISO 9000 quality system must be extended to include the marketing and sales
process.
The measurement of process performance must be extended and a culture of
continual improvement established.
All employees must be encouraged to participate in improvement through project
groups, quality circles etc,.
29
3.0 Introduction
TQM is a continuous improvement process which involves the cooperation of everyone
in an organization and associated business processes to furnish products and services
which meets the needs and expectations of customers.
A number of other experts also have contributed to the recent evolution of quality
management. Most notable among this is Armand Feigunbaum, who was the first to
start using the word "total' in relation to quality. Though the Japanese quality revolution
was originally based on the work of Deming and Juran, Japanese are adding their own
experts : Kaori Ishikawa, Genichi Taguichi, Musaalci Imai, and Shigru Mizuno
(Macdonald and Piggot 1990).
existing organizational framework, but his ideas benefit from Japan's historically better
access to top management. Lately Juran has also called for top management.
Further Juran proposed a three step process for continual quality improvement,
refereed to as Juran's trilogy.
Table 3.1 : Juran's three-step process in quality improvement. ( Source : Wallace and
Vallence 1993)
Evaluate the cost of quality and explain its use as a management tool.
Raise the quality awareness and personal concern of all employees.
Take formal actions to correct problems identified through previous steps.
Establish a committee for the zero defects program.
Train all employees to actively carry out their part of the quality improvement
program.
Hold a "zero defects day" to let all employees realize that there has been a change.
Encourage individuals to establish improvement goals for themselves and their
groups.
Encourage employees to communicate to management the obstacles they face in
attaining their improvement goals.
Recognize and appreciate those who participate.
Establish quality councils to communicate on a regular basis.
Do it all over again to emphasize that the quality improvement program never ends.
( cited in Brocka and Brocka 1992)
Ninety five percent of the problems in a company can be solved by the seven tools
of quality control.
Data without dispersion information is false data ( e.g. stating an average without
supplying the standard deviation ) .
Quality goal Zero defects Minimize cost of Zero defects Zero defects
quality
Project selection Pareto error Cost analysis Cost analysis Cost analysis
analysis
How to measure Direct Cost of quality data COQ and direct Direct
improvement measurement measurement measurement
Statistical analysis High use by all For lower Mixed High use by all
management
Table 3.2 : Comparison of Quality Management strategies. ( Source : Vogel and Mills
1992, cited in Lu and Sohal 1993)
34
In all these strategies "management commitment" and "involvement" are the key issues
to quality improvement. According to Macdonald and Piggot ( 1993 ) the applicability
of different approaches is dependent on the "corporate culture" and nature of a business
judged on a national or location basis.
Gitlow and Gitlow ( 1987 ) suggest to disseminate this vision statement to management,
employees, vendors, customers and stakeholders to get their input for possible changes.
practices, philosophies and tools. In effective communication will doom the most clever
of Quality Management initiatives. Understanding and refining skills for written, verbal
or non verbal communication is an ongoing process for everyone.
improvement for some time. ( "Kaizan" ). This idea fits hand in hand with team
building approaches such as quality circles ( Brocka and Brocka 1993).
Circles are quality improvement and self improvement study groups. A primary
contribution of quality circles in Japan according to Juran, has been in improving
workers knowledge and skills and developing interest in the job by providing
opportunities for planning and decision making not present in the daily routine.
To reduce costs and increase productivity the focus has to be projected on process that
produces the product. Improving the process reduces or eliminates variation and
increases the uniformity of the product. This results in lower cost through reduction of
scrap, rework, and complexity ( Brocka and Brocka 1993).
Customer / Vendor relationships : The "hearing of the voice of the customer "has
become a key phrase in the past few years. Listening to the customer requires listening
throughout a product life cycle, from requirements definition to maintenance after sale.
Listening to the customer entails surveys, research, and the implementation of tools
such as Quality Function Development ( QFD ).
Empowering the worker : This means enabling a worker to achieve his or her highest
potential. A key strategy in empowering employees is to allow them ownership of a
tasking, project, or division. Ownership implies trust and it requires a delegation of
authority commensurate with the responsibility of the task. Ownership also demands
that the final resolution of the tasking be in the hands of the owner.
Generally these principles can be applied to any organization, which commited to the
continuous improvement process. According to Brocka and Brocka ( 1992 ) this
method is particularly suitable for a organizations which are initially making the move to
a QM program.
Each of the principles can be used to drive the improvement process. To achieve this,
each principle is translated into practice by using two core concepts. The concepts show
how to make the principal happen. These concepts are :
Customer satisfaction.
Internal customers are real.
38
la
4i -0
'ro
0.,, T.
sc-- , s
P., 7 6.3 z °S5 0..,,,
s,q,
oc :250 o
4-1
.... !)
q7 .e ,
g.' al
laC.
s',1>
1r
,
.,) 4.41,
e
Figure 3 .1: Pyramid principles of TQM. ( Source : Kanji and Asher 1993)
Each individual employee or team plays two roles in the quality chain as an internal
customer and as a supplier. Each person in the quality chain has to ask him or herself
who their immediate suppliers and customers are and what they actually require.
39
The core concepts of TQM that relate to "delight the customer" are "customer
satisfaction" and "internal customers are real".
2 Management by fact : Having the facts necessary to manage the business at all levels
is the second principle of total quality. Giving that Information to people so that
decisions are based upon fact rather than "gut feeling" is essential for continuous
improvement. Another possible focus for improvement is reduce variations in business
process. A process is a combination of methods, materials, manpower and machinery
that taken together to produce a product or service.
Taylor ( 1911 ) believed that the major responsibility of management was to find the
best way to do a job and then train the worker to do it that way. TQM extends this
concept of finding the best way to do a job to the entire system.
3. People based management : Knowing what to do, how to do it and getting feed back
on performance are all part of encouraging people to take responsibility for the quality
of their own work. Involvement and commitment to customer satisfaction are ways of
generating this. The third principle of TQM recognizes that systems, standards and
technology themselves will not mean quality. Therefore, the role of people is vital.
Likert ( 1967 ) proposed that a typical organization would operate more effectively if it
was thought of as a cluster of groups linked together with managers functioning as
"linking pins". Each manager in Likert's model could be a leader of one group and
member of a second group. In such a scheme, communication would flow more easily
and decisions across departmental lines would be made more realistically than in a
straight bureaucratic system. TQM incorporates this same philosophy. Hierarchal
relationships are minimized and team relationships are fostered ( Schmidt and
Finningen 1992 ).The core concepts that relate to "people based management" are
"team work" and "people make quality". .
40
il -
the "continuous improvement cycle" and the "prevention".
Benefits
Employees feel that they are vulnerable and their motivation and commitment
increases as a result.
Improvement in the quality of goods and services.
Principles and processes can be applied to a wide range of organizations.
The organizations reputation increases and so does their profitability.
"Waste" reduction ( in both goods and services ).
Disadvantages
Any changes to the way things are done is a difficult and prolonged process.
Changes are hard to sustain.
May become dependent upon one or a small group of charismatic individuals.
TQM is not closely enough related to the implementation of suggestions that will
achieve competitiveness.
Seems to be a management - driven or top down system.
No implementation strategy has yet been developed so that everyone benefits
immediately from its introduction.
( Wallace and Vallence 1993)
41
CEO Briefing
Planning Workshop
Review of First
Stage Projects
Consultant Mansii-ci-
Technique
Training
Advanced and
Specific
Annual Review
& Audit
There are ten steps in the first stage of the TQM " How to "approach.
Initial review and diagnostic are conducted by a consultant to understand the
current situation and issues to be addressed. This step ends with the preparation of
consultant's report for discussion with CEO.
In a briefing session CEO and consultant develop a shared vision and decide the key
issues to be addressed in TQM program. Subsequently set the timetable for future
workshops and choose members of the Implementation Planning Team.
The next step is a senior management vision setting workshop. It aims at an
enhanced awareness of TQM, a shared commitment for its adoption and a
knowledge of how to proceed.
Followed by is a middle management vision setting workshop with similar contents
as to the senior management vision setting workshop.
A planning workshop is held for the Implementation Planning Team to identify the
specific actions required to facilitate the "cultural change" in the organization. Issues
( choices of projects ) focused in the planning workshop are :
Infrastructure development
QA and Accreditation
Process improvement
In the next step, basic techniques training workshops are held for those people in
the organization who attended vision setting workshops to train participants in the
basic techniques and tools of TQM, communication and team skills.
This is the first stage project. From here on, the programs aim at a process of
continuous improvement. Regular feed back and review sessions, under the
guidance of the Implementation Planning Team, will allow to monitor the progress.
The next step is supervisors and operative awareness workshop for all supervisors
and shopfloor people, which is similar to the vision setting workshop.
Here is the review of first stage project. After an appropriate time ( e.g. : 6 months,
depending upon the size of organization ) consultants undertake a formal review of
the first stage projects in process improvement, structural development and QA /
Accreditation. This review also creates a format for future annual management
reviews within the enterprise.
Upon completion of this stage, the Implementation Planning Team moves on to
identify and create second stage projects in both process improvement and
structural development. This step builds on the previous nine steps in enabling
TQM to proceed to a largely self managed phase.
Achievements of QM
Private sector companies tended to claim a higher degree of success than public
sector.
The main impact of QM is in raising staff awareness of quality issues.
Improvements in customer satisfaction, complaints and team work were among
other benefits.
Most of the organizations felt that quality management programs had achieved a
reasonable degree of success, but over 10% reported adverse effects, particularly
on productivity, cost efficiency, profitability and employee morale.
44
A TQM program that does not address this element runs several risks.
Lack of cohesive forces which drive quality throughout the organization.
Conveying the massage that quality is foreign to the business.
Missed opportunity to strengthen team work at senior level.
Performance measures within the organization are identified and measured against
customer expectations.
Data from surveys are communicated throughout the organization.
As a result, most people who have little interaction with external customers remain
relatively ignorant about customer expectations and perceptions.
Cross - functional teams remain useful for projects which require expertise from a
number of areas. These projects are typically of a technical or a business nature.
7. QA system
Most of the manufacturing organizations studied were accredited, or in the process of
gaining accreditation, to the ISO 9000 / AS 3900 standards. Among the benefits quoted
are
Disciplined approach to business administration.
Increased awareness of the quality moment.
Upto date and documented procedures.
Improved communications and team work within the organization.
Sense of achievement and confidence in project management.
Few service organizations believe there is a need for formal accreditation in their
industry, particularly as the final decision on quality is made by the end customer.
Several factors may contribute to this belief :
Perception that the standards are only appropriate to manufacturing.
Difficulty in defining measures for service performance.
No contractual requirement by customers for formal accreditation.
Belief that formalization introduces bureaucracy.
In general organizations which did choose a suitable consultant were able to achieve a
continuous improvement culture with fewer hiccups. Some advantages offered by
external consultants are :
Availability of experience.
Objective perspective by person external to the organization.
Knowledge of what not to do.
Change catalyst.
The choice of consultant, if the organization decides to employ one, is critical to the
success of the TQM program.
It was also observed that organizational theory is seldom included as part of training in
TQM. It is important to analyse the organizational climate before embracing on a TQM
program. There are other areas where improvement can be made to the quality moment
in Australia. Consultants and the industry leaders together need to strengthen their
knowledge of management strategy, organizational theory and the new quality
techniques. Knowledge in TQM alone is insufficient - the case studies show that the
most successful organizations are those able to manage several improvement programs
concurrently ( Lu and Sohal 1993).
48
4.0 Introduction
Construction is the worlds largest and most challenging industry. A construction project
involves starting with nothing but an idea and creating a permanent and lasting facility
that meets aesthetic, quality, safety and functional requirements. It is the contracting
part of the industry which undertakes to organaize, move and assemble the various
materials and component parts so that they form a composite whole of a building or
other work. The product which the contracting industry is providing is basically the
service of moving earth and material, of assembling and managing the whole process.
This chapter provides an overview of the nature and the complexity of the construction
industry. Unlike manufacturing, construction industry inherent some special features
such as uncertainty, risk and the efficiency and effectiveness of communication among
the project participants throughout the building process which directly affect to the
success of the project. Misunderstandings, lack or poor communication between project
participants, use of incorrect or improper documents, drawing etc, often lead to
unnecessary claims and dispute which finally end up with arbitration or litigation. These
issues are briefly discussed in this chapter.
Size is important because changes in out put of the construction industry affect the size
of the national product both directly and indirectly, but it also means that what is
happening to the construction industry must be a matter of national concern.
Construction is an investment goods industry, i.e. its new products are wanted, not for
their own sake, but on account of the goods or services which they can create or help to
create. Construction is very subject to fluctuations in demand, for most of its products
will be required only if certain other factors are favourable.
49
The dependence of government as a client means that government is able to reduce the
demands on the industry by action on its own proposed projects, in addition to that
indirect control it is able to exert on overall investment through control of credits and
interest rates.
The effects of the construction industry on the economy and of the economy on the
industry occur at all levels and in virtually all aspects of economic life. According to
riiiiebrandt (1985) the four main ones are, however, the muluummp of the economy
and the industry
in demand an out put
in employment and incomes
in balance of payments
in the level of prices.
It is unfortunate for construction industry that the ways in which it is easiest and least
painful for the government to injects new factor into the economic cycle have been
found to be raising the rate of interest and restricting credit, so that it becomes more
difficult and more expensive to borrow money; reducing purchasing power through an
increase in taxation; and reducing its own spending, especially capital spending which
easier to postpone than current expenditure. The construction industry is affected
directly or indirectly by all these measures ( Hillebrandt 1985).
The final product of the construction industry is large, heavy and expensive. It is
required over a wide geographical area and is for the most part made specially to the
requirements of the each individual customer. A large part of the components of the
product are manufactured elsewhere by other industries. It is largely these product
characteristics which determine the structure of the industry, including the large number
of dispersed contracting firms and the separation of design in professional offices from
construction firms, which has important repercussions. The nature of the product,
together with the structure of the industry it encourages, also means that each contract
often represents a large proportion of the work of a contractor in any year, causing
substantial discontinuitys in production functions. The work of the contracting part of
the industry involves the assembly of a large variety of materials and components with
implications for the relative importance of scare resources.
Size of contract is clearly determinant of the number of firms who can undertake work.
A large contract requires more of all inputs than a small contract. Capital is particularly
important in this connection. Complexity of contract is another determinant of the
potential competitors. A complicated building can be constructed only by firms having
control over the technical expertise required.
Generally the firms do not operate out side a certain geographical area of an operation
because the costs in terms of transport of materials, plant and men become excessive in
relation to total costs. If however the building is very complex, other things being equal,
the cost per sq. m. is likely to be large and the costs of the transport decrease in relation
to the total cost of the project.
Size also has an effect. For small projects some distance away it would not be
economical to set up a local recruitment office, because their fixed cost would be too
high in relation to the total cost of a project. For large projects, however the fixed costs
could be spread over a large turn over and the existence of a local office of the project
would enable the variable costs of transport and control to be substantially reduced
(Hillebrandt 1985).
among different parties and fmally lead to delays, stoppage and abortive work in the
construction industry.
"Risk" arises when the assessment of the probability of a certain event is statistically
possible. Risk is insurable. Uncertainty arises when the probability of the occurrence or
non occurrence of an event is indeterminate. Uncertainty is not insurable ( Knight
1921). There is no hard and fast line between risk and uncertainty. The occurrence of
some events may be moved from the category of uncertainty to that a risk by better
information.
Barrell, Nixon et al ( 1988 ) have recommended in their research report "Strategies for
the Reduction of Claims and Disputes in the Construction Industry" that the party best
equipped to control a particular risk should be allocated that risk.
A study of the building industry undertaken by Higgin and Jessop ( 1966 ) of Tavistock
Institute, UK provides some useful thoughts about the nature of "interdependence and
uncertainty" of the industry. Findings from this study is summarized below :
Uncertainties can arise within the building process as a result of the interdependence
decisions. The essence of building in the building process is the relevance of different
streams of information to each other in particular contexts.
52
Uncertainties can arise from out side the building process as well. Higgin and Jessop
(1966) identified two sources of uncertainties.
There are uncertainties engineered by the action of those not directly involved in the
building process such as government departments, planning authorities, public
bodies, client organizations and even the general public.
There are uncertainties which stem from resources : labour, equipment and
materials. These uncertainties arise mainly because there are large number of
building processes competing for the same resources. Although these uncertainties
are out side any one building process, they do arise from within the building
industry.
Attempts to lessen these uncertainties are made in various ways. For example, the
nomination of sub contractors, selective tendering, negotiated contracts, and the
package deal tend to reduce the uncertainties between the client I design team group
and the construction team. The package deal or design and construction contracts,
allows the builder to contribute to decisions on design, thereby reducing uncertainty in
the field.
public, and the government on the other hand, it is evident that there is not likely to be
single generally accepted criterion would have to take account of the costs and
incentives of all parties as well as of matters of time, security, amenity, functional
success, environment contribution, rateable value, prestige and so on.
Labour : It is well known that building labour is in short supply and that certain
specialist tradesmen are hard to come by in certain areas. Mass production and
technological advances in the material supply have combined with increased wage,
rates so that labour is now the most expensive and volatile resource affecting a project
success.
Equipment and material : The delay and disruption also caused by the availability,
storage of manufacture and supply of materials. It is not implied that only suppliers are
to blame. Orders placed too late, insufficient attention to detail, wrong schedules,
revised drawings, changed construction programs and incorrect bills all add to the
confusion. The root of the problem is the fact that high demand puts greater pressure
on supply system.
There is probably no single characteristic, such as time, cost function, amenity, which
will be appropriate to measure the efficiency of a building process. The ideal situation
would be a set of building operations managed as perfectly as possible in the interest of
the client / user / community complex. As suggested by Higgin and Jessop (1966) the
conditions would include :
Assembly of skills ( managerial, technological, and analytical ) if necessary drawn
from out side the industry.
Removal of artificial barriers in management. The designers would be a part of the
site management team.
Adequate management tools. Planning and progress data would be continuously
revised and made available to all parties.
Abolition of conflicting interests by a structure of incentives to minimize
"defensive" action.
Resources for obtaining off site information.
Insulation from external uncertainties, for example ,other projects.
Complete record for later analysis of all events and actions quite separate from any
management records.
Higgin and Jessop 1966)
54
4.2.2 Communication
A successful project is the result of a formation of an efficient an effective project team
where trust cooperation, mutual respect, mutual acceptance and open communication
among the team members are key characteristics. Communication is the glue that binds
all the project team members together.
In fact the root cause for most of the inefficiencies, claims and disputes in the
construction industry is due to the lack of coordination or communication among
project team members.
Apart from the basic two types of communications, non verbal communication ( body
language ) is also used in the negotiation process. According to Riggenbach (1986)
more than 60% of all communication is non verbal. The impact of the body language
during negotiations can be either positive or negative, depending on ones awareness of
gestures. The impact of presentation can be determined by observing the non verbal
communication of opponent. Through the observation of body language it can be
determined whether the opponent feels superior or concerned, or holding back,
doubting integrity, accepting presentation, thinking negatively but talking positively,
respecting, wanting to make all the decisions, domineering, seeking reassurance or
making decisions ( Riggenbach 1986).
All these forms of communication take place in the building process among various
participants in different levels. Major problem areas associated with communication in
the building industry had been identified in a pilot study undertaken by Higgin and
Jessop ( 1965 ) of Tavistock Institute, UK. These communication related problems are
relevant to the different professionals in the building process in varying degrees.
Higgin and Jessop ( 1965 ) noted that out of the five problems outlined, the first two
affect in some degree all members of the building team. The third mainly affects
architects and consultants. The fourth again affects all members, but mainly quantity
surveyors, while the fifth mainly affects builders, subcontractors and those on the
supply side.
55
Communications within the design team : Sufficient thought and time does not seem
to be given to ensuring, either as a design team brief or during the designing processes,
that all who must contribute understand the common objective similarly and fully.
There is seldom a full awareness of all the steps necessary to realize an optimum overall
out come without loss of time, and the means of ensuring design co-ordination is often
not clear.
Communications related to contract : There is a very wide and very complex variety
of ways in which the members of the building team can be contractually related to each
other. The nature of relationships is defined afresh for everybody as any project
develops, at the price of delays and confusions. The frank sorting out of these
difficulties at the commencement of a contract is prevented by the silent reservations of
all parties about points of possible disadvantage each feels he must watch for.
However conflicts and disagreements can occur among project team members during
the project, regardless of members competence or the level of communication. Hensey
( 1987 ) emphasizes the greatest need in pursuing the resolution, or even the
understanding of disagreements as "patience" and "goodwill" which overcome the
natural tendencies toward haste, sarcasm or blame - placing in oneself and others.
56
The causes of problems are widespread and relate to the attitudes, policies, practices,
actions and errors of clients, consultants and contractors. There is no single source of
problems which generate claims and disputes. The following general sources of claims
and disputes have been identified by Barrell, Nixon et al. ( 1988 ).
Lack of coordination and quality of contract documents.
Adversarial relationships.
Going to tender with inadequate documentation for a traditional lump sum fixed
price contract.
Attempting to fast track construction on a traditional lump sum fixed price contract.
Problems in contract formation.
Problems arising from late supply or errors, omissions and ambiguities in contract
documentation.
Delays by the client or those for whom the client is responsible.
Variations.
Bills of Quantities.
Nominated sub contractors.
Latent conditions.
The role of architect / engineer in contract administration.
The role of architect / engineer in dispute resolution.
Untimely presentation of claims.
Poor quality claims.
Poor management of claims and disputes.
Inadequacies of dispute resolution systems.
The problems of claims and disputes in the construction industry are a worldwide
phenomenon. However it is considered that many of the problems experienced in
Australia arise from the traditional English system of contracting, which can lead to
adversarial relationships.
It is not within the scope of this study to describe each of the sources of claims and
disputes in detail. However some of the selected issues are discussed here.
57
The rules of "Do's" and "Dont's" of specification writing contained in the Institution of
Engineers, Australia ( 1988 ) publication is worthwhile to mention here ( cited in
Turner 1990).
Don't use archaic specifications - update them frequently. Do make them adequate,
clear and concise with minimum ambiguity.
Don't force the contractor to accept extreme, unreasonable or hidden risks.
Ensure that anticipated contingencies are addressed.
Don't amend drawings without checking for discrepancies between individual
drawings and between drawings and specifications.
Computer Aided Drafting and other modern aids will ensure fast and accurate
amendments to plans and specifications.
Don't include computer print outs without checking to ensure that they are
compatible with the intent of design.
Give all relevant reports and information and state the standards and quality controls
to be used, together with clear statements of the extent to which they can be relied
upon.
Don't expect contacts to be completed in impossible time spans and don't provide
unrealistic escalation clauses.
Clearly define any special items of plant or equipment to be used or particular
operator skills required.
The role and powers of the superintendent must be clearly defined but he should
not have wider powers than that are necessary.
Clearly set out the controls to be exercised by other authorities.
Define the limits of each subcontract clearly, its relationship with the others and
with the head contract. Careful consideration must be given to the position of
nominated subcontractors.
Don't ignore weather conditions and their effect on costs and extensions of time.
The question of access and the provision of other services must be covered.
Barren, Nixon et al ( 1988 ) also noted that the errors or ambiguities in contract
documentation and its late delivery as the greatest cause of claims, disputes and
litigation.
58
Quick ( 1991 ) further iterates the importance of "getting the documentation right", as
the most important step to avoid claims and litigations. Getting the documentation right
means, among other things such as :
Ensuring that the principal's commercial objectives and performance requirements
for the project are adequately defmed in a brief to design consultants.
Paying design consultants realistic fees for the work which they are required to
undertake, and allowing them sufficient time to undertake the work.
Getting design consultants to agree to redline their fees if there are cost increases
during the construction period for which they are responsible.
Co-ordinating the work as a whole of the design consultant so that ambiguities in
the documents they prepare are eliminated. A related aim should be to ensure that
design is co-ordinated with construction.
Making the allocation required of contractual obligations and risks and ensuring the
contract documentation accurately records this allocation.
Avoid routine use of Bills of Quantities in tendering, and making sure such bills are
measured from completed tender documents in accordance with an agreed method
of measurement.
Minimizing or an avoiding the use of nominated subcontract system. Options to the
system include providing a list of acceptable specialist subcontractors to the
contractor or engaging the subcontractor seperatively and putting an obligation for
co-ordination of both the subcontractor and builder, or entering into one of the
alternative contracts such as construction management or project management
(described in Chapter 5).
Trying to anticipate and quantify delay and delay costs.
Avoiding standard form general conditions of contract in "fast-track" projects and
making clients aware of the implications of varying work.
Considering how disputes are best resolved. In particular this means considering
possibilities such as providing for mediation as a preliminary step in the resolution
of any disputes, providing for contract adjudicator rather than the superintendent
administering the contract to resolve disputes during the construction process, or
providing for procedures such as non-binding expert appraisal to ensure a
negotiated settlement ( further explained in Section 4.4 ) ( Quick 1991).
59
4.3.2 Variations
The major source of claims and disputes relate to variations. There are variations which
are required to overcome unforseen problems. There are variations which result from
errors in and late supply of documents in relation to both "fast track" and normal
projects. Variations also arise as a result of changes in client requirements.
Attempts to use traditional lump sum contracts in relation to "fast track" projects, where
the design is not fmalised and fully documented at tender time, are likely to be
disastrous with respect to variations. It is unreasonable to expect that "fast tracking" can
be done under a traditional contract without claims and disputes over variations..
Therefore greater focus needs to be placed on the quality of documentation to avoid
variations ( Barrell, Nixon et al. 1988 ).
A vital factor in the successful control of variations is the timing of price negotiations.
Only too often because the pressure for physical progress with the work and the
complexities in assessing the price change, instructions are given to the contractor to
make the change, with the alternation in price to be negotiated later.
Marsh ( 1988 ) suggests to adopt the following sequence of events in relation to control
variations.
Client decides that a particular variation would be desirable.
Contractor is instructed to assess the effect of the proposal variation in terms of :
- price
- time
- performance
Contractor submits his proposal under the above three headings.
Clint decides whether he can afford the variation taking all factors in to account.
If client decides to proceed with the variations, then he negotiates amendments to
price, time for completion and specification.
Client issues formal variation order in writing.
Contractor proceeds with the work.
60
Clints are often faced with difficult arrangements to resolve between the contractor and
the nominated sub contractor with respect to practical, contractual and commercial
matters. These include objections by the head contractor to the nominated
subcontractor, disputes between both the head contractor and the nominated sub
contractor as to incompatibilities in their respective proposed programs, disputes over
the quantum of security, liquidated damages etc,.
However the client and its consultants may gain the advantage of design input from the
nominated subcontractor, at no cost, during the design development and documentation
phase. The client maintains control over the quality of important aspect of the work,
through selection and nomination of competent specialists contractors. In consideration
of nomination, specialists contractors often provide input into the development of
feasibility studies, estimates and budgets for the project.
In relation to major projects, clients often undertake site investigations and testing
programs for the purpose of designing the project. When undertaking and evaluating
the results of such investigations, it is vital to address the issue of risk management for
both the design and construction phases, in the interests of the project and the client
(Baffell, Nixon et al 1988, Hillebrandt 1985, Turner 1990 ).
The Institution of Engineers, Australia, publication "Guide lines for the provision of
geotechnical information in construction contracts" ( 1987 ) recommend a balanced
approach to risk allocation between the parties, in the event that latent condition
problems are encountered. The guidelines make number of suggestions to minimize
such risks.
In countries such as Japan, where the traditional English system has not been used,
there is a considerable opposition to the role of the architect / engineer in contract
administration. The architect / engineer are seen as an independent to negotiations with
the client to resolve problems which arise in construction and as a source of both the
creation and prolongation of disputes.
Barren, Nixon et al ( 1988 ) recommend that the contract administrator should not be
responsible for the resolution of disputes. This role should be performed by an
independent contract "Adjudicator" ( Barrell, Nixon et al 1988).
62
As far as the parties to building contracts are concerned, disputes are best avoided or
resolved amicably between the parties.
"The most desirable way of resolving any dispute is that it should enjoy the
confidence of the parties as a method likely to arrive at a just answer The
most desirable way of resolving any dispute is for the parties themselves to
reach a mutually acceptable compromise. This is likely to be quicker and
cheaper; no third party may be involved or even in form of the dispute; and
future business relations can be maintained. " - Norman Royce
Barren, Nixon et al ( 1988 ) view the fundamental problem with arbitration in the
industry as the nature of disputes refereed to arbitration. The increasing extent of
arbitrations which involve a determination of the parties legal rights and obligations,
rather than a determination of matters such as quality is an important factor in the
deterioration of the efficiency of the arbitral process in the industry.
A frequent criticism of the arbitration is that arbitrators do not decide the rights of the
parties, but incorrectly reach compromise decisions, which satisfy no one. The
problems of litigation and arbitration in terms of costs, delays and disruption have lead
many to consider "alternative dispute resolution techniques" prior to and in lieu of
arbitration or litigation.
Work Scope Definition Clauses : Those which describe the physical work to be
completed, the minimum standards of acceptability, and procedural guide lines for
completing the work, along with supporting drawings and specifications. Most
problems with these clauses stemmed from omissions, ambiguities and
inconsistencies.
Change Clauses : Those which deal with additions or deletions, and with variations
or omissions in design, construction, and management efforts. These clauses
provide a method for dealing with an event that was not anticipated in the original
contract. Disputes involving change clauses were found to affect negatively the
project performance parameters of cost, schedule, quality and safety. Problems
most often encountered with construction change clauses involved definition and
negotiation of costs, dispute resolution, and time required for approvals. A lack of
well defined procedures often compound the problem.
Project Control Clauses : those which involve mechanisms to monitor and approve
project performance, to confirm acceptability, and to correct unacceptable
variations. Failure to reach a mutual understanding on these matters in pre-
construction negotiations was a frequent source of disputes ( cited in Band, Nixon
et al 1988).
The results of the study of professional opinion within the construction industry
regarding the causes of disputes, the types of owners that are most often involved in
disputes, roles of the attorneys in disputes resolution, are as follows :
Many construction disputes arise because society is adverse to accepting the results of
risky situations. Instead of accepting these bad results, citizens often file law suits.
Bccaus- construction is zi risky business, disputes arise frequently.
Private owners are usually preferred over public owners. However in many cases, the
experience and competence of the owner's staff with regard to construction may be
more important than public or private status. Owners with experienced competent
construction staffs are preferred over those with inexperienced and incompetent staffs.
Similarly, construction experience is a desirable qualification for an attorney who is
involved in construction disputes.
If possible, involvement in high risk projects should be avoided ( such as "fast tracked"
projects or those with poor specifications or field investigations - many disputes result
from changed conditions in these. two categories). Involvement with owners
experiencing problems with payment or employing an inexperienced construction staff
is also undesirable. Firms should be staffed with experienced people who communicate
well and treat others with respect. Also, it is important to develop contracts that share
risk in a fair manner among all parties. The possibility of retaining an attorney to
develop problems solutions before disputes arise should be considered. Finally, if it is
necessary to retain an attorney to resolve a dispute, it is important to choose one who
has construction experience.
66
5.0 Introduction
As the construction industry is an evolutionary stage concerning management concepts
and project delivery systems many of the clients needs have not been properly
considered. Innovative planning will be required to survive, to grow, and to meet the
needs of clients of construction projects ( Kirschenman 1986).
Different types of project delivery systems are used around the world. As observed by
Barrel!, Nixon et al ( 1988 ) some practices in the industry which are historical and
cultural, rather than based on the most efficient method of dealing with the particular
issue. Each system inherent it's own advantages and disadvantages. The traditional
English system is the most widely used contracting system in Australia.
Masterman ( 1992 ) catogarizes most wide/37 used procurement systems into three
groups.
Separated and co-operative procurement systems: where the responsibility for the
design and construction aspects of the project are the responsibility of separate
organizations. This category contains one main procurement system : the conventional
method ( traditional ). Variants of the conventional system include : two stage selective
tendering, negotiation, continuity contracts, serial contracts and cost - reimbursable
contracts. In most cases these variants have been devised, or have evolved over the
years, as means of mitigating the short comings of the basic system.
The other systems include : British Property System ( BPF System ), novation and
partnering.
67
Mainly this chapter deals with different ( most common ) types of contract strategies
and their advantages and disadvantages. Characteristics of a successful project is
reported at the end of the chapter.
The type of contract and the actual conditions to be used must be defmed before the
contractor can be selected and before the contract price or method of calculating it can
be settled ( Bagnall 1992).
One of the basic criteria for determining the type of contract best suited to the clients
needs is the information that is available or that can be made available, for tendering in
the time scale dictated by client's brief Traditionally, information to enable a contractor
to construct a project is set out in drawings and specifications, with the administrative
details relative to the contract being set out in Bills Of Quantities ( BOQ ). All are
essential as part of the tender documents in traditional procedures.
There are several standard forms of building contracts currently use in Australia.
Whatever these forms are used, the contractor undertakes to carry out the works in
accordance with the contract documents. Mohyla ( 1992 ) points out some of the
commonly used ones :
NPWC 3 ( National Public Works Conference, General Conditions of Contract,
Edition 3, 1981).
AS 2124 ( Australian Standards 2124 - 1986, General Conditions of Contract,
1985).
JCC A & B ( Joint Contracts Committee Building Works, 1985).
SBW2 ( Lump-Sum Contract for Simple Building Works, Edition 2, 1992).
E5b ( Lump-Sum Contract Edition 5 b).
( Mohyla 1992 )
68
Although at present is neither the standard form of contract nor standard method of
measurement is to envisaged that quantities will be used for management
purposes,(e.g. : for ordering ), they do in fact provide documents which are a great
help on the site for this purpose. Furthermore, it is likely that new methods of
measurement, coupled with computer application, will lead to their far greater use
for management purpose in future.
The process of quantification before tender is one of the severest tests as to whether
what has been drawn and specified can in fact be built. Examine the drawings and
analyse the construction in detail is a substantial help in foreseeing problems not
apparent at first sight.
The provision of BOQ's to tenderers is not a universal practice. Basically the system is
used where the English approach to contracting has been adopted. It is not common
practice in Europe, US, some countries in Asia or Japan.
However, the common practice in Australia of providing BOQ to tenderers for building
projects involves a shift in the contractor's responsibility which opens up the potential
for claim and dispute. Instead of the contractor's obligation being to construct the
project in accordance with the drawings and specification for the price tendered, the
obligation becomes to construct the project in accordance with the drawings and
specifications as described in the BOQ. Claims and disputes then frequently arise as to
errors and omissions in the Bill when compared to the drawings and specification and
the method of measurement by which the Bill was prepared. There is a relatively high
level of claim and disputation in Australia in relation to the BOQs ( Barrell, Nixon et al
1988).
70
In order to ensure a successful choice of procurement system, the client's brief has to
be clear and comprehensive and contain not only the aesthetic, technical and
perfomiancec.:fireria for .rterrt;
Fa Pr,*
1..0 vu, ;^-1port2nce, his nrim arv anti
secominry objectives in terms of functionality, quality, time and cost.
Achieving adequate functional performance and the right level of quality is usually the
dominant primary objective in most construction projects. Unless the completed facility
is suitable for its purpose and intended use , the client's needs will not have been
satisfied and value for money will not have been achieved ( Mastennan 1992).
Many authors ( Marsh 1988, Mastertman 1992, Bagnall 1993, Ramus 1993 ) describe
advantages and disadvantages of different procurement systems and provide guide lines
to select the most appropriate contract strategy.
However the allocation of risk between client and contractor is not independent of the
contractual arrangements, as can be seen from Figure 5.1. The impact on price of the
different contractual arrangements is awkward to specify since this impact is not
independent of the competitive environment. As the industry has become more
competitive in recent years there has been a move to management fee and design - build
forms of contract, with demand for a guaranteed maximum price. Nevertheless it can
be stated that the greater the risk imposed on the contractor, the greater the price the
client must accept. In other words, the client has to trade off price and risk in the choice
of contractual arrangements ( Hillebrandt and Cannon 1989).
71
Client Contractor
1. Design - build
(package deal, turnkey) RISK
6. Management fee
contracting with
guarantee maximum RISK.
price and a fixed
management fee
7. Management fee
contracting with a target
price and a fixed RISK
management fee
8. Management fee
contracting with a target
price and a fluctuating RISK
managment fee
9. Cost reimbursement
daywork basis RISK
Under the traditional contract strategy the principal engages professional consultants to
prepare the concept design, the detail design and the contract documentation for the
works. The Principal then enters into a contract with a general contractor to construct
the whole of the works. Such a contract may be on the basis of a lump-sum, pr,wisir,n21
BOQ or schedule of rates. During the construction the consultants are normally
engaged to provide advice to the principal and to act as a certifier.
Project
Finance Contract
Financier Principal
Subcontracts
Subcontractors Suppliers
A traditional contract strategy may be the optimum strategy for projects where the
following requirements are satisfied or substantially satisfied :
Where the optimum design can be established without involving the prospective
builder or specialist subcontractor.
Where the principal prefers to manage the interface between the detailed design and
documentation and construction, and to select and engage the consultants and have
them directly responsible to the principal.
Where the principal requires the consultants to provide advice and monitoring of the
project through the design, documentation and construction phases.
73
Where the time available for the project is such that detailed design of the project is
complete or may be substantially completed before construction commences.
Few variations to the project design are anticipated to be required during
construction.
( NPWC/NBCC Report May 1990)
In general contract forms traditionally used on construction projects do not provide for
effective communication between the construction tcam and design team and the
principal matters such as buildability, variations and the timely supply of information.
Collins ( 1991 ) comments that the traditional contract strategy is inappropriate for
"fast track" projects, because the traditional "arms length" relationship between the
design team and the construction team is inappropriate when the detailed design is
carried out concurrently with the construction of the project. The use of traditional
contract strategy on "fast track" projects is a significant cause of delay, disruption and
additional cost ( Collins 1991).
Attention has focused on reducing the time traditionally occupied in producing a design
and preparing tender documentation, thus enabling construction work to begin sooner.
Another important fact has been bringing the contractor in at an early stage in the
design of a project. Under the traditional procedures, the contractor rarely played any
part until the tender stage was reached, after virtual completion of the design ( Ramus
1993).
74
Certain alternative contract strategies facilitate better communication between the design
team and the construction team, such as :
- Detail design and construction
- Design and construction
Project management
- Construction management
Novation
Collins ( 1991 ) further iterates that when such alternative strategies are used in
appropriate circumstances, significant project efficiencies can be achieved that benefit
all members of the project team.
Detail design and construction strategy may be the optimum strategy when the
following requirements are satisfied :
The principal wishes to develop the concept design as well as the performance
specification for the project.
The principal requires the Contractor to be responsible for the detail design and
documentation of the project and the construction and commissioning of the
project.
In a detail design and construction contract, construction can start, at the contractor's
risk, prior to the finalisation of the detail design, thereby reducing the project time to a
minimum. This occurrence of detail design, documentation and construction is possible
because the design team and the construction team work closely together and avoid the
formality necessary between the design team and the construction team when design is
carried out at "anus length" to construction.
NPWC/NBCC Report suggests to take care to ensure the concept design and
performance specifications prepared by the principal's consultants are stated in clear,
75
objective performance terms, because failure to do this may cause disputes as tho
whether the contractor's detail design satisfies the requirements of the "concept design
and performance specifications" ( NPWC/NBCC Report, May 1990).
The contractor is not entitled to extensions of time or increases in the contract sum for
variations to the detail design caused by the progressive development of the design
during the construction phase, or for late supply of design information, lack of
coordination between documents and errors in the BOQ's, except where these are
caused by the principal directing variations to the principals specified quality and
performance requirements.
There is an incentive for the detail design and documentation to be fine tuned by the
use of buildability studies and value management to ensure that the adopted detail
design and construction methodology minimizes time and costs whilst complying with
the principal's specified quality and performance requirements ( Collins 1991).
The assertion was made that 95% of construction activity under this system is claims
free and that problems only arise in relation to huge, one-off, technically complex
projects. It was also asserted that the system results in the most efficient engineering
design possible. The system will accommodate "fast tracking" ( Barrell, Nixon et al
1988).
The most significant advantage of full design and construct is the sole responsibility for
delivery. The system solves the interface problems of design and construction.
Contractor is responsible for the full design and as a consequence, places more focus
than is usually in the case on cost implications of design including the assessment of
buildability and alternatives, coordination of design and timely provision of design
documentation ( Nixon, Barell et al 1988).
76
Head
Contract
Subcontracts
1
Subcontract Suppliers
ors
Design and construction contract strategy may be the optimum strategy when the
following requirements are satisfied:
The principal's brief for the project can be properly identified and expressed in
objective, performance terms.
The principal requires tenderers or the contractor to develop concept design(s) to
satisfy the Principal performance brief for the project.
NPWC/NBCC Report, suggests to take care to ensure the principal's brief is stated in
clear, objective, performance terms, because failure to do this may cause disputes as to
whether the contractor's design satisfies the requirements of the concept design and
performance specifications provided by the principal. ( NPWC/NBCC Report May
1990).
Bagnall ( 1992 ), Chappell and Powell ( 1993 ) observed the following disadvantages
inherent in the design and build contract strategy :
Design and build by its very nature a rigid system, which does not allow the client,
the benefit of developing his requirements and ideas.
Where several tenders are invited, comparison of these can be difficult as the end
production in each case will be different and subjective judgement will apply.
Any variations required by the client after signing a contract can prove expensive
and difficult to evaluate.
There is always a risk with regard to the quality of the work. If the original brief is
not precise and the specification offered by the contractor equally vague there is a
temptation for the contractor to reduce standards.
77
Most design and build contracts are qualified in some respect ( e.g. ground
conditions, the inclusion of provisional sums ) which to a certain extent negates the
clients ideal of a known commitment.
In this project delivery system the principal engages an agent, ( a Project Manager ), to
provide a management service for all phases of a project from inception to completion
and who, in particular, undertakes for a fee the management of the consultants and
trade contractors for the project within the parameters defmed by the principal. Project
manager does not assume time and cost risks. The risk allocation depends upon the
particular requirements of the principal and the project.
Building Contracts
Contractor Contractor
Subcontracts
Subcontract Suppliers
ors
The major benefits of project management lie in management of both the design and
construction phases of the project and the flexibility to fast track and change
requirements, without significant claims and cost consequences.
With this project delivery system the construction manager is responsible to the
principal for the control, management and coordination of the construction of the
project.
79
manager's lack of control over and input into the design process. There may be
solutions to this problem in providing for the construction manager to have an input
into the buildability and cost of design and the inclusion of cost control objectives in the
terms of construction management contract ( e.g. : the inclusion of a guaranteed
maximum price requirement on the construction manager) ( Barrell, Nixon et al 1988).
5.3.2.5 Novation
The use of novafion system within the Australian building industry has been relatively
limited and it is not until recent years that novation has gained recognition and
acceptance as an independent project delivery system. In relation to the building
industry novation involves the transfer of consultants responsibility, conditions of
engagement and professional duty of care from the proprietor to the builder, at
specified point of time, usually upon the letting of the tender.
The novation system of project delivery is particularly suited to buildings which do not
entail complex architectural design / or structural concepts, but do employ repetitive or
modular elements and components. This is particularly due to the fact that under such a
system, design and documentation is incomplete at the tender stage. It is difficult
therefore, for tenders to accurately assess requirements under these conditions. Like
wise unresolved design issues relating to complicated elements have the potential to
create problems post novation ( Mohyla 1992).
81
Develop base
design brief
If going to
ricr-rfe
consultant
discuss
Appoint design
consultants
Involve Design
selected deve opment
tenderers in
design
Deve op
specification
Combine final
tender
documents
Tender / bid
project
Analyse
tenders/award
Assign design
responsibilities
to successful
contractor
Construct
outstanding
project
The increasing sophistication and complexity of building and construction projects and
the increasing need to complete projects in the minimum practical time demand ever-
increasing professionalism from every member of the project team ( NPWC/NBCC
Report, May 1990).
Given the enormous discrepancy between the time and cost of apparently similar
projects , there is a very real incentive for all members of the project team to work
together to achieve an efficient project environment.
Successful building and construction projects - projects that are completed to the
required quality, ahead of time and below estimated costs - occur as a result of team
work and professionalism from all members of the project team. Successful project
creates a "win- win" result for all members of the project team. Better quality work,
lower construction costs, shorter construction times, and more predictable project out
comes create additional opportunities as more projects become viable and industry
becomes more internationally competitive.
Factors that promote efficient project delivery and contribute to a successful "win win"
project include:
Appropriate allocation of obligation and risks.
Selection of an appropriate contract strategy.
Clear objective performance statement of the principal's requirements.
Minimum variations to the project specifications.
Careful selection of the project team.
Comprehensive planning of all aspects of project - time, cost, quality.
Effective communication between the members of the project team.
Effective time and cost management.
QA of both design and construction.
Avoidance of claim situations.
Effective and prompt remedial action if a team member defaults.
( Collins 1991)
84
6.0 Introduction
Construction industry does not have a series of products that can be tested, measured,
judged, or evaluated objectively, like a manufactured product. However the fmal
outcome of the construction process is a large, heavy and relatively expensive product,
made to suit to the requirements of particular owner.
It is well known that manufacturing industry is far ahead than construction industry in
respect of achieving quality products. Brown and Beaton ( 1990 ) contend that
whether the construction shares any of the characteristics that bring quality result to
manufactures.
Quality planning ?
Statistical Analysis ?
Employee involvement in reward ?
Customer feedback ?
These terms are well understood by other industries, but they have little meaning to
most construction organizations. Then how do you measure the quality in a constructed
project ?
This chapter describes the quality management tools, techniques and it's applications to
construction. The results of number of research studies given at the end of the chapter
illustrate problem areas in construction industry.
Successful construction projects are conceived planned, designed and built by a project
team consisting of the owner, design professional and constructor (major participants ).
There are, offcourse, many other professionals who play a significant but more limited
role within the overall project. Within this context, quality is produced when each team
member completely and, in a timely fashion, fulfils his obligation in cooperation with
the other members.
Providing quality in the design, construction and operation of a project cost less, is safer
to the public and site personnel, and minimizes disagreements and subsequent litigation.
Quality in design and construction results in significant benefits for the owner, design
professional and constructor ( ASCE Manual 1988).
86
Fritz ( 1990 ) suggests to undertake the following major tasks in order to implement
QA which confum to ISO 9000 / AS 3900 series.
Establish contract documentation QC, and specification of quality requirements for
the works.
Establish, or clarify, the lines of responsibility and authority with respect to quality.
Appoint quality representatives and support staff.
Enunciate the organization's quality policy.
Develop QA systems and documentation.
Develop and implement training programs.
Develop in-house skills to assess QC.
Retain construction supervisory personnel.
Improve briefing procedures to ensure quality requirements are clearly stated in the
contract documents in measurable terms and fully understood by all parties to the
construction process.
Review and if necessary, modify existing checking and review procedures.
Apply formal QA to builder selection and design and documentation, as well as to
the actual construction process.
Recognize the need for longer establishment periods for each new project to allow
builders to develop and implement QA systems.
Carry out regular audits of builder's, subcontractor's, consultant's and owner's QA
performance.
Respond as necessary to Quality Audits by owners.
87
In recent years guide lines and recommendations to improve the quality of design has
been developed. As this effort evolved from drawing control in to other aspects of
"good engineering practice", the methodology become known as "Design Control or
Design Assurance ".
Burgess ( 1988 ) defines "Design Assurance" as those planned and systematic actions
taken to provide confidence that the completed design will satisfy the requirements of
its intended use. A typical Design Assurance program covers all phases of engineering
associated with the project, including the identification of requirements, drawing and
specification control, verification of design accuracy, control of changes and supporting
documentation. Time and energy spent in developing a clear and complete set of
requirements up front has a high rate of return later in avoiding problems and satisfying
customers.
There are two commonly used methods to verify the adequacy of a project design:
design calculation and design review. Although these can be used individually, it is quite
common to use one in conjunction with the other.
88
Design Analysis
Calculations are used routinely to size components, predict performances, determine
limits etc,. However, for many projects, the calculation methods, assumptions, and
results are virtually invisible to everyone except the person who performed the
calculation. Also calculation records tend to be surprisingly unstructured, abbreviated,
and frequently inaccessible for later reference. One caution about engineering
calculations - problems seldom come from mathematical inaccuracies. The real culprits
are the use of improper methods, invalid assumptions, or incorrect modelling
techniques. For this reason, it is a good practice to require a second - party technical
review of calculations as an independent check on the analysis for decision - making
purposes.
Engineering software also presents many new challenges. Often, the construction and
content of the programs have low visibility, coupled with limited use documentation.
This especially true when using software which was developed out side the company.
Yet a strong tendency for engineers is to give the software developers the benefit of the
doubt and to use the software somewhat blindly. Again it is quite easy to misplay
computer software, to use it beyond its proven limits, or to make assumptions about it
that differ from those made by the software developers. So it is vital to study the
software documentation carefully and apply it with cautious.
Design review
A design review is simply a critical but objective review of the design before it is
released for construction. It is an opportunity to expose the design to knowledgeable
and experienced personnel to avoid errors and omissions. A list of questions to consider
when calculating a design review as follows.
Does the design satisfy the requirements ?
Do the assumptions used in the design seem reasonable ?
Are there areas where the risks appear to be higher than normal ?
Are there items of significance that have not been addressed ?
Are the design methods used appropriate for this project?
What problems remain to be solved?
Is there adequate assurance that the problems remaining can be solved in a
reasonable manner and appropriate time frame ?
( Burgess 1988)
89
The cost of design is generally considered to be roughly between 2% and 10% of the
total costs ( Institution of Civil Engineers, UK). Since design costs represent only a
small proportion of total costs, it becomes worthwhile to increase design effort
significantly in order to achieve comparatively small reductions in construction costs.
McGeorge ( 1989 ) explains this concept with a simple example ( Costs are given in $
thousands in the following Table 6.1).
Design cost is taken 5%. In this case it has been assumed that a 50% increase in design
input yields a 10% saving in construction cost. The net result is a 7% reduction in total
cost, or a saving almost 3 times the cost of the extra design work. Research carried out
on constructibility and value engineering reviews typically yield construction cost
savings of 10 to 20 times the cost of the extra design input ( Business Round Table
1982, cited in McGeorge 1988 ). Even these figures understate the true potential for
improvements, as constructibility exercises, by definition, aim at reducing only
construction costs, and the picture is dramatically improved by including operating and
maintenance costs.
Plotting design input against total yields the curve shown in Figure 6.2. The rational
policy then would be to aim at the optimum design effort "o", but most engineering
projects fall well to the left, at some point "a".
90
TOTAL
COST
a
DESIGN INPUT
Figure 6.1: Effect of design input in project cost. ( Source : McGeorge 1988)
The topic of constnictibility leads to the idea of design quality - a good design will be
effective ( i.e. serve the purpose for which it was intended ) and constructible with the
best possible economy and safety. Vlatas points out that design deficiencies are a major
cause of contract disputes and changes during construction, and notes several causes for
the increase in design deficiencies. ( Vlatas 1986). However the question of producing
better quality designs is obviously a complex one, with implications affecting the whole
construction industry. The issues are hostly debated ( Richards 1983, Cassano 1983,
Zweig 1984 ) which is an indication of the perceived need for solutions (cited in
McGeorge 1988 ).
Cornick ( 1991 ) emphasizes the need to manage quality in the briefing, designing and
specification phases of a building project, rather than trying to merely control quality in
the construction phase. The latter approach will only solve the problems that come to
light during construction and not those that remain latent, appearing during the life of
the building.
Logically, the requirements for a building can only begin during the briefing phase of a
project, be further developed during the scheme and detail design phases, and be finally
refmed for the physical production of the building during the specfing phases. The
subsequent tendering and constructing phases should add nothing to the fundamental
requirements of the building's design. The management of the processes involved in
those four early project phases is vital, if the likely causes of quality problems are to be
identified and prevented. This is the only cost effective way that quality can be achieved
in the later constructing and maintaining phases of a building project ( Cornick 1991).
The Royal Commission Report into Productivity in the Building Industry in New South
Wales ( 1992 ) observed that poor project documentations are the major causes of
inefficiencies, claims and disputes in the building industries.
92
/Materials
Deliveries : Deliveries to site must be monitored to ensure compliance with
specifications.
Storage, protection and distribution : All materials and components must be stored in
accordance with locations and conditions agreed with the site manager. The storage
methods for any materials supplied by specialist sub-contractors are agreed in detail
with the sub-contractor prior to his commencement on site and the agreed procedure is
clearly recorded.
Rejection or awaiting acceptance for incorporation : The materials falling into this
category must be stored in a location or manner which clearly identifies and prevents
the material being used until the necessary authority has been given. A procedure for
establishing this must be clearly set out and followed.
The checklist is completed first by the operative carrying out the work and then checked
by his immediate supervisor. The next stage of the work should not take place until
93
each checklist has been agreed and signed by both parties. By adopting this approach,
potential problems are identified at the earliest opportunity and solved before they
become major defects.
The completed checklists also provide a record of the defects that have occurred
throughout the project and the ways in which each problem has been solved. This
experience is fed back to the system. Data are now available identifying the frequency
of defects and common solutions so that investigations can be focused on those
problems which require the most urgent attention.
During the course of construction, QA procedures should ensure that the program is
prepared at an appropriate time, that it is in compliance with the contract requirements,
that it is effectively monitored, that the effects of the monitoring are assessed and that a
completion date is forecast. In the event that some activities fall behind program, it
should be agreed what action should be taken to avoid the delay and who should take
such action. If required, the construction sequence should be revised.
Cost : The QA procedures for cost control ensure compliance with the client's
requirements for comparison against the cost plan. The procedures define who has the
authority to issue instructions under the contract, the limits of financial authority for
each party and the manner in which proposals are to be costed and assessed alongside
other options before a financial commitment is made. They also define the method and
frequency of cost reporting to the client.
COST
Figure 6.2 : Cost vs Quality. ( Source : Mathur and McGeorge 1990 / 1991)
It has been assumed in the graph, that each level of cost is allocated optimally among
various demands. This is because cost allocation is a difficult balancing act if there are
budget restrictions ( Mathur and McGeorge 1990 / 1991 ).
On the other hand lack of quality invariably results in a higher total cost. Though the
initial cost may be less through the use of minimal design functions, substandard
materials, or unskilled workmanship, the total cost to the user or owner over the life of
the project will be greater due to frequent repairs, breakdowns and shorter useful life.
( ASCE Manual 1988)
Some of the items which contribute to the costs of poor quality are: repair of defective
work; purchase of replacement materials; delays or disruption while repairs are carried
out or replacements obtained; handling of customer complaints; after sales remedial
work; wastage of marketing effort; legal representation; court costs; and compensation
payments.
Companies which have seriously attempted to quantify these costs usually arrive at
totals varying between 10% and 40% of turnover. By comparison, the typical cost of
95
quality system for conventional construction work is likely to lie a fraction of 1%. Even
in extreme cases, such as offshore or nuclear construction, it is unlikely to exceed 5%.
So even if the quality system can prevent only a small proportion of the costs of the non
quality, the potential for savings is enormous ( Ashford 1989).
Graves ( 1993 ) suggests the following ideas for quality improvement in design and
construction.
Concurrent engineering involving all specialists and project participants on a team
during all phases.
Quality Function Deployment ( QFD ), a disciplined technique of designing to meet
customer requirements.
Better planning and managing of the design process to avoid rework and waste
satisfaction.
Factual information, not just opinion.
Client supplier partnerships ( partnering ).
High level of client staff participation in the design process.
Quality teams to address specific design issues, both product and process.
Documents review by specialists for constructibility, buildability, operatability, and
value engineering.
A client report card to monitor client satisfaction and identify improvement
opportunities
( Graves 1993).
96
Following is a review of the results of some research studies undertaken in UK, USA
and Australia. These studies show the quality related problems in the industry.
Design faults
Product faults
Construction faults
Figure 6.3 : The cause of failure pie chart. ( Source : Comick 1991)
97
Allocation of time and resources : Few companies in the survey used anything more
sophisticated than hand-drawn bar charts to plan time and some were of the view that
problems with time, in particular, were inevitable in the construction industry and that
little could be done to improve the situation. The constraints on time were most felt by
the designers in the early stages of a project caused by either the client or the designers
being unwilling or unable to freeze the design at particular point and then restricting the
time for the sub contracted designers such as structural and service engineers.
Design errors : These were mainly omissions with a few miscalculations, all of which
could be avoided.
Poor workmanship : This was mainly caused by poor supervision or, in many cases the
complete lack of it. Many sub-contractors employing a few people on each site find it
impossible to justify a continual site presence and roving supervisors are used.
Poor management : The problems here are of a more general nature - organization of
who does what and when on site.
Technical problems with materials : The largest group in this category is goods arriving
on-site not matching the specification that was ordered. Poor handling of materials was
another problem, with the most difficult problems being those of handling materials
new to the industry.
surveyor - or one specifying one item and the other something different.
98
Site conditions : All these instances were of public authorities failing to do surveys of
land or buildings before commencing and then discovering that there were unforseen
problems.
Contractual : Theses -problems occur when different forms of contract are used. For
example, a client changed from nominated to domestic subcontractors and yet still
thought that he had the right to deal with them directly.
Buildability : Buildability problems arise where a contractor is not on hand at the design
stage to advise on easier or more economical methods of construction.
Inadequate training It would appear that inadequate training is often a scapegoat for
:
The study showed that the most common defects were following:
Set-out of form work, frame carpentry on-site and the factory production of frames
and trusses.
Inadequate appreciation of structural elements ( e.g. : carpentry in relation to
building regulations; steel fixing in relation to concrete cover ; excavation in relation
to the function of the foundations, as a structural base for building ).
Performance of building systems ( e.g. : cavity wall construction ).
Incomplete work.
The main factors which contribute to the occurrence of these defects are :
Inadequate knowledge of construction.
A careless approach to quality control.
Insufficient awareness of building regulations and correct trade practices.
99
Based on the findings of research Forsythe and Marosszeky ( 1988 ) made the
following observations and recommendations.
Trade training :The study showed that the education of tradesmen, supervisors and
builders needs to be modified in order to better reflect the current industry structure and
its needs. It is necessary to emphasize all aspects of work relating to the achievement of
better quality.
Support for sub-contractors : The study found that the sub contractors in the domestic
sector have no support in the form of continuing education about technical and
management issues. Their primary source of information is through manufacturer's
trade rights.
/ The supervisor : The study showed that the building supervisor is in the best position to
improve quality control in construction. In summary the study indicated that :
Insufficient time is spent on assessing the quality of construction.
Few supervisors adhere to an organised quality program.
Many supervisors worked to the regime of inspections adopted by council
inspectors to identify quality problems and accepted a passed inspection as an
indication of satisfactory work.
There is a shortage of skilled supervisors.
There is a clear need for a supervisor training course.
1 The builder : Essentially, the builder is responsible for the supervision of the quality of
all work that is under his control. Consequently it is the builder who must develop
management policies that ensure supervisors can effectively monitor quality and that
provide tradesmen with the information they need to do their work adequately. To
achieve this end the research team has recommended that the management policies
must focus in four main areas:
A clear definition of responsibility. Responsibility for ensuring quality achievement
must be clean), defined, lines of communication must be clear and achievements
must be regularly reviewed.
Assessment of standards. Objective standards must be used wherever possible to
define acceptable quality. These should be clearly set out so that they can provide
100
tradesmen with the information they need to assess their own work. In addition they
will provide supervisors with consistent standards to work to.
Practical contract documents. Contract documentation must be developed to be a
useful communication tool clearly specifying commitments, construction
information and standards rather than being merely formal documents.
Design documentation. It is necessary to review the use of documentation as a
communication tool in order to help sub-contractors improve their own construction
and quality control.
Clearly the quality of end product is believed to be dependent primarily on the workers
doing the job and it was noted that experience and skill was regarded marginally higher
than is training and education. Emphasis was also placed on the supervision under
which the work was carried out. It was notable that frequent comment was made,
particularly in respect to the higher skilled areas such as the mechanical engineering and
services, that the tradesmen are often their own supervisors as the work cannot be
checked on a continuous basis.
Accuracy of drawings is a high priority and criticism was made of frequent inaccuracies
in drawings and that they often become out of trade by the time work is carried out.
Drawings are given a higher overall priority than are specifications. Quality of material
is given as an important source of quality fall down, as is dimensional inaccuracy
resulting from errors by previous trades. Coordination between different trades is also
rated highly as a determinant of quality which can be impaired if misunderstandings
arise of work is not carried out in a desirable sequence.
A strong point made by many respondents is the impact on quality brought about by the
overall competence and attitude of the head contractor. If the management is competent
and well organised, if there is a good communication and activities flow as planned then
job quality is enhanced.
Criticism was frequently made of the quality of specifications, on the basis that they
seem often to be general ones reproduced on a word processor and fail to recognize the
particular characteristics of the job in question. Criticism was also made of consultants
drawings which were said to have more inaccuracies than one is entitled to expect.
These features either impact on quality directly or add to difficulty and take time, thus
putting cost pressure on the time available.
Another significant area of concern, expressed particularly by the finishing trades whose
work is exposed to view, is the abuse by other trades after the work has been
completed. Plasters, roofers and painters are particularly susceptible.
Many respondents made a comment, and indeed expressed their deep concern, as to the
current extreme of competition in the industry, whereby attempts to quote on the basis
of adequate attention to quality, fail to win contracts. Most clients are said to be
accepting the lowest bids ( Woodhead and Ball 1991).
Of the forty problems studied, about 25% were due to at least in part to communication
- coordination failures. These failures in communication / coordination occurred
variously between owner and designer, various design disciplines, designer and
vendor(s), designer and constructor, constructor and subcontractor, owner and
constructor.
102
The structural problems reviewed indicate that quality in the constructed project is not
simply a function of the skills and diligence of the various parties involved. It is also a
function of their ability to communicate needed information about scope, costs,
schedules, technical information and changes.
A coordinated effort among the various contributors on the team will be required in
order to achieve an integrated program, design and completed project - one that is
functional and meets the client's needs. This includes the various communication
processes by which needed information is exchanged among individual team members.
7.0 Introduction
The business world changes from traditional management practices to TQM.
Construction industry has followed manufacturing and service industries in beginning to
implement TQM. Implementation of TQM can be viewed under two scenarios.
Considering each project as a separate business unit and applying TQM principles
to accomplish project mission ( TQM / None TQ1'vl organization construct projects
applying TQM principles on project by project basis ).
Organizations who have already progressed well into their TQM journey, apply
TQM principles for projects ( TQM organization may construct all projects in
accordance with TQM principles ).
One can assume that, both of these methods could be used to produce a Total Quality
project. However it is understood that applying TQM to construction is a challenging
and complex task. As observed by Deffenbaugh ( 1993 ) construction companies that
embrace TQM would prefer all repeat clients with the same cooperative design team
and sole - source subcontractor and supplier partners. This may be not the case in most
of the countries.
Deffenbaugh ( 1993 ) suggested to view the project team like a small business it self,
the project team also can practice the same approach to empower people, satisfy both
internal and external customers and continually improve. When this is done total project
success is inevitable. This chapter briefly reviews application of TQM principles to the
construction. Three different TQM models are described in this chapter.
For years TQM has been readily applied to manufacturing, in which work is repetitious
and the workforce is generally stable. construction however offers much more
variability ; each project represents a unique formula of design, location, personnel,
materials, weather, cost and time. According to Deffenbaugh ( 1993 ) the major
105
challenge in implementing TQM in the design and construction industry is applying its
principles to jobsite.( Deffenbaugh 1993).
Strange and Vaughan (1993 ) commented about the complexity and unique nature of
construction and challengers to implement TQM as follows.
"It is the point of view, or paradigm, that many construction leaders have
about their industry. Thai view, which c4muunts to a belief that construction
management is art, not science, and that project success is almost impossible,
because of the natural entropy in the system, can be summarized by what we
call the "can'ts":
You can't apply industrial management solutions to construction,
because of the unique nature of the construction industry.
You can't do statistical analysis of construction processes, because
they are unique and nonrepetetive.
You can't invest in training at the job level, because individual
employment is short-term, the people have no company loyalty, and the
environment is too difficult.
You can't spend money on management programs, because there is too
much competition and the margins won't allow it.
You can't take time away from doing the work for seminars, retreats or
symposia" - Strange and Vaughan.
According to Strange and Vaughan ( 1993 ) the challenge of applying TQM or other
forward thinking management philosophies to construction stems from the definition of
two words, "product" and "success". Product is currently defmed as the fmished
building, or project. Success is defined as meeting company goals for profit, growth
and so on. In TQM product must be redefined to be the management service provided
in planning and executing construction, and that success must be redefined as meeting
the goals of customers of that product. ( Strange and Vaughan 1993).
In 1990 Iowa State University researches held a national workshop for owners
designers, contractors, and sub contractors to address TQM in the design and building
process. The participants identified many problems that faced the industry in the US,
but the first three were noted as lack of team work, poor communication and
inadequate planning and scheduling
106
The ASCE Manual also highlights the importance of a team effort in producing a
quality project. A team effort is based on mutual trust and understanding among all
parties. Mutual trust and understanding can only occur when integrity exists. Honesty
and integrity are critical in developing mutual trust and understanding among the
individuals of the project team. Though it is difficult to do at times, participants must
state facts regardless of the consequences. Honest and open communications among the
project team members will largely determine the success of the project ( ASCE Manual
1988).
107
Model 1 ( Chase 1993 ) : The ten elements model described here, is based on the input
of contractors who have developed formalized QM processes. According to Chase
(1993 ) this method is being applied successfully by the design and construction firms
in US.
Model 3 : ( Burati and Oswald 1993) : This model had been developed, by using the
data collected from the interviews with engineering and construction companies who
have successfully accomplished TQM. Findings of this study indicate that there is a
general sequence of four implementation phases that produce the best results. These
phases include : exploration and commitment, planning and preparation,
implementation and sustaining. According to Burati and Oswald (1993 ) this
approach is helpful to companies making new starts at TQM or those wishing to make
modifications to their ongoing TQM implementation efforts.
108
uOUS IMPROVE
SUPPLIER PROCESS
IMPROVEMENT IMPROVEMENT
CUSTOMER FOCUS ON
SATISFACTION EMPLOYEES
TEAMWORK
IMPROVED COMMUNICATIONS
VISION. UPPER
MISSION. MANAGEMENT
TRAINING INVOLVEMENT,
GUIDING COMMITMENT,
PRINCIPLES LEADERSHIP
Several foundation members are required to support the structure. These are training
(and education ) , vision, mission, goals and guiding principles, and upper- management
involvement, commitment and leadership.
2.Vision, mission, goals, and guiding principles : The vision is a written statement
starting with the company ultimately intends to become. The mission states what a
company is in business to do. Goals are broad targets that stem from the vision and
mission. There can be goals for many areas, such as safety, customer satisfaction,
business growth, and worker satisfaction. Guiding principles are general statements that
reflect in broad terms the company's value system and approach to quality.
5.Teamwork: TQM recognizes that people working together in teams toward mutual
goals are generally more effective than individuals working alone. On individual
construction projects the parties may establish a team environment. Sometimes this is
the result of TQM; other times it is the result of "partnering" process. Sometimes it is
both.
9.Focus on Employees : TQM recognizes that every employee has significant potential
to make improvements not only in his or her own function, but to see and make known
needs for improvements in other areas. This potential is tapped through a combination
of :
Motivating.
Instilling the internal customer concept.
Training as mentioned earlier.
Providing a meaningful orientation for new employees on the company, its
customers, and the company's quality policies.
Providing a safe, clean, stimulating and satisfying work environment.
Encouraging two way communication and employee suggestions.
Breaking down communications bathers inside and outside of the organization.
Allowing and encouraging employee participation in planning, problem solving, and
decision making.
Providing individual and team recognition for quality improvement.
improvement. This feature distinguishes TQM from short tenn management fixes. With
TQM, everybody within the organization is looking constantly for ways to improve
(Chase 1993 ) .
111
Jobsite Quality
Planning Session
One Day
Meeting
Mission
Key Tasks
Duration
of Project
Duality
Indlcators
Recognition j
Quality Lead Team
Total Project
Success.
The process start with job site quality planning session at which representatives of the
project team meet to develop a mission for their workshop. They also determine initial
key tasks that will help them accomplish the mission. The team become a quality lead
team for the project.
It addresses the initial and subsequent key tasks identified under one of the four specific
headings shown. Recognition reflects that all the individuals on the project are
respected for the part they play in making the job a success. Quality Indicators are
used to manage key processes using facts. Training and Development help
112
management and workers alike grow and contribute to their fullest extent. Quality
Improvement Teams standardize processes and solve problems to assure overall
customer satisfaction. As work proceeds, the Quality Lead Teams meet regularly to
oversee the total - quality effort and progress toward accomplishing the mission. When
the mission is accomplished there is a total project success. The PDCA cycle forms
the basis outline for continuous improvement and as such is key to the Jobsite Quality
Planning Process.
Quality
Recognition
Indicators
Examples: Examples:
Precast Production Quality Crew of the
Month
Window Installation
Shop Drawing Quality Quote of the
Week
Turnaround
Worker Suggestions Training Certificates
Quality Lead Team Safety Awards
Examples: Examples:
TOM Orientation Design Submittal Team
Elevator Basics Utility Coordination Team
Safety/First Aid Embed Placement Team
Fire Alarm System Clean-Up Team
Total Project
Success
Figure 7.3 illustrates how the diagram might look as the project continuous through
construction. Due to the unique characteristics of each project, the specific items
change. Thus the list needs to be flexible.
113
Recognition items promote teamwork on the job and pride in one's work. There are
three primary types of Quality Teams that may be used on a project.
1. Coordination teams have been effectively used both during the submittal process
and when work is progressing. Rather than one group doing their work on an item
and passing it on, groups come together to discuss and negotiate their requirements
for the project to satisfy everyone involved. This approach eliminates rework both
in design and construction.
Stanclardimtion teams meet at the beginning of a process, whether it be paper work
or field installation, and agree on the steps and method of measurement As the
work proceeds, team members measure themselves against the requirements they
established.
3. Finally problem solving teams are formed to address problems that arise on the
project. These teams use a fast track approach to eliminate the problem quickly with
minimal negative effect on productivity.
Quality Lead Teams closely monitor all teams on the job site so that designer and
worker time are effectively used for positive results. Quality Indicators measure
progress toward accomplishing the mission. These measurements are openly displayed
on the project to create awareness and team accountability. The final focus on the
Quality Lead Team is on Training and Development.
As work progresses Quality Lead Team reviews the quality progress regularly. It is also
important for the Quality Lead Team to look out side of its group for improvement
ideas. Projects also need ongoing feed back from the ultimate customer, the owner
(Deffenbaugh 1993).
114
TQM often termed a journey, not a destination. This is because of its nature as a
collection of improvement-centred processes and techniques that are performed in a
transformed management environment. The concept of continuous improvement holds
that this environment must prevail for the life of the enterprise, and that the methods
will become routine/3r used on a regular, recurring basis. The improvement process
never ends, therefore no true destination is ever reached.
The metaphor of a road map was selected to illustrate the TQM journey. The road map
is a composite of the experiences of 15 out of 17 companies interviewed that have
comparable TQM processes.
Participant, helper
Decision
Activity, task
Multiple activities
Meeting
Figure 7.4 : Legend of Symbols on Road Map. ( Source : Burati and Oswald 1993)
115
Chief Internal
Senior Middle Work External
Executive TOM
Managers Managers Force Consultant
Officer Coordio taw,
deed. to No
END
Change?
Yes
No
Is TO
END
the way?
Yes
I
Define expectations
I
Select
approach 8
consultant
O Appoint
TOM
Coord.
1
0 I
0 Develop
training
plan
i
Receive TOM
awareness training
eaffirm No
00
END
Figure 7.5 : TQM Road Map : Exploration and Commitment phase. ( Source : Burati
and Oswald 1993)
116
The work of this phase is essentially concluded when top management, having had the
benefit of training of quality awareness, and having understood its implications and
requirements, formally commits to major change in the philosophical and operational
conduct of the enterprise.
Chief Internal
Senior Middle Work External
Executive TOM
Managers Managers Force Consultant
Officer Coordinator
Develop strategic
quality
deplo rnent process
Receive training:
Top Mgmt-Ot tools
Middle Mgmt - Awareness
1
III
I
Receive training:
. Middle Mgrs - 01 tools
i
i
Receive selected
training as:
Facititalors
Instructors
leaders
a
0
Develop in rastructure
8 process
to coordinate learns
Establish
team
process
model(s)
I
Figure 7.6 : TQM Road Map : Planning and Preparation phase. ( Source : Burati and
Oswald 1993)
117
The work of this phase can be considered to be concluded only when the necessary
planning, including commitment of resources, and basic training are in place.
3. Implementation phase
The implementation phase is that period of time in which the commitment, planning,
and preparation of the two initial phases are translated into action.
Chief Internal
Senior Middle Work External
Executive TOM
Managers Managers Force Coordinator Consultant
Officer
Continue to realign
the rewa d system
1
J
Receive J- -T training as learns
Team skills
01 tools refresher (as needed) -
I I I
Receive training in advanced
1:11 methods for selected
resource peoile"
I
a
gain experience &
generate success
stories
Implement pilot project
results & publish
success stories
o--
Figure 7.7 : TQM Road Map : Implementation phase. ( Source : Burati and Oswald
1993)
The major activities are :
Extending the infrastructure by creating and chartering teams at various levels,
including high - level oversight teams, and action teams to perform a few
strategically chosen pilot QI projects.
Continuing to realign the reward system to support the desired behaviours.
118
Training teams, as teams, in the skills and techniques needed to perform their
assigned QI projects.
Top management rolling out the TQM process, by implementing the results of the
pilot project teams, publishing the attendant success stories, and extending the QI
effort to teams and projects throughout the organization.
Formally celebrating the implementation results to date.
Extending the TQM process to vendors and suppliers once the in-house program is
considered to be progressing satis.factorily
The end of the implementation phase is less clearly definable than the ends of the two
initial phases. ( Even those boundaries are inexact ) Implementation should never cease.
Rather it transitions gradually into the period of sustaining activity, that of continuous
improvement.
4. Sustaining phase
Chief Internal
Senior Middle Work External
Executive TOM
Managers Managers Force Consultant
Officer Coordinator
Figure 7.8 : TQM Road Map : Sustaining phase. ( Source : Burati and Oswald 1993)
119
Following this initial push, there is a gradual transition into the sustaining phase. This
part of the endless journey is characterized more by prevailing conditions than by a
progression of discrete events. Some of the conditions prevailing in the sustaining phase
are
Integrating the specially created TQM infrastructure features ( or organizational
elements, processes etc,. ) into the normal management processes of the business.
Continuing planning for long term quality improvement.
Continuing and intensifying focus on the improvement of the work processes of the
organization, with the objective of increasing customer satisfaction.
Continuing management commitment to the internal workings of the process, as
clearly evidenced by its ( management's ) attitudes and its behaviour.
Continuing action in the training, team work, empowerment, and participation of
the work force across the full spectrum of TQM activities.
Continuing study and implementation of advanced training and leadership practices.
Continuing active oversight by management of the TQM process, as opposed to
"just letting it run itself ".
The sustaining phase brings with it the possibility that long term TQM planning will
gradually lose its identity and therefore its momentum. Therefore Burati and Oswald
(1993) recommend that the management should exert conscious effort to establishing
guarantees that planning for continuous improvement will retain its high profile and be
pursued with as much or more discipline as in the earlier phases.
Only four of the six owners and five of the eight contractors are considered to be
approaching a sustaining posture. Their individual degrees of attainment vary widely.
120
1982 83 1 84
1 85 1 86 1 871 88 1 89 1 90
6 Owners
2MM= raTtnal VWVZ:11'ZKSIT212 111111111111111MINiell r'711ENII OW= liNEW53
11111111111111=1
110/t."'^ff -2`J IIMOSSIMMINME IMIESEMEI
111111.111111111. ---
--
031/41',;:ehlIMMIVIKX412=23021169=21151=11111119=1=
Implementation
nffilinfla
(Early) Sustaining
Figure 7.9 : Approximate durations for TQM histories. ( Source : Burati and Oswald
1993)
121
Also we have examined the nature and complexity of construction industry, current
adversarial style and dispute prone nature of the project environment coupled with the
common contract strategies adopted by the industry.
Referring to the NIES "How to" model ( Section 3.5 ), "people", "variations" and
"systems" are the interacting factors that affect the ability of supplier / contractor to
satisfy the customer needs. All people serve customers through and within people.
Therefore the "ideal management system" should to be based on the fundamental
values ideas of common sense, trust, commitment, openness ( open conununication ) to
foster a better understanding environment with enhanced cooperation. This is the
essence of partnering. The following Chapters 8, 9, 10, and 11 address the partnering
concept, it's benefits, concerns, challenges and its application in detail.
122
8.0 Introduction
In the early 1970's the business environment for engineering and construction changed
sharply. Faced with ever increasing inflation, oil embargoes, and other economic
factors, the industry was forced to develop new strategies to handle these challenges.
The industry is again faced with new challenges and must respond with new and
innovative strategies. New technologies, hostile take overs, foreign competition. Profit
pressures, changing regulations, and high investment risks are forcing the industry to
shift away from traditional approaches and seek new ways of doing business ; seek new
ways to lower costs and differentiate themselves to gain competitive advantage; break
from old patterns and prepare for change. The concept of partnering is one such
approach to conduct business that confronts the economic and technological challenges
in 1990's ( CII 1989).
8.1 Background
Global competition, the increasing cost of product development, and the accent on
product quality are forcing construction owners to seek more cost effective and timely
methods for obtaining design and construction services for their capital projects.
Owners are also seeking methods to reduce the high cost of fixed resources in their own
organizations. Constructors and engineers are seeking ways to grow and to maintain
competitiveness. These firms are finding that traditional contracting relationships may
be too slow and too expensive and result in too many adversarial relationships to meet
the time, cost, and quality constraints in the new environment ( Goldbaum 1988,
Hancher 1989, cited in Cook and Hancher 1990).
This approach focuses on malcing the goals of the owner, contractor, designer, and
supplier better understood and easier to manage. Partnering is a type of contractual
agreement that out lines mutually attainable goals, satisfies long term needs, and assigns
risk among all the parties involved ( CII 1989 ). However partnering is not a legal
contract.
"True partnering" is based on meeting mutual needs and interests, exhibiting sincere
trust and allowing time to uninature and de-v-elop the relationship. Partneririg also mearbs
sharing the rewards and recognition derived from the relationship ( CII 1991).
For partnering to become an effective business tool in the construction industry, the
owner - constructor - engineer relationships must be reshaped so that partners to seek to
identify common goals, not slightly different sets of priorities. The objective of a
partnering agreement should be to achieve mutual profit and mutual success for each
company. The partnering agreement must reduce or eliminate adversarial relationships
and replace them with a long term relationship based on mutual trust and mutual benefit
( Rubin and Lawson 1988, Provost and Lipscomb 1989, cited in Cook and Hancher
1990).
The matrix organizations in the 80's provided a half way solution between functional
and flexible organizations. Matrix organizations rely on negotiation ( win- lose ) and
standardisation of the process ( particularly legal process ) to control the large number
of stake holders in a project - matrix organizations are driven by structure, not culture.
As observed by Dombkins ( 1993 ) matrix organizations have by their nature conflict
built into the structure. Trust and open communication were not considered critical
factors to organizational high performance. To remain high performing organization in
the 90's and beyond, organizations need to change to be stakeholder focuses and
flexible. The challenge is for today's organizations to change their cultures to fit with the
124
new environment and then to constantly keep changing to maintain fit with the ever
changing environment.
The emphasis on coordinating work through documentation has resulted in their being
little contact - other than contractual - between designers and contractors and effectively
no contact between clients and contractors. This reliance on documentation to
coordinate work has meant that there was no perceived need for shared objectives and
open communication. All issues resolved through the contract documentation. This
process establishes and maintains a win-lose mentality. Each of the stake holders in this
process focused on it self and not on the overall project. The contract, drawings,
specifications and direct supervision were assumed adequate to coordinate the work -
there were no perceived need for shared objectives and open communication.
Over the past thirty years there has been a significant increase in overall output per
person due to technological change, while there has been a drop in individual
productivity. Reliance on technology is no longer sufficient to keep pace with
international competition. When flexibility is required in an organization, open
communication is the high leverage organizational design factor. In order to minimise
response time and maximise effectiveness of communication, Dombkins ( 1993 )
suggests that organizations should be designed to :
Empower and multi skill its workers.
Resolve the maximum number of interdependencies within the individual groups.
Provide effective inter and intra group communication ( liaison devises).
Industry has focused on structural solutions to increase its productivity and quality. The
emphasis has been on restructing to increase multi skilling and reduce demarcations.
There has also been a move towards letting larger subcontract packages significantly
improve communication, reduce the need for cross - sub contractor communication and
provide a frame work for multi skilling and long term employment with larger, stronger
and more skilled sub contract organizations.
Dombkins ( 1993 ) further iterates that restructing programs have todate ignore the
industries culture. Without a trust based, shared objectives culture all of these cultural
changes will have very limited long term effect. The existing culture will simply reshape
the new structural changes to remain the same - "win-loose". Partnering is a cultural
process for organizations It is a bridge for organizations to change from machine
bureaucracies to stakeholder focused flexible learning organizations. The key to
organizational change is the organization's culture.
Partnering takes the key elements required for cultural change and combines them into
a simply process that is easily understood and emotionally accepted by all organization
members. Partnering focuses on cultural change rather than structural change. It is a
strategic change process that deals with a small number of high leverage points initially
while laying the foundations for an ongoing change process. ( Dombkitts 1993 ).
126
The following Table 8.1 identifies key partnering relationship practices and compares
them with traditional practices of most organizations and individuals :
Partnering is going back to the way people used to do business when a person's word
was their bond and people accepted responsibility. Partnering not a contract, but a
recognition that every contract includes at the convenant of "good faith and fair
dealing". While the contract establishes the legal relationships among the parties
(stakeholders ) through a mutually developed, formal strategy of commitment and
communication. It attempts to create an environment where trust and team work
prevent disputes, foster a co-operative bond to everyone's benefit, and facilitate the
completion of a successful project.
Partnering is not a contractual agreement nor does it create any legally enforceable
rights or duties. It is the contract that provides the legal relationship, with partnering
establishing the working relationships among the stakeholders through a mutually -
developed, formal strategy of communication and commitment.
However partnering has a great potential to affect the legal relationship of the parties,
particularly at the issue resolution stage where the parties are to enter into discussions
with each other and be frank and open with the communication. Therefore to avoid the
contractual being inconsistent with the actual relationship between parties, The
Australian Legal Group recommends that the contracts should be drafted to reflect the
partnering relationship developed by the parties. ( The Australian Legal Group 1993).
- -
According to the definition of partnering given by Task Force, the key elements of any
partnering relationship are : trust, long-term commitment, and shared vision. As these
key elements are developed in a relationship, other sub elements are achieved and the
benefits to all parties are maximized. Both the customer and the supplier can profit
from reduced overhead and workload stability. Competitive advantage in their
respective markets is enhanced through improved cost, quality and schedule. Most
importantly, TQM and continuous improvement are achieved.
Trust : Trust enables combining the resources and knowledge of each partner in a
fashion to eliminate adversarial relationships. Partners are then be able to share
information, tolerate contact with others and accept diminished control resulting in
enhanced capabilities for the partnering relationship.
Shared Vision : Each of the partnering organizations must understand the need for a
shared vision and common mission for the partnering relationship. To achieve this there
nee-1- to be a innt-.1 exchange of ideas and an agreement of expectations. Shared
vision will be achieved when an atmosphere of openness and candidness has been
established.
Investment : All parties invest in partnering; each invests the strengths uniquely
possessed that can contribute to success. Investment in new business systems also may
be required.
Shared Risk : All parties take appropriate risk commensurate with their rewards and the
concepts unique to their partnering relationship.
Rewards : There must be advantages and opportunities. All parties should expect more
than is available in other relationships commensurate with their investments and risks.
Competitive edge : All parties seek new ways to lower costs and differentiate
themselves to gain competitive advantage.
( CH 1991).
132
Non-structural elements
Commitment : There must be a real commitment to partnering at all management levels
within each stakeholder's organization.
Equity : Each stakeholder's interests, needs, expectations, constraints and risks must be
given fair and proper consideration by the other stakeholders. Where possible, both the
beneficial and adverse outcomes of risks should be shared among the stakeholders on
an equitable basis.
Trust : Teamwork is not possible where there is cynicism about other stakeholder's
motives. Through equity comes understanding which leads to trust and hence the ability
of the stakeholders to function as a team.
Structural elements
Partnering charter : Stakeholders identify all respective objectives for the project in
which their interests overlap. They then jointly develop a set of mutually agreed
objectives which becomes the shared objectives of the project within the partnering
relationship. The shared objectives may be set down in a "partnering charter" along
with a jointly formulated mission statement.
structure and roles for the on-site and off-site management teams together with a
timetable for partnering meetings.
The other difference is that the CPSC / MBA model seems to be readily applicable for
construction industry while US model is general in nature. Both of these methods are
being used in public and private sectors in US and Australia. Partnering is relatively
new concept to Australia and most of the relationships are still not mature enough to
provide maximum benefits..
It can be assumed that the elements of both models have some relationships with
social, cultural and legal issues in respective countries. In spite of that both methods
aim at the same goals. That is to create a "win-win" situation for all the parties within a
harmonious project environment, while providing maximum benefits to all.
134
9.0 Introduction
The partnering process is a set of guidelines for establishing and maintaining a
partnering relationship. Because every project is unique and the particular stakeholder's
for each project will vary, the process should be tailored by and for these stakeholders
for the project. A partnering process can be developed for any type project and any size
project.
This chapter describes the partnering processes ( as defined by the Partnering Task
Force of US and Construction Policy Steering Committee of NSW / Master Builders
Association ) its benefits and, concerns. Following is a partnering realignment process,
a corrective process that can be implemented to save the troubled projects.
Optimal crisis
prevention
period
Figure 9.1: Project life cycle. ( Source : Harback, Basham, Buhts 1994)
The life cycle of a project can be shown as a downward sloping curve when the impact
one has on the project is compared with specific points of time during the project's
135
"!,4 project cost is most influenced by what happens in the pre-project planning
phases. Team members communicating at this point can avoid mistakes, thus
saving real capital dollars and real schedule completion time"- Jack Whitney,
Project Director of CUH2A, Inc., Princeton, New Jersey ( cited in FMI
publication 1993).
The strategy development step involves a partnering feasibility study and defining the
objectives and rationale for entering a partnering relationship. The partner selection step
includes analysing a potential partner's strengths and weaknesses, and preparing
appropriate selection criteria. The contract negotiations step includes the process of
writing the contract to meet the objectives of both parties. The implementation step
136
includes preparations of all parties involved to initiate and maintain the new partnering
relationship ( CH 1989).
Partnering Task Force has developed set of guidelines on selecting a partner. The
process, usually initiated by the owner, includes an in-depth self evaluation of the needs
and objectives to be served by a partnering approach. After the internal assessment is
concluded and decision is made to pursue partnering, the owner then needs to identify a
team, develop a plan and proceed with selecting partner.
Potential partners are selected from a long list. The process of moving from a long to a
short list of potential partners can be accomplished either through personnel interviews
or by requesting written responses to an inquiry document.
The partner selection process takes longer time than the traditional contractor selection
schedule. The experience of companies that currently have partnering arrangements
indicate that generally from 6 to 18 months were required from the time of
management approval to pursue their first partnering relationship until start of the work
under the partnering agreement began. Reasons for this relatively long time requirement
may include :
The need for greater involvement of their total organization in developing the
selection criteria and evaluation.
The need to ensure a philosophical / cultural match between the two companies.
The need to obtain top management approval of the partner selection.
The need to develop a new method of doing business where traditional procedures
and documents do not apply.
The length of time required appears to be most influenced by the owner's readiness to
enter into a partnering agreement and whether a well-thought-out partner selection
process has been utilized In some cases, the schedule was heavily influenced by the
availability ( or lack ) of work ( CII 1991).
There are certain prerequisites that must be met before the commencement of
partnering process. CPSC ( 1993 ) consider these prerequisites are essential because it
will provide a sound basis for the successful implementation.
Make partnering intensions clear : The owners intention to encourage partnering can be
mentioned in the tender document. The provision would emphasize the voluntary
nature of partnering and that the costs associated with implementing it would be shared
equally but with no additional change in the contract price.
" In order to effectively and efficiently accomplish the work provided for in this
contract, the government is encouraging formation of a cohesive, mutually
beneficial partnership with the contractor and its subcontractors. This
partnership would strive to draw on strengths, skills and knowledge of each
organization to achieve a quality project done right the first time, within budget,
safely and schedule. The focus of partnering is to build cooperative
relationships, avoid or minimize disputes, and actively pursue the attainment of
138
The non-structural human value elements of commitment, equity and trusts are
established through open communications and the development of team spirit. This is
achieved by all stakeholders identifying and discussing their respective issues, problems,
opportunities and constraints along with their interests, expectations, goals and
objectives.
These are used as the basis for development of the structural elements in which shared
objectives and a mission statement are defined that together form the partnering charter
This leads to the formulation of the "communication frame work" along with the
evaluation and conflict avoidance procedures to assist in the achievement of the stated
shared objectives ( CPSC 1993).
Normally the workshop is led by a facilitator who explains the goals of the session and
serves as a moderator during the ensuring group discussions. He or she must be
reasonably neutral on the subject under discussion and has a primary goal of reaching
consensus among the team. Choosing a facilitator is important because each one has a
unique that needs to be matched to the focus and personalities of the partners
(Abydayyeh 1994, Harback, Basham, Buhts 1994).
139
While not essential, CPSC also recommend that a professional facilitator be used in
these early development stages of partnering. The workshop concludes with the signing
of the partnering charter by each participant, including off-site partners, as a formal
commitment to the partnering relationship ( CPSC 1993 ).
Under this process contract is drafted after selecting the partner to meet the objectives
of both parties. Contractor can provide input to the buildability of the project and
advice client on various aspects before commencement of the work. Another
advantage is the contractual relationship will not be inconsistent with the actual
relationship between parties.
However the US Army Corps of Engineers has used the partnering for full and open
competitive strategy for construction projects successfully ( project by project basis by
following a similar method like CPSC / MBA method ) The central objective of
partnering here is to encourage contracting parties to change their traditional adversarial
relationship to a more team based approach ( Weston and Gibson 1993).
140
Under this process it does not require contractors to enter into a partnering agreement
as part of the contract. It is totally a voluntary decision. When tenders are calling a
general statement of intent is included to convey the client's intention to use partnering
at the earlier stages of project inception. This process appears to be popular in US and
Australia.
Harback, Basham, Buhts ( 1994 ) expressed their concern, about the difficult in
establishing a successful partnering without first instituting a Total Quality process
within the organization. And before Total Quality can take root, there has to be a clear
corporate vision that has been communicated to all employees. First vision, then focus
on Total Quality. It is in this paradigm that the customer, continuous improvement and
team work are paramount.
141
Partnering provides the ideal environment for TQM as it focuses on a long term
approach of improving ongoing processes rather than emphasizing individual projects
or tasks ( CH 1991 ). It is evident that such environment is only created by "true
partnering" with long term commitment. The overall success of the business objectives
and the participants will be achieved through effective resource utilization and the
continuous improvement of the quality of the products and services.
Relationships
Joint Perspective
Adversarial relationships will be reduced which will allow focus on
mutual goals to the benefit of both organizations.
Responsiveness A partner will be more responsive to the short-term emergency,
changing project or business needs.
Survey results
Less Adversarial 85% Increased openness 82 %
Improved res. planning 85% Increased trust 78%
Table 9.3 : Benefit : Reduced cost and schedule and improved profit ( value )
Item Contractor's Perspective Owner's perspective
In-House Cost A long term commitment is made A capable partner will allow
to support the contractor's owners to reduce in-house fixed
overhead costs associated with the staff and minimize oversight of
core group. contractor.
Selection The cost associated with bidding The costs associated with
on a project basis will be contractor selection on a project
eliminated, basis is eliminated.
Administration The cost to negotiate and administer contracts will be decreased as
partners become knowledgeable of their counterparts legal and
litigation concerns.
Learning curve The costs associated with kickoff and indoctrination of a project will
be significantly reduced as partners move down the learning curve and
better understand requirements. In addition the time to initiate a project
will be reduced.
Innovation The partners will be able to discuss innovation and associated risks in
an open manner, and share risks and rewards fairly.
Constructibility The early involvement by the contractor can assist in constructability
input and maximizing value engineering, thus improving both cost and
schedule.
Commitment The long term trust relationship will contribute to all parties focusing
on the project goals and result in improved cost and schedule
performance.
Survey Results
Total project cost reduced 8 %
Improved contractor profitability 10 %
Improvement in schedule 7 %
Survey results
Engineering cost reduction 10 %
Administrative cost reduction 6 %
Improved Communications and teamwork 82 % of
respondents
A Partnering relationship also presents some challenges and concerns to both owners
and contractors. Some of the major opinions of the industry participants contacted by
partnering Task Force are summarized in thc Tables 9.5 and 9.6 ( An owners view
point and a contractor's view point respectively ), along with suggested actions to avoid
or minimize the listed challenge or concern ( Source : CH 1991).
For all stakeholders involved in the delivery of a project, partnering requires effort. It
may require increased staff and management time initially, but benefits will accrue due
to a more harmonious, less confrontational process, and by completion of a successful
project without litigation claims.
MBA ( 1992 ) identified the following list of benefits to the stakeholders in partnering
projects. All stakeholders benefit by an increased opportunity for a financial successful
project because of non adversarial "win - win" attitude.
146
Current financial and corporate culture limitations existing in the Australian market
places at risk this positive initiative reaching its full potential. Some of the concerns,
challenges and legal issues prevailing in Australia are reported in Section 11.5.
147
Partnering realignment comes before and goes beyond the dispute resolution steps of
negotiation, arbitration, mediation, and litigation. It is an attempt to regain and retain
control of the project and plan ways to avoid future problems. The minimum
requirements for successful implementation are
Executive sponsors from each of the participating organizations must champion the
recovery effort;
Each stakeholder organization must acknowledge that they are a part of the problem
and must be a part of the solution;
Adequate resources must be allocated; a one time team-building event won't end the
trouble.
Roll Down
The partnering realignment process involves six steps as shown in the Figure 9.2. The
level of effort and activities undertaken depend on the needs of the project.
1. Situation appraisal and perception interviews : Interviews are conducted with project
executives and key members identified by the executives, coveting each persons
perspective of the issues, concerns, opportunities and threats presented by the project.
148
Executive debriefing and planning session :Since the project executives are pivotal
for the realignment and recovery effort they must be debriefed on the composite report
and agree to champion change. The facilitator records the work of the executives in a
focus document and sends it back to the participants to aid communications and follows
through.
Each session is unique because each project and the problems to be dealt with are
different. The session ended with a group dinner at which the executives shared this
information with key project personnel. Project goals were shared along with
expectations for the remainder of the project.
Initial partnering realignment session : Key members of the project team are brought
together for a two day work session. During the session, a structured process is used to
focus existing issues and answer the remaining process questions :
Where do we want to go ?
How will we get there together ?
How can we ensure success ?
How can we measure our progress?
Since the session is based on perception interview data and the executive debriefmg out
come, each is unique. Within a week after this session, a realignment focus report is
distributed to all participants and project executives outlining what was agreed to.
5 Intercompany team building : Just because teams may work for the same organization
does not mean that they have the same goals. The most common example of this
involves the client's organization. Within the client's organization, problems frequently
occur among functional departments that do not have the same project objectives.
Intercompany conflict creates problems for the other contracting organizations and
results in more work unless properly addressed and managed. Team building sessions
typically address these issues, as well as the cost of making changes during c,oristractiori
and a process to manage the scope of the project.
Follow-up sessions are required to reinforce the lessons learned and the agreements
made during the initial workshops. At this session the team formally evaluates their
progress, address remaining and emerging concerns, and identifies any readjustment
that must be made.
With partnering realignment the project focuses on existing opportunities that benefit all
stake holders. By contrast, someone always roses in post project litigation. Litigation
cannot turn the project or help realize potential savings.
Successful realignment benefits everyone. The owner gains better control of project
costs and a better product because less energy is being spent on misdirected adversarial
concerns and case building. Other project stake holders benefit from more timely owner
decisions and improved cash flow due to fewer disputes and with held payments. The
less tangible benefits include improved communication and morale.
150
Barriers to realignment
Realignment can be achieved if the organizations and their project representatives want
to be successful. If the desire for success is not there, no realignment process will work
completely. Some typical problems include :
The inability to get together often becomes the largest barrier to addressing the
problems and determining the way out;
Realignment must continue even which things seems to improve. The engineering
process is not halted just because construction appears to be going well.
Commitment has to be for the remainder of the project;
The phenomenon of frustrated progress needs to be understand. Frustrated progress
is the dynamic created when recognized problems increase although actual
problems may be decreasing. Although progress being made, frustration can occur.
( Brown 1994)
151
10.0 Introduction
Partnering for the projects was initiated by the US Army Corps of Engineers in the late
80's when it was used on large civil engineering projects. The partnering process has
been spread rapidly across US and now widely used by both private and public
organizations on a broad spectrum of project types.
Partnering has been successfully used on building, civil engineering, mechanical
engineering, structural technology implementation, maintenance and organizational
change projects.
Partnering has been successfully used on negotiated, open tender, selective tender,
novation, and design and construct projects.
( Dombkins 1993)
Partnering Task Force has found many business affiances in other countries, specially
in Japan and Europe, but are not called partnering. According to the findings of Task
Force Japanese and European companies are far ahead of US companies when it
comes to the number of alliances formed.
Apart from a brief review of the Japanese way of doing businesses, mainly this
chapter describes the US experience with partnering applications and provides case
histories.
Japan has been prohibited by their constitution from creating nothing more than a
national defence force. So the government has spent very little on defence and been
able to focus its full attention and resources on economic growth. In Japan there is one
general contractor for every third of a square mile 75% of who are capitalized for less
than US$ 37,000, but where there area half a dozen companies Kajima, Shimizu,
Takenaka, Taisei, Ohbayashi, and Kumagai Gumi known as the "Big Six" who have
yearly sales totalling US$ 35 - 40 billion (Levy 1990).
152
These six major companies have long term relationships with many owners in Japan,
extending to overseas projects for those companies. Such close relationships in the US
would be difficult to develop and maintain due to US anti-trust laws. The relationship
between owner and contractor is based on mutual trust and commitment. Businesses in
Japan prefer to make verbal commitments rather than written ones. The owner trusts
that the contractor will finish on time ; the contractor has faith that the owner will
compensate for any justifiable expenses that are suffered when trying to enhance the
('IT 1991 ).
The good faith concept in construction contracts is exhibited by purposely leaving the
details vague so that they can be filled in as construction progress and the previous
understandings between the parties start to unfold.
The harmony that pervades Japanese daily life is alive and well in construction
contracts, and the relative ease with which these contracts are executed in mainly the
result of a builder - client relationship that has existed over many years, in some cases
over 100 years. During that time contractor and client have grown to know each other
and the relationship is some cases has passed from generation to generation. In many
cases, the builder has already completed similar buildings for his client and very familiar
with the owner's requirements, quality levels and preferred choice of materials and
equipment. By making minor changes in a new building program and updating project
costs, a new project concept and budget can be prepared with minimal additional owner
input. The client on the other hand, is aware of construction costs and general building
and construction details from previous projects with his contractor, so that the meeting
of the minds of a new structure can be simply and quickly attained ( Levy 1990).
153
10.2 US Experience
Partnering on construction projects was pioneered by the Portland District of the US
Army Corps of Engineers and they have derived substantial benefits from its
application.
The US$ 34 million Bonneville Navlock Diaphragm Wall was the first large project in
the Portland District to use the partnering process. It was completed in February 1992
as part of the US$ 330 million Borunneville Navigation Lock Dam project on the
Colombia River with the following out comes :
No outstanding claims or litigation.
Value management savings of US$ 1.8 million, exceeding the goal of US$ 1.0
million.
Cost growth contained to 3.3% compared with a typical 10% for a major
construction project.
On schedule completion.
No lost time due to injuries.
Two thirds reduction in paper work.
The US$ 5 million Hatchery Wells project was also part of the Bonneville Navigation
Lock and Dam project and one on which partnering was used. All goals were met and
the project was completed one month early with no lost time accidents. It was 4.38%
under budget and returned US$ 72,000 in value management savings.
In Arizona, the Department of Transport ( DOT ) has been utilizing partnering for the
last two years. As of March 1992, partnering had been adopted on 12 projects ranging
from US$ 900,000 to US$ 18 million and worth a total of US$ 87 million in all. The
first seven projects reaped US$ 635,000 in value management savings. They were
completed a total of 16 months early, yielding another US$ 500,000 in construction /
engineering savings ( cited in CPSC 1993).
proposed and implemented innovative construction methods that benefit him and
Caltrans ( cited in Abudayyeh 1994).
From the supplier's and the contractor's side, there may be a need for a stable workload
and enhanced business opportunities. Partnering requires that contractors participate
with the owner in the project planning and estimating phases to minimize both cost and
schedule. In addition it requires that contractors and suppliers be involved in the
procurement of needed materials, be able to carry the extra work load and provide the
quality of work required. Moreover, they should be open to learning owner's
procedures, adopting their goals and being prepared to spend time and money in order
to accomplish these requirements ( CU 1991 ).
155
Partnering is also being applied on small projects. In this instance the relationship covers
many small projects for the same owner, thus creating a largc volume of work.
Partnering does not appear applicable to small, stand alone single projects because the
size of such projects does not support there effort to develop the relationship. A series
of small projects evenly spread over time, however would be a candidate application.
Partnering also applicable to small businesses.
There is a tremendous potential for much broader beneficial applications. Two key
factors may stimulate such applications.
Existing relationships must continue to be successful and show measurable benefits.
A method of measuring the benefits of the broader application must be developed.
( CH 1991).
The focus of the small owner / contractor relationships are beginning to focus on long -
term improvements.
Partnering Task Force define "small owner" and "small contractor" as follows :
"Small owner is a manufacturing processing, or service business whose yearly
volume does not gain entry in to the Fortune 500 listings".
"Small contractor is an architect, engineer or constructor whose business is
regional or local in nature".
The opportunity for partnering is at least as great for the small owner and small
contractor as for their large counterparts. Many continuous, but low volume services
are required at small owner's manufacturing and processing facilities that lend them
157
For many small owners, a continuous stream of small capital and / or maintenance
projects also provide an opportunity for partnering for engineering and / or
construction. Only those owners who are so small where there is no continuous or
frequent need for out side services do not have a viable opportunity to partner.
The great diversity of services needed by the small owner community described above
offers a varied field or small contractors. Speciality design, specialty construction,
general engineering, general construction, and engineer - procure - construct are all
services provided by small contractors in a near partnering or partnering mode ( CII
1991).
Lack of formality : In SBP arrangements the focus is on a lean, efficient project group
that maximizes short-term execution benefits. The long term is not managed other than
as an extension of the short-term focus to succeeding projects. LBP participants have
found it necessary to formalize the partnering culture. The search for a partner,
commercial negotiations for the partnering work ( including contract format ), and
development of internal structures are significant activities.
approaches to risk management for what is perceived as a large volume, unique service
versus a low volume, readily available service.
Project Execution : Project execution by SBP generally differs from that of LBP simply
because the services performed are different, and the small contractor's personnel
generally have different skills. These differences are based on contractor function rather
than on partnering aspects ( CH 1991).
The partnering Task Force has confirmed several instances of partnering between
owners and contractors for small projects. Irrespective of the participant size, partnering
relationships have been formed to execute small projects.
Most opportunities for small projects include small capital projects and maintenance.
Work may include design, specialty construction, general construction, maintenance,
start up and operation assistance, and construction management. Small project
partnering appears to favour construction companies rather than engineering firms since
much of the small of capital work are not design- intensive and can be engineered by a
small plant ( owner ) engineering staff( al 1991 ).
locates the design team in a regional office or at the owner's plant site. The construction
contractor will typically have a reduced field organization reflecting the smaller scope of
work. However, the ability to properly interface owner and contractor personnel is also
critical to the successful execution of small project partnering.
The selection process : Due to the small scale of work , the potential contractor's
familiarity with the plant and operations is often a greater concern to the owner than in
the case of large project relationships. Geographic proximity is often a key criterion.
Initiation of the partnering arrangement : 90% of the respondents to the second Task
Force survey indicate that the owner is responsible for initiating the partnering
arrangement, with a few initiated by contractors. Most companies have chosen the
negotiation process to establish their arrangements. In the second Task Force 68% of
the relationships responding were established through negotiations, while 32% were
established through a bidding procedure.
160
Information reported indicates that projects have ranged from US$ 10,000 to US$ 1
billion, a large spectrum of project sizes The average project size was US$ 3.4 million
for "small" projects, US$ 35 million for "medium" size projects, and US$ 119 million
for "large" projects. Typically the sizes of the of projects performed are directly related
to the sizes of the parties involved.
Improved communication .
Cultural differences :
Overcoming cultural and procedural differences between the two organizations is
essential and difficult.
162
Acceptance of mixed-team leadership and taking orders from the other company's
representative are important, but difficult.
Creating a cultural shift at the working levels of the contract is difficult at the
beginning of a relationship.
Continuity of workload :
Uncertain workload makes planning difficult in the beginning.
Results
Overall results cannot be measured until a series of projects is completed.
Unexpected weaknesses in each other's organization could be discovered that are
detertninantal to the relationship.
Regulatory requirements for public agencies, such as the Corps of Engineers, require
(with few exceptions ) the use of a full and open, competitive low bid contracting
strategy for construction projects. Therefore they are unable to establish there sort of
long term relationships that are essential to partnering in the private sector. However,
Corps of Engineers districts have completed 19 projects since 1988 using project
partnering agreements with an additional 85 projects ongoing or scheduled to start.
Research methodology
Those districts with completed partnering projects were asked to provide project data
for those projects. Additionally, data for similar non partnering projects were requested
for use as a comparison sample. These data ( cost, cost of change orders, cost of
claims, value engineering savings and schedule ) were then normalized as a percentage
of total original construction award cost or duration. A "t test" of sample means ( an
introduction to "t-distribution" is given in Appendix 3 ) was performed to show that the
partnering project sample was statistically different from the sample of non partnering
projects.
163
Presentation of data
Partnering projects : The survey of districts revealed that 19 partnering have been
completed in 9 districts. Weston and Gibson ( 1993 ) were able to obtain data for 16 of
the 19 partnering completed projects. Of the 16 projects, 12 ( 75%) were civil-works
construction projects, while four ( 25% ) were military construction projects. The
contract award price for partnering projects ranged from a low of US$ 1,551,340 to a
high of US$ 33,900,000. The average contract award price for the partnering projects
as US$10,368,643.
Non partnering projects : Eight districts contributed project data for 39 non partnering
projects, 28 were selected for use as comparison projects. Of those 28 projects, 13
were selected because they came from the same districts as the partnering projects. The
remaining 15 projects were selected because they fell within a range of US$ 1 to 33
million. Of the non partnering projects, 16 ( 57% ) were civil works construction
projects and 12 ( 43% ) were military construction projects. The contract award price
for non partnering projects ranges from a low of US$ 321,696 to a high of US$
56,490,000. The average contract award price was US$11,448,745.
Analysis of data
The following Table 10.1 summarizes the average performance for both partnering
projects and non partnering projects. The results tend to show that partnering projects
performed better on average than the sample of non partnering projects in the
categories of cost, schedule, change - order cost, claims cost, and value engineering
samples for the samples used in the study.
Table 10.1: Project performance comparison. ( Source : Weston and Gibson 1993)
164
The results of the "t test", applied to the sample means for the average contract award
price, cost change, duration change, and change order cost are given in Table 10.2.
The sample variances of the cost change, duration change, and change order costs for
partnering and non partnering projects are shown in Table 10.3.
Project controls are the techniques, methods, tools, and style of implementation used to
control the time, cost, and quality of a project. According to Thamhain ( 1991 )
"effective project control is the ability to manage a project according to an established
plan ( time, budget, resources ) producing agreed upon results ( time, budget, expected
deliverables ) "
People are the most valuable asset of an organization, and it follows that the control of
a project starts with the team development. It is the team involved in a project that can
ultimately produce success or failure. Motivation and commitment of people on a
project are critical to the successful control of that project. Leadership, among other
things, strives to achieve commitment from the people involved, i.e. commitment
towards the project and its efficient completion. The metrics ( which refers to
measurable quantities, management style, and effectiveness ) of a project are the
deliverables and the plans to achieve them, as compared to the results finally obtained
(Thamhain 1991, cited in Woodrich 1993).
Partnering at J - 6 provides the environment for people to meet on the same grounds
(without hidden agendas ), work out a detailed plan, reach agreement between the
teams, obtain commitment from the team and management, defme measurable
milestones, detect problems early, communicate the true project status, and meet
milestones ( including the delivery of final product ).
Performance value indexing those figures, one has an estimated cost at completion of
US$ 200,000,000 that equates to 113% efficiency. Although J - 6 personnel claim that
the entire US$ 226,000,000 will be utilized due to the government's program funding
restrictions.
166
"By using J - 6 as a test bed for not only rocket motors, but the implementation
of partnering within the Air Force, we have created the true success stoiy" -
Woodrich
Woodrich ( 1993 ) introduces partnering as a possible second generation TQM tool and
further suggests that the entire Department of Defence procurement system should
entertain the thought of implementation.
167
11.0 Introduction
According to Domblcins ( 1993 ) the construction industry in Australia is characterized
by lack of trust between all stakeholders. The party in the best bargaining position takes
advantage of the position. The disadvantage parties bide their time and wait for the
cycle to change for their turn to take advantage ( Dombkins 1993). In general this may
be true.
However the results of partnering projects in Australia have been very encouraging
with projects coming in under budget and under time, with no claims or litigation,
achieving a higher quality and the projects are being undertaken in a wonderful spirit of
cooperation and teamwork which has not been the experience in the last few decades
(MBA of SA 1994).
11.1 Background
One of the conclusions of the NSW Royal Commission into Productivity in the
Building Industry research was that project outcomes were heavily influenced by the
relationships between the parties involved in the industry.
This adversarial approach has evolved over many years. It often has it roots in the
earliest stages of project inception with each party developing their own management
team. Each team then independent/ formulates its own goals and decision frameworks
for the project without regard for the other parties interests or expectations. As a
consequence, communication is limited and often non-existent - with the result that
conflicts are inevitable as paths diverge and expectations are not met.
This adversarial climate has severely reduced the productivity of the construction
industry and consequently its ability to achieve the primary goal of producing quality
projects on time and within budget.
168
A concept termed "partnering" is a move towards such a cultural change. It has been
adopted by the NSW government as part of its integrated reform philosophy for the
industry ( CPSC 1993).
Initially, Partnering will be trialled on projects which have a value of $5.0 million and
above. A target has been set with the Government's overall capital program that 20 %
of all projects which meet the criteria will be partnered in 1994. Should the partnering
process achieve, within that range of capital investment, similar levels of return on
investment to that experienced elsewhere in the world, it will be progressively applied to
a wider range of capital projects
169
The CPSC will co-ordinate the trialling process to achieve the 20% target. The CPSC
will then assess the worth of the process prior to its consideration of wider application
to the State's capital investment program from 1 July 1995 ( CPSC 1993).
Master Builders Australia continues to foster the concept through its Director of
Training, Denis Wilson who has facilitated many of these projects that have embraced
the concept of partnering ( MBA of SA 1994).
"It has spread like wildfire. I guess we have partnered $ 600 million of
projects. Productivity has increased and people are comfortable they are
managing project better" - Denis Wilson ( cited in Rowbotham 1993)
Wthington had done research for the Commission into attitudes and behaviour on
building sites, became the facilitator of the partnering between Macquarie University,
Leighton Contractors and the architectural firm Devine, Erby Mazlin Australia in the
construction of the $ 12 million science and technology building on the campus.
Partnering has been favourably received in other circles : The New South Wales
University of Technology law faculty has included it in the curriculum as part of the
alternate dispute - resolution masters program, and anuQantasnr.1_,
. A AL"
Department of Environment, Land and Planning and a private consultant, Willing and
Partners as well as the principal and the contractor. According to Reilly there are
savings of tens of thousands of dollars from Yerrabi Pond project.
Queensland based Thiess Contractors discovered partnering about the same time as the
MBA and is using it on 15 projects valued at more than $ 120 million. Thiess
Contractors interest in the idea grew out of a change in internal culture through TQM.
Russell Todd, National Contracts Manager of Thiess Contractors describes :
"This partnering concept is not something that happens overnight, it needs
commitment and dedication to make it work because you are looking at
environmental change within the industry."
( cited in Rowbotham 1993)
In NSW, Public Works has been using partnering approach for more than $ 160
million worth of projects over the past year ( 1993 ), including six hospitals as far afield
as Penrith, Albury and Maitland. On NSW health projects, Public Works partners
include :
Nepean Hospital Main building - Barclay Mowlem Construction
Nepean Hospital Theatres - Stuart Bros.
Albury Hospital - Leighton Contractors
Sydney Hospital - Fletcher Construction
Maitland Hospital - Fletcher construction
The cooperative partnering approach adopted for these and other NSW Public Works
projects has been an outstanding success : in 1993 Public Works won the two national
partnering awards from MBA, one of them going to the Nepean Hospital Project team.
( cited in The Australian Project Manager 1994).
The first step was to bring the participants together at a two day workshop, to focus on
the individual and project objectives to formulate a project mission statement. The
participants are the Wentworth Area Health Service and Nepean Hospital ( client ), the
Public Works Department of NSW ( project managers ). Barclay Mowlem ( builders )
design development consultants ( headed by the architects Brown Brewer and Gregory
Pty Ltd. ) and contractors.
The workshop enabled all parties to get to know each other and breakdown the barriers
that can exist in any project activities at the workshop included team building, conflict
resolution and establishment of a communication matrix. General discussion on the
goals of each organization and how this related to the goals of the project was also
encouraged. At this stage, the client and builder relationship was established on a
partnering basis with all parties committed to maintaining a harmonious and fruitful
effort.
The subcontractors were invited to attend a workshop on site to discuss the principles
of partnering. This allowed them to communicate to each other their goals for the
project. Many subcontractors had commented that it was refreshing to have an
opportunity to influence their own future, rather than to be told of the main contractors
decisions, made in isolation that often cost them vast sums. Continuing commitment to
the partnering process was maintained through a regular series of project forums. These
meetings enabled subcontractors to discuss issues with each other and with the main
contractor.
A positive relationship had been established with many of the workers, which had
reinforced the attitude of teamwork and mutual commitment to the project. The team
had taken ownership of problems and jointly resolved them to the benefit of the
project and to all its partners.
173
"Client's satisfaction" is a high priority in any project, without this, the project cannot
be regarded as a success. Milne ( 1994 ) explains that the partnering allows to
understand fully the client's needs and motivation for the project.. Further he iterates
that partnering allows the contractor and the client to share and minimize "risks" and to
create an environment of "fairness to all" - recognize the rights of all parties to fair and
equitable treatment.
BARCLAY MOWLEM
The Neoean Hosoaal
Penntn
N
WENT WORTH AREA
HEALTH SERVICE
PARTNERING CHARTER
NEPEAN HOSPITAL UPGRADE PROJECT
Main Building
MISSION STATEMENT
Our Mission is to manage the project as a team to achieve a common gaol bcsect
on the concept of partners, ensuring the team strives for excellence in the areas of
co-operation, trust and understanding, minimising project tisk by supporting irriParltolIV
each partners efforts for improvement to reach the following objectives.
PARTNERING OBJECTIVES
1. BUDGET All stakeholders realise their financial goals.
2. TIME Achieve agreed milestones with final hanclover by 30th June, 1994.
3. QUALITY AND FUNCTIONAUTY Meets or exceeds specified quality standards.
4. HOSPITAL FUNCTIONING Maintain hospital activities through effective co-ordination
of construction activities, with sensitMly to hospital staff, patients and visitors.
S. SAFETY Ensure a safe working environment for all people associated with the project.
6. CONFLICT RESOLUTION Ensure effective resolution of grievances and
claims within agreed time period.
7. ENJOYABLE PROJECT Provide an atmosphere conducive to hign morale and
productivity and where all participants achieve job satisfaction.
a. FAIRNESS TO ALL Recognise the rights of all parties to fair and equitable treatment.
9. EXTERNAL RELATIONS Meet all obligations to the community and government.
so. INDUSTRY MODEL Create a new industry model which can be
a benchmark for future protects.
Figure 11.1: Partnering charter - Nepean hospital upgrade project. ( Source : CPSC
1993)
174
Apparently Australia has not achieved a similar position. Issues such as capital adequacy
testing and the recently introduced ODA Code of Performance criteria go some way to
establishing a more predictable playing field. According to Chandler's (1994 ) openion
the resolution subject will only occur when self interested customer groups become
prepared to fully expose their real performances and stop hiding behind the lack of
competition argument.
The Australian Legal Group ( 1993 ) noted that there is a great potential to affect the
legal relationships of the parties, particularly at the issue resolution stage where the
parties are to enter into discussions with each other and be frank and open with their
communication. To avoid the contractual relationships being inconsistent with the actual
relationship between parties, the Australian Legal group ( 1993 ) recommend to draft
the contracts to reflect the partnering relationship developed by the parties. For
example:
The objectives in the partnering charter should be reflected in the contracts.
Representations made in the workshop which have been relied upon should be
incorporated in the contracts.
Review procedures in contracts should be consistent with the joint evaluation
process.
Disputes resolution clause in contracts should be consistent with the issue resolution
process.
( The Australian Legal Group - April 1993)
Hibbert ( 1994 ) raises some legal issues related to the partnering application. The
essence of partnering is a cooperative management style of work, intent upon
overcoming traditional adversarial and litigious relationships and directed to achieving
the project objectives of all parties.
But because in practice partnering may involve principal and contractor jointly assessing
actual or potential non conformances, it can give rise to significant legal issues for
175
project managers in areas such as authority, delegation of powers and the establishment
and documentation of on-site procedures.
Apparently most partnering projects to date used relatively unamended standard forms
of contract, supplemented by an agreed set of partnering procedures and the necessary
partnering charter. Hibbert ( 1994 ) further questioned whether would it not be better
for the construction contract to attempt to express better the aims of and objectives of
the partnering parties ? Should not those responsible for the preparation of the key
project documentation try to ensure that not only represents, but importantly facilitates,
all the various partnering procedures ?
Therefore the industry need to structure and document project contracts better, not only
to accommodate, but more importantly facilitate the partnering principles and their
associated procedures.
More and more "key people" in both contractors and principal's organizations are being
declared for projects. This is specially important on a partnered project, because the
emphasis on constant frank communications. So the concern in here is that if principal
or contractor nominate key personnel who are, or at least appear to be, inappropriate to
participate honestly and openly in the partnering procedures, the project manager will
have to work with those people and "re-train" them in the ways of partnering or
otherwise suggest that they be replaced.
Most modern contracts now recognize the need for an advantage of an early warning of
alerting process. The objective is to encourage the contractor, or other parties if need
be, to raise issues with the other which may affect performance adversely but which,
constructively, should be addressed by both parties to the project. The essence of alerts
or warnings is early, constructive communication. It is difficult to imagine a partnering
project being successful without a willingness on both sides to discuss events which
may effect time, cost or quality or either party's ability to carry out obligations ( Hibbert
1994).
There are certain issues that may place the positive side of partnering at risk. Some of
them are:
The industry has not shown a broad CEO to CEO commitment to the process either
internally or externally to their organization.
Partnering is being used for short term gain in some instances which leaves a trial of
disillusioned customers or project partners. Hibbert ( 1994 ) has observed that many
176
of the users of partnering fear that the process leaves some established contractual
rights and remedies uncertain.
Measurement needs to be substantially refmed and project performance measured
against some real benchmarks so that long term competitive outcomes can be
maintained ( Chandler 1994).
177
12.0 Introduction
As mentioned in the research methodology, under the phases 1 and 2, received seven
completed questionnaires giving an overall response rate of 14%. The sizes ( number
of employees ) and the range of project sizes in terms of contract sums undertaking by
each company C 1, C2, C3, C4, C5, C6 and C7 are summarized in the Table 12.1. The
responses given by companies CG and C7 arc related to South LI 1.1.40...11.1l sae., --L..,
only.
All seven companies are following As 3900 / ISO 9000 quality system. Company Cl
has already achieved accreditation to AS 3901. Majority of these are leading
construction companies in Australia with offices in most of the states and even
overseas. The business operation of these companies covered a broad area including,
civil engineering, mining, marine engineering, environmental engineering, and so many
on. Companies Cl, C2, C4 C6 and C7 are experienced with partnering projects.
Responses given to the questionnaire by each company are reported in Section 12.1.
Discussions based on findings from the questionnaire ( phases 1 and 2), and interviews
with project management consultants ( phase 3 ) are given in Sections 12.2 and 12.3
respectively.
12.1.1 Company Cl
Quality system : Construction company C 1 has already got the accreditation to AS
3901. "Quality" training programs are conducted for most of the company staff, from
General Manager, Construction Managers, Project Managers, Design Managers,
Project Engineers to Foremen, Superintendents and secretaries. Two day work shops,
modules ( specifically targeted at elements of quality system i.e. inspection and test
plans, procurements etc, ) and Quality Audits are also being carried out periodically as
required.
Even though company has not quantified the amounts of increase of business, savings
from rework or increases in profit after application of quality system, noted many other
benefits, such as :
Standardization in documentation and practices.
Planning prior to execution of construction activities.
Ability to audit against documented actions / criteria.
Evaluate / target problem areas quicker.
Provide feed back for continuous improvement in systems and processes.
Integrate and coordinate existing systems into one standardized management system
structure.
Project evaluation : Company has around 80 projects running at any time, duration of
6 months to 2 years. No details were given about completed projects in respect to
costs, schedules or procurement systems.
Company found the main reasons for the project cost overruns as "variations" and
"change of durations". Therefore as a policy company attempts to complete projects
early in order to minimize time related costs.
Other than small disputes with some* subcontractors no any major disputes had been
reported during the last three years.
Partnering : Company established it's first partnering relationship in 1991, which was
initiated by a client ( a private company ). Apparently it was not difficult to introduce
partnering initially due to the following contributing factors.
The client wanted partnering.
Partnering fits the style of operating the company.
Partnering enhances trust and the opportunity for repeat business.
179
Overall comments : The quality system is successful. The company intends to approach
to TQM through following practices :
Quality system certification to AS 3901 - achieved.
Quality Improvement Process - progressive formulation of existing systems into the
quality system on a function by function basis.
Development and application of a quality - cost system. This means application of
bench marking and best practice techniques.
Continuous improvement techniques applied on project by project basis as opposed
to quality circles in manufacturing.
Company has also observed some critical factors, that will facilitate to TQM approach.
Commitment from the Managing Director and Senior Management.
To develop a strategy using various Quality Management techniques tailored to the
needs of the company ( ie. avoid off the shelf methods ).
Involvement by all levels.
Control over the process and adequate provision of resources.
Training.
As noted by the company, lack of commitment from top management is the main
obstacle to TQM approach.
180
12.1.2 Company C2
Quality system : The quality system adopted by the construction company C2 is ISO
9000 / AS 3900. Basically "quality" training is provided in two levels:
Foremen and above - Quality Assurance and company procedures.
Below foremen - Quality control and job instructions.
Company has achieved 20% increase of business after the application of quality
system. Savings from reduction of rework and increase in profits are also significant
factors. The other benefits reported by the company are :
Standardized system across all states.
Audit reveals best practices ( as well as deficiencies ).
Company has observed significant benefits in the partnering projects. Not only client
and contractor, but also consultants, subcontractors and suppliers getting benefited
from partnering. It had been roughly estimated that up to 5 % of overall reduction of
cost, schedule and profit gained from partnering projects. Company further iterates
that there are more opportunities available to further improve the present partnering
relationship.
181
It has also noted some disadvantages in partnering projects. One such occasion is that
when partnering relationship rely on all parties putting the contract to one side and
pressing the project goals. Obviously this is never completely possible as commercial
and contractual situations will always present problems for one or more of the parties.
Overall comments : The quality system of the company is successful but it has to be
further improved. Company intends to approach to TQM through fulfilling the
following goals :
First goal is to achieve Quality Assurance accreditation.
Incorporate best practice in management system.
Encourage employees to find waste and inefficiencies and measure them. Help
them and management can find real causes, solutions and subsequently implement
and monitor improvements.
Company identified some critical factors, that will facilitate to such an approach.
Change of overall culture.
Change management's attitudes to empower employees.
Implement, manage and monitor change.
182
12.1.3 Company C3
Quality system : Construction company C3 also follows ISO 9000 / As 3900 quality
system. "Quality" training is in a classroom format with staff instructed on the
procedures generally and within specific reference to how it relates to their work.
Training is provided to all the staff.
After the application of quality system company gained savings from reduction of
rework up to 5 %. But there were no such increases in business, noted after the
application of quality system. Company has not quantified the amounts of profit
increases either. However there are some other obvious benefits.
Better understanding of the job by employees.
Greater project controls.
During the last three years there were no such delays in completing projects. However
company has stated that there were certain disputes occurred during this period, but
no reasons were given for such disputes.
12.1.4 Company C4
Quality system ; Company C4 also follows ISO 9000 / AS 3900 quality system.
"Quality" training is provided in the forms of inductions, courses. Management's
involvement and reviews are considered important, by the company when providing
training to it's staff.
Project evaluation : No details about the completed projects were given by the
company. Last three projects undertaken., completed on time and to budget. As
commented by the company this is attributed to good client relationships, management
practices and approval to Quality Assurance on the job. No major disputes were
reported during last three years.
Company also noted certain disadvantages in partnering projects. Some of them are:
Issue resolution process is not clear.
Lack of trust.
The current partnering relationship is required to be improved.. Team work and
enhanced communication in partnering projects are contributing factors those facilitate
the continuous improvement process.
12.1.5 Company C 5
Quality system : Construction company C5 is following the ISO 9000 / AS 3900 quality
system. "Quality" training is provided to all staff.
Partnering : Company has reported that it started the first partnering relationship in
1910. Company is considering to apply partnering for future projects as well. When
introduced partnering, company faced some difficulties. The reasons for such
difficulties quoted by the company "depends on definition on partnering".
Company also highlighted that "client is always right if he is paying". According to the
experience of company, there are mutual benefits in partnering projects, but no
disadvantages. Partnering provides a better environment for TQM. The contributing
factor for such an environment is quoted as "you are honour bound to perform". It
further states that the current partnering relationship needs improvements.
Company has expressed concern whether it can afford the cost involved with TQM
implementation.
NOTE: Some of the responses given by company are not clear and misleading.
Therefore so called "relationship" cannot be considered as a "partnering"
relationship.
186
12.1.6 Company C 6
Quality System : Company C6 adopts ISO 9000 / AS 3900 series. "Quality" training
causes are conducted for top, middle and lower management and for technical staff, in
different levels.
QM certificate course - QA Manager, QA Coordinator, Operation Manager.
Introduction to QA course ( two days ) - Project Managers, Administrators and
Foremen.
Auditor training course ( two days ) - Foremen.
Subcontract compliance verification course ( one day ) - Foremen.
By following the quality system, company has been able to gain increase in business
and saving,s from reworks. Other benefits noted are :
Able to provide documented verification of compliance with client's requirements.
Improves project planning during initial stages of project.
Reduces rework - makes subcontractors more accountable for the work they do.
Project evaluation
"Client variations" are the main reasons for increase of costs. "Inclement weather" and
"poor performances of trade contractors" caused delays.
Partnering : As described by the company, over the last 7 - 8 years, it's policy had
been to adopt so called "team relationships" with clients. Company outlines the
following factors that have initiated to establish such relationships.
Heavy involvement in construction and project management.
Policy of creating a harmonious relationship and avoiding confrontational
reputations.
To build long term relationship to facilitate repeat business.
Trade contractors - Those who are reputed, progressive and having enough
resources.
Company observed mutual benefits in such relationships, but not been able to
generalize such benefits, because they vary with project to project. It has also noted
the better environment for continuous improvement that created by such relationships.
Overall comments: The quality system adopted by the company is successful. In TQM
approach company is planning to
Implementation of a system.
Provide further training.
Continual improvement.
12.1.7 Company C 7
Quality system : Company has only implemented ISO 9000 / AS 3900 quality system
for approximately four months. The training programs provided for employees include:
Skills training.
Auditor training.
ISO 9000 application training.
Due to the unmature stage, it is too early to assess the long term benefits of the quality
system. However company has already noted the following benefits.
Ongoing improvement of procedures.
Increased understanding of roles and responsibilities.
Project evaluation:
"Major variations" to the contract works are the main the reasons for cost increases.
The third project which adopted construction management contract strategy had shown
positive results in respect of cost savings and schedule because the budget was strictly
controlled.
A dispute has been reported between a subcontractor and company which has lead to
arbitration. According to the company the reason for such dispute is underprice of
project Apparently now subcontractor is keenly pursuing all means to reclaim costs.
not quantified in such benefits in amounts. Company also noted the better environment
created by partnering for TQM. Some of the contributing factors are:
Shared objectives.
Common goals.
Team work.
Overall comments : As mentioned earlier it is too early to evaluate the quality system of
..Ii
Company further contends that when management does not give enough information
and education to employees regarding the reasons and necessity for change, it is not
possible to create an environment for continuous improvement process.
190
Quality systems
All the construction companies surveyed adopt ISO 9000 / As 3900 quality system.
This is a positive indication of the industry, which reflects that the industry has realized
the importance and necessity to complying to a standard quality system. More and
more clients are demanding quality constructed projects, completed to a standard
quality system. Accordingly construction companies are compelled to follow such
systems, to survive and sustain in the business.
"Quality "training is an essential part of any quality system. All the companies provide
suitable training to employees in various levels. However it has been observed that only
few companies evaluate and monitor the progress of training programs. The efficiency
and effectiveness of training programs are depend on the "level of training" i.e.
contents, standard of training, relevance of the training to each individual etc,.
Apparently Quality Audits are also not much in used.
After the application quality systems all the companies surveyed, have achieved
substantial benefits. Company C2 has gained nearly 20% business increases and also
noted increase of profits and reduction of costs from reworks. Company C3 was able to
save approximately 5% from reworks. Company C4 has observed it's increase of
business up to 10%. Company C6 also has noted increase in business and savings from
reduction of rework. Among other benefits noted in a quality system are :
Standardization in documentation and practices.
Opportunities for better planning.
Ability to audit and evaluate.
Provide feedback for continued improvement in systems and processes.
Better understanding of work.
Greater project control.
Better communication and team coordination.
Increased understanding of roles and responsibilities.
Ability to make subcontractors more accountable for their work.
It can be concluded that not only clients of the industry, but also construction
companies can achieve significant benefits through a properly implemented quality
system. Most important of all these is that the quality system provides a feed back for a
continuous improvement process, i.e. TQM.
191
Project evaluation
Available data was not sufficient to perform an analysis of project performances. Most
companies have identified "variations", as the main reasons for cost overruns. In order
to control variations Marsh ( 1988 ) suggested a sequence of events, which is outlined
in Section 4.3.2. As a result of "change of duration" also cost of a project may
increases or decreases. Other factors are:
Clarity of project definition in brief.
Effectiveness of communication.
Plan and Schedule.
Weather conditions.
Management practices.
Relationships among project participants.
Underestimation.
Performance of trade contractors.
Only two cases of disputes with subcontractors have been reported.
Partnering
Out of seven companies surveyed, five companies Cl, C2, C4, C6 and C7 are
experienced with partnering projects. As mentioned earlier the responses given by
company C5 regarding it's partnering is not very clear. Company C5 had
overemphasized one sided "monetary gains" from partnering relationship. This indicates
that the concept of partnering is still new and unknown to some construction
companies.
According to the definition given by partnering Task Force "long term commitment" is
one of the key elements in "true partnering" relationships. None of the relationships
studied are comply with this definition. However companies C 1 and C6 have
highlighted the benefits of "long term commitment" and the opportunity for "repeat
business". Although their relationships are still in urunature stages, there are reasons to
believe that these companies have realized the essence of "true partnering". Other
companies C2, C4 and C7 performed partnering project by project basis, followed by a
tendering procedure. Generally, contractor is selected by client as discussed in Section
9.3. Statement of intent is sent along with the tender documents. Subsequently,
partnering is implemented through a mutual arrangement with the lowest bidder.
reason that the style of operating the company fits with partnering. To say more
precisely the "corporate culture" of the company matches with partnering.
Some common factors that have initiated companies to introduce partnering are
Partnering enhances trust and provide opportunity for repeat business.
Improved customer and associate relationships through communication lines
opened.
Understanding of other parties concerns and objectives.
Increased profits.
Increased workload / turnover.
To build long term relationships.
Dispute resolution ( harmonious relationship which avoid confrontational
situations).
All the companies have highlighted the mutual benefits that can be achieved by
partnering. Companies Cl and C2 have observed reductions in cost and schedule up to
5% for both the company and the partner. Company C2 has also gained profit increase
by 5%. Company C 1 considers the "risk sharing" nature in partnering as another
significant advantage for both parties. Company C4 has achieved 10% reduction of cost
and schedule while profitability has been increased by 10%. The partner of company
C4 has observed 20% reduction of overall cost, 10% increase profitability and 10%
reduction in schedule. Generally speaking partnering helps to improve project
performances.
On the other hand companies C2 and C4 have noted some disadvantages in partnering.
According to the experience of company C2 in a partnering relationship where there is
a considerable imbalance in contract ( i.e. one party is in a more favourable and
advantageous position having significant benefits over the other party ) such
relationship will not work well. In fact partnering should provide a fair and equitable
environment to all project participants. This is implemented through partnering charter.
Company C4 has identified the issues such as "lack of trust" and "unclear issue
resolution process " might create difficulties to the participants. The Australian legal
Group ( 1994 ), Chandler ( 1994 ) and Hibbert ( 1994 ) also expressed concern over
these issues.
All the companies with partnering experience are positive about the culture of
continuous improvement, i.e. TQM environment that created by partnering. According
to company C I, the level of understanding of TQM principles by both parties will
determine the progress towards TQM. Companies C2 and C4 have indicated the
193
contributing factors for TQM as team work, improved open communication, and
atmosphere conducive to improvement. Company C7 also quoted the issues such as
shared objectives, common goals, and team work in partnering facilitate TQM
approach.
Apparently most of the companies used partnering only for short term goals. As
mentioned earlier, only long term relationships provide maximum benefits from
partnering. However in summarizing a", it can be stated that partnering creates and
enhances continuous improvement culture.
Overall comments
Achievement of quality accreditation to a standard quality system ( ISO 9000 / AS
3900) is probably the first most important step towards TQM approach. Company Cl
has already achieved this status and company C2 is on the way to get accreditation. The
method described by Bradely ( 1994 ) reported in Section 2.8 illustrates how to
approach to TQM starting from ISO 9000.
Through employee contribution and participation, getting feed back from them to
minimize waste and inefficiencies is an another strategy suggested by company C2 in
it's TQM journey. Company C5 intends to educate employees, give them opportunities
and encourage continuous improvement at all levels. Company C6 has realized the
importance of implementing a system, further training and continual improvement in
TQM approach. Company C7 also has suggested to provide a system that encourages
input from all the parts of the organization. Further it has already introduced an
enterprise agreement.
However currently not all the companies are prepared to accept TQM. For instance,
company C3 is sceptical about the TQM approach. Company C4 is planning to
introduce TQM gradually within next years. Company C5 also has expressed concern
about the possible cost involvements in such an approach.
194
Change of overall culture of the organization is probably the most difficult and time
consuming issue in TQM approach. This has been observed by companies C2, C6 and
C7.
It was revealed that the following factors contribute to gain most benefits from QM.
Total commitment from top management.
Implementation of a project specific quality plan ( not the generic system ).
Correct attitude and commitment from other project participants.
Ensuring the quality standards.
Better monitored projects ( good monitoring and checking system ).
Communication - information flow among project participants.
Regular induction training at appropriate levels.
Out of five consultants interviewed three expressed their concerns about partnering.
One consultant describes partnering as only a form of contract strategy, which has no
relation with TQM. Other two have not heard much about partnering applications in
Australia. According to them it is difficult to implement in Australia due to the fact that
the concept is still new to the industry and most clients are unaware about it. They also
believe that partnering involves extremely high risk. The reason given was that
partnering cannot be implemented legally.
Other two consultants positively commented about partnering. They further clarified
that the common goals and shared culture observed in partnering create a better
environment for TQM. It was also revealed that the success of partnering depends on
the facilitator and willingness of team players to change their traditional attitudes for a
more corporate culture. Different agendas by different players, personal problems
(personality ), lack of commitment etc. were seen as barriers to partnering.
196
General Conclusions
"Variations" were seen as the main reason for project cost overruns and delays.
"Change of project durations" ( increase the construction period ) alen invarilbly result
cost increases. The subcontracting system create considerable difficulties. This is
evident from the fact that most of the disputes were reported with subcontractors.
Large and medium size construction firms are aiming at getting accreditation to ISO
9000 / AS 3900 quality system. This provides a basis for continuous improvement
process, i.e. Total Quality Management ( TQM ) which is a never ending journey. Due
to the nature and complexity of the industry it is a challenging task to introduce TQM
principles to the construction. Unlike manufacturing, construction offers much more
variability; each project represents a unique design, location, personnel, material,
weather, cost and time. Some of the barriers for TQM implementation that were found
from the study are
Difficulty in changing the organizational culture ( change the attitude of people ).
Lack of commitment from top management.
Lack of commitment and involvement of others.
Lack of trust.
Lack of resources.
Lack of knowledge.
Change management attitude to empower employees.
Negativity among the trade contractors.
Misunderstandings / Misinterpretations of Quality Management principles.
Partnering creates a better environment for TQM. The reason is that long term
commitment provides an opportunity for continuous improvement. It was also observed
that the characteristics of TQM can be found in successful partnering relationships.
Partnering is a new concept to the Australian construction industry. All the partnering
relationships studied were still in unmature stages. Out of five relationships only two
companies had "relatively" long term relationships that incorporated the intention of
doing "repeat business" in future. Other relationships were restricted to project by
project basis and established following tender procedures.
197
Nevertheless partnering projects had already shown promising results. This includes
mutual benefits such as reduction of project costs, schedules, increase profits and so on.
It was also observed that partnering is primarily used for short term goals. ( as a
cooperative non adversarial procurement system ). "True partnering" based on trust,
shared vision and long term commitment will provide maximum benefits. However this
requires a considerable long time, total commitment, and willingness to change attitudes
to a more corporate culture.
Currently there are some difficulties in introducing partnering. This study found
following obstacles for implementation of partnering.
Reluctance of the client to accept partnering.
Lack of knowledge about partnering ( particularly clients, and also contractors,
consultants )
Lack of trust.
Lack of commitment.
Unclear issue resolution process.
Difficulty in changing the attitudes ( cultural change ).
As noted by Hibbert ( 1994 ) the industry need to structure and document project
contracts better not only to accommodate, but more importantly facilitate the partnering
principles and associated procedures. Further success of partnering is depends on the
resolution of these issues.
Partnering concept is now getting popular within the industry. In spite of it's short term
focused limited applications, partnering has shown impressive results. However there is
a tremendous potential for much broader application. As observed by Construction
Industry Institute of US two factors stimulate such applications.
Existing relationships must continue to be successful and show measurable benefits.
A method of measuring the benefits of the broader application must be developed.
REFERENCES
Bagnall, Brian ( 1992 ), The AQUA Group - Tenders and Contracts for Building,
Oxford Blackwell Scientific Publications, UK, 1992, pp 33 - 35.
Barrell, Trevor and Nixon, Trevor et al. ( 1988 ), Strategies for the Reduction of
Claims and Disputes in the Construction Industry, A research report by some
Australian experts, November 1988, pp 15 - 28, 37 - 39, 47 - 53.
Bradely, Michael ( 1994 ), "Starting Total Quality Management from ISO 9000", The
TQM Magazine, Vol. 6, No. 1, 1994, pp 50 - 54.
Brocka, Bruce and Brocka, Suzane ( 1992 ), Quality Management - Implementing the
best ideas of the masters, Richard D. Irwin Inc., USA, 1992, pp 3, 4, 23 - 45, 61 - 97.
Brown, C. D. and Beaton, H. R.( 1990) "Looking Back at Design, Looking Forward
to Construction" Journal of Management in Engineering, Vol. 6, No. 3, July 1990, pp
342 - 349.
Brown, C. D. and Beaton H. R.( 1990), "Looking back at design, looking forward to
construction", Journal of Management in Engineering, Vol. 6, No. 3, July 1990, pp
125 - 137.
Chappell David and Powell Vincent ( 1993 ), The JCT Design and Build Contract,
Smith Blackwell Scientific Publications, UK, 1993, pp 4 - 5.
pp 433 - 443.
Cook, Lynn E. and Hancher, Don E. ( 1990 ), "Partnering : Contracting for the future"
, Journal of Management in Engineering, Vol. 6, No. 4, October 1990, pp 431 - 447.
Dale, Barrie and Cooper, Larry ( 1992 ), Total Quality and Human Resources - An
Executive Guide, Blackwell Publishers, UK, 1992, pp 2 - 21, 174 - 195, 180 - 181.
Duncan, John M., Thorpe, Brian and Sumner, Peter ( 1990 ), Quality Assurance in
Construction, Gower Publishing Company Ltd, UK, 1990.
Fenwick, J. M.( 1990), "Quality Assurance - Benefits and Problems", Paper presented
at seminar on Quality Assurance, Concrete Institute of Australia on 15th March.
Fox, Michael J. ( 1993 ), Quality Assurance Management, Chapman and Hall, UK,
1993, pp 4 - 17, 108 - 109, 222 - 226, 265 - 273.
Fox, Michael J. ( 1993 ),Quality Assurance Management, Chapman and Hall, UK,
1993, pp 4 - 17, 108 - 109, 114 - 115, 222 - 226, 265 - 273.
Gitlow, Howard S. and Gitlow Shelly J., The Deming guide to quality and competitive
position, Pretence Hall Inc., USA, 1987, pp 19, 142 - 144.
Graves, Ray ( 1993 ), "Total Quality - Does it work in engineering Management ?",
Journal of Management in Engineering, Vol. 9, No. 4, October 1993, pp 444 - 455.
Harback, Herbet F., Basham, Donald L., Buhts, Robert E. ( 1994 )," Partnering
Paradigm", Journal of Management in Engineering, Vol. 10, No. 1, May / June 1994,
pp 23 - 27.
Higgin, Gurth and Jessop, Neil ( 1966 ), Interdependence and Uncertainty - A Study of
the Building Industry, Digest of a report from the Tavistock Institute, Tavistock
Publications, UK, 1966.
Higgin, Gurth and Jessop, Neil ( 1965 ), Communication in the Building Industry, A
report from the Tavistock Institute, Tavistock Publications, UK, 1965.
Juran, J. M. and Gryna, Frank M. ( 1988 ), Juran's Quality control Handbook, Fourth
Edition, Mc Graw Hill Inc, USA, 1988, pp 9-2, 9-4, 9-20 and 9-21.
Kanji, Gopal K. and Mike, Asher ( 1993 ), Total Quality Management Process -
systematic approach, Carfex Publishing Company, UK, 1993, pp 1 - 8, 10, 60 - 75.
Levin, Richard I. ( 1981 ), Statistics for Management, Prentice - Hall Inc., USA, 1981,
pp 307, 308
Lu, Edmund and Sohal Amrik .( 1993 ) , "Success factors, weaknesses and myths
concerning TQM implementation in Australia", Journal of Total Quality Management,
Vol. 4, No. 3, 1993, pp 245 - 255.
204
Macdonald, John and Piggot, John ( 1993 ), Global Quality - The new management
culture, Pfeiffer and Company, USA, 1993, pp 8, 84 - 85, 131, 136 - 139.
Malcolm, Taylor and Hosker Harry H. ( 1992 ), Quality Assurance for Building
Design, Longman Scientific and Technical, UK, 1992.
MBA ( 1994 ), South Australian Builder, Master Builder's Association of SA, April
1994.
MBA ( 1992 ), Partnering - A strategy for excellence - An Introductory Guide for the
Building and Construction Industry, Master Builder's Association, October 1992.
Mathur, Krishan and McGeorge, Denny, ( 1990 / 1991 ) "Towards the Achievement of
Total Quality in Building Process", Australian Institute of Building Papers No 4, 1990 / )1
1991, p 4.
Milne, Chris ( 1994 ), " Partnering in action, Nepean Hospital Upgrade", Australian
Project manager, 1994, pp 18 - 19.
205
Mohyla Lolita V. ( 1992 ), Alternative forms of building contract, and implications for
the practice of architecture and influences upon the Australian Building Industry,
Master of Architecture thesis, Dept. of Architecture, Adelaide University, December
1992, pp 64, 194 - 231.
NIES ( 1990 ), A TQM 'How to" approach, Department of Industry Technology and
Commerce.
NPWC / NBCC joint working party report ( 1990 ), No Dispute - Strategies for
Improvement in the Australian Building and Construction Industry, May 1990, pp
176, 188 - 198.
Poirot, James W. ( 1990 ), "Defining Quality, Responsibility and Liability", The Quest
for Quality, American Society of Civil Engineers Publication, 1990, pp 11, 12.
Ramus, J.W. ( 1993 ), Contract Practice for Quantity Surveyors, UK, 1993, pp 2 - 3,
27 - 41.
Riggenbach, Judy A. ( 1986 ), "Silent Negotiations : Listen with your Eyes" , Journal
of Management in Engineering, Vol 2, No 2, April 1986, pp 91 - 99.
Schmidt, H. Warren and Finningen, P. Jerome ( 1992 ), The Race Without Finish,
Jossey Bass Publishers, USA, 1992, p 5, 16, 17, 26, 27.
Spenley, Paul ( 1992 ), World Class Performance through Total Quality, Chapman
and Hall, UK, 1992, pp 8- 10.
206
Stebbing Lionel ( 1993 ), " Quality Assurance - The rote to efficiency and
competitiveness, Ellis Horwood Ltd., UK, 1993, pp 23, 33 - 36.
Strage, Peter S. and Vaughan Gareth D. ( 1993 ), "TQM : A view from the playing
field", Journal of Management in Engineering, Vol. 9, No. 4, October 1993, pp 390 -
398.
Teys, Peter (1989 ), "Selection of the Team", The Australian Project Manager, May
1989.
The Australian legal Group ( 1993 ), "Construction Headlines", A news sheet from the
Australian legal Group, Construction No. 6, April 1993.
The Australian Project Manager ( 1992 ), "Project management skills played a major
role in the success of the MCG Stand Project", 1992 February / March, pp 12 - 13.
The Australian Project Manager ( 1994 ), Article on "Partnering for public works
NSW", p27
The Chartered Institute of Building, Quality Assurance of the Building Process, UK, p
2 - 3, 13 - 26.
The Royal Commission Report into productivity in the Building Industry in NSW
(1992), Contracts, Claims and Disputes : towards implementation of existing reform
proposals, Research and Policy Division.
Turner Dennis F. ( 1989 ), Design and Build Contract Practice, Longman Scientific
and Technical, 'UK, 1989.
Wallace, Laurie and Vallence, Kevin ( 1993 ), Quality Concepts, Thomas Nelson,
Australia, 1993, pp 37, 40, 49, 41,
Wilkinson, Adrian and Redman, Tom and Snape, Ed ( 1989 ) "What is happening in
Quality Management ?", Findings from an IM Survey, Institute of Management, UK,
"The TQM Magazine", Vol. 6, No. 1, 1989, pp 55 - 58.
APPENDIX 1: Questionnaire
Yes [ ] No[ ]
* If " yes " to what level / type of staff. ? Please describe briefly particulars of the
training program.
Are there any substantial benefits to the company in following areas after the
application of quality system.?
Please state the main reasons for increase / decrease of the total cost of project at
completion :
Please state the main reasons for delaying in completion / early completion :
3
11. Were there any claims or disputes which have lead to an arbitration (or litigation)
PART D: Partnering
Do you intend to adopt the concept of "partnering" for your future projects.?
Does the company face any difficulties in introducing partnering concept for the
projects.?
* If" yes "please describe briefly the reasons for such difficulties :
Yes [ ] No[ ]
Please state three main factors that have initiated your company to introduce
partnering concept. ?
(a)
(b)
(c)
Are there any significant mutual benefits ( such as reduction of costs, increase the
profitability or reduction of schedules ) in the partnering projects. ?
* If "yes" please estimate the average percentages of such benefits for the company and
Are there any disadvantages when applying partnering concept to the projects. ?
Successful
Unsuccessful [
To be improved
6
Successful [ ]
Unsuccessful [ ]
To be improved [ 1
Please describe briefly the way how the company intend to approach to Total
Quality Management.?
What are the critical factors that will facilitate to such an approach. ?
What are the critical factors that will obstruct to such an approach. ?
APPENDIX 2: Statistical Process Control ( SPC )
All processes can be monitored and brought "under control" by gathering and using
data. This refers to measurement of the performance of the process and the feed back
required for corrective action, where necessary. Statistical Process Control ( SPC )
methods, backed by management commitment and good organization, provide
objective means of controlling quality in any transformation process.
SPC is not only a tool kit. It is a strategy for reducing variability, the cause of most
quality problems : variation in products, in times of deliveries, in ways of doing things,
in materials, in peoples attitudes, in equipment and its use, in maintenance practices, in
everything. Control by it self is not sufficient. TQM requires that the process should be
improved continually by reducing its variability. This is brought about by studying all
aspects of the process using the basic question. "Could we do this job more consistently
and on target ?". The answering of which drives the search for improvements. This
significant features of SPC means that it is not constrained to measuring conformance,
and that it is intended to lead to action on processes which are operating within the
"specification" to minimize variability.
In addition to the basic elements of quality system, which will provide a frame work for
recording, there exists a set of tools which Ishikawa has called the sewn basic tools.
These tools provide answers for the following questions.
Process flow charting - What is done ?
Check sheets I Tally charts - How often is done ?
Histograms - What overall variations look like ?
Pareto analysis - Which are the big problems ?
Cause and effect analysis and Brain storming - What causes the problem ?
Scatter diagrams - What are the relationships between factors ?
Control charts - Which variations to control and how ?
( Oakland -1989 )
APPENDIX 3 : T - Distribution
When the normal distribution is not the appropriate sample distribution; "t-distribution"
is used. The t-distribution is also called by "student's t distribution" and, or simply
"students distribution". Since it is used when the sample size is 30 or less, statisticians
often associate the t-distribution with small sample statistics. The second condition is
that the population standard deviation must be unknown. Therefore, use of t-
distribution for estimating is required whenever the sample size is 30 or less and the
population standard deviation is not known. Furthermore, in using the t-distribution, it
is assumed that the population is normal or approximately normal.
Normal distribution
t distribution for
sample size n = 15 t distribution for
sample size n = 2
The above figure compares one normal distribution with two t-distributions of different
sample sizes. This figure shows two characteristics of t-distributions.
T-distribution is lower at the mean and high at the tails than a normal distribution.
T-distribution proportionally more area in its tails than the normal distribution.