Construction of Tower and Pipeline for Irrigation

(Horizontal Construction)

September October
Activities
9 10 11 12 13 14 16 17 18 19 20 21 23 24 25 26 27 28 30 1 2 3 4 5 7 8 9 10 11 12 14 15
1. Reconnaissance
2. Surveying Works
3. Planning and Designing of Pipeline /Pontoon Tower
4.Prefabrication of Materials
5. Assembly of the Base of Terrain
6. Excavation Works
7. Fabrication of Forms for Slabs
8. Installation of Forms
9. Installation of Reinforcing Bars
10. Pouring of Concrete on Slabs
11. Fabrication of Forms for RCP Installation
12. Installation of Forms For RCP Installation
13. Installation of Reinforcing Bars for Bottom Bars
14. Laying out of the RCP
15. Collar Works of Joints
16.Fabrication of Forms for Top bars
17. Installation of Rebars for Top Bars
18. Concrete Pouring for Top
19. Curing
20. Fabrication of Forms for Pontoon Tower
21. Installation of forms for Pontoon Tower
22. Installation of Rebars for Pontoon Tower
23. Concrete Pouring Base
24.Concrete Pouring for Pontoon Tower
25. Curing
26. Removal of Forms
27. Turnover
28. Presentation Preparation
29. Project Presentation Copy Deadline
30.Scaled Model Deadline

Submitted by:

BEN DANIEL N. GAMUTAN


Project Manager
Tower and Pipeline for Irrigation
izontal Construction)

October November December


16 17 18 19 21 22 23 24 25 26 28 29 30 31 1 2 4 5 6 7 8 9 11 12 13 14 15 16 18 19 20 21 22 23 25 26 27 28 29 30 2 3 4 5 6

Legend
Actual Construction Works
Scaled Model Works
Deadlines

Approved:

ENGR. RAMIL VINCULADO JR.


General Manager