Beruflich Dokumente
Kultur Dokumente
IC / Business: Date:
1
2016 version1.0
Project Profile
Owner/Client Owner/Client
Location Owner/Client
Nature of Contract
Project Valve
(LSTK, Item rate etc)
2
2016 version1.0
Project Profile Continued…
Performance BG FEED
3
2016 version1.0
Client Profile
4
2016 version1.0
Consortium / JV Details, if any
5
2016 version1.0
Scope of Work
Detailed Scope of Work (Including work split with consortium partner, if any and
breakup for Engineering, Procurement, Construction / Fabrication, Installation,
Commissioning etc. )
6
2016 version1.0
Project Site Profile
7
2016 version1.0
Major Project Milestones (sample)
0 33 36 45 48 60 108
12 Months
LDP*
Completion
Certificate after
PGTR
48
Months
DLP
33 Months 3 months
12 Months
Reinforcement
64 103 66 108
kg/sqm
Commercial Comparison
9
2016 version1.0
Client Obligation (Sample)
• Approval of drawings
• Free issue materials
• Work front availability / Shutdown
• Utilities provided by client
• Clearances (Safety, gate entry pass, permit to work etc.)
• Milestones certification – Client / PMC
• Invoice certification – procedure / timeline
• Contractual protection for non-fulfilment of client obligation resulting in
schedule delay, cost escalation, overstay cost etc.
• Any other
10
2016 version1.0
Commercial Details
Performance LD FEED
11
2016 version1.0
Commercial Details Continued…
Limitation of liability
Owner/Client
(value & timeline)
Intellectual property
Type of Contract/ PMC
rights
12
2016 version1.0
Legal aspects : Check list for Pre-bid review
Particulars Applicability (Yes / No) Remarks
General :
Have the tender conditions been checked up with the legal department ?
Qualification Criteria :
Are there any ambiguities in the wordings of the qualification criteria that
need to be clarified with the Client ?
Change Order :
Liabilities :
Is there a cap on the overall contractual liability & is there any adverse
conditionality for determination and fixation of the overall liability ? What is
the trigger point of the contractual liabilities?
Is there any clause in the BG which makes its tenure open-ended & the
liability under the BG detrimental to L&T’s interests ?
Extent of L&T’s share in the liability when the liability event is triggered by
other members (JV/UJV) ?
13
2016 version1.0
Legal aspects : Check list for Pre-bid review (Continued…)
Particulars Applicability (Yes / No) Remarks
Time extension :
If yes, Whether the contract also allows compensation for indirect cost like
extended stay?
Indemnities :
Force Majeure :
Does the definition include all events related to weather & other natural
calamities, acts of government, strikes, riots, political unrest and other similar
events specific to the project site ?
Is there a clear Arbitration clause and the applicable law specified in the tender
documents ?
Change in Law: Is there a pass through for change in law under the contract?
14
2016 version1.0
Tax Checklist
Applicability
Particulars Remarks
(Yes / No)
15
2016 version1.0
Environment, Health & Safety
Additional details:
16
2016 version1.0
Insurance
Client Contractor
Coverage
(Yes / No) (Yes / No)
All Risk Marine Cargo
CAR / EAR
Comprehensive General Liability
Workmen’s Compensation & Employer’s Liability
Automotive Third Party Liability
Construction Plant & Equipment
Pollution & Environmental Liability coverage
Loss of anticipated revenue / Consequential
damages
Decennial liability / Latent defect / Perpetual
warranty cover
17
2016 version1.0
Major Subcontractors/Vendors
18
2016 version1.0
Manpower Resources Required (Sample)
600
500
No. of workmen
400
300
200
100
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14
Months
Total Man-months required
VISA Requirement
Localisation requirements
19
2016 version1.0
Project Team
Project coordinator
Contracts Manager
Head of Finance
Cost Engineer
Head of Safety
Construction Manager
20
2016 version1.0
Project Cost Breakup (Sample)
Percentage (%)
5 10
5
Engineering
Supply
Project Management
30
Construction
40 Commissioning
Others
10
21
2016 version1.0
Projected Cash Flow
100.00%
Pre-bid Cash flow
80.00%
60.00%
40.00%
20.00%
0.00%
-20.00%
Month 1 2 3 4 5 6 7 8 9
Inflow
Outflow
Net
Please exclude the capex while plotting the projected cash flow graph, also mention the capex required for the project
22
2016 version1.0
Forex Exposure – Currency Risk (Sample)
Amount in Mn
Receivable Payables Net receivable
Currency
(A) (B) (C=A-B)
USD
EUR
JPY
INR
GBP
…..
…….
23
2016 version1.0
Commodity Exposure (Sample)
Aluminum
Nickel
Others
(Pls. specify)
24
2016 version1.0
Monte Carlo Simulation
• VaR
• Contingency
25
2016 version1.0
Learning from Similar Past Projects
Project 1
Project 2
Project 3
….
….
26
2016 version1.0
Risk Assessment Profile
27
2016 version1.0
Risk Matrix (5X5)
Probability (P)
(0to1) 1,6
A -Most Likely
More than 0.75
B -Likely 2,7
0.5 to 0.75
C –Occasional 3,4
0..25 to 0.5
8,9,10
D –Unlikely 5,11
0.10 to 0.25
E –Remote
Less than 0.10
Severity(S) V Insignificant IV Minor III Significant II Major I Catastrophic
(As %age of Less than 0.25 0.25 to 0.5 0.5 to 1 1 to 2 More than 2
Contract Value )
28
2016 version1.0
Risks - Assessment & Mitigation
1 Local unrest
Economical
Social
3 Omanisation challenges
Environmental
Execution challenges while
4
working in extreme temperature
5 Weather standby
29
2016 version1.0
Risks - Assessment & Mitigation
10 Forex variation
30
2016 version1.0
Competitors Analysis
Level of
Competitor Technical ability Financial health
Competitiveness
31
2016 version1.0
Bidding Rationale
Core Business
Strategic Fit
Competitive Strength
Availability of Team /
Manpower
Risk Management
Attractiveness of
Returns
Rating
Excellent
Good
32
2016 version1.0
33
2016 version1.0