MANPOWER SCHEDULE
REQUIREMENTS EFFICIENCY
LAY OUT & EXCAVATION
3 HELPERS 1man (hr)/m3
REBAR FABRICATION & INSTALLATION
3 STEELFIXERS 1man 10/kg
FORM WORKS INSTALLATION
2 CARPENTERS 2 man hr/m2
POURING OF CONCRETE
3 MASONS AND HELPERS 1man day/0.25m3
CHB INSTALLATION
3 MASONS AND HELPERS 1 man day/60pcs
TRUSSES FABRICATION AND INSTALLATION
2 CARPENTER/ HELPERS 4.88m2/man day
2 ROOF INSTALLER/HELPER
WALL PLASTERING
3 MASONS 8 m2/day
ELECTRICAL/PLUMBING/ROUGHING INSTALLATION
1 ELECTRICAL/HELPER
TILES INSTALLATION
2 TILE SETTERS 4m2/day
DOOR & WINDOW INSTALLATION
2 CARPENTERS
DOOR KNOBS,FAUCETS/SWITCHES/LIGHTINGS
1 ELECTRICIAN/PLUMBER
PAINTINGS
2 PAINTERS
1 HELPERS
CLEANING AND TURN OVER
UNIT
PCS
length
length
length
length
length
bags
cubic meter
cubic meter
set
length
length
length
pcs
set
pcs
pcs
pcs
set
pcs
cartoon
cartoon
sets
pcs
pcs
pcs
pcs
pcs
pcs
pcs
sets
PHP 446,400.00
PHP 273,600.00
PHP 720,000.00
6
6
10
10
6
2
720,000.00
446,400.00
273,600.00
720,000.00