Beruflich Dokumente
Kultur Dokumente
EMBANKMENT CONSTRUCTION
Embankment construction, Type 1 2,328.00
Embankment construction, Type 2 2,279.50
Embankment construction using rock fill 4,151.60
Trimming, Levelling and compaction of original
82.45
ground to standard density
Geotextile 1,018.50
Preliminaries
CULVERTS Rate
Aggregate backfill 4,462.00
Filter medium 4,656.00
Impervious layer 363.75
Weep hole, PVC pipe (Type600)-75mm diameter 873.00
Granular aggregate bedding 4,656.00
Concrete for encasement of pipes (Grade20) 19,720.10
Laying & Jointing concrete pipes 900mm diameter ((Single Row)
13,647.90
Laying & Jointing concrete pipes 900mm diameter(Double Rows)
26,966.00
Laying & Jointing concrete pipes 1200mm diameter ((Single Row)
26,432.50
Concrete: Grade C 15 16,490.00
Concrete: Grade C25 19,545.50
Concrete: Grade C30 23,037.50
Tor steel reinforcement (460N/mm2) 218,250.00
Random rubble masonry 10,864.00
Plastering, 1:3 cement sand mix, 16mm thick 1,086.40
Formwork smooth finish 1,964.25
Formwork rough finish 1,867.25
25mm Steel dowels at 500mm c/c 873.00
STRUCTURES -
Aggregate backfill 4,151.60
Filter medium 4,355.30
Impervious layer 358.90
Weep hole, PVC pipe (Type600)-75mm diameter 824.50
Gabion wall construction
Concrete: Grade C 15 16,490.00
Concrete: Grade C 25 19,545.50
Tor steel reinforcement 218,250.00
Random rubble masonry 10,864.00
Plastering,1:3cement sand mix,16mm thick 1,154.30
Formwork smooth finish 1,940.00
Formwork rough finish 1,843.00
Incidental Works
MAINTENANCE OF CARRIAGEWAY
Filling pot holes and patch repairs with Asphalt
1,241.60
concrete cold mix (MC30), 20mm and less in depth
Filling pot holes and patch repairs with Asphalt
1,251.30
concrete cold mix (MC30) 75mm and less in depth
Filling pot holes and patch repairs with Asphalt
2,609.30
concrete cold mix (MC30) deeper than 75mm
Provisonal Sum
Provisions and maintenance of temporary by pass
2,000,000.00
roads for culverts, bridges and other structures, if any
Provide adequate environmental protection and
precautions during construction and implement the 3,000,000.00
Environment Management Plan,
Provide Standards and Documents 650,000.00
Repairs to damages of existing servises 800,000.00
Demolition/Rebuilding of property 2,000,000.00
Diversion,protection or removal of electrical servises 15,000,000.00
Diversion,protection or removal of water servises 5,000,000.00
Diversion,protection or removal of telecommunication
5,000,000.00
servises
Provide & maintain Survey equipment 5,000,000.00
Special testes ordered by the Engineer 500,000.00
Grade adjustment of existing manholes 1,000,000.00
Bus Bays/Parking Bays 2,000,000.00
Chemical Blasting 1,000,000.00