Beruflich Dokumente
Kultur Dokumente
Err:509
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino
A. Name and Capacity of Equipment (Operated) No. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
One Bagger Mixer 1.00 36.50 ₱ 190.00 ₱ 6,935.00
Water Truck 1.00 36.50 1,065.00 38,872.50
Backhoe (Wheel Type 0.28 cu.m.) 1.00 36.50 840.00 30,660.00
B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Construction Foreman 1.00 36.50 ₱ 67.72 ₱ 2,471.78
Skilled Laborer 3.00 36.50 56.64 6,202.08
Laborer 6.00 36.50 37.94 8,308.86
C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
Portland Cement 5.50 3,743.25 bags ₱ 240.00 ₱ 898,378.80
Sand 0.30 204.18 cu.m. 579.52 118,324.66
Gravel Fill 0.02 13.61 cu.m. 603.64 8,216.63
Weep Holes 0.30 204.18 ln.m. 100.00 20,417.70
Filter Cloth 0.02 10.21 sq.m. 160.00 1,633.42
Boulders 1.05 714.62 cu.m. 793.71 567,200.64
SUMMARY :
A. Equipment ₱ 76,467.50
B. Labor ₱ 16,982.72
C. Materials ₱ 1,614,171.84
D. TOTAL DIRECT COST ₱ 1,707,622.06
DIRECT UNIT COST ₱ 2,509.03
E. OCM 9.00 ₱ 153,685.99
F. Profit 8.00 ₱ 136,609.76
G. VAT 5% of (D+E+F) ₱ 99,895.89
H. Total Cost (D+E+F+G) ₱ 2,097,813.71
I. Unit Cost H/Quantity ₱ 3,082.35
ITEM NO. DESCRIPTION QUANTITY UNIT
A. EARTHWORKS
done (a) Wall Footing Volume: 0.4 x 0.20 x 24.7 = 1.976 cu.m.
done (b) Slab on Fill(stage) Volume: 5.5 x 9.9 x 0.1 = 5.445 cu.m.
(b) Slab on Fill(rm01) Volume: 2.9 x 2.9 x 0.1 = 0.841 cu.m.
(b) Slab on Fill(rm02) Volume: 2.9 x 2.9 x 0.1 = 0.841 cu.m.
done (c) Beam Volume: 0.25 x 0.30 x 30.85 = 2.314 cu.m.
done (d) Column Volume: 0.25 x 0.30 x 5 = 0.38 cu.m. x 9.00 =
done (d) SC Volume: 0.15 x 0.40 x 3.4 = 0.204 cu.m. x 4.00 =
0.4 x 0.50 x 0.25 = 0.05 cu.m. x 9.00 =
done (d) Footing Volume: 1 x 1.00 x 0.25 = 0.25 cu.m. x 9.00 =
done (e ) Footing Tie Beam Volume: 0.2 x 0.30 x 39.45 = 2.37 cu.m.
done (e ) Corbel Volume: 0.25 x 0.30 x 0.3 = 0.02 x 2 =
done (e ) Stairs Volume: 1 x 1.70 x 0.15 = 0.26 x 4 =
0.2 x 0.15 x 2 = x 1 x
0.1 x 0.30 x 1 = 0.03 x 4 =
(e ) Stairs Volume: 0.1 x 1.00 x 1.5 = 0.15 x 2 =
148.2
= 24.7 pcs say
6
= 514.32 kgs.
2,418.28 kgs.
done (e) Column Footing Spacing: 6-16mm dia. Equally spaced both ways
384
= 76.8 pcs say
5
h
Form Lumber 2" x 2" 1.20 x 5 x 32 = 192.00 sq.m. Size of
Column
192.00 / 2.88 = 67.00 pcs. of plywood Wood
67 x 29.67 = 1,987.89 bd.ft. Frame
2" x 2"
2" x 3"
1.20 x 30.85 = 37.02 sq.m.
Beam
37 / 2.88 = 13 pcs. of plywood
13.00 x 11.70 = 122 bd.ft.
1.20 x 39.45 = 47.34 sq.m.
Tie Beam
47 / 2.88 = 17 pcs. of plywood
17.00 x 29.67 = 504 bd.ft.
Column
Scaffoldings 2" x 3" 5.00 x 32 = 160 m
Length
Vert. 160 x 7.00 = 1,120.00 bd.ft. Lumber Column
Hor. 160 x 31.67 = 5,067 bd.ft. Board Ft. per M. H
Size
8,987 bd.ft. Vert.
Brace 160 x 17.50 = 2,800 bd.ft. 2" x 2" 4.70
2" x 3" 7.00
Beam
31 = 31 2" x 4" 9.35
Length
Vert. 31 x 6.00 = 185 bd.ft.
Hor. 31 x 7.00 = 216 bd.ft.
401 bd.ft.
Tie Beam
39 = 39
Length
RSB
Length 0.5 x 6 = 3
0.5 x 3 x 4 = 6
0.5 x 8 = 4
13 x 1.1 = 14.3
CB1 14.3 x 1 = 14.3
CB2 14.3 x 8 = 114.4
CB3 14.3 x 4 = 57.2
CB4 14.3 x 1 = 14.3
200.2 x 0.6167 = 123.462266508 kgs.
1008
Aluminum
(1) a Glass Windows (Sliding Type) sq.m.
Name Description Quantity w x h Area
W1 Analok Sliding Type 3 = 3 x 1.2 = 10.8 Summary
Sliding
W2 Analok Sliding Type 3 2.5 x 1.2 = 41.4 sq.m.
= 9 Type
Awning
W3 Analok Sliding Type 9 2 x 1.2 = 3.05 sq.m.
= 21.6 Type
W4 Analok Awning Type 2 = 0.8 x 0.5 = 0.8
W5 Analok Awning Type 1 = 2 x 0.5 = 1
W6 Analok Awning Type 1 = 2.5 x 0.5 = 1.25
Total 19 44.45
1008
Aluminum
(1) c Glass Windows (Awning Type)
I. ROOFING WORKS
L: 6.71
width 18.40
min.width of panel 1.01
Area: 123.464 say
123.46 sq.m
Area: 58.8
Area: 182.26 sq.m
J. FINISHING WORKS
additional 10%
586.00 x 1.1 = 644.60 sq.m
waste Factor
K. PAINTING WORKS
1032 (1) a1 Painting Works (Masonry, Concrete) sq.m.
Total 644.60
Flat Latex
Paint
1st Coating 22 gals
2nd Coating 19 gals
Total 41 gals
Gloss Latex
Paint
1st Coating 19 gals
2nd Coating 26 gals
Total 45 gals
L. MASONRY WORKS
1046 (2) a Masonry Works (100mm thick CHB)
Area:
CHB
= - sq.m.
done = - sq.m.
= - sq.m.
Total Area = 127.22 sq.m.
127.22 sq.m. x 12.5 =
Reinforcing Steel Bars
By Area Method
Vertical Reinforcement Spacing: 0.60m ; 10mm dia.
CHB
= - sq.m.
= - sq.m.
= - sq.m.
Total Area = 272.00 sq.m.
272.00 sq.m. x 12.5 =
Reinforcing Steel Bars
By Area Method
Vertical Reinforcement Spacing: 0.60m ; 10mm dia.
M. METAL STRUCTURES
Total Waste
Canal Lining
Length Factor
No. of Longitudinal ÷
7 x 72.5 = 507.5 x 1.1 = 558.25 6
RSB
Spacing 0.30 m
No. of Transverse ÷
72.5 0.3 = 241.66666667 plus 1 pc. 301 x 2 = 602 m
RSB
0.05 cu.m.
1.02 cu.m.
20.00 =
0.12 cu.m.
0.30 cu.m.
7 pcs
25 pcs
32
500 pcs
123 pcs
m
= 200.53
77 pcs
164 pcs
@ 2
pcs. say
x 5.32824167
3.375 cu.m.
42.25 23.35
0.94
7.53
3.73
0.95
13.15
= 0.1792
pcs
pcs
1590.25 say
adopted
adopted
3400.00 say
adopted
adopted
= 93.0416667
602 ÷
101 x
1.20 cu.m.
CABUA-AN
pcs
= 326.6
55
= 293.053292
3400 pcs
102
3,502.00 pcs
pcs. say 94
A. Name and Capacity of Equipment (OperateNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
A. SUB-TOTAL, EQUIPMENT ₱ -
B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Laborer 2.00 16.00 P 45.25 P 1,448.00 32.00
C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
C. SUB-TOTAL, MATERIAL ₱ -
SUMMARY :
A. Equipment ₱ -
B. Labor ₱ 1,448.00
C. Materials ₱ -
D. TOTAL DIRECT COST ₱ 1,448.00
DIRECT UNIT COST ₱ 1,448.00
E. OCM 12% of D ₱ 130.32
F. Profit 8% of D ₱ 115.84
G. VAT 5% of (D+E+F) ₱ 84.71
H. Total Cost (D+E+F+G) ₱ 1,778.87
I. Unit Cost H/Quantity ₱ 1,778.87
to be demolished:
x 0.2 x 4 = 0.16
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino
A. Name and Capacity of Equipment (OperateNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
A. SUB-TOTAL, EQUIPMENT ₱ -
B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Laborer 4.00 81.50 45.25 14,751.50
C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
Factor
C. SUB-TOTAL, MATERIAL ₱ -
SUMMARY :
A. Equipment ₱ -
B. Labor ₱ 14,751.50
C. Materials ₱ -
D. TOTAL DIRECT COST ₱ 14,751.50
DIRECT UNIT COST ₱ 181.33
E. OCM 12% of D ₱ 1,770.18
F. Profit 8% of D ₱ 1,180.12
G. VAT 5% of (D+E+F) ₱ 885.09
H. Total Cost (D+E+F+G) ₱ 18,586.89
I. Unit Cost H/Quantity ₱ 228.48
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino
A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
A. SUB-TOTAL, EQUIPMENT ₱ -
B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Foreman 4.00 46.50 ₱ 81.30 ₱ 15,121.80
Laborer 4.00 46.50 ₱ 45.25 ₱ 8,416.50
C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
Selected Borrow
(w/ 15% shrinkage factor 1.15 166.70 cu.m. 213.00 35,507.95
SUMMARY :
A. Equipment ₱ -
B. Labor ₱ 23,538.30
C. Materials ₱ 35,507.95
D. TOTAL DIRECT COST ₱ 59,046.25
DIRECT UNIT COST ₱ 407.33
E. OCM 12% of D ₱ 7,085.55
F. Profit 8% of D ₱ 4,723.70
G. VAT 5% of (D+E+F) ₱ 3,542.78
H. Total Cost (D+E+F+G) ₱ 74,398.28
I. Unit Cost H/Quantity ₱ 513.23
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino
A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
A. SUB-TOTAL, EQUIPMENT ₱ -
B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Laborer 4.00 13.50 ₱ 45.25 ₱ 2,443.50
C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
Factor
Coarse Aggregates 1.150 36.23 cu.m. ₱ 603.64 ₱ 21,866.86
SUMMARY :
A. Equipment ₱ -
B. Labor ₱ 2,443.50
C. Materials ₱ 21,866.86
D. TOTAL DIRECT COST ₱ 24,310.36
DIRECT UNIT COST ₱ 771.76
E. OCM 12% of D ₱ 2,917.24
F. Profit 8% of D ₱ 1,944.83
G. VAT 5% of (D+E+F) ₱ 1,458.62
H. Total Cost (D+E+F+G) ₱ 30,631.05
I. Unit Cost H/Quantity ₱ 972.41
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino
A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
One Bagger Mixer 1.00 6.75 ₱ 172.00 ₱ 1,161.00
A. SUB-TOTAL, EQUIPMENT ₱
B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
B. SUB-TOTAL, LABOR ₱
C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
Factor
Stairs
Portland Cement 9.500 32.00 bags ₱ 260.00 ₱ 8,320.00
Fine Aggregates 0.450 2.00 cu.m. 579.52 1,159.04
Crushed Aggregates 0.900 4.00 cu.m. 820.40 3,281.60
C. SUB-TOTAL, MATERIAL ₱
SUMMARY :
A. Equipment ₱
B. Labor ₱
C. Materials ₱
D. TOTAL DIRECT COST ₱ -
DIRECT UNIT COST ₱ -
E. OCM 12% of D ₱ -
F. Profit 8% of D ₱ -
G. VAT 5% of (D+E+F) ₱ -
H. Total Cost (D+E+F+G) ₱ -
I. Unit Cost H/Quantity ₱ -
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino
tal No. of Hours : 127.50 hrs. Total No. of Days : 16.25 days
A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
One Bagger Mixer 1.00 127.50 ₱ 172.00 ₱ 21,930.00
Concrete Vibrator 1.00 127.50 ₱ 56.00 ₱ 7,140.00
A. SUB-TOTAL, EQUIPMENT ₱ 29,070.00
B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Slab on Fill
Construction Foreman 1.00 92.75 ₱ 81.30 ₱ 7,540.58
Mason 4.00 92.75 58.76 21,799.96
Laborer 4.00 92.75 45.25 16,787.75
Footing
Construction Foreman 1.00 34.75 81.30 2,825.18
Mason 4.00 34.75 58.76 8,167.64
Laborer 4.00 34.75 45.25 6,289.75
B. SUB-TOTAL, LABOR ₱ 63,410.85
C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
Factor
Footing
Portland Cement 9.500 135.00 bags ₱ 260.00 ₱ 35,100.00
Fine Aggregates 0.420 6.00 cu.m. 579.52 3,477.12
Crushed Aggregates 0.851 13.00 cu.m. 820.40 10,665.20
Slab on Fill
Portland Cement 9.500 452.00 bags ₱ 260.00 ₱ 117,520.00
Fine Aggregates 0.450 22.00 cu.m. 579.52 12,749.44
Crushed Aggregates 0.900 43.00 cu.m. 820.40 35,277.20
C. SUB-TOTAL, MATERIAL ₱ 214,788.96
SUMMARY :
A. Equipment ₱ 29,070.00
B. Labor ₱ 63,410.85
C. Materials ₱ 214,788.96
D. TOTAL DIRECT COST ₱ 307,269.81
DIRECT UNIT COST ₱ 4,982.48
E. OCM 12% of D ₱ 36,872.38
F. Profit 8% of D ₱ 24,581.58
G. VAT 5% of (D+E+F) ₱ 18,436.19
H. Total Cost (D+E+F+G) ₱ 387,159.96
I. Unit Cost H/Quantity ₱ 6,277.93
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino
A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
One Bagger Mixer 1.00 9.25 ₱ 172.00 ₱ 1,591.00
One Bagger Mixer 1.00 9.25 ₱ 56.00 ₱ 518.00
B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Construction Foreman 1.00 4.63 ₱ 81.30 ₱ 376.01
Mason 4.00 9.25 58.76 2,174.12
Laborer 4.00 9.25 45.25 1,674.25
C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
Factor
Portland Cement 9.500 32.00 bags ₱ 260.00 ₱ 8,320.00
Fine Aggregates 0.425 2.00 cu.m. 579.52 1,159.04
Crushed Aggregates 0.850 3.00 cu.m. 820.40 2,461.20
SUMMARY :
A. Equipment ₱ 2,109.00
B. Labor ₱ 4,224.38
C. Materials ₱ 11,940.24
D. TOTAL DIRECT COST ₱ 18,273.62
DIRECT UNIT COST ₱ 5,471.14
E. OCM 12% of D ₱ 2,192.83
F. Profit 8% of D ₱ 1,461.89
G. VAT 5% of (D+E+F) ₱ 1,096.42
H. Total Cost (D+E+F+G) ₱ 23,024.76
I. Unit Cost H/Quantity ₱ 6,893.64
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino
A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
One Bagger Mixer 1.00 111.25 ₱ 172.00 ₱ 19,135.00
Concrete Vibrator 1.00 111.25 ₱ 56.00 ₱ 6,230.00
A. SUB-TOTAL, EQUIPMENT ₱
B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Construction Foreman 1.00 111.25 ₱ 81.30 ₱ 9,044.63
Mason 4.00 111.25 58.76 26,148.20
Laborer 4.00 111.25 45.25 20,136.25
B. SUB-TOTAL, LABOR ₱
C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
Factor
Portland Cement 9.500 212.00 bags ₱ 260.00 ₱ 55,120.00
Fine Aggregates 0.429 10.00 cu.m. 579.52 5,795.20
Crushed Aggregates 0.852 19.00 cu.m. 820.40 15,587.60
C. SUB-TOTAL, MATERIAL ₱
SUMMARY :
A. Equipment ₱ -
B. Labor ₱ -
C. Materials ₱ -
D. TOTAL DIRECT COST ₱ -
DIRECT UNIT COST ₱ -
E. OCM 12% of D ₱ -
F. Profit 8% of D ₱ -
G. VAT 5% of (D+E+F) ₱ -
H. Total Cost (D+E+F+G) ₱ -
I. Unit Cost H/Quantity ₱ -
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino
A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
One Bagger Mixer 1.00 60.75 ₱ 172.00 ₱ 10,449.00
Concrete Vibrator 1.00 60.75 ₱ 56.00 ₱ 3,402.00
B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Construction Foreman 1.00 60.75 ₱ 81.30 ₱ 4,938.98
Mason 4.00 60.75 58.76 14,278.68
Laborer 4.00 60.75 45.25 10,995.75
C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
Factor
Portland Cement 9.500 116.00 bags ₱ 260.00 ₱ 30,160.00
Fine Aggregates 0.429 6.00 cu.m. 579.52 3,477.12
Crushed Aggregates 0.852 11.00 cu.m. 820.40 9,024.40
SUMMARY :
A. Equipment ₱ 13,851.00
B. Labor ₱ 30,213.41
C. Materials ₱ 42,661.52
D. TOTAL DIRECT COST ₱ 86,725.93
DIRECT UNIT COST ₱ 7,143.82
E. OCM 12% of D ₱ 10,407.11
F. Profit 8% of D ₱ 6,938.07
G. VAT 5% of (D+E+F) ₱ 5,203.56
H. Total Cost (D+E+F+G) ₱ 109,274.67
I. Unit Cost H/Quantity ₱ 9,001.21
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino
A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
One Bagger Mixer 1.00 48.50 ₱ 172.00 ₱ 8,342.00
B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Construction Foreman 1.00 48.50 ₱ 81.30 ₱ 3,943.05
Mason 4.00 48.50 58.76 11,399.44
Laborer 4.00 48.50 45.25 8,778.50
C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
Factor
Portland Cement 9.500 93.00 bags ₱ 260.00 ₱ 24,180.00
Fine Aggregates 0.429 5.00 cu.m. 579.52 2,897.60
Crushed Aggregates 0.852 9.00 cu.m. 820.40 7,383.60
SUMMARY :
A. Equipment ₱ 8,342.00
B. Labor ₱ 24,120.99
C. Materials ₱ 34,461.20
D. TOTAL DIRECT COST ₱ 66,924.19
DIRECT UNIT COST ₱ 6,906.52
E. OCM 12% of D ₱ 8,030.90
F. Profit 8% of D ₱ 5,353.94
G. VAT 5% of (D+E+F) ₱ 4,015.45
H. Total Cost (D+E+F+G) ₱ 84,324.48
I. Unit Cost H/Quantity ₱ 8,702.22
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino
Column
rd. Output/gang : 21.0700 kgs. /hr.
oduction Output : 42.1400 kgs. /hr.
No. of Hours : 55.75 hrs.
No. of Days : 7.00 days
No. of Gang : 2.00 gang
tal No. of Hours : 186.00 hrs. Total No. of Days : 24.00 days
A. Name and Capacity of Equipment (OperateNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Bar Cutter 2.00 186.00 ₱ 158.25 ₱ 58,869.00
A. SUB-TOTAL, EQUIPMENT ₱ 58,869.00
B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Construction Foreman 1.00 186.00 ₱ 81.30 ₱ 15,121.80
Steelman 6.00 186.00 58.76 65,576.16
Laborer 3.00 186.00 45.25 25,249.50
B. SUB-TOTAL, LABOR ₱ 105,947.46
C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
Page 60 of 188
Wall Footing &Column Footing
Deformed RSB ( 20mm, 16mm, 12mm & 10mm ) 653.61 kgs. 40.00 26,144.40
Tie Wire (2% of RSB) 14.00 kgs. 65.00 910.00
Slab on Fill
Deformed RSB ( 10mm ), Grade 40 462.00 kgs. 40.00 18,480.00
Tie Wire (2% of RSB) 10.00 kgs. 65.00 650.00
Septic Tank
Deformed RSB ( 10mm ), Grade 40 162.80 kgs. 40.00 6,512.00
Tie Wire (2% of RSB) 4.00 kgs. 65.00 260.00
Beam
Deformed RSB ( 16mm & 10mm ), Gr 2,556.00 kgs. ₱ 40.00 ₱ 102,240.00
Tie Wire (2% of RSB) 15.00 kgs. 65.00 975.00
Column
Deformed RSB ( 20mm, 16mm & 10m 2,445.90 kgs. ₱ 40.00 ₱ 97,836.00
Tie Wire (2% of RSB) 47.00 kgs. 65.00 3,055.00
SUMMARY :
A. Equipment ₱ 58,869.00
B. Labor ₱ 105,947.46
C. Materials ₱ 285,531.60
D. TOTAL DIRECT COST ₱ 450,348.06
DIRECT UNIT COST ₱ 75.04
E. OCM 12% of D ₱ 54,041.77
F. Profit 8% of D ₱ 36,027.84
G. VAT 5% of (D+E+F) ₱ 27,020.88
H. Total Cost (D+E+F+G) ₱ 567,438.56
I. Unit Cost H/Quantity ₱ 94.55
Page 61 of 188
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino
A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
A. SUB-TOTAL, EQUIPMENT ₱ -
B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Construction Foreman 1.00 88.75 ₱ 81.30 ₱ 7,215.38
Carpenter 5.00 88.75 58.76 26,074.75
Laborer 8.00 88.75 45.25 32,127.50
C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
Factor
2" x 3" Good Lumber (Scaffolding) 2,549.32 bd.ft. ₱ 40.00 ₱ 101,972.80
2" x 2" Form Lumber (Forms and Staking) 980.13 bd.ft. 40.00 39,205.20
Assorted C.W. Nails 17.00 kgs. 75.00 1,275.00
1/4" × 4' × 8' Ordinary Plywood 30.00 pcs. 350.00 10,500.00
SUMMARY :
A. Equipment ₱ -
B. Labor ₱ 65,417.63
C. Materials ₱ 152,953.00
D. TOTAL DIRECT COST ₱ 218,370.63
DIRECT UNIT COST ₱ 218,370.63
E. OCM 12% of D ₱ 26,204.48
F. Profit 8% of D ₱ 17,469.65
G. VAT 5% of (D+E+F) ₱ 13,102.24
H. Total Cost (D+E+F+G) ₱ 275,146.99
I. Unit Cost H/Quantity ₱ 275,146.99
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino
A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
A. SUB-TOTAL, EQUIPMENT ₱ -
B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Laborer 4.00 7.50 45.25 1,357.50
C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
Factor
Soil Poisoning 12.00 liters ₱ 250.00 ₱ 3,000.00
SUMMARY :
A. Equipment ₱ -
B. Labor ₱ 1,357.50
C. Materials ₱ 3,000.00
D. TOTAL DIRECT COST ₱ 4,357.50
DIRECT UNIT COST ₱ 217.88
E. OCM 12% of D ₱ 522.90
F. Profit 8% of D ₱ 348.60
G. VAT 5% of (D+E+F) ₱ 261.45
H. Total Cost (D+E+F+G) ₱ 5,490.45
I. Unit Cost H/Quantity ₱ 274.52
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino
A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
A. SUB-TOTAL, EQUIPMENT ₱ -
B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Plumber 1.00 32.00 ₱ 58.76 ₱ 1,880.32
Laborer 1.00 32.00 45.25 1,448.00
C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
100mm dia. X 3.00 m. PVC Pipe (orange) 15.00 pc/s ₱ 600.00 ₱ 9,000.00
50mm dia. X 3.00 m. PVC Pipe (orange) 7.00 pc/s 275.00 1,925.00
100mm dia. Wye 5.00 pc/s 130.00 650.00
100mm dia. Clean Out w/ plug 2.00 pc/s 80.00 160.00
100mm dia. X 50mm dia. Wye 3.00 pc/s 130.00 390.00
100mm dia. Elbow 4.00 pc/s 90.00 360.00
50mm dia. Elbow 15.00 pc/s 45.00 675.00
50mm dia. Tee 5.00 pc/s 45.00 225.00
50mm dia. P-trap 3.00 pc/s 60.00 180.00
50mm dia. Clean out w/ plug 2.00 pc/s 45.00 90.00
SUMMARY :
A. Equipment ₱ -
B. Labor ₱ 3,328.32
C. Materials ₱ 13,655.00
D. TOTAL DIRECT COST ₱ 16,983.32
DIRECT UNIT COST ₱ 16,983.32
E. OCM 12% of D ₱ 2,038.00
F. Profit 8% of D ₱ 1,358.67
G. VAT 5% of (D+E+F) ₱ 1,019.00
H. Total Cost (D+E+F+G) ₱ 21,398.99
I. Unit Cost H/Quantity ₱ 21,398.99
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino
A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
A. SUB-TOTAL, EQUIPMENT ₱ -
B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Plumber 1.00 32.00 ₱ 58.76 ₱ 1,880.32
Laborer 1.00 32.00 45.25 1,448.00
C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
100mm dia. X 3.00 m. PVC Pipe (orange) 20.00 pcs ₱ 485.00 ₱ 9,700.00
100mm dia Elbow, 90 degree PVC 40.00 pcs 130.00 5,200.00
Flat Bar Metal Clamp 50mm x 1.2m 100.00 pcs 50.00 5,000.00
4mm dia Metal Screw with Tox 200.00 pcs 5.00 1,000.00
Masonry Drill Bit 4.00 pcs 120.00 480.00
Steel Drill Bit 4.00 pcs 150.00 600.00
Solvent Cement 2.00 pcs 460.00 920.00
50mm dia x 3.00 m PVC 2.00 pcs 275.00 550.00
SUMMARY :
A. Equipment ₱ -
B. Labor ₱ 3,328.32
C. Materials ₱ 23,450.00
D. TOTAL DIRECT COST ₱ 26,778.32
DIRECT UNIT COST ₱ 26,778.32
E. OCM 12% of D ₱ 3,213.40
F. Profit 8% of D ₱ 2,142.27
G. VAT 5% of (D+E+F) ₱ 1,606.70
H. Total Cost (D+E+F+G) ₱ 33,740.69
I. Unit Cost H/Quantity ₱ 33,740.69
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino
A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
A. SUB-TOTAL, EQUIPMENT ₱ -
B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Plumber 1.00 36.00 ₱ 58.76 ₱ 2,115.36
Laborer 1.00 36.00 45.25 1,629.00
B. SUB-TOTAL, LABOR ₱
C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
50mm dia. X 3.00 m. PVC Pipe (orange) 8.00 pcs ₱ 291.00 ₱ 2,328.00
C. SUB-TOTAL, MATERIAL ₱
SUMMARY :
A. Equipment ₱
B. Labor ₱
C. Materials ₱
D. TOTAL DIRECT COST ₱ -
DIRECT UNIT COST ₱ -
E. OCM 12% of D ₱ -
F. Profit 8% of D ₱ -
G. VAT 5% of (D+E+F) ₱ -
H. Total Cost (D+E+F+G) ₱ -
I. Unit Cost H/Quantity ₱ -
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino
A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
A. SUB-TOTAL, EQUIPMENT ₱ -
B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Plumber 1.00 16.00 ₱ 58.76 ₱ 940.16
Laborer 1.00 16.00 45.25 724.00
B. SUB-TOTAL, LABOR ₱
C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
100mm dia. PVC 1/8 Bend (orange) 9.00 pc ₱ 60.00 ₱ 540.00
C. SUB-TOTAL, MATERIAL ₱
SUMMARY :
A. Equipment ₱
B. Labor ₱
C. Materials ₱
D. TOTAL DIRECT COST ₱ -
DIRECT UNIT COST ₱ -
E. OCM 12% of D ₱ -
F. Profit 8% of D ₱ -
G. VAT 5% of (D+E+F) ₱ -
H. Total Cost (D+E+F+G) ₱ -
I. Unit Cost H/Quantity ₱ -
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino
A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
A. SUB-TOTAL, EQUIPMENT ₱ -
B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Plumber 1.00 2.00 ₱ 58.76 ₱ 117.52
Laborer 1.00 2.00 45.25 90.50
B. SUB-TOTAL, LABOR ₱
C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
50mm dia. PVC 1/4 Bend (orange) 24.00 pc ₱ 26.00 ₱ 624.00
C. SUB-TOTAL, MATERIAL ₱
SUMMARY :
A. Equipment ₱
B. Labor ₱
C. Materials ₱
D. TOTAL DIRECT COST ₱ -
DIRECT UNIT COST ₱ -
E. OCM 12% of D ₱ -
F. Profit 8% of D ₱ -
G. VAT 5% of (D+E+F) ₱ -
H. Total Cost (D+E+F+G) ₱ -
I. Unit Cost H/Quantity ₱ -
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino
A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
A. SUB-TOTAL, EQUIPMENT ₱ -
B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Plumber 1.00 8.00 ₱ 58.76 ₱ 470.08
Laborer 1.00 8.00 45.25 362.00
B. SUB-TOTAL, LABOR ₱
C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
100mm dia. PVC 1/4 Bend (orange) 9.00 pc ₱ 70.00 ₱ 630.00
C. SUB-TOTAL, MATERIAL ₱
SUMMARY :
A. Equipment ₱
B. Labor ₱
C. Materials ₱
D. TOTAL DIRECT COST ₱ -
DIRECT UNIT COST ₱ -
E. OCM 12% of D ₱ -
F. Profit 8% of D ₱ -
G. VAT 5% of (D+E+F) ₱ -
H. Total Cost (D+E+F+G) ₱ -
I. Unit Cost H/Quantity ₱ -
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino
A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
A. SUB-TOTAL, EQUIPMENT ₱ -
B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Plumber 1.00 10.00 ₱ 58.76 ₱ 587.60
Laborer 1.00 10.00 45.25 452.50
B. SUB-TOTAL, LABOR ₱
C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
100mm dia. PVC Clean Out with Plug & Seal 4.00 pc ₱ 55.00 ₱ 220.00
(orange)
C. SUB-TOTAL, MATERIAL ₱
SUMMARY :
A. Equipment ₱
B. Labor ₱
C. Materials ₱
D. TOTAL DIRECT COST ₱ -
DIRECT UNIT COST ₱ -
E. OCM 12% of D ₱ -
F. Profit 8% of D ₱ -
G. VAT 5% of (D+E+F) ₱ -
H. Total Cost (D+E+F+G) ₱ -
I. Unit Cost H/Quantity ₱ -
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino
A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
A. SUB-TOTAL, EQUIPMENT ₱ -
B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Plumber 1.00 4.00 ₱ 58.76 ₱ 235.04
Laborer 1.00 4.00 45.25 181.00
B. SUB-TOTAL, LABOR ₱
C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
50mm dia. PVC P-Trap w/ Plug and Sealing R 12.00 pc ₱ 107.00 ₱ 1,284.00
(orange)
C. SUB-TOTAL, MATERIAL ₱
SUMMARY :
A. Equipment ₱
B. Labor ₱
C. Materials ₱
D. TOTAL DIRECT COST ₱ -
DIRECT UNIT COST ₱ -
E. OCM 12% of D ₱ -
F. Profit 8% of D ₱ -
G. VAT 5% of (D+E+F) ₱ -
H. Total Cost (D+E+F+G) ₱ -
I. Unit Cost H/Quantity ₱ -
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino
A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
A. SUB-TOTAL, EQUIPMENT ₱ -
B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Plumber 1.00 4.00 ₱ 58.76 ₱ 235.04
Laborer 1.00 4.00 45.25 181.00
B. SUB-TOTAL, LABOR ₱
C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
50mm dia. PVC Tee (orange) 4.00 pc ₱ 37.00 ₱ 148.00
C. SUB-TOTAL, MATERIAL ₱
SUMMARY :
A. Equipment ₱
B. Labor ₱
C. Materials ₱
D. TOTAL DIRECT COST ₱ -
DIRECT UNIT COST ₱ -
E. OCM 12% of D ₱ -
F. Profit 8% of D ₱ -
G. VAT 5% of (D+E+F) ₱ -
H. Total Cost (D+E+F+G) ₱ -
I. Unit Cost H/Quantity ₱ -
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino
A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
A. SUB-TOTAL, EQUIPMENT ₱ -
B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Plumber 1.00 2.00 ₱ 58.76 ₱ 117.52
Laborer 1.00 2.00 45.25 90.50
B. SUB-TOTAL, LABOR ₱
C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
100mm dia. PVC 1/8 Bend (orange) 18.00 pc ₱ 60.00 ₱ 1,080.00
C. SUB-TOTAL, MATERIAL ₱
SUMMARY :
A. Equipment ₱
B. Labor ₱
C. Materials ₱
D. TOTAL DIRECT COST ₱ -
DIRECT UNIT COST ₱ -
E. OCM 12% of D ₱ -
F. Profit 8% of D ₱ -
G. VAT 5% of (D+E+F) ₱ -
H. Total Cost (D+E+F+G) ₱ -
I. Unit Cost H/Quantity ₱ -
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino
A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
A. SUB-TOTAL, EQUIPMENT ₱ -
B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Plumber 1.00 16.00 ₱ 58.76 ₱ 940.16
Laborer 1.00 16.00 45.25 724.00
B. SUB-TOTAL, LABOR ₱
C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
50mm dia. PVC Wye (orange) 9.00 pc ₱ 81.00 ₱ 729.00
C. SUB-TOTAL, MATERIAL ₱
SUMMARY :
A. Equipment ₱
B. Labor ₱
C. Materials ₱
D. TOTAL DIRECT COST ₱ -
DIRECT UNIT COST ₱ -
E. OCM 12% of D ₱ -
F. Profit 8% of D ₱ -
G. VAT 5% of (D+E+F) ₱ -
H. Total Cost (D+E+F+G) ₱ -
I. Unit Cost H/Quantity ₱ -
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino
A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
A. SUB-TOTAL, EQUIPMENT ₱ -
B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Plumber 1.00 10.00 ₱ 58.76 ₱ 587.60
Laborer 1.00 10.00 45.25 452.50
B. SUB-TOTAL, LABOR ₱
C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
100mm x 50mm dia. PVC Wye (orange) 5.00 pc ₱ 100.00 ₱ 500.00
C. SUB-TOTAL, MATERIAL ₱
SUMMARY :
A. Equipment ₱
B. Labor ₱
C. Materials ₱
D. TOTAL DIRECT COST ₱ -
DIRECT UNIT COST ₱ -
E. OCM 12% of D ₱ -
F. Profit 8% of D ₱ -
G. VAT 5% of (D+E+F) ₱ -
H. Total Cost (D+E+F+G) ₱ -
I. Unit Cost H/Quantity ₱ -
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino
A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
A. SUB-TOTAL, EQUIPMENT ₱ -
B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Plumber 1.00 10.00 ₱ 58.76 ₱ 587.60
Laborer 1.00 10.00 45.25 452.50
B. SUB-TOTAL, LABOR ₱
C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
100mm x 50mm dia. PVC Tee (orange) 2.00 pc ₱ 100.00 ₱ 200.00
C. SUB-TOTAL, MATERIAL ₱
SUMMARY :
A. Equipment ₱
B. Labor ₱
C. Materials ₱
D. TOTAL DIRECT COST ₱ -
DIRECT UNIT COST ₱ -
E. OCM 12% of D ₱ -
F. Profit 8% of D ₱ -
G. VAT 5% of (D+E+F) ₱ -
H. Total Cost (D+E+F+G) ₱ -
I. Unit Cost H/Quantity ₱ -
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino
A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
A. SUB-TOTAL, EQUIPMENT ₱ -
B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Mason 1.00 1.00 ₱ ₱ -
Laborer 1.00 1.00 -
B. SUB-TOTAL, LABOR ₱ -
C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
C. SUB-TOTAL, MATERIAL ₱ -
SUMMARY :
A. Equipment ₱ -
B. Labor ₱ -
C. Materials ₱ -
D. TOTAL DIRECT COST ₱ -
DIRECT UNIT COST ₱ -
E. OCM 12% of D ₱ -
F. Profit 8% of D ₱ -
G. VAT 5% of (D+E+F) ₱ -
H. Total Cost (D+E+F+G) ₱ -
I. Unit Cost H/Quantity ₱ -
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino
A. Name and Capacity of Equipment (OperateNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
A. SUB-TOTAL, EQUIPMENT ₱ -
B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Excavation
Laborer 4.00 8.00 45.25 1,448.00
Masonry Works
Mason 1.00 40.00 58.76 2,350.40
Laborer 2.00 40.00 45.25 3,620.00
Cement Plaster Finish
Mason 1.00 40.00 58.76 2,350.40
Laborer 2.00 40.00 45.25 3,620.00
Concrete Works
Mason 1.00 40.00 58.76 2,350.40
Carpenter 1.00 40.00 58.76 2,350.40
Laborer 1.00 40.00 45.25 1,810.00
Pipe
Plumber 1.00 40.00 58.76 2,350.40
Laborer 2.00 40.00 45.25 3,620.00
C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
Excavation
none
Masonry Works
a. 100mmx200mmx400 CHB 360.00 pcs ₱ 12.00 ₱ 4,320.00
b. Portland Cement (Class B) 33.26 bags 260.00 8,647.60
c. Fine Aggregates 0.67 cu.m. 579.52 388.28
d. 10mmDx6m RSB; 11.00 kls 40.00 440.00
e. Tie Wire (2% of RSB) 0.89 kls 75.00 66.75
Cement Plaster Finish
a. Portland Cement (Class A, 1:2 ratio) 21.00 bags 260.00 5,460.00
b. Fine Aggregates 2.50 cu.m. 579.52 1,448.80
Concrete Works
a. Portland Cement 12.00 bags 260.00 3,120.00
b. Fine Aggregates 0.55 cu.m 579.52 318.74
c. Crushed Aggregates 1.10 cu.m 820.40 902.44
Pipe
100 mm dia uPVC 81.00 pcs 600.00 48,600.00
C. SUB-TOTAL, MATERIAL ₱ 73,712.60
SUMMARY :
A. Equipment ₱ -
B. Labor ₱ 25,870.00
C. Materials ₱ 73,712.60
D. TOTAL DIRECT COST ₱ 99,582.60
DIRECT UNIT COST ₱ 8,298.55
E. OCM 12% of D ₱ 11,949.91
F. Profit 8% of D ₱ 7,966.61
G. VAT 5% of (D+E+F) ₱ 5,974.96
H. Total Cost (D+E+F+G) ₱ 125,474.08
I. Unit Cost H/Quantity ₱ 10,456.17
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino
A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
A. SUB-TOTAL, EQUIPMENT ₱ -
B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Plumber 2.00 40.00 ₱ 58.76 ₱ 4,700.80
Laborer 1.00 40.00 45.25 1,810.00
C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
Water Closet including fittings and 3.00 sets ₱ 6,500.00 ₱ 19,500.00
accessories (Round Front)
Lavatory with complete accessories 1.00 sets 5,500.00 5,500.00
Floor Drain 8.00 pcs 280.00 2,240.00
Stainless Faucet 12.00 pcs 400.00 4,800.00
Vulcaseal 2.00 ltr 250.00 500.00
PVC Solvent 3.00 ltr 35.00 105.00
Teflon Tape 15.00 pcs 850.00 12,750.00
Stainless Kitchen Sink 5.00 sets 5,000.00 25,000.00
SUMMARY :
A. Equipment ₱ -
B. Labor ₱ 6,510.80
C. Materials ₱ 70,395.00
D. TOTAL DIRECT COST ₱ 76,905.80
DIRECT UNIT COST ₱ 76,905.80
E. OCM 12% of D ₱ 9,228.70
F. Profit 8% of D ₱ 6,152.46
G. VAT 5% of (D+E+F) ₱ 4,614.35
H. Total Cost (D+E+F+G) ₱ 96,901.31
I. Unit Cost H/Quantity ₱ 96,901.31
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino
rd. Output/gang :
oduction Output :
No. of Hours :
No. of Days :
No. of Gang :
A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
A. SUB-TOTAL, EQUIPMENT ₱ -
B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Plumber 1.00 30.00 ₱ 58.76 ₱ 1,762.80
Laborer 1.00 30.00 45.25 1,357.50
C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
20mm dia Gate Valve 5.00 pcs. ₱ 150.00 ₱ 750.00
32mm dia Fusion Device 1.00 pcs. 2,500.00 2,500.00
32mm x 20mm dia Tee Reducer 4.00 pcs. 260.00 1,040.00
20mm dia Equal Tee 6.00 pcs. 260.00 1,560.00
20mm dia Elbow 90 degrees 7.00 pcs. 180.00 1,260.00
20mm dia Female Elbow 10.00 pcs. 250.00 2,500.00
32mm dia x 4.00m PPR Pipe 25.00 pcs. 580.00 14,500.00
20mm dia x 4.00m PPR Pipe 8.00 pcs. 350.00 2,800.00
32mm dia End Cap 1.00 pcs. 25.00 25.00
PPR Cutter 1.00 pcs. 850.00 850.00
SUMMARY :
A. Equipment ₱ -
B. Labor ₱ 3,120.30
C. Materials ₱ 27,785.00
D. TOTAL DIRECT COST ₱ 30,905.30
DIRECT UNIT COST ₱ 30,905.30
E. OCM 12% of D ₱ 3,708.64
F. Profit 8% of D ₱ 2,472.42
G. VAT 5% of (D+E+F) ₱ 1,854.32
H. Total Cost (D+E+F+G) ₱ 38,940.68
I. Unit Cost H/Quantity ₱ 38,940.68
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino
A. Name and Capacity of Equipment (OperatedNo. of UnitsNo. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
A. SUB-TOTAL, EQUIPMENT ₱ -
B. Designation of Personnel No. of MenNo. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Foreman 1.00 92.00 81.30 7,479.60
Carpenter 6.00 92.00 ₱ 58.76 ₱ 32,435.52
Laborer 4.00 92.00 45.25 16,652.00
B. SUB-TOTAL, LABOR ₱ 56,567.12
C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
Metal Furring (12mm x 38mm x0.80mm) 250.00 pcs ₱ 125.00 ₱ 31,250.00
Primary Channel (12mm x38mm x 0.80mm) 125.00 pcs 110.00 13,750.00
Wall Angle (25mm x 25mm x0.40mm) 150.00 pcs 55.00 8,250.00
Rod Joiner Clip 1,050.00 pcs 15.00 15,750.00
W-Clip 1,200.00 pcs 5.00 6,000.00
# 10 GI Wire 210.00 kls 60.00 12,600.00
Rivets 80.00 boxes 250.00 20,000.00
Fiber Cement Ceiling Board 125.00 pcs 350.00 43,750.00
Screw # 6 14,000.00 screw 0.50 7,000.00
Insulator 276.08 sq.m. 130.00 35,890.40
0.4mm x 6" width @ 1.00m length - spandrel
682.00 lin.m 50.00 34,100.00
eaves cover with air vent design
0.4mm x 6" width @ 1.50m length - spandrel
459.00 50.00 22,950.00
eaves cover with air vent design lin.m
0.4mm x 6" width @ 3.20m length - spandrel
288.00 lin.m 50.00 14,400.00
eaves cover with air vent design
0.5mm thick x 8' end mouldings 199.20 lin.m 50.00 9,960.00
0.5mm thick x 8' center mouldings 12.00 lin.m 50.00 600.00
C. SUB-TOTAL, MATERIAL ₱ 276,250.40
SUMMARY :
A. Equipment ₱ -
B. Labor ₱ 56,567.12
C. Materials ₱ 276,250.40
D. TOTAL DIRECT COST ₱ 332,817.52
DIRECT UNIT COST ₱ 710.37
E. OCM 12% of D ₱ 39,938.10
F. Profit 8% of D ₱ 26,625.40
G. VAT 5% of (D+E+F) ₱ 19,969.05
H. Total Cost (D+E+F+G) ₱ 419,350.08
I. Unit Cost H/Quantity ₱ 895.07
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino
A. Name and Capacity of Equipment (OperateNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
A. SUB-TOTAL, EQUIPMENT ₱ -
B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Carpenter 2.00 80.00 ₱ 58.76 ₱ 9,401.60
Laborer 2.00 80.00 45.25 7,240.00
C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
Factor
-
2" x 6" Steel Door Jambs 5.00 pcs ₱ 1,500.00 ₱ 7,500.00
Roll up Door 58.89 sq.m ₱ 550.00 ₱ 32,389.50
SUMMARY :
A. Equipment ₱ -
B. Labor ₱ 16,641.60
C. Materials ₱ 39,889.50
D. TOTAL DIRECT COST ₱ 56,531.10
DIRECT UNIT COST ₱ 3,325.36
E. OCM 12% of D ₱ 6,783.73
F. Profit 8% of D ₱ 4,522.49
G. VAT 5% of (D+E+F) ₱ 3,391.87
H. Total Cost (D+E+F+G) ₱ 71,229.19
I. Unit Cost H/Quantity ₱ 4,189.95
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino
A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
A. SUB-TOTAL, EQUIPMENT ₱ -
B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Carpenter 2.00 21.75 ₱ 58.76 ₱ 2,556.06
C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
Door Lockset 23.00 sets ₱ 1,550.00 ₱ 35,650.00
SUMMARY :
A. Equipment ₱ -
B. Labor ₱ 2,556.06
C. Materials ₱ 35,650.00
D. TOTAL DIRECT COST ₱ 38,206.06
DIRECT UNIT COST ₱ 1,661.13
E. OCM 12% of D ₱ 4,584.73
F. Profit 8% of D ₱ 3,056.48
G. VAT 5% of (D+E+F) ₱ 2,292.36
H. Total Cost (D+E+F+G) ₱ 48,139.64
I. Unit Cost H/Quantity ₱ 2,093.03
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino
A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
A. SUB-TOTAL, EQUIPMENT ₱ -
B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Carpenter 2.00 14.75 ₱ 58.76 P 1,733.42
Laborer 2.00 14.75 45.25 1,334.88
C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
4" x 4" Hinges 68.00 pcs. ₱ 50.00 P 3,400.00
SUMMARY :
A. Equipment ₱ -
B. Labor ₱ 3,068.30
C. Materials ₱ 3,400.00
D. TOTAL DIRECT COST ₱ 6,468.30
DIRECT UNIT COST ₱ 58.80
E. OCM 12% of D ₱ 776.20
F. Profit 8% of D ₱ 517.46
G. VAT 5% of (D+E+F) ₱ 388.10
H. Total Cost (D+E+F+G) ₱ 8,150.05
I. Unit Cost H/Quantity ₱ 74.09
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino
A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
A. SUB-TOTAL, EQUIPMENT ₱ -
B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Installer 4.00 34.75 ₱ 58.76 ₱ 8,167.64
Laborer 1.00 34.75 45.25 1,572.44
C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
Steel Matting Window
W-1, (3-2.40 x 3.60m) 25.92 sq.m. P 2,500.00 P 64,800.00
W-2, (1-1.20 x 3.60m) 4.32 sq.m. 2,500.00 10,800.00
W-3, (2-1.20 x 2.40m) 5.76 sq.m. 2,500.00 14,400.00
W-4, (1 - 1.20m x 2.40m) 2.88 sq.m. 2,500.00 7,200.00
Steel Casement Window
W-5, (1 - 1.20m x 1.20m) 1.44 sq.m. 2,500.00 3,600.00
W-6, (1 - 0.50m x 1.00m) 1.50 sq.m. 2,500.00 3,750.00
C. SUB-TOTAL, MATERIAL ₱ 104,550.00
SUMMARY :
A. Equipment ₱ -
B. Labor ₱ 9,740.08
C. Materials ₱ 104,550.00
D. TOTAL DIRECT COST ₱ 114,290.08
DIRECT UNIT COST ₱ 2,939.56
E. OCM 12% of D ₱ 13,714.81
F. Profit 8% of D ₱ 9,143.21
G. VAT 5% of (D+E+F) ₱ 6,857.40
H. Total Cost (D+E+F+G) ₱ 144,005.50
I. Unit Cost H/Quantity ₱ 3,703.85
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino
A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
A. SUB-TOTAL, EQUIPMENT ₱ -
B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Carpenter 2.00 112.00 ₱ 58.76 ₱ 13,162.24
C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
D3 - (1.00m × 2.10m.) Panel Type Door 2.00 sets ₱ 6,500.00 ₱ 13,000.00
D4 - (0.90m × 2.10m.) Panel Type Door 3.00 sets 5,500.00 16,500.00
SUMMARY :
A. Equipment ₱ -
B. Labor ₱ 13,162.24
C. Materials ₱ 29,500.00
D. TOTAL DIRECT COST ₱ 42,662.24
DIRECT UNIT COST ₱ 1,612.33
E. OCM 12% of D ₱ 5,119.47
F. Profit 8% of D ₱ 3,412.98
G. VAT 5% of (D+E+F) ₱ 2,559.73
H. Total Cost (D+E+F+G) ₱ 53,754.42
I. Unit Cost H/Quantity ₱ 2,031.54
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino
A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
A. SUB-TOTAL, EQUIPMENT ₱ -
B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Tinsmith 4.00 79.75 ₱ 58.76 ₱ 18,744.44
Laborer 4.00 79.75 45.25 14,434.75
C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
SUMMARY :
A. Equipment ₱ -
B. Labor ₱ 33,179.19
C. Materials ₱ 194,647.00
D. TOTAL DIRECT COST ₱ 227,826.19
DIRECT UNIT COST ₱ 439.46
E. OCM 12% of D ₱ 27,339.14
F. Profit 8% of D ₱ 18,226.10
G. VAT 5% of (D+E+F) ₱ 13,669.57
H. Total Cost (D+E+F+G) ₱ 287,061.00
I. Unit Cost H/Quantity ₱ 553.72
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino
A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
A. SUB-TOTAL, EQUIPMENT ₱ -
B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Tinsmith 2.00 9.25 ₱ 58.76 ₱ 1,087.06
Laborer 2.00 9.25 45.25 837.13
C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
Prepinted G. I Ridge Roll 22.00 pcs ₱ 450.00 ₱ 9,900.00
SUMMARY :
A. Equipment ₱ -
B. Labor ₱ 1,924.19
C. Materials ₱ 9,900.00
D. TOTAL DIRECT COST ₱ 11,824.19
DIRECT UNIT COST ₱ 244.30
E. OCM 12% of D ₱ 1,418.90
F. Profit 8% of D ₱ 945.93
G. VAT 5% of (D+E+F) ₱ 709.45
H. Total Cost (D+E+F+G) ₱ 14,898.47
I. Unit Cost H/Quantity ₱ 307.82
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino
A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
A. SUB-TOTAL, EQUIPMENT ₱ -
B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Tinsmith 2.00 6.50 ₱ 58.76 ₱ 763.88
Laborer 2.00 6.50 45.25 588.25
C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
Prepainted Flashing 14.00 pcs ₱ 450.00 ₱ 6,300.00
SUMMARY :
A. Equipment ₱ -
B. Labor ₱ 1,352.13
C. Materials ₱ 6,300.00
D. TOTAL DIRECT COST ₱ 7,652.13
DIRECT UNIT COST ₱ 227.74
E. OCM 12% of D ₱ 918.26
F. Profit 8% of D ₱ 612.17
G. VAT 5% of (D+E+F) ₱ 459.13
H. Total Cost (D+E+F+G) ₱ 9,641.68
I. Unit Cost H/Quantity ₱ 286.95
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino
A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
A. SUB-TOTAL, EQUIPMENT ₱ -
B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Tinsmith 2.00 20.00 ₱ 58.76 ₱
Laborer 2.00 20.00 45.25
B. SUB-TOTAL, LABOR ₱ -
C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
0.40mm x 2.4m S-type gutter - prepainted 44.00 pcs ₱ 450.00 ₱
0.40mm x 2.4m @ 24" width Valley gutter -
5.00 pcs 450.00
pre painted
C. SUB-TOTAL, MATERIAL ₱ -
SUMMARY :
A. Equipment ₱ -
B. Labor ₱ -
C. Materials ₱ -
D. TOTAL DIRECT COST ₱ -
DIRECT UNIT COST ₱ -
E. OCM 12% of D ₱ -
F. Profit 8% of D ₱ -
G. VAT 5% of (D+E+F) ₱ -
H. Total Cost (D+E+F+G) ₱ -
I. Unit Cost H/Quantity ₱ -
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino
A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
A. SUB-TOTAL, EQUIPMENT ₱ -
B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Tile Setter 4.00 84.00 ₱ 58.76 ₱ 19,743.36
Laborer 2.00 84.00 45.25 7,602.00
C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
Ceramic Glazed Tiles (0.30m × 0.30m) 3,129.00 pcs. P 45.00 P 140,805.00
Portland Cement 68.00 bags 260.00 17,680.00
Tile Adhesive, 25kg 120.00 bags 310.00 37,200.00
Sand 10.00 cu.m. 600.00 6,000.00
Tile Grout 84.00 bags 180.00 15,120.00
SUMMARY :
A. Equipment ₱ -
B. Labor ₱ 27,345.36
C. Materials ₱ 216,805.00
D. TOTAL DIRECT COST ₱ 244,150.36
DIRECT UNIT COST ₱ 867.01
E. OCM 12% of D ₱ 29,298.04
F. Profit 8% of D ₱ 19,532.03
G. VAT 5% of (D+E+F) ₱ 14,649.02
H. Total Cost (D+E+F+G) ₱ 307,629.45
I. Unit Cost H/Quantity ₱ 1,092.43
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino
A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
A. SUB-TOTAL, EQUIPMENT ₱ -
B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Mason 8.00 2.75 ₱ 58.76 ₱ 1,292.72
Laborer 8.00 2.75 45.25 995.50
C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
Ceramic Unglazed Tiles (0.30 x 0.30) 96.00 pcs. ₱ 70.00 ₱ 6,720.00
Portland Cement 2.00 bags 260.00 520.00
Tile Adhesive, 25kg 4.00 bags 350.00 1,400.00
Sand 1.00 cu.m. 579.52 579.52
Tile Grout 3.00 bags 180.00 540.00
SUMMARY :
A. Equipment ₱ -
B. Labor ₱ 2,288.22
C. Materials ₱ 9,759.52
D. TOTAL DIRECT COST ₱ 12,047.74
DIRECT UNIT COST ₱ 1,404.17
E. OCM 12% of D ₱ 1,445.73
F. Profit 8% of D ₱ 963.82
G. VAT 5% of (D+E+F) ₱ 722.86
H. Total Cost (D+E+F+G) ₱ 15,180.15
I. Unit Cost H/Quantity ₱ 1,769.25
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino
A. Name and Capacity of Equipment (OperatNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
A. SUB-TOTAL, EQUIPMENT ₱ -
B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Mason 8.00 57.50 ₱ 58.76 ₱ 27,029.60
Laborer 8.00 57.50 45.25 20,815.00
C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
Factor
Portland Cement 0.360 393.00 bags ₱ 260.00 ₱ 102,180.00
Fine Aggregates 0.021 23.00 cu.m. 579.52 13,328.96
SUMMARY :
A. Equipment ₱ -
B. Labor ₱ 47,844.60
C. Materials ₱ 115,508.96
D. TOTAL DIRECT COST ₱ 163,353.56
DIRECT UNIT COST ₱ 149.88
E. OCM 12% of D ₱ 19,602.43
F. Profit 8% of D ₱ 13,068.28
G. VAT 5% of (D+E+F) ₱ 9,801.21
H. Total Cost (D+E+F+G) ₱ 205,825.49
I. Unit Cost H/Quantity ₱ 188.85
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino
Masonry
oduction Output : 6.2700 sq.m. /hr.
rd. Output/gang : 18.810 sq.m. /hr.
No. of Hours : 58.00 hrs.
No. of Days : 7.25 days
No. of Gang : 3.00 gang
A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
A. SUB-TOTAL, EQUIPMENT ₱ -
B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Painter 6.00 58.00 ₱ 58.76 ₱ 20,448.48
Laborer 3.00 58.00 45.25 7,873.50
C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
Concrete Neutralizer 51.00 gals. ₱ 550.00 ₱ 28,050.00
Flat Latex Paint (white) 80.00 gals. 550.00 44,000.00
Gloss Latex Paint (white) 80.00 gals. 500.00 40,000.00
Tinting Color 24.00 qrt. 55.00 1,320.00
Masonry Putty 50.00 gals. 400.00 20,000.00
Paint Thinner 12.00 glas 200.00 2,400.00
#120 Sand Paper 41.00 pcs. 30.00 1,230.00
3M Sand Paper 41.00 pcs. 120.00 4,920.00
Paint Roller w/ Tray 5.00 sets 250.00 1,250.00
Paint Brush 4" 5.00 pcs. 75.00 375.00
Paint Brush 2" 12.00 pcs. 60.00 720.00
Paleta 4" 12.00 pairs 65.00 780.00
C. SUB-TOTAL, MATERIAL ₱ 145,045.00
SUMMARY :
A. Equipment ₱ -
B. Labor ₱ 28,321.98
C. Materials ₱ 145,045.00
D. TOTAL DIRECT COST ₱ 173,366.98
DIRECT UNIT COST ₱ 159.20
E. OCM 12% of D ₱ 20,804.04
F. Profit 8% of D ₱ 13,869.36
G. VAT 5% of (D+E+F) ₱ 10,402.02
H. Total Cost (D+E+F+G) ₱ 218,442.39
I. Unit Cost H/Quantity ₱ 200.59
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino
Masonry
oduction Output : 5.7600 sq.m. /hr.
rd. Output/gang : 5.760 sq.m. /hr.
No. of Hours : 63.75 hrs.
No. of Days : 8.00 days
No. of Gang : 1.00 gang
A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
A. SUB-TOTAL, EQUIPMENT ₱ -
B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Painter 2.00 63.75 ₱ 58.76 ₱ 7,491.90
Laborer 1.00 63.75 45.25 2,884.69
C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
Enamel, Flatwall 40.00 gals. ₱ 550.00 ₱ 22,000.00
Enamel, Semi Gloss 35.00 gals. 600.00 21,000.00
Tinting Color 7.00 qrt. 55.00 385.00
Lacquer Thinner 4.00 gals. 415.00 1,660.00
Paint Thinner 7.00 gals. 200.00 1,400.00
Glazing Putty 37.00 gals. 600.00 22,200.00
Sand Paper 61.00 ln.m. 50.00 3,050.00
Paint Brush 2" 1.00 pcs. 60.00 60.00
Paleta 4" 40.00 pcs. 65.00 2,600.00
SUMMARY :
A. Equipment ₱ -
B. Labor ₱ 10,376.59
C. Materials ₱ 74,355.00
D. TOTAL DIRECT COST ₱ 84,731.59
DIRECT UNIT COST ₱ 231.32
E. OCM 12% of D ₱ 10,167.79
F. Profit 8% of D ₱ 6,778.53
G. VAT 5% of (D+E+F) ₱ 5,083.90
H. Total Cost (D+E+F+G) ₱ 106,761.80
I. Unit Cost H/Quantity ₱ 291.46
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino
A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
A. SUB-TOTAL, EQUIPMENT ₱ -
B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Painter 4.00 2.75 ₱ 58.76 ₱ 646.36
Laborer 2.00 2.75 45.25 248.88
C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
Red Lead Primer 10.00 gals. ₱ 675.00 ₱ 6,750.00
QDE Choco Brown 10.00 gals. 675.00 6,750.00
Paint Brush 3" 2.00 pcs 60.00 120.00
Paint Brush 1" 2.00 pcs 50.00 100.00
Paint Thinner 3.00 gals. 275.00 825.00
SUMMARY :
A. Equipment ₱ -
B. Labor ₱ 895.24
C. Materials ₱ 14,545.00
D. TOTAL DIRECT COST ₱ 15,440.24
DIRECT UNIT COST ₱ 449.11
E. OCM 12% of D ₱ 1,389.62
F. Profit 8% of D ₱ 1,235.22
G. VAT 5% of (D+E+F) ₱ 903.25
H. Total Cost (D+E+F+G) ₱ 18,968.33
I. Unit Cost H/Quantity ₱ 551.73
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino
A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
A. SUB-TOTAL, EQUIPMENT ₱ -
B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Foreman 1.00 3.25 ₱ 81.30 ₱
Carpenter 4.00 3.25 ₱ 58.76 ₱
Laborer 6.00 3.25 ₱ 45.25 ₱
B. SUB-TOTAL, LABOR ₱ -
C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
ACP Cladding on Frames 13.28 sq.m. ₱ 3,500.00 ₱
C. SUB-TOTAL, MATERIAL ₱ -
SUMMARY :
A. Equipment ₱ -
B. Labor ₱ -
C. Materials ₱ -
D. TOTAL DIRECT COST ₱ -
DIRECT UNIT COST ₱ -
E. OCM 12% of D ₱ -
F. Profit 8% of D ₱ -
G. VAT 5% of (D+E+F) ₱ -
H. Total Cost (D+E+F+G) ₱ -
I. Unit Cost H/Quantity ₱ -
Construction of Machinery Shed
D
ITEM DESCRIPTION % QTTY. UNIT
TOTAL
PART II OTHER GENERAL REQUIREMENTS
B.5 Project Billboard/Signboard1 0.07 1.00 each 2,5
B.7 Occupational Safety & Health Program2 1.37 7.00 month 53,4
B.9 Mobilization/Demobilization2 0.98 1.00 lump sum 38,1
TOTAL OF PART II 2.41 94,14
PART III CIVIL, MECHANICAL, ELECTRICAL & SANITARY/PLUMBING WORKS
DIVISION I - GENERAL
PART A EARTHWORKS
803 (1) a Structure Excavation (Common Soil) 0.38 81.35 cu.m. 14,7
804 (1) b Embankment (From Borrow) 1.51 144.96 cu.m. 59,0
804 (4) Gravel Fill 0.62 31.50 cu.m. 24,3
PART B PLAIN & REINFORCED CONCRETE WORKS
900 (1) c2 Structural Concrete (Footings and Slab on Fill) 7.87 61.67 cu.m. 307,2
900 (1) c3 Structural Concrete (Tie Beam) 0.47 3.34 cu.m. 18,2
900 (1) c5 Structural Concrete (Columns) 2.22 12.14 cu.m. 86,7
900 (1) c6 Structural Concrete (Beams/Girders) 1.71 9.69 cu.m. 66,9
902 (1)a1 Reinforcing Steel (Deformed, Grade 40) 11.54 6,001.34 kgs. 450,3
903 (1) Formworks and Falseworks 5.59 1.00 l.s. 218,3
DIVISION II - BUILDINGS
PART C FINISHING
1000(1) Soil Poisoning 0.11 20.00 liters 4,3
31.92 1,250,37
Prepared by:
CRISTOBAL B. LASLAS
Civil Engineer
Recommending Approval:
DENNIS S. OPIANO
OIC - Director, Physical Plant
Site Development
Prepared by:
CRISTOBAL B. LASLAS
Civil Engineer
Recommending Approval:
DENNIS S. OPIANO
OIC - Director, Physical Plant
Site Development
N. ELECTRICAL WORKS
1100 (30) Conduits, Boxes & Fittings 0.78 1.00 l.s. 30,4
1101 (42) Wires and Wiring Devices 4.94 1.00 l.s. 193,0
1102 (1) b1 Panelboard with Main & Branch Breakers 0.23 1.00 sets 9,0
1103 (6) a1 LED Tube Lighting Fixture 1.42 42.00 sets 55,2
26.91 1,050,64
SUB-TOTAL 3,810,00
100.00 TOTAL 3,904,15
Prepared by:
CRISTOBAL B. LASLAS
Civil Engineer
Recommending Approval:
DENNIS S. OPIANO
OIC - Director, Physical Plant
Site Development
JEREMIAS A. PASCUAL
Chief, Planning & Design Section
DPWH Representative
Approved:
JEREMIAS A. PASCUAL
Chief, Planning & Design Section
DPWH Representative
Approved:
1,050,644.88
3,810,007.52
3,904,150.06
JEREMIAS A. PASCUAL
Chief, Planning & Design Section
DPWH Representative
Approved:
% OF EQUIPMENT
DESCRIPTION OF WORKS TO BE DONE
TOTAL DESCRIPTION REQUIRED
PART II-OTHER GENERAL REQUIREMENTS 0.17
PART III-CIVIL, MECHANICAL, ELECTRICAL 0.83
AND SANITARY/PLUMBING WORKS
TOTAL 100.00%
ESTIMATED COST OF THE PROJECT
BREAKDOWN OF EXPENDITURE :
Prepared by :
CRISTOBAL B. LASLAS
Civil Engineer
Recommending Approval:
DENNIS S. OPIANO
OIC - Director, Physical Plant &
Site Development
Prepared by :
CRISTOBAL B. LASLAS
Civil Engineer
Recommending Approval:
DENNIS S. OPIANO
OIC - Director, Physical Plant &
Site Development
N. ELECTRICAL WORKS
1100 (30) Conduits, Boxes & Fittings 1.00 l.s. 30,430.00 12% 8% 20% 6,086.00
1101 (42) Wires and Wiring Devices 1.00 l.s. 193,005.00 12% 8% 20% 38,601.00
1102 (1) b1 Panelboard with Main & Branch Breakers 1.00 sets 9,075.20 12% 8% 20% 1,815.04
1103 (6) a1 LED Tube Lighting Fixture 42.00 sets 55,284.21 12% 8% 20% 11,056.84
###
Prepared by:
CRISTOBAL B. LASLAS
Civil Engineer
Recommending Approval:
DENNIS S. OPIANO
OIC - Director, Physical Plant &
Site Development
JEREMIAS A. PASCUAL
Chief, Planning & Design Section
DPWH Representative
Approved:
JEREMIAS A. PASCUAL
Chief, Planning & Design Section
DPWH Representative
Approved:
JEREMIAS A. PASCUAL
Chief, Planning & Design Section
DPWH Representative
Approved:
A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
A. SUB-TOTAL, EQUIPMENT ₱ -
B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Carpenter 2.00 5.50 ₱ 58.76 ₱ 646.36
C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
D6 (3 - 2.1m.x0.6m.) PVC Doors 3.78 sq.m. ₱ 3,500.00 ₱ 13,230.00
SUMMARY :
A. Equipment ₱ -
B. Labor ₱ 646.36
C. Materials ₱ 13,230.00
D. TOTAL DIRECT COST ₱ 13,876.36
DIRECT UNIT COST ₱ 5,506.49
E. OCM 12% of D ₱ 1,665.16
F. Profit 8% of D ₱ 1,110.11
G. VAT 5% of (D+E+F) ₱ 832.58
H. Total Cost (D+E+F+G) ₱ 17,484.21
I. Unit Cost H/Quantity ₱ 6,938.18
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino
A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
A. SUB-TOTAL, EQUIPMENT ₱ -
B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Construction Foreman 1.00 26.00 ₱ 81.30 ₱ 2,113.80
Mason 8.00 26.00 58.76 12,222.08
Laborer 4.00 26.00 45.25 4,706.00
C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
Factor
100mm × 200mm × 400mm CHB 12.500 2,054.00 pcs. ₱ 12.00 ₱ 24,648.00
Portland Cement (Class C) 0.759 125.00 bags 260.00 32,500.00
Fine Aggregates 0.084 14.00 cu.m. 579.52 8,113.28
10mm Ø × 6.00m. RSB 1,015.93 kgs. 40.00 40,637.20
Tie Wire (2% of RSB) 21.00 kgs. 65.00 1,365.00
SUMMARY :
A. Equipment ₱ -
B. Labor ₱ 19,041.88
C. Materials ₱ 107,263.48
D. TOTAL DIRECT COST ₱ 126,305.36
DIRECT UNIT COST ₱ 768.70
E. OCM 12% of D ₱ 15,156.64
F. Profit 8% of D ₱ 10,104.43
G. VAT 5% of (D+E+F) ₱ 7,578.32
H. Total Cost (D+E+F+G) ₱ 159,144.75
I. Unit Cost H/Quantity ₱ 968.56
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino
A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
A. SUB-TOTAL, EQUIPMENT ₱ -
B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Construction Foreman 1.00 16.17 ₱ 81.30 ₱ 1,314.35
Mason 8.00 48.50 58.76 22,798.88
Laborer 4.00 48.50 45.25 8,778.50
C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
Factor
125mm × 200mm × 400mm CHB 12.500 3,502.00 pcs. ₱ 14.00 ₱ 49,028.00
Portland Cement (Class C) 0.759 234.00 bags 260.00 60,840.00
Fine Aggregates 0.084 26.00 cu.m. 579.52 15,067.52
10mm Ø × 6.00m. RSB 131.26 kgs. 40.00 5,250.40
Tie Wire (2% of RSB) 3.00 kgs. 65.00 195.00
SUMMARY :
A. Equipment ₱ -
B. Labor ₱ 32,891.73
C. Materials ₱ 130,380.92
D. TOTAL DIRECT COST ₱ 163,272.65
DIRECT UNIT COST ₱ 530.11
E. OCM 12% of D ₱ 19,592.72
F. Profit 8% of D ₱ 13,061.81
G. VAT 5% of (D+E+F) ₱ 9,796.36
H. Total Cost (D+E+F+G) ₱ 205,723.54
I. Unit Cost H/Quantity ₱ 667.93
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino
A. Name and Capacity of Equipment (OperateNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Welding Machine 2.00 4.25 ₱ 62.50 ₱ 531.25
Electric Bar Cutter 2.00 4.25 158.25 1,345.13
B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Construction Foreman 1.00 1.42 ₱ 81.30 ₱ 115.18
Welder 12.00 4.25 58.76 2,996.76
Laborer 6.00 4.25 45.25 1,153.88
C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
50-5mmx50mmx 50mm angle bar 188.50 kgs. ₱ 70.00 ₱ 13,195.00
10-5mmx38mmx 38mm angle bar 28.17 70.00 1,971.90
14" Cutting Disk 2.00 sets 250.00 500.00
Welding Rod 60.00 kgs. 65.00 3,900.00
Oxygen 1.00 tanks 300.00 300.00
Acetylene 1.00 tanks 650.00 650.00
Red Lead Primer 1.00 gals. 400.00 400.00
Paint Thinner 1.00 gals. 190.00 190.00
Paint brush 2" 2.00 pcs. 60.00 120.00
SUMMARY :
A. Equipment ₱ 1,876.38
B. Labor ₱ 4,265.81
C. Materials ₱ 21,226.90
D. TOTAL DIRECT COST ₱ 27,369.09
DIRECT UNIT COST ₱ 126.32
E. OCM 12% of D ₱ 3,284.29
F. Profit 8% of D ₱ 2,189.53
G. VAT 5% of (D+E+F) ₱ 1,642.15
H. Total Cost (D+E+F+G) ₱ 34,485.05
I. Unit Cost H/Quantity ₱ 159.16
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino
B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Construction Foreman 1.00 13.50 ₱ 81.30 ₱ 1,097.55
Welder 4.00 40.50 58.76 9,519.12
Laborer 2.00 40.50 45.25 3,665.25
C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
SUMMARY :
A. Equipment ₱ 22,244.63
B. Labor ₱ 14,281.92
C. Materials ₱ 102,518.00
D. TOTAL DIRECT COST ₱ 139,044.55
DIRECT UNIT COST ₱ 95.41
E. OCM 12% of D ₱ 16,685.35
F. Profit 8% of D ₱ 11,123.56
G. VAT 5% of (D+E+F) ₱ 8,342.67
H. Total Cost (D+E+F+G) ₱ 175,196.13
I. Unit Cost H/Quantity ₱ 120.21
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino
A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
A. SUB-TOTAL, EQUIPMENT ₱ -
B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Tinsmith 2.00 12.00 58.76 1,410.24
Laborer 1.00 12.00 45.25 543.00
C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
16mm dia. x 300mm Long Bend Anchor Bolt 120.00 pcs. ₱ 35.00 ₱ 4,200.00
with Nuts and Washer
SUMMARY :
A. Equipment ₱ -
B. Labor ₱ 1,953.24
C. Materials ₱ 4,200.00
D. TOTAL DIRECT COST ₱ 6,153.24
DIRECT UNIT COST ₱ 51.28
E. OCM 12% of D ₱ 738.39
F. Profit 8% of D ₱ 492.26
G. VAT 5% of (D+E+F) ₱ 369.19
H. Total Cost (D+E+F+G) ₱ 7,753.08
I. Unit Cost H/Quantity ₱ 64.61
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino
A. Name and Capacity of Equipment (OperatNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
A. SUB-TOTAL, EQUIPMENT ₱ -
B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Welder 4.00 1.75 ₱ 58.76 ₱ 411.32
Laborer 2.00 1.75 45.25 158.38
C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
12mm dia. x 6m Plain Round Bar;Sag Rod 181.22 kgs. ₱ 40.00 ₱ 7,248.80
With Nuts and Washer
SUMMARY :
A. Equipment ₱ -
B. Labor ₱ 569.70
C. Materials ₱ 7,248.80
D. TOTAL DIRECT COST ₱ 7,818.50
DIRECT UNIT COST ₱ 229.96
E. OCM 12% of D ₱ 938.22
F. Profit 8% of D ₱ 625.48
G. VAT 5% of (D+E+F) ₱ 469.11
H. Total Cost (D+E+F+G) ₱ 9,851.30
I. Unit Cost H/Quantity ₱ 289.74
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino
A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
A. SUB-TOTAL, EQUIPMENT ₱ -
B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Skilled Labor 2.00 3.50 ₱ 58.76 ₱ 411.32
Laborer 1.00 3.50 45.25 158.38
C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
Turn Buckle; 16mm dia. 10.00 pcs. ₱ 185.00 ₱ 1,850.00
SUMMARY :
A. Equipment ₱ -
B. Labor ₱ 569.70
C. Materials ₱ 1,850.00
D. TOTAL DIRECT COST ₱ 2,419.70
DIRECT UNIT COST ₱ 241.97
E. OCM 12% of D ₱ 290.36
F. Profit 8% of D ₱ 193.58
G. VAT 5% of (D+E+F) ₱ 145.18
H. Total Cost (D+E+F+G) ₱ 3,048.82
I. Unit Cost H/Quantity ₱ 304.88
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino
A. Name and Capacity of Equipment (OperatNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
A. SUB-TOTAL, EQUIPMENT ₱ -
B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Welder 2.00 2.25 ₱ 58.76 ₱ 264.42
Laborer 1.00 2.25 45.25 101.81
C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
Cross Bracing; 16mm dia. x 6m. Plain Bar 33.28 kgs. ₱ 40.00 ₱ 1,331.20
SUMMARY :
A. Equipment ₱ -
B. Labor ₱ 366.23
C. Materials ₱ 1,331.20
D. TOTAL DIRECT COST ₱ 1,697.43
DIRECT UNIT COST ₱ 51.00
E. OCM 12% of D ₱ 203.69
F. Profit 8% of D ₱ 135.79
G. VAT 5% of (D+E+F) ₱ 101.85
H. Total Cost (D+E+F+G) ₱ 2,138.76
I. Unit Cost H/Quantity ₱ 64.27
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino
A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
A. SUB-TOTAL, EQUIPMENT ₱ -
B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Welder 2.00 31.25 ₱ 58.76 ₱ 3,672.50
Laborer 1.00 31.25 45.25 1,414.06
C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
Base Plate (10mm thk.) 226.08 kgs. ₱ 70.00 ₱ 15,825.60
SUMMARY :
A. Equipment ₱ -
B. Labor ₱ 5,086.56
C. Materials ₱ 15,825.60
D. TOTAL DIRECT COST ₱ 20,912.16
DIRECT UNIT COST ₱ 92.50
E. OCM 12% of D ₱ 2,509.46
F. Profit 8% of D ₱ 1,672.97
G. VAT 5% of (D+E+F) ₱ 1,254.73
H. Total Cost (D+E+F+G) ₱ 26,349.32
I. Unit Cost H/Quantity ₱ 116.55
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino
A. Name and Capacity of Equipment (OpeNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
A. SUB-TOTAL, EQUIPMENT ₱ -
B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Electrician 2.00 18.00 ₱
C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
Ceiling Receptacle Socket 4" dia 4.00 pcs ₱ 45.00 ₱ 180.00
Service Drop Wire twisted #2 100.00 meter 205.00 20,500.00
Entrance cap 75mm dia 1.00 pcs 200.00 200.00
PVC Junction Box 4x4 w/ cover 35.00 pcs 35.00 1,225.00
Utility Box Metal deep type 85.00 pcs 35.00 2,975.00
Moldflex 20mm x 100m 6.00 rolls 850.00 5,100.00
SUMMARY :
A. Equipment ₱ -
B. Labor ₱ 250.00
C. Materials ₱ 30,180.00
D. TOTAL DIRECT COST ₱ 30,430.00
DIRECT UNIT COST ₱ 30,430.00
E. OCM 12% of D ₱ 3,651.60
F. Profit 8% of D ₱ 2,434.40
G. VAT 5% of (D+E+F) ₱ 1,825.80
H. Total Cost (D+E+F+G) ₱ 38,341.80
I. Unit Cost H/Quantity ₱ 38,341.80
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino
A. SUB-TOTAL, EQUIPMENT ₱ -
B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Electrician 3.00 40.00
C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
Electric Wire 2.0mm² THHN 6.00 boxes ₱ 2,700.00 ₱ 16,200.00
Electric Wire3.5mm² THHN 7.00 boxes 3,300.00 23,100.00
Electric Wire 5.5mm² THHN 5.00 boxes 4,250.00 21,250.00
Electric Wire 50.0mm² THHN 60.00 mtrs 375.00 22,500.00
Duplex Convenience Outlets, Grounding Type 46.00 sets 150.00 6,900.00
Orbit fan Standard E-16 18.00 sets 1,200.00 21,600.00
Two Gang Single Pole Switch Wide Series 4.00 sets 155.00 620.00
One Gang Single Pole Switch Wide Series 5.00 sets 65.00 325.00
Three way, three gang switch w/ plate (widw 12.00 sets 195.00 2,340.00
Electrical Tape, Big 25.00 rolls 30.00 750.00
Ground Rod 5/8 x10' 1.00 pc 686.00 686.00
Ground Clamp 5/8 2.00 pcs 42.00 84.00
Service drop wire #04 Twisted 200.00 mtrs 120.00 24,000.00
Exhaust Fan 12" x 12" Ceiling Type 2.00 sets 1,200.00 2,400.00
SUMMARY :
A. Equipment ₱ -
B. Labor ₱ 50,250.00
C. Materials ₱ 142,755.00
D. TOTAL DIRECT COST ₱ 193,005.00
DIRECT UNIT COST ₱ 193,005.00
E. OCM 12% of D ₱ 23,160.60
F. Profit 8% of D ₱ 15,440.40
G. VAT 5% of (D+E+F) ₱ 11,580.30
H. Total Cost (D+E+F+G) ₱ 243,186.30
I. Unit Cost H/Quantity ₱ 243,186.30
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino
A. Name and Capacity of Equipment (OperateNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
A. SUB-TOTAL, EQUIPMENT ₱ -
B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Electrician 1.00 20.00 ₱ 58.76 ₱ 1,175.20
C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
Panel box Bolt on type, single phase, center main 1.00 assembly ₱ 500.00 ₱ 500.00
w/ 20 branches
1 pair Main Circuit Breaker 125 amp (GE) 1.00 pairs 1,000.00 1,000.00
6 pairs Branches Circuit Breaker 15 amp (GE) 6.00 pairs 320.00 1,920.00
5 pairs Branches Circuit Breaker 20 amp (GE) 5.00 pairs 320.00 1,600.00
9 pairs Branches Circuit Breaker 30 amp (GE) 9.00 pairs 320.00 2,880.00
SUMMARY :
A. Equipment ₱ -
B. Labor ₱ 1,175.20
C. Materials ₱ 7,900.00
D. TOTAL DIRECT COST ₱ 9,075.20
DIRECT UNIT COST ₱ 9,075.20
E. OCM 12% of D ₱ 1,089.02
F. Profit 8% of D ₱ 726.02
G. VAT 5% of (D+E+F) ₱ 544.51
H. Total Cost (D+E+F+G) ₱ 11,434.75
I. Unit Cost H/Quantity ₱ 11,434.75
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino
A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
A. SUB-TOTAL, EQUIPMENT ₱ -
B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Electrician 1.00 21.00 ₱ 58.76 ₱ 1,233.96
Laborer 1.00 21.00 45.25 950.25
C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
SUMMARY :
A. Equipment ₱ -
B. Labor ₱ 2,184.21
C. Materials ₱ 53,100.00
D. TOTAL DIRECT COST ₱ 55,284.21
DIRECT UNIT COST ₱ 1,316.29
E. OCM 12% of D ₱ 6,634.11
F. Profit 8% of D ₱ 4,422.74
G. VAT 5% of (D+E+F) ₱ 3,317.05
H. Total Cost (D+E+F+G) ₱ 69,658.10
I. Unit Cost H/Quantity ₱ 1,658.53
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino
oduction Output :
No. of Hrs. : hrs.
No. of Days : days
A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
A. SUB-TOTAL, EQUIPMENT ₱ -
B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Construction Foreman 1.00 24.00 ₱ 67.72 ₱ 1,625.28
Carpenter 2.00 24.00 56.64 2,718.72
Laborer 2.00 24.00 37.94 1,821.12
C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
Corrugated Roofing, Gauge 26 (0.40mm × 2.44m.) 38.65 sq.m. ₱ 250.00 ₱ 9,662.50
Assorted Lumber 362.00 bd.ft. 40.00 14,480.00
6mm × 4' × 8' Ordinary Plywood 7.00 pcs. 320.00 2,240.00
6mm × 4' × 8' Marine Plywood 16.00 pcs. 345.00 5,520.00
Assorted C.W. Nails 11.00 kgs. 60.00 660.00
SUMMARY :
A. Equipment ₱ -
B. Labor ₱ 6,165.12
C. Materials ₱ 32,562.50
D. TOTAL DIRECT COST ₱ 38,727.62
DIRECT UNIT COST ₱ 38,727.62
E. OCM 0% of D ₱ -
F. Profit 0% of D ₱ -
G. VAT 5% of (D+E+F) ₱ 1,936.38
H. Total Cost (D+E+F+G) ₱ 40,664.01
I. Unit Cost H/Quantity ₱ 40,664.01
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino
oduction Output :
No. of Hrs. : hrs.
No. of Days : days
A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
A. SUB-TOTAL, EQUIPMENT ₱ -
B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
B. SUB-TOTAL, LABOR ₱ -
C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
Office Desk 4.00 pcs. ₱ 2,450.00 ₱ 9,800.00
Swivel Chair 6.00 pcs. 1,100.00 6,600.00
Mono Block Chairs 6.00 pcs. 350.00 2,100.00
SUMMARY :
A. Equipment ₱ -
B. Labor ₱ -
C. Materials ₱ 18,500.00
D. TOTAL DIRECT COST ₱ 18,500.00
DIRECT UNIT COST ₱ 18,500.00
E. OCM 0% of D ₱ -
F. Profit 0% of D ₱ -
G. VAT 5% of (D+E+F) ₱ 925.00
H. Total Cost (D+E+F+G) ₱ 19,425.00
I. Unit Cost H/Quantity ₱ 19,425.00
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino
oduction Output :
No. of Hrs. : hrs.
No. of Days : days
A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
A. SUB-TOTAL, EQUIPMENT ₱ -
B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Carpenter 1.00 2.20 58.76 129.27
Laborer 1.00 2.20 45.25 99.55
C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
Billboard:
1/4"x 4"x 8' Plywood 1.00 pc. 350.00 350.00
Tarpaulin 1.00 pc. 1,300.00 1,300.00
C.W. Nails 0.50 kls. 60.00 30.00
Lumber materials:
4 - 2"x2"x 4' 5.33 bd.ft. 40.00 213.33
2 - 2"x2"x 8' 5.33 bd.ft. 40.00 213.33
2 - 2"x3"x 6' 6.00 bd.ft. 40.00 240.00
SUMMARY :
A. Equipment ₱ -
B. Labor ₱ 228.82
C. Materials ₱ 2,346.67
D. TOTAL DIRECT COST ₱ 2,575.49
DIRECT UNIT COST ₱ 2,575.49
E. OCM 12% of D ₱ 309.06
F. Profit 8% of D ₱ 206.04
G. VAT 5% of (D+E+F) ₱ 154.53
H. Total Cost (D+E+F+G) ₱ 3,245.12
I. Unit Cost H/Quantity ₱ 3,245.12
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino
oduction Output :
No. of Hrs. : hrs.
No. of Days : - days
A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
A. SUB-TOTAL, EQUIPMENT ₱ -
B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Safety Officer 1.00 50.00 ₱ 62.50 ₱ 3,125.00
C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
Safety Helmet 4,000.00 man-hours ₱ 7.68 ₱ 30,720.00
Safety Gloves 4,000.00 man-hours 0.31 1,240.00
Safety Shoes 4,000.00 man-hours 2.88 11,520.00
Medicine 1.00 l.s. 6,861.98
SUMMARY :
A. Equipment ₱ -
B. Labor ₱ 3,125.00
C. Materials ₱ 50,341.98
D. TOTAL DIRECT COST ₱ 53,466.98
DIRECT UNIT COST ₱ 7,638.14
E. OCM 0% of D ₱ -
F. Profit 0% of D ₱ -
G. VAT 5% of (D+E+F) ₱ 2,673.35
H. Total Cost (D+E+F+G) ₱ 56,140.33
I. Unit Cost H/Quantity ₱ 8,020.05
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino
oduction Output :
No. of Hrs. : hrs.
No. of Days : days
A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
1% of Civil Works 38,100.08
B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
B. SUB-TOTAL, LABOR ₱ -
C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
C. SUB-TOTAL, MATERIAL ₱ -
SUMMARY :
A. Equipment ₱ 38,100.08
B. Labor ₱ -
C. Materials ₱ -
D. TOTAL DIRECT COST ₱ 38,100.08
DIRECT UNIT COST ₱ 38,100.08
E. OCM 0% of D ₱ -
F. Profit 0% of D ₱ -
G. VAT 5% of (D+E+F) ₱ 1,905.00
H. Total Cost (D+E+F+G) ₱ 40,005.08
I. Unit Cost H/Quantity ₱ 40,005.08
FURNISHING OF AGGREGATES
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino
2. Hauling Cost
Dump Truck Travel Speed
Terrain Condition Road Condition
(kph)
Loaded Empty
Flat Paved 40 60
Unpaved 30 50
Rolling Paved 30 40
Unpaved 25 30
Mountainous Paved 25 30
Unpaved 15 20
1st Distance = 0.20 km. 1st Speed = 10.00 kph 1st Period = 1.20 min.
2nd Distance= 39.60 km. 2nd Speed = 30.00 kph 2nd Period = 79.20 min.
Last Distanc = 0.20 km. Last Speed = 15.00 kph Last Period = 0.80 min.
1st Distance = 0.20 km. 1st Speed = 10.00 kph 1st Period = 1.20 min.
2nd Distance= 39.60 km. 2nd Speed = 40.00 kph 2nd Period = 59.40 min.
Last Distanc = 0.20 km. Last Speed = 15.00 kph Last Period = 0.80 min.
Fine Aggregates:
Coarse Aggregates:
2. Hauling Cost
Dump Truck Travel Speed
Terrain Condition Road Condition
(kph)
Loaded Empty
Flat Paved 40 60
Unpaved 30 50
Rolling Paved 30 40
Unpaved 25 30
Mountainous Paved 25 30
Unpaved 15 20
1st Distance = 0.20 km. 1st Speed = 10.00 kph 1st Period = 1.20 min.
2nd Distance= 29.60 km. 2nd Speed = 30.00 kph 2nd Period = 59.20 min.
Last Distanc = 0.20 km. Last Speed = 15.00 kph Last Period = 0.80 min.
1st Distance = 0.20 km. 1st Speed = 10.00 kph 1st Period = 1.20 min.
2nd Distance= 29.60 km. 2nd Speed = 40.00 kph 2nd Period = 44.40 min.
Last Distanc = 0.20 km. Last Speed = 15.00 kph Last Period = 0.80 min.
FURNISHING OF BOULDERS
Source of Aggregate = SAN PEDRO site(km.) quary(km.)
Hauling Distance = 4 kms. 338 368
Grade =
Terrain = Mountainous loaded empty
Road Condition = Paved = 30 40
STOCKPILING AND LOADING:
capacity/man-day = 2 cu.m/day
P 278.60 /day
1 Stockpiling Cost = = P 139.3
2 cu.m./day
LOADING AND UNLOADING
capacity/ man-day to load = 2 cu.m./day at quarry
capacity/ man-day to unload = 3 cu.m./day
HAULING COST
Average Hauling Distance = 4 km.
Unload/Manuever = 60.0
uarry
/ cu.m.
min.
min.
min.
min.
min. at site
min.
min.
min.
min.
min.
Truck
/cu.m.
/cu.m.
/cu.m.
/cu.m.
47 375.84
36.2 289.68
Schedule of Construction Equipment
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino
Equipment
Part 187 of 1
Equipment
Part 188 of 1