Sie sind auf Seite 1von 188

DETAIL ABC DIFFERENCE

### ### 0.01


Err:509 Err:509 Err:509
### ### 0.01
### ### -
Err:509 Err:509 Err:509
Err:509 Err:509 Err:509

Err:509 Err:509 Err:509


10,000,000.00

Err:509
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino

Item No. : 506 (1) Quantity : 680.59


Description : Stone Masonry Unit : cu.m.

oduction Output : 6.2400 cu.m. /hr.


rd. Output/gang : 18.7200 cu.m. /hr.
No. of Hours : 36.50 hrs.
No. of Days : 4.75 days
No. of Gang : 3.00 gang

A. Name and Capacity of Equipment (Operated) No. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
One Bagger Mixer 1.00 36.50 ₱ 190.00 ₱ 6,935.00
Water Truck 1.00 36.50 1,065.00 38,872.50
Backhoe (Wheel Type 0.28 cu.m.) 1.00 36.50 840.00 30,660.00

A. SUB-TOTAL, EQUIPMENT ₱ 76,467.50

B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Construction Foreman 1.00 36.50 ₱ 67.72 ₱ 2,471.78
Skilled Laborer 3.00 36.50 56.64 6,202.08
Laborer 6.00 36.50 37.94 8,308.86

B. SUB-TOTAL, LABOR ₱ 16,982.72

C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
Portland Cement 5.50 3,743.25 bags ₱ 240.00 ₱ 898,378.80
Sand 0.30 204.18 cu.m. 579.52 118,324.66
Gravel Fill 0.02 13.61 cu.m. 603.64 8,216.63
Weep Holes 0.30 204.18 ln.m. 100.00 20,417.70
Filter Cloth 0.02 10.21 sq.m. 160.00 1,633.42
Boulders 1.05 714.62 cu.m. 793.71 567,200.64

C. SUB-TOTAL, MATERIAL ₱ 1,614,171.84

SUMMARY :
A. Equipment ₱ 76,467.50
B. Labor ₱ 16,982.72
C. Materials ₱ 1,614,171.84
D. TOTAL DIRECT COST ₱ 1,707,622.06
DIRECT UNIT COST ₱ 2,509.03
E. OCM 9.00 ₱ 153,685.99
F. Profit 8.00 ₱ 136,609.76
G. VAT 5% of (D+E+F) ₱ 99,895.89
H. Total Cost (D+E+F+G) ₱ 2,097,813.71
I. Unit Cost H/Quantity ₱ 3,082.35
ITEM NO. DESCRIPTION QUANTITY UNIT
A. EARTHWORKS

803 (1) a Structure Excavation (Common Soil)

Wall Footing (WF) Volume: 0.4 x x 0.65 x 24.7 = 6.42 cu.m.


SC Volume: 0.3 x 0.4 x 0.7 x 4 = 0.336 cu.m.
Septic Tank Volume: 3.2 x 1.2 x 1.3 = 4.992 cu.m.

done Total Volume = 11.75 cu.m.

804 (1) a Embankment (From Borrow)


Volume: 2.9 x 2.9 x 0.9 = 14.15 cu.m.
Room 01 Volume: 2.9 x 2.9 x 0.9 = 7.57 cu.m.
Room 02 Volume: 2.9 x 2.9 x 0.9 = 7.57 cu.m.
Stairs Volume: 0.9 x 1.5 x 0.9 x 2 = 2.43 cu.m.
0.8 x 0.8 x 0.9 x 2 = 1.15 cu.m.
done Total Volume 14.000 cu.m.

804 (4) Gravel Fill


Wall Footing (WF) Volume: 0.4 x 0.1 X 0.65 x 24.7 = 0.64 cu.m.
SC Volume: 0.4 x 0.15 X 0.1 x 4 = 0.024 cu.m.
Volume (CR & walkway) 0.1 x 1.2 X 6.7 = 0.80 cu.m.

0.1 x 4.2 X 3.7 = 1.55 cu.m.


Volume (Septic Tank) 0.1 x 3.2 X 1.2 = 0.38 cu.m.
done Total Volume = 3.41 cu.m.
B. CONCRETE WORKS
900 Reinforced Concrete

done (a) Wall Footing Volume: 0.4 x 0.20 x 24.7 = 1.976 cu.m.
done (b) Slab on Fill(stage) Volume: 5.5 x 9.9 x 0.1 = 5.445 cu.m.
(b) Slab on Fill(rm01) Volume: 2.9 x 2.9 x 0.1 = 0.841 cu.m.
(b) Slab on Fill(rm02) Volume: 2.9 x 2.9 x 0.1 = 0.841 cu.m.
done (c) Beam Volume: 0.25 x 0.30 x 30.85 = 2.314 cu.m.
done (d) Column Volume: 0.25 x 0.30 x 5 = 0.38 cu.m. x 9.00 =
done (d) SC Volume: 0.15 x 0.40 x 3.4 = 0.204 cu.m. x 4.00 =
0.4 x 0.50 x 0.25 = 0.05 cu.m. x 9.00 =
done (d) Footing Volume: 1 x 1.00 x 0.25 = 0.25 cu.m. x 9.00 =
done (e ) Footing Tie Beam Volume: 0.2 x 0.30 x 39.45 = 2.37 cu.m.
done (e ) Corbel Volume: 0.25 x 0.30 x 0.3 = 0.02 x 2 =
done (e ) Stairs Volume: 1 x 1.70 x 0.15 = 0.26 x 4 =
0.2 x 0.15 x 2 = x 1 x
0.1 x 0.30 x 1 = 0.03 x 4 =
(e ) Stairs Volume: 0.1 x 1.00 x 1.5 = 0.15 x 2 =

total slab Volume: 5.99 cu.m.


total column&sc Volume: 4.236 cu.m.
total beam&corbel Volume: 2.36 cu.m.

C. REINFORCING STEEL WORKS


902 Reinforcing Steel

done (a) Wall Footing Spacing: 0.3m ; 10mm dia.


Estimating Transvers Bars
Total Length of Footing Number of
=
Spacing of Bars x Transverse Bars Available from Full-Length Bar F/L Bars Required
49.4
= 6.86 pcs say
7.2

3-10mm dia. Continuous Bar


Estimating Longitudinal Bars
Total Length of Footing x No. of Longitudinal Bars Number of
=
Selected Length of Full-Length Bars F/L Bars Required

148.2
= 24.7 pcs say
6

33 x 3.7 122.10 kgs.

done (b) Slab on Fill Spacing: 0.3m ; 10mm dia.


Long Span = 30 @ 50 = 1500 m
Short Span = 15 @ 100 = 1500 m
3000 m = 500 pcs say

500 x 3.70017 1,850.08 kgs.

done (c) Beam Main Bars: 6-20mm dia.


Length = 184.45 @ 4 = 737.80 m = 122.96667 pcs say

123 x 14.8 1,820.40 kgs.


Cut Bars: 16mm dia. = 293.65 kgs.
2,114.05

Stirrups: 10mm dia. = 769.63 kgs.


2,883.68 kgs.

done (d) Column Main Bars: 8-16mm dia. # of Columns


Length = 4.7 @ 8 = 37.60 m x 32 = 1203.2
= 1,203.20 / 6

say 201.00 x 9.47243 1,903.96 kgs.

Ties: 10mm dia.

= 514.32 kgs.
2,418.28 kgs.

done (e) Column Footing Spacing: 6-16mm dia. Equally spaced both ways

Estimating Transvers Bars


Total Number of Footing Bars Number of
=
Footing Bars Available from F/L Bar F/L Bars Required

384
= 76.8 pcs say
5

77 x 9.47243 729.38 kgs.

done (f) Footing Tie Beam Main Bars: 6-16mm dia.


Length = 163.35 @ 6 = 980.10 m = 163.35 pcs say
164 x 9.47243 1,553.48 kgs.
Web Bars Continuous 12mm dia. = 293.05 kgs. 163.3
1,846.53 54.43333
55
Stirrups: 10mm dia. = 703.03 kgs.
2,549.56 kgs.

D. FORMS AND FALSEWORKS


903 (1) Forms and Falseworks
Form Lumber 2" x 2"
(c) Beam Volume: 0.25 x 0.30 x 30.85 = 2.31 cu.m.
(d) Column Volume: 0.25 x 0.30 x 5 = 0.38 cu.m. x 9.00 =
(c) Tie Beam Volume: 0.2 x 0.30 x 30.85 = 1.85 cu.m.
7.54
Total Volume = all l.s.

h
Form Lumber 2" x 2" 1.20 x 5 x 32 = 192.00 sq.m. Size of
Column
192.00 / 2.88 = 67.00 pcs. of plywood Wood
67 x 29.67 = 1,987.89 bd.ft. Frame
2" x 2"
2" x 3"
1.20 x 30.85 = 37.02 sq.m.
Beam
37 / 2.88 = 13 pcs. of plywood
13.00 x 11.70 = 122 bd.ft.
1.20 x 39.45 = 47.34 sq.m.
Tie Beam
47 / 2.88 = 17 pcs. of plywood
17.00 x 29.67 = 504 bd.ft.

done Total 2,613.96 bd.ft. 97.00 pcs. of plywood

Staking 2" x 2" Length 18 + 5.5 x 2 = 29.40 = 30 m


30 x 6.10 = 183.00 bd.ft.

Column
Scaffoldings 2" x 3" 5.00 x 32 = 160 m
Length
Vert. 160 x 7.00 = 1,120.00 bd.ft. Lumber Column
Hor. 160 x 31.67 = 5,067 bd.ft. Board Ft. per M. H
Size
8,987 bd.ft. Vert.
Brace 160 x 17.50 = 2,800 bd.ft. 2" x 2" 4.70
2" x 3" 7.00
Beam
31 = 31 2" x 4" 9.35
Length
Vert. 31 x 6.00 = 185 bd.ft.
Hor. 31 x 7.00 = 216 bd.ft.
401 bd.ft.

Tie Beam
39 = 39
Length

Vert. 39 x 6.00 = 237 bd.ft.


Hor. 39 x 7.00 = 276 bd.ft.
513 bd.ft.
done Total 3,714 bd.ft.

E. TERMITE CONTROL WORK


1000 (1) Soil Poisoning
Area with additional Area: 27.5 x 14.5 = 398.75 sq.m.
1.5 outside

558.00 x 4 ÷ 50 = 44.64 liters

F. PLUMBING WORKS/SANITARY WORKS


1001 (8) Sewer Line Works
100mm Ø × 3.00 m. uPVC Pipe 32.00 pcs.
100mm dia 1/8 Bend PVC Elbow 5.00 pcs.
100mm dia 1/4 Bend PVC 6.00 pcs.
100mm x 100mm Ø uPVC Sanitary Tee 15.00 pcs.
100mm Ø uPVC Clean out with Plug & Seal Ring 5.00 pcs.
100mm Ø uPVC Coupling 5.00 pcs.
100mm dia. x 75mm dia. PVC Reducer-Sanitary Tee 8.00 pcs.
100mm Ø uPVC P-trap w/ plug 6.00 pcs.
75mm Ø × 3.00 m. uPVC Pipe 26.00 pcs.
75mm x 75mm Ø uPVC Tee 6.00 pcs.
75mm dia 1/4 Bend PVC Elbow 2.00 pcs.
75mm x 75mm Ø uPVC Cross Tee 1.00 pc.
Solvent Cement 10.00 cans
PVC Pipe Cement 3.00 cans
100mm x 3.2mm x 3m PVC Pipe 15.00 pcs.
100mm Bend 87 deg 20.00 pcs.
1006 (1) Catch Basin
Excavation Volume 0.6 x 0.6 x 0.55 = 0.198 x 14 = 2.772 cu.m.

CHB qtty area of pipe with qtty


CB1 Area 0.4 x 0.6 x 4 = 0.96 - 0.01900664 = 0.9409934 x 1
CB2 Area 0.4 x 0.6 x 4 = 0.96 - 0.01900664 = 0.9409934 x 8
CB3 Area 0.4 x 0.6 x 4 = 0.96 - 0.02850995 = 0.93149 x 4
CB4 Area 0.4 x 0.6 x 4 = 0.96 - 0.00950332 = 0.9504967 x 1

13.15 x 12.5 = 164.32 say 170

RSB
Length 0.5 x 6 = 3
0.5 x 3 x 4 = 6
0.5 x 8 = 4
13 x 1.1 = 14.3
CB1 14.3 x 1 = 14.3
CB2 14.3 x 8 = 114.4
CB3 14.3 x 4 = 57.2
CB4 14.3 x 1 = 14.3
200.2 x 0.6167 = 123.462266508 kgs.

Concrete Bottom Volume 0.6 x 0.6 x 0.1 = 0.036 x 14 = 0.504 cu.m


Top Volume 0.5 x 0.5 x 0.1 = 0.025 x 14 = 0.35 cu.m
Total 0.854 cu.m
faces
Plastering
Volume 0.4 x 0.4 x 0.02 = 0.0032 x 4 = 0.0128 x 14
inside

Pipe 110mm dia. uPVC


Length 89 + 12 = 101 / 3 = 33.6666666667 say 34

200mm dia. uPVC


Length 5 = 5 / 3 = 1.6666666667 say 2

G. CARPENTRY AND JOINERY WORKS


1003 (1) a1 Ceiling (4.5mm thick, Metal Frame) sq.m.

1003 (5) a2 Fascia Board (Lumber) m

1003 (7) a1 Moulding (Cornice,Wood) 181 m


H. FABRICATED MATERIALS AND HARDWARE
1004 (2) a Finishing Hardware (Lockset) set

Name Description Quantity w x h Area height width


Clear Glass on
D1 1 = 1.8 x 2.1 = 3.78 2 2
Analok Frame
Clear Glass on
D2 1 1.6 x 2.1 = 3.36 12 3
Analok Frame =
D3 Panel Type Door 9 = 0.9 x 2.1 = 17.01 8 2
D4 uPVC Door 3 = 0.8 x 2.1 = 5.04 12 3
Total 14 29.19 34 10

1004 (2) g Finishing Hardware (Hinges) set


12 x 4 = 48

1007 (1) b Aluminum Glass Door (Swing Type) sq.m.


Clear Glass on
D1 1 = 1.8 x 2.1 = 3.78
Analok Frame
Clear Glass on
D2 1 = 1.6 x 2.1 = 3.36
Analok Frame
7.14 sq.m.

1008
Aluminum
(1) a Glass Windows (Sliding Type) sq.m.
Name Description Quantity w x h Area
W1 Analok Sliding Type 3 = 3 x 1.2 = 10.8 Summary
Sliding
W2 Analok Sliding Type 3 2.5 x 1.2 = 41.4 sq.m.
= 9 Type
Awning
W3 Analok Sliding Type 9 2 x 1.2 = 3.05 sq.m.
= 21.6 Type
W4 Analok Awning Type 2 = 0.8 x 0.5 = 0.8
W5 Analok Awning Type 1 = 2 x 0.5 = 1
W6 Analok Awning Type 1 = 2.5 x 0.5 = 1.25
Total 19 44.45

1008
Aluminum
(1) c Glass Windows (Awning Type)

1010 (1) Frames set


Doors 14
Windows 19
Total 33

1010 (2) a Doors (Flush) sq.m.


D2 Flush Type Door 6 = 0.9 x 2.1 = 11.34

1010 (2) b Doors (Wood Panel) sq.m.


D3 Panel Type Door 9 = 0.9 x 2.1 = 17.01

I. ROOFING WORKS

L: 6.71
width 18.40
min.width of panel 1.01
Area: 123.464 say
123.46 sq.m
Area: 58.8
Area: 182.26 sq.m
J. FINISHING WORKS

1027 (1) Cement Plaster Finish sq.m.


Wall 286.22 x 2 = 572.44
Beam 10.2
Column 3.36 sq.m
Total 586.00

additional 10%
586.00 x 1.1 = 644.60 sq.m
waste Factor

K. PAINTING WORKS
1032 (1) a1 Painting Works (Masonry, Concrete) sq.m.

Total 644.60

Flat Latex
Paint
1st Coating 22 gals
2nd Coating 19 gals
Total 41 gals
Gloss Latex
Paint
1st Coating 19 gals
2nd Coating 26 gals
Total 45 gals

1032 (1) a2 Painting Works (Wood) sq.m.

1032 (1) a3 Painting Works (Steel) sq.m.

L. MASONRY WORKS
1046 (2) a Masonry Works (100mm thick CHB)
Area:
CHB
= - sq.m.
done = - sq.m.
= - sq.m.
Total Area = 127.22 sq.m.
127.22 sq.m. x 12.5 =
Reinforcing Steel Bars

By Area Method
Vertical Reinforcement Spacing: 0.60m ; 10mm dia.

Lv = 127.22 sq.m. × 2.13 = 270.98

Horizontal Reinforcement Spacing: 0.60m ; 10mm dia.


Lh = 127.22 sq.m. × 2.15 = 273.52 m/m²
544.50 m

Total 91.00 x 3.70 = 336.70 kgs 10.10 346.80 kgs

1046 (2) b Masonry Works (150mm thick CHB)

CHB
= - sq.m.
= - sq.m.
= - sq.m.
Total Area = 272.00 sq.m.
272.00 sq.m. x 12.5 =
Reinforcing Steel Bars

By Area Method
Vertical Reinforcement Spacing: 0.60m ; 10mm dia.

Lv = 272.00 sq.m. × 2.13 = 579.36

Horizontal Reinforcement Spacing: 0.60m ; 10mm dia.


Lh = 272.00 sq.m. × 2.15 = 584.80 m/m²
1,164.16 m

Total 195.00 x 3.70 = 721.50 kgs 21.65 743.15 kgs

M. METAL STRUCTURES

Total Waste
Canal Lining
Length Factor
No. of Longitudinal ÷
7 x 72.5 = 507.5 x 1.1 = 558.25 6
RSB

Spacing 0.30 m

No. of Transverse ÷
72.5 0.3 = 241.66666667 plus 1 pc. 301 x 2 = 602 m
RSB

volume of concrete 13.78


3.42 cu.m.
0.816 cu.m.
0.45 cu.m.
2.25 cu.m.

0.05 cu.m.
1.02 cu.m.
20.00 =
0.12 cu.m.
0.30 cu.m.
7 pcs

25 pcs

32

500 pcs

123 pcs
m
= 200.53

77 pcs

164 pcs
@ 2
pcs. say
x 5.32824167

3.375 cu.m.

Thickness of Plywood Form


Column
6mm (1/4")1 2mm (1/2")
29.67 25.06
44.50 30.50
Column
Board Ft. per M. Ht.
Hor. Brace
21.00 11.70
31.67 17.50

42.25 23.35
0.94
7.53
3.73
0.95
13.15
= 0.1792

pcs

pcs
1590.25 say

adopted

adopted

3400.00 say

adopted
adopted

= 93.0416667

602 ÷

101 x
1.20 cu.m.
CABUA-AN
pcs
= 326.6
55
= 293.053292

hickness of Plywood Form


Beam
6mm (1/4") 12mm (1/2")
11.70 4.00
37.60 28.00
Beam
Board Ft. per M. Ht. Board
Ft. per
Vert. Hor. Sq.M.
4.00 4.70 6.10
6.00 7.00 9.10

8.00 9.35 12.10


cu.m.
1590 pcs
47.7
1,638.00 pcs

3400 pcs
102
3,502.00 pcs
pcs. say 94

6 = 100.3333 say 101 pcs

3.70016783 = 373.717 kgs.


DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino

Item No. : 801 (1) Quantity : 1.00


Description : Removal of Structures and Obstruction Unit : l.s to be demolished:
5.00 col. = 0.2
rd. Output/gang : l.s /hr.
oduction Output : l.s /hr.
No. of Hours : hrs.
No. of Days : days
No. of Gang : gang

A. Name and Capacity of Equipment (OperateNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)

A. SUB-TOTAL, EQUIPMENT ₱ -

B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Laborer 2.00 16.00 P 45.25 P 1,448.00 32.00

B. SUB-TOTAL, LABOR ₱ 1,448.00

C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)

C. SUB-TOTAL, MATERIAL ₱ -

SUMMARY :
A. Equipment ₱ -
B. Labor ₱ 1,448.00
C. Materials ₱ -
D. TOTAL DIRECT COST ₱ 1,448.00
DIRECT UNIT COST ₱ 1,448.00
E. OCM 12% of D ₱ 130.32
F. Profit 8% of D ₱ 115.84
G. VAT 5% of (D+E+F) ₱ 84.71
H. Total Cost (D+E+F+G) ₱ 1,778.87
I. Unit Cost H/Quantity ₱ 1,778.87
to be demolished:
x 0.2 x 4 = 0.16
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino

Item No. : 803 (1) a Quantity : 81.35


Description : Structure Excavation (Common Soil) Unit : cu.m.
(Septic Tank & CR)
rd. Output/gang : 0.5000 cu.m. /hr.
oduction Output : 1.0000 cu.m. /hr.
No. of Hours : 81.50 hrs.
No. of Days : 10.25 days
No. of Gang : 2.00 gang

A. Name and Capacity of Equipment (OperateNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)

A. SUB-TOTAL, EQUIPMENT ₱ -

B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Laborer 4.00 81.50 45.25 14,751.50

B. SUB-TOTAL, LABOR ₱ 14,751.50

C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
Factor

C. SUB-TOTAL, MATERIAL ₱ -

SUMMARY :
A. Equipment ₱ -
B. Labor ₱ 14,751.50
C. Materials ₱ -
D. TOTAL DIRECT COST ₱ 14,751.50
DIRECT UNIT COST ₱ 181.33
E. OCM 12% of D ₱ 1,770.18
F. Profit 8% of D ₱ 1,180.12
G. VAT 5% of (D+E+F) ₱ 885.09
H. Total Cost (D+E+F+G) ₱ 18,586.89
I. Unit Cost H/Quantity ₱ 228.48
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino

Item No. : 804 (1) b Quantity : 144.96


Description : Embankment (From Borrow) Unit : cu.m.

rd. Output/gang : 1.0400 cu.m. /hr.


oduction Output : 3.1200 cu.m. /hr.
No. of Hours : 46.50 hrs.
No. of Days : 6.00 days
No. of Gang : 3.00 gang

A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)

A. SUB-TOTAL, EQUIPMENT ₱ -

B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Foreman 4.00 46.50 ₱ 81.30 ₱ 15,121.80
Laborer 4.00 46.50 ₱ 45.25 ₱ 8,416.50

B. SUB-TOTAL, LABOR ₱ 23,538.30

C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)

Selected Borrow
(w/ 15% shrinkage factor 1.15 166.70 cu.m. 213.00 35,507.95

C. SUB-TOTAL, MATERIAL ₱ 35,507.95

SUMMARY :
A. Equipment ₱ -
B. Labor ₱ 23,538.30
C. Materials ₱ 35,507.95
D. TOTAL DIRECT COST ₱ 59,046.25
DIRECT UNIT COST ₱ 407.33
E. OCM 12% of D ₱ 7,085.55
F. Profit 8% of D ₱ 4,723.70
G. VAT 5% of (D+E+F) ₱ 3,542.78
H. Total Cost (D+E+F+G) ₱ 74,398.28
I. Unit Cost H/Quantity ₱ 513.23
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino

Item No. : 804 (4) Quantity : 31.50


Description : Gravel Fill Unit : cu.m.

rd. Output/gang : 2.3650 cu.m. /hr.


oduction Output : 2.3650 cu.m. /hr.
No. of Hours : 13.50 hrs.
No. of Days : 1.75 days
No. of Gang : 1.00 gang

A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)

A. SUB-TOTAL, EQUIPMENT ₱ -

B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Laborer 4.00 13.50 ₱ 45.25 ₱ 2,443.50

B. SUB-TOTAL, LABOR ₱ 2,443.50

C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
Factor
Coarse Aggregates 1.150 36.23 cu.m. ₱ 603.64 ₱ 21,866.86

Note : Gravel Fill is 100mm thick

C. SUB-TOTAL, MATERIAL ₱ 21,866.86

SUMMARY :
A. Equipment ₱ -
B. Labor ₱ 2,443.50
C. Materials ₱ 21,866.86
D. TOTAL DIRECT COST ₱ 24,310.36
DIRECT UNIT COST ₱ 771.76
E. OCM 12% of D ₱ 2,917.24
F. Profit 8% of D ₱ 1,944.83
G. VAT 5% of (D+E+F) ₱ 1,458.62
H. Total Cost (D+E+F+G) ₱ 30,631.05
I. Unit Cost H/Quantity ₱ 972.41
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino

Item No. : 900 (1) c1 Quantity : 3.35


Description : Structural Concrete Unit : cu.m.

rd. Output/gang : 0.2565 cu.m /hr.


oduction Output : 0.5130 cu.m /hr.
No. of Hours : 6.75 hrs.
No. of Days : 1.00 days
No. of Gang : 2.00 gang

A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
One Bagger Mixer 1.00 6.75 ₱ 172.00 ₱ 1,161.00

A. SUB-TOTAL, EQUIPMENT ₱

B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)

Construction Foreman 1.00 6.75 ₱ 81.30 ₱ 548.78


Mason 4.00 6.75 58.76 1,586.52
Laborer 4.00 6.75 45.25 1,221.75

B. SUB-TOTAL, LABOR ₱

C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
Factor
Stairs
Portland Cement 9.500 32.00 bags ₱ 260.00 ₱ 8,320.00
Fine Aggregates 0.450 2.00 cu.m. 579.52 1,159.04
Crushed Aggregates 0.900 4.00 cu.m. 820.40 3,281.60

C. SUB-TOTAL, MATERIAL ₱

SUMMARY :
A. Equipment ₱
B. Labor ₱
C. Materials ₱
D. TOTAL DIRECT COST ₱ -
DIRECT UNIT COST ₱ -
E. OCM 12% of D ₱ -
F. Profit 8% of D ₱ -
G. VAT 5% of (D+E+F) ₱ -
H. Total Cost (D+E+F+G) ₱ -
I. Unit Cost H/Quantity ₱ -
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino

Item No. : 900 (1) c2 Quantity : 61.67


Description : Structural Concrete (Footings and Slab on Fill) Unit : cu.m.

Slab on Fill Footing


rd. Output/gang : 0.2565 cu.m /hr. 0.2050 cu.m /hr.
oduction Output : 0.5130 cu.m /hr. 0.4100 cu.m /hr. Footing = 14.19
No. of Hours : 92.75 hrs. 34.75 hrs. Slab on Fill = 47.48
No. of Days : 11.75 days 4.50 days 61.67
No. of Gang : 2.00 gang 2.00 gang

tal No. of Hours : 127.50 hrs. Total No. of Days : 16.25 days

A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
One Bagger Mixer 1.00 127.50 ₱ 172.00 ₱ 21,930.00
Concrete Vibrator 1.00 127.50 ₱ 56.00 ₱ 7,140.00
A. SUB-TOTAL, EQUIPMENT ₱ 29,070.00

B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Slab on Fill
Construction Foreman 1.00 92.75 ₱ 81.30 ₱ 7,540.58
Mason 4.00 92.75 58.76 21,799.96
Laborer 4.00 92.75 45.25 16,787.75
Footing
Construction Foreman 1.00 34.75 81.30 2,825.18
Mason 4.00 34.75 58.76 8,167.64
Laborer 4.00 34.75 45.25 6,289.75
B. SUB-TOTAL, LABOR ₱ 63,410.85

C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
Factor
Footing
Portland Cement 9.500 135.00 bags ₱ 260.00 ₱ 35,100.00
Fine Aggregates 0.420 6.00 cu.m. 579.52 3,477.12
Crushed Aggregates 0.851 13.00 cu.m. 820.40 10,665.20
Slab on Fill
Portland Cement 9.500 452.00 bags ₱ 260.00 ₱ 117,520.00
Fine Aggregates 0.450 22.00 cu.m. 579.52 12,749.44
Crushed Aggregates 0.900 43.00 cu.m. 820.40 35,277.20
C. SUB-TOTAL, MATERIAL ₱ 214,788.96

SUMMARY :
A. Equipment ₱ 29,070.00
B. Labor ₱ 63,410.85
C. Materials ₱ 214,788.96
D. TOTAL DIRECT COST ₱ 307,269.81
DIRECT UNIT COST ₱ 4,982.48
E. OCM 12% of D ₱ 36,872.38
F. Profit 8% of D ₱ 24,581.58
G. VAT 5% of (D+E+F) ₱ 18,436.19
H. Total Cost (D+E+F+G) ₱ 387,159.96
I. Unit Cost H/Quantity ₱ 6,277.93
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino

Item No. : 900 (1) c3 Quantity : 3.34


Description : Structural Concrete (Tie Beam) Unit : cu.m.

rd. Output/gang : 0.1835 cu.m. /hr.


oduction Output : 0.3670 cu.m. /hr.
No. of Hours : 9.25 hrs.
No. of Days : 1.25 days
No. of Gang : 2.00 gang

A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
One Bagger Mixer 1.00 9.25 ₱ 172.00 ₱ 1,591.00
One Bagger Mixer 1.00 9.25 ₱ 56.00 ₱ 518.00

A. SUB-TOTAL, EQUIPMENT ₱ 2,109.00

B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Construction Foreman 1.00 4.63 ₱ 81.30 ₱ 376.01
Mason 4.00 9.25 58.76 2,174.12
Laborer 4.00 9.25 45.25 1,674.25

B. SUB-TOTAL, LABOR ₱ 4,224.38

C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
Factor
Portland Cement 9.500 32.00 bags ₱ 260.00 ₱ 8,320.00
Fine Aggregates 0.425 2.00 cu.m. 579.52 1,159.04
Crushed Aggregates 0.850 3.00 cu.m. 820.40 2,461.20

C. SUB-TOTAL, MATERIAL ₱ 11,940.24

SUMMARY :
A. Equipment ₱ 2,109.00
B. Labor ₱ 4,224.38
C. Materials ₱ 11,940.24
D. TOTAL DIRECT COST ₱ 18,273.62
DIRECT UNIT COST ₱ 5,471.14
E. OCM 12% of D ₱ 2,192.83
F. Profit 8% of D ₱ 1,461.89
G. VAT 5% of (D+E+F) ₱ 1,096.42
H. Total Cost (D+E+F+G) ₱ 23,024.76
I. Unit Cost H/Quantity ₱ 6,893.64
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino

Item No. : 900 (1) c4 Quantity : 22.250


Description : Structural Concrete (Suspended Slab) Unit : cu.m.

rd. Output/gang : 0.1000 cu.m. /hr.


oduction Output : 0.2000 cu.m. /hr.
No. of Hours : 111.25 hrs.
No. of Days : 14.00 days
No. of Gang : 2.00 gang

A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
One Bagger Mixer 1.00 111.25 ₱ 172.00 ₱ 19,135.00
Concrete Vibrator 1.00 111.25 ₱ 56.00 ₱ 6,230.00

A. SUB-TOTAL, EQUIPMENT ₱

B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Construction Foreman 1.00 111.25 ₱ 81.30 ₱ 9,044.63
Mason 4.00 111.25 58.76 26,148.20
Laborer 4.00 111.25 45.25 20,136.25

B. SUB-TOTAL, LABOR ₱

C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
Factor
Portland Cement 9.500 212.00 bags ₱ 260.00 ₱ 55,120.00
Fine Aggregates 0.429 10.00 cu.m. 579.52 5,795.20
Crushed Aggregates 0.852 19.00 cu.m. 820.40 15,587.60

C. SUB-TOTAL, MATERIAL ₱

SUMMARY :
A. Equipment ₱ -
B. Labor ₱ -
C. Materials ₱ -
D. TOTAL DIRECT COST ₱ -
DIRECT UNIT COST ₱ -
E. OCM 12% of D ₱ -
F. Profit 8% of D ₱ -
G. VAT 5% of (D+E+F) ₱ -
H. Total Cost (D+E+F+G) ₱ -
I. Unit Cost H/Quantity ₱ -
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino

Item No. : 900 (1) c5 Quantity : 12.140


Description : Structural Concrete (Columns) Unit : cu.m.

rd. Output/gang : 0.1000 cu.m. /hr.


oduction Output : 0.2000 cu.m. /hr.
No. of Hours : 60.75 hrs.
No. of Days : 7.75 days
No. of Gang : 2.00 gang

A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
One Bagger Mixer 1.00 60.75 ₱ 172.00 ₱ 10,449.00
Concrete Vibrator 1.00 60.75 ₱ 56.00 ₱ 3,402.00

A. SUB-TOTAL, EQUIPMENT ₱ 13,851.00

B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Construction Foreman 1.00 60.75 ₱ 81.30 ₱ 4,938.98
Mason 4.00 60.75 58.76 14,278.68
Laborer 4.00 60.75 45.25 10,995.75

B. SUB-TOTAL, LABOR ₱ 30,213.41

C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
Factor
Portland Cement 9.500 116.00 bags ₱ 260.00 ₱ 30,160.00
Fine Aggregates 0.429 6.00 cu.m. 579.52 3,477.12
Crushed Aggregates 0.852 11.00 cu.m. 820.40 9,024.40

C. SUB-TOTAL, MATERIAL ₱ 42,661.52

SUMMARY :
A. Equipment ₱ 13,851.00
B. Labor ₱ 30,213.41
C. Materials ₱ 42,661.52
D. TOTAL DIRECT COST ₱ 86,725.93
DIRECT UNIT COST ₱ 7,143.82
E. OCM 12% of D ₱ 10,407.11
F. Profit 8% of D ₱ 6,938.07
G. VAT 5% of (D+E+F) ₱ 5,203.56
H. Total Cost (D+E+F+G) ₱ 109,274.67
I. Unit Cost H/Quantity ₱ 9,001.21
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino

Item No. : 900 (1) c6 Quantity : 9.690


Description : Structural Concrete (Beams/Girders) Unit : cu.m.

rd. Output/gang : 0.1000 cu.m. /hr.


oduction Output : 0.2000 cu.m. /hr.
No. of Hours : 48.50 hrs.
No. of Days : 6.25 days
No. of Gang : 2.00 gang

A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
One Bagger Mixer 1.00 48.50 ₱ 172.00 ₱ 8,342.00

A. SUB-TOTAL, EQUIPMENT ₱ 8,342.00

B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Construction Foreman 1.00 48.50 ₱ 81.30 ₱ 3,943.05
Mason 4.00 48.50 58.76 11,399.44
Laborer 4.00 48.50 45.25 8,778.50

B. SUB-TOTAL, LABOR ₱ 24,120.99

C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
Factor
Portland Cement 9.500 93.00 bags ₱ 260.00 ₱ 24,180.00
Fine Aggregates 0.429 5.00 cu.m. 579.52 2,897.60
Crushed Aggregates 0.852 9.00 cu.m. 820.40 7,383.60

C. SUB-TOTAL, MATERIAL ₱ 34,461.20

SUMMARY :
A. Equipment ₱ 8,342.00
B. Labor ₱ 24,120.99
C. Materials ₱ 34,461.20
D. TOTAL DIRECT COST ₱ 66,924.19
DIRECT UNIT COST ₱ 6,906.52
E. OCM 12% of D ₱ 8,030.90
F. Profit 8% of D ₱ 5,353.94
G. VAT 5% of (D+E+F) ₱ 4,015.45
H. Total Cost (D+E+F+G) ₱ 84,324.48
I. Unit Cost H/Quantity ₱ 8,702.22
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino

Item No. : 902 (1)a1 Quantity : 6,001.34


Description : Reinforcing Steel (Deformed, Grade 40) Unit : kgs.

Slab on Fill Beams


rd. Output/gang : 9.9300 kgs. /hr. 14.0400 kgs. /hr. Footing Tie Beam = 688.98
oduction Output : 29.790 kgs. /hr. 28.080 kgs. /hr. Wall Footing &Column Footing = 653.61
No. of Hours : 47.50 hrs. 26.25 hrs. Slab on Fill = 1,413.40
No. of Days : 6.00 days 3.50 days Septic Tank = 162.80
No. of Gang : 3.00 gang 2.00 gang Beam = 736.92
Column = 2,345.63
Wall Footing 6,001.34
rd. Output/gang : 14.0400 kgs /hr.
oduction Output : 28.080 kgs /hr.
No. of Hours : 23.50 hrs.
No. of Days : 3.00 days
No. of Gang : 2.00 gang

Septic Tank Footing Tie Beam


rd. Output/gang : 9.9300 kgs /hr. 14.0400 kgs /hr.
oduction Output : 19.860 kgs /hr. 28.080 kgs /hr.
No. of Hours : 8.25 hrs. 24.75 hrs.
No. of Days : 1.25 days 3.25 days
No. of Gang : 2.00 gang 2.00 gang

Column
rd. Output/gang : 21.0700 kgs. /hr.
oduction Output : 42.1400 kgs. /hr.
No. of Hours : 55.75 hrs.
No. of Days : 7.00 days
No. of Gang : 2.00 gang

tal No. of Hours : 186.00 hrs. Total No. of Days : 24.00 days
A. Name and Capacity of Equipment (OperateNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Bar Cutter 2.00 186.00 ₱ 158.25 ₱ 58,869.00
A. SUB-TOTAL, EQUIPMENT ₱ 58,869.00

B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Construction Foreman 1.00 186.00 ₱ 81.30 ₱ 15,121.80
Steelman 6.00 186.00 58.76 65,576.16
Laborer 3.00 186.00 45.25 25,249.50
B. SUB-TOTAL, LABOR ₱ 105,947.46

C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)

Footing Tie Beam


Deformed RSB ( 20mm, 16mm, 12mm 688.98 kgs. ₱ 40.00 ₱ 27,559.20
Tie Wire (2% of RSB) 14.00 kgs. 65.00 910.00

Page 60 of 188
Wall Footing &Column Footing
Deformed RSB ( 20mm, 16mm, 12mm & 10mm ) 653.61 kgs. 40.00 26,144.40
Tie Wire (2% of RSB) 14.00 kgs. 65.00 910.00
Slab on Fill
Deformed RSB ( 10mm ), Grade 40 462.00 kgs. 40.00 18,480.00
Tie Wire (2% of RSB) 10.00 kgs. 65.00 650.00
Septic Tank
Deformed RSB ( 10mm ), Grade 40 162.80 kgs. 40.00 6,512.00
Tie Wire (2% of RSB) 4.00 kgs. 65.00 260.00
Beam
Deformed RSB ( 16mm & 10mm ), Gr 2,556.00 kgs. ₱ 40.00 ₱ 102,240.00
Tie Wire (2% of RSB) 15.00 kgs. 65.00 975.00
Column
Deformed RSB ( 20mm, 16mm & 10m 2,445.90 kgs. ₱ 40.00 ₱ 97,836.00
Tie Wire (2% of RSB) 47.00 kgs. 65.00 3,055.00

C. SUB-TOTAL, MATERIAL ₱ 285,531.60

SUMMARY :
A. Equipment ₱ 58,869.00
B. Labor ₱ 105,947.46
C. Materials ₱ 285,531.60
D. TOTAL DIRECT COST ₱ 450,348.06
DIRECT UNIT COST ₱ 75.04
E. OCM 12% of D ₱ 54,041.77
F. Profit 8% of D ₱ 36,027.84
G. VAT 5% of (D+E+F) ₱ 27,020.88
H. Total Cost (D+E+F+G) ₱ 567,438.56
I. Unit Cost H/Quantity ₱ 94.55

Page 61 of 188
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino

Item No. : 903 (1) Quantity : 1.00


Description : Formworks and Falseworks Unit : l.s.

rd. Output/gang : l.s. /hr.


oduction Output : l.s. /hr.
No. of Hours : hrs.
No. of Days : days
No. of Gang : gang

A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)

A. SUB-TOTAL, EQUIPMENT ₱ -

B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Construction Foreman 1.00 88.75 ₱ 81.30 ₱ 7,215.38
Carpenter 5.00 88.75 58.76 26,074.75
Laborer 8.00 88.75 45.25 32,127.50

B. SUB-TOTAL, LABOR ₱ 65,417.63

C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
Factor
2" x 3" Good Lumber (Scaffolding) 2,549.32 bd.ft. ₱ 40.00 ₱ 101,972.80
2" x 2" Form Lumber (Forms and Staking) 980.13 bd.ft. 40.00 39,205.20
Assorted C.W. Nails 17.00 kgs. 75.00 1,275.00
1/4" × 4' × 8' Ordinary Plywood 30.00 pcs. 350.00 10,500.00

C. SUB-TOTAL, MATERIAL ₱ 152,953.00

SUMMARY :
A. Equipment ₱ -
B. Labor ₱ 65,417.63
C. Materials ₱ 152,953.00
D. TOTAL DIRECT COST ₱ 218,370.63
DIRECT UNIT COST ₱ 218,370.63
E. OCM 12% of D ₱ 26,204.48
F. Profit 8% of D ₱ 17,469.65
G. VAT 5% of (D+E+F) ₱ 13,102.24
H. Total Cost (D+E+F+G) ₱ 275,146.99
I. Unit Cost H/Quantity ₱ 275,146.99
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino

Item No. : 1000(1) Quantity : 20.00


Description : Soil Poisoning Unit : liters

rd. Output/gang : 1.3500 liters /hr.


oduction Output : 2.7000 liters /hr.
No. of Hours : 7.50 hrs.
No. of Days : 1.00 days
No. of Gang : 2.00 gang

A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)

A. SUB-TOTAL, EQUIPMENT ₱ -

B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Laborer 4.00 7.50 45.25 1,357.50

B. SUB-TOTAL, LABOR ₱ 1,357.50

C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
Factor
Soil Poisoning 12.00 liters ₱ 250.00 ₱ 3,000.00

C. SUB-TOTAL, MATERIAL ₱ 3,000.00

SUMMARY :
A. Equipment ₱ -
B. Labor ₱ 1,357.50
C. Materials ₱ 3,000.00
D. TOTAL DIRECT COST ₱ 4,357.50
DIRECT UNIT COST ₱ 217.88
E. OCM 12% of D ₱ 522.90
F. Profit 8% of D ₱ 348.60
G. VAT 5% of (D+E+F) ₱ 261.45
H. Total Cost (D+E+F+G) ₱ 5,490.45
I. Unit Cost H/Quantity ₱ 274.52
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino

Item No. : 1001(8) Quantity : 1.00


Description : Sewer Line Works Unit : l.s

rd. Output/gang : l.s /hr.


oduction Output : l.s /hr.
No. of Hours : 32.00 hrs.
No. of Days : 4.00 day
No. of Gang : 1.00 gang

A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)

A. SUB-TOTAL, EQUIPMENT ₱ -

B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Plumber 1.00 32.00 ₱ 58.76 ₱ 1,880.32
Laborer 1.00 32.00 45.25 1,448.00

B. SUB-TOTAL, LABOR ₱ 3,328.32

C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
100mm dia. X 3.00 m. PVC Pipe (orange) 15.00 pc/s ₱ 600.00 ₱ 9,000.00
50mm dia. X 3.00 m. PVC Pipe (orange) 7.00 pc/s 275.00 1,925.00
100mm dia. Wye 5.00 pc/s 130.00 650.00
100mm dia. Clean Out w/ plug 2.00 pc/s 80.00 160.00
100mm dia. X 50mm dia. Wye 3.00 pc/s 130.00 390.00
100mm dia. Elbow 4.00 pc/s 90.00 360.00
50mm dia. Elbow 15.00 pc/s 45.00 675.00
50mm dia. Tee 5.00 pc/s 45.00 225.00
50mm dia. P-trap 3.00 pc/s 60.00 180.00
50mm dia. Clean out w/ plug 2.00 pc/s 45.00 90.00

C. SUB-TOTAL, MATERIAL ₱ 13,655.00

SUMMARY :
A. Equipment ₱ -
B. Labor ₱ 3,328.32
C. Materials ₱ 13,655.00
D. TOTAL DIRECT COST ₱ 16,983.32
DIRECT UNIT COST ₱ 16,983.32
E. OCM 12% of D ₱ 2,038.00
F. Profit 8% of D ₱ 1,358.67
G. VAT 5% of (D+E+F) ₱ 1,019.00
H. Total Cost (D+E+F+G) ₱ 21,398.99
I. Unit Cost H/Quantity ₱ 21,398.99
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino

Item No. : 1001(9) Quantity : 1.00


Description : Storm Drainage and Downspout Unit : l.s

rd. Output/gang : l.s /hr.


oduction Output : l.s /hr.
No. of Hours : 32.00 hrs.
No. of Days : 4.00 day
No. of Gang : 1.00 gang

A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)

A. SUB-TOTAL, EQUIPMENT ₱ -

B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Plumber 1.00 32.00 ₱ 58.76 ₱ 1,880.32
Laborer 1.00 32.00 45.25 1,448.00

B. SUB-TOTAL, LABOR ₱ 3,328.32

C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
100mm dia. X 3.00 m. PVC Pipe (orange) 20.00 pcs ₱ 485.00 ₱ 9,700.00
100mm dia Elbow, 90 degree PVC 40.00 pcs 130.00 5,200.00
Flat Bar Metal Clamp 50mm x 1.2m 100.00 pcs 50.00 5,000.00
4mm dia Metal Screw with Tox 200.00 pcs 5.00 1,000.00
Masonry Drill Bit 4.00 pcs 120.00 480.00
Steel Drill Bit 4.00 pcs 150.00 600.00
Solvent Cement 2.00 pcs 460.00 920.00
50mm dia x 3.00 m PVC 2.00 pcs 275.00 550.00

C. SUB-TOTAL, MATERIAL ₱ 23,450.00

SUMMARY :
A. Equipment ₱ -
B. Labor ₱ 3,328.32
C. Materials ₱ 23,450.00
D. TOTAL DIRECT COST ₱ 26,778.32
DIRECT UNIT COST ₱ 26,778.32
E. OCM 12% of D ₱ 3,213.40
F. Profit 8% of D ₱ 2,142.27
G. VAT 5% of (D+E+F) ₱ 1,606.70
H. Total Cost (D+E+F+G) ₱ 33,740.69
I. Unit Cost H/Quantity ₱ 33,740.69
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino

Item No. : 1001(1)a5 Quantity : 18.00


Description : Pipe 50mm dia. PVC, Series 1000 Unit : m

rd. Output/gang : 0.5000 m /hr.


oduction Output : 0.5000 m /hr.
No. of Hours : 36.00 hrs.
No. of Days : 4.50 day
No. of Gang : 1.00 gang

A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)

A. SUB-TOTAL, EQUIPMENT ₱ -

B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Plumber 1.00 36.00 ₱ 58.76 ₱ 2,115.36
Laborer 1.00 36.00 45.25 1,629.00

B. SUB-TOTAL, LABOR ₱

C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
50mm dia. X 3.00 m. PVC Pipe (orange) 8.00 pcs ₱ 291.00 ₱ 2,328.00

C. SUB-TOTAL, MATERIAL ₱

SUMMARY :
A. Equipment ₱
B. Labor ₱
C. Materials ₱
D. TOTAL DIRECT COST ₱ -
DIRECT UNIT COST ₱ -
E. OCM 12% of D ₱ -
F. Profit 8% of D ₱ -
G. VAT 5% of (D+E+F) ₱ -
H. Total Cost (D+E+F+G) ₱ -
I. Unit Cost H/Quantity ₱ -
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino

Item No. : 1001 (2) a3 Quantity : 8.00


Description : Fittings 100mm dia. PVC(Elbow, 1/8 Bend,45 deg.) Unit : each

rd. Output/gang : 0.5000 each /hr.


oduction Output : 0.5000 each /hr.
No. of Hours : 16.00 hrs.
No. of Days : 2.00 day
No. of Gang : 1.00 gang

A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)

A. SUB-TOTAL, EQUIPMENT ₱ -

B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Plumber 1.00 16.00 ₱ 58.76 ₱ 940.16
Laborer 1.00 16.00 45.25 724.00

B. SUB-TOTAL, LABOR ₱

C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
100mm dia. PVC 1/8 Bend (orange) 9.00 pc ₱ 60.00 ₱ 540.00

C. SUB-TOTAL, MATERIAL ₱

SUMMARY :
A. Equipment ₱
B. Labor ₱
C. Materials ₱
D. TOTAL DIRECT COST ₱ -
DIRECT UNIT COST ₱ -
E. OCM 12% of D ₱ -
F. Profit 8% of D ₱ -
G. VAT 5% of (D+E+F) ₱ -
H. Total Cost (D+E+F+G) ₱ -
I. Unit Cost H/Quantity ₱ -
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino

Item No. : 1001 (2) b1 Quantity : 1.00


Description : Fittings 50mm dia. PVC(Elbow, 1/4 Bend,90 deg.) Unit : each

rd. Output/gang : 0.5000 each /hr.


oduction Output : 0.5000 each /hr.
No. of Hours : 2.00 hrs.
No. of Days : 0.25 day
No. of Gang : 1.00 gang

A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)

A. SUB-TOTAL, EQUIPMENT ₱ -

B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Plumber 1.00 2.00 ₱ 58.76 ₱ 117.52
Laborer 1.00 2.00 45.25 90.50

B. SUB-TOTAL, LABOR ₱

C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
50mm dia. PVC 1/4 Bend (orange) 24.00 pc ₱ 26.00 ₱ 624.00

C. SUB-TOTAL, MATERIAL ₱

SUMMARY :
A. Equipment ₱
B. Labor ₱
C. Materials ₱
D. TOTAL DIRECT COST ₱ -
DIRECT UNIT COST ₱ -
E. OCM 12% of D ₱ -
F. Profit 8% of D ₱ -
G. VAT 5% of (D+E+F) ₱ -
H. Total Cost (D+E+F+G) ₱ -
I. Unit Cost H/Quantity ₱ -
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino

Item No. : 1001 (2) b3 Quantity : 4.00


Description : Fittings 100mm dia. PVC(Elbow, 1/4 Bend,90 deg.) Unit : each

rd. Output/gang : 0.5000 each /hr.


oduction Output : 0.5000 each /hr.
No. of Hours : 8.00 hrs.
No. of Days : 1.00 day
No. of Gang : 1.00 gang

A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)

A. SUB-TOTAL, EQUIPMENT ₱ -

B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Plumber 1.00 8.00 ₱ 58.76 ₱ 470.08
Laborer 1.00 8.00 45.25 362.00

B. SUB-TOTAL, LABOR ₱

C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
100mm dia. PVC 1/4 Bend (orange) 9.00 pc ₱ 70.00 ₱ 630.00

C. SUB-TOTAL, MATERIAL ₱

SUMMARY :
A. Equipment ₱
B. Labor ₱
C. Materials ₱
D. TOTAL DIRECT COST ₱ -
DIRECT UNIT COST ₱ -
E. OCM 12% of D ₱ -
F. Profit 8% of D ₱ -
G. VAT 5% of (D+E+F) ₱ -
H. Total Cost (D+E+F+G) ₱ -
I. Unit Cost H/Quantity ₱ -
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino

Item No. : 1001 (2) c3 Quantity : 5.00


Description : Fittings 100mm dia. PVC(Clean Out with Plug) Unit : each

rd. Output/gang : 0.5000 each /hr.


oduction Output : 0.5000 each /hr.
No. of Hours : 10.00 hrs.
No. of Days : 1.25 day
No. of Gang : 1.00 gang

A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)

A. SUB-TOTAL, EQUIPMENT ₱ -

B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Plumber 1.00 10.00 ₱ 58.76 ₱ 587.60
Laborer 1.00 10.00 45.25 452.50

B. SUB-TOTAL, LABOR ₱

C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
100mm dia. PVC Clean Out with Plug & Seal 4.00 pc ₱ 55.00 ₱ 220.00
(orange)

C. SUB-TOTAL, MATERIAL ₱

SUMMARY :
A. Equipment ₱
B. Labor ₱
C. Materials ₱
D. TOTAL DIRECT COST ₱ -
DIRECT UNIT COST ₱ -
E. OCM 12% of D ₱ -
F. Profit 8% of D ₱ -
G. VAT 5% of (D+E+F) ₱ -
H. Total Cost (D+E+F+G) ₱ -
I. Unit Cost H/Quantity ₱ -
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino

Item No. : 1001 (2) e1 Quantity : 2.00


Description : Fittings 50mm dia. PVC(P-Trap) Unit : each

rd. Output/gang : 0.5000 each /hr.


oduction Output : 0.5000 each /hr.
No. of Hours : 4.00 hrs.
No. of Days : 0.50 day
No. of Gang : 1.00 gang

A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)

A. SUB-TOTAL, EQUIPMENT ₱ -

B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Plumber 1.00 4.00 ₱ 58.76 ₱ 235.04
Laborer 1.00 4.00 45.25 181.00

B. SUB-TOTAL, LABOR ₱

C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
50mm dia. PVC P-Trap w/ Plug and Sealing R 12.00 pc ₱ 107.00 ₱ 1,284.00
(orange)

C. SUB-TOTAL, MATERIAL ₱

SUMMARY :
A. Equipment ₱
B. Labor ₱
C. Materials ₱
D. TOTAL DIRECT COST ₱ -
DIRECT UNIT COST ₱ -
E. OCM 12% of D ₱ -
F. Profit 8% of D ₱ -
G. VAT 5% of (D+E+F) ₱ -
H. Total Cost (D+E+F+G) ₱ -
I. Unit Cost H/Quantity ₱ -
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino

Item No. : 1001 (2) f1 Quantity : 2.00


Description : Fittings 50mm dia. PVC(Sanitary Tee) Unit : each

rd. Output/gang : 0.5000 each /hr.


oduction Output : 0.5000 each /hr.
No. of Hours : 4.00 hrs.
No. of Days : 0.50 day
No. of Gang : 1.00 gang

A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)

A. SUB-TOTAL, EQUIPMENT ₱ -

B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Plumber 1.00 4.00 ₱ 58.76 ₱ 235.04
Laborer 1.00 4.00 45.25 181.00

B. SUB-TOTAL, LABOR ₱

C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
50mm dia. PVC Tee (orange) 4.00 pc ₱ 37.00 ₱ 148.00

C. SUB-TOTAL, MATERIAL ₱

SUMMARY :
A. Equipment ₱
B. Labor ₱
C. Materials ₱
D. TOTAL DIRECT COST ₱ -
DIRECT UNIT COST ₱ -
E. OCM 12% of D ₱ -
F. Profit 8% of D ₱ -
G. VAT 5% of (D+E+F) ₱ -
H. Total Cost (D+E+F+G) ₱ -
I. Unit Cost H/Quantity ₱ -
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino

Item No. : 1001 (2) f3 Quantity : 1.00


Description : Fittings 100mm dia. PVC(Elbow, 1/8 Bend,45 deg.) Unit : each

rd. Output/gang : 0.5000 each /hr.


oduction Output : 0.5000 each /hr.
No. of Hours : 2.00 hrs.
No. of Days : 0.25 day
No. of Gang : 1.00 gang

A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)

A. SUB-TOTAL, EQUIPMENT ₱ -

B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Plumber 1.00 2.00 ₱ 58.76 ₱ 117.52
Laborer 1.00 2.00 45.25 90.50

B. SUB-TOTAL, LABOR ₱

C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
100mm dia. PVC 1/8 Bend (orange) 18.00 pc ₱ 60.00 ₱ 1,080.00

C. SUB-TOTAL, MATERIAL ₱

SUMMARY :
A. Equipment ₱
B. Labor ₱
C. Materials ₱
D. TOTAL DIRECT COST ₱ -
DIRECT UNIT COST ₱ -
E. OCM 12% of D ₱ -
F. Profit 8% of D ₱ -
G. VAT 5% of (D+E+F) ₱ -
H. Total Cost (D+E+F+G) ₱ -
I. Unit Cost H/Quantity ₱ -
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino

Item No. : 1001 (2) g1 Quantity : 8.00


Description : Fittings 50mm dia. PVC(Sanitary Wye) Unit : each

rd. Output/gang : 0.5000 each /hr.


oduction Output : 0.5000 each /hr.
No. of Hours : 16.00 hrs.
No. of Days : 2.00 day
No. of Gang : 1.00 gang

A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)

A. SUB-TOTAL, EQUIPMENT ₱ -

B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Plumber 1.00 16.00 ₱ 58.76 ₱ 940.16
Laborer 1.00 16.00 45.25 724.00

B. SUB-TOTAL, LABOR ₱

C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
50mm dia. PVC Wye (orange) 9.00 pc ₱ 81.00 ₱ 729.00

C. SUB-TOTAL, MATERIAL ₱

SUMMARY :
A. Equipment ₱
B. Labor ₱
C. Materials ₱
D. TOTAL DIRECT COST ₱ -
DIRECT UNIT COST ₱ -
E. OCM 12% of D ₱ -
F. Profit 8% of D ₱ -
G. VAT 5% of (D+E+F) ₱ -
H. Total Cost (D+E+F+G) ₱ -
I. Unit Cost H/Quantity ₱ -
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino

Item No. : 1001 (2) l2 Quantity : 5.00


Description : Fittings 100mm dia. PVC(Sanitary Wye) Unit : each

rd. Output/gang : 0.5000 each /hr.


oduction Output : 0.5000 each /hr.
No. of Hours : 10.00 hrs.
No. of Days : 1.25 day
No. of Gang : 1.00 gang

A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)

A. SUB-TOTAL, EQUIPMENT ₱ -

B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Plumber 1.00 10.00 ₱ 58.76 ₱ 587.60
Laborer 1.00 10.00 45.25 452.50

B. SUB-TOTAL, LABOR ₱

C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
100mm x 50mm dia. PVC Wye (orange) 5.00 pc ₱ 100.00 ₱ 500.00

C. SUB-TOTAL, MATERIAL ₱

SUMMARY :
A. Equipment ₱
B. Labor ₱
C. Materials ₱
D. TOTAL DIRECT COST ₱ -
DIRECT UNIT COST ₱ -
E. OCM 12% of D ₱ -
F. Profit 8% of D ₱ -
G. VAT 5% of (D+E+F) ₱ -
H. Total Cost (D+E+F+G) ₱ -
I. Unit Cost H/Quantity ₱ -
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino

Item No. : 1001 (2) k2 Quantity : 5.00


Description : Fittings 100mm x 50mm dia PVC(Reducer-Sanitary Tee) Unit : each

rd. Output/gang : 0.5000 each /hr.


oduction Output : 0.5000 each /hr.
No. of Hours : 10.00 hrs.
No. of Days : 1.25 day
No. of Gang : 1.00 gang

A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)

A. SUB-TOTAL, EQUIPMENT ₱ -

B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Plumber 1.00 10.00 ₱ 58.76 ₱ 587.60
Laborer 1.00 10.00 45.25 452.50

B. SUB-TOTAL, LABOR ₱

C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
100mm x 50mm dia. PVC Tee (orange) 2.00 pc ₱ 100.00 ₱ 200.00

C. SUB-TOTAL, MATERIAL ₱

SUMMARY :
A. Equipment ₱
B. Labor ₱
C. Materials ₱
D. TOTAL DIRECT COST ₱ -
DIRECT UNIT COST ₱ -
E. OCM 12% of D ₱ -
F. Profit 8% of D ₱ -
G. VAT 5% of (D+E+F) ₱ -
H. Total Cost (D+E+F+G) ₱ -
I. Unit Cost H/Quantity ₱ -
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino

Item No. : 1001 (6) a Quantity : 0.26


Description : Catch Basin - Concrete Unit : cu.m.

rd. Output/gang : 0.5000 cu.m. /hr.


oduction Output : 0.2600 cu.m. /hr.
No. of Hours : 1.00 hrs.
No. of Days : 0.25 day
No. of Gang : 1.00 gang

A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)

A. SUB-TOTAL, EQUIPMENT ₱ -

B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Mason 1.00 1.00 ₱ ₱ -
Laborer 1.00 1.00 -

B. SUB-TOTAL, LABOR ₱ -

C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)

a. Portland Cement 9.000 3.00 bags ₱ -


b. Fine Aggregates 0.4246 1.00 cu.m. -
c. Crushed Gravel 0.8999 1.00 cu.m. -

C. SUB-TOTAL, MATERIAL ₱ -

SUMMARY :
A. Equipment ₱ -
B. Labor ₱ -
C. Materials ₱ -
D. TOTAL DIRECT COST ₱ -
DIRECT UNIT COST ₱ -
E. OCM 12% of D ₱ -
F. Profit 8% of D ₱ -
G. VAT 5% of (D+E+F) ₱ -
H. Total Cost (D+E+F+G) ₱ -
I. Unit Cost H/Quantity ₱ -
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino

Item No. : 1001 (6) b Quantity : 12.00


Description : Catch Basin - CHB Unit : each

rd. Output/gang : 0.5000 each /hr.


oduction Output : 0.5000 each /hr.
No. of Hours : 40.00 hrs.
No. of Days : 5.00 day
No. of Gang : 1.00 gang

A. Name and Capacity of Equipment (OperateNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)

A. SUB-TOTAL, EQUIPMENT ₱ -

B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Excavation
Laborer 4.00 8.00 45.25 1,448.00
Masonry Works
Mason 1.00 40.00 58.76 2,350.40
Laborer 2.00 40.00 45.25 3,620.00
Cement Plaster Finish
Mason 1.00 40.00 58.76 2,350.40
Laborer 2.00 40.00 45.25 3,620.00
Concrete Works
Mason 1.00 40.00 58.76 2,350.40
Carpenter 1.00 40.00 58.76 2,350.40
Laborer 1.00 40.00 45.25 1,810.00
Pipe
Plumber 1.00 40.00 58.76 2,350.40
Laborer 2.00 40.00 45.25 3,620.00

B. SUB-TOTAL, LABOR ₱ 25,870.00

C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
Excavation
none
Masonry Works
a. 100mmx200mmx400 CHB 360.00 pcs ₱ 12.00 ₱ 4,320.00
b. Portland Cement (Class B) 33.26 bags 260.00 8,647.60
c. Fine Aggregates 0.67 cu.m. 579.52 388.28
d. 10mmDx6m RSB; 11.00 kls 40.00 440.00
e. Tie Wire (2% of RSB) 0.89 kls 75.00 66.75
Cement Plaster Finish
a. Portland Cement (Class A, 1:2 ratio) 21.00 bags 260.00 5,460.00
b. Fine Aggregates 2.50 cu.m. 579.52 1,448.80
Concrete Works
a. Portland Cement 12.00 bags 260.00 3,120.00
b. Fine Aggregates 0.55 cu.m 579.52 318.74
c. Crushed Aggregates 1.10 cu.m 820.40 902.44
Pipe
100 mm dia uPVC 81.00 pcs 600.00 48,600.00
C. SUB-TOTAL, MATERIAL ₱ 73,712.60

SUMMARY :
A. Equipment ₱ -
B. Labor ₱ 25,870.00
C. Materials ₱ 73,712.60
D. TOTAL DIRECT COST ₱ 99,582.60
DIRECT UNIT COST ₱ 8,298.55
E. OCM 12% of D ₱ 11,949.91
F. Profit 8% of D ₱ 7,966.61
G. VAT 5% of (D+E+F) ₱ 5,974.96
H. Total Cost (D+E+F+G) ₱ 125,474.08
I. Unit Cost H/Quantity ₱ 10,456.17
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino

Item No. : 1002 (8) Quantity : 1.00


Description : Plumbing Fixtures Unit : l.s

rd. Output/gang : l.s /hr.


oduction Output : - l.s /hr.
No. of Hours : - hrs.
No. of Days : - day
No. of Gang : 1.00 gang

A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)

A. SUB-TOTAL, EQUIPMENT ₱ -

B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Plumber 2.00 40.00 ₱ 58.76 ₱ 4,700.80
Laborer 1.00 40.00 45.25 1,810.00

B. SUB-TOTAL, LABOR ₱ 6,510.80

C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
Water Closet including fittings and 3.00 sets ₱ 6,500.00 ₱ 19,500.00
accessories (Round Front)
Lavatory with complete accessories 1.00 sets 5,500.00 5,500.00
Floor Drain 8.00 pcs 280.00 2,240.00
Stainless Faucet 12.00 pcs 400.00 4,800.00
Vulcaseal 2.00 ltr 250.00 500.00
PVC Solvent 3.00 ltr 35.00 105.00
Teflon Tape 15.00 pcs 850.00 12,750.00
Stainless Kitchen Sink 5.00 sets 5,000.00 25,000.00

C. SUB-TOTAL, MATERIAL ₱ 70,395.00

SUMMARY :
A. Equipment ₱ -
B. Labor ₱ 6,510.80
C. Materials ₱ 70,395.00
D. TOTAL DIRECT COST ₱ 76,905.80
DIRECT UNIT COST ₱ 76,905.80
E. OCM 12% of D ₱ 9,228.70
F. Profit 8% of D ₱ 6,152.46
G. VAT 5% of (D+E+F) ₱ 4,614.35
H. Total Cost (D+E+F+G) ₱ 96,901.31
I. Unit Cost H/Quantity ₱ 96,901.31
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino

Item No. : 1002 (28) Quantity : 1.00


Description : Cold Water Line Unit : l.s

rd. Output/gang :
oduction Output :
No. of Hours :
No. of Days :
No. of Gang :

A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)

A. SUB-TOTAL, EQUIPMENT ₱ -

B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Plumber 1.00 30.00 ₱ 58.76 ₱ 1,762.80
Laborer 1.00 30.00 45.25 1,357.50

B. SUB-TOTAL, LABOR ₱ 3,120.30

C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
20mm dia Gate Valve 5.00 pcs. ₱ 150.00 ₱ 750.00
32mm dia Fusion Device 1.00 pcs. 2,500.00 2,500.00
32mm x 20mm dia Tee Reducer 4.00 pcs. 260.00 1,040.00
20mm dia Equal Tee 6.00 pcs. 260.00 1,560.00
20mm dia Elbow 90 degrees 7.00 pcs. 180.00 1,260.00
20mm dia Female Elbow 10.00 pcs. 250.00 2,500.00
32mm dia x 4.00m PPR Pipe 25.00 pcs. 580.00 14,500.00
20mm dia x 4.00m PPR Pipe 8.00 pcs. 350.00 2,800.00
32mm dia End Cap 1.00 pcs. 25.00 25.00
PPR Cutter 1.00 pcs. 850.00 850.00

C. SUB-TOTAL, MATERIAL ₱ 27,785.00

SUMMARY :
A. Equipment ₱ -
B. Labor ₱ 3,120.30
C. Materials ₱ 27,785.00
D. TOTAL DIRECT COST ₱ 30,905.30
DIRECT UNIT COST ₱ 30,905.30
E. OCM 12% of D ₱ 3,708.64
F. Profit 8% of D ₱ 2,472.42
G. VAT 5% of (D+E+F) ₱ 1,854.32
H. Total Cost (D+E+F+G) ₱ 38,940.68
I. Unit Cost H/Quantity ₱ 38,940.68
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino

Item No. : 1003 (1)a1 Quantity : 468.51


Description : Ceiling (Metal Frame) Unit : sq.m.

rd. Output/gang : 2.5500 sq.m. /hr.


oduction Output : 5.1000 sq.m. /hr.
No. of Hrs. : 92.00 hrs.
No. of Days : 11.50 days
No. of Gang : 2.00 gang

A. Name and Capacity of Equipment (OperatedNo. of UnitsNo. of Hrs. Unit Rate/Hr. Total Cost (Pesos)

A. SUB-TOTAL, EQUIPMENT ₱ -

B. Designation of Personnel No. of MenNo. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Foreman 1.00 92.00 81.30 7,479.60
Carpenter 6.00 92.00 ₱ 58.76 ₱ 32,435.52
Laborer 4.00 92.00 45.25 16,652.00
B. SUB-TOTAL, LABOR ₱ 56,567.12

C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
Metal Furring (12mm x 38mm x0.80mm) 250.00 pcs ₱ 125.00 ₱ 31,250.00
Primary Channel (12mm x38mm x 0.80mm) 125.00 pcs 110.00 13,750.00
Wall Angle (25mm x 25mm x0.40mm) 150.00 pcs 55.00 8,250.00
Rod Joiner Clip 1,050.00 pcs 15.00 15,750.00
W-Clip 1,200.00 pcs 5.00 6,000.00
# 10 GI Wire 210.00 kls 60.00 12,600.00
Rivets 80.00 boxes 250.00 20,000.00
Fiber Cement Ceiling Board 125.00 pcs 350.00 43,750.00
Screw # 6 14,000.00 screw 0.50 7,000.00
Insulator 276.08 sq.m. 130.00 35,890.40
0.4mm x 6" width @ 1.00m length - spandrel
682.00 lin.m 50.00 34,100.00
eaves cover with air vent design
0.4mm x 6" width @ 1.50m length - spandrel
459.00 50.00 22,950.00
eaves cover with air vent design lin.m
0.4mm x 6" width @ 3.20m length - spandrel
288.00 lin.m 50.00 14,400.00
eaves cover with air vent design
0.5mm thick x 8' end mouldings 199.20 lin.m 50.00 9,960.00
0.5mm thick x 8' center mouldings 12.00 lin.m 50.00 600.00
C. SUB-TOTAL, MATERIAL ₱ 276,250.40

SUMMARY :
A. Equipment ₱ -
B. Labor ₱ 56,567.12
C. Materials ₱ 276,250.40
D. TOTAL DIRECT COST ₱ 332,817.52
DIRECT UNIT COST ₱ 710.37
E. OCM 12% of D ₱ 39,938.10
F. Profit 8% of D ₱ 26,625.40
G. VAT 5% of (D+E+F) ₱ 19,969.05
H. Total Cost (D+E+F+G) ₱ 419,350.08
I. Unit Cost H/Quantity ₱ 895.07
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino

Item No. : 1006 (6) Quantity : 17.00


Description : Steel Doors and Frames Unit : l.s

rd. Output/gang : l.s /hr.


oduction Output : - l.s /hr.
No. of Hrs. : 80.00 hrs.
No. of Days : 10.00 days
No. of Gang : 2.00 gang

A. Name and Capacity of Equipment (OperateNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)

A. SUB-TOTAL, EQUIPMENT ₱ -

B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Carpenter 2.00 80.00 ₱ 58.76 ₱ 9,401.60
Laborer 2.00 80.00 45.25 7,240.00

B. SUB-TOTAL, LABOR ₱ 16,641.60

C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
Factor
-
2" x 6" Steel Door Jambs 5.00 pcs ₱ 1,500.00 ₱ 7,500.00
Roll up Door 58.89 sq.m ₱ 550.00 ₱ 32,389.50

C. SUB-TOTAL, MATERIAL ₱ 39,889.50

SUMMARY :
A. Equipment ₱ -
B. Labor ₱ 16,641.60
C. Materials ₱ 39,889.50
D. TOTAL DIRECT COST ₱ 56,531.10
DIRECT UNIT COST ₱ 3,325.36
E. OCM 12% of D ₱ 6,783.73
F. Profit 8% of D ₱ 4,522.49
G. VAT 5% of (D+E+F) ₱ 3,391.87
H. Total Cost (D+E+F+G) ₱ 71,229.19
I. Unit Cost H/Quantity ₱ 4,189.95
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino

Item No. : 1004 (2) a Quantity : 23.00


Description : Finishing Hardware (Lockset) Unit : sets

oduction Output : 0.5313 sets /hr.


rd. Output/gang : 1.0626 sets /hr.
No. of Hours : 21.75 hrs.
No. of Days : 2.75 days
No. of Gang : 2.00 gang

A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)

A. SUB-TOTAL, EQUIPMENT ₱ -

B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Carpenter 2.00 21.75 ₱ 58.76 ₱ 2,556.06

B. SUB-TOTAL, LABOR ₱ 2,556.06

C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
Door Lockset 23.00 sets ₱ 1,550.00 ₱ 35,650.00

C. SUB-TOTAL, MATERIAL ₱ 35,650.00

SUMMARY :
A. Equipment ₱ -
B. Labor ₱ 2,556.06
C. Materials ₱ 35,650.00
D. TOTAL DIRECT COST ₱ 38,206.06
DIRECT UNIT COST ₱ 1,661.13
E. OCM 12% of D ₱ 4,584.73
F. Profit 8% of D ₱ 3,056.48
G. VAT 5% of (D+E+F) ₱ 2,292.36
H. Total Cost (D+E+F+G) ₱ 48,139.64
I. Unit Cost H/Quantity ₱ 2,093.03
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino

Item No. : 1004 (2) g Quantity : 110.00


Description : Finishing Hardware (Hinges) Unit : sets

a. Door Lock Set


oduction Output : 3.7500 sets /hr.
rd. Output/gang : 7.5000 sets /hr.
No. of Hours : 14.75 hrs.
No. of Days : 2.00 days
No. of Gang : 2.00 gang

A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)

A. SUB-TOTAL, EQUIPMENT ₱ -

B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Carpenter 2.00 14.75 ₱ 58.76 P 1,733.42
Laborer 2.00 14.75 45.25 1,334.88

B. SUB-TOTAL, LABOR ₱ 3,068.30

C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
4" x 4" Hinges 68.00 pcs. ₱ 50.00 P 3,400.00

C. SUB-TOTAL, MATERIAL ₱ 3,400.00

SUMMARY :
A. Equipment ₱ -
B. Labor ₱ 3,068.30
C. Materials ₱ 3,400.00
D. TOTAL DIRECT COST ₱ 6,468.30
DIRECT UNIT COST ₱ 58.80
E. OCM 12% of D ₱ 776.20
F. Profit 8% of D ₱ 517.46
G. VAT 5% of (D+E+F) ₱ 388.10
H. Total Cost (D+E+F+G) ₱ 8,150.05
I. Unit Cost H/Quantity ₱ 74.09
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino

Item No. : 1005 (6) Quantity : 38.88


Description : Steel Window Unit : sq.m

oduction Output : 0.560 sq.m /hr.


rd. Output/gang : 1.120 sq.m /hr.
No. of Hours : 34.75 hrs.
No. of Days : 4.50 days
No. of Gang : 2.00 gang

A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)

A. SUB-TOTAL, EQUIPMENT ₱ -

B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Installer 4.00 34.75 ₱ 58.76 ₱ 8,167.64
Laborer 1.00 34.75 45.25 1,572.44

B. SUB-TOTAL, LABOR ₱ 9,740.08

C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
Steel Matting Window
W-1, (3-2.40 x 3.60m) 25.92 sq.m. P 2,500.00 P 64,800.00
W-2, (1-1.20 x 3.60m) 4.32 sq.m. 2,500.00 10,800.00
W-3, (2-1.20 x 2.40m) 5.76 sq.m. 2,500.00 14,400.00
W-4, (1 - 1.20m x 2.40m) 2.88 sq.m. 2,500.00 7,200.00
Steel Casement Window
W-5, (1 - 1.20m x 1.20m) 1.44 sq.m. 2,500.00 3,600.00
W-6, (1 - 0.50m x 1.00m) 1.50 sq.m. 2,500.00 3,750.00
C. SUB-TOTAL, MATERIAL ₱ 104,550.00

SUMMARY :
A. Equipment ₱ -
B. Labor ₱ 9,740.08
C. Materials ₱ 104,550.00
D. TOTAL DIRECT COST ₱ 114,290.08
DIRECT UNIT COST ₱ 2,939.56
E. OCM 12% of D ₱ 13,714.81
F. Profit 8% of D ₱ 9,143.21
G. VAT 5% of (D+E+F) ₱ 6,857.40
H. Total Cost (D+E+F+G) ₱ 144,005.50
I. Unit Cost H/Quantity ₱ 3,703.85
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino

Item No. : 1010 (2) b Quantity : 26.46


Description : Doors (Wood Panel) Unit : sq.m.

oduction Output : 0.2363 sq.m. /hr.


rd. Output/gang : 0.2363 sq.m. /hr.
No. of Hours : 112.00 hrs.
No. of Days : 14.00 days
No. of Gang : 1.00 gang

A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)

A. SUB-TOTAL, EQUIPMENT ₱ -

B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Carpenter 2.00 112.00 ₱ 58.76 ₱ 13,162.24

B. SUB-TOTAL, LABOR ₱ 13,162.24

C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
D3 - (1.00m × 2.10m.) Panel Type Door 2.00 sets ₱ 6,500.00 ₱ 13,000.00
D4 - (0.90m × 2.10m.) Panel Type Door 3.00 sets 5,500.00 16,500.00

C. SUB-TOTAL, MATERIAL ₱ 29,500.00

SUMMARY :
A. Equipment ₱ -
B. Labor ₱ 13,162.24
C. Materials ₱ 29,500.00
D. TOTAL DIRECT COST ₱ 42,662.24
DIRECT UNIT COST ₱ 1,612.33
E. OCM 12% of D ₱ 5,119.47
F. Profit 8% of D ₱ 3,412.98
G. VAT 5% of (D+E+F) ₱ 2,559.73
H. Total Cost (D+E+F+G) ₱ 53,754.42
I. Unit Cost H/Quantity ₱ 2,031.54
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino

Item No. : 1014 (1) b2 Quantity : 518.42


Description : Prepainted Metal Sheets Unit : sq.m.

oduction Output : 3.2600 sq.m. /hr.


rd. Output/gang : 6.5200 sq.m. /hr.
No. of Hours : 79.75 hrs.
No. of Days : 10.00 days
No. of Gang : 2.00 gang

A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)

A. SUB-TOTAL, EQUIPMENT ₱ -

B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Tinsmith 4.00 79.75 ₱ 58.76 ₱ 18,744.44
Laborer 4.00 79.75 45.25 14,434.75

B. SUB-TOTAL, LABOR ₱ 33,179.19

C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)

Long-Span Roofing,corrugated, 518.42 sq.m. ₱ 350.00 ₱ 181,447.00


Texscrew 5,000.00 pcs. 2.50 12,500.00
Blind Rivets 2.00 boxes 350.00 700.00

C. SUB-TOTAL, MATERIAL ₱ 194,647.00

SUMMARY :
A. Equipment ₱ -
B. Labor ₱ 33,179.19
C. Materials ₱ 194,647.00
D. TOTAL DIRECT COST ₱ 227,826.19
DIRECT UNIT COST ₱ 439.46
E. OCM 12% of D ₱ 27,339.14
F. Profit 8% of D ₱ 18,226.10
G. VAT 5% of (D+E+F) ₱ 13,669.57
H. Total Cost (D+E+F+G) ₱ 287,061.00
I. Unit Cost H/Quantity ₱ 553.72
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino

Item No. : 1013 (2) a Quantity : 48.40


Description : Fabricated Metal Roofing Accessory (Ridge/Hip Rolls) Unit : ln.m.

oduction Output : 5.3125 ln.m. /hr.


rd. Output/gang : 5.3125 ln.m. /hr.
No. of Hours : 9.25 hrs.
No. of Days : 1.25 days
No. of Gang : 1.00 gang

A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)

A. SUB-TOTAL, EQUIPMENT ₱ -

B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Tinsmith 2.00 9.25 ₱ 58.76 ₱ 1,087.06
Laborer 2.00 9.25 45.25 837.13

B. SUB-TOTAL, LABOR ₱ 1,924.19

C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
Prepinted G. I Ridge Roll 22.00 pcs ₱ 450.00 ₱ 9,900.00

C. SUB-TOTAL, MATERIAL ₱ 9,900.00

SUMMARY :
A. Equipment ₱ -
B. Labor ₱ 1,924.19
C. Materials ₱ 9,900.00
D. TOTAL DIRECT COST ₱ 11,824.19
DIRECT UNIT COST ₱ 244.30
E. OCM 12% of D ₱ 1,418.90
F. Profit 8% of D ₱ 945.93
G. VAT 5% of (D+E+F) ₱ 709.45
H. Total Cost (D+E+F+G) ₱ 14,898.47
I. Unit Cost H/Quantity ₱ 307.82
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino

Item No. : 1013 (2) b Quantity : 33.60


Description : Fabricated Metal Roofing Accessory (Flashings) Unit : ln.m.

oduction Output : 5.3125 ln.m. /hr.


rd. Output/gang : 5.3125 ln.m. /hr.
No. of Hours : 6.50 hrs.
No. of Days : 1.00 days
No. of Gang : 1.00 gang

A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)

A. SUB-TOTAL, EQUIPMENT ₱ -

B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Tinsmith 2.00 6.50 ₱ 58.76 ₱ 763.88
Laborer 2.00 6.50 45.25 588.25

B. SUB-TOTAL, LABOR ₱ 1,352.13

C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
Prepainted Flashing 14.00 pcs ₱ 450.00 ₱ 6,300.00

C. SUB-TOTAL, MATERIAL ₱ 6,300.00

SUMMARY :
A. Equipment ₱ -
B. Labor ₱ 1,352.13
C. Materials ₱ 6,300.00
D. TOTAL DIRECT COST ₱ 7,652.13
DIRECT UNIT COST ₱ 227.74
E. OCM 12% of D ₱ 918.26
F. Profit 8% of D ₱ 612.17
G. VAT 5% of (D+E+F) ₱ 459.13
H. Total Cost (D+E+F+G) ₱ 9,641.68
I. Unit Cost H/Quantity ₱ 286.95
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino

Item No. : 1013 (2) c Quantity : 105.60


Description : Fabricated Metal Roofing Accessory (Gutters) Unit : ln.m.

oduction Output : 5.3125 ln.m. /hr.


rd. Output/gang : 5.3125 ln.m. /hr.
No. of Hours : 20.00 hrs.
No. of Days : 2.50 days
No. of Gang : 1.00 gang

A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)

A. SUB-TOTAL, EQUIPMENT ₱ -

B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Tinsmith 2.00 20.00 ₱ 58.76 ₱
Laborer 2.00 20.00 45.25

B. SUB-TOTAL, LABOR ₱ -

C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
0.40mm x 2.4m S-type gutter - prepainted 44.00 pcs ₱ 450.00 ₱
0.40mm x 2.4m @ 24" width Valley gutter -
5.00 pcs 450.00
pre painted

C. SUB-TOTAL, MATERIAL ₱ -

SUMMARY :
A. Equipment ₱ -
B. Labor ₱ -
C. Materials ₱ -
D. TOTAL DIRECT COST ₱ -
DIRECT UNIT COST ₱ -
E. OCM 12% of D ₱ -
F. Profit 8% of D ₱ -
G. VAT 5% of (D+E+F) ₱ -
H. Total Cost (D+E+F+G) ₱ -
I. Unit Cost H/Quantity ₱ -
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino

Item No. : 1018(1) Quantity : 281.60


Description : Glazed Tiles and Trims Unit : sq.m

rd. Output/gang : 0.2800 sq.m /hr.


oduction Output : 3.3600 sq.m /hr.
No. of Hours : 84.00 hrs.
No. of Days : 10.50 days
No. of Gang : 2.00 gang

A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)

A. SUB-TOTAL, EQUIPMENT ₱ -

B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Tile Setter 4.00 84.00 ₱ 58.76 ₱ 19,743.36
Laborer 2.00 84.00 45.25 7,602.00

B. SUB-TOTAL, LABOR ₱ 27,345.36

C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
Ceramic Glazed Tiles (0.30m × 0.30m) 3,129.00 pcs. P 45.00 P 140,805.00
Portland Cement 68.00 bags 260.00 17,680.00
Tile Adhesive, 25kg 120.00 bags 310.00 37,200.00
Sand 10.00 cu.m. 600.00 6,000.00
Tile Grout 84.00 bags 180.00 15,120.00

C. SUB-TOTAL, MATERIAL ₱ 216,805.00

SUMMARY :
A. Equipment ₱ -
B. Labor ₱ 27,345.36
C. Materials ₱ 216,805.00
D. TOTAL DIRECT COST ₱ 244,150.36
DIRECT UNIT COST ₱ 867.01
E. OCM 12% of D ₱ 29,298.04
F. Profit 8% of D ₱ 19,532.03
G. VAT 5% of (D+E+F) ₱ 14,649.02
H. Total Cost (D+E+F+G) ₱ 307,629.45
I. Unit Cost H/Quantity ₱ 1,092.43
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino

Item No. : 1018 (2) Quantity : 8.58


Description : Unglazed Tiles Unit : sq.m.

oduction Output : 0.1950 sq.m. /hr.


rd. Output/gang : 3.1200 sq.m. /hr.
No. of Hours : 2.75 hrs.
No. of Days : 0.50 days
No. of Gang : 4.00 gang

A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)

A. SUB-TOTAL, EQUIPMENT ₱ -

B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Mason 8.00 2.75 ₱ 58.76 ₱ 1,292.72
Laborer 8.00 2.75 45.25 995.50

B. SUB-TOTAL, LABOR ₱ 2,288.22

C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
Ceramic Unglazed Tiles (0.30 x 0.30) 96.00 pcs. ₱ 70.00 ₱ 6,720.00
Portland Cement 2.00 bags 260.00 520.00
Tile Adhesive, 25kg 4.00 bags 350.00 1,400.00
Sand 1.00 cu.m. 579.52 579.52
Tile Grout 3.00 bags 180.00 540.00

C. SUB-TOTAL, MATERIAL ₱ 9,759.52

SUMMARY :
A. Equipment ₱ -
B. Labor ₱ 2,288.22
C. Materials ₱ 9,759.52
D. TOTAL DIRECT COST ₱ 12,047.74
DIRECT UNIT COST ₱ 1,404.17
E. OCM 12% of D ₱ 1,445.73
F. Profit 8% of D ₱ 963.82
G. VAT 5% of (D+E+F) ₱ 722.86
H. Total Cost (D+E+F+G) ₱ 15,180.15
I. Unit Cost H/Quantity ₱ 1,769.25
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino

Item No. : 1027 (1) Quantity : 1,089.90


Description : Cement Plaster Finish Unit : sq.m.

oduction Output : 4.7500 sq.m. /hr.


rd. Output/gang : 19.0000 sq.m. /hr.
No. of Hours : 57.50 hrs.
No. of Days : 7.25 days
No. of Gang : 4.00 gang

A. Name and Capacity of Equipment (OperatNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)

A. SUB-TOTAL, EQUIPMENT ₱ -

B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Mason 8.00 57.50 ₱ 58.76 ₱ 27,029.60
Laborer 8.00 57.50 45.25 20,815.00

B. SUB-TOTAL, LABOR ₱ 47,844.60

C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
Factor
Portland Cement 0.360 393.00 bags ₱ 260.00 ₱ 102,180.00
Fine Aggregates 0.021 23.00 cu.m. 579.52 13,328.96

C. SUB-TOTAL, MATERIAL ₱ 115,508.96

SUMMARY :
A. Equipment ₱ -
B. Labor ₱ 47,844.60
C. Materials ₱ 115,508.96
D. TOTAL DIRECT COST ₱ 163,353.56
DIRECT UNIT COST ₱ 149.88
E. OCM 12% of D ₱ 19,602.43
F. Profit 8% of D ₱ 13,068.28
G. VAT 5% of (D+E+F) ₱ 9,801.21
H. Total Cost (D+E+F+G) ₱ 205,825.49
I. Unit Cost H/Quantity ₱ 188.85
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino

Item No. : 1032 (1) a Quantity : 1,089.00


Description : Painting Works (Masonry/Concrete) Unit : sq.m.

Masonry
oduction Output : 6.2700 sq.m. /hr.
rd. Output/gang : 18.810 sq.m. /hr.
No. of Hours : 58.00 hrs.
No. of Days : 7.25 days
No. of Gang : 3.00 gang

A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)

A. SUB-TOTAL, EQUIPMENT ₱ -

B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Painter 6.00 58.00 ₱ 58.76 ₱ 20,448.48
Laborer 3.00 58.00 45.25 7,873.50

B. SUB-TOTAL, LABOR ₱ 28,321.98

C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
Concrete Neutralizer 51.00 gals. ₱ 550.00 ₱ 28,050.00
Flat Latex Paint (white) 80.00 gals. 550.00 44,000.00
Gloss Latex Paint (white) 80.00 gals. 500.00 40,000.00
Tinting Color 24.00 qrt. 55.00 1,320.00
Masonry Putty 50.00 gals. 400.00 20,000.00
Paint Thinner 12.00 glas 200.00 2,400.00
#120 Sand Paper 41.00 pcs. 30.00 1,230.00
3M Sand Paper 41.00 pcs. 120.00 4,920.00
Paint Roller w/ Tray 5.00 sets 250.00 1,250.00
Paint Brush 4" 5.00 pcs. 75.00 375.00
Paint Brush 2" 12.00 pcs. 60.00 720.00
Paleta 4" 12.00 pairs 65.00 780.00
C. SUB-TOTAL, MATERIAL ₱ 145,045.00

SUMMARY :

A. Equipment ₱ -
B. Labor ₱ 28,321.98
C. Materials ₱ 145,045.00
D. TOTAL DIRECT COST ₱ 173,366.98
DIRECT UNIT COST ₱ 159.20
E. OCM 12% of D ₱ 20,804.04
F. Profit 8% of D ₱ 13,869.36
G. VAT 5% of (D+E+F) ₱ 10,402.02
H. Total Cost (D+E+F+G) ₱ 218,442.39
I. Unit Cost H/Quantity ₱ 200.59
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino

Item No. : 1032 (1) b Quantity : 366.30


Description : Painting Works (Wood) Unit : sq.m.

Masonry
oduction Output : 5.7600 sq.m. /hr.
rd. Output/gang : 5.760 sq.m. /hr.
No. of Hours : 63.75 hrs.
No. of Days : 8.00 days
No. of Gang : 1.00 gang

A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)

A. SUB-TOTAL, EQUIPMENT ₱ -

B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Painter 2.00 63.75 ₱ 58.76 ₱ 7,491.90
Laborer 1.00 63.75 45.25 2,884.69

B. SUB-TOTAL, LABOR ₱ 10,376.59

C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
Enamel, Flatwall 40.00 gals. ₱ 550.00 ₱ 22,000.00
Enamel, Semi Gloss 35.00 gals. 600.00 21,000.00
Tinting Color 7.00 qrt. 55.00 385.00
Lacquer Thinner 4.00 gals. 415.00 1,660.00
Paint Thinner 7.00 gals. 200.00 1,400.00
Glazing Putty 37.00 gals. 600.00 22,200.00
Sand Paper 61.00 ln.m. 50.00 3,050.00
Paint Brush 2" 1.00 pcs. 60.00 60.00
Paleta 4" 40.00 pcs. 65.00 2,600.00

C. SUB-TOTAL, MATERIAL ₱ 74,355.00

SUMMARY :
A. Equipment ₱ -
B. Labor ₱ 10,376.59
C. Materials ₱ 74,355.00
D. TOTAL DIRECT COST ₱ 84,731.59
DIRECT UNIT COST ₱ 231.32
E. OCM 12% of D ₱ 10,167.79
F. Profit 8% of D ₱ 6,778.53
G. VAT 5% of (D+E+F) ₱ 5,083.90
H. Total Cost (D+E+F+G) ₱ 106,761.80
I. Unit Cost H/Quantity ₱ 291.46
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino

Item No. : 1032 (1) a3 Quantity : 34.38


Description : Painting Works (Steel) Unit : sq.m.

oduction Output : 6.2700 sq.m. /hr.


rd. Output/gang : 12.540 sq.m. /hr.
No. of Hours : 2.75 hrs.
No. of Days : 4.00 days
No. of Gang : 2.00 gang

A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)

A. SUB-TOTAL, EQUIPMENT ₱ -

B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Painter 4.00 2.75 ₱ 58.76 ₱ 646.36
Laborer 2.00 2.75 45.25 248.88

B. SUB-TOTAL, LABOR ₱ 895.24

C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
Red Lead Primer 10.00 gals. ₱ 675.00 ₱ 6,750.00
QDE Choco Brown 10.00 gals. 675.00 6,750.00
Paint Brush 3" 2.00 pcs 60.00 120.00
Paint Brush 1" 2.00 pcs 50.00 100.00
Paint Thinner 3.00 gals. 275.00 825.00

C. SUB-TOTAL, MATERIAL ₱ 14,545.00

SUMMARY :
A. Equipment ₱ -
B. Labor ₱ 895.24
C. Materials ₱ 14,545.00
D. TOTAL DIRECT COST ₱ 15,440.24
DIRECT UNIT COST ₱ 449.11
E. OCM 12% of D ₱ 1,389.62
F. Profit 8% of D ₱ 1,235.22
G. VAT 5% of (D+E+F) ₱ 903.25
H. Total Cost (D+E+F+G) ₱ 18,968.33
I. Unit Cost H/Quantity ₱ 551.73
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino

Item No. : 1039(1) Quantity : 13.28


Description : Aluminum Cladding Unit : sq.m

oduction Output : 4.1826 sq.m /hr.


rd. Output/gang : 4.1826 sq.m /hr.
No. of Hours : 3.25 hrs.
No. of Days : 0.50 days
No. of Gang : 1.00 gang

A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)

A. SUB-TOTAL, EQUIPMENT ₱ -

B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Foreman 1.00 3.25 ₱ 81.30 ₱
Carpenter 4.00 3.25 ₱ 58.76 ₱
Laborer 6.00 3.25 ₱ 45.25 ₱

B. SUB-TOTAL, LABOR ₱ -

C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
ACP Cladding on Frames 13.28 sq.m. ₱ 3,500.00 ₱

C. SUB-TOTAL, MATERIAL ₱ -

SUMMARY :
A. Equipment ₱ -
B. Labor ₱ -
C. Materials ₱ -
D. TOTAL DIRECT COST ₱ -
DIRECT UNIT COST ₱ -
E. OCM 12% of D ₱ -
F. Profit 8% of D ₱ -
G. VAT 5% of (D+E+F) ₱ -
H. Total Cost (D+E+F+G) ₱ -
I. Unit Cost H/Quantity ₱ -
Construction of Machinery Shed

Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino

ESTIMATED COST OF PROPOSED WORK

D
ITEM DESCRIPTION % QTTY. UNIT
TOTAL
PART II OTHER GENERAL REQUIREMENTS
B.5 Project Billboard/Signboard1 0.07 1.00 each 2,5
B.7 Occupational Safety & Health Program2 1.37 7.00 month 53,4
B.9 Mobilization/Demobilization2 0.98 1.00 lump sum 38,1
TOTAL OF PART II 2.41 94,14
PART III CIVIL, MECHANICAL, ELECTRICAL & SANITARY/PLUMBING WORKS
DIVISION I - GENERAL
PART A EARTHWORKS
803 (1) a Structure Excavation (Common Soil) 0.38 81.35 cu.m. 14,7
804 (1) b Embankment (From Borrow) 1.51 144.96 cu.m. 59,0
804 (4) Gravel Fill 0.62 31.50 cu.m. 24,3
PART B PLAIN & REINFORCED CONCRETE WORKS
900 (1) c2 Structural Concrete (Footings and Slab on Fill) 7.87 61.67 cu.m. 307,2
900 (1) c3 Structural Concrete (Tie Beam) 0.47 3.34 cu.m. 18,2
900 (1) c5 Structural Concrete (Columns) 2.22 12.14 cu.m. 86,7
900 (1) c6 Structural Concrete (Beams/Girders) 1.71 9.69 cu.m. 66,9
902 (1)a1 Reinforcing Steel (Deformed, Grade 40) 11.54 6,001.34 kgs. 450,3
903 (1) Formworks and Falseworks 5.59 1.00 l.s. 218,3
DIVISION II - BUILDINGS
PART C FINISHING
1000(1) Soil Poisoning 0.11 20.00 liters 4,3
31.92 1,250,37

Prepared by:

CRISTOBAL B. LASLAS
Civil Engineer

Recommending Approval:

DENNIS S. OPIANO
OIC - Director, Physical Plant
Site Development

Page 127 of 188


Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino

ESTIMATED COST OF PROPOSED WORK


D
ITEM DESCRIPTION % QTTY. UNIT
TOTAL
1001(8) Sewer Line Works 0.44 1.00 l.s 16,9
1001(9) Storm Drainage and Downspout 1.00 l.s 26,7
1001 (6) b Catch Basin - CHB 2.55 12.00 each 99,5
1002 (8) Plumbing Fixtures 1.97 1.00 l.s 76,9
1002 (28) Cold Water Line 0.79 1.00 l.s 30,9
1003 (1)a1 Ceiling (Metal Frame) 8.52 468.51 sq.m. 332,8
1006 (6) Steel Doors and Frames 1.45 17.00 l.s 56,5
1004 (2) a Finishing Hardware (Lockset) 0.98 23.00 sets 38,2
1004 (2) g Finishing Hardware (Hinges) 0.17 110.00 sets 6,4
1005 (6) Steel Window 2.93 38.88 sq.m 114,2
1010 (2) b Doors (Wood Panel) 1.09 26.46 sq.m. 42,6
1013 (2) a Fabricated Metal Roofing Accessory (Ridge/Hip Rolls) 0.30 48.40 ln.m. 11,8
1013 (2) b Fabricated Metal Roofing Accessory (Flashings) 0.20 33.60 ln.m. 7,6
1014 (1) b2 Prepainted Metal Sheets 5.84 518.42 sq.m. 227,8
1018(1) Glazed Tiles and Trims 6.25 281.60 sq.m 244,1
1018 (2) Unglazed Tiles 0.31 8.58 sq.m. 12,0
1027 (1) Cement Plaster Finish 4.18 1,089.90 sq.m. 163,3
32.22 1,508,98

Prepared by:

CRISTOBAL B. LASLAS
Civil Engineer

Recommending Approval:

DENNIS S. OPIANO
OIC - Director, Physical Plant
Site Development

Page 128 of 188


Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino

ESTIMATED COST OF PROPOSED WORK


D
ITEM DESCRIPTION % QTTY. UNIT
TOTAL
1032 (1) a Painting Works (Masonry/Concrete) 4.44 1,089.00 sq.m. 173,3
1032 (1) b Painting Works (Wood) 2.17 366.30 sq.m. 84,7
1043(1) PVC Doors and Frames 0.36 2.52 sq.m 13,8
1046 (2) a1 CHB Non Load Bearing (including Reinforcing Steel, 100mm) 3.24 164.31 sq.m. 126,3
1046 (2) a2 CHB Non Load Bearing (including Reinforcing Steel, 125mm) 4.18 308.00 sq.m. 163,2
1047 (2) b Structural Steel (Trusses) 0.70 216.67 kgs. 27,3
1047 (2) c Structural Steel (Purlins) 3.56 1,457.40 kgs. 139,0
1047 (3) a Metal Structure Accessories (Bolts) 0.16 120.00 pcs. 6,1
1047 (3) b Metal Structure Accessories (Sagrods) 0.20 34.00 pcs. 7,8
1047 (5) b Metal Structure Accessories (Steel Plates) 0.54 226.08 kgs. 20,9

N. ELECTRICAL WORKS
1100 (30) Conduits, Boxes & Fittings 0.78 1.00 l.s. 30,4
1101 (42) Wires and Wiring Devices 4.94 1.00 l.s. 193,0
1102 (1) b1 Panelboard with Main & Branch Breakers 0.23 1.00 sets 9,0
1103 (6) a1 LED Tube Lighting Fixture 1.42 42.00 sets 55,2

26.91 1,050,64
SUB-TOTAL 3,810,00
100.00 TOTAL 3,904,15

Prepared by:

CRISTOBAL B. LASLAS
Civil Engineer

Recommending Approval:

DENNIS S. OPIANO
OIC - Director, Physical Plant
Site Development

Page 129 of 188


ion of Machinery Shed

barroguis Campus, Cabarroguis, Quirino

OST OF PROPOSED WORK

DIRECT COST ADJUSTED UNIT


COST
TOTAL UNIT COST

2,575.49 2,575.49 3,245.12


53,466.98 7,638.14 8,020.05
38,100.08 38,100.08 40,005.08
94,142.54 .

14,751.50 181.33 228.48


59,046.25 407.33 513.23
24,310.36 771.76 972.41

307,269.81 4,982.48 6,277.93


18,273.62 5,471.14 6,893.64
86,725.93 7,143.82 9,001.21
66,924.19 6,906.52 8,702.22
450,348.06 75.04 94.55
218,370.63 218,370.63 275,146.99

4,357.50 217.88 274.52


1,250,377.84

Checked & Reviewed by:

JEREMIAS A. PASCUAL
Chief, Planning & Design Section
DPWH Representative

Approved:

SAMUEL O. BENIGNO, Ph.D.


University President

Page 130 of 188


ion of Machinery Shed
barroguis Campus, Cabarroguis, Quirino

OST OF PROPOSED WORK


DIRECT COST ADJUSTED UNIT
COST
TOTAL UNIT COST
16,983.32 16,983.32 21,398.99
26,778.32 26,778.32 33,740.69
99,582.60 8,298.55 10,456.17
76,905.80 76,905.80 96,901.31
30,905.30 30,905.30 38,940.68
332,817.52 710.37 895.07
56,531.10 3,325.36 4,189.95
38,206.06 1,661.13 2,093.03
6,468.30 58.80 74.09
114,290.08 2,939.56 3,703.85
42,662.24 1,612.33 2,031.54
11,824.19 244.30 307.82
7,652.13 227.74 286.95
227,826.19 439.46 553.72
244,150.36 867.01 1,092.43
12,047.74 1,404.17 1,769.25
163,353.56 149.88 188.85
1,508,984.80

JEREMIAS A. PASCUAL
Chief, Planning & Design Section
DPWH Representative

Approved:

SAMUEL O. BENIGNO, Ph.D.


University Prsident

Page 131 of 188


ion of Machinery Shed
barroguis Campus, Cabarroguis, Quirino

OST OF PROPOSED WORK


DIRECT COST ADJUSTED UNIT
COST
TOTAL UNIT COST
173,366.98 159.20 200.59
84,731.59 231.32 291.46
13,876.36 5,506.49 6,938.18
126,305.36 768.70 968.56
163,272.65 530.11 667.93
27,369.09 126.32 159.16
139,044.55 95.41 120.21
6,153.24 51.28 64.61
7,818.50 229.96 289.74
20,912.16 92.50 116.55

30,430.00 30,430.00 38,341.80


193,005.00 193,005.00 243,186.30
9,075.20 9,075.20 11,434.75
55,284.21 1,316.29 1,658.53

1,050,644.88
3,810,007.52
3,904,150.06

Checked and Reviewed by:

JEREMIAS A. PASCUAL
Chief, Planning & Design Section
DPWH Representative

Approved:

SAMUEL O. BENIGNO, Ph.D.


University President

Page 132 of 188


Republic of the Philippines
QUIRINO STATE UNIVERSITY
Diffun, Quirino

PROGRAM OF WORK / BUDGET COST

Project : Construction of Machinery Shed Date : 25-Mar-19


Description : Construction of Machinery Shed

Location : QSU, Cabarroguis Campus, Net Length :


Cabarroguis, Quirino Dimension :
Appropriation : ₱ 5,000,000.00 Thickness :
Estd. Proj. Cost : ₱ 5,000,000.00 Classification : Building
Source of Fund : Department of Budget & Management Starting Date : Upon Approval
Limits : Total Proj. Duration : 210 CD

% OF EQUIPMENT
DESCRIPTION OF WORKS TO BE DONE
TOTAL DESCRIPTION REQUIRED
PART II-OTHER GENERAL REQUIREMENTS 0.17
PART III-CIVIL, MECHANICAL, ELECTRICAL 0.83
AND SANITARY/PLUMBING WORKS
TOTAL 100.00%
ESTIMATED COST OF THE PROJECT

DESCRIPTION QTTY. AMOUNT TOTAL


PART II-OTHER GENERAL REQUIREMENTS ₱ 94,142.54
PART III-CIVIL, MECHANICAL, ELECTRICAL ₱ 3,810,007.52
AND SANITARY/PLUMBING WORKS
TOTAL ₱ 3,904,150.06

BREAKDOWN OF EXPENDITURE :

1. Labor ₱ 767,901.33 A. Total Direct Cost ₱ 3,904,150.06


2. Materials ₱ 2,961,786.66 B. Mark up ₱ 762,516.60
3. Rental of Equipment ₱ 136,362.00 C. VAT ₱ 233,333.33
4. Mob./Demob. (1% of Civil Works) ₱ 38,100.08 D. Cost of Engineering, 1.5% ₱ 100,000.00
5. Total Direct Cost ₱ 3,904,150.06 E. ROW Acquisition Cost ₱ -
6. OCM & Profit ₱ 762,516.60 F. Total Estimated Cost ₱ 5,000,000.00
7. VAT ₱ 233,333.33
8. Engineering Overhead ₱ 100,000.00
9. ROW Acquisition ₱
10. Total ₱ 5,000,000.00

Prepared by: Checked and Reviewed by:

CRISTOBAL B. LASLAS JEREMIAS A. PASCUAL


Civil Engineer Chief, Planning & Design Section
DPWH Representaive

Recommending Approval: Approved:


DENNIS S. OPIANO SAMUEL O. BENIGNO, Ph.D.
OIC - Director, Physical Plant University President
& Site Development
APPROVED BUDGET FOR THE CONTRACT

Construction of Machinery Shed


Quirino State University, Diffun Campus, Diffun, Quirino
(Project Name & Location)
MARK-UP IN
EST. DIRECT TOTAL MARK-UP
ITEM DESCRIPTION QTTY. UNIT PERCENT
COST
OCM PROFIT % VALUE
(9)
(1) (2) (3) (4) (5) (6) (7) (8)
(5)×(8)
PART II OTHER GENERAL REQUIREMENTS
B.5 Project Billboard/Signboard 1.00 each 2,575.49 12% 8% 20% 515.10
B.7 Occupational Safety & Health Program 7.00 months 53,466.98 0% 0% 0% -
B.9 Mobilization/Demobilization 1.00 l.s. 38,100.08 0% 0% 0% -
TOTAL OF PART II 94,142.54
PART III CIVIL, MECHANICAL, ELECTRICAL
& SANITARY/PLUMBING WORKS
DIVISION I - GENERAL
PART A EARTHWORKS
803 (1) a Structure Excavation (Common Soil) 81.35 cu.m. 14,751.50 12% 8% 20% 2,950.30
804 (1) b Embankment (From Borrow) 144.96 cu.m. 59,046.25 12% 8% 20% 11,809.25
804 (4) Gravel Fill 31.50 cu.m. 24,310.36 12% 8% 20% 4,862.07
PART B PLAIN & REINFORCED CONCRETE WORKS
900 (1) c2 Structural Concrete (Footings and Slab on Fill) 61.67 cu.m. 307,269.81 12% 8% 20% 61,453.96
900 (1) c3 Structural Concrete (Tie Beam) 3.34 cu.m. 18,273.62 12% 8% 20% 3,654.72
900 (1) c5 Structural Concrete (Columns) 12.14 cu.m. 86,725.93 12% 8% 20% 17,345.19
900 (1) c6 Structural Concrete (Beams/Girders) 9.69 cu.m. 66,924.19 12% 8% 20% 13,384.84
902 (1)a1 Reinforcing Steel (Deformed, Grade 40) 6,001.34 kgs. 450,348.06 12% 8% 20% 90,069.61
903 (1) Formworks and Falseworks 1.00 l.s. 218,370.63 12% 8% 20% 43,674.13
DIVISION II - BUILDINGS
PART C FINISHING
1000(1) Soil Poisoning 20.00 liters 4,357.50 12% 8% 20% 871.50
###

Prepared by :

CRISTOBAL B. LASLAS
Civil Engineer

Recommending Approval:

DENNIS S. OPIANO
OIC - Director, Physical Plant &
Site Development

Page 135 of 188


Construction of Machinery Shed
Quirino State University, Diffun Campus, Diffun, Quirino
(Project Name & Location)
MARK-UP IN
EST. DIRECT TOTAL MARK-UP
ITEM DESCRIPTION QTTY. UNIT PERCENT
COST
OCM PROFIT % VALUE
(9) =
(1) (2) (3) (4) (5) (6) (7) (8)
(5)×(8)
1001(8) Sewer Line Works 1.00 l.s 16,983.32 12% 8% 20% 3,396.66
1001(9) Storm Drainage and Downspout 1.00 l.s 26,778.32 12% 8% 20% 5,355.66
1001 (6) b Catch Basin - CHB 12.00 each 99,582.60 12% 8% 20% 19,916.52
1002 (8) Plumbing Fixtures 1.00 l.s 76,905.80 12% 8% 20% 15,381.16
1002 (28) Cold Water Line 1.00 l.s 30,905.30 12% 8% 20% 6,181.06
1003 (1)a1 Ceiling (Metal Frame) 468.51 sq.m. 332,817.52 12% 8% 20% 66,563.50
1006 (6) Steel Doors and Frames 17.00 l.s 56,531.10 12% 8% 20% 11,306.22
1004 (2) a Finishing Hardware (Lockset) 23.00 sets 38,206.06 12% 8% 20% 7,641.21
1004 (2) g Finishing Hardware (Hinges) 110.00 sets 6,468.30 12% 8% 20% 1,293.66
1005 (6) Steel Window 38.88 sq.m 114,290.08 12% 8% 20% 22,858.02
1010 (2) b Doors (Wood Panel) 26.46 sq.m. 42,662.24 12% 8% 20% 8,532.45
1013 (2) a Fabricated Metal Roofing Accessory (Ridge/Hip Rolls) 48.40 ln.m. 11,824.19 12% 8% 20% 2,364.84
1013 (2) b Fabricated Metal Roofing Accessory (Flashings) 33.60 ln.m. 7,652.13 12% 8% 20% 1,530.43
1014 (1) b2 Prepainted Metal Sheets 518.42 sq.m. 227,826.19 12% 8% 20% 45,565.24
1018 (2) Unglazed Tiles 8.58 sq.m. 12,047.74 12% 8% 20% 2,409.55
1018(1) Glazed Tiles and Trims 281.60 sq.m 244,150.36 12% 8% 20% 48,830.07
1027 (1) Cement Plaster Finish 1,089.90 sq.m. 163,353.56 12% 8% 20% 32,670.71
###

Prepared by :

CRISTOBAL B. LASLAS
Civil Engineer

Recommending Approval:

DENNIS S. OPIANO
OIC - Director, Physical Plant &
Site Development

Page 136 of 188


Construction of Machinery Shed
Quirino State University, Diffun Campus, Diffun, Quirino
(Project Name & Location)
MARK-UP IN
EST. DIRECT TOTAL MARK-UP
ITEM DESCRIPTION QTTY. UNIT PERCENT
COST
OCM PROFIT % VALUE
(9) =
(1) (2) (3) (4) (5) (6) (7) (8)
(5)×(8)
1032 (1) a Painting Works (Masonry/Concrete) 1,089.00 sq.m. 173,366.98 12% 8% 20% 34,673.40
1032 (1) b Painting Works (Wood) 366.30 sq.m. 84,731.59 12% 8% 20% 16,946.32
1043(1) PVC Doors and Frames 2.52 sq.m 13,876.36 12% 8% 20% 2,775.27
1046 (2) a1 CHB Non Load Bearing (including Reinforcing Steel, 100mm) 164.31 sq.m. 126,305.36 12% 8% 20% 25,261.07
1046 (2) a2 CHB Non Load Bearing 308.00 sq.m. 163,272.65 12% 8% 20% 32,654.53
1047 (2) b Structural Steel (Trusses) 216.67 kgs. 27,369.09 12% 8% 20% 5,473.82
1047 (2) c Structural Steel (Purlins) 1,457.40 kgs. 139,044.55 12% 8% 20% 27,808.91
1047 (3) a Metal Structure Accessories (Bolts) 120.00 pcs. 6,153.24 12% 8% 20% 1,230.65
1047 (3) b Metal Structure Accessories (Sagrods) 34.00 pcs. 7,818.50 12% 8% 20% 1,563.70
1047 (5) b Metal Structure Accessories (Steel Plates) 226.08 kgs. 20,912.16 12% 8% 20% 4,182.43

N. ELECTRICAL WORKS
1100 (30) Conduits, Boxes & Fittings 1.00 l.s. 30,430.00 12% 8% 20% 6,086.00
1101 (42) Wires and Wiring Devices 1.00 l.s. 193,005.00 12% 8% 20% 38,601.00
1102 (1) b1 Panelboard with Main & Branch Breakers 1.00 sets 9,075.20 12% 8% 20% 1,815.04
1103 (6) a1 LED Tube Lighting Fixture 42.00 sets 55,284.21 12% 8% 20% 11,056.84

###

Prepared by:

CRISTOBAL B. LASLAS
Civil Engineer

Recommending Approval:

DENNIS S. OPIANO
OIC - Director, Physical Plant &
Site Development

Page 137 of 188


UDGET FOR THE CONTRACT

tion of Machinery Shed


sity, Diffun Campus, Diffun, Quirino
ect Name & Location)
TOTAL
TOTAL MARK-UP
VAT INDIRECT TOTAL COST UNIT COST
VALUE COST
(9) (10) 5% (11) (12) (13)
(5)×(8) [(5)+(9)] (9)+(10) (5)+(11) (12)÷(3)

515.10 154.53 669.63 3,245.12 3,245.12


- 2,673.35 2,673.35 56,140.33 8,020.05
- 1,905.00 1,905.00 40,005.08 40,005.08
4,732.88 5,247.98 99,390.52

2,950.30 885.09 3,835.39 18,586.89 228.48


11,809.25 3,542.78 15,352.03 74,398.28 513.23
4,862.07 1,458.62 6,320.69 30,631.05 972.41

61,453.96 18,436.19 79,890.15 387,159.96 6,277.93


3,654.72 1,096.42 4,751.14 23,024.76 6,893.64
17,345.19 5,203.56 22,548.74 109,274.67 9,001.21
13,384.84 4,015.45 17,400.29 84,324.48 8,702.22
90,069.61 27,020.88 117,090.50 567,438.56 94.55
43,674.13 13,102.24 56,776.36 275,146.99 275,146.99
-

871.50 261.45 1,132.95 5,490.45 274.52


325,098.24 1,575,476.08

Checked & Reviewed by:

JEREMIAS A. PASCUAL
Chief, Planning & Design Section
DPWH Representative

Approved:

SAMUEL O. BENIGNO, Ph.D.


University President

Page 138 of 188


tion of Machinery Shed
sity, Diffun Campus, Diffun, Quirino
ect Name & Location)
TOTAL
TOTAL MARK-UP
VAT INDIRECT TOTAL COST UNIT COST
VALUE COST
(9) = (10) = (11) = (12) = (13) =
(5)×(8) 5%[(5)+(9)] (9)+(10) (5)+(11) (12)÷(3)
3,396.66 1,019.00 4,415.66 21,398.98 21,398.99
5,355.66 1,606.70 6,962.36 33,740.68 33,740.69
19,916.52 5,974.96 25,891.48 125,474.08 10,456.17
15,381.16 4,614.35 19,995.51 96,901.31 96,901.31
6,181.06 1,854.32 8,035.38 38,940.68 38,940.68
66,563.50 19,969.05 86,532.56 419,350.08 895.07
11,306.22 3,391.87 14,698.09 71,229.19 4,189.95
7,641.21 2,292.36 9,933.58 48,139.64 2,093.03
1,293.66 388.10 1,681.76 8,150.05 74.09
22,858.02 6,857.40 29,715.42 144,005.50 3,703.85
8,532.45 2,559.73 11,092.18 53,754.42 2,031.54
2,364.84 709.45 3,074.29 14,898.47 307.82
1,530.43 459.13 1,989.55 9,641.68 286.95
45,565.24 13,669.57 59,234.81 287,061.00 553.72
2,409.55 722.86 3,132.41 15,180.15 1,769.25
48,830.07 14,649.02 63,479.09 307,629.45 1,092.43
32,670.71 9,801.21 42,471.93 205,825.49 188.85
327,035.66 1,901,320.85

Checked & Reviewed by:

JEREMIAS A. PASCUAL
Chief, Planning & Design Section
DPWH Representative

Approved:

SAMUEL O. BENIGNO, Ph.D.


University President

Page 139 of 188


tion of Machinery Shed
sity, Diffun Campus, Diffun, Quirino
ect Name & Location)
TOTAL
TOTAL MARK-UP
VAT INDIRECT TOTAL COST UNIT COST
VALUE COST
(9) = (10) = (11) = (12) = (13) =
(5)×(8) 5%[(5)+(9)] (9)+(10) (5)+(11) (12)÷(3)
34,673.40 10,402.02 45,075.41 218,442.39 200.59
16,946.32 5,083.90 22,030.21 106,761.80 291.46
2,775.27 832.58 3,607.85 17,484.21 6,938.18
25,261.07 7,578.32 32,839.39 159,144.75 968.56
32,654.53 9,796.36 42,450.89 205,723.54 667.93
5,473.82 1,642.15 7,115.96 34,485.05 159.16
27,808.91 8,342.67 36,151.58 175,196.13 120.21
1,230.65 369.19 1,599.84 7,753.08 64.61
1,563.70 469.11 2,032.81 9,851.30 289.74
4,182.43 1,254.73 5,437.16 26,349.32 116.55
-
-
6,086.00 1,825.80 7,911.80 38,341.80 38,341.80
38,601.00 11,580.30 50,181.30 243,186.30 243,186.30
1,815.04 544.51 2,359.55 11,434.75 11,434.75
11,056.84 3,317.05 14,373.89 69,658.10 1,658.53
-
-
273,167.67 1,323,812.52

TOTAL AMOUNT OF ABC 4,900,000.00

Checked & Reviewed by:

JEREMIAS A. PASCUAL
Chief, Planning & Design Section
DPWH Representative

Approved:

SAMUEL O. BENIGNO, Ph.D.


University President

Page 140 of 188


DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino

Item No. : 1043(1) Quantity : 2.52


Description : PVC Doors and Frames Unit : sq.m

oduction Output : 0.4726 sq.m /hr.


rd. Output/gang : 0.4726 sq.m /hr.
No. of Hours : 5.50 hrs.
No. of Days : 0.75 days
No. of Gang : 1.00 gang

A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)

A. SUB-TOTAL, EQUIPMENT ₱ -

B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Carpenter 2.00 5.50 ₱ 58.76 ₱ 646.36

B. SUB-TOTAL, LABOR ₱ 646.36

C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
D6 (3 - 2.1m.x0.6m.) PVC Doors 3.78 sq.m. ₱ 3,500.00 ₱ 13,230.00

C. SUB-TOTAL, MATERIAL ₱ 13,230.00

SUMMARY :
A. Equipment ₱ -
B. Labor ₱ 646.36
C. Materials ₱ 13,230.00
D. TOTAL DIRECT COST ₱ 13,876.36
DIRECT UNIT COST ₱ 5,506.49
E. OCM 12% of D ₱ 1,665.16
F. Profit 8% of D ₱ 1,110.11
G. VAT 5% of (D+E+F) ₱ 832.58
H. Total Cost (D+E+F+G) ₱ 17,484.21
I. Unit Cost H/Quantity ₱ 6,938.18
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino

Item No. : 1046 (2) a1 Quantity : 164.31


Description : CHB Non Load Bearing (including Reinforcing Steel, 100mm)
Unit : sq.m.

rd. Output/gang : 1.5939 sq.m. /hr.


oduction Output : 6.3756 sq.m. /hr.
No. of Hours : 26.00 hrs.
No. of Days : 3.25 days
No. of Gang : 4.00 gang

A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)

A. SUB-TOTAL, EQUIPMENT ₱ -

B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Construction Foreman 1.00 26.00 ₱ 81.30 ₱ 2,113.80
Mason 8.00 26.00 58.76 12,222.08
Laborer 4.00 26.00 45.25 4,706.00

B. SUB-TOTAL, LABOR ₱ 19,041.88

C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
Factor
100mm × 200mm × 400mm CHB 12.500 2,054.00 pcs. ₱ 12.00 ₱ 24,648.00
Portland Cement (Class C) 0.759 125.00 bags 260.00 32,500.00
Fine Aggregates 0.084 14.00 cu.m. 579.52 8,113.28
10mm Ø × 6.00m. RSB 1,015.93 kgs. 40.00 40,637.20
Tie Wire (2% of RSB) 21.00 kgs. 65.00 1,365.00

C. SUB-TOTAL, MATERIAL ₱ 107,263.48

SUMMARY :
A. Equipment ₱ -
B. Labor ₱ 19,041.88
C. Materials ₱ 107,263.48
D. TOTAL DIRECT COST ₱ 126,305.36
DIRECT UNIT COST ₱ 768.70
E. OCM 12% of D ₱ 15,156.64
F. Profit 8% of D ₱ 10,104.43
G. VAT 5% of (D+E+F) ₱ 7,578.32
H. Total Cost (D+E+F+G) ₱ 159,144.75
I. Unit Cost H/Quantity ₱ 968.56
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino

Item No. : 1046 (2) a2 Quantity : 308.00


Description : CHB Non Load Bearing Unit : sq.m.
(including Reinforcing Steel, 125mm)

rd. Output/gang : 1.5939 sq.m. /hr.


oduction Output : 6.3756 sq.m. /hr.
No. of Hours : 48.50 hrs.
No. of Days : 6.25 days
No. of Gang : 4.00 gang

A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)

A. SUB-TOTAL, EQUIPMENT ₱ -

B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Construction Foreman 1.00 16.17 ₱ 81.30 ₱ 1,314.35
Mason 8.00 48.50 58.76 22,798.88
Laborer 4.00 48.50 45.25 8,778.50

B. SUB-TOTAL, LABOR ₱ 32,891.73

C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
Factor
125mm × 200mm × 400mm CHB 12.500 3,502.00 pcs. ₱ 14.00 ₱ 49,028.00
Portland Cement (Class C) 0.759 234.00 bags 260.00 60,840.00
Fine Aggregates 0.084 26.00 cu.m. 579.52 15,067.52
10mm Ø × 6.00m. RSB 131.26 kgs. 40.00 5,250.40
Tie Wire (2% of RSB) 3.00 kgs. 65.00 195.00

C. SUB-TOTAL, MATERIAL ₱ 130,380.92

SUMMARY :
A. Equipment ₱ -
B. Labor ₱ 32,891.73
C. Materials ₱ 130,380.92
D. TOTAL DIRECT COST ₱ 163,272.65
DIRECT UNIT COST ₱ 530.11
E. OCM 12% of D ₱ 19,592.72
F. Profit 8% of D ₱ 13,061.81
G. VAT 5% of (D+E+F) ₱ 9,796.36
H. Total Cost (D+E+F+G) ₱ 205,723.54
I. Unit Cost H/Quantity ₱ 667.93
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino

Item No. : 1047 (2) b Quantity : 216.67


Description : Structural Steel (Trusses) Unit : kgs.

rd. Output/gang : ### kgs. /hr.


oduction Output : 54.0900 kgs. /hr.
No. of Hours : 4.25 hrs.
No. of Days : 0.75 days
No. of Gang : 3.00 gang

A. Name and Capacity of Equipment (OperateNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Welding Machine 2.00 4.25 ₱ 62.50 ₱ 531.25
Electric Bar Cutter 2.00 4.25 158.25 1,345.13

A. SUB-TOTAL, EQUIPMENT ₱ 1,876.38

B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Construction Foreman 1.00 1.42 ₱ 81.30 ₱ 115.18
Welder 12.00 4.25 58.76 2,996.76
Laborer 6.00 4.25 45.25 1,153.88

B. SUB-TOTAL, LABOR ₱ 4,265.81

C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
50-5mmx50mmx 50mm angle bar 188.50 kgs. ₱ 70.00 ₱ 13,195.00
10-5mmx38mmx 38mm angle bar 28.17 70.00 1,971.90
14" Cutting Disk 2.00 sets 250.00 500.00
Welding Rod 60.00 kgs. 65.00 3,900.00
Oxygen 1.00 tanks 300.00 300.00
Acetylene 1.00 tanks 650.00 650.00
Red Lead Primer 1.00 gals. 400.00 400.00
Paint Thinner 1.00 gals. 190.00 190.00
Paint brush 2" 2.00 pcs. 60.00 120.00

C. SUB-TOTAL, MATERIAL ₱ 21,226.90

SUMMARY :
A. Equipment ₱ 1,876.38
B. Labor ₱ 4,265.81
C. Materials ₱ 21,226.90
D. TOTAL DIRECT COST ₱ 27,369.09
DIRECT UNIT COST ₱ 126.32
E. OCM 12% of D ₱ 3,284.29
F. Profit 8% of D ₱ 2,189.53
G. VAT 5% of (D+E+F) ₱ 1,642.15
H. Total Cost (D+E+F+G) ₱ 34,485.05
I. Unit Cost H/Quantity ₱ 159.16
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino

Item No. : 1047 (2) c Quantity : 1,457.40


Description : Structural Steel (Purlins) Unit : kgs.

rd. Output/gang : 18.0300 kgs. /hr.


oduction Output : 36.0600 kgs. /hr.
No. of Hours : 40.50 hrs.
No. of Days : 5.25 days
No. of Gang : 2.00 gang

A. Name and Capacity of Equipment (Operated)


No. of UnitsNo. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Welding Machine 1.00 40.50 ₱ 391.00 ₱ 15,835.50
Electric Bar Cutter 1.00 40.50 158.25 6,409.13

A. SUB-TOTAL, EQUIPMENT ₱ 22,244.63

B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Construction Foreman 1.00 13.50 ₱ 81.30 ₱ 1,097.55
Welder 4.00 40.50 58.76 9,519.12
Laborer 2.00 40.50 45.25 3,665.25

B. SUB-TOTAL, LABOR ₱ 14,281.92

C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)

150mm x 65mm x 20mm x 3mm C-Purlins (with


Fascia Board) 848.40 kgs. ₱ 70.00 ₱ 59,388.00
100mm x 50mm x 15mm x 2mm C-Purlins 609.00 kgs. 70.00 42,630.00
14" Cutting Disk 2.00 set 250.00 500.00

C. SUB-TOTAL, MATERIAL ₱ 102,518.00

SUMMARY :
A. Equipment ₱ 22,244.63
B. Labor ₱ 14,281.92
C. Materials ₱ 102,518.00
D. TOTAL DIRECT COST ₱ 139,044.55
DIRECT UNIT COST ₱ 95.41
E. OCM 12% of D ₱ 16,685.35
F. Profit 8% of D ₱ 11,123.56
G. VAT 5% of (D+E+F) ₱ 8,342.67
H. Total Cost (D+E+F+G) ₱ 175,196.13
I. Unit Cost H/Quantity ₱ 120.21
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino

Item No. : 1047 (3) a Quantity : 120.00


Description : Metal Structure Accessories (Bolts) Unit : pcs.

rd. Output/gang : ### pcs. /hr.


oduction Output : 10.0000 pcs. /hr.
No. of Hours : 12.00 hrs.
No. of Days : 1.50 days
No. of Gang : 1.00 gang

A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)

A. SUB-TOTAL, EQUIPMENT ₱ -

B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Tinsmith 2.00 12.00 58.76 1,410.24
Laborer 1.00 12.00 45.25 543.00

B. SUB-TOTAL, LABOR ₱ 1,953.24

C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)

16mm dia. x 300mm Long Bend Anchor Bolt 120.00 pcs. ₱ 35.00 ₱ 4,200.00
with Nuts and Washer

C. SUB-TOTAL, MATERIAL ₱ 4,200.00

SUMMARY :
A. Equipment ₱ -
B. Labor ₱ 1,953.24
C. Materials ₱ 4,200.00
D. TOTAL DIRECT COST ₱ 6,153.24
DIRECT UNIT COST ₱ 51.28
E. OCM 12% of D ₱ 738.39
F. Profit 8% of D ₱ 492.26
G. VAT 5% of (D+E+F) ₱ 369.19
H. Total Cost (D+E+F+G) ₱ 7,753.08
I. Unit Cost H/Quantity ₱ 64.61
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino

Item No. : 1047 (3) b Quantity : 34.00


Description : Metal Structure Accessories (Sagrods) Unit : pcs.

rd. Output/gang : 10.0000 pcs. /hr.


oduction Output : 20.0000 pcs. /hr.
No. of Hours : 1.75 hrs.
No. of Days : 0.25 days
No. of Gang : 2.00 gang

A. Name and Capacity of Equipment (OperatNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)

A. SUB-TOTAL, EQUIPMENT ₱ -

B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Welder 4.00 1.75 ₱ 58.76 ₱ 411.32
Laborer 2.00 1.75 45.25 158.38

B. SUB-TOTAL, LABOR ₱ 569.70

C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
12mm dia. x 6m Plain Round Bar;Sag Rod 181.22 kgs. ₱ 40.00 ₱ 7,248.80
With Nuts and Washer

C. SUB-TOTAL, MATERIAL ₱ 7,248.80

SUMMARY :
A. Equipment ₱ -
B. Labor ₱ 569.70
C. Materials ₱ 7,248.80
D. TOTAL DIRECT COST ₱ 7,818.50
DIRECT UNIT COST ₱ 229.96
E. OCM 12% of D ₱ 938.22
F. Profit 8% of D ₱ 625.48
G. VAT 5% of (D+E+F) ₱ 469.11
H. Total Cost (D+E+F+G) ₱ 9,851.30
I. Unit Cost H/Quantity ₱ 289.74
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino

Item No. : 1047 (3) c Quantity : 10.00


Description : Metal Structure Accessories (Turnbuckle) Unit : pcs.

rd. Output/gang : 3.000 pcs. /hr.


oduction Output : 3.000 pcs. /hr.
No. of Hours : 3.50 hrs.
No. of Days : 0.50 days
No. of Gang : 1.00 gang

A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)

A. SUB-TOTAL, EQUIPMENT ₱ -

B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Skilled Labor 2.00 3.50 ₱ 58.76 ₱ 411.32
Laborer 1.00 3.50 45.25 158.38

B. SUB-TOTAL, LABOR ₱ 569.70

C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
Turn Buckle; 16mm dia. 10.00 pcs. ₱ 185.00 ₱ 1,850.00

C. SUB-TOTAL, MATERIAL ₱ 1,850.00

SUMMARY :
A. Equipment ₱ -
B. Labor ₱ 569.70
C. Materials ₱ 1,850.00
D. TOTAL DIRECT COST ₱ 2,419.70
DIRECT UNIT COST ₱ 241.97
E. OCM 12% of D ₱ 290.36
F. Profit 8% of D ₱ 193.58
G. VAT 5% of (D+E+F) ₱ 145.18
H. Total Cost (D+E+F+G) ₱ 3,048.82
I. Unit Cost H/Quantity ₱ 304.88
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino

Item No. : 1047 (4) Quantity : 33.28


Description : Metal Structure Accessories (Cross Bracing) Unit : kgs.

rd. Output/gang : ### kgs. /hr.


oduction Output : 15.0000 kgs. /hr.
No. of Hours : 2.25 hrs.
No. of Days : 0.50 days
No. of Gang : 1.00 gang

A. Name and Capacity of Equipment (OperatNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)

A. SUB-TOTAL, EQUIPMENT ₱ -

B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Welder 2.00 2.25 ₱ 58.76 ₱ 264.42
Laborer 1.00 2.25 45.25 101.81

B. SUB-TOTAL, LABOR ₱ 366.23

C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
Cross Bracing; 16mm dia. x 6m. Plain Bar 33.28 kgs. ₱ 40.00 ₱ 1,331.20

C. SUB-TOTAL, MATERIAL ₱ 1,331.20

SUMMARY :
A. Equipment ₱ -
B. Labor ₱ 366.23
C. Materials ₱ 1,331.20
D. TOTAL DIRECT COST ₱ 1,697.43
DIRECT UNIT COST ₱ 51.00
E. OCM 12% of D ₱ 203.69
F. Profit 8% of D ₱ 135.79
G. VAT 5% of (D+E+F) ₱ 101.85
H. Total Cost (D+E+F+G) ₱ 2,138.76
I. Unit Cost H/Quantity ₱ 64.27
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino

Item No. : 1047 (5) b Quantity : 226.08


Description : Metal Structure Accessories (Steel Plates) Unit : kgs.

rd. Output/gang : 7.2500 kgs. /hr.


oduction Output : 7.250 kgs. /hr.
No. of Hours : 31.25 hrs.
No. of Days : 4.00 days
No. of Gang : 1.00 gang

A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)

A. SUB-TOTAL, EQUIPMENT ₱ -

B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Welder 2.00 31.25 ₱ 58.76 ₱ 3,672.50
Laborer 1.00 31.25 45.25 1,414.06

B. SUB-TOTAL, LABOR ₱ 5,086.56

C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
Base Plate (10mm thk.) 226.08 kgs. ₱ 70.00 ₱ 15,825.60

C. SUB-TOTAL, MATERIAL ₱ 15,825.60

SUMMARY :
A. Equipment ₱ -
B. Labor ₱ 5,086.56
C. Materials ₱ 15,825.60
D. TOTAL DIRECT COST ₱ 20,912.16
DIRECT UNIT COST ₱ 92.50
E. OCM 12% of D ₱ 2,509.46
F. Profit 8% of D ₱ 1,672.97
G. VAT 5% of (D+E+F) ₱ 1,254.73
H. Total Cost (D+E+F+G) ₱ 26,349.32
I. Unit Cost H/Quantity ₱ 116.55
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino

Item No. : 1100 (30) Quantity : 1.00


Description : Conduits, Boxes & Fittings Unit : l.s.

oduction Output : 0.0400 l.s. /hr.


rd. Output/gang : 0.04 l.s. /hr.
No. of Hours : 25.00 hrs.
No. of Days : 3.25 days
No. of Gang : 1.00 gang

A. Name and Capacity of Equipment (OpeNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)

A. SUB-TOTAL, EQUIPMENT ₱ -

B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Electrician 2.00 18.00 ₱

No. of OutletUnit Cost per Outlet


1.00 ₱ 250.00 ₱ 250.00

B. SUB-TOTAL, LABOR ₱ 250.00

C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
Ceiling Receptacle Socket 4" dia 4.00 pcs ₱ 45.00 ₱ 180.00
Service Drop Wire twisted #2 100.00 meter 205.00 20,500.00
Entrance cap 75mm dia 1.00 pcs 200.00 200.00
PVC Junction Box 4x4 w/ cover 35.00 pcs 35.00 1,225.00
Utility Box Metal deep type 85.00 pcs 35.00 2,975.00
Moldflex 20mm x 100m 6.00 rolls 850.00 5,100.00

C. SUB-TOTAL, MATERIAL ₱ 30,180.00

SUMMARY :
A. Equipment ₱ -
B. Labor ₱ 250.00
C. Materials ₱ 30,180.00
D. TOTAL DIRECT COST ₱ 30,430.00
DIRECT UNIT COST ₱ 30,430.00
E. OCM 12% of D ₱ 3,651.60
F. Profit 8% of D ₱ 2,434.40
G. VAT 5% of (D+E+F) ₱ 1,825.80
H. Total Cost (D+E+F+G) ₱ 38,341.80
I. Unit Cost H/Quantity ₱ 38,341.80
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino

Item No. : 1101 (42) Quantity : 1.00


Description : Wires and Wiring Devices Unit : l.s.

oduction Output : 9.0000 l.s. /hr.


rd. Output/gang : 9.00 l.s. /hr.
No. of Hours : 0.25 hrs.
No. of Days : 0.25 days
No. of Gang : 1.00 gang

A. Name and Capacity of Equipment (Opera


No. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)

A. SUB-TOTAL, EQUIPMENT ₱ -

B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Electrician 3.00 40.00

No. of OutletUnit Cost per Outlet


67.00 ₱ 250.00 ₱ 50,250.00

B. SUB-TOTAL, LABOR ₱ 50,250.00

C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
Electric Wire 2.0mm² THHN 6.00 boxes ₱ 2,700.00 ₱ 16,200.00
Electric Wire3.5mm² THHN 7.00 boxes 3,300.00 23,100.00
Electric Wire 5.5mm² THHN 5.00 boxes 4,250.00 21,250.00
Electric Wire 50.0mm² THHN 60.00 mtrs 375.00 22,500.00
Duplex Convenience Outlets, Grounding Type 46.00 sets 150.00 6,900.00
Orbit fan Standard E-16 18.00 sets 1,200.00 21,600.00
Two Gang Single Pole Switch Wide Series 4.00 sets 155.00 620.00
One Gang Single Pole Switch Wide Series 5.00 sets 65.00 325.00
Three way, three gang switch w/ plate (widw 12.00 sets 195.00 2,340.00
Electrical Tape, Big 25.00 rolls 30.00 750.00
Ground Rod 5/8 x10' 1.00 pc 686.00 686.00
Ground Clamp 5/8 2.00 pcs 42.00 84.00
Service drop wire #04 Twisted 200.00 mtrs 120.00 24,000.00
Exhaust Fan 12" x 12" Ceiling Type 2.00 sets 1,200.00 2,400.00

C. SUB-TOTAL, MATERIAL ₱ 142,755.00

SUMMARY :
A. Equipment ₱ -
B. Labor ₱ 50,250.00
C. Materials ₱ 142,755.00
D. TOTAL DIRECT COST ₱ 193,005.00
DIRECT UNIT COST ₱ 193,005.00
E. OCM 12% of D ₱ 23,160.60
F. Profit 8% of D ₱ 15,440.40
G. VAT 5% of (D+E+F) ₱ 11,580.30
H. Total Cost (D+E+F+G) ₱ 243,186.30
I. Unit Cost H/Quantity ₱ 243,186.30
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino

Item No. : 1102 (1) b1 Quantity : 1.00


Description : Panelboard with Main & Branch Breakers Unit : sets

rd. Output/gang : 0.0500 sets /hr.


oduction Output : 0.05 sets /hr.
No. of Hours : 20.00 hrs.
No. of Days : 2.50 days
No. of Gang : 1.00 gang

A. Name and Capacity of Equipment (OperateNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)

A. SUB-TOTAL, EQUIPMENT ₱ -

B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Electrician 1.00 20.00 ₱ 58.76 ₱ 1,175.20

B. SUB-TOTAL, LABOR ₱ 1,175.20

C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)

Panel box Bolt on type, single phase, center main 1.00 assembly ₱ 500.00 ₱ 500.00
w/ 20 branches
1 pair Main Circuit Breaker 125 amp (GE) 1.00 pairs 1,000.00 1,000.00
6 pairs Branches Circuit Breaker 15 amp (GE) 6.00 pairs 320.00 1,920.00
5 pairs Branches Circuit Breaker 20 amp (GE) 5.00 pairs 320.00 1,600.00
9 pairs Branches Circuit Breaker 30 amp (GE) 9.00 pairs 320.00 2,880.00

C. SUB-TOTAL, MATERIAL ₱ 7,900.00

SUMMARY :
A. Equipment ₱ -
B. Labor ₱ 1,175.20
C. Materials ₱ 7,900.00
D. TOTAL DIRECT COST ₱ 9,075.20
DIRECT UNIT COST ₱ 9,075.20
E. OCM 12% of D ₱ 1,089.02
F. Profit 8% of D ₱ 726.02
G. VAT 5% of (D+E+F) ₱ 544.51
H. Total Cost (D+E+F+G) ₱ 11,434.75
I. Unit Cost H/Quantity ₱ 11,434.75
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino

Item No. : 1103 (6) a1 Quantity : 42.00


Description : LED Tube Lighting Fixture Unit : sets

rd. Output/gang : 2.0000 sets /hr.


oduction Output : 2.00 sets /hr.
No. of Hrs. : 21.00 hrs.
No. of Days : 2.75 days
No. of Gang : 1.00 gang

A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)

A. SUB-TOTAL, EQUIPMENT ₱ -

B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Electrician 1.00 21.00 ₱ 58.76 ₱ 1,233.96
Laborer 1.00 21.00 45.25 950.25

B. SUB-TOTAL, LABOR ₱ 2,184.21

C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)

Wide Recessed Type w/ aluminum reflector


24.00 set 1,800.00 43,200.00
LED Tubular Lamp 2 x 28 watts day light
LED Tubular 21 watts with holder 18.00 set P 550.00 P 9,900.00

C. SUB-TOTAL, MATERIAL ₱ 53,100.00

SUMMARY :
A. Equipment ₱ -
B. Labor ₱ 2,184.21
C. Materials ₱ 53,100.00
D. TOTAL DIRECT COST ₱ 55,284.21
DIRECT UNIT COST ₱ 1,316.29
E. OCM 12% of D ₱ 6,634.11
F. Profit 8% of D ₱ 4,422.74
G. VAT 5% of (D+E+F) ₱ 3,317.05
H. Total Cost (D+E+F+G) ₱ 69,658.10
I. Unit Cost H/Quantity ₱ 1,658.53
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino

Item No. : A.1.1 (3) Quantity : all


Description : Construction of Field Office for the Engineer Unit : l.s.

oduction Output :
No. of Hrs. : hrs.
No. of Days : days

A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)

A. SUB-TOTAL, EQUIPMENT ₱ -

B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Construction Foreman 1.00 24.00 ₱ 67.72 ₱ 1,625.28
Carpenter 2.00 24.00 56.64 2,718.72
Laborer 2.00 24.00 37.94 1,821.12

B. SUB-TOTAL, LABOR ₱ 6,165.12

C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
Corrugated Roofing, Gauge 26 (0.40mm × 2.44m.) 38.65 sq.m. ₱ 250.00 ₱ 9,662.50
Assorted Lumber 362.00 bd.ft. 40.00 14,480.00
6mm × 4' × 8' Ordinary Plywood 7.00 pcs. 320.00 2,240.00
6mm × 4' × 8' Marine Plywood 16.00 pcs. 345.00 5,520.00
Assorted C.W. Nails 11.00 kgs. 60.00 660.00

C. SUB-TOTAL, MATERIAL ₱ 32,562.50

SUMMARY :
A. Equipment ₱ -
B. Labor ₱ 6,165.12
C. Materials ₱ 32,562.50
D. TOTAL DIRECT COST ₱ 38,727.62
DIRECT UNIT COST ₱ 38,727.62
E. OCM 0% of D ₱ -
F. Profit 0% of D ₱ -
G. VAT 5% of (D+E+F) ₱ 1,936.38
H. Total Cost (D+E+F+G) ₱ 40,664.01
I. Unit Cost H/Quantity ₱ 40,664.01
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino

Item No. : A.1.1 (11) Quantity : all


Description : Provision of Furnitures/Fixtures Equipment and AppliancesUnit : l.s.
for the Field Office of the Engineer

oduction Output :
No. of Hrs. : hrs.
No. of Days : days

A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)

A. SUB-TOTAL, EQUIPMENT ₱ -

B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)

B. SUB-TOTAL, LABOR ₱ -

C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
Office Desk 4.00 pcs. ₱ 2,450.00 ₱ 9,800.00
Swivel Chair 6.00 pcs. 1,100.00 6,600.00
Mono Block Chairs 6.00 pcs. 350.00 2,100.00

C. SUB-TOTAL, MATERIAL ₱ 18,500.00

SUMMARY :
A. Equipment ₱ -
B. Labor ₱ -
C. Materials ₱ 18,500.00
D. TOTAL DIRECT COST ₱ 18,500.00
DIRECT UNIT COST ₱ 18,500.00
E. OCM 0% of D ₱ -
F. Profit 0% of D ₱ -
G. VAT 5% of (D+E+F) ₱ 925.00
H. Total Cost (D+E+F+G) ₱ 19,425.00
I. Unit Cost H/Quantity ₱ 19,425.00
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino

Item No. : B.5 Quantity : 1.00


Description : Project Billboard/Signboard Unit : each

oduction Output :
No. of Hrs. : hrs.
No. of Days : days

A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)

A. SUB-TOTAL, EQUIPMENT ₱ -

B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Carpenter 1.00 2.20 58.76 129.27
Laborer 1.00 2.20 45.25 99.55

B. SUB-TOTAL, LABOR ₱ 228.82

C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
Billboard:
1/4"x 4"x 8' Plywood 1.00 pc. 350.00 350.00
Tarpaulin 1.00 pc. 1,300.00 1,300.00
C.W. Nails 0.50 kls. 60.00 30.00
Lumber materials:
4 - 2"x2"x 4' 5.33 bd.ft. 40.00 213.33
2 - 2"x2"x 8' 5.33 bd.ft. 40.00 213.33
2 - 2"x3"x 6' 6.00 bd.ft. 40.00 240.00

C. SUB-TOTAL, MATERIAL ₱ 2,346.67

SUMMARY :
A. Equipment ₱ -
B. Labor ₱ 228.82
C. Materials ₱ 2,346.67
D. TOTAL DIRECT COST ₱ 2,575.49
DIRECT UNIT COST ₱ 2,575.49
E. OCM 12% of D ₱ 309.06
F. Profit 8% of D ₱ 206.04
G. VAT 5% of (D+E+F) ₱ 154.53
H. Total Cost (D+E+F+G) ₱ 3,245.12
I. Unit Cost H/Quantity ₱ 3,245.12
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino

Item No. : B.7 Quantity : 7.00


Description : Occupational Safety & Health Program Unit : months

oduction Output :
No. of Hrs. : hrs.
No. of Days : - days

A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)

A. SUB-TOTAL, EQUIPMENT ₱ -

B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
Safety Officer 1.00 50.00 ₱ 62.50 ₱ 3,125.00

B. SUB-TOTAL, LABOR ₱ 3,125.00

C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)
Safety Helmet 4,000.00 man-hours ₱ 7.68 ₱ 30,720.00
Safety Gloves 4,000.00 man-hours 0.31 1,240.00
Safety Shoes 4,000.00 man-hours 2.88 11,520.00
Medicine 1.00 l.s. 6,861.98

C. SUB-TOTAL, MATERIAL ₱ 50,341.98

SUMMARY :
A. Equipment ₱ -
B. Labor ₱ 3,125.00
C. Materials ₱ 50,341.98
D. TOTAL DIRECT COST ₱ 53,466.98
DIRECT UNIT COST ₱ 7,638.14
E. OCM 0% of D ₱ -
F. Profit 0% of D ₱ -
G. VAT 5% of (D+E+F) ₱ 2,673.35
H. Total Cost (D+E+F+G) ₱ 56,140.33
I. Unit Cost H/Quantity ₱ 8,020.05
DETAILED UNIT PRICE ANALYSIS
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino

Item No. : B.9 Quantity : 1.00


Description : Mobilization/Demobilization Unit : l.s

oduction Output :
No. of Hrs. : hrs.
No. of Days : days

A. Name and Capacity of Equipment (OperaNo. of Units No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)
1% of Civil Works 38,100.08

A. SUB-TOTAL, EQUIPMENT ₱ 38,100.08

B. Designation of Personnel No. of Men No. of Hrs. Unit Rate/Hr. Total Cost (Pesos)

B. SUB-TOTAL, LABOR ₱ -

C. Name and Description Qty. Unit Unit Cost Total Cost (Pesos)

C. SUB-TOTAL, MATERIAL ₱ -

SUMMARY :
A. Equipment ₱ 38,100.08
B. Labor ₱ -
C. Materials ₱ -
D. TOTAL DIRECT COST ₱ 38,100.08
DIRECT UNIT COST ₱ 38,100.08
E. OCM 0% of D ₱ -
F. Profit 0% of D ₱ -
G. VAT 5% of (D+E+F) ₱ 1,905.00
H. Total Cost (D+E+F+G) ₱ 40,005.08
I. Unit Cost H/Quantity ₱ 40,005.08
FURNISHING OF AGGREGATES
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino

Source of Aggregat = San Pedro, Maddela Site (km) = km.


Hauling Distance = 40 km. Quary (km) = 368 km.
Grade =
Terrain = Rolling
Road Condition = Paved

1. Stockpiling & Loading

use 1 - Bulldozer(Komatsu D65A-8, 155HP); Capacity = 500.00 cu.m./day


use 1 - Payloader, 2.10 cu.m., 148HP; Capacity = 500.00 cu.m./day

A. Unit Cost = ( ₱ 18,392.00 + ₱ 13,864.00 ) day = ₱ 64.52 /cu.m.


500.00 cu.m./day

2. Hauling Cost
Dump Truck Travel Speed
Terrain Condition Road Condition
(kph)
Loaded Empty
Flat Paved 40 60
Unpaved 30 50
Rolling Paved 30 40
Unpaved 25 30
Mountainous Paved 25 30
Unpaved 15 20

Loading time = 5 min.


Unloading time = 3 min.
Allowance for delay = 2 min.

Average Hauling Distance = 40 km.


Average Speed, Loaded = 30 kph
Average Speed, Empty = 40 kph

Travel time, Loaded

Loading time = 5.00 min.

1st Distance = 0.20 km. 1st Speed = 10.00 kph 1st Period = 1.20 min.
2nd Distance= 39.60 km. 2nd Speed = 30.00 kph 2nd Period = 79.20 min.
Last Distanc = 0.20 km. Last Speed = 15.00 kph Last Period = 0.80 min.

Unloading time = 3.00 min.

Return time, Loaded

1st Distance = 0.20 km. 1st Speed = 10.00 kph 1st Period = 1.20 min.
2nd Distance= 39.60 km. 2nd Speed = 40.00 kph 2nd Period = 59.40 min.
Last Distanc = 0.20 km. Last Speed = 15.00 kph Last Period = 0.80 min.

Allowance for Delay= 2.00 min.

TOTAL CYCLE TIME = 152.60 min.

3. Computation of Hauling Cost

No. of Trips = 8 × 60 = 3 trips/day/10 cu.m. DT


152.60
Rental of Dumptruck (10 cu.m.) = ₱ 10,816.00 cu.m./day

B. Hauling Cost = Rental = ₱ 360.54 /cu.m.


Load Capacity × No. of Trips
C. Excise Tax 3% (A & B) = ₱ 12.76 /cu.m.
D. Royalty access road, Prov'l. & Brgy. Tax = ₱ 20.00 /cu.m.

COST OF AGGREGATES = ₱ 457.82 /cu.m.

3. Processing: Employing a Laborer, Skilled & Loader

Fine Aggregates:

Screenin = (₱ 13,864.00 + ₱ 326.77 + ₱ 278.60 )/day = ₱ 72.35 /cu.m.


200.00 cu.m./day

Washing = (₱ 13,864.00 + ₱ 326.77 + ₱ 278.60 + ₱ 335.50 )/day = ₱ 49.35 /cu.m.


300.00 cu.m./day

Cost of Fine Aggregate= ₱ 579.52 /cu.m.

Coarse Aggregates:

Screenin = (₱ 13,864.00 + ₱ 326.77 + ₱ 278.60 )/day = ₱ 96.47 /cu.m.


150.00 cu.m./day

Washing = (₱ 13,864.00 + ₱ 326.77 + ₱ 278.60 + ₱ 335.50 )/day = ₱ 49.35 /cu.m.


300.00 cu.m./day

Cost of Coarse Aggreg = ₱ 603.64 /cu.m.


FURNISHING OF CRUSHED AGGREGATES
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino

Source of Aggregat = San Pedro, Maddela Site (km) = km.


Hauling Distance = 30 km. Quary (km) = 368 km.
Grade =
Terrain = Rolling
Road Condition = Paved

1. Crushed Aggregates (Pickup Price)

A. Unit Cost = ₱ 550.00 /cu.m.

2. Hauling Cost
Dump Truck Travel Speed
Terrain Condition Road Condition
(kph)
Loaded Empty
Flat Paved 40 60
Unpaved 30 50
Rolling Paved 30 40
Unpaved 25 30
Mountainous Paved 25 30
Unpaved 15 20

Loading time = 5 min.


Unloading time = 3 min.
Allowance for delay = 2 min.

Average Hauling Distance = 30 km.


Average Speed, Loaded = 30 kph
Average Speed, Empty = 40 kph

Travel time, Loaded

Loading time = 5.00 min.

1st Distance = 0.20 km. 1st Speed = 10.00 kph 1st Period = 1.20 min.
2nd Distance= 29.60 km. 2nd Speed = 30.00 kph 2nd Period = 59.20 min.
Last Distanc = 0.20 km. Last Speed = 15.00 kph Last Period = 0.80 min.

Unloading time = 3.00 min.

Return time, Loaded

1st Distance = 0.20 km. 1st Speed = 10.00 kph 1st Period = 1.20 min.
2nd Distance= 29.60 km. 2nd Speed = 40.00 kph 2nd Period = 44.40 min.
Last Distanc = 0.20 km. Last Speed = 15.00 kph Last Period = 0.80 min.

Allowance for Delay= 2.00 min.

TOTAL CYCLE TIME = 117.60 min.

3. Computation of Hauling Cost

No. of Trips = 8 × 60 = 4 trips/day/10 cu.m. DT


117.60
Rental of Dumptruck (10 cu.m.) = ₱ 10,816.00 cu.m./day

B. Hauling Cost = Rental = ₱ 270.40 /cu.m.


Load Capacity × No. of Trips
C. Excise Tax 3% (A & B) = ₱ - /cu.m.
D. Royalty access road, Prov'l. & Brgy. Tax = ₱ - /cu.m.

COST OF CRUSHED AGGREGA = ₱ 820.40 /cu.m.


Project :Construction of MPB, Diduyon, Maddela, Quirino
Maddela, Quirino

FURNISHING OF BOULDERS
Source of Aggregate = SAN PEDRO site(km.) quary(km.)
Hauling Distance = 4 kms. 338 368
Grade =
Terrain = Mountainous loaded empty
Road Condition = Paved = 30 40
STOCKPILING AND LOADING:
capacity/man-day = 2 cu.m/day
P 278.60 /day
1 Stockpiling Cost = = P 139.3
2 cu.m./day
LOADING AND UNLOADING
capacity/ man-day to load = 2 cu.m./day at quarry
capacity/ man-day to unload = 3 cu.m./day

P 278.60 /day+ P 278.60 /day


Loading and Unloading = = P 232.17
2 cu.m./day 3 cu.m./day

HAULING COST
Average Hauling Distance = 4 km.

Average Speed, Loaded = 30 kph


Average Speed, Empty = 40 kph

Loading Time = 60.0


Travel Time, Loaded
First 200 m. = 10 kph = 1.20
3.6 km. = 30 kph = 7.20
Last 200 m. = 15 kph = 0.80

Unload/Manuever = 60.0

Return Time, Empty


Travel Time, Loaded
First 200 m. = 10 kph = 1.20
3.6 km. = 40 kph = 5.40
Last 200 m. = 15 kph = 0.80
Allowance for Delay = 2.0
TOTAL CYCLE TIME 138.60
COMPUTATION OF HAULING COST

No. of trips = 8 x 60 = 3.46 trips/day/5 cu.m. Stake Truck


138.60
say 3.00 trips/day

Rental of Stake Truck (5cu.m.) = P 5,696.00 cu.m./day

2 Hauling Cost rental DT = P 379.70


load capacity x no. of trips

4 Excise Tax 3% (1 & 2) = P 22.54


5 Royalty access road, Prov'l. & Brgy. Tax = P 20.00
COST OF BOULDERS P 793.71
/ cu.m.

uarry

/ cu.m.

min.

min.
min.
min.

min. at site

min.
min.
min.
min.
min.

Truck

/cu.m.

/cu.m.
/cu.m.
/cu.m.
47 375.84
36.2 289.68
Schedule of Construction Equipment
Project : Construction of Machinery Shed
Quirino State University, Cabarroguis Campus, Cabarroguis, Quirino

Description and Capacity Required Total


1. One-Bagger Mixer 2 2
2. Bar Cutter (Electric Model) 1 1
3. Electric Drill 1 1

Equipment
Part 187 of 1
Equipment
Part 188 of 1

Das könnte Ihnen auch gefallen