DATE : Date:
Address : Nyati Unitree, East Wing, Nagar Road, Yerwada, Pune 411006
Tele : 020-6686 3333
Email : sirsikar@nyatigroup.com
Website : www.nyatigroup.com
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/301/REV-0
Page : 1 of 3
A) QUALITY
1.0 SCOPE:-
2.0 EQUIPMENT:-
3.0 RESPONSIBILITY:-
1) HOD D&D
2) Surveyor
3) Site Incharge
3) HOD D&D to comply the variance & get the building setting
out layout drawing from Licenced Architect.
6) Site Incharge to call surveyor & get setting of all buildings. Make
brick pillar or erect pegs for 4 corner points of each building &
services
9) Record the details in M&M register and obtain sign of HOD D&D
12) With respect to 4 pegs, fix the railing minimum 6’ to 9’ away from
building line.
13) For Railing, use wooden bullies 6’ c/c & fix the silver patti
4”x1/2” @ 3’ above the ground level or preferably @ plinth level.
14) If railing is not @ plinth level, mark the plinth level on bullies.
15) Transfer the 4 corner points on railing & check Length, Breadth &
Diagonals.
16) Measure & mark all column centerline on railing on either side of
X & Y direction.
20) Confirm all numbering is neat & visible from at least 50’ distance
(painting preferably to be done by professional painter).
21) D&D to verify & certify the accuracy for the centerline.
B) ENVIRONMENT
1) Before the start of site cleaning, sprinkle water to reduce dust and
prevent air pollution
2) Use mask, safety shoes for site cleaning and line out.
A) QUALITY
1.0 SCOPE:-
2.0 EQUIPMENT:-
3.0 RESPONSIBILITY:-
1) Site Incharge/QA
2) Site Supervisor
1) Ensure approved Good for Construction drawings for setting out &
RCC drawing for column footing is available.
2) Confirm B.C. assumed in drawing is as per trial pit results.
4) Mark the grid 5m x 5m and take original ground level with respect to
B.M. as 100.00
6) With every change of strata take & record the levels with the same
grid to derive the excavated quantity for that particular strata.
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/302/REV-0
Page : 2 of 2
7) Take the strata checked for first footing from RCC consultant &
obtain the certificate. Record the same in M&M Register.
9) Confirm that excavation pit size doesn’t exceed by 2 feet than footing
size.
10) Remove all loose material & confirm that excavated pit is fairly
leveled.
B) ENVIRONMENT
5) Excavate the entire pit in 45 – degree angle and shore all the area if
excavation is in loose soil, and below 2m depth.
A) QUALITY
1.0 SCOPE:-
2.0 EQUIPMENT:-
1) Approved Layout
2) GI Sheets
3) 30m Tape
4) Paint
3.0 RESPONSIBILITY:-
1) Zonal CE
2) Site Incharge
3) HOD D&D to comply the variance & get the building setting out
layout drawing from licensed architect.
6) Site Incharge to call surveyor & get setting of all building make brick
pillaer or erect pegs for y corner point of each building & services.
9) Record the details in M&M Register & obtain sign of HOD D&D.
11) Location is that free from water flooding and any temporary
retaining wall or near land slide area.
12) Make approach road at site labour camp for water tanker unloading.
13) All hutments in GI Sheets only (As per attached drawing). Make of
drawing of labour camp hutment & list of labours staying therein.
14) Give one light point in each hutment in conduit pipe only.
B. ENVIRONMENT
1) Check water storage tank for leaks and prevent waste of water.
4) Do not allow any person to use open area for toilet purposes.
1) Labour camp should have well defined lay out with low congestion
& more open spaces.
2) Use only G.I sheets for huts and maintain sufficient distance between
two huts.
10) Check every time hut for any smoke when people leave for work.
11) Ensure labour hut floor at mini. 1’’- 0’’ above the ground level.
REF : QEHS/304/REV-0
Page : 1 of 3
A) QUALITY
1.0 SCOPE :
2.0 EQUIPMENT :
3.0 RESPONSIBILITY :
5) Site Incharge
6) Site Supervisor
7) Store Keeper
8) Operator.
REF : QEHS/304/REV-0
Page : 2 of 3
14) Check the proportion of Anti termite chemical & water as per the
specification i.e. 1:99 (100 lit of mix contains 1 lit of chemicals & 99 lit
of water).
15) Ensure the drills in the plinth are adequate per Square Meter of the
area to be treated.
16) Pour/spread the anti termite mix (Chemical + Water) over the area
and reconcile the quantity to ensure the adequate utilization; (5 lit of
mix per Sq.m. is the decided criteria).
17) Restrict the area to other labours, to ensure they are not affected by
the emission/ smell of the said mix.
18) See that the operator cleans his hands properly before handling any
other material / food.
19) Ensure that no material is left out at the stores or working place after
work is completed.
20) Ensure that disposal of empty tins from the site is done by the same
agency immediately.
21) Display the MSDS of the chemical at site office & stores as well.
B) ENVIRONMENT :
2) Ensure that chemicals are not spread over on the ground, and they
are inserted through
REF : QEHS/304/REV-0
Page : 3 of 3
2) Operators must put on the mask, hand gloves and goggles before
starting the work.
3) The empty container is taken away from the site after the work is
over.
4) Ensure that the workers do not use the empty container for carrying
water.
A) QUALITY
1.0 SCOPE:-
2.0 EQUIPMENT:-
3.0 RESPONSIBILITY:-
1) Site Incharge
2) Site Supervisor
3) Q.A.
4) Clean the pit & give the level data minimum 100 mm thick or as
specified in R.C.C. drawing. Make a shuttering box 100mm thk of
required dimension.
6) Ensure the supports to have true line, level & plumb of shuttering.
8) Incase of highwater table start PCC only after the Pit is dry. Keep
minimum one standby pump at site, so that work does not get
delayed/wrong procedures followed during casting
11) Pour the concrete in position from a height not more than 5’0” to
avoid segregation.
12) Erect “Pour Shoot” or working platform to pour the concrete from
depth more than 5’0”.
15) Remove the shuttering next day by taking upmost care to maintain
the edges & corners of the concrete intact.
B) ENVIRONMENT:-
3) Do not use water pipe having any leakage / damage to prevent waste
of water.
1) Use safety helmet, safety shoes, rubber hand gloves and safety belt at
height.
5) Keep the area clean from iron bars and wooden pieces.
A. QUALITY
1. SCOPE:-
Applicable for concrete dispatch activities to our existing projects.
2. EQUIPMENTS:-
1) RMC Plant (CP-30)
2) Transit Mixers,
3) JCB Machine,
4) Diesel Generator,
5) Material Stock Yard,
6) U.G.Water Tank of capacity 30,000 ltr.
7) Curing Tank of concrete Cube.
8) Cement Godown of capacity 6000 bags,
9) Annual maintenance contract.
10) Weekly maintenance of transit mixer & plant,
11) Q.C. Lab Equipments:-
i. Cube moulds of size 15cm x 15cmx15cm,
ii. Ventilated Oven,
iii. I.S. Sieve set for material gradation,
iv. Sand pouring cylinder for calculating proctor density of material,
v. Compressive Testing Machine for testing of cubes,
vi. Slump cone with graduated tamping rod.
3. RESPONSIBILITY:-
Plant Incharge.
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/306/REV-0
Page : 2 of 5
QEHS WORK INSTRUCTIONS FOR RMC PLANT
TITLE :
OPERATION.
4. WORK INSTRUCTIONS:-
1) INPUTS :-
Following are considered as inputs to this procedure.
1) Concrete requirements received from site,
2) Raw material received from supplier,
3) Mix design.
2) PROCESS / OPERATION :-
PLANNING :-
3) If a quantity of diesel is less, fill the diesel in proper quantity & record it
in a register, also the quantity of diesel in DG checked before concreting
gets starts.
4) Ensuring that, all the mix designs are properly set in a control panel of
batching plant.
6) Only passed material is released for further processing & only kept at
stock / site/ store.
ACTIVITIES / OPERATION:-
1) As per the requirement of concrete from site, particular grade of
concrete is set to deliver the concrete.
2) Plant operator sets the quality of material on control panel as per the
mix design of particular grad of concrete.
6) After completion of batch of 6 cum. then 6 nos. of cube casted for each
grade of concrete for particular day. 6 cubes are casted for every 50 cum
of each grade.
8) Cubes are tested on CTM at 7 days & 28 days of interval at RMC plant,
for compressive strength purpose.
9) Before unloading of the RMC at the site, the challan is to be signed the
store keeper and the site engineer. Clearly stating the grade and
quantity of concrete and the location of unloading.
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/306/REV-0
Page : 4 of 5
QEHS WORK INSTRUCTIONS FOR RMC PLANT
TITLE :
OPERATION.
RECONCILLATION:-
1) Consumption of material is checked, whether it goes as per mix design
or not.
2) The empty cement bags are then counted & checked with the
consumption report & also checked whether all the cement bags are
stacked properly with any leakages inside.
3) Before closing the plant, seal must be there for diesel tank of every TM,
Q.C. Lab, Computer cabin, Cement godown etc.
MATERIAL STACKING:-
1) Cement:-
2) Admixer:-
3) Materials:-
All the materials regarding concreting like 10mm metal, 20mm metal,
Crused sand should be stacked separately with maintaining & updating
records of every lot.
B) ENVIRONMENT:-
1) Cut Cement bag by removing stitches & change directly in beaching /
mixing plant to prevent west of cement.
4) Do not use Water pipe having any leakage / damage & prevent waste of
water.
7) Use Hessian cloth to cover the concrete surface to reduce evaporation loss.
REF : QEHS/307/REV-0
Page : 1 of 3
A) QUALITY:
1. SCOPE :-
Applicable for all residential / Commercial Buildings for Reinforcement Cover
2. EQUIPMENTS :-
1) Tray (6’X4’X8”), Ghamela, Spade, Trowel, Bucket.
2) PVC Farma of Size :
3) For footing (LXH) Ø 60mmX 50mm
4) For Column (LXH) Ø 90mmX25mm & Central Hole of Ø 10mm.
5) For Beam (LXH) Ø 30mm X 20mm
6) For Slab (LXH) Ø 30mm X20mm
7) Piece of Binding wire of length 150mm.
3. RESPONSIBILITY :-
1) Sr. Engineer
4. WORK INSTRUCTIONS :-
1) PVC Farma of above mention size issued from store after checking by Senior Engineer.
3) Mix the Cement & Crush Sand in Ratio of 1:2 in the tray. Water is added till get hand
paste. Cement, Crush Sand & water is mixed with spade properly. Now Cement, Crush
Sand paste is ready. We should ensure that prepared paste should consumed within 1
Hours. This is the normal method of mixing of normal grade of Concrete.
1
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/307/REV-0
Page : 2 of 3
4) For Higher grade of concrete, we mention the water cement ratio while mixing with
crush sand of required grade of concrete cover.
5) Pastes is poured in farma over plane M.S. Hard surface & compacted with trowel &
maintain the top surface equal with PVC Farma .Now remove the farma by keeping
molded mortar on the same position. Same process continues on another adjacent
surface area.
7) For Slab cover Block, Round notch of Ø 10mm & 2mm depth is provided in 20mm
depth cover Block.
8) For round cover of column : Round mould paste is placed over hard surface & than hole
of Ø 10mm is done with the help of M.S.Rod in the centre of mould cover Block.
9) Next day all molded C.M. Block of Same grade is Kept in to Cement Bag & then Put in
to water tank for Curing up to 14 days.
10) Daily C.M. Block making quantity is counted & record send to H.O.
B) ENVIRONMENT:-
1) Open Cement bag by removing stitches & unload directly in beaching / mixing plant
to prevent west of cement.
2) Do not throw / drop cement bags to prevent air pollution by dust separation.
4) Do not use Water pipe having any leakage / damage & prevent wastage of water.
REF : QEHS/307/REV-0
Page : 3 of 3
7) Use Hessian cloth to cover the concrete surface to reduce evaporation loss.
8) Spilled & waste concrete If any should be used for temporary structure.
3
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/308/REV-0
Page : 1 of 5
A) QUALITY:
1. SCOPE :-
2. EQUIPMENTS :-
2) Weigh Batcher with one Bag Mixer or R.M.800 or R.M.C. Plant with transit mixer.
5) May be Total station if project is more than 1lack sq. ft. area.
6) May be Tower crane if project is more than 2 lack sq. ft. area & required fast work.
7) Shuttering materials like – 12mm P.C. Ply, Wooden Patti 3”x2”, wooden Chavi
4”x3”, M.S. Props, Shikanja, M.S. Sq Pipe 50mm x 50mm.
8) Spades, Mortor pan, plumb, Right Angle, Tape 5mtr, may scaffolding material for
heavy footing, Trowel, linedoori, Nails ( size – 1 ½” , 2 ½” , 3” ) lubricant, R.C.C.
Cover Block as specified in R.C.C. drawing, Wheel Barrow, Concrete Pump with all
accessories, Curing pipe, hessian cloth, 6 No’s Cube, Slump cone, Measuring Tape of
30 m.
3. RESPONSIBILITY :-
1) Site Incharge
2) Sr. Engineer
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/308/REV-0
Page : 2 of 5
4. WORK INSTRUCTIONS :-
Shuttering :
1) Ensure the approved Good for Construction, R.C.C. & Architectural drawing with
revision status.
2) Ensure the required level of footing & mark the center along with all four corner of
footing size over P.C.C. with the help of centerline boundary or Total Station.
3) Clean the surface & start shuttering as shape & size mentioned in R.C.C. Drawing.
5) Sides of Shuttering are supported laterally by M.S. Props & Wooden Chavi at 2’0”
c/c at bottom & top. Support may insure if footing size are heavy as per S.I.
instruction. Bottom portion of side is locked by wooden Patti 4” X1 ½” with the help
of nails over PCC. All four corners of shuttering from top is provided diagonally
cross wooden Patti 4”X 1 ½” for fixing of corners in position.
6) Line, Level, Size & Plumb of shuttering should be perfect, if not set perfect than
rectified till Ok.
Reinforcement:
1) Reinforcement starts laying for Jali & column as per length & shape indicated in
R.C.C. Drawing.
2) Position & Orientation of reinforcement check & get ok with the help of linedoori,
Plumb & cover for reinforcement provided properly.
3) Now finally checked the shuttering & reinforcement at a time & instruction issued for
casting footing after everything Ok as per drawing.
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/308/REV-0
Page : 3 of 5
Concreting:
1) Concrete prepared at site by mixer or placed order to R.M.C. Plant as per mix
specified in R.C.C. Drawing.
2) For small footing concreting done by mixer & wheel Barrow, if footing size is more
than 10 cum. than concreting done by concrete pump.
3) If concreting done by mixer RM 800 than mix design set into panel & Labour gang set
for filling of Aggregates, Cement & Admixture in mixer delivered. Concrete
delivered in wheel barrow or Concrete Pump.
4) Concrete grout is passed through pipe line Just before starting concrete. Transit mixer
shute placed over concrete pump hopper. Concrete delivered in to Pump suit & than
concrete transport up to req. position by pressure system.
5) Concrete is done by concrete pump than pipe line of pump is placed up to concrete
delivered point. Oil & diesel checked before starting Pump.
6) Concrete is vibrated by 60mm needle for proper vibration & labour gang spread the
concrete with the help of spades.
7) Concrete get over after filling up to required depth & set finish with the help of
mason properly.
8) 6 Cube cast for checking strength of concrete in 7 days & 28 days. With Coding as
date of Casting, Location of structure, Grade of concrete.
1) Remove the shuttering after 24 hours by taking up most care to maintain the edges &
corners of the concrete.
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/308/REV-0
Page : 4 of 5
B) ENVIRONMENT:-
1) Open Cement bag by removing stitches & unload directly in beaching / mixing plant
to prevent west of cement.
2) Do not throw / drop cement bags to prevent air pollution by dust severation.
4) Do not use Water pipe having any leakage / damage & prevent wastage of water.
7) Use Hessian cloth to cover the concrete surface to reduce evaporation loss.
8) Spilled & waste concrete If any should be used for temporary structure.
REF : QEHS/308/REV-0
Page : 5 of 5
5) Keep the area clean from iron bar & wooden pieces.
12) Use safety belt for tying of reinforcement above three meter height.
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/309/REV-0
Page : 1 of 4
A. QUALITY :
1. SCOPE:
Application for Residential / Commercial Buildings for RCC Column work.
2. EQUIPMENTS:-
2) Weigh Batcher with one Bag Mixture Or R.M.800 or RMC plant with Transit Mixer, lift
hoist, Concrete Pump.
3) Shuttering material like:- 12mm P.C.Ply, Wooden Patti 3”x2”, Joint channel 75mm
flange called shoulder of req. size, M.S. Props, Tie rod with nut of req. size, Shikanja 3’,
Wooden Chavi 4”x3”, Nails 1 ½”, 2 ½”, Lubricant.
4) Vibrator with needle of 60mm dia. & 40mm dia. & measuring tape 5m & 30m,
Scaffolding materials for staging, Trowel, Right Angle, Plumb bob.
5) Concrete cover block of required size, Spades, Pan, Wheel Barrow, concrete pump with
all accessories or lift with hoist, Curing pipe, Hessian cloth, 6 nos. cube mould, slump
cone.
3. RESPONSIBILITY:-
1) Site Incharge
2) Sr. Engineer
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/309/REV-0
Page : 2 of 4
4. WORK INSTRUCTIONS:-
SHUTTERING:-
1) Ensure the approved Good for construction, R.C.C. & Architectural drawings with
revision status.
2) Make the column size mould with the help of 12mm P.C.Ply & 3”x2”x8’ wooden batten.
Batten is fixed over ply @ 10” c/c vertically. Both end of ply has also horizontal batten
along the width. Batten is fixed on edge over ply by 1 ½” Nails.
3) First we cast starter of column having height 6” after erecting proper steel & ring in
column with req. cover. Starter ensures the line, level & size of column at surface level.
level. Distance and diagonals & Centre lines are checked strictly with respect to
building face.
4) Makes farma of column is Erecting over starter with the help of shikanja. Then M.S.
shoulder is placed with tie rod & nut, all four sides in such a way that 1st Shoulder
should fixed over the starter, than 1’6” & there after 2’0” c/c up to top end. All Tie rods
are tight with the help of nut.
5) Lubricant should apply over the inner surface of ply before erecting form & false work.
7) Line, level, orientation, size, rectangle, plumb checked by Jr. Engineer/ Sr. Engineer &
Q.A. Permission issued for pouring concrete.
REINFORCEMENT:-
1) Reinforcement of column is cut & band in steel yard as per R.C.C. drawing & placed in
existing reinforcement with appropriate lap. Rings provided as per mention in
drawing. Cover for reinforcement provided in center & top of column as specified in
drawing. Round precast concrete cover with centre whole are fixed at bottom & top on
all four faces before erecting shuttering.
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/309/REV-0
Page : 3 of 4
1) Concrete prepared at site by mixer or placed order to R.M.C. Plant as mix specified in
R.C.C. drawing.
2) For small column concrete placing is done by manually with spade & ghamella. If
column is heavy than it pourd by concrete pump.
3) Concrete filled till level marked & finished by trowel. Vibrator needle of 60 is placed till
get concrete is proper compacted.
4) Position of column rechecked 12 hours after de-shuttering & hessian cloth wounded for
curring up to 14 days to 28 days.
7) Record for work process, measurements & checked is recorded in M & M in process
activity register (QAD/702), daily signed by Q.A. /S.I.
A. ENVIRONMENT:-
1) Cut Cement bag by removing stitches & change directly in beaching / mixing plant to
prevent west of cement.
2) Do not throw / drop cement bags to prevent air pollution by dust generation.
4) Do not use Water pipe having any leakage / damage & prevent west of water.
REF : QEHS/309/REV-0
Page : 4 of 4
7) Use Hessian cloth to cover the concrete surface to reduce evaporation loss.
1) Use Helmet, safety shoes, Rubber Hand Gloves & safety Belt at height.
5) Keep the area clean from iron bar & wooden pieces.
11) Ensure concrete pump delivery pipe is not tied to any supporting structure of Slab,
Beam and Column.
12) Ensure horizontal pipes of Concrete pump are resting on M.S. Chair.
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/310/REV-0
Page : 1 of 7
A) Quality:
1. SCOPE :-
2. EQUIPMENTS :-
1) Measuring farma (1’x1’x1’25’’), ghamella , R.M.800 also with lift hoist or R.M.C.
Plant with transit mixer. & Concrete Pump, R.M. 800 with concrete Pump.
3) Shuttering material like:- 12mm P.C.Ply, Wooden Patti 4”x1 ½”, Lapha 4”x1 ½”,
M.S. Props 3mtr, shikanja 2’6”, Wooden chavi 3”x4”, Nails 1 ½”, 2 ½”, 3”,
Lubricant, M.S. Span 2.4 to 4.2mtr, Scaffolding materials for staging, Bracing Pipe
50mm dia.
4) Measuring Tape 5m & 30m, Vibrator with needle 40mm dia. & 60mm dia. ,
Vacuum Cleaner.
5) Concrete cover block of req. size, Spades, Pan, Wheel Barrow, Trowel, Right
Angle, Plumb bob, Lift with hoist or Concrete Pump with all accessories, Curing
Pipe, Hessian Cloth, 6 nos. cube mould, Slump cone, Randha, Aluminum Patti 6’
or 12’ Long.
3. RESPONSIBILITY :-
1) Site Incharge
2) Sr. Engineer
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/310/REV-0
Page : 2 of 7
4. WORK INSTRUCTIONS :-
Shuttering :
1) Ensure the approved Good for Construction, R.C.C. & Architectural drawing with
revision status.
2) Making of ply for beam bottom & sides of beam. Beam bottom is made with
12mm P.C.Ply with two Nos of 4”x1 ½” wooden Patti. Beam side is made with
12mm P.C.Ply as required size in drawing with 4”x1 ½” batten @ 10” c/c along
length & both end in width.Making of ply is made as described above method for
waist slab & Landing.Riser of specified size is also made with Ply supported by 4”
X 1 ½” wooden Batten on both end along the length.
3) Level mark on column for fixing beam bottom as per Landing/Floor height
mention on drawing.
4) Topi of beam bottom fixed over column as per req. depth of beam & than beam
bottom rest over them with vertical props support @ 2’ c/c. wooden chavi 4”x3”
placed as cantilever if projection of Chajja is required.
5) Outer beam side erect over beam bottom with the help of nails. Making sides are
also placed over cantilever chavi 4”x3”, if projection is required.
6) Span is placed @ 2’0” c/c as per concreting thickness of Landing size & span edge
rest over 4”x3” wooden chavi with vertical M.S.Props at 2’0” c/c.
7) Now wooden Chavi 4”x3” of required length @ 10” c/c is placed across the span,
than P.C. Ply is laid over with nails as per size of Landing. We should take care
that there should be no gap between two ply. Now shuttering for waist Slab is
placed diagonally matching with top & bottom landing. Wooden chavi of 4”X3”
of req. length is placed on the bottom face of waist Slab @ 1’ 6”.Chavi is supported
by M.S. Props @ 2’ C/C. Shuttering of first landing is goes to 300mm more than
the size of Landing & Second Landing as less than 300 mm by landing size. Steps
are calculated and mark over the side face of waist Slab properly. Now riser is
fixed over the side waist Slab after laying a steel.Line & level is fixed with the help
of line dori & tube level. Two cross top Bandhi of wooden patti of 4”X1 ½” is
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/310/REV-0
Page : 3 of 7
placed over riser and nailed it properly so that riser should intact in position.
Diagonal, size of room, thickness of concrete for Landing & waist Slab are checked
by Sr. Engineer, Surface of ply cleaned by Vacuum cleaner & lubricant apply.
Now clearance given to reinforcement contractor for laying steel.
8) After laying steel, outer side of beam is fixed with the inclined supported of 4”x1
½”, wooden Patti in center & top. Chajja side is also fixed with making Ply &
supported given from cantilever wooden chavi. Outer line is checked properly
with the help of linedoori.
9) Beam bottom is clamped with shikanja & middle top portion is supported by
wooden Patti & 4”x1 ½” taking support from span chavi.
10) All M.S. props is braced by 2”dia. M.S. Pipe with the help of swing coupler.
11) All column junctions are closed properly in shape, size & clamped by shikanja all
around.
12) Remove the excess shuttering materials stacked below the slab level.
Reinforcement:
1) Reinforcement is cut & bend in steel yard as per required size & position. Specified
in RCC Drawing.
2) Cut & bend steel is placed over slab manually or by crane. Tagging start by
binding wire with proper placement of steel. Ring is also provided for Beams &
columns as specified.
4) Steel Chair is provided over bent up & double Zali for proper position of
reinforcement.
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/310/REV-0
Page : 4 of 7
7) Now we can pour the concrete in Staircase, beam, and chajja after rectification
done.
Concreting:
1) Before starting concreting, we check the condition of R.M.800 mixer, lift hoist &
concrete pump. Diesel & Oil is filled if machine is diesel.
2) One mason with Randha, Patti, spatula is required for finishing concrete surface.
3) Vibrator of needle 40mm dia. & 60mm dia. are kept over slab with one stand by.
4) Concrete filling level is marked over beam side & column for maintaining surface.
Concrete filling Kanda is also provided to mason for checking randomly.
2) Mix design set in panel for required weight of Aggregate, Cement, Sand & water.
3) Aggregate & cement placed into mixer manually, till getting correct required at
display, mixer takes water automatically. Admixture placed manually by
measuring Jar.
4) Concrete is mixed & unloaded in suit of lift & concrete lifted through hoist &
dump in tray over the surface of slab.
5) Concrete is transported at required place with the help of wheel barrow. Wheel
barrow runs over the surface of making ply side laid up to required position.
6) Concrete placed in slab & beams are vibrated & mason level the surface.
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/310/REV-0
Page : 5 of 7
1) Concrete grade & quantity is ordered to R.M.C. Plant one day before & concreting
time decided by R.M.C. plant & site incharge mutually.
3) Pipe line lay up to the required position of slab, with proper support.
4) Cement slurry passed over concrete pipe before just starting concrete.
5) Concreting carrying through transit mixer is delivered in concrete pump, Bucket &
than pumped it to require level. Concrete pipe can moved anywhere with the help
of additional pipe, bends & clamp.
6) Concrete vibrated by vibrator with needle 40mm dia. & 60mm dia. Surface leveled
by mason with Patti & trowel. After completing the concrete Ball Pass process is
done for cleaning pipe line & Pump Hopper with the help of Air pressure or water
pressure.
7) Cube cast 6 nos. with tamping 35 times for each layer & finished with trowel. &
Coding done as date of casting, Grade of concrete, Location of the structure.
2) If honey comb seen than it finished by cement, trowel as per S.I. instruction.
REF : QEHS/310/REV-0
Page : 6 of 7
7) Water sprinkling just after concrete set during casting of slab for arounding surface
cracks.
B) ENVIRONMENT:-
1) Open Cement bag by removing stitches & change directly in beaching / mixing
plant to prevent west of cement.
2) Do not throw / drop cement bags to prevent air pollution by dust severation.
4) Do not use Water pipe having any leakage / damage & prevent west of water.
7) Use Hessian cloth to cover the concrete surface to reduce evaporation loss.
1) Use Helmet, safety shoes, Gum boot, Rubber Hand Gloves & safety Belt at height.
REF : QEHS/310/REV-0
Page : 7 of 7
5) Keep the area clean from iron bar & wooden pieces.
REF : QEHS/311/REV-0
Page : 1 of 5
A. QUALITY :
1. SCOPE:
2. EQUIPMENTS:-
2) Weigh Batcher with one Bag Mixture Or R.M.800 or RMC plant with Transit Mixer,
lift hoist, Concrete Pump.
3) Shuttering material like:- 12mm P.C.Ply, Wooden Patti 3”x2”, Joint channel 75mm
flange called shoulder of req. size, M.S. Props, Tie rod with nut of req. size, Shikanja
3’, Wooden Chavi 4”x3”, Nails 1 ½”, 2 ½”, Lubricant.
4) Vibrator with needle of 60mm dia. & 40mm dia. & measuring tape 5m & 30m,
Scaffolding materials for staging, Trowel, Right Angle, Plumb bob.
5) Concrete cover block of required size, Spades, Pan, Wheel Barrow, concrete pump
with all accessories or lift with hoist, Curing pipe, Hessian cloth, 6 nos. cube mould,
slump cone.
3. RESPONSIBILITY:-
1) Site Incharge
2) Sr. Engineer
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/311/REV-0
Page : 2 of 5
4. WORK INSTRUCTIONS:-
SHUTTERING:-
1) Ensure the approved Good for construction, R.C.C. & Architectural drawings with
revision status.
2) Make the Pardi size mould with the help of 12mm P.C.Ply & 3”x2”x8’ wooden
batten. Batten is fixed over ply @ 10” c/c vertically. Both end of ply has also
horizontal batten along the width. Batten is fixed on edge over ply by 1 ½” Nails.
3) First we cast starter of Pardi having height 6” after erecting proper steel & ring in
Pardi with req. cover. Starter ensures the line, level & size of Pardi at surface
level.Distance and diagonals & Centre lines are checked strictly with respect to
building face.
4) Makes farme of Pardi as Erecting over starter with the help of shikanja. 50mm
X50mm Square M.S. Pipe is placed along length @ 1’ 6” C/C over the Batten of
Ply. Then M.S. shoulder is placed with tie rod & nut, all sides in such a way that
1st Shoulder should fixed over the starter, than 1’6” & there after 2’0” c/c up to top
end. Shoulder /Joint Channel which placed over square pipe with the help of Tie
rod @ 2’ 6” C/C . All Tie rods are tight with the help of nut & tie rod pass through
1” PVC conduit betn two face of shuttering. So that Tie rod need not to lock with
concrete.
5) Lubricant should apply over the inner surface of ply before erecting form & false
work.
7) Line, level, orientation, size, rectangle, position, plumb are checked by Jr.
Engineer/ Sr. Engineer & Permission issued for pouring concrete.
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/311/REV-0
Page : 3 of 5
REINFORCEMENT:-
1) Reinforcement of Pardi is cut & band in steel yard as per R.C.C. drawing & placed
in existing reinforcement with appropriate lap. Rings provided as per mention in
drawing. Cover for reinforcement provided in center & top of Pardi as specified in
drawing. Round precast concrete cover with centre whole are fixed at bottom &
top on all four faces before erecting shuttering.
2) For small Pardi concrete placing is done by manually with spade & ghamella. If
Pardi is heavy than it pourd by concrete pump.
3) Concrete filled till level marked & finished by trowel. Vibrator needle of 60 is
placed till get concrete is proper compacted.
4) Position of Pardi rechecked 12 hours after de-shuttering & hessian cloth wounded
for curring up to 14 days to 28 days.
REF : QEHS/311/REV-0
Page : 4 of 5
A. ENVIRONMENT:-
1) Cut Cement bag by removing stitches & change directly in beaching / mixing
plant to prevent west of cement.
2) Do not throw / drop cement bags to prevent air pollution by dust generation.
4) Do not use Water pipe having any leakage / damage & prevent west of water.
7) Use Hessian cloth to cover the concrete surface to reduce evaporation loss.
1) Use Helmet, safety shoes, Rubber Hand Gloves & safety Belt at height.
5) Keep the area clean from iron bar & wooden pieces.
REF : QEHS/311/REV-0
Page : 5 of 5
11) Ensure concrete pump delivery pipe is not tied to any supporting structure of
Slab, Beam, Pardi.
12) Ensure horizontal pipes of Concrete pump are resting on M.S. Chair.
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/312/REV-0
Page : 1 of 6
A) Quality:
1. SCOPE :-
2. EQUIPMENTS :-
1) Measuring farma (1’x1’x1’25’’), ghamella , R.M.800 also with lift hoist or R.M.C.
Plant with transit mixer. & Concrete Pump, R.M. 800 with concrete Pump.
3) Shuttering material like:- 12mm P.C.Ply, Wooden Patti 4”x1 ½”, Lapha 4”x1 ½”,
M.S. Props 3mtr, shikanja 2’6”, Wooden chavi 3”x4”, Nails 1 ½”, 2 ½”, 3”,
Lubricant, M.S. Span 2.4 to 4.2mtr, Scaffolding materials for staging, Bracing Pipe
50mm dia.
4) Measuring Tape 5m & 30m, Vibrator with needle 40mm dia. & 60mm dia. , Vacuum
Cleaner.
5) Concrete cover block of req. size, Spades, Pan, Wheel Barrow, Trowel, Right Angle,
Plumb bob, Lift with hoist or Concrete Pump with all accessories, Curing Pipe,
Hessian Cloth, 6 nos. cube mould, Slump cone, Randha, Aluminum Patti 6’ or 12’
Long.
3. RESPONSIBILITY :-
1) Site Incharge
2) Sr. Engineer
4. WORK INSTRUCTIONS :-
Shuttering :
1) Ensure the approved Good for Construction, R.C.C. & Architectural drawing with
revision status.
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/312/REV-0
Page : 2 of 6
2) Making of ply for beam bottom & sides of beam. Beam bottom is made with 12mm
P.C. Ply with two Nos of 4”x1 ½” wooden Patti. Beam side is made with 12mm
P.C.Ply as required size in drawing with 4”x1 ½” batten at 10” c/c along length &
both end in width.
3) Level mark on column for fixing beam bottom as per floor height mention on
drawing.
4) Topi of beam bottom fixed over column as per req. depth of beam & than beam
bottom rest over them with vertical props support @ 2’ c/c. wooden chavi 4”x3”
placed as cantilever if projection of Chajja is required.
5) Inner beam side erect over beam bottom with the help of nails. Making sides are
also placed over cantilever chavi 4”x3”, if projection is required.
6) Span is placed @ 2’0” c/c as per concreting thickness of room size & span edge rest
over 4”x3” wooden chavi with vertical M.S.Props at 2’0” c/c.
7) Now wooden Patti 4”x1 ½”x8’ long at 10” c/c is placed across the span, than P.C.
Ply is laid over with nails as per size of rooms. We should take care that there
should be no gap between two ply. Diagonal, size of room, thickness of concrete for
slab & beams are checked by Sr. Engineer, Surface of ply cleaned by Vacuum
cleaner & lubricant apply. Now clearance given to reinforcement contractor for
laying steel.
8) After laying steel, outer side of beam is fixed with the inclined supported of 4”x1
½”, wooden Patti in center & top. Chajja side is also fixed with making Ply &
supported given from cantilever wooden chavi. Outer line is checked properly with
the help of linedoori.
9) Beam bottom is clamped with shikanja & middle top portion is supported by
wooden Patti & 4”x1 ½” taking support from span chavi.
10) Outer portion of M.S. props is braced by 2”dia. M.S. Pipe with the help of swing
coupler.
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/312/REV-0
Page : 3 of 6
11) All column junctions are closed properly in shape, size & clamped by shikanja
all around.
12) Remove the excess shuttering materials stacked below the slab level.
Reinforcement:
1) Reinforcement is cut & bend in steel yard as per required size & position. Specified
in RCC Drawing.
2) Cut & bend steel is placed over slab by manually or by crane. Tagging start by
binding wire with proper placement of steel. Ring is also provided for Beams &
columns as specified.
4) Steel Chair is provided over bent up & double Zali for proper position of
reinforcement.
7) Now we can pour the concrete in slab, beam, and chajja after rectification done.
Concreting:
1) Before starting concreting, we check the condition of R.M.800 mixer, lift hoist &
concrete pump. Diesel & Oil is filled if machine is diesel.
2) One mason with Randha, Patti, spatula is required for finishing concrete surface.
3) Vibrator of needle 40mm dia. & 60mm dia. are kept over slab with one stand by.
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/312/REV-0
Page : 4 of 6
4) Concrete filling level is marked over beam side & column for maintaining surface.
Concrete filling Kanda is also provided to mason for checking randomly.
2) Mix design set in panel for required weight of Aggregate, Cement, Sand & water.
3) Aggregate & cement placed into mixer manually, till getting correct required at
display, mixer takes water automatically. Admixture placed manually by
measuring Jar.
4) Concrete is mixed & unloaded in suit of lift & concrete lifted through hoist & dump
in tray over the surface of slab.
5) Concrete is transported at required place with the help of wheel barrow. Wheel
barrow runs over the surface of making ply side laid up to required position.
6) Concrete placed in slab & beams are vibrated & mason level the surface.
1) Concrete grade & quantity is ordered to R.M.C. Plant one day before & concreting
time decided by R.M.C. plant & site incharge mutually.
3) Pipe line lay up to the required position of slab, with proper support.
4) Cement slurry passed over concrete pipe before just starting concrete.
5) Concreting carrying through transit mixer is delivered in concrete pump, Bucket &
than pumped it to require level. Concrete pipe can moved anywhere with the help
of additional pipe, bends & clamp.
6) Concrete vibrated by vibrator with needle 40mm dia. & 60mm dia. Surface leveled
by mason with Patti & trowel. After completing the concrete Ball Pass process is
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/312/REV-0
Page : 5 of 6
done for cleaning pipe line & Pump Hopper with the help of Air pressure or water
pressure.
7) Cube cast 6 nos. with tamping 16 times for each layer & finished with trowel. &
Coding done as date of casting, Grade of concrete, Location of the structure.
2) If honey comb seen than it finished by cement, trowel as per S.I. instruction.
3) Watta is making over slab next day & ponded with water for 14 to 28 days.
7) Water sprinkling just after concrete set during casting of slab for rounding surface
cracks.
B) ENVIRONMENT:-
1) Open Cement bag by removing stitches & change directly in beaching / mixing
plant to prevent west of cement.
2) Do not throw / drop cement bags to prevent air pollution by dust severation.
4) Do not use Water pipe having any leakage / damage & prevent west of water.
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/312/REV-0
Page : 6 of 6
7) Use Hessian cloth to cover the concrete surface to reduce evaporation loss.
1) Use Helmet, safety shoes, Gum boot, Rubber Hand Gloves & safety Belt at height.
5) Keep the area clean from iron bar & wooden pieces.
A) QUALITY
1. SCOPE :-
2. EQUIPMENTS :-
R.M.800 Mixer or Batching plant with transit mixer or concrete out sources from
supplier.
2) Dumpy level.
3) Tower Crane.
8) Shuttering material like:- M.S. Props 4mtr & 3mtr, Span 2.4mtr to 4.0 mtr, Cup lock
(Vertical 3mtr, horizontal 1.2m, horizontal 2.4m), Base Plate, Stirrup Head 2’0”,I-
section 125x65 mm, I-section 100x50mm, M.S. sq. pipe 50m x 50m, Joint channel
called shoulder, Tie rod with nut, coupler, 50mm dia. M.S. Round pipe, M.S. Clamp
2’6” & 3’0”, Ton Buckle, Nails 1 ½”, 2 ½”, 3”, 12 mm P.C. Ply, Wooden Chavi
3”x4”x5’, Lapha 4”x1 ½”x3”, Lubricant, Wooden Patti 4”X1 ½”X8’.
9) Spade, Pan, Plumb, Right Angle, Trowel, Linedoori, Curing Pipe 1” dia., Hessian
Cloth, Tarpolin Sheet, Concrete cover block,
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/313/REV-0
Page : 2 of 7
3. RESPONSIBILITY :-
1) Site Incharge
2) Sr. Engineer
4. WORK INSTRUCTIONS :-
1) Ensure the approved Good for Construction, R.C.C. & Architectural drawing with
revision status.
2) Load design calculated & plan to design safe shuttering arrangement. Arrangement
of cuplock should be in the pattern of 1.2x1.2mtr. Or 1.2x2.4mtr. Or 2.4x2.4mtr. is
decided on that load calculation. Spacing & placing of M.S. props is also decided by
calculating safe load design calculation. Get approved from V.P./C.E./E.E.
3) List of material required is calculated & write in tabular form. S.I. discussed with
Store Incharge & C.E./E.D. for availability of materials / equipment as per required
barchart & work schedule. Then, S.I. finalise the list of materials / equipment
supplied by store & requisition submitted for purchasing balance
materials/equipments. All these exercise done during mobilization period of
project.
4) Making of ply start for beam bottom & side of beam. Beam bottom is made with
12mm P.C. Ply with battens of 4”x1 ½” @ 10” c/c. Beam side is made with 12mm
P.C. Ply as required size in drawing with 4:x1 ½” batten @ 10” c/c along length &
both end in width.
5) Datum Level mark on column for fixing beam bottom as per floor height mention
in drawing.We should ensure the beam face over respective column as per room
dimensions with respect to RCC & Architctural drawings.
6) Topi of beam bottom fixed on column as per required depth of beam & than beam
bottom rest over them with vertical props supports @ 2’ c/c. If there is projection of
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/313/REV-0
Page : 3 of 7
chajja or beam bottom width is more than 1’0”, than beam bottom along with
chajjais placed over adjutant two span with cantilever, wooden chavi of 4”x3”x5’
length. Both end of span is supported by M.S. Props.
9) Inner beam side erect over beam bottom with the help of nails. Making sides are
also placed over cantilever chavi 4”x3”, if projection is required for chajja.
10) Gabdi of column & beam junction closed properly. Gabdi of slab also set by ply. We
should insure that ply junction should have miner gap. Gabdi of column is clamped
by shoulder & tie rod.
12) Beam bottom & side is clamped with Shikanja & middle & top portion is supported
by wooden Patti of 4”x1 ½” taking support from cantilever chavi.
13) M.S. Props is braced by 2” dia. M.S. pipe with the help of swing coupler.
Reinforcement:
1) Reinforcement is cut & bends in steel yard as per required size & position
mentioned in RCC Drawing.
2) Cut & bend steel is placed over slab by manually or by crane. Tagging start by
binding wire with proper placement of steel. Ring is also provided for Beams &
columns as specified.
4) Steel Chair is provided over bent up & double Jali for proper position of
reinforcement.
7) Take the JMR of Reinforcement for 1st slab only with estimation division & confirm
the estimated qty to proceed for rest of Slab.
8) Now we can pour the concrete in slab, beam, and chajja after rectification done.
Concreting:
1) Before starting concreting, we check the condition of R.M.800 mixer, lift hoist &
concrete pump. Diesel & Oil is filled if machine of diesel.
2) One mason with Randha, Patti, spatula is required for finishing concrete surface.
3) Vibrator of needle 40mm dia. & 60mm dia. is kept over slab with one stand by.
4) Concrete filling level is marked over beam side & column for maintaining surface.
Concrete filling Kanda is also provided to mason for checking randomly.
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/313/REV-0
Page : 5 of 7
2) Mix design set in panel for required weight of Aggregate, Cement, Sand,
Admixture & water.
3) Aggregate & cement placed into mixer manually, till getting correct required
display, mixer takes water automatically admixture is placed manually by
measuring Jar.
4) Concrete is mixed & unloaded in suit of lift. Concrete lifted through hoist &
dump in tray over the surface of slab.
5) Concrete is transported at required place with the help of wheel barrow. Wheel
barrow runs over the surface of making ply side laid up to required position.
6) Placed concrete in slab, beams are vibrated & mason level the surface.
1) Concrete grade & quantity is Send to R.M.C. Plant one day before & concreting
time decided by R.M.C. plant & site incharge mutually.
3) Pipe line lay up to the required position of slab, with proper support.
5) Concreting carrying through transit mixer is delivered in concrete pump, Bucket &
than pump it to required level. Concrete pipe is moved anywhere with the help of
additional pipe, bends & clamp.
6) Concrete vibrated by vibrator with needle 40mm dia. & 60mm dia. Surface leveled
by mason with Aluminum Patti & trowel.
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/313/REV-0
Page : 6 of 7
7) After completing the concrete Ball Pass process is done for cleaning pipe line &
Pump Hopper with the help of Air pressure or water pressure.
8) Cube cast 6 nos. with tamping 16 times for each layer & finished with trowel.
2) If honey comb seen than it finished by cement, trowel as per S.I. instruction.
3) Watta is making over slab next day & ponded with water for 14 to 28 days.
7) Water sprinkling just after concrete set during casting of slab for arounding surface
cracks.
B) ENVIRONMENT:-
1) Cut Cement bag by removing stitches & change directly in beaching / mixing plant
to prevent west of cement.
2) Do not throw / drop cement bags to prevent air pollution by dust severation.
3) P.U.C. Checked of all vehicle enter in premises.
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/313/REV-0
Page : 7 of 7
4) Do not use Water pipe having any leakage / damage & prevent west of water.
7) Use Hessian cloth to cover the concrete surface to reduce evaporation loss.
1) Use Helmet, safety shoes, Rubber Hand Gloves & safety Belt at height.
5) Keep the area clean from iron bar & wooden pieces.
A) QUALITY
1.0 SCOPE:-
2.0 EQUIPMENT:-
Farma, Tray (6’x4’x0’8”=16 cft), Spades, Mortar Pan, Line Dori, Plumb,
Rt. Angle, Tape, Scaffolding material, Planks, Chisels, Trowel, Drilling
machine, Curing Pipe, Primer, Hold fasts, etc.
3.0 RESPONSIBILITY:-
1) Site Incharge/QA
2) Site Supervisors
2) Get the entire floor clean & hack (min 50 Nos/sft) column, beam,
slab, etc. from R.C.C. contractor.
5) Remove the loose material & water the surface where brick work is to
be erected.
11) Apply rich mortar (1:4) on column face which has to be in contact
with brick work for proper bonding.
12) Execute the brick work layer by layer up to window cill level.
13) Check each layer of brick work for line, level & plumb.
14) Ensure the joints of brick work are staggered & uniform (15mm).
15) Use following material for dry mix (should not more than 2 bags at a
time)
Cement – 1 bag
Fly Ash – 1 bag (30 kg)
Crush Sand – 15 cft (farma 2’6”x2’6’x1’2”=7.5 cft x 2)
16) Take part of dry mix and pour water to get workable mortar.
18) Rake the joints after every 3-4 layers, reuse the splitted mortar.
20) For 4” thick brick wall cast R.C.C. patli of 4” thick at every 1m
height.
21) Continue brick work above sill & keep window opening as per
drawing considering margin of plaster/gypsum (25 mm).
24) Fix the khadi in mortar for the joint between beam & the last layer of
brick work and vertical face of column & brick work.
26) Cure the brick work for 15 days atleast 3-4 times a day.
27) Daily reconcile the material used for the quantum of work done w.r.t.
constant given in estimate.
28) Site Incharge to prepare the material consumption statement for the
1st floor compare with the estimate and further get it approved if
any correction is required.
29) Get the written clearance from HOD Estimation (EST/M&P/501) for
material consumption.
B) ENVIRONMENT:-
5) Spread some sheets below the work place for collecting the mortar
falling down for reuse.
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/314/REV-0
Page : 4 of 4
QEHS WORK INSTRUCTIONS FOR CONSTRUCTION OF
TITLE :
BRICK WORK.
3) Use safety Helmet, Shoes, Rubber Hand Gloves, Mask and Safety
Belt.
5) Ensure lifting machines are not overloaded, & brakes are intact.
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/315/REV-0
Page : 1 of 4
QEHS WORK INSTRUCTIONS FOR INTERNAL GYPSUM
TITLE :
FINISH PLASTER.
A) QUALITY
1.0 SCOPE:-
Applicable for internal walls & celling for all rooms except the kitchen & toilet
dado areas.
2.0 EQUIPMENT:-
3) Check the entire floor should be neat & clean after masonary work.
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/315/REV-0
Page : 2 of 4
QEHS WORK INSTRUCTIONS FOR INTERNAL GYPSUM
TITLE :
FINISH PLASTER.
4) Check the opening kept for main door , Bed room doors , terrace F.D
toilets doors , & all windows are correctly kepts as per the chart
prepared by site incharge e.g.
5) Execute the thiyya work by using M.S farma made especially for Gyp.
6) Check all the thiyyas given by Gyp agencies by using the farma only.
Set the right angle w.r.t long wall & ie Dinning passage wall (Base
line.)
Set the right angle for all the bedrooms, toilets. Kitchen. Etc w.r.t to
base line.
Mark all the thiyyas at 16” ht. ie farma ht level.
Extend all the thiyyas up to 8’0” ht called as Dhaddas.
Start all concealed electrical works.
Check all Ele. Concealed conduits, joints in BBM are filled with
morter.
Apply 1’-0” ht smooth ghotai plater at skirting level as shown.
Ensure all the Ele. Points are done as per the drg & Specification.
Ensure all Electrical point heights as per the sample flat done at site.
Check the P.V.C chicken mesh 6” wide patta used for all R.C.C &
masonry joints & over the concealed conduits.
Ensure tachya 50 no. / Sft. for beam , column, ceiling, loft/lintel cills.
Before calling QAD. For NOC.
Get the NOC from ( QAD/Gyp/501) for the commencement of Gyp.
Check the Gyp cutting on wall 7” from slab level to avoid excessive
but finishing /waviness in Buttfinishing.
Check all the dhars made rounded by using farmas it should be 5mm
rounded.
Use kerakol P-5 chemical for ceiling before application of Gyp.
Kerakol P-5 chemical to be used 1:1:3 – mix 1part chemical +1part
cement +3parts of water application by brush to avoid debonding of
ceiling Gyp.
Keracol has suppose to give Guarantee certificate of chemical
bonding.
Ensure the consumption. - 1.0 lit / 165 sft.
Check the reference level marked on beam 9” below the ceiling level.
Check rest ceiling gyp done in line not in level tube & should not
found any waviness by visual.
Check for maindoor & bedroom doors , opening one side & top is
finished in Gyp to fix the wooden door frame.
Check the ceiling Dhadda at corners with reference to level marked
on Beam.
Check the kutch of ceiling & wall, should not found any waviness.
Gyp at ceiling min 1’-0” patta should be in perfect level.
Keep the all toilets /passages ceiling Gypsum should be in perfect
level b-coz of the small areas.
Carry out toilet ceiling and wall gypsum only after completion of
Dado & floor only to maintain the accuracy in line / level.
Carry out kitchen Dry balcony side wall after completion of kitchen
otta Dado.
Check all the kutch perfectly done in right angle & should not found
waviness.
Carry out the Butt finishing work 1 week after completion of skirting.
Use Farma for Butt finishing to maintain perfect 4mm Tile projection
all over.
Try to maintain loft patta 5” wide uniformly all over.
Try to maintain vertical jams of window 5” wide all over.
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/315/REV-0
Page : 4 of 4
QEHS WORK INSTRUCTIONS FOR INTERNAL GYPSUM
TITLE :
FINISH PLASTER.
1.0 ENVIRONMENT :
A) QUALITY
1.0 SCOPE:-
2.0 EQUIPMENT:-
2. Site supervisor.
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/316/REV-0
Page : 2 of 3
a) Internal Plastering :
I ) Procedure :
B) ENVIRONMENT:-
Use safety helmets for the working masons, M/C & F/C.
Use safety belts for persons working on scaffolding.
Use safety jackets for mason & M/C.
Use safety shoes for the mortar mixing male coolie.
Use hand gloves for mason , mortar mixing m/c & who are handling the
mortar pans.
Check the stability of M.S scaffolding tie it every alternate floor by 2” Φ M.S
bracing pipe & coupler.
Tie the bamboo / m.s plank used by katya.
Tie it M.S / Bamboo planks used for working platform by kathya ensure the
tying done correctly or not.
Ensure the safety net provide at different levels ie 2nd floor , 5th floor , 8th floor
& 11th floor level.
Ensure proper bamboo/G.I sheet baricatting around lift M/C.
Ensure lifting machines are firmely fixed with prop & sand bags to avoid
toppling.
Ensure lifting machines are not overloaded & brakes are in intact.
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/316/REV-0
Page : 1 of 4
QEHS WORK INSTRUCTIONS FOR EXTERNAL SAND FACE
TITLE :
PLASTER.
A) QUALITY
1.0 SCOPE:-
Applicable for external sides, all ducts above terrace , Dry balconys ,Entire
parking column & walls etc.
2.0 EQUIPMENT:-
Use 8” wide ½ x ½” size G.I chicken mesh for all RCC & masonary joints.
Use 1 ½” G.I nails & ¾” G.I washers for fixing chicken mesh.
Check the stability of M.S Scaffolding as well as bamboo scaffolding.
If M.S scaffolding is used, provide cross support 2” Φ M.S pipe bracing with
coupler for alternate floor to avoid the lateral movement.
Equipment - Ensure the requirement of cuplock in the ratio of q -
1: 2.5: 1.5
10’0” 4’0” 8’0”
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/316/REV-0
Page : 2 of 4
QEHS WORK INSTRUCTIONS FOR EXTERNAL SAND FACE
TITLE :
PLASTER.
Check the Grooves provided for the plain surface & at two level only.
Check the depth of groove. ( should not more than 5mm) 1 at 6” above cill level
& 2nd at 6” below lintel.
Check the finishing & level of the groove, It should be neatly finished in cement
past.
For the eye level terrace maintain 6” cutting of plaster above normal slab for
waterproofing work.
In any case do not raise the plaster thickness for patta more than 1” thick.
For box type window cill , check the level of outside patta & subframe level as
per sketch given. IPS plaster – It should be ¾” drop & 1” slope towords outside
in BBM & RCC. As per sketch -
Ensure & Check the panipattis of size 1 ½” x 5 mm project for all the external
side openings.
Record details in M&M in process activity registers ( QAD / 702 ) duly singed
by QA / S.I.
Site incharge to prepare the material consumption statement for side wise &
compare with the estimate & further get it approved if any correction is
required.
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/316/REV-0
Page : 4 of 4
QEHS WORK INSTRUCTIONS FOR EXTERNAL SAND FACE
TITLE :
PLASTER.
B) ENVIRONMENT:-
Use safety helmets for the working masons, M/C & F/C.
Use safety belts for persons working on scaffolding.
Use safety jackets for mason & M/C.
Use safety shoes for the mortar mixing male coolie.
Use hand gloves for mason , mortar mixing m/c & who are handling the
mortar pans.
Check the stability of M.S scaffolding tie it every alternate floor by 2” Φ M.S
bracing pipe & coupler.
Tie the bamboo / m.s plank used by katya.
Tie it M.S / Bamboo planks used for working platform by kathya ensure the
tying done correctly or not.
Ensure the safety net provide at different levels ie 2nd floor , 5th floor , 8th floor
& 11th floor level.
Ensure proper bamboo/G.I sheet baricatting around lift M/C.
Ensure lifting machines are firmely fixed with prop & sand bags to avoid
toppling.
Ensure lifting machines are not overloaded & brakes are in intact.
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/317/REV-0
Page : 1 of 4
1.0 QUALITY :
C. P. Fittings :
Check extra amenity if any.
Fix C.P. fitting with Teflon tapes to proper points.
Cover all fittings with Polythin bag after fixing.
Flanges for all taps is MUST.
Check CP fitting for water flow and clean the same.
Check CP fitting for pressure 2.5 kg/cm2
Cover all fitting with polythin bag after pressure testing
Sanitary Fittings :
Check extra amenity if any.
Fix all Sanitary wares in position, line & level.
Check all joints for water tightness.
Check all sanitary ware for its fixity.
Record details are in M&M in Process Activity Register. (QAD/702)
duly signed by QA/S.I.
2.0 ENVIRONMENT:
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/317/REV-0
Page : 4 of 4
REF : QEHS/318/REV-0
Page : 1 of 5
A) QUALITY
1.0 SCOPE:-
2.0 EQUIPMENT:-
Measuring tape, line dori, G.I socket 1 ¼” 5’0” 4.6 pipe (1 ¼”), Thapi,
Wooden floor, Randha, Plum bob, level tube, Morter, Farma – size
1:6,1:4, Aluminium patti, Curing pipe, Drum.
3.0 RESPONSIBILITY:-
1. Site Incharge
2. Site Engineer./superviser.
i) Ensure the relevant drg. Is available & read for plumbing out
let & inlet.
iv) Proper fixing & checking for inlet & outlet fixing as per drg. – (
NOC from QA)
1
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/318/REV-0
Page : 2 of 5
x) After 12 hours started curing & fill up the tank with water in 3 to 4
days. 15 days check for any leakages.
B) U.G.W.T
10. Proper cleaning at raft thickness & joint of bottom slab rough shabad
& paradi , joint above raft.
11. Fixing of rough shahbad in offset for raft & parade with cement pro
& seal the joint with cement mortar 1:3 with 15 mm metal.
12. Fix rough shahbad on vertical pardi with cement at 1 m hight only.
2
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/318/REV-0
Page : 3 of 5
16. Seal the top of final layer with cement paste.( NOC From QA)
C) TOILET W/P
vi) Fixing of nahni trap W/C outlet & WHB outlet.( NOC from QA)
viii) Fill up the joint with cement mortar 1:6 ( Farma size)
ix) Finish the top coat with 1:4 cement mortar continue top ghodi on
wall up to 1’0” hight above floor finish level.
x) Cure for 7 days by closing nahni trap outlet & by filling water.
xi) Record the details in M&M in process activity register ( QAD 102 )
daily sign by S.E , S.I , QA.
3
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/318/REV-0
Page : 4 of 5
C) Terrace W/P
2) Clean the entire terrace slab. With water. ( NOC from QAD)
8) Finishing top coat with 1:4 cement mortar & make up to 9” hight on
parapet on wall ie watta in cement ghotai. ( NOC from QAD )
9) Ensure that watta (ie joint of parapet & brick bat ) in 15mm metal in
1:4 cement morter.
10) Next day make kani dhar 9” above top finish coat in level.
11) Close the rain water opening & curing the terrace by ponding ( filling
water up to 6” min)
B) ENVIORNMENT
4
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/318/REV-0
Page : 5 of 5
5) Before starting the work for cleaning dabries & chaseling Sprink
water to reduce air pollution dust and privent.
2) Use safety helmet / shoes / rubber handgloves marker & safety belt
on slopping side.
4) Ensure that proper baricating around material lift machine & winch
machine.
5) Ensure that lifting machines are not overloaded & brakes are intact
5
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/319/REV-0
Page : 1 of 9
A) QUALITY
1.0 SCOPE:-
2.0 EQUIPMENT:-
3.0 RESPONSIBILITY:-
1) Site Incharge
2) Site Engineer/Supervisor.
FLOORING
1) Ensure the shop Drawing is made available from HOD Estimation &
read.
2) Get the samples approved for various tiles from HOD Purchase.
4) Ensure that material required for activity is received & duly checked
by SI.
7) Mark level @ 60 cm. (2’.0”) height on walls of entire flat in blue colour
with line dhori.
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/319/REV-0
Page : 2 of 9
8) Confirm “L” type cement ghotai 1’0” on wall & 3” on slab top is done
(at skirting level)
9) Use 50% crush sand & 50% River sand for bedding.
a. Cement - 1 bag
b. River sand – 6.25 cft.
c. Crush Sand- 6.25 cft.
d. Farma Size – 2’ 0”x 2’0”x 1’7”
10) Lay the Electrical conduits in bedding before starting the flooring (if
any).
11) Take right angle as per shop drawing. ( i.e. Main door adjacent wall
& passage) for fixing tile .
12) Fix the tiles, one by one (bedding at a time for one tile only).
13) Ensure the arrow on back side of the tile is in one direction only.
14) At the time of fixing check the tile for bend , crack & Otta.
15) Check the tiles for shade variation at the time of fixing.
16) Maintain the line of tile for living / Dining / Passage /Kitchen and
for other rooms, lines are separately maintained.
19) Collect the cut pieces balance from flooring and use for the skirting as
per required size.
20) Fix 3” skirting parallel to line of flooring tile (to maintain uniform
Dutta) and maintain the joints w.r.t. flooring joints.
REF : QEHS/319/REV-0
Page : 3 of 9
22) Grout the skirting with 1:3 Mortar and finish the top.
25) Fill up the joint of flooring & skirting with white Cement.
28) Finish the butt of skirting with gypsum after one week.
30) Get the actual consumption of tiles verified with HOD Estimation,
finalize the percentage wastage and maintenance quantity for further
procurement.
33) Prepare the chart of receive/issue of tiles Lot-wise and date-wise for
flats.
TERRACE FLOORING
2) Ensure the shop Drawing is made available from HOD Estimation &
read.
3) Get the samples approved for various tiles from HOD Purchase.
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/319/REV-0
Page : 4 of 9
5) Ensure that material required for activity is received & duly checked
by SI.
11) Check equal offset from tile joint (line) to Balcony/ Door frame for
right angle.
14) Fix the skirting top in level (not in slope) Minimum height 3” from
flooring & 15 mm projected from External plaster.
17) Ensure that the joint between bedroom flooring & terrace flooring
(off-set) is sealed and tile piece is fixed.
REF : QEHS/319/REV-0
Page : 5 of 9
23) Get the actual consumption of tiles verified with HOD Estimation,
finalize the percentage wastage and maintenance quantity for further
procurement.
26) Prepare the chart of receive/issue of tiles Lot-wise and date-wise for
flats.
TOILET FLOORING
1) Ensure the shop Drawing is made available from HOD Estimation &
read.
2) Get the samples approved for various tiles from HOD Purchase.
4) Ensure that material required for activity is received & duly checked
by SI.
REF : QEHS/319/REV-0
Page : 6 of 9
9) Ensure empty bag in N. Trap, WHB, outlet & commode out let to
avoid chock up.
Nahani Trap
17) Ensure that the joint between flat flooring & toilet flooring ( Drop )
finished with grout to avoid Seepage.
REF : QEHS/319/REV-0
Page : 7 of 9
24) Get the actual consumption of tiles verified with HOD Estimation,
finalize the percentage wastage and maintenance quantity for further
procurement.
27) Prepare the chart of receive/issue of tiles Lot-wise and date-wise for
flats.
DADO TILING
1) Ensure the shop Drawing is made available from HOD Estimation &
read.
2) Get the samples approved for various tiles from HOD Purchase.
4) Ensure that material required for activity is received & duly checked
by SI.
9) Set the base line up tile in line, level , plumb & right angle.
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/319/REV-0
Page : 8 of 9
10) Take full tile height from wet area (N. Trap).
12) Ensure that all concealed plumbing inlet & outlet sealed with plug.
14) Ensure that cutting of tile concealed plumbing & Electrical switch
board as per size of fitting.
15) Fix the tile with cement paste (Entire surface area of tile ).
18) Finish the top of tile dado with cement paste in line, level & right
angle.
22) Get the actual consumption of tiles verified with HOD Estimation;
finalize the percentage wastage and maintenance quantity for further
procurement.
25) Prepare the chart of receive/issue of tiles Lot-wise and date-wise for
flats.
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/319/REV-0
Page : 9 of 9
B) ENVIRONMENT :
1) Do not waste cement, sand, water and tiles because of mishandling / leaks.
2) During tilling work if polishing machine is used, ensure doors and windows
are closed.
4) Collect all the broken tiles / stones in bags and reuse them in staircase or
landings, if possible
5) Keep cut pieces with short corners away from work place.
8) Keep the marble & granite uncut pieces in proper stand, and avoid cutting
near stand with proper angle.
REF : QEHS/320/REV-0
Page : 1 of 4
A) QUALITY
1.0 SCOPE:-
2.0 EQUIPMENT:-
3.0 RESPONSIBILITY:-
1) Site Incharge
2) Site Engineer/Supervisor.
1) Slab conduiting.
2) Ensure that relevant approved drg is available electrical work & read it.
6) Junction boxes & fan boxes fix as per drg at the time conducting.
1
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/320/REV-0
Page : 2 of 4
2) WALL DROPING
1) Ensure that relevant approved drg is available electrical work & read
4) Mark the floor level on wall & wall droping line vertical with
cancelled Box position.
5) Fix the concealed box in line , level & flush to gypsum thiyya in
mortar 1:4
9) In droping more than two pipe provide fiber mesh before plastering.
3) WIRING/SWITCH PLATE
2
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/320/REV-0
Page : 3 of 4
6) Fix dummy plate for all open fan point ,A/C outlet, junction box if
require.
B) ENVIRONMENT :
Do not allow more temporary electrical connections than the
sanctioned.
Ensure lights / fans are put off in site office whenever you are leaving
the office.
Do not spread insulation material in the working place.
Use proper equipment for warming up and handling of tar.
Use proper size conductors to minimize losses.
Use timer / photo voltaic switch for control of outdoor lights.
3
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/320/REV-0
Page : 4 of 4
4
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/321/REV-0
Page : 1 of 4
WORK INSTRUCTIONS FOR FIXING ALUMINIUM
TITLE :
WINDOW
A) QUALITY
1.0 SCOPE :-
2.0 EQUIPMENT:
i) Drill Machine
ii) Screw Driver
iii) Hammer
iv) Chisel
v) Silicon Sealant Gun
vii) Blower
viii) Helmet
3.0 RESPONSIBILITY:-
i) Site Incharge
ii) Site Supervisors.
iii) QAD Engineer
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/321/REV-0
Page : 2 of 4
WORK INSTRUCTIONS FOR FIXING ALUMINIUM
TITLE :
WINDOW
8 Track fixing on the sub frame with screw of required size @ 2' C/c
9 Lock fixing at centre of shutter
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/321/REV-0
Page : 3 of 4
WORK INSTRUCTIONS FOR FIXING ALUMINIUM
TITLE :
WINDOW
10 Slot for lock is of exact size (It should not be over size)
S.S. Net Shutter fixed after final Coat & acid wash, antilifter should be
11
provided to each Shutter
12 Protection tap of Section remove after S.S. Net Shutter fixing
Silicon Sealant Filled at all Corner of Track & the gap between Bottom
13
Track & sub frame
14 Visible verification of window for any Damage & Scratch
15 Clean the bottom track by air Blower
16 Ensure Smooth working of Shutter ( sliding) & it should be Tilt free
17 Ensure smooth working of Lock
B) ENVIRONMENT :
Use proper plumb scaffolding; tie the entire platform used for men and material.
Ensure ladders are sturdy.
Use handrail and guard rail while working at height. (guard rails)
Use safety Helmet, Shoes, Rubber Hand Gloves, Mask and Safety Belt.
Ensure proper barricading around material lift machine.
Ensure lifting machines are not overloaded, & brakes are intact.
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/322/REV-0
Page : 1 of 9
WORK INSTRUCTIONS FOR INTERNAL, EXTERNAL
TITLE :
PAINTING AND MELAMINE POLISHING WORKS
A) QUALITY
1.0 SCOPE :-
2.0 EQUIPMENT:-
1) 4" Brush
2) M.S Patti
3) Ladder
4) Mug
5) Steel Scraper.
6) Mask
7) Sand Paper
3.0 RESPONSIBILITY:-
i) Site Incharge
ii) Site Supervisors.
iii) QAD Engineer
4.0 WORK INSTRUCTIONS:-
INTERNAL PAINTING
OBD : -
1) Ensure the Specification of Material & Location of Application &
its Finish.
2) Ensure that all Internal Finishing work Gypsum, Tiling &
Electrical Work Completed, also QAD NOC for the same.
3) Ensure that all walls are sufficiently dried. No
dampness/leakages observed.
4) Ensure that Main Door Shutter & Aluminium Window are Fixed.
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/322/REV-0
Page : 2 of 9
WORK INSTRUCTIONS FOR INTERNAL, EXTERNAL
TITLE :
PAINTING AND MELAMINE POLISHING WORKS
INTERNAL PAINTING
Luster : -
1) Ensure the Specification of Material & Location of Application & its
Finish.
2) Ensure that all Internal Finishing work Gypsum,Tiling & Electrical
Work Completed, also QAD NOC for the same.
3) Ensure that all walls are sufficiently dried. No damages/leakages
observed.
4) Ensure that Main Door Shutter & Aluminium Window Fixed.
5) Put on the mask before starting any scraping/painting activity, while
cleaning the surface, ensure Doors & Windows are closed/covered so
as to prevent spreading of paint smell /emission.
6) Clean the surface by Sand Paper No 100 for wall & Ceiling & clean by
Dry Cloth.
7) For 1stCoat of primer of approved brand, mix 1 litre primer to 100ml of
Turpentine thoroughly.
8) Apply 1st coat primer with brush uniformly.
9) Drying period for Primer minimum 12 to 24 hrs.it should not be
elongated more than 15 days.
10) Prepare lambi by mixing 20kg whitening powder with 6 litre of water &
2 litre of oil paint .
11) Apply lambi with Palti patra in line & level.
12) Ensure proper finish at dhar ,kutch & Jambs.
13) After completely drying of 1st coat lambi , apply 2nd coat as per above
procedure with proper surface finish.Thickness of lambi should not be
more than 2mm including 1st & 2nd Coat.
14) Ensure surface should be in line, level without any undulation.
15) After completely drying of 2nd coat, lambi start sanding by the wall
surface with sand paper No.150 & clean with dry cloth.
16) Prepare the Aster (Base) coat paint by mixing 1 litre of Primer with 1
litre of oil paint(1:1 Ratio) & add 300ml Turpentine in the mixture.
17) Apply Aster (base)coat by brush & finish immediately by roller Apply
it Vertically & horizontally.
18) Next day any cracks/surface damage, scratches observed will be filled
by putty & paint touchup.
19) After completing crack filling & paint touchup, 1st coat of Luster paint
should start.
20) Prepare mix for luster paint by mixing 1 litre of luster with 100 to 125
ml of Turpentine.
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/322/REV-0
Page : 4 of 9
WORK INSTRUCTIONS FOR INTERNAL, EXTERNAL
TITLE :
PAINTING AND MELAMINE POLISHING WORKS
INTERNAL PAINTING
PLASTIC PAINT : -
1) Ensure the Specification of Material & Location of Application & its
Finish.
2) Ensure that all Internal Finishing work Gypsum, Tiling & Electrical
Work Completed, also QAD NOC for the same.
3) Ensure that all walls are sufficiently dried. No damages/leakages
observed.
4) Ensure that Main Door Shutter & Aluminium Window Fixed.
5) Put on the mask before starting any scraping/painting activity, while
cleaning the surface ,ensure Doors & Windows are closed/covered so
as to prevent spreading of paint smell /emission.
6) Clean the surface by Sand Paper No 100 for wall & Ceiling & clean by
Dry Cloth.
7) For 1stCoat of primer of approved brand, mix 1 litre primer to 100ml of
Turpentine thoroughly.
8) Apply 1st coat primer with brush uniformly.
9) Drying period for Primer minimum 12 to 24 hrs.it should not be
elongated more than 15 days.
10) Prepare lambi by mixing 20kg whitening powder with 6 litre of water &
2 litre of oil paint .
11) Apply lambi with Palti patra in line & level.
12) Ensure proper finish at dhar ,kutch & Jambs.
13) After completely drying of 2nd coat, lambi start sanding by the wall
surface with sand paper No.150 & clean with dry cloth.
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/322/REV-0
Page : 5 of 9
WORK INSTRUCTIONS FOR INTERNAL, EXTERNAL
TITLE :
PAINTING AND MELAMINE POLISHING WORKS
14) Prepare the Aster (Base) coat paint by mixing 1 litre of Primer with 1
litre of oil paint(1:1 Ratio) & add 300ml Turpentine in the mixture.
15) Prepare the Aster (Base) coat paint by mixing 1 litre of Primer with 1
litre of oil paint(1:1 Ratio) & add 300ml Turpentine in the mixture.
16) Apply Aster (base)coat by brush & finish immediately by roller Apply
it Vertically & horizontally.
17) Next day any cracks/surface damage, scratches observed will be filled
by putty & paint touchup.
18) After completing crack filling & paint touchup, 1st coat of Plastic paint
should start.
19) Prepare mix for Plastic paint by mixing 1 litre of Plastic paint with 500
ml of water.
20) Apply 1st coat or plastic paint with brush & finish immediately by roller
vertically & horizontally.
21) Ensure finish as per approved sample/requirement.
22) Minimum drying period is 24 to 48 hours.
23) Ensure surface should be completely dry.
24) Before applying 2nd coat ensure that all electrical accessories /door
fitting & melamine polish door shutter to be covered.
25) Ensure all touch up work done with paint before final painting
wherever required.
26) Apply 2nd coat of plastic paint with proper paint cutting at wall &
ceiling with most care of application with same above procedure & mix.
27) Ensure that no brush mark, air bubble, roller strip, shine .
28) Clean all the paint stain after final painting.
INTERNAL PAINTING
1) Ensure the Specification of Material & Location of Application & its Finish.
2) Ensure that all Internal Finishing work Gypsum, Tiling & Electrical Work
Completed, also QAD NOC for the same.
3) Ensure that all walls are sufficiently dried. No dampness/leakages
observed.
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/322/REV-0
Page : 6 of 9
WORK INSTRUCTIONS FOR INTERNAL, EXTERNAL
TITLE :
PAINTING AND MELAMINE POLISHING WORKS
4) Ensure that Main Door Shutter & Aluminium Window are Fixed.
5) Put on the mask before starting any scraping/painting activity, while
cleaning the surface ensure Doors & Windows are closed/covered so as to
prevent spreading of paint smell /emission.
6) First clean the the wall surface with wire brush, Sand paper (150 grit) or
blade (patra) to remove all loose material (Cement mortar/gypsum).
7) Pre-wet/dampen the wall with water by brush or roller.
8) Mix putty of approved brand with water in ratio 2:1 . Mixing should be
done by machine to make thick paste. Maximum 10kg of putty mix with 5
litre of Water at one time.
9) Apply first coat of putty with blade starting from bottom upwards. Keep
the thickness of 1st Coat upto 1.2mm.
10) Wait for complete drying, it takes 3 to 4 hrs.
11) No need of sanding after 1st coat. Apply 2nd coat of putty with blade.
Thickness of 2nd Coat is nearly half the thickness of 1st coat (i.e
0.6mm).Keep total thickness of putty(1st + 2nd coat) upto 1.8mm on
gypsum surface.
12) Sanding the surface after 2 days with fine Emery paper (400 grit) to
remove blade scratch mark & make surface smooth.
13) Prepare Oil paint mix by mixing 1 ltr Oil paint with 150 ml turpentine.
14) Apply 1st Coat of Oil Paint from Top to Bottom with 4" brush than finish
immediately with roller applied vertically & horizontally.
15) Leave the paint surface to dry at least One Day.
16) Before applying 2nd coat ensure that all electrical accessories /door
fitting & melamine Polish door shutter to be covered.
17) Ensure that all dents/scratches/undulation properly filled & finished.
18) Ensure all touchup marks work to be painted before 2nd coat painting.
19) Apply 2nd coat paint with proper paint cutting at wall & ceiling with
most care of application with same above procedure.
20) Ensure that no brush mark, air bubble, roller strip, shine.
21) Clean all the paint stain after painting.
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/322/REV-0
Page : 7 of 9
WORK INSTRUCTIONS FOR INTERNAL, EXTERNAL
TITLE :
PAINTING AND MELAMINE POLISHING WORKS
INTERNAL PAINTING
EXTERNAL PAINTING
12) Apply 1st coat of Acrylic Paint by mixing 1 ltr paint to 400 ml of
water (It may be vary brand to brand.
13) Apply paint with brush uniformly with both direction.
14) Cleaning the work place & remove all paint stains immediately.
15) After application of 1st coat, application of 2nd coat should be done
after minimum 24hrs gap.
16) If applied after gap of 7 days or more than remove dust & loose
particle by water.
17) Ensure Surface should be dry before application of 2nd Coat.
18) Apply 2nd coat with mix same as 1st coat by brush in both diection.
19) Ensure paint should be applied at every corner, nitch, patta
downtake lines etc.
20) Ensure all cleaning work at window glass frame/railing/folding
shutter etc.
MELAMINE POLISH
B) ENVIRONMENT
i) Before the start of site cleaning, sprinkle water to reduce dust and
prevent air pollution
ii) Use mask, safety shoes for site cleaning and line out.
A) Quality:-
Equipment:-
2) Working drawings
4) T. B. M.
6) Machineries
Responsibility:-
Work Instructions:-
HOD D&D to issue approved drawings i.e. layout done with total station,
working drawings, cross Section of wall and detail drawings.
Study of drawings.
Physical demarkation & line out by surveyor on site with total station.
Take the original ground levels w.r.t. TBM.
Excavation up to design strata & dewatering if required.
Take the excavated levels for estimation & billing purpose.
PCC as a leveling course.
UCR masonry below GL as per section drawing, 4” dia. PVC pipe weep holes at
5’0” C/C & staggered above at 2’6” height, RCC headers at 5’0” C/C &
staggered above at 2’6” height.
Keep the expansion joint of 3” width after every five bays of BBM above UCR.
Fixing of key stones at 2’ c/c distance at every layer of UCR for bonding the
next above layer.
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/323/REV-0
Page : 2 of 2
QEHS WORK INSTRUCTIONS FOR CONSTRUCTION OF
TITLE :
COMPOUND WALL WORK
Max. height of UCR 1’6” above made up GL or adjucent plot which ever is
higher.
Casting of the PCC coping 100mm thick above top of UCR.
Divide the entire length of wall in to equal bays between 9’ to 10’ ( each bay ).
Keep the expansion joint of 3” after every 5 bays.
6” brick wall to be construction at external face between two pillar of 15” x 15”
for each bay.
Height of compound wall including railing shall be min 7’ above made up GL.
Top of pillar should be 1’ above railing / brick wall top.
Keep 4” gap between brick work & railing.
Grout the railing in brick pillar with two hold fasts on either side.
Pointing / plaster for UCR masonry above GL.
Double coat sand faced plaster from inside per drawing & design approved by
D&D dept.
Curing.
Painting of compound wall as per project theme.
Take NOC by QAD Engineer.
In charge development to fill the checklist – ‘C’ duly verified & approved by
P.E. & QAD.
Checklist handover to HOD co-ordination dept.
B) Environment:-
During excavation sprinkle the water to reduce dust and prevent air pollution.
G.I. sheet as barricading to reduce noise level of machineries.
Quality:-
Equipment:-
Demarkation & layout of boundary line
Working drawings
Cross section of wall
T. B. M.
Tools & plants
Machineries
Responsibility:-
HOD D&D to issue the drawings
Site In charge
Q.A.D. Engineer
In charge Development
Surveyor
Work Instructions:-
HOD D&D to issue approved drawings i.e. layout done with total station, working
drawings, cross Section of wall & detail drawings.
Study of drawings.
Demarkation & line out by surveyor on site with total station.
Take the original ground levels.
Excavation up to hard strata & dewatering if required.
Take the excavated levels for estimation & billing purpose.
PCC as a leveling course.
RCC retaining wall as per the RCC Consultant drawing approved by HOD D&D.
Shuttering for raft slab & pardi.
Cutting, binding of reinforcement at the place for raft & pardi. Tie precast covers
50mm & 40mm for raft & pardi respective.
Casting of the raft slab in required grade of concrete.
Use of tie rod system for shuttering, shuttering for RCC pardi up to 4’0” height at a
time with proper supporting from inside & outside by m.s. props at 45°.
Casting of pardi in required grade of concrete.
Curing.
Hacking for expose surface where plaster is required.
Double coat sand faced plaster with grooves & design approved by HOD D&D.
Curing.
Painting as per the project theme.
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/324/REV-0
Page : 2 of 2
QEHS WORK INSTRUCTIONS FOR CONSTRUCTION OF
TITLE :
RETAINING WALL
Environment:-
During excavation sprinkle the water to reduce dust and prevent air pollution.
G.I. sheet as barricading to reduce noise level of machineries.
Quality:-
Equipment:-
Layout
working drawings
RCC drawings
electrical drawing
Tools & plants
Machineries
Responsibility:-
HOD D&D
Site In charge
Q.A.D. Engineer
In charge Development
Work Instructions:-
HOD D&D to issue approved drawings i.e. layout, working, RCC & electrical
drawings.
Study of all drawings.
Line out of main entrance gate & security cabin.
Marking of final F.F.L. levels, road top levels etc & decide the plinth top level of
security cabin i.e. min. 1’6” above adjucent F.F.L.
Record the OGL.
Excavation of footing for main entrance & security cabin.
Record the excavated levels.
PCC for footing.
Curing to all cement activities.
Mark the column centers.
Cutting & binding reinforcement for footings & columns of main entrance gate.
Laying & fixing of electrical conduits for main entrance gate columns.
Casting of footing & columns of main entrance gate.
Errection of designed m. s. gate, rest on pivot at GL & embed top hinges in RCC
columns with m. s. plate & chemical fastener.
Keep 3” clearance between m.s. gate bottom & highest F.F.L., check the clearance
with close & open position of the gate.
Granite cladding for entrance gate columns.
Electrical wiring for main entrance gate columns with control in security cabin.
Fixing of decorative light fittings on the top of main entrance gate columns.
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/325/REV-0
Page : 2 of 2
QEHS WORK INSTRUCTIONS FOR CONSTRUCTION OF
TITLE :
MAIN ENTRANCE GATE & SECURITY CABIN
In charge development to fill the checklist – ‘C’ duly verified & approved by P.E.
& QAD.
Checklist handover to HOD co-ordination dept.
Security Cabin :
Cutting , binding reinforcement, shuttering & casting for footings , stub columns, tie
beams, columns up to slab beam bottom, beam & slab.
Complete BBM of security cabin.
Internal plaster in gypsum & external double coat sand face.
Chemical w/p for slope roof slab.
Fixing of roof tiles.
Steel grey granite flooring size 12” x 12” & skirting of same granite, 5mm out side
from gypsum finish.
Butt finish.
Door & window frame in Krishna grey black granite.
Door & window shutters in anodized / powder coated aluminum with plain glass.
Internal & external painting as per project theme.
Carry out the furniture work in security cabin i.e. one table, key cabinet & shutters
for control panels of fountain street lights & gate lights.
Fixing of one tube light & one wall clock.
Fixing of the name board on security cabin i.e. security.
Take NOC by QAD Engineer.
In charge development to fill the checklist – ‘C’ duly verified & approved by P.E.
& QAD.
Checklist handover to HOD co-ordination dept.
Environment:-
During excavation sprinkle the water to reduce dust and prevent air pollution.
G.I. sheet as barricading to reduce noise level of machineries.
Quality:-
Equipment:-
Layout
working drawings
RCC drawings
Electrical drawings
Drainage & Plumbing Drawings
Working drawing for swimming pool from swimming pool consultant
Tools & plants
Machineries
.
Responsibility:-
HOD D&D
Site In charge
Swimming Pool Consultant
Q.A.D. Engineer
In charge Development
Surveyor
Work Instructions:-
HOD D&D to issue approved drawings i.e. layout, working, RCC & electrical
drawings.
Study of all drawings.
Line out of club house.
Take OGL.
Check the line out from D&D and take approval with NOC.
Excavation for club house footings.
PCC for footings & curing for all cement activities.
Cutting, binding, reinforcement, shuttering, casting for footings, stub columns, tie /
plinth beams, columns above plinth, beam & slabs. ( refer RCC instructions for
details )
Plinth back filling, watering, compaction, 9” thk. Soling.
Anti termite treatment for plinth.
4” thk. PCC.
Brick work ( refer work instructions of brick masonry for details ).
Internal plumbing in PPRC as per approved drawing.
Internal plaster in gypsum & external sand faced double coat plaster.
External plumbing & drainage as per approved drawing.
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/326/REV-0
Page : 2 of 2
QEHS WORK INSTRUCTIONS FOR CONSTRUCTION OF
TITLE :
CLUB HOUSE
Environment:-
During excavation sprinkle the water to reduce dust and prevent air pollution.
G.I. sheet as barricading to reduce noise level of machineries.
Quality:-
Equipment:-
Layout
working drawings
RCC drawings
Electrical drawings
Drainage & Plumbing Drawings
Working drawing for swimming pool from swimming pool consultant
Tools & plants
Machineries
.
Responsibility:-
HOD D&D
Site In charge
Swimming Pool Consultant
Q.A.D. Engineer
In charge Development
Surveyor
HOD D&D to
Study of
issue approved Line out Take OGL
all drawings
drawings
NOC from
Box type w/p PCC Excavation
D&D
lay electrical
conduit back filling in 9" thk. Soling,
pardi casting
in pardi for under deck area out side slope
water lights
fix icon brown screed type preparation for 4" thk. PCC,
granite coping w/p inside w/p out side slope
fix instructions,
fix fiber grating ladies & gents
fix under water fill the tank with
for over flow changing room
light fittings PMC water
gutter identification
boards
Commissioning
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/327/REV-0
Page : 3 of 3
QEHS WORK INSTRUCTIONS FOR CONSTRUCTION OF
TITLE :
SWIMMING POOL
Note : Balancing water tank & under ground filtration room – i) refer work
instructions of UGWT ( RCC & w/p ) ii) provide proper ventilation openings & fix
the m.s. ladder for under ground filtration room.
Environment:-
During excavation sprinkle the water to reduce dust and prevent air pollution.
G.I. sheet as barricading to reduce noise level of machineries.
Quality:-
Equipment:-
Responsibility:-
HOD D&D
Site In charge
Q.A.D. Engineer
In charge Development
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/328/REV-0
Page : 2 of 3
QEHS WORK INSTRUCTIONS FOR CONSTRUCTION OF
TITLE :
TRIMIX CONCRETE ROAD
Work Instructions:-
Study of drawings, existing drainage / electrical, water line etc.
Line out of road marking of the levels with respect to plinth level.
Excavation cutting & filling ( in case of BC soil remove up to 3’0” )
Sub grade preparation i.e. watering, rolling & compaction by 10 to 12 ton roller
(check proctor density test if required). The roller must roll minimum 30 times up
and down the subgrade stretch, so that the leveling and compaction is achieved.
Slope of road (i) In ‘L’ section, adjust as per the plinth F.F.L. i.e. drop (ramp) from
F.F.L. to road top should not be more than 1’ ii) Across the road 1:100 towards
gutter.
Construct storm water gutters size min. 1’ x 1’ along the road & slope according to
the ‘L’ section of the road.
9” thick. Soling or 4” thick compacted 2 metal layers in required line level & slope,
filling the gaps with kapchi .
Murum spreading above the soling dry rolling by 10 to 12 ton roller.
Fixing of the 5” channels in line level required slope & width 4.0 meter maximum.
Laying of the plastic sheet.
Pour of M 20 grade concrete, spreading, leveling & vibrating by surface vibrator.
Dewatering by vacuum pump till water stop dripping.
Check by foot impression.
Smooth finishing by floater & patra.
Brooming by wire brush across the vehicular movement.
Remove the channel on next day.
Curing by ponding method, minimum 14days.
Remove the pond mortar, cleaning, washing of the concrete road.
5 mm wide groove cutting by cutter machine with groove pattern
i) Centrally along the road should be done within two days of concreting being
done.
ii) 3 m c/c across the road.
Cleaning of groove by air pressure.
Filling of the groove with tikitar.
Fixing of the curb stone after & along the gutter.
Fixing of m.s. grating cover above storm water gutter.
Painting i) grating cover in bronze shade oil paint. ii) curb stone in sandtex shade
one yellow & one red brown with application of primer & birla putti .
Take NOC by QAD Engineer.
In charge development to fill the checklist – ‘C’ duly verified & approved by P.E.
& QAD.
Checklist handover to HOD co-ordination dept.
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/328/REV-0
Page : 3 of 3
QEHS WORK INSTRUCTIONS FOR CONSTRUCTION OF
TITLE :
TRIMIX CONCRETE ROAD
Environment:-
During excavation sprinkle the water to reduce dust and prevent air pollution.
G.I. sheet as barricading to reduce noise level of machineries.
Quality:-
Equipment:-
Megar
Tongue tester
Cramping tools
Spanner
Screw Driver
Tester
Plier
Hacksaw
Hammer
Wire cutting pliers
Knife
Tools & plants
Machineries
Responsibility:-
HOD Co-ordination Department
Site In charge
Q.A.D. Engineer
In charge Development
Work Instructions:-
HOD Co-ordination department to issue demarkation & layout drawings.
Study of drawings.
Lineout of D.G. plinth.
Excavation up to hard strata.
PCC
Height of the D.G. plinth 1’0” above road level.
UCR work at the periphery of the D.G. plinth.
Murum filling with watering & compaction in plinth area up to soling bottom.
9” thick rubble soling.
Casting of the slab with reinforcement 8 mm dia. @ 150mm c/c.
External plaster in sand faced double coat and top finishing with IPS finish with line
marking 12” x 12”, 5mm thick string.
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/329/REV-0
Page : 2 of 2
QEHS WORK INSTRUCTIONS FOR INSTALLATION OF
TITLE :
DIESEL GENERATOR
Sandtex bottle green shade painting on top of plinth and side as per the project
theme.
Curing for all cement activities.
Excavation for earthing 5’ x 5’ x 5’ = 4 nos near D.G. plinth
Do the earthing work using charcoal, salt, CI plate, GI strip & GI pipes, funnel at
top & GI pipe.
Installation of D.G. with sound proof canopy on D.G. plinth.
Fixing of AMF panel near D.G.
Cabling work i.e. alteration to AMF panel & sensor to AMF panel from M.S.E.D.
Co. Ltd.
Testing of the D.G. checking output i.e. rpm, frequency, voltage etc.
Laying of armoud cable as per drawing given by electrical consultant through
existing electrical conduits from D.G. auto change over panel to feeder pillar.
Laying armored cables from feeder pillar to individual building change over panel
through existing electrical conduit.
Connection from building auto change over panel to common meters & individual
flats. ( supply to light, fan & 5 amp point )
Fixing of board on D.G. plinth i.e. Diesel Generator.
Take NOC by QAD Engineer.
In charge development to fill the checklist – ‘C’ duly verified & approved by P.E.
& QAD.
Checklist handover to HOD co-ordination dept.
Environment:-
During excavation sprinkle the water to reduce dust and prevent air pollution.
G.I. sheet as barricading to reduce noise level of machineries.
Quality:-
Equipment:-
Megar
Tongue tester
Cramping tools
Spanner
Screw Driver
Tester
Plier
Hacksaw
Hammer
Wire cutting pliers
Knife
Tools & plants
Machineries
Responsibility:-
HOD D&D
Electrical Consultant
Licensed Electrical Contractor
Site In charge
Q.A.D. Engineer
In charge Development
Work Instructions:-
Take the necessary sanction through M.S.E.D. Co. Ltd. through licensed
electrical contractor.
HOD D&D to issue a layout approved and detail drawing prepared & verified by
electrical consultant.
Study of drawings.
Line out of the L.T. / transformer room.
Excavation for footings.
PCC for footings.
Centre line marking for footing column.
Shuttering, cutting, binding, reinforcement, casting footing, stub column, plinth
beam & slab.
9” thick BBM for cable trenches as per the layout.
Back filling up to soling bottom with watering & compaction.
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/330/REV-0
Page : 2 of 3
QEHS WORK INSTRUCTIONS FOR CONSTRUCTION OF
TITLE :
L.T. ROOM & INSTALLATION OF TRANSFORMER
9” thick soling murum spreading, watering, & compaction for the entire plinth..
PCC for plinth.
9” thick BBM above the plinth openings as per working drawing.
Internal gypsum finish plaster.
External double coat sand faced plaster.
Slab top finish with brickbat coba water proofing with line marking 12” x 12”, 5mm
thick string.
Cable trench cement ghotai plaster sides & bottom.
12” x 12” ceramic tile flooring.
Fixing m. s. grating on cable trench.
Internal OBD painting & external as per project theme.
Fixing of the rolling shutter size 9’0” x 10’0”, service door 5’0” x 8’0” two panel
m.s. folding door no. as per requirement.
Fixing of the anodized / powder coated aluminum window bottom half in aluminum
luvers & top half sliding shutters.
Installation of transformer – LT, HT cable panel.
Write the safety instructions on wall inside the room identification for cable &
transformer.
Fixing of rubberized tiles 2’0” x 2’0” on ceramic flooring.
Laying & connection of HT cable coming from M.S.E.D. Co. Ltd. HT pole to HT
feeder pillar near our project. HT feeder pillar to HT feeder pillar in transformer
room then feeder pillar to transformer.
Laying the LT cable coming from transformer to LT feeder pillar in transformer
room, then connects to feeder pillar near the bldg. Distribution of LT cable from
feeder pillar to individual bldg. bus bar in meter room.
Construction of inspection chamber in 9” thick B.B.M. every 50’0” length with
RCC chamber cover.
Fixing of name board i.e. LT / Transformer.
Take NOC by QAD Engineer.
In charge development to fill the checklist – ‘C’ duly verified & approved by P.E.
& QAD.
Checklist handover to HOD co-ordination dept.
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/330/REV-0
Page : 3 of 3
QEHS WORK INSTRUCTIONS FOR CONSTRUCTION OF
TITLE :
L.T. ROOM & INSTALLATION OF TRANSFORMER
Environment:-
During excavation sprinkle the water to reduce dust and prevent air pollution.
G.I. sheet as barricading to reduce noise level of machineries.
Quality:-
Equipment:-
Air blower
Dual media filter
Activated carbon filter
Feed pump
Air grid
Tool kit
Dosing tank 100 lit - 2 nos
Exhaust fan – 01 no.
Cleaning jar – 01 no.
Plastic bucket – 02 nos
Hypo chlorine & poly dosing powder
Tools & plants
Machineries
Responsibility:-
HOD D&D Co-ordination Department
Site In charge
Q.A.D. Engineer
In charge Development
Work Instructions:-
HOD Co-ordination issue approved layout drawings.
HOD D&D to issue RCC drawings.
Study of drawings.
Line out for bar screen chamber oil & grease chamber equalization tank fab1, fab2
tank tube shetler tank, chlorine contact tank, sludge digester tank & treated water
tank.
Excavation for all tanks.
PCC for all tanks.
Box type water proofing above the P.C.C.
Shuttering, cutting, binding reinforcement and casting of raft pardi and slab.
Box type W/P for the RCC pardi.
Internal w/p smooth cement ghotai patra finish.
External double coat sand faced plaster which are above the ground ( fab1, fab2
tube shetler chlorine contact tank).
Fixing of the m.s. chamber cover top of slab finish with smooth cement ghotai w/p.
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/331/REV-0
Page : 2 of 2
QEHS WORK INSTRUCTIONS FOR CONSTRUCTION AND
TITLE :
INSTALLATION OF SEWAGE TREATMENT PLANT
Flow chart :-
Inlet to bar screen chamber --- oil & grees chamber --- equalization tank --- fab
reactor --- tube shetler --- chlorine contact tank --- filter feed tank ( dual media filter
activated carbon filter ACF ) --- sludge digester--- treated water tank
Environment:-
During excavation sprinkle the water to reduce dust and prevent air pollution.
G.I. sheet as barricading to reduce noise level of machineries.
Quality:-
Equipment:-
Raw water Pump - 02 nos.
Dual Media filter (sand filter) – 01 no.
ACF ( Activated carbon filter) – 01no.
Softener – 01 no.
Brine solution tank – 01 no.
Chlorine dosing pump – 02 nos.
Chlorine dosing Tank – 01 no.
Pump power panel – 01 no.
Polishing carbon filter – 01 no.
Work manual
Tools & plants
Machineries
Responsibility:-
HOD Co-ordination
Site In charge
Q.A.D. Engineer
In charge Development
Work Instructions:-
HOD Co-ordination to issue approved working drawings.
Study of drawings.
Study of drawings.
Confirm clear height 4 mtr from FFL to bottom of slab & size as per approved
drawing.
Line out as per layout plan.
Excavation for column footing.
PCC.
Shuttering, Cutting , binding, reinforcement, stub column, plinth beam, slab casting.
9” brick masonry for plinth.
Back filling, soling & PCC for plinth.
9” soling for WTP Room.
Fixing of m. s. subframes for windows & door frames ( size 5’ x 8’ ).
Construction of gutter with ghotai plaster to run all pipe lines concealed in gutter.
Construction of 6” raised plat form size 2 mtr x 1 mtr for stacking salt bags.
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/332/REV-0
Page : 2 of 2
QEHS WORK INSTRUCTIONS FOR CONSTRUCTION AND
TITLE :
INSTALLATION OF WATER TREATMENT PLANT
Environment:-
During excavation sprinkle the water to reduce dust and prevent air pollution.
G.I. sheet as barricading to reduce noise level of machineries.
Quality:-
Equipment:-
1. Submersible Pump
2. Tools & plants
3. Machineries
Responsibility:-
HOD D&D
site In charge
Q.A.D. Engineer
In charge Development
Work Instructions:-
HOD D&D to issue approved layout working drawings, RCC Drawings.
Study & drawing preferable circular UGWT includes domestic PMC water, raw
water, fire water tank & underground pump room for fire pump ( rectangular in
shape).
Verify & confirm capacity of under ground fire water tank i.e. ( a ) 50000 ltrs. per
building & OHWT 20000 ltrs. Per building if building height above 21.0 mtr. ( b )
If building height less than 21 mtr, capacity of OHWT 10000 ltrs per building.
Line out.
Finalization of top of water tank 1’0” above road level.
Excavation up to required depth, considering, soling thickness if required.
PCC thickness, raft thickness into in depth & top slab thickness.
Excavation for the sump considering margin size for PCC raft & pardi.
Soling & PCC.
Box water proofing above PCC.
Shuttering, Cutting ,binding reinforcement casting raft slab pardi and top slab (
before casting of slab inlet outlet overflow sleeve to refixt )
Construct elevated manhole chambers in RCC pardi 3’ above tank FFL to avoid
contamination of STP water.
Fixing of light weight CI chamber covers for all manholes.
Box type waterproofing for outer periphery of the pardi cement ghotai water
proofing inside of the UGWT and top slab, outer periphery of the tank.
Fixing of the M.S ladder with painting in fire pump room
Installations of submersible water pump in tank fixating of control panel in WTP
room.
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/333/REV-0
Page : 2 of 2
QEHS WORK INSTRUCTIONS FOR CONSTRUCTION OF
TITLE :
UNDER GROUND WATER TANK
Environment:-
During excavation sprinkle the water to reduce dust and prevent air pollution.
G.I. sheet as barricading to reduce noise level of machineries.
Quality:-
Equipment:-
Ghamela
Phavada
Pixas
Hand roller
Grass cutter machine
Recreational equipment
Tools & Plants
Machineries
Responsibility:-
HOD D&D
Site In charge
Q.A.D. Engineer
In charge Development
Landscape Architect
Work Instructions:-
HOD D&D to issue approved landscaping drawing including layout details of soft
& hard landscaping, fountain, flower beds, RLS etc.
Line out & mark RLS of finish landscaping.
Laying of all conduits, waterline, construction of chambers, laying of fire fighting’s
pipe for court yard system, earthing, gutters, fixing of paving blocks, laying of all
cables for street light & decorative lights in garden.
Fixing of street light & decorative light pole with foundation.
Construction of all structures flowerbed in landscaping area & road side flooring
pattern, pathway.
Fixing of recreational equipment.
Laying of plumbing line for sprinkler & water supply to garden area.
Removing & cleaning of rabbit, cementasius materials etc.
Laying the one layer bricks hard & concrete area e.g. garden above podium slab.
Filling of garden soil 8” depth for lawn area & 1’0” depth for
Plantation area along with manure, vermi compost.
Placing the CI ready benches in lawn area, pavilions & where necessary.
Leveling, rolling, compaction, of lawn area.
Plantation of the lawn & plants.
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/334/REV-0
Page : 2 of 2
QEHS WORK INSTRUCTIONS FOR DEVELOPMENT OF
TITLE :
LANDSCAPED GARDEN
Environment:-
Before the start of site cleaning, sprinkle water to reduce dust & prevent air
pollution.
Quality:-
Equipment:-
Tools & Plants
Machineries
Responsibility:-
HOD Co-ordination Dept.
Site In charge
Q.A.D. Engineer
In charge Development
Vermiculture Consultant.
Work Instructions:-
HOD Co-ordination dept. to issue details vermiculture drawing.
Lineout for vermiculture plants ( 7 pits ).
9” soling 12” width below wall area only.
PCC 1:3:6 for wall ( soling area )
6” thick BBM 2’6” above the adjsent ground level.
External side double coat sand faced plaster from GL to top of wall & inside 6”
from top of wall.
Fixing of weld mesh fixed with angle frame covers on top of all 7 pits ( openable)
Painting of shutter angle frame & external painting as per the project theme.
No PCC soling in pit area, natural ground is required. Lay one large brick on natural
ground.
Provide 2 ½” GI water spout to scape excess rain water from the pit.
Fill of the pits 1’0” depth with garden waste.
Charging of Biosanitizer pit by spreading Biosanitizer.
Fix the name palate for each pit on external side of wall to identify days Sunday to
Saturday.
Fixing of the instruction & notice board back side of the wall.
Take NOC by QAD Engineer.
In charge development to fill the checklist – ‘C’ duly verified & approved by P.E.
& QAD.
Checklist handover to HOD co-ordination dept.
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/335/REV-0
Page : 2 of 2
QEHS WORK INSTRUCTIONS FOR CONSTRUCTION OF
TITLE :
VERMICULTURE (BIOSANITIZER PROJECT IIT-CO. PAVAI
TECHNOLOGY)
Environment:-
During excavation sprinkle the water to reduce dust and prevent air pollution.
G.I. sheet as barricading to reduce noise level of machineries.
Quality:-
Equipment:-
Tools & Plants
Machineries
Responsibility:-
HOD Co-ordination Dept.
Site In charge
Rain Water Harvesting Consultant
RCC Consultant
Q.A.D. Engineer
In charge Development
Work Instructions:-
HOD Co-ordination dept. to issue working details drawing as per rain water
harvesting consultant’s survey at site.
Line out rain water harvesting recharge pits / tanks in our premises at different
location as per the survey done by the rain water harvesting consultant.
Bore the 6” dia holes up to 50’ depth at the center of the each recharge pit area &
bore the 6”dia holes as a bore well find point’s shown in consultant’s drawing.
Purpose to utilize the bore well after recharge the ground.
Excavation for rain water harvesting pit’s.
PCC for brick wall only, natural ground is required.
9” BBM walls where recharge pit`s are in garden area & RCC pardi & top slab
designed for truck load.
Casting of the top slab as per consultant drawing.
Single coat sand faced plaster at periphery of the wall no internal plaster.
Do 5mm dia holes for 6” bore pipe as per preporation up to 1.0 mtr length from
recharge pit G.L.
Cover the top of pipe end cap.
Cover the PVC pipe with G.I. mesh size 5mm x 5mm
Filling the filter media 1” metal up to O.5 mtr depth.
Connect the rain water gutters each recharge pit as a rain water inlet.
Make a provision outlet from recharge pit to release excess water & connect to next
recharge pit.
Fixing the identification board near recharge pit i.e. Rain Water Harvesting.
Take NOC by QAD Engineer.
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/336/REV-0
Page : 2 of 2
QEHS WORK INSTRUCTIONS FOR CONSTRUCTION OF
TITLE :
RAIN WATER HARVESTING
In charge development to fill the checklist – ‘C’ duly verified & approved by P.E.
& QAD.
Checklist handover to HOD co-ordination dept.
Environment:-
During excavation sprinkle the water to reduce dust and prevent air pollution.
G.I. sheet as barricading to reduce noise level of machineries.
Quality:-
Equipment:-
Gas meter
M.S. pipe & Copper pipe
Valves
Tools & plants
Machineries
Responsibility:-
HOD Co-ordination
Site In charge
Q.A.D. Engineer
In charge Development
Work Instructions:-
Line out as per layout plan.
Excavation for column footing.
PCC.
Shuttering, Cutting , binding, reinforcement, stub column, plinth beam, slab casting.
9” brick masonry for plinth.
Back filling, watering, compaction, 9” thick soling & PCC for plinth.
Fixing of m. s. door frames ( size 5’ x 7’ ).
Fixing of 3mm dia. proporated sheet 16” height periphery of the gas bank at plinth
level & slab beam bottom
Internal double coat sand faced plaster.
External double coat sand faced plaster.
Slab top finish with brickbat coba w/p, line marking 12” x 12” with 5mm thick
string.
Fixing of 2” thick rough shahabad flooring.
Fixing of glass folding m.s. door shutter
Internal painting in white cement two coats & externally as per project theme , door
frame, shutter in white oil paint & proporated sheet in black oil paint.
Fixing of gas m. s. pipe network in gas bank up to building, running on parking
slab beam till kitchen duct up word vertical & connect to gas meter in dry balcony.
Copper piping from gas meter to kitchen otta granite skirting top.
Construction of inspection chamber with RCC covers at ground level.
Yellow color oil paint 6” dia. at the center of chamber cover & write Gas.
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/337/REV-0
Page : 2 of 2
QEHS WORK INSTRUCTIONS FOR CONSTRUCTION OF
TITLE :
GAS BANK
Environment:-
During excavation sprinkle the water to reduce dust and prevent air pollution.
G.I. sheet as barricading to reduce noise level of machineries.
1.0 ENVIRONMENT :
1) Use safety helmet, safety shoes, rubber hand gloves and safety belt at height.
2) Ensure that placing of concrete is done in proper sequence.
3) Always use good quality ladder.
4) Use of safety net, if an opening in the slab.
5) Keep the area clean from iron bars and wooden pieces.
6) Concrete mixer and lifting machine must be properly checked before
starting of work.
7) Check the stability of scaffold carrying pipe for pumping of concrete or lift
is strong enough to bear the load of the pipe filled with concrete, water.
Building worker working on the platform is stable and strong.
8) Ensure that the building workers are out of the range of any kickbacks or
bucket full of concrete.
9) Ensure that the concrete bucket used with hoists is free from projection from
which accumulation of concrete could fall from height.
10) Use of earplug by vibrator operator
.
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/339/REV-0
Page : 1 of 1
1.0 ENVIRONMENT :
1.0 ENVIRONMENT:
1.0 QUALITY
Not Applicable
2.0 ENVIRONMENT:
1.0 QUALITY
Not applicable
2.0 ENVIRONMENT :
11) Ensure there is place for everything and everything in its place.
12) Files, records, drawings are indexed, ensure fast retrieval.
13) Ensure files / papers / documents kept at their place.
14) Ensure the lights and fans are switched off when not in use.
15) Ensure air conditioners switched off when not occupied.
16) Ensure visual control displayed (posters, sign, graphs, symbols etc.)
17) Ensure employees have undergone training on health, hygiene,
safety, environment, and housekeeping.
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/343/REV-0
Page : 1 of 1
QEHS WORK INSTRUCTIONS FOR MONITORING AND
TITLE :
MEASURING OF NOISE, LIGHT & DUST
1. LIGHT:
a. If lighting on work place is below specified level, efforts shall be
made
to improve it and bring it to specified level.
b. Over illumination should be avoided.
c. All lights should be switched off at the end of the work.
d. Use maximum of low watt appliances / lighting source ( eg:- meta
halide lamps, CFL, Solar lamps eco friendly electrical products)
2. NOISE:
Measure noise after every 6 months for all machines and D.G.Sets, if noise
level is above 75 decibels at point of operations, efforts shall be made to
reduce it and the report is submitted to Management Representative.
3. DUST: (SPM)
It will be checked after every 6 months by outside party, record shall be
maintained, if dust levels are above specified level efforts shall be made to
bring it to specified limits. dust level shall be checked at site.
5. RECORDS:
Air, SPM, Noise monitoring reports maintained by site in – charge.
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/344/REV-0
Page : 1 of 1
QEHS WORK INSTRUCTIONS FOR CONTROL AND
TITLE :
MONITORING OF WASTE GENERATED IN
CONSTRUCTION
1.0 ENVIRONMENT:
1) Scrap such as steel, broken tiles, wooden cut ends and plastics shall
be collected everyday and kept in designated area for reuse /
disposal.
2) Sale / disposal of scrap to be done to recyclers through scrap
vendors.
3) Scrap shall be sorted out and kept in separate bins.
REF : QEHS/345/REV-0
Page : 1 of 1
1.0 ENVIRONMENT
2. Preventive maintenance schedules are strictly adhered to ensure that all plant and
machinery are systematically inspected, serviced, repaired and maintained as
necessary. Brakes are checked regularly.
3. Non-essential personnel are kept well away from the area of operation and trained
signal man are provided wherever necessary.
6. Moving vehicles are fitted with proper rear view mirror and reversing alarms.
Vehicles are not moved in reverse without directions from cleaner.
7. Employees and workmen working in the vicinity of earth moving operations are
working with safety helmets, shoes, eye-glasses, if required.
8. Sleeping / resting under or rear side of vehicle like Tippers, Hyvas, Hydra,
Tractors, etc. are strictly prohibited. This is checked by watchman appointed at
various locations. No unauthorized person is allowed to enter in driver’s cabin.
9. Vehicles are not parked on a slope for push starting, if battery is weak. All vehicles
are having self-starter.
10. No workman other than operator is allowed to sit / ride on stationery or moving
tower crane, mobile crane etc. No. passengers are allowed in operator’s cabin.
11. Walky talky is provided, if required for better communication between crane
operator and lifting gang.
13. Operating any machine beyond its design limits can damage the machine & it can
cause very serious accidents. Any machine is not overloaded.
14. The engine of any machine has exposed rotating parts. Engine cover is not opened
while the engine is running. All other guards & protective devices are in place
while operating any machine.
15. While using excavator, because of long boom & dipper arm, one must be very
careful when slewing. Operator should not slew quickly and strike the dipper arm
against any obstacle.
16. Loose clothing is not used by operator as it can catch in moving parts of machine
and cause serious accidents.
17. While lifting the load by crane, nobody should work / stand in the crane coverage
area.
18. Ensure the use of air plug while working in noisy area to avoid deafness / irritation
to individuals.
REF : QEHS/347/REV-0
Page : 1 of 2
1.0 ENVIRONMENT:
1.1 Do not allow leakage/spillage of oil & Grease used.
1.2 Do not throw oil / grease rags in open area, use bins.
1.3 Lifting of material plan should be made to ensure effective usage of
electrical energy for operation; switch off when not in use.
REF : QEHS/347/REV-0
Page : 2 of 2
REF : QEHS/348/REV-0
Page : 1 of 1
1) Suitable footwear, safety helmets and necessary PPEs are used by personnel during
loading, unloading and handling of material.
2) Vehicles are not overloaded by any materials.
3) Proper approaches for vehicle movements are ensured around the site. Approach
roads are fairly leveled and compacted to avoid skidding of vehicles.
4) Proper capacity wire rope is used while handling the material with cranes.
5) Valid test certificates of wire rope sling, chain pulley block, wire ropes, pulley, etc.
are maintained.
6) Hand gloves are worn by workers while handling / shifting steel.
7) Suitable equipment is used to lift the steelwork.
REF : QEHS/349/REV-0
Page : 1 of 1
1.0 ENVIRONMENT:
Quality:-
Equipment:-
Megar
Tongue tester
Cramping tools
Spanner
Screw Driver
Tester
Plier
Hacksaw
Hammer
Wire cutting pliers
Knife
Tools & plants
Machineries
Responsibility:-
HOD D&D
Electrical Consultant
Licensed Electrical Contractor
Site In charge
Q.A.D. Engineer
In charge Development
Work Instructions:-
Take the necessary sanction through M.S.E.D. Co. Ltd. through licensed
electrical contractor.
HOD D&D to issue a layout approved and detail drawing prepared & verified by
electrical consultant.
Study of drawings.
Line out of the L.T. / transformer room.
Excavation for footings.
PCC for footings.
Centre line marking for footing column.
Shuttering, cutting, binding, reinforcement, casting footing, stub column, plinth
beam & slab.
9” thick BBM for cable trenches as per the layout.
Back filling up to soling bottom with watering & compaction.
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/330/REV-0
Page : 2 of 3
QEHS WORK INSTRUCTIONS FOR CONSTRUCTION OF
TITLE :
L.T. ROOM & INSTALLATION OF TRANSFORMER
9” thick soling murum spreading, watering, & compaction for the entire plinth..
PCC for plinth.
9” thick BBM above the plinth openings as per working drawing.
Internal gypsum finish plaster.
External double coat sand faced plaster.
Slab top finish with brickbat coba water proofing with line marking 12” x 12”, 5mm
thick string.
Cable trench cement ghotai plaster sides & bottom.
12” x 12” ceramic tile flooring.
Fixing m. s. grating on cable trench.
Internal OBD painting & external as per project theme.
Fixing of the rolling shutter size 9’0” x 10’0”, service door 5’0” x 8’0” two panel
m.s. folding door no. as per requirement.
Fixing of the anodized / powder coated aluminum window bottom half in aluminum
luvers & top half sliding shutters.
Installation of transformer – LT, HT cable panel.
Write the safety instructions on wall inside the room identification for cable &
transformer.
Fixing of rubberized tiles 2’0” x 2’0” on ceramic flooring.
Laying & connection of HT cable coming from M.S.E.D. Co. Ltd. HT pole to HT
feeder pillar near our project. HT feeder pillar to HT feeder pillar in transformer
room then feeder pillar to transformer.
Laying the LT cable coming from transformer to LT feeder pillar in transformer
room, then connects to feeder pillar near the bldg. Distribution of LT cable from
feeder pillar to individual bldg. bus bar in meter room.
Construction of inspection chamber in 9” thick B.B.M. every 50’0” length with
RCC chamber cover.
Fixing of name board i.e. LT / Transformer.
Take NOC by QAD Engineer.
In charge development to fill the checklist – ‘C’ duly verified & approved by P.E.
& QAD.
Checklist handover to HOD co-ordination dept.
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/330/REV-0
Page : 3 of 3
QEHS WORK INSTRUCTIONS FOR CONSTRUCTION OF
TITLE :
L.T. ROOM & INSTALLATION OF TRANSFORMER
Environment:-
During excavation sprinkle the water to reduce dust and prevent air pollution.
G.I. sheet as barricading to reduce noise level of machineries.
Quality:-
Equipment:-
Air blower
Dual media filter
Activated carbon filter
Feed pump
Air grid
Tool kit
Dosing tank 100 lit - 2 nos
Exhaust fan – 01 no.
Cleaning jar – 01 no.
Plastic bucket – 02 nos
Hypo chlorine & poly dosing powder
Tools & plants
Machineries
Responsibility:-
HOD D&D Co-ordination Department
Site In charge
Q.A.D. Engineer
In charge Development
Work Instructions:-
HOD Co-ordination issue approved layout drawings.
HOD D&D to issue RCC drawings.
Study of drawings.
Line out for bar screen chamber oil & grease chamber equalization tank fab1, fab2
tank tube shetler tank, chlorine contact tank, sludge digester tank & treated water
tank.
Excavation for all tanks.
PCC for all tanks.
Box type water proofing above the P.C.C.
Shuttering, cutting, binding reinforcement and casting of raft pardi and slab.
Box type W/P for the RCC pardi.
Internal w/p smooth cement ghotai patra finish.
External double coat sand faced plaster which are above the ground ( fab1, fab2
tube shetler chlorine contact tank).
Fixing of the m.s. chamber cover top of slab finish with smooth cement ghotai w/p.
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/331/REV-0
Page : 2 of 2
QEHS WORK INSTRUCTIONS FOR CONSTRUCTION AND
TITLE :
INSTALLATION OF SEWAGE TREATMENT PLANT
Flow chart :-
Inlet to bar screen chamber --- oil & grees chamber --- equalization tank --- fab
reactor --- tube shetler --- chlorine contact tank --- filter feed tank ( dual media filter
activated carbon filter ACF ) --- sludge digester--- treated water tank
Environment:-
During excavation sprinkle the water to reduce dust and prevent air pollution.
G.I. sheet as barricading to reduce noise level of machineries.
Quality:-
Equipment:-
Raw water Pump - 02 nos.
Dual Media filter (sand filter) – 01 no.
ACF ( Activated carbon filter) – 01no.
Softener – 01 no.
Brine solution tank – 01 no.
Chlorine dosing pump – 02 nos.
Chlorine dosing Tank – 01 no.
Pump power panel – 01 no.
Polishing carbon filter – 01 no.
Work manual
Tools & plants
Machineries
Responsibility:-
HOD Co-ordination
Site In charge
Q.A.D. Engineer
In charge Development
Work Instructions:-
HOD Co-ordination to issue approved working drawings.
Study of drawings.
Study of drawings.
Confirm clear height 4 mtr from FFL to bottom of slab & size as per approved
drawing.
Line out as per layout plan.
Excavation for column footing.
PCC.
Shuttering, Cutting , binding, reinforcement, stub column, plinth beam, slab casting.
9” brick masonry for plinth.
Back filling, soling & PCC for plinth.
9” soling for WTP Room.
Fixing of m. s. subframes for windows & door frames ( size 5’ x 8’ ).
Construction of gutter with ghotai plaster to run all pipe lines concealed in gutter.
Construction of 6” raised plat form size 2 mtr x 1 mtr for stacking salt bags.
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/332/REV-0
Page : 2 of 2
QEHS WORK INSTRUCTIONS FOR CONSTRUCTION AND
TITLE :
INSTALLATION OF WATER TREATMENT PLANT
Environment:-
During excavation sprinkle the water to reduce dust and prevent air pollution.
G.I. sheet as barricading to reduce noise level of machineries.
Quality:-
Equipment:-
1. Submersible Pump
2. Tools & plants
3. Machineries
Responsibility:-
HOD D&D
site In charge
Q.A.D. Engineer
In charge Development
Work Instructions:-
HOD D&D to issue approved layout working drawings, RCC Drawings.
Study & drawing preferable circular UGWT includes domestic PMC water, raw
water, fire water tank & underground pump room for fire pump ( rectangular in
shape).
Verify & confirm capacity of under ground fire water tank i.e. ( a ) 50000 ltrs. per
building & OHWT 20000 ltrs. Per building if building height above 21.0 mtr. ( b )
If building height less than 21 mtr, capacity of OHWT 10000 ltrs per building.
Line out.
Finalization of top of water tank 1’0” above road level.
Excavation up to required depth, considering, soling thickness if required.
PCC thickness, raft thickness into in depth & top slab thickness.
Excavation for the sump considering margin size for PCC raft & pardi.
Soling & PCC.
Box water proofing above PCC.
Shuttering, Cutting ,binding reinforcement casting raft slab pardi and top slab (
before casting of slab inlet outlet overflow sleeve to refixt )
Construct elevated manhole chambers in RCC pardi 3’ above tank FFL to avoid
contamination of STP water.
Fixing of light weight CI chamber covers for all manholes.
Box type waterproofing for outer periphery of the pardi cement ghotai water
proofing inside of the UGWT and top slab, outer periphery of the tank.
Fixing of the M.S ladder with painting in fire pump room
Installations of submersible water pump in tank fixating of control panel in WTP
room.
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/333/REV-0
Page : 2 of 2
QEHS WORK INSTRUCTIONS FOR CONSTRUCTION OF
TITLE :
UNDER GROUND WATER TANK
Environment:-
During excavation sprinkle the water to reduce dust and prevent air pollution.
G.I. sheet as barricading to reduce noise level of machineries.
Quality:-
Equipment:-
Ghamela
Phavada
Pixas
Hand roller
Grass cutter machine
Recreational equipment
Tools & Plants
Machineries
Responsibility:-
HOD D&D
Site In charge
Q.A.D. Engineer
In charge Development
Landscape Architect
Work Instructions:-
HOD D&D to issue approved landscaping drawing including layout details of soft
& hard landscaping, fountain, flower beds, RLS etc.
Line out & mark RLS of finish landscaping.
Laying of all conduits, waterline, construction of chambers, laying of fire fighting’s
pipe for court yard system, earthing, gutters, fixing of paving blocks, laying of all
cables for street light & decorative lights in garden.
Fixing of street light & decorative light pole with foundation.
Construction of all structures flowerbed in landscaping area & road side flooring
pattern, pathway.
Fixing of recreational equipment.
Laying of plumbing line for sprinkler & water supply to garden area.
Removing & cleaning of rabbit, cementasius materials etc.
Laying the one layer bricks hard & concrete area e.g. garden above podium slab.
Filling of garden soil 8” depth for lawn area & 1’0” depth for
Plantation area along with manure, vermi compost.
Placing the CI ready benches in lawn area, pavilions & where necessary.
Leveling, rolling, compaction, of lawn area.
Plantation of the lawn & plants.
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/334/REV-0
Page : 2 of 2
QEHS WORK INSTRUCTIONS FOR DEVELOPMENT OF
TITLE :
LANDSCAPED GARDEN
Environment:-
Before the start of site cleaning, sprinkle water to reduce dust & prevent air
pollution.
Quality:-
Equipment:-
Tools & Plants
Machineries
Responsibility:-
HOD Co-ordination Dept.
Site In charge
Q.A.D. Engineer
In charge Development
Vermiculture Consultant.
Work Instructions:-
HOD Co-ordination dept. to issue details vermiculture drawing.
Lineout for vermiculture plants ( 7 pits ).
9” soling 12” width below wall area only.
PCC 1:3:6 for wall ( soling area )
6” thick BBM 2’6” above the adjsent ground level.
External side double coat sand faced plaster from GL to top of wall & inside 6”
from top of wall.
Fixing of weld mesh fixed with angle frame covers on top of all 7 pits ( openable)
Painting of shutter angle frame & external painting as per the project theme.
No PCC soling in pit area, natural ground is required. Lay one large brick on natural
ground.
Provide 2 ½” GI water spout to scape excess rain water from the pit.
Fill of the pits 1’0” depth with garden waste.
Charging of Biosanitizer pit by spreading Biosanitizer.
Fix the name palate for each pit on external side of wall to identify days Sunday to
Saturday.
Fixing of the instruction & notice board back side of the wall.
Take NOC by QAD Engineer.
In charge development to fill the checklist – ‘C’ duly verified & approved by P.E.
& QAD.
Checklist handover to HOD co-ordination dept.
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/335/REV-0
Page : 2 of 2
QEHS WORK INSTRUCTIONS FOR CONSTRUCTION OF
TITLE :
VERMICULTURE (BIOSANITIZER PROJECT IIT-CO. PAVAI
TECHNOLOGY)
Environment:-
During excavation sprinkle the water to reduce dust and prevent air pollution.
G.I. sheet as barricading to reduce noise level of machineries.
Quality:-
Equipment:-
Tools & Plants
Machineries
Responsibility:-
HOD Co-ordination Dept.
Site In charge
Rain Water Harvesting Consultant
RCC Consultant
Q.A.D. Engineer
In charge Development
Work Instructions:-
HOD Co-ordination dept. to issue working details drawing as per rain water
harvesting consultant’s survey at site.
Line out rain water harvesting recharge pits / tanks in our premises at different
location as per the survey done by the rain water harvesting consultant.
Bore the 6” dia holes up to 50’ depth at the center of the each recharge pit area &
bore the 6”dia holes as a bore well find point’s shown in consultant’s drawing.
Purpose to utilize the bore well after recharge the ground.
Excavation for rain water harvesting pit’s.
PCC for brick wall only, natural ground is required.
9” BBM walls where recharge pit`s are in garden area & RCC pardi & top slab
designed for truck load.
Casting of the top slab as per consultant drawing.
Single coat sand faced plaster at periphery of the wall no internal plaster.
Do 5mm dia holes for 6” bore pipe as per preporation up to 1.0 mtr length from
recharge pit G.L.
Cover the top of pipe end cap.
Cover the PVC pipe with G.I. mesh size 5mm x 5mm
Filling the filter media 1” metal up to O.5 mtr depth.
Connect the rain water gutters each recharge pit as a rain water inlet.
Make a provision outlet from recharge pit to release excess water & connect to next
recharge pit.
Fixing the identification board near recharge pit i.e. Rain Water Harvesting.
Take NOC by QAD Engineer.
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/336/REV-0
Page : 2 of 2
QEHS WORK INSTRUCTIONS FOR CONSTRUCTION OF
TITLE :
RAIN WATER HARVESTING
In charge development to fill the checklist – ‘C’ duly verified & approved by P.E.
& QAD.
Checklist handover to HOD co-ordination dept.
Environment:-
During excavation sprinkle the water to reduce dust and prevent air pollution.
G.I. sheet as barricading to reduce noise level of machineries.
Quality:-
Equipment:-
Gas meter
M.S. pipe & Copper pipe
Valves
Tools & plants
Machineries
Responsibility:-
HOD Co-ordination
Site In charge
Q.A.D. Engineer
In charge Development
Work Instructions:-
Line out as per layout plan.
Excavation for column footing.
PCC.
Shuttering, Cutting , binding, reinforcement, stub column, plinth beam, slab casting.
9” brick masonry for plinth.
Back filling, watering, compaction, 9” thick soling & PCC for plinth.
Fixing of m. s. door frames ( size 5’ x 7’ ).
Fixing of 3mm dia. proporated sheet 16” height periphery of the gas bank at plinth
level & slab beam bottom
Internal double coat sand faced plaster.
External double coat sand faced plaster.
Slab top finish with brickbat coba w/p, line marking 12” x 12” with 5mm thick
string.
Fixing of 2” thick rough shahabad flooring.
Fixing of glass folding m.s. door shutter
Internal painting in white cement two coats & externally as per project theme , door
frame, shutter in white oil paint & proporated sheet in black oil paint.
Fixing of gas m. s. pipe network in gas bank up to building, running on parking
slab beam till kitchen duct up word vertical & connect to gas meter in dry balcony.
Copper piping from gas meter to kitchen otta granite skirting top.
Construction of inspection chamber with RCC covers at ground level.
Yellow color oil paint 6” dia. at the center of chamber cover & write Gas.
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/337/REV-0
Page : 2 of 2
QEHS WORK INSTRUCTIONS FOR CONSTRUCTION OF
TITLE :
GAS BANK
Environment:-
During excavation sprinkle the water to reduce dust and prevent air pollution.
G.I. sheet as barricading to reduce noise level of machineries.
1.0 ENVIRONMENT :
1) Use safety helmet, safety shoes, rubber hand gloves and safety belt at height.
2) Ensure that placing of concrete is done in proper sequence.
3) Always use good quality ladder.
4) Use of safety net, if an opening in the slab.
5) Keep the area clean from iron bars and wooden pieces.
6) Concrete mixer and lifting machine must be properly checked before
starting of work.
7) Check the stability of scaffold carrying pipe for pumping of concrete or lift
is strong enough to bear the load of the pipe filled with concrete, water.
Building worker working on the platform is stable and strong.
8) Ensure that the building workers are out of the range of any kickbacks or
bucket full of concrete.
9) Ensure that the concrete bucket used with hoists is free from projection from
which accumulation of concrete could fall from height.
10) Use of earplug by vibrator operator
.
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/339/REV-0
Page : 1 of 1
1.0 ENVIRONMENT :
1.0 ENVIRONMENT:
1.0 QUALITY
Not Applicable
2.0 ENVIRONMENT:
1.0 QUALITY
Not applicable
2.0 ENVIRONMENT :
11) Ensure there is place for everything and everything in its place.
12) Files, records, drawings are indexed, ensure fast retrieval.
13) Ensure files / papers / documents kept at their place.
14) Ensure the lights and fans are switched off when not in use.
15) Ensure air conditioners switched off when not occupied.
16) Ensure visual control displayed (posters, sign, graphs, symbols etc.)
17) Ensure employees have undergone training on health, hygiene,
safety, environment, and housekeeping.
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/343/REV-0
Page : 1 of 1
QEHS WORK INSTRUCTIONS FOR MONITORING AND
TITLE :
MEASURING OF NOISE, LIGHT & DUST
1. LIGHT:
a. If lighting on work place is below specified level, efforts shall be
made
to improve it and bring it to specified level.
b. Over illumination should be avoided.
c. All lights should be switched off at the end of the work.
d. Use maximum of low watt appliances / lighting source ( eg:- meta
halide lamps, CFL, Solar lamps eco friendly electrical products)
2. NOISE:
Measure noise after every 6 months for all machines and D.G.Sets, if noise
level is above 75 decibels at point of operations, efforts shall be made to
reduce it and the report is submitted to Management Representative.
3. DUST: (SPM)
It will be checked after every 6 months by outside party, record shall be
maintained, if dust levels are above specified level efforts shall be made to
bring it to specified limits. dust level shall be checked at site.
5. RECORDS:
Air, SPM, Noise monitoring reports maintained by site in – charge.
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/344/REV-0
Page : 1 of 1
QEHS WORK INSTRUCTIONS FOR CONTROL AND
TITLE :
MONITORING OF WASTE GENERATED IN
CONSTRUCTION
1.0 ENVIRONMENT:
1) Scrap such as steel, broken tiles, wooden cut ends and plastics shall
be collected everyday and kept in designated area for reuse /
disposal.
2) Sale / disposal of scrap to be done to recyclers through scrap
vendors.
3) Scrap shall be sorted out and kept in separate bins.
REF : QEHS/345/REV-0
Page : 1 of 1
1.0 ENVIRONMENT
2. Preventive maintenance schedules are strictly adhered to ensure that all plant and
machinery are systematically inspected, serviced, repaired and maintained as
necessary. Brakes are checked regularly.
3. Non-essential personnel are kept well away from the area of operation and trained
signal man are provided wherever necessary.
6. Moving vehicles are fitted with proper rear view mirror and reversing alarms.
Vehicles are not moved in reverse without directions from cleaner.
7. Employees and workmen working in the vicinity of earth moving operations are
working with safety helmets, shoes, eye-glasses, if required.
8. Sleeping / resting under or rear side of vehicle like Tippers, Hyvas, Hydra,
Tractors, etc. are strictly prohibited. This is checked by watchman appointed at
various locations. No unauthorized person is allowed to enter in driver’s cabin.
9. Vehicles are not parked on a slope for push starting, if battery is weak. All vehicles
are having self-starter.
10. No workman other than operator is allowed to sit / ride on stationery or moving
tower crane, mobile crane etc. No. passengers are allowed in operator’s cabin.
11. Walky talky is provided, if required for better communication between crane
operator and lifting gang.
13. Operating any machine beyond its design limits can damage the machine & it can
cause very serious accidents. Any machine is not overloaded.
14. The engine of any machine has exposed rotating parts. Engine cover is not opened
while the engine is running. All other guards & protective devices are in place
while operating any machine.
15. While using excavator, because of long boom & dipper arm, one must be very
careful when slewing. Operator should not slew quickly and strike the dipper arm
against any obstacle.
16. Loose clothing is not used by operator as it can catch in moving parts of machine
and cause serious accidents.
17. While lifting the load by crane, nobody should work / stand in the crane coverage
area.
18. Ensure the use of air plug while working in noisy area to avoid deafness / irritation
to individuals.
REF : QEHS/347/REV-0
Page : 1 of 2
1.0 ENVIRONMENT:
1.1 Do not allow leakage/spillage of oil & Grease used.
1.2 Do not throw oil / grease rags in open area, use bins.
1.3 Lifting of material plan should be made to ensure effective usage of
electrical energy for operation; switch off when not in use.
REF : QEHS/347/REV-0
Page : 2 of 2
REF : QEHS/348/REV-0
Page : 1 of 1
1) Suitable footwear, safety helmets and necessary PPEs are used by personnel during
loading, unloading and handling of material.
2) Vehicles are not overloaded by any materials.
3) Proper approaches for vehicle movements are ensured around the site. Approach
roads are fairly leveled and compacted to avoid skidding of vehicles.
4) Proper capacity wire rope is used while handling the material with cranes.
5) Valid test certificates of wire rope sling, chain pulley block, wire ropes, pulley, etc.
are maintained.
6) Hand gloves are worn by workers while handling / shifting steel.
7) Suitable equipment is used to lift the steelwork.
REF : QEHS/349/REV-0
Page : 1 of 1
1.0 ENVIRONMENT:
REF : QEHS/350/REV-0
Page : 1 of 1
1.0 Environment
1.1 Ensure there is no dust or smoke generation during the night work.
1.2 Prevent noise generated caused by machines and hammering by
barricading the area.
REF : QEHS/351/REV-0
Page : 1 of 1
1.0 ENVIRONNMENT
A. QUALITY
1. SCOPE:-
Applicable for production of Cellular Light Weight Concrete Blocks
2. EQUIPMENTS
1) Mixer Plant of 1.3 C.M. Capacity/batch.
2) Trolley to carry the mix & trolley for carriage of blocks.
3) The foam generator
4) Hopper and Belt/ Screw conveyer for Pond Ash & Cement respectively
5) Curing Bay
6) Production Bay to have moulds for CLC Bricks
7) Under Ground Water Tank capacity - 10,000 Ltrs.
8) Cement Go-down capacity - 1200 bags.
3. RESPONSIBILITY
Plant Incharge
4. WORK INSTRUCTIONS
I) INPUTS :-
Following are considered as inputs to this procedure.
1) C L C Blocks requirement received from site
2) Raw material received from supplier
3) Mix design as given below
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/352/REV-0
Page : 2 of 5
1) PROCESS / OPERATION :-
PLANNING :-
ACTIVITIES / OPERATION
1) As per Design Mix the data is loaded on the Design Pannel by the Plant
Operator.
2) Each time the Mixer is filled up its of 1.3 cum of Mix, which takes
around half an hour to make.
3) The flow chart for the production of Cellular Light Weight Block
RECONCILLATION:-
1) The consumption of material will be as per the mix design given below:
a) Cement 53 grade - 250 bags
b) Pond Ash - 500 Kgs
c) Calcium Chloride - 5 Kgs
d) Foam - 140 seconds pour
e) Water - 220 ltrs.
2) The density of the mix should be 840 Kg/m3 to 860 Kgs/m3
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/352/REV-0
Page : 4 of 5
3) The details of production will be recorded and the said record will be
maintained for every day production as per the format attached.
4) The empty bags of Cement are counted & checked with the consumption
report.
MATERIAL STACKING:-
1) Cement:-
Cement is unloaded at cement godown at site/ CLC Plant / Silo / Store.
2) Foaming Agent
Foaming agent is kept in a drum connected to the foam generator.
3) Pond ash:-
To be stacked in the covered stacking yard.
4) Do not use water pipe having any leakage / damage & prevent west of
water.
A) QUALITY
1.0) SCOPE
2.0) EQUIPMENTS
a) Measuring Tape
b) Level Tube
c) Ghodi for Standing
d) Hammer, Drill Machine
e) Line Dori
f) Colour Blue/Red
g) Screw Drivers star & flat both
h) Cutting Tools
3.0) RESPONSIBILITY
a) Site Incharge
b) Building Incharge
c) Q.A. Representative
xii) Fix POP/Gypsum sheet by drilling holes at nine locations per sheet with nettle
fold full threaded screw 25 X 8’
xiii) Do not finishing of sheet joints and screw location point to make it look
uniform finish.
xiv) Record details in M & M in process activities register (QAD/702) duly signed
by QA/SI
ENVIRONMENT
i) Cut the POP bags by removing stitches, do not spill the POP
ii) Stack the POP sheets in such a way that they don’t get damaged, and all
the sheets can be u sed.
iii) The screw, MS Sheets/Suspender wastage is removed from the site and
stacked as scrap/ taken away by the contractor.
iv) Do not allow the POP sheets getting mixed up with water. Only the POP
powder is mixed after the fixing of sheets and the POP paste is used with
care to finish the joint, if any.
I) Use Safety Helmet, rubber hand gloves, Safety Belt if working at heights
II) Ensure that the POP sheets and the grid of boxing is made in advance and
fixed in situ.
III) Used good quality Ghodi for working which has a balanced base.
IV) Keep area clean of nails & screw and metal pieces.
V) Use goggles and ear plugs while drilling.
VI) Insulate all electrical wire joints with insulation tape and use two pin/three
top pin for electrical sockets.
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/354/REV-0
Page : 1 of 4
QEHS WORK INSTRUCTIONS FOR CONSTRUCTION OF
TITLE :
RAMP IN STILT PARKING
A) QUALITY
1.0 SCOPE:-
2.0 EQUIPMENT:-
3.0 RESPONSIBILITY:-
1) HOD D&D
2) Site In charge.
3) QAD Engineer.
4) Development In charge.
2) The Plinth level of Building is known, line out the Road Marking
levels with respect to plinth levels.
4) Keep the slope of road 1:100 transversely toward the gutter and
longitudinally adjust the slope as per plinth FFL so that everywhere
Tremix road is maximum 3.5” below top of plinth beam level and
minimum levels of finish Tremix road & top of plinth beam should
equal.
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/354/REV-0
Page : 2 of 4
QEHS WORK INSTRUCTIONS FOR CONSTRUCTION OF
TITLE :
RAMP IN STILT PARKING
8) 3” P.C.C. done over compacted surface for parking, Keep plinth beam
top and P.C.C top level same.
10) Provide 3” PCC for Ramp, keep P.C.C top 2.5” below Tremix road
top level at roadside and same as plinth beam top at parking side.
11) For the Podium at the starting of the Building. Level of Top of
Podium slab should below the stilt floor slab by maximum 6” for
ramp of 1:6 gradient(Consider 3”trimix over podium slab) and give
the slope to stilt slab same as slope of podium slab. Accordingly cast
the Podium slab & Stilt slab of building. Also check the unsupported
height of column which should be within the specified limit.
12) Provide 3” P.C.C for ramp keeping top 2.5” below Tremix top level at
road side and same as stilt slab top level at building parking side.
13) Fix the granite or kadappa patti 7” width at the entry of parking.
14) Level marking on Entry column and wall keeping slope of 1:10
towards granite patti from other end. Fix the chequered tile in mortar
bed of proportion 1:10. (Take 50% Crush sand and 50% River sand
chal )
16) Fill the 10mm joint between two granite pieces by cement, finish the
joint 2mm below the granite top surface & curing done for 3 days.
NYATI BUILDERS PVT. LTD. &
NYATI ENGINEERS & CONSULTANTS
REF : QEHS/354/REV-0
Page : 4 of 4
QEHS WORK INSTRUCTIONS FOR CONSTRUCTION OF
TITLE :
RAMP IN STILT PARKING
B) ENVIRONMENT:-
3) Collect all broken tiles or bags and use them where cut piece is
required.
1) Use safety Helmet, Ear plug, Shoes, Rubber Hand Gloves, Mask,
Goggles and Safety Belt.
30 QEHS / 330 Environment and safety work instruction for LT Room 0 30-04-17 3
31 QEHS / 331 Environment and safety work instruction for Sewage 0 30-04-17 2
Treatment Plant
32 QEHS / 332 Environment and safety work instruction for Water 0 30-04-17 2
Treatment Plant
33 QEHS / 333 Environment and safety work instruction for Under 0 30-04-17 2
Ground Water Tank
34 QEHS / 334 Environment and safety work instruction for Landscape 0 30-04-17 2
Garden
35 QEHS / 335 Environment and safety work instruction for 0 30-04-17 2
Vermiculture (Bio-sanitizer)
36 QEHS / 336 Environment and safety work instruction for Rainwater 0 30-04-17 2
Harvesting
37 QEHS / 337 Environment and safety work instruction for Gas Bank 0 30-04-17 2
38 QEHS / 338 Environment and safety work instruction for Pumping 0 30-04-17 1
for Concreting
39 QEHS / 339 Environment and safety work instruction for Scaffolding 0 30-04-17 1
40 QEHS / 340 Environment and safety work instruction for Cleaning of 0 30-04-17 1
Underground and Overhead Water Tank
41 QEHS / 341 Environment and safety work instruction for Using 0 30-04-17 1
Ladder as per Design
42 QEHS / 342 Environment and safety work instruction for 0 30-04-17 2
Housekeeping
43 QEHS / 343 Environment and safety work instruction for Monitoring 0 30-04-17 1
and Measuring of Noise, Light and Dust
44 QEHS / 344 Environment and safety work instruction for Monitoring 0 30-04-17 1
of Waste Generated in Construction
45 QEHS / 345 Environment and safety work instruction for Piling and 0 30-04-17 1
Construction of Manhole and RCC Pipes
46 QEHS / 346 Environment and safety work instruction for use of 0 30-04-17 2
Construction Equipment at Site
47 QEHS / 347 Environment and Safety work instruction for Operation 0 30-04-17 2
of Tower Crane
48 QEHS / 348 Environment and Safety work instruction for Loading, 0 30-04-17 1
Unloading and Handling of Material
49 QEHS / 349 Environment and Safety work instruction for 0 30-04-17 1
Fabrication, Aluminium and Glass Work
50 QEHS / 350 Environment and Safety work instruction for Working at 0 30-04-17 1
Night up to 10:00 p.m.
51 QEHS / 351 Environment and Safety work instruction for Office 0 30-04-17 1
Work
52 QEHS / 352 Environment and Safety work instruction for CLC Plant 0 30-04-17 1
53 QEHS / 353 0 30-04-17 3
False Ceiling Work Instructions
54 QEHS/354 Ramp in Stilt Parking 0 30-04-17 4