Beruflich Dokumente
Kultur Dokumente
TECHNICAL SPECIFICATIONS
I. GENERAL REQUIREMENTS
PART A – EARTHWORKS
2A.1 Scope
2A.2 General
2A.4 Excavation, general
2A.5 Compaction
2A.6 Sub-grade preparation
2A.7 Excavating, filling and backfilling for building
2A.8 Excavation, trenching and backfilling for utilities
DIVISION 3 – CONCRETE
DIVISION 4 – MASONRY
DIVISION 5 – METAL
00 01 10-1
10-01-18
DIVISION 9 – FINISHES
15110 Valves
15140 Domestic Water Piping
15440 Plumbing Fixtures
DIVISION 16 – Electrical
00 01 10-2
10-01-18
GENERAL REQUIREMENTS
1.3.1 Field Office and Staff House for the Engineer (DOTC-PMO)
and Engineer’s Representative (Consultant) including their Staff
During the performance of the contract, the Contractor shall provide
and maintain field office for the Engineer and Engineer’s
representative within the site of the work at designated location
indicated on the Drawings while the work is in progress. The Contractor
shall also maintain the existing staff house of the Engineer and shall
also provide and maintain a separate office on rental basis for the
Engineer’s Representative at location approved by the Engineer during
the entire duration of the contract. Construction shanties, sheds and
temporary facilities provided as required for the Contractor's
convenience shall be maintained in good condition and neat appearance
including finishes as required by the Engineer. The field office for
the Engineer/Engineer’s representative shall be constructed all in
accordance with the Standard Specification and design shown on the
approved Drawings. The building shall have the floor area prescribed
on the Plans and shall have a 24-hour security services and shall
strictly comply with the provisions of Batas Pambansa 344
(Accessibility Law) and the Building National Code. The building shall
contain the equipment, supplies, furnishing and appliances specified
in Schedules B. All facilities to be provided by the Contractor shall
conform to the best standard for the required types. The facilities
provided by the Contractor including utilities and communication
facilities shall revert to the Government including office equipment,
furnitures, etc. upon completion of the Project. The Contractor shall
be responsible for raising the ground (if necessary), the grading and
provision of drainage facilities in the vicinity of the facility with
suitable access walkways,
00 01 10-3
10-01-18
00 01 10-4
10-01-18
1.5.1 Measurement
a) Field Office and Staff House for the Engineer and Engineer’s
Representative
00 01 10-5
10-01-18
1.5.3 Payment
Payment shall be made under the following pay items included in the
Bill of Quantities. Such payments shall be full compensation for
furnishing, maintaining and insuring against loss of the facilities
and equipment specified including removal and restoration of the
site(s). The requirement that ownership of facilities shall revert
to the government shall not apply if such facilities are provided on
rental basis under terms approved by the Procuring Entity. For all
work executed or goods, materials, or services supplied by the
00 01 10-6
10-01-18
00 01 10-7
10-01-18
PART A – EARTHWORKS
2A.1 Scope
This section includes the following:
• Complete clearing of site, general site grading, and provision
of backfill and garden soil, as indicated
• Complete excavating, filling and backfilling for building, as
well as for utilities within the building and to the points of
connection with the building utility lines or to terminal points
indicated.
2A.2 General
2A.5 Compaction
00 01 10-8
10-01-18
00 01 10-9
10-01-18
00 01 10-10
10-01-18
PART 1 – GENERAL
2.1.1 Backfill
PART 3 - EXECUTION
3.1 PROTECTION
3.1.2 Dewatering
00 01 10-11
10-01-18
3.6 BACKFILLING
3.7 COMPACTION
00 01 10-12
10-01-18
CAST-IN-PLACE CONCRETE
PART 2 – PRODUCTS
2.1 CONCRETE
2.2 MATERIALS
2.2.1 Cement
2.2.2 Water
2.2.5 Admixtures
00 01 10-13
10-01-18
2.2.7 Reinforcement
a. Reinforcing Bars
ASTM A 615 (Weldable). All reinforcing steel shall be deformed.
Reinforcing steel shall have a minimum yield strength of 275 MPa
(Grade 40) for bars dia. 12mm and smaller, and 414 MPa (Grade 60)
for bars dia. 16 and larger.
PART 3 – EXECUTION
a. Weight Measurement
b. Volumetric Measurement
00 01 10-14
10-01-18
3.1.2 Mixing
00 01 10-15
10-01-18
DIVISION 4 – MASONRY
PART 2- PRODUCTS
2.1 Masonry Units
2.1.1 Concrete Masonry Units (CHB):
a. Aggregates: ASTM C33
b. Linear Drying Shrinkage: Not to exceed 0.065 percent when tested
in accordance with ASTM 426.
c. Kinds and Shapes: In addition to the requirements specified,
concrete masonry units of the various kinds shall conform to PNS 16,
Type II for 150 mm thick(f’m = 7 MPa / 5 MPa) and for 100 mm thick
(f’m = 2.5 MPa). Include closer, jamb, lintel and bond beam units
and special shapes and sizes to complete the work as indicated.
2.4.1 Admixtures
ASTM C 144, except that not less than 3 percent nor more than 15
percent shall pass the No. 100 sieve. Aggregate used in mortar for
joint 6 mm or less shall have 100 percent passing the No. 8 sieve
with 10 percent being retained on the No. 16 sieve.
00 01 10-16
10-01-18
2.6.1 Proportions
PART 3 – EXECUTION
3.1 Preparation
3.1.1 Protection
a. Forms and Shores: Where required, construct forms to the shapes,
lines, and dimensions of the members indicated. Construct forms
sufficiently rigid to prevent deflections which may result in
cracking or other damage to supported masonry and sufficiently tight
to prevent leakage of mortar and grout. Do not remove supporting
forms or shores until the supported masonry has acquired sufficient
strength to support its weight and construction loads to which it
may be subjected. In no case shall supporting forms or shores be
removed in less than 10 days. Wait at least 16 hours after grouting
masonry walls after applying uniform loads and wait an additional 48
hours before applying concentrated loads.
00 01 10-17
10-01-18
c. Wall Bracing: Brace walls against wind and other forces during
construction. Allow sufficient time between lifts to prevent
cracking of face shells of hollow masonry units. If blowouts,
misalignment, or cracking of face-shells should occur during
construction, tear down and rebuild the wall at no additional
cost to the Owner.
3.5 Tolerance
Lay masonry plumb, true to line, with course level. Keep bond
patterns plumb throughout.
00 01 10-18
10-01-18
DIVISION 5 – METAL
PRODUCTS
2.1 MATERIALS
2.1.1 General
Comply with standards indicated for forms and types of metals
indicated or required for handrail and railing system components.
PART 3 – EXECUTION
3.6 PROTECTION
00 01 10-19
10-01-18
PART 2 – PRODUCTS
2.1 MATERIALS
Expansion Shield shall be of high quality, heavy duty, with size,
group, type, class, and style best suited for the purpose. Shield
shall be accurately recessed and shall be not less than 63 mm into
concrete or masonry.
a. Nails and Staples shall be of best quality with type and size
best suited for the purpose. Nails may be of the annular ring
or the screw type, with mechanically deformed shanks.
PART 3 – EXECUTION
3.1 INSTALLATION
00 01 10-20
10-01-18
PART 1 – GENERAL
1.1 SCOPE
PART 2 – PRODUCTS
2.2 SEALANT
As specified I Section 07900, “Sealant and Caulking”.
00 01 10-21
10-01-18
PART 3 – EXECUTION
3.1 PREPARATION
3.1.1 Flashings
3.1.1.1 Drains
00 01 10-22
10-01-18
PART 1 – GENERAL
1.1 SCOPE
PART 2 - PRODUCTS
2.1 THERMAL RESISTANCE VALUE (R-VALUE)
2.3 ACCESSORIES
PART 3 - EXECUTION
3.1 PREPARATION OF SURFACES
00 01 10-23
10-01-18
PART 1 – GENERAL
1.1 SCOPE
PART 2 - PRODUCTS
2.1 THERMAL RESISTANCE VALUE (R-VALUE)
2.3 ACCESSORIES
PART 3 – EXECUTION
Batts or laid over purlins (below roofing sheets) with vapor barrier
towards inside and secured in place with wire mesh secured to
purlins with tie wire.
00 01 10-24
10-01-18
PART 1 – GENERAL
1.1 SCOPE
PART 2 - PRODUCTS
2.1 STANDARD STEEL DOORS
2.2 LOUVERS
00 01 10-25
10-01-18
DIVISION 9 – FINISHES
PART 1- GENERAL
1.1 SCOPE
PART 2 – PRODUCTS
2.1 MATERIALS
PART 3 – EXECUTION
3.3 INSTALLATION
3.3.1 Coordination
00 01 10-26
10-01-18
PART 1 GENERAL
1.1 SCOPE
PART 2 – PRODUCTS
2. 1 MATERIALS
00 01 10-27
10-01-18
2.3 SAND
Clean, potable.
ASTM C1500, Type I, white for grout, gray for other uses.
PART 3 – EXECUTION
3. L INSTALLATION
Do not start tile work until roughing-in for plumbing and electrical
work has been completed and tested. All surfaces to receive tile-
work shall be cleaned of loose materials and given proper surface
preparation prior to ceramic tile-work. Prepare and install in
accordance with ANSI A108.1 and ANSI A108.5.
c. Evenly rake scratch coats, but not dash coats, to provide good
mechanical key for subsequent course before the mortar has
fully hardened.
00 01 10-28
10-01-18
g. f. Keep the joints parallel and straight over the entire area
by using straight edges.
h. g. Tamp the tile solidly onto the bed, using wood blocks of
size to ensure solid bedding
3.1.4 Grouting
d. During grouting clean all excess grout off with clean burlap,
other cloth or sponges.
3.2 CLEANING
Sponge and wash tile thoroughly with clean water after the grout has
stiffened. Then clean by rubbing with damp cloth or sponges and
polish clean with dry cloth.
00 01 10-29
10-01-18
3.3 PROTECTION
Cover finished tile floors with clean 13.6 kg. Natural Kraft paper
before permitting foot traffic. Place board walkways on floors that
are to be continuously used as passageways by workers. Protect tiled
corners external angles, with board corner strips in areas used as
passageways by workers.
00 01 10-30
10-01-18
PART 1- GENERAL
1.1 Scope
This section covers gate valves, check valves, and angle valves.
Valves shall be furnished and installed complete with all fittings,
jointing materials, hangers, supports, anchors, and other necessary
appurtenances.
PART 2- PRODUCTS
2.1 Materials
a. Gate valves
(1) 65 mm and smaller MSS-SP-80
(2) 75 mm and larger AWWA C500
b. Check valves
2.2 Performance
Check valves, 65mm and larger, which are installed in water pump
discharge piping having a working pressure of 125 psig or less shall
be swing type designed for installation between two pipe flanges.
Each check valve shall have a cast iron or bronze body.
Check valves 50mm and smaller in water piping shall be rated 125
psig at a minimum temperature of 28°C, all bronze, Y-pattern,
regrinding, horizontal swing type.
00 01 10-31
10-01-18
PART 3- EXECUTION
3.1 Installation
Valves and valve boxes shall be set plumb. Each valve box shall be
placed directly over the valve it serves, with the top of the box
brought flush with the finished grade. After being place in proper
position, earth shall be filled in around each valve box and
thoroughly tamped on each side of the box.
3.2 Cleaning
The valves shall be smooth, clean, and free from blister, loose mill
scale, sand, dirt, and other foreign matter when erected. The
interior of all lines shall be thoroughly cleaned, to the
satisfaction of the Owner’s Representative, before being placed in
service.
PART 1 – GENERAL
1.1 Scope
PART 2 - PRODUCTS
2.1 Materials
2.1.1 Pipes and Fittings
a) Cold Water Piping
00 01 10-32
10-01-18
PART 3 – EXECUTION
3.1 Preparation
Pipe shall be cut from measurements taken at the site and not from
the drawings.
3.2 Installation
3.2.1 Piping
3.4.1 Cleaning
00 01 10-33
10-01-18
PART 1- GENERAL
1.1 SCOPE
PART 2 – PRODUCTS
2.2.3 Lavatory
3.8 LPF flush valve fitting for urinal with Ø 3/4” vacuum breaker
with bushing reducer.
2.2.8 Faucet
00 01 10-34
10-01-18
PART 3 – EXECUTION
3.1 INSTALLATION
00 01 10-35
10-01-18
PART 1 – GENERAL
1.1 APPLICATION
00 01 10-36
10-01-18
Division 16 – Electrical
PART 1 – GENERAL
1.1 APPLICATION
00 01 10-37
10-01-18
PART 2 – PRODUCTS
2.1 NAMEPLATES
Provide laminated plastic nameplates for each panel-board, equipment
enclosure, relay, switch, and device. Each nameplate inscription
shall identify the function and, when applicable, the position.
Nameplates shall be melamine plastic, 3.17 mm thick, white with
black center core. Surface shall be matte finish. Corners shall be
square. Accurately align lettering and engrave into the black core.
Minimum size of nameplates shall be 25.4 mm by 63.5 mm. Lettering
shall be a minimum of 6.35 mm high normal block style.
00 01 10-38
10-01-18
PART 3 - EXECUTION
3.1 NAMEPLATE MOUNTING
Provide number, location, and letter designation of nameplates as
indicated. Fasten nameplates to the device with a minimum of two
sheet-metal screws or two rivets. 3.2 FEES AND PERMITS
a. Pay all required fees and obtain all required permits related
to the ELECTRICAL installation.
General:
00 01 10-39
10-01-18
00 01 10-40
10-01-18
00 01 10-41
10-01-18
PART 1 – GENERAL
PART 2 – PRODUCTS
00 01 10-42
10-01-18
2.4.1 Conductors
Minimum size for branch circuits shall be 3.5 mm²; for Class 1
remote-control and signal circuits, 2.0 mm²; and for Class 2 low-
energy remote-control and signal circuits, 1.25 mm².
2.4.4 Insulation
2.5 CABINETS, JUNCTION BOXES AND PULL BOXES (WITH VOLUME GREATER
THAN 100 CU. INCHES) Provide hot-dipped, zinc-coated if steel sheet.
00 01 10-43
10-01-18
One-piece device plates for outlets and fittings to suit the devices
installed. Plates on unfinished walls and or fittings shall be of
zinc-coated sheet steel or cast metal having round or beveled edges.
Plates on finished walls shall be urea or phenolic, minimum 2.54 mm
wall thickness. Plates shall be the same color as the receptacle or
toggle switch with which it is mounted. Screws shall be machine type
with countersunk heads in a color to match the finish of the plate.
The use of sectional type device plates will not be permitted.
Plates, installed in wet locations shall be gasketed.
00 01 10-44
10-01-18
PART 1 – GENERAL
PART 2 – PRODUCTS
2.1.1.1 Lamp
PART 3 – EXECUTION
3.1 INSTALLATION
3.2 GROUNDING
PART 1 – GENERAL
PART 2 - PRODUCT
2.1 GENERAL
Specifications are intended to describe the requirements of
Structured Cabling System.
00 01 10-45
10-01-18
The distribution frame shall link the horizontal system & backbone
system together. Shall be composed of floor-mounted rack, patch
panels, terminal block, cross connection wires, patch cord, and
cable management system.
00 01 10-46
10-01-18
PART 3- EXECUTION
3.1 INSTALLATION
All horizontal cables shall not exceed ninety 90 meters from the
Main/Intermediate Distribution Frame.
The total length of patch cord and equipment cable shall not exceed
ten (10) meters.
00 01 10-47
10-01-18
PART 1 - GENERAL
1.1 GENERAL REQUIREMENTS
Section 16011, "Electrical General Requirements," applies to this
section, with the additions and modifications specified herein.
PART 2 – PRODUCTS
2.1 GENERAL
00 01 10-48
10-01-18
Upon the alarm activation of any area smoke detector, heat detector,
manual pull station, sprinkler water flow, the following functions
shall automatically occur:
00 01 10-49
10-01-18
PART 3 – EXECUTION
3.1 INSTALLATION
00 01 10-50