Chevron Thailand Exploration and Production Ltd.

Guidelines on issuing CM for anomaly relying on Visual inspection 
Corrective Action Priority
Item Type of Anomaly P1  P2  P3  P4  P4  P5  Example of anomaly Example of Recommendation
(24 hrs) (7 days) (180 days) (1 year) (2 year) (Next S/D)
A: Damaged painting with significant  A: Repaint within 6 months.
corrosion B: Repaint within 1 year.
B: Damaged painting without significant  C: Repaint within 2 year.
1 External Painting A B C corrosion
C. Damaged painting for non‐pressure 
part.

A: Breakage, Extensive damage or  A: Replace bolting within 7 days.
Extreme corrosion which can lead to  B: Replace flange within next shutdown.
2 Bolting / Flange A B
failures before next shutdown
B: Significant corrosion
A: Breakage, Extensive damage or  A: Repair pipe support within 7 days. 
Extreme corrosion which can lead to  Qualified piping Engineer may need to be consulted in developing a 
failures before next shutdown. repair method in order to restore sufficient integrity to continue safe 
Pipe support / Structure  B: Significant corrosion operation.
3 Damage or Corrosion A B B: Repair pipe support within next shutdown. 
Qualified piping Engineer may need to be consulted in developing a 
repair method in order to restore sufficient integrity to continue safe 
operation.

A1: Excessive piping vibration which can 
lead to failures A: Eliminate the vibration within 6 months.
A2: Inadequate support ‐ Frequency & Amplitude may need to be determined by Vibration 
Piping vibration, 
A3: Pipe jostle other object team in case inspectors doubt whether it is still acceptable pipe 
4 Inadequate support, Pipe  A
vibration (Allowable vibration levels VS Frequency can be used as a 
jostle other object, etc.
first evaluation).
‐ Qualified piping engineer should be consulted to eliminate the piping 
vibration.
Seeping through thread,  A: liquid or gas seeps somewhere  A: Stop leak or replace in kind within 6 months. 
5 stem, flange connection,  A Repaired date can be changed, depending on judgment from O&M.
etc.
A1. Damage/penetrations. A. Repair insulation within 1 year.
A2. Missing jacketing/insulation.
6 Insulation A
A3. Sealing deterioration.

Note:
1. This document shall be used by Inspectors as a guide for inspecting the in‐service process piping and pressure equipment.
2. This document defines typical Corrective Action Priority and Recommended Corrective Action for the anomaly relying on visual inspection only. It does not apply to wall thinning and welding/surface defect caused by 
either from fabrication or operation. 
3. Specific Corrective Action Priority and Recommended Corrective Action may change on case‐by‐case basis depending on inspector's judgment.

Revision No.: 01
Date: 14‐May‐2013 Page 1 of 1