Date Shif Name Work Description Duration

22.05.2019 Morning Aziz BSDG Annual PM (Filters and oil replacement) 7 hrs
Wajahat Shifting of EDG spares and Oil 30 min
Imtiaz

22.05.2019 Night Waseem Oil replacement continued 5 hrs


Taufeeq Floating gas tank-B chain sprocket greasing 1 hr
PM of coagulant metering pump 30 min

23.05.2019 Morning Aziz GT-2 Varnish Removal skid dismantling 3 hrs


Wajahat Filter removal and replacement 1 hr
Farman Oil drainage 1 hr
Imtiaz Dismantling of NG CCCW NRV
Shifting of scrapped oil and filters 1 hr

23.05.2019 Night Waseem NG CCCW Pump rotor dismantling 5 hrs


Toufeeq Support to the waste sea water pump installation 3 hrs

24.05.2019 Morning Farooq Limit Adjustment of GT-2 88 EF-2 3 hrs


Imtiaz Oil sampling of BSDG 1,2,3 1 hr
Wajahat
Farman

24.05.2019 Night Aziz Strainer Cleaning of GT1 and 2 2 hrs


Wajahat

27.05.2019 Morning Sunawwar GT-3 88 EF-2 Damper adjustment 2 hrs


Farman Potable water pump-2 casing leakage 4 hrs
Wajahat

27.05.2019 Night Farooq PM Permits 4 hrs


Imtiaz

28.05.2019 Morning Waseem Valve shifting 1 hr


Wajahat Potable pump dismantling
Taufeeq

07.06.2019 Morning Aziz GT-1/2 Strainer Cleaning 2 hrs

08.06.2019 Morning Aziz Potable Water Pump Permit 4 hrs


Waqas GT 1/2 Strainer Cleaning 1 hr
Imtiaz Leftover Material Returned to store 2 hr

Scrap material shifted to HE Area 30 min


Leftover Gaskets Listing 3 hrs

17.06.2019 Morning Farooq Manholes opening HSD Tank-2


Waseem Potable pump coupling adjustment
Imtiaz Air compressor shifting
Farman hydrant 10 testing
Wajahat

17.06.2019 Night Aziz Night permits not issued


Jamil

18.06.2019 Morning Waseem GT-2 Pre filter replacement 19221165


Sunawwar WTP Compressor dismantling
Taufeeq IAC 1 and 2 Oil makeup
Farooq WTP compressor oil sampling
Potable jamming issue permit

18.06.2019 Night Aziz Weekly PM of GT1/2/3/

19.06.2019 Morning Waseem


Sunawwar
Taufeeq
Wajahat
Farman

24.06.2019 Morning Aziz FF PRV and Isolation valves issuance


Farman Potable pump-1 overhauling
Waseem I&C support at N2 station
Wajahat WTP workshop compressor dismantling
Sunawwar WTP new site compressor canopy removal
SAC-1 bolt tightening
Fabrication for ff recirculation line
GT 1& 2 HX Cleaning

26.06.2019 Morning Sunawwar HSD tank inspection with performance


Farman NG-1 lube oil purifier
Wajahat Test run of SAC-1
Taufeeq Preservation of repairable and reapired Air compressors

Imtiaz PM of oil unloading pumps

26.09.2019 Night Aziz Weekly PM of GT 1/2/3


PM of compressor washin pump A and B
26.06.2019 Morning Sunawwar
Farman
Wajahat
Taufeeq
Waseem

02.07.2019 Morning Aziz Potable pump assembling


Waseem NRV and SAC returned to stores
Imtiaz
Wajahat
Farman

03.07.2019 Morning Farman


Wajahat
Imtiaz H2 plant potable line leakage notification verification
Farooq Diesel pump bolt tightening and radiator water makeup
Sunawar Fire fighting jockey pump installation
Waseem WTP compressor oil cooler replacement and gasket
19195467
19236012
ZR55 Spares

19342510 (bolts)

18903758 CN against refurbishment order (890000479)


19364768 DN against W/O no. (780080265)
Date Shift Persons Job Description Duration
10.06.2019 Morning Farooq HSD Tank Risk Assessment 2 hrs
Imtiaz Potable pump casing removed 2 hrs
Farman Gaskets Seggregation at CNI-22 3 hrs

10.06.2019 Night Aziz Potable pump seal adjustment


Wajahat Casing assembled 6 hrs
Pump Coupled

11.06.2019 Morning Sunawwar PM of IAC 4 hrs


Farman Safety Hour 1 hr
Potable pump casing repair 4 hrs

Farooq
11.06.2019 Night Absent
Imtiaz

12.06.2019 Morning Sunawwar Potable pump 2 dismantling


Farman wtp compressor oil sampling 1 hr
Taufeeq Gaskets Listing 5 hrs
Wajahat Blind removal 1 hr

12.06.2019 Night Farooq PM of floculant pump A 2 hr


Imtiaz PM of dissolved gas pump B 2 hr

13.06.2019 Morning Sunawwar bush machining 1 hr


Farman Assembling of potable pump 4 hr
Taufeeq Blind removal 1 hr
Wajahat WTP Comp HX testing 2 hr

14.06.2019 Morning Sunawwar Gaskets Manual CN


Imtiaz SAC Filters Issuance
Wajahat
Taufeeq