Beruflich Dokumente
Kultur Dokumente
Many challenges are encountered during the five phases of the materials
management process. These challenges were grouped into three categories:
information technology, decision modeling and implementation
management.
132
5.1 CHALLENGES - INFORMATION TECHNOLOGY
During the Bidding Phase, the firm may be forced to cut costs to satisfy
budget limits of owners while still committing to the same scope of work.
The Electrical Contracting (EC) is usually one of the last trades to be
procured in a project and many times is asked by the General Contractor
(GC), prior to finalizing the sub-contract agreement, to absorb some of these
cost reductions. This puts pressure on the EC to complete the scope of work
for a lower cost than what was initially budgeted. This situation usually
arises because the GC promises unrealistic estimates to the owner without
the direct involvement of his specialty contractors. The problem could be
minimized if the EC is involved in the pre- construction planning and design
phase of the project (Figure 4.3).
The EC can provide to the owner expertise regarding materials and means
and methods for installation, as well as more realistic cost estimates. The
EC could also provide information about the difficulty, cost and time
required for installation in order to better assess the effect that the changes
in scope could have on overall cost and schedule. The enabling technology
133
for such integration of the EC in the project's bid estimation is internet-
based communications between the GC and the EC and the electrical
contractor's access to a database of material prices, lead times, wage rates
and standard job times.
The Sourcing Phase requires access to data regarding prices, quality, and
delivery performance and existing contractual arrangements with
manufacturers and suppliers. Typically, prices are requested by a fax
transmittal from the EC to the potential suppliers. Fax technology is
becoming more time consuming compared to other recent means of data
communication. Fax machines are also more prone to breakdown problems
(e.g. paper jams, incomplete transmittal, signal loss etc.) compared to other
methods (e.g. Computers, emails). Furthermore, it could take longer for the
fax information to reach the person in charge of providing quotes and for the
EC to get an answer to the request for pricing. There have been some efforts
to develop a P2P network pricing system that will allow ECs' personnel to
have immediate access to the current prices of a particular supplier with
near real-time updates, therefore reducing the difficulties that the current
practice presents. Ideally, the EC would be able to draw on historical data
reflecting experience with different supply sources as well as up-to-date
pricing and delivery data. Clearly, a combination of on-line and proprietary
data is required.
134
material. Ready access to contract data and project scheduling data as well
as a means to communicate delivery instructions to personnel on site is
essential to performing these tasks. Material is usually procured by a fax
transmittal from the EC to the supplier indicating the material needed
quantities and delivery dates. This process might present the same
challenges that are present in the sourcing phase. Similar to the sourcing
phase, there have been efforts to develop a P2P network that will allow the
EC to place orders through a computer. This will accelerate the ordering
process and reduce errors that often occur in current practice.
135
material is needed immediately. If the person receiving the material does not
verify the material and/or does not identify any damage, the contractor may
end up responsible for the damaged material, which will result in a loss.
Similarly, the contractor assumes responsibility for damages to material
while it is stored prior to installation. An automated system, such as bar
codes, could greatly improve tracking and inventory control and could
minimize lost and misplacement of materials.
There are a number of managerial decisions that create and regulate the
supply chain and are embedded in the five-phase process for materials
management that is described in the previous sections. In Figures 4.3 to 4.6
those junctures or nodes in the materials- management process that
constitute decisions are identified. Table 5.1 offers a consolidated list of
these decisions and the elements of each decision in terms of alternatives,
parameters, and performance measures.
136
Table 5.1b: Sourcing Phase Decisions
Decision Alternatives Parameters Performance
Measures
What type of • Major • Project • On site
material to material specifications availability
buy? • Commodities • Project • Purchase
• Consumables schedule cost
• Foreman’s • Alternative
habits/practices use
• Production and • Suitability
usage
• Needed vs.
wanted
Award • Local • Arrangement • Projected
supplier/manuf suppliers with suppliers shortages
acturer • Non-local • Availability • Inventory
contracts. suppliers • Criticality • Quality
• Vendor • Location of • Quantities
Managed supplier
Inventory • Location of
• Manufacturers project
• Supplier’s
performance
• Discounts
137
Table 5.1c: Procurement Phase Decisions
Decision Alternatives Parameters Performance
Measures
When to • 3 months • Type of material • Projected
buy in advance (commodity vs. major) shortages
material? • 1 month in • Project schedule • Inventory
advance • Uncertainty in project • Direct costs
• 1 week in schedule • Indirect
advance • Storage Capacity costs
• 1 day in • Location of the project
advance • Location of the
• Same day supplier
• Criticality of the
material
• Order to install vs.
order to pre-fab
• Supplier’s performance
and ability to meet
schedules
How much • As • Project schedule • Surplus
to order? estimated Uncertainty in project • Projected
• Less than schedule shortages
estimated • Storage capacity • Indirect
• More than • Installation rate and costs
estimated usage
• Procurement cost rates
• Indirect cost rates
• Discounts
When to • Single or • Project schedule • Surplus
deliver? multiple • Uncertainty in project • Project
shipments schedule shortages
• Shipment • Storage capacity • Indirect
quantities • Installation rate and costs
usage
• Procurement cost rates
• Indirect cost rates
138
Table 5.1d: Construction Phase Decisions
139
During the Bidding Phase various decisions need to be made regarding
bidding and estimating the job. The first decision faced by the EC is the
contract price to enter as a bid. The quantity takeoff and estimate need to be
completed in order to prepare and submit a bid package to the owner. These
data must be evaluated in light of the firm's commitments on existing
contracts as well as the contractor's required profit margin and tolerance of
financial risk. The tradeoff presented to the firm by this decision and the
complex influences of numerous contract parameters makes the decision of
how much to bid an overwhelming task without the aid of the quantitative
analysis offered by a decision model.
During the Sourcing Phase, the firm has to decide between entering into a
blanket contract or a competitive bidding approach. Although guaranteed
availability is insured through a blanket contract, better prices could be
realized through a competitive bidding process. In addition, the contractor
has to decide which suppliers are the most qualified to satisfy the conditions
and services under a contract. The tradeoff between the performance
measures of availability and cost and their subsequent impact on job
activities and project delays need to be analyzed.
Once the Procurement Phase is underway, the industry needs to decide how
much material is needed, and when the material should be delivered to the
site. The decision of how much to buy is very important to assure that
material quantities needed are available and that there are no material
shortages. Typically, contractors purchase an amount of material that is less
than the amount estimated (e.g., 75% of original estimated material needed)
in order to avoid material surplus at the jobsite. Additional quantities are
purchased when the job is near completion and a better estimate is realized.
This approach to materials management highlights the contractors’ need for
140
information systems and decision analysis. The cost of surplus materials is
traded off against the costs of extra shipments and the risk of material
shortages and ensuing project delays. Furthermore, a miscellaneous item
may be used on more than one project providing the contractor an
opportunity to trade off inventory holding costs with purchase costs and
shipping costs by combining requirements into larger, batch shipments.
Quantitative analysis of this tradeoff and obtaining the most accurate
forecasts of material needs are required for optimizing the extent of deferred
material purchases.
Once the fabrication phase has started, the decision of timing deliveries of
material is based on a baseline project schedule indicating the amount of
material needed at different times in the schedule, as well as anticipated
productivity and past performance. From our interviews of contractors, it
was found that most of the electrical contractors deliver large amounts of
their material early in the project schedule based on field-personnel
purchase requests without planning deliveries with respect to material
needs. The decision of the timing deliveries strikes up a tradeoff between
receiving materials early and incurring storage costs and not having
materials on the construction site when needed. Furthermore, space
constraints at the jobsite that could be critical for storage purposes are
usually not considered by contractors in scheduling material delivery early
in the project. This practice results in additional costs associated with
storage fees, damage during storage, theft and re-handling due to space
limitations. Ideally, the contractor integrates the material release schedule
with the work schedule. A decision model could project space availability
for every alternative delivery schedule that the contractor would like to
consider. If space availability becomes a critical issue, the cost of various
141
means of storage (e.g. "sea cans" or offsite storage locations) can be
evaluated based on different factors including distance from the jobsite and
associate costs.
The decision of where to deliver the material requires space planning and
consideration of site limitations, pre-fabrication strategies, and
subcontractors to be used. Material is generally requested for delivery to the
job site. From our site visits to some projects, it was observed that in many
instances the material was stored in "sea cans" located far away from the
jobsite. This increases the potential of material loss due to theft. Regarding
material stored in the work area, this was done without proper planning, and
material often needs to be moved to free space so that other trades can work
in the area. The costs associated with re-handling, loss and/or theft are not
realized when ordering the material. The EC could use better procurement
policies to avoid having over-stocking of inventory on the jobsite, and to
decrease inventory costs. However, the effort of changing ordering policies
will require a commitment of delivery when needed by the supplier.
Another approach that could be used to decrease inventory is called vendor-
managed inventory (VMI), described in Chapter 4. When this approach is
used, the distributor places a trailer on site with the needed material and
equipment and takes the responsibility of maintaining the inventory
throughout the project. The distributor charges the contractor for material
and equipment used at predetermined prices. At the end of the project, the
distributor removes the trailer along with the unused inventory. The
company can also outsource their warehouse operation to the distributor.
Each of these many options for locating material storage incurs several costs
and affects the risk of material shortages differently. A decision model
could support a quantitative analysis of these alternatives.
142
Once the construction phase is completed, the decision of what to do with
the surplus material depends on many factors such as availability of a
warehouse and storage space, expected need for the material in future
projects, actual need for the material in an existing project, inventory
holding costs, opportunity costs due to having capital invested in material
that is being stocked, among other factors. The EC needs to decide between
sending the surplus to the supplier (a penalty cost might be incurred for
specialty items), selling the material to other contractors, sending the
material to the warehouse or scrapping. The decision taken depends heavily
on the tradeoffs between cost savings from making material readily
available versus holding costs.
143
has developed incentive programs to introduce site staff to the benefits of
pre-fabrication and to facilitate a change of culture and acceptance of the
process.
144