Beruflich Dokumente
Kultur Dokumente
An IEER Submitted
In Partial Fulfillment of the Requirements for the Degree of
Bachelor of Science in Chemical Engineering
i
(Reserved for Project Fact Sheet)
ii
Table of Contents
iii
4. BASELINE ENVIRONMENTAL CONDITIONS, IMPACT ASSESSMENT 21
AND MITIGATION
4.1. The Land 21
4.2. The Water 29
4.3. The Air 36
4.4. The People 38
5. ENVIRONMENTAL MANAGEMENT PLAN 40
5.1. Impact Management Plan 40
5.2. Emergency Response Policy and Generic Guidelines 42
5.3. Environmental Monitoring Plan 48
5.4. Institutional Plan for EMP Implementation 54
6. BIBLIOGRAPHY/REFERENCES 56
7. ANNEXES 57
7.1. Scoping Checklist 58
7.2. Original Sworn Accountability Statement of Proponent 66
7.3. Original Sworn Accountability Statement of IEE Preparer 67
7.4. Baseline Study Support Information 68
iv
List of Tables
v
List of Figures
vi
Executive Summary
NAPKA, Inc. is designing an NPK fertilizer plant with nitric acid plant in Light
Industry & Science Park III in San Rafael, Santo Tomas, Batangas. It is expected to
consume 2 hectare of land area in the vicinity and designed to produce about 30,000
MT of NPK fertilizer annually. It has been developed in order to add up as an additional
supplier of fertilizer to cope up to increasing demand in food. The plants will
incorporate two processes, mainly, high-pressure nitric acid process with nitro
phosphate production of NPK fertilizer. Expected environmental impacts are
documented in IEER for each phases of the project. Project costs, such as capital
investment costs and annual production costs, are about P 3 billion and P 1.5 billion
annually, respectively. Total number of employees reaches 120 for overall operation
of the plant. The expected duration of the plant may exceed 20 years.
Every EIA process makes sure that environmental issues are raised when a project
or plan is first discussed and that all concerns are addressed as a project gains
momentum through to implementation. The IEE is a first assessment of the reasonably
foreseeable impacts on the environment of a proposed activity or activities. These
impacts often depend on the environmental mitigation and monitoring activities
specified in the IEE. IEE was carried out with the usual flow of EIA process with
informal consultations through each step:
• Screening
• Scoping
• Drafting of EIA (Project Description; Baseline Study; Environmental Management
Plan)
• Review
Final EIA/IEER
1
3) Summary of Baseline Characterization
The Baseline characterization of the plant considered the following areas affected
like Land, Water, Air, and the People in the region. Region 4-A where Batangas
province is located have different land use classifications and mostly the land is
classified as developing urban center for industries. The area of the plant in Batangas
which is LISP III in San Rafael, Sto. Tomas City, Batangas is surrounded by land mass.
These lands vary from terrains and rock formations that are classified at their age.
Terrestrial biology of the province and the habitat of the marine animals in the area
are dictated in the National List of Threatened Fauna which is listed in DENR
Administrative Order No. 2004-15.
Climate assessment and air quality is conducted for the pollution checking of the
province. The Climate is known to be Type 1 which consists of wet and dry season.
The Air quality of Batangas is inspected at Realtime basis and has a value of 80 index
depicted in AirVisual PM2.5 detection site. Other pollution measurement integration is
also provided for the value integration of the region. The project site is also considered
and mostly located within the park premises. It is consisting mostly of trees and an
aerial view of the industrial park is provided.
2
DENR have their own control strategies. Mitigation of polluting gas such as NO was
controlled using humid air method. The wastewater which includes some nutrients is
also controlled by a sequential batch reactor. The plan, in case of eutrophication, was
included along with its prevention and control
3
1. BASIC PROJECT INFORMATION
4
Figure 1. Topography of LISP III
5
2. DESCRIPTION OF THE PROJECT’S IEE PROCESS
The IEE study is conducted for the proposed plant of NPK fertilizer manufacturing
plant. This assess the Environmental Management Plan that scopes the Impacts
Management Plan, Control Strategies, Wastewater treatment, Emergency response
policies, Emergency response plan, Environmental monitoring Plan, Self-Monitoring
Plan, Hazard Identification, Confined Spaces, Containment Plan, Multi-sectorial
Monitoring framework, Hydrology Monitoring, Environmental Guarantee and EMP
implementation. The study provides initial information of the project and is limited to
information like data on their degree of uncertainty as to the exact nature and
magnitude of environmental impacts and resulting effects. It also assesses the
remedial measures for development of projects. This was conducted prior to the
proposal of the manufacturing plant.
This report was prepared by Plant Design Group with the code 2018CHE008 for
“CHE185: Industrial Waste Management and Control” of 3rd Semester 2018-2019. The
group is composed by 3 members under the supervision of Engr. Jor Quidilig in partial
fulfillment of Plant design. Table 2 shows the members name and educational
background.
6
Table 2. 2018CHE008 Members
May 3,2019
May 6,2019
May 8,2019
May 10,2019
May 13,2019
May 15,2019
7
environmental impact caused by implementation of the proposed projects and
programs based on available data and information and limited field reconnaissance.
Another is that it recommends necessary preventive measure and modification of
projects and programs, if necessary. It also suggests necessary environmental impact
study such as IEE and/or EIS at feasibility study stage
Aside from the natural environmental conditions and pollution issues, other
significant concerns relating to the project include:
8
Screening
Informal Consultation
Scoping
Regulatory Review
Project Description
Environmental
Management Plan
Expert Review
Final EIA
9
3. PROJECT DESCRIPTION
10
Figure 5. Santo Tomas Location Map
11
Figure 7. NAMRIA Calamba Topographical Map
12
Figure 8. Close-up of Site near San Rafael
13
Table 3. Light Industry & Science Park III Profile
In order to cope up with the increase in the demand of food due to population
growth, escalation in productivity of the agricultural sector is required. Through the use
of fertilizers, increasing nutrients necessary for crops to increase yield, speeds up
growth and retain the quality of the crops can be realized. Thus, a fertilizer
manufacturing plant is being developed in order to cope up with increased in demand
in food and reduce reliance to expensive imported fertilizers.
In correlation to the result of market research in the plant design project, it shows
that the fertilizer demand is higher than its supply, thus, reliance to imported fertilizer
14
is necessary to compensate the low production of existing fertilizer plants, not
considering the fact that they also export fertilizers to other countries. The production
capacity of the existing plant in the Philippines is calculated to have about 60,000 MT
of NPK fertilizer annually. But, import capacity exceeded the production capacity by
almost eight times.
Plant Design
The plant will be developed into two sections: the nitric acid production plant and
the fertilizer manufacturing plant. For the nitric acid production process, the Ostwald
process will be utilized with process condition under high pressure. Under this process,
three phases are designed, namely, raw material pre-treatment, ammonia oxidation,
and absorption of NOx in water. Effluent treatment of gas will not be necessary as the
high-pressure process is designed in order to conform to effluent standards provided
by Philippine Clean Air Act or R.A. 8749. There is no wastewater produced under this
process.
The second process involved production of NPK fertilizer using nitric acid produced
from the first plant. Uhde process or the nitrophosphate process will be used in order
to produce NPK fertilizer. It is composed of four phases, digestion of phosphate rock,
crystallization of calcium nitrate tetrahydrate, blending and granulation of NPK fertilizer,
and post-treatment of granulated NPK fertilizer. Negligible gas effluents are produced
by in this process and no solid wastes are also expected. For wastewater, nutrients
are known to be dominant in the effluent. As such, sequential batch reactor will be
used in the process to remove phosphorus and nitrogen from the effluent, thus,
following the government standards for wastewater effluent. The removed nutrients
may be used to be recycled to the plant or disposed it to the upstream of irrigation
system for fields.
Planning principles and design considerations will be combined in the site planning
process whenever possible. The design concepts considered are: efficiency of
15
process, air quality emission conformance, protection of the water quality of the
receiving water, safety of employees, ecological resources and availability of raw
materials and location of the market.
Before the design is prepared, pilot plant will be built in order to determine the
validity of preliminary design and readjust parameters that does not conform from the
data from the pilot plant. After adjustments, revision of the plant design under feasibility
study will be made in order to correct costing and design parameters.
In addition to pilot plant construction, land, water, air characterization will be done
in order to determine the prior conditions of the site and the impact of plant operation
to the plant.
Design will also consider the potential vulnerability of the plants’ structure to natural
hazards such as extreme rainfall and earthquake events. For that, studies will be taken
under detailed engineering design, and the corresponding structural measures and
standards will be integrated in the final design.
For that, relevant engineering standards will be applied to consider natural hazards.
All civil works shall account construction criterial applicable to the observed level of
risk. Disaster risk mitigation shall combine enough elevation for structural foundation
to take into consideration the projected or estimated flood depths; avoidance of area
of known to seismic risks as component locations; and ensuring structural design are
conforming to applicable codes and standards. All of these will be incorporated under
detailed engineering design.
Construction of the plant will be contracted to qualified contractors who will provide
the equipment, manpower, materials and labor. Bid documents shall include
requirements for assimilating pertinent provisions of the environmental management
plan to be executed by the contractors during construction.
16
the terms and conditions of the contract are followed. During trial run, influents and
effluents will be characterized to determine the actual efficiency of the wastewater
treatment facility. Other performance tests, such as leak/hydraulic testing, are also
part of the agreement.
Under the Cultural Properties Preservation Act (Presidential Decree No. 374) when
excavators shall strike upon any buried cultural property, the excavation shall be
suspended and the matter will be reported immediately to the Director of National
Museum who shall take the appropriate steps to have the discovery investigated and
to ensure the proper and safe removal thereof, with the knowledge and consent of the
owner. The suspension can only be lifted by the Director of National Museum.
Accordingly, in case of archaeological, historical, cultural chance finds, the following
procedure would be observed to avoid damage to cultural properties: (i) detailed
design of all civil works will be located away from all cultural/archaeological/historical
properties; (ii) procedures for chance finds of valued relics and cultural values will be
stipulated in the contract with contractors in order to avoid damaging such valuable
properties; (iii) site supervisors will be on the watch for chance finds; (iv) upon a
chance find, all work will be stopped immediately, find will be left untouched, notify
local government units and LISP III officials who in turn will notify the National
Museum; (v) work at the find site will remain suspended until the National Museum
allows work to resume.
Technicians and operators will undertake operation and maintenance of the plant
after undergoing training. Operations and maintenance activities includes monitoring
product quality, raw material quality, monitoring plant operations, raw material and
product inventory, transport of product to market, periodic cleaning and shutdown
planning, replacement of equipment or consumables, monitoring influents and
effluents and inspection of control equipment. Annual scheduled shutdown is done in
order to ensure consistent process operations and reduce potential hazards and
negative impacts to environment. All operations and maintenance activities are to be
done regularly to decrease chances of emergency shutdowns.
17
3.4.4. Abandonment phase
Due to relatively long operational life of the plant, abandonment or closure is not
envision in the near or medium term (25 – 50 years). In case of abandonment
becomes an option, the appropriate action plan will be prepared and executed in
compliance with GOP regulatory requirements.
Project costs can be classified into two: capital investment and annual cost of
production. Capital investment can be further classified into two: fixed capital
investment and working capital. Fixed capital investment is the overall cost of design,
construction and erection of plant and the related modifications necessary to prepare
the plant site. It is composed of inside battery limit, offsite battery limit, engineering
and construction cost, and contingency charges.
Inside battery limit investment is the actual cost of the plant itself. The
procurement and installation cost of all process equipment are part of inside battery
limit investment. Offsite battery limit investment includes all cost required for the
additions made site infrastructure, taking consideration plant expansion, whether
establishing new plants or increasing operating capacity of the existing plant.
Contingency charges are extra cost added to the budget in order to consider errors
in cost estimations and increases flexibility in cost evaluation.
18
The other cost considered in project cost is the cost of production which is
evaluated annually. It also classified into two: variable cost of production and fixed
cost of production. Variable costs of production are costs that heavily depends on the
capacity of the plant and any fluctuation to plant production capacity will in effect
cause variation of costs under variable cost of production. Variable cost of production
includes raw materials cost, utility costs for plant operations and consumable costs
(catalysts). Fixed costs of production involve that are not related to the capacity of
plant production. This includes labor cost, telecommunication cost, real property tax
and income tax, utility costs unrelated to plant operations.
Under manpower requirements, about 120 employees are required in the site
both for office and plant production line.
Number
CEO 1.00
Plant Manager 1.00
19
Accounting Staff 9.00
IT Supervisor 1.00
IT Staff 3.00
Company Nurse 2.00
Driver 6.00
Janitor 6.00
Security Guard 6.00
Total 118.00
Project planning started 2018 and it is expected to end till 2020. From 2020 to
2022, the project enters the construction phase and will be prepared for operation
and maintenance phase. After construction phase, the plant begins operations on
2022. The plant is expected to operate until 2042 but before 2042, top management
will decide whether to consider expansion, build new plant, increase capacity,
abandon/shutdown the plant or do nothing and let it run-to-failure approach.
20
4. BASELINE ENVIRONMENTAL CONDITIONS, IMPACT ASSESSMENT AND
MITIGATION
Land Use
21
Watershed (4,301.32) (15.57)
Pedology
There are seven types of soil that could be found in the area of Batangas City. The
following information tells its type, location and agricultural potentials.
22
Location : Calicanto and Wawa
23
Type of Soil : Ibaan Loam (Gravely Phase)
24
Geology
The region the plant would be erected is located in San Rafael, Batangas. The
area has a low landslide susceptibility. It also has a high flood susceptibility with flood
heights of 1-2 meters in a duration of 3 or more days. The Province is predominantly
Tertiary to Quaternary and largely of igneous and sedimentary rocks.
Geomorphology
Batangas City consists of 0% to 30% rolling terrains in slope. The highest point is
located at Mount Banoy in Barangay Talumpok Silangan that is 968 meters above sea
level and is 13.5 km east of Poblacion. Coastal Barangays starting Sta. Rita Aplaya
from the north down to Ambulong on the south are at 0% to 3% in slope. Beyond the
barangays of Mabacong, Simlong and Pinamucan Ibaba, the slope is from 8% to 30%.
25
The southwest tip of the city which is Matuco Point has a slope of 30%. Verde Island
which is composed of six barangays are mountainous and has a slope ranging from
3% to 30%.
0% – 3% 6,578.80 23.05%
4% – 8% 10,902.83 38.20%
26
Figure 10. Geological Formations of Batangas Province and the Batangas Bay Region.
Terrestrial biology
Scope
This section covers terrestrial investigation of the initial alignments of the proposed
plant location to identify the impacts to ecological conditions that assess the level of
impacts, and propose measures to mitigate these problems.
Mangroves
As of 2010, Batangas has an estimated total mangrove area of 610.94 hectares that
are protected within the last ten years. Batangas has 12 mangrove species and 8
associate species that is being protected by DENR. The species include Avicennia
alba, Avicennia marina, Avicennia officinalis, Bruguiera gymnorrhiza, Bruguiera
sexangula, Ceriops decandra, Ceriops tagal, Excoecaria agallocha, Rhizophora
apiculata, Rhizophora mucronata, Rhizophora stylosa, and Sonneratia alba. As for the
mangrove associate species include Acacia farnesiana, Dolichandrone spathacea,
Hibiscus tiliaceus, Ipomoea pescaprae, Morinda citrifolia, Pongamia pinnata,
Sesuvium portulacastrum, and Terminalia catappa. (Samson 2012).
27
National List of Threatened Fauna
28
4.2. The Water
Hydrology
29
Figure 11. Hydrogeological Map of Batangas City
Water Quality
Water primarily come from Calumpang River, wells and springs. Water source
could be correlated with the Taal Lake that also supplies water for aquaculture and
non-aquaculture in Batangas. Assessment of Water Quality were determined from
August 2013 to May 2014 for 10 months. This includes the pH, nitrates, phosphates,
salinity, total dissolved solids (TDS) and dissolved oxygen (DO).
30
Figure 12. Overview of Taal Lake, Philippines and the water sampling stations
Figure 12 shows the vicinity of the Taal Lake and the surrounding lands it supports
for the use of Batangas City. Measurement of the parameters of water were carried in
situ at the surface and at a depth of 10 m. Water samples were collected and done
from 9 A.M. to 2 P.M. Specialized laboratory equipment were used to measure the
parameters for the water quality with 95% confidence level. Phosphate levels were
reported higher than the standard DENR issued (0.05 -1.0mg/L) recommended Class
C (aquaculture purpose) waters. Nitrates were recorded inside fish cages which
ranged from 1.76 mg/L to 3.69 mg/L and the values were significantly higher than in
non-aquaculture sites. Total Dissolved Solids concentration were above the usual
1000mg/L which freshwater usually have. The pH ranged from 7.5 to 9.14 which were
similar to the findings of Rosana et al. (2008). Salinity was 0.8-.9 ppt, which is uniform
throughout the entire sampling period in the freshwater body.
31
Figure 13. Average values of the physico-chemical parameters of the water in
aquaculture and non-aquaculture sampling stations in Taal Lake from August 2013-
May 2014.
Figure 13 showed the statistical results of the study of water around Taal Lake.
This includes the industrial and aquaculture sectors that primarily affects the Lake’s
water quality.
32
Fresh Water Biology
33
Figure 14. Freshwater Species in Batangas
34
Marine Biology
Table 11 classifies the mammals that were listed in DENR Administrative Order
No. 2004-15. The information states the species and family and its scientific name.
35
4.3. The Air
Meteorology
The region falls under Climate Type I of the modified Corona Classification of
Philippine climate (Flores and Balagot,1963). This is characterized into two seasons
which are wet or rainy and dry. Rainy season lasts for 4 months when the southwest
monsoon prevails and dry season lasts from 3 to 7 months which is depicted in figure
15.
Minimum, maximum and mean temperatures of the city were also conducted and
shown in figure 16.
36
Figure 16. Maximum, mean, and minimum air temperatures
The region has a max. temperature of 29.30 ºC in April and has a steady fall of
temperature by 26 ºC with the driest months from January to April. The average
monthly rainfall is less than 50mm per month.
Air Quality
According to Batangas air quality index and PM2.5 air pollution, the region
experiences Moderate quality that poses little health risk and it is recorded by AirVisual
depicted in Figure 17.
37
Noise
Figure 19 states the Noise Pollution in Batangas has a low value which means that
the air is safe and integrated for industrial and commercial areas affected.
The project site consist mostly of trees and no family are mostly located within the
park. Affected people would be coming from manpower of every companies and some
consumers. For identification and delineate distribution of ecological habitats found
38
within the Project area. Habitat types, including people and animals, were identified
initially by referring to the latest available aerial photographs. Field surveys were
undertaken to ground focusing particularly on those area would be affected by the
proposed development directly. The aerial view is given below:
The toxic chemicals found in fertilizers can be absorbed into the plants and enter
the food chain via vegetables and cereals. However, the largest health risk is when
the chemicals flow into ground water, which is then extracted for drinking. The effect
of products and raw materials utilized by our process is discussion in the Hazard
Identification table along with its mitigation plan in the Environmental Mitigation Plan.
39
5. ENVIRONMENTAL MANAGEMENT PLAN
The production of nitric acid release different NOx compounds from the reaction
of ammonia with air and water and NO. This would have an impact to the production
of regulated gas pollutants by the DENR. Another important thing is the regulation of
release of phosphate and nitrogen as it can cause eutrophication.
NO Controlling Plan
The controlling plan of NO focuses on the utilization of humid air method. In this
method, water vapor is mixed in the combustion air before supplying it to the cylinder.
Air from the T/C blower is passed through a cell that humidifies and chills the hot air
taking moisture from the cooling water until air saturation is achieved. Generally saline
sea water is utilized in this method by heating it with jacket water and turbo charger
heat, and the left-over brine is disposed back to the sea. This method can achieve
reduction of NOx by 70-80%.
Control Strategy
40
Compliance and enforcement programs are also very important to
include. These programs help owners or operators of sources understand the
requirements, as well as the actions that environmental authorities can take if
the sources don’t comply.
Involve the public. Invite input from the regulated community and others,
including the general public when developing the control strategy. This early
consultation reduces later challenges and can help streamline implementation.
Wastewater Treatment
Use of fertilizers: Agricultural practices and the use of fertilizers in the soil
contribute to the accumulation of nutrients
41
Discharge of wastewater into water bodies: In various parts of the world, and
particularly in developing countries, wastewater is discharged directly into
water bodies such as rivers, lakes and seas.
Reduction of self-purification capacity: Over the years, lakes accumulate large
quantities of solid material transported by the water (sediments).
The following activities shall be done by NAPKA Inc. to comply with its
prevention and mitigation:
Controlling release of Nutrient wastewater with the use of PBR along with
maintenance and improvement;
A. Upon discovering Fire or spill of any kind immediately alert all people on site.
If necessary, manually set off alarm.
B. Fire - Fight the fire only if can be done safely
42
C. Spill – If spill can be safely contained, put on proper clean-up clothing and limit
spill
D. Contact Site Emergency Coordinator or alternate to call local Fire Department
(911) Site Emergency Coordinator: Kent Wood
E. Assess the situation (better to overreact where not sure):
Severity – nature, size and extent of the situation
Urgency – potential to escalate quickly
Threat – effects or risk of damage may become significant
Impact – effects to people, the environment, property, or Cavendish
F. At discretion of Site Emergency Coordinator or if unsure, evacuate property to
designated gathering area (Kensington Agri Services office) and perform head
count.
G. Follow Cavendish Agri Emergency Response Tree 8. Upon notification or if
necessary, proceed to begin notifying Emergency Contact List
Continuing Response
Emergency Contacts:
The emergency contacts are based on the most reliable and closest
department in Batangas.
Department Landline
Mayor's Action Center 723-1511 / 723-2930
Fire Department (043) 301-7996
Local Police (043) 725-2125
43
BFP Batangas City 301-7996
(Telefax) 723-7299
Alangilan Substation 702-1973
PNP Batangas City (Office) 723-2030
980-0382
HOTLINES 980-0340
723-7500
Chief of Police 723-2434
Traffic Division 723-2476
Investigation Division 300-0230
Property Division 723-2066
HOSPITALS
Batangas Medical Center 740-8307
St. Patrick’s Hospital & Medical Center (Admitting) 723-1605
(Emergency Room) 723-2387
723-4144
Jesus of Nazareth Hospital (Trunk line) 723-2918
300-3645
(Emergency Room) 723-4608
Golden Gate General Hospital 341-3112
MERALCO - All Departments 723-6432
All Departments 723-6431
Collection 723-3872
Billing 723-1933
National Power Corporation – (National Highway) 723-4357
Bolbok 723-3386
PrimeWater Batangas City 09178966930/09494142633
City Disaster Risk Reduction and Management
702-3902
Office
LTO Batangas City 740-9738
44
For Environmental Spills: (Land/Building)
For the technical and administrative duties that help with Emergency Management
Programs for institutions such as municipalities, private companies, and government
agencies, Emergency Coordinator was hired for the company.
o Take charge and coordinate all activities until the emergency response team
arrive
o Confirm the emergency, determine immediate response, and contact
responders
o Ensure the proper Company contacts and Industrial/Corporate Security are
advised of the emergency as soon as practical. Industrial Security is to be focal
point of information.
o Greet responders and identify hazards and present Emergency Response Plan
o Inform responders of all dangerous and hazardous materials, where they are,
and how much there is.
o Responsible for designating someone to inform surrounding
homes/businesses
o Responsible for ensuring no visitors, deliveries, public or media enter the site
o Responsible for giving the “All Clear” to employees
o Responsible for completing the Internal and External Incident reports complete
with pictures and timelines.
45
Emergency Showers Process Rooms Emergency Box
Respirators Laboratories
Safety Glasses Process Rooms Emergency Box
Rubber Gloves Process Rooms Emergency Box
Emergency Lightings Process Rooms Emergency Box
Flashlights Process Rooms Emergency Box
2. Ensure everyone involved in clean-up has reviewed MSDS, wear proper PPE
4. Rope off the affected area and do not let anyone inside without reviewing MSDS. This
includes Fire and Police departments, Contractors, etc.
5. Any exposure should be treated immediately. Paramedics must be made aware of that
they are dealing with.
6. If spill enters water, ditch, drain, or manhole, immediately notify local Environmental
Agency.
If Liquid Spill:
If Solid Spill:
o Do not spray with water even to control dust and air-born material
o If wind is a factor cover with a tarp Decontamination:
o Use manufacturers suggested methods of decontaminating the area once
clean-up complete. This may include Clorox or soda ash.
o Be prepared to repeat contamination procedures 2-3 times.
46
Response Training Test
All Employees of NAPKA Inc. are to review the Company Safety Manual and
are required to use this document as a reference as required. The NAPKA Inc.
Safety Manual in located on the company intranet site.
47
Abandonment/Decommissioning/Rehabilitation Policies and Generic
Guidelines
It is expected the life capacity of the proposed facility will be a minimum of 20 years.
At some point it is understood the proposed facility will be decommissioned at the end
of its service life. At that time the site will be decommissioned in accordance with the
applicable standards, guidelines and regulations for that period.
During the construction period of NAPKA Inc, project manager will conduct regular
environmental monitoring site inspections to ensure all construction components
adhere to the provincial and federal regulations and codes as well as the
procedures/controls outlined in the contractors Environmental Protection Plan.
Self-Monitoring Plan
48
General risk assessment concludes that we are at risk of experiencing several
unwanted events. These include:
o Fire
o Major Injury
o Chemical Spills
o Theft
o Natural Disasters
o Vandalism
Self-monitoring data can provide a basis for verification of compliance with legal
requirements and enforcement, and for calculation of environmental or administrative
charges. They also help to optimize national, regional, and local ambient monitoring
systems, and establish priorities for inspection. For the regulated community, reliable
data on emissions, and the environmental impact of their production, can be significant
from an economic viewpoint. For example, such data can help to better identify and
reduce environment-related costs (that can be as high as 30 per cent of operational
costs in some branches), and minimise environmental liabilities. Disclosure of facility-
specific data and their comparison between enterprises within the same industrial
sector, or with international benchmarks, can further indicate where cost-savings are
possible. Furthermore, access to other companies’ facility-specific data can build trust
within industries that the government is targeting to ensure a level playing field.
Hazard Identification
These items are listed at their planned peak quantity and may not exist at this site
at all times or at these levels. The exact location can be found in the Site Plan. A complete
Chemical inventory listing is attached.
49
Raw Material/Product Quantity in MT per year Hazard
Ammonia 11,542 decompose at high
temperatures forming very
flammable hydrogen and
toxic nitrogen dioxide
Phosphate Rock 30,392 Negligible fire hazard when
exposed to heat or flame.
Thermal decomposition
may release
toxic/hazardous gases.
50
Eye contact: may cause
irritation in case of
prolonged or repeated
contact Ingestion
Confined Spaces
51
Containment Plan
o Safely stop the leak or spill from continuing, use sandbags or dike if
required
o Review the MSDS sheet
o Under no circumstances is a spill to be washed off pavement, road or
property with water into a drain, knowingly or unknowingly.
The framework of the Monitoring and Evaluation (M&E) system in NAPKA Inc. is
structured to include Impact, Outcome, Output, Process and Input Assessments. The
national M&E system will monitor impact, outcome and some output while the
programmatic monitoring will include some outcome, process and input monitoring.
We specifically assessed 5 component strategies which includes:
Component 2: Prevention
Hydrology Monitoring
Local hydrology shall be regularly monitored during the span of the project. Long-
term monitoring is necessary to ensure minimum impacts on the bodies of waters. For
surface waters such as rivers the following are the variables for monitoring:
Toxicity
BOD
pH
TSS
52
Volume Discharge Existing use of river systems at drainage outfalls should be
noted to determine the possible sources of anthropogenic pollutants.
The hydrology at siltation sections and pollution point sources should also be
appraised. The following techniques of intermittent monitoring can be considered:
53
In general, the description of the ELV in the permit (in terms of, e.g., total amount
and peaks) is the basis for setting up the monitoring timing requirements. These
requirements and associated compliance monitoring must be clearly defined and indicated
in the permit so as to avoid ambiguity. The monitoring timing requirements expressed in
the permit mostly depend on the type of process and more specifically on the emission
patterns. When the emission is subject to random or systematic variations, statistical
parameters including means, standard deviations, maxima, and minima provide only
estimates of the true values. In general, the uncertainty decreases as the number of
samples increases. The magnitude and duration of changes may determine the monitoring
timing requirements. The determination of the timing requirements (time, averaging time,
frequency, etc.) for ELVs and related monitoring also needs to take into account the
following factors:
Nutrient waste
Sediment
Hazardous elements
Water biology, bacteriology and inorganic constituents
Species survival
Atmosphere Monitoring
Suspended particles, odor, noise level, gas and wind direction and velocity, and
gaseous emissions are the parameters pertaining to atmospheric condition to be
evaluated quarterly in designated monitoring stations. Monitoring may be done using
visual inspection.
54
Emission factors
Emission factors are generally derived through the testing of certain process
equipment (e.g. boilers using a particular fuel type). This information can be used to relate
the quantity of material emitted to some general measure of the scale of activity (e.g. for
boilers, emission factors are generally based on the quantity of fuel consumed or the
energy content of the fuel fed into the boiler). In the absence of other information, the
literature values of emission factors can be used to provide an estimate of the emissions.
Emission factors require “activity data”, which are combined with the emission factor to
generate the emission estimates. The formula for calculation of emissions is the following
Anthropological Concerns
People’s activities and attitudes are the controllable parameters to avert bodies of
water degradation and depletion of the resources. The following are people-centered
interests and activities where water and environmental resource soundness depend:
55
Project Monitoring and Evaluation
Reporting Requirement
56
Environmental Guarantee and Monitoring Fund Commitment
NAPKA’s operational policies and guidelines are tailored towards the need to
timely and appropriately meet the needs, wants and requirements of DENR while
managing inherent risks effectively. To this end, NAPKA always strives to ensure that
its products and services are always relevant. NAPKA’s operations in this regard have
a DENR Orientation and are anchored on sound and efficient credit processes.
NAPKA uses Fund & Portfolio Monitoring app for fund monitoring. 4 features of
fund monitoring were included in such app which gives end user the ability to analyze
all key financial, operational and performance data of the fund. The model produces
key statistics such as ROI, DPI, TPVI, and IRR for underlying funds’ investments and
their portfolio companies / properties. Listed below are the 4 features of such
application:
Analyze key metrics over time for all General Partners Covered (i.e.
Commitment, Unfunded Commitment, Contributions, Distributions, NAV, TVPI,
DPI, RVPI)
View key portfolio company statistics over time (Shares Outstanding, Cost,
Market Value, etc.)
4. Cross-Functional Collaboration
Front office team can track financial metrics, relationship information, and static
data
57
Operations, Finance and Accounting can pierce through data to deliver rapid
requests to other stakeholders (i.e. Compliance, Investors, Management, Front
Office)
During the operation of the project, the office designated to handle the operation
and maintenance shall be responsible in ensuring that provisions stipulated in the ECC
and the EMP are followed. To ensure the effective environmental management of the
project, all participating parties must know their responsibilities related to the
protection of environmental, biological, and socioeconomic resources and be
committed in implementing appropriate measures to fulfill these responsibilities.
The establishment of yet another new body should always be avoided if possible.
Existing institutional arrangements are not providing the degree of co-ordination and
integration needed for the proper environmental management of NAPKA Inc and its
process. In the circumstances, the study proposes establishment of a body referred to
as a “Conservancy”, which is a recognized forum of stakeholders and a body that can
execute the decisions of the forum. The main strategy of the Institutional Plan is thus
“establishment of a Conservancy”.
The agency (DPWH) shall closely coordinate with the contractor to ensure that
provisions in the environmental program are effectively implemented. Regular inspection
of the working area shall be conducted. During the operation of the project, the office
designated to handle the operation and maintenance shall be responsible in ensuring that
provisions stipulated in the ECC and the EMP are followed. To ensure the effective
environmental management of the project, all participating parties must know their
responsibilities related to the protection of environmental, biological, and socioeconomic
resources and be committed in implementing appropriate measures to fulfill these
responsibilities. The Contractor’s plan to minimize construction impacts to the environment
must include the following:
Engineering Works
58
• Evaluation works during the dry months of the year. The contractor must adjust the
time schedules in order to harmonize with the climate of the are as this will affect
the quality of fertilizer
• Provision of a safe and healthy workplace that must be equipped with proper
sanitation systems for the workers. I-94 JICA CTI Engineering International Co.,
Ltd.
• Drafting a waste management plan for the camp and whole construction area.
The committee would meet frequently (perhaps monthly) and would direct the work
of the executive. Apart from guiding the regular management of NAPKA Inc, such a
59
forum would clearly facilitate dialogue on major planning issues, which in the past has
been lacking.
60
6. BIBLIOGRAPHY/REFERENCES
2004 statistics on Philippine protected areas and wildlife resources. (2004). Quezon City:
AirVisual | Air quality information you can trust. (n.d.). Retrieved from
https://www.airvisual.com/
G The state of water resources in the Philippines - Greenpeace. (n.d.). Retrieved from
http://www.greenpeace.org/seasia/ph/Global/seasia/report/2007/10/the-state-of-water-in-
the-phil.pdf
http://www.jebas.org/
Mines and Geosciences Bureau Regional Office IV-A - Geosciences Division, 8/F DENR
by the Bay Building 1515, Roxas Blvd., Ermita, Manila (2019). (n.d.). Retrieved from
https://www.govserv.org/PH/Manila/1672064089731897/Mines-and-Geosciences-
Bureau-Regional-Office-IV-A---Geosciences-Division
National Fisheries Research and Development Institute ... (n.d.). Retrieved from
http://www.nfrdi.da.gov.ph/
Physical & Geographical Aspects | Welcome to Batangas City. (n.d.). Retrieved from
http://batangascity.gov.ph/bats2/?page_id=129
61
Revised Procedural Manual DAO 03-30. (2016). Retrieved from http://eia.emb.gov.ph/wp-
content/uploads/2016/06/Revised-Procedural-Manual-DAO-03-30.pdf
Sustainable Development of the Seas of East Asia through Meaningful Partnerships. (n.d.).
http://www.maplandia.com/philippines/region-4/batangas/batangas/
62
7. ANNEXES
63