Beruflich Dokumente
Kultur Dokumente
A0552 – Rajashree #3
Contents
1 Introduction .................................................................................... 4
2 Safety .............................................................................................. 5
4 Prerequisite .................................................................................... 6
4.1 Delivery of IKN Supply and Unloading .......................................................6
4.2 Warehouse, Storage Area and Pre-assembly Area ...................................6
4.3 Dismantling and Demolition of Existing Equipment ...................................7
4.4 Cooler Centre Line and IKN Base Line ......................................................7
4.5 Loads to be Moved and/or Lifted ................................................................7
4.6 Monorail ......................................................................................................8
4.7 Manpower, Equipment and Tools ..............................................................9
4.7.1 Manpower ...................................................................................9
4.7.2 Equipment .................................................................................10
4.7.3 Tools .........................................................................................10
4.7.4 Consumables ............................................................................12
A0552_016_0000_H2_001_D_B_GUIDELINE.D
09.04.2014 Page 1 of 52
OCX
8.8 AG 8000: Electrical Work (Outside IKN Supply and Responsibility) ........33
8.9 AG 0600: Kiln Hood ..................................................................................34
8.10 Dep. 15 AG 0760: Kiln Outlet Seal ...........................................................35
9 Tolerances .................................................................................... 37
Tables
Table 1. Assembly Group Overview .........................................................................6
Illustrations
Fig. 1. Monorails Attached to the Concrete Girders of the Burner Floor ...............8
Fig. 2. Monorail and Hoist Installed Inside Existing Cooler Housing .....................9
Fig. 16. Alignment of the Drive Reaction Buttress with the Distance Gauge ........26
A0552_016_0000_H2_001_D_B_GUIDELINE.D
09.04.2014 Page 2 of 52
OCX
Fig. 19. Assembly of the Wear Spacers, Outer Boards and Wear Boards ...........29
A0552_016_0000_H2_001_D_B_GUIDELINE.D
09.04.2014 Page 3 of 52
OCX
Project details
Production Capacity 5.300 tpd
Cement Plant RAJASHREE CEMENT WORKS
Location Rajashree
Purchaser Ultratech Cement Limited
Contract Number 95070_016_0000_S2_000_N_H
1 Introduction
This installation guideline specifies necessary services for the installation of an IKN
Pendulum Cooler in terms of basic information in a key-worded and summarized way.
Additionally it gives proposals for the execution of works and activities beyond IKN‟s
responsibilities.
This document describes the necessary workload, items for the mechanical
installation of the IKN pendulum cooler and refractory work (outside IKN‟s scope). A
list of preparations for the cold and hot commissioning can be found in this document
as well, whereas the range of the electrical installations is not included.
The sequence of steps indicated in this guideline for installation is subject to revision
and may be altered by the IKN supervisor according to local conditions and/or on the
completion of interfaces. The work and activities are described generally and are
based on the experience gained with previous installations. Individual pre-conditions
and necessary details should be verified by the installation company through an
advance inspection on site. Special attention should be paid to site access and rigging
options.
The selection of a suitable installation company and the delegation of work tasks is the
responsibility of the customer. The major items subject to the cooler installation and
installation works are:
A0552_016_0000_H2_001_D_B_GUIDELINE.D
09.04.2014 Page 4 of 52
OCX
During the whole installation period the contractor must provide sufficient manpower
with regard to number and skill level.
All site assembly, installation and modification works must be of good workmanship
and in accordance with IKN‟s high quality standards. All work will be executed under
continuous supervision of an IKN supervisor.
2 Safety
Please refer to the Operation and Maintenance Manual for safety instructions.
3 IKN Glossary
Assembly
Assembly Group (AG) Description
Group No.
0000 General assembly
0100 Sealing
0200 Air ducts, cooling fans
0300 Heat shield
0500 Air beams, Coanda nozzles
0600 Kiln hood
0700 Kiln outlet seal
1000 Mobile grate structure
1100 Fixed grate structure
1300 Crusher
1400 Hydraulics
1600 TDE
1700 Clinker discharge
1800 Cooler housing including doors (AG 1900)
2000 Platforms, stairs
5000 Foundations
5900 Refractory
7000 Pneumatics, air blowing units
8000 Electrical equipment
9000 Water injection
9900 Spare parts
A0552_016_0000_H2_001_D_B_GUIDELINE.D
09.04.2014 Page 5 of 52
OCX
Table 1. Assembly Group Overview
All IKN cooler assembly group layout and sub-assembly layout drawings are
numbered with an 18 string alpha-numeric code which has the following format:
A0XXXxxx(Dep)xxxx(AGN)------(sequential number).
the assembly group number (AGN) – 0000 for the general layout of the cooler,
0100 for sealing, and so on.
The IKN cooler general assembly drawings are numbered with an 18 string alpha-
numeric code, which has the following format: M1xx(DEP)xx(AGN)xx00(SUB)--------
(sequential number).
Drawings are sorted into their respective assembly groups in the drawing list included
in the document: A0XXX_016_0000_H9_001_D_A_Drawings_Parts_Lists.
4 Prerequisite
4.1 Delivery of IKN Supply and Unloading
The overseas parts of the IKN Pendulum Cooler equipment will be delivered by truck
transport in 40' standard or high cube containers. To ease unloading it is
recommended to have an unloading ramp available or to place the containers on even
ground. The packing list will indicate a colli numbering from 1 - 6 corresponding to the
"sequence of installation", i.e. the colli marked with No. 1 contain the parts and
equipment that will be needed first for the cooler installation. Then all colli showing No.
2 will be needed and so on. This identification must be considered for the storage of
the goods. Easy access should be given at any time. It should generally be possible to
reach and unpack any colli or container, also by rearranging the storage pattern if
necessary.
A covered warehouse area of approx. 150 m² is required for the storage of the IKN
hydraulic and electrical equipment; please refer to the IKN packing list for the storage
instructions.
A0552_016_0000_H2_001_D_B_GUIDELINE.D
09.04.2014 Page 6 of 52
OCX
A storage area of approx. 1000 m² has to be made available for the IKN supply portion
and a pre-assembly area of about 300 m², directly at the site. A short and
unobstructed access route from the warehouse and storage area(s) to the
construction site must be ensured.
A storage container with installed shelves (ideally a 40‟ container) should be placed in
the direct vicinity of the cooler construction site, preferably in a shady area. This
container will be needed to store small parts (bolts, nuts, etc.) in order to have them
well-sorted and quickly available. The IKN supervisor will determine which packages
will be unpacked for this purpose.
The equipment that must be dismantled includes the existing cooler grate, grate drive,
crusher, discharge chutes, fans and auxiliary equipment. The demolition work includes
predetermined parts of the cooler housing and hoppers and the existing crusher and
fan foundations. The scope and time frame of dismantling and demolition remains the
responsibility of the customer.
The centre lines or reference lines must be made clearly visible by means of marked
embedded or bolted steel plates, imprints or colour marks at the beginning and at the
end of the cooler building or installation area. For pre-assembly and final installation of
the IKN Clinker Cooler, the IKN base line or equivalent must be marked the same way
and according to the layout ("no marks = no starts"). This applies for the pre-assembly
and the final installation period.
During the assembly and installation works, individual parts with a weight of up to 10 t
and pre-assembled components with a weight of up to 40 t will have to be moved
and/or lifted.
A0552_016_0000_H2_001_D_B_GUIDELINE.D
09.04.2014 Page 7 of 52
OCX
Fig. 1. Monorails Attached to the Concrete Girders of the Burner Floor
4.6 Monorail
A0552_016_0000_H2_001_D_B_GUIDELINE.D
09.04.2014 Page 8 of 52
OCX
Fig. 2. Monorail and Hoist Installed Inside Existing Cooler Housing
The size of the construction teams, parts and materials as listed below are exemplary
for the mechanical installation of an IKN Pendulum Cooler, but do not replace or limit
the manpower requirements, standard tools and equipment for construction and
installation works in general. Items and manpower must be made available as soon as
needed respectively on short notice.
4.7.1 Manpower
Based on the assumption that the work crews will consist of qualified millwright fitters
the following minimum team sizes are recommended for the pre-assembly and
installation of the clinker cooler:
installation (two shifts): 16 fitters per shift (including at least 6 fitters with all
welding certificates up to 4G for structural welding)
during certain phases of the installation work, especially after completion of the
upper and lower cooler housing, it will be necessary to have at least 5 dedicated
welders available per shift in addition to the installation team
A0552_016_0000_H2_001_D_B_GUIDELINE.D
09.04.2014 Page 9 of 52
OCX
4.7.2 Equipment
monorails – refer to IKN layout drawings for required locations and capacity
chain blocks @ 5 t
chain blocks @ 10 t
plumbs and 100 m of steel wire ø1 mm
4.7.3 Tools
pick hammers
A0552_016_0000_H2_001_D_B_GUIDELINE.D
09.04.2014 Page 10 of 52
OCX
electric impact wrenches driver (17…36 mm)
isolating transformers
grab trolleys (3 t/10 m) with metal rope
sling bands (4 t, 1 m)
sling bands(4 t, 2 m)
shackles (A1.6)
shackles (A2.5)
crowbars (1.5 m)
torque wrench (10…120 Nm, 400 Nm, 730 Nm und 1100 Nm)
handspikes (0.5 m)
pipe wrench
hammers (1 kg)
levels (0.5 m)
A0552_016_0000_H2_001_D_B_GUIDELINE.D
09.04.2014 Page 11 of 52
OCX
4.7.4 Consumables
normal concrete
non-shrinking concrete for grouting
oxygen
acetylene
shielding gas
compressed air
supply of personal safety equipment, e.g. gloves or glasses, are outside IKN
responsibility.
The complete foundation work has to be finished and checked prior to the start of the
mechanical installation.
foundations
embedded base plates
A0552_016_0000_H2_001_D_B_GUIDELINE.D
09.04.2014 Page 12 of 52
OCX
5.1 Cooler Level Foundation
preparation (cleaning of parts and area, removal of possible obstacles etc.) of the
foundation area for the mechanical installation.
building of hydraulic room, openings for doors, ventilation and pipe outlets
according to IKN drawings
installation of the foundations including oil resistant basin and embedded steel
frame for the power pack unit as shown in the corresponding drawing
preparation (cleaning of parts and area, removal of possible obstacles etc.) of the
foundation area for the mechanical installation.
A0552_016_0000_H2_001_D_B_GUIDELINE.D
09.04.2014 Page 13 of 52
OCX
6 Pre-assembly Activities
6.1 AG 0500: KIDS
pre-assemble the support frame and check the level accuracy with an optical level
mount and align the side and centre supports of the KIDS onto the support frame
mount the air beams onto the side supports and tighten the connecting bolts after
checking the level
install three Coanda nozzles (left, middle and right) on each air beam to check the
alignment of the beams
push the support plates of the centre support upwards until they touch the air
beams and weld according to the drawing
mount the distribution air ducts under the KIDS air beams
mount the Coanda nozzles and thermocouples onto the air beams
A0552_016_0000_H2_001_D_B_GUIDELINE.D
09.04.2014 Page 14 of 52
OCX
Fig. 4. Installation of Pre-assembled KIDS
A0552_016_0000_H2_001_D_B_GUIDELINE.D
09.04.2014 Page 15 of 52
OCX
6.2 AG 0500: Triple Packs
mount two fixed and one movable air beam on the pre-assembly stand
install the bridge plates, the lifting lugs and the brackets on the fixed air beams
pre-assemble air ducts, fans including compensators and silencers (apply sealing
cord for flange connections).
align crusher housing according to markings and pins and weld only lower
crusher side walls
A0552_016_0000_H2_001_D_B_GUIDELINE.D
09.04.2014 Page 16 of 52
OCX
Fig. 6. Pre-assembly Crusher Casing
depending on lifting capabilities take out crusher rollers for final installation
pre-assemble upper and lower sealing frames.
A0552_016_0000_H2_001_D_B_GUIDELINE.D
09.04.2014 Page 17 of 52
OCX
6.5 AG 1000: LPS Units
place opposite LPS units on even ground and insert pendulum beam
pin pendulum beam to spring plates of LPS and fix into center position with
mounting plate.
A0552_016_0000_H2_001_D_B_GUIDELINE.D
09.04.2014 Page 18 of 52
OCX
6.6 AG 1400: Hydraulic Power Pack (HPP)
position oil pan for the HPP inside hydraulic room, align and fix to ground with
anchors
place the HPP onto the oil pan, align and bolt to oil pan
place the local control board of the hydraulic drive and fix into place
A0552_016_0000_H2_001_D_B_GUIDELINE.D
09.04.2014 Page 19 of 52
OCX
Fig. 9. Pipe-Flaring Machine
mount and connect the piping between the HPP up to the cooler inlet, use pipe
flaring machine (IKN supply) where applicable, some pipes may have to be
welded
7 Shutdown Activities
7.1 Demolition Work (Outside IKN Responsibility)
safety platform within the cooler throat will be necessary in case work on the kiln
and the cooler are carried out at the same time at the same time
A0552_016_0000_H2_001_D_B_GUIDELINE.D
09.04.2014 Page 20 of 52
OCX
7.1.1 Refractory Demolition Work (Outside IKN Responsibility)
partially remove the cooler refractory on the side walls for installation of the new
grate system
A0552_016_0000_H2_001_D_B_GUIDELINE.D
09.04.2014 Page 21 of 52
OCX
7.1.2 Existing Cooler Including Grate and Fans
remove existing cooler grate, including grate system, sealing, compartment walls,
drive units and support structure
cut openings into lower cooler housing for grate suspension units (LPS within
existing housing) and new air ducts
cut openings into lower cooler housing for new grate drive
A0552_016_0000_H2_001_D_B_GUIDELINE.D
09.04.2014 Page 22 of 52
OCX
Fig. 12. Opening for LPS Units
8 Installation Work
8.1 AG 1800: Cooler Housing Including Doors and Inspection Ports
position lower part of compartment walls, align and weld to support beams
respectively fix to the concrete with stud anchors
assemble and install cooler housing front walls, drive reaction buttress and cooler
inlet roof
assemble and install segments of lower cooler housing for cooler housing
modification
close lower cooler housing at back by inserting back wall
position panels of upper cooler housing for cooler housing modification, align and
tack weld
after installation of LPS stands, weld lower cooler housing airtight – inside and
outside
weld the upper cooler housing airtight – inside and outside
A0552_016_0000_H2_001_D_B_GUIDELINE.D
09.04.2014 Page 23 of 52
OCX
mount all doors and inspection ports
A0552_016_0000_H2_001_D_B_GUIDELINE.D
09.04.2014 Page 24 of 52
OCX
8.2 AG 1000: Movable Structure
the support stands for the LPS units need to be installed prior to the installation of
the mobile structure
lift the LPS units into the cooler through openings in the housing and position
them on the support stands
align the LPS units in the centre position and fix the position with the mounting
plate
align and adjust the LPS with the total station together with the IKN supervisor
and secure the position by tightening the temporary jack bolts.
A0552_016_0000_H2_001_D_B_GUIDELINE.D
09.04.2014 Page 25 of 52
OCX
Fig. 15. Integrated LPS-Stands
mount the fork flange on the drive reaction buttress using the adjusting sleeves
and the distance gauge for alignment
Fig. 16. Alignment of the Drive Reaction Buttress with the Distance Gauge
A0552_016_0000_H2_001_D_B_GUIDELINE.D
09.04.2014 Page 26 of 52
OCX
Fig. 17. Installation of the Drive Yoke
after alignment fix the movable structure in the centre position, tighten the bolts
with the correct torque and weld according to the drawing
fit and align the membrane housing of the hydraulic drive to the cooler front wall
A0552_016_0000_H2_001_D_B_GUIDELINE.D
09.04.2014 Page 27 of 52
OCX
install the sealing, cover plates and inspection ports at the LPS units
install the upper part of each compartment wall around the movable frame
mount the guide rollers under the pendulum beams at each LPS unit
position the side support beams of the fixed structure inside the cooler
equip the fixed air beam consoles of the first and last triple pack along the length
of each side support beam with the conical alignment washers
bolt the side supports of the fixed structure to the first and last triple pack along
the length of each side support beam
mount the support brackets under the fixed side support beams and weld them to
the lower cooler housing
attach the compartment wall supports to the side support beams, cut to length,
align and weld to the compartment wall
replace the conical alignment washers in the fixed air beam consoles with the
normal washers and tighten all the bolts with 390Nm
A0552_016_0000_H2_001_D_B_GUIDELINE.D
09.04.2014 Page 28 of 52
OCX
Fig. 19. Assembly of the Wear Spacers, Outer Boards and Wear Boards
A0552_016_0000_H2_001_D_B_GUIDELINE.D
09.04.2014 Page 29 of 52
OCX
mount the sealing between KIDS and cooler grate
fit the side sealing plates along the sides of the cooler grate
set the clearance of the labyrinth seals around the longitudinal beams of the
mobile frame
fit and weld the upper parts of the compartment walls and weld air tight
position and weld the lower sealing frame on the crusher base frame
assemble and weld the lower crusher housing in maintenance position on the rails
A0552_016_0000_H2_001_D_B_GUIDELINE.D
09.04.2014 Page 30 of 52
OCX
Fig. 22. Crusher in Maintenance Position
A0552_016_0000_H2_001_D_B_GUIDELINE.D
09.04.2014 Page 31 of 52
OCX
align the upper sealing frame and weld it to the crusher bridge
install the air ducts of the fans including compensator (apply silicone and sealing
cord for flange connections)
place all the fans into position on shims and align with the air ducts
install all heat-resistant expansion jet nozzles and the pipes through the cooler
housing, close openings with cover plates
weld the flanges to the blow pipes
A0552_016_0000_H2_001_D_B_GUIDELINE.D
09.04.2014 Page 32 of 52
OCX
Fig. 25. Heat-Resistant Expansion Jet Nozzles
install cables and connect all drives, instruments, distribution cabinets, etc.
install direct telephone line for the modem or prepare a network connection for
internet access
A0552_016_0000_H2_001_D_B_GUIDELINE.D
09.04.2014 Page 33 of 52
OCX
8.9 AG 0600: Kiln Hood
Depending on the available lifting equipment and the site conditions, the kiln hood can
be lifted into position fully assembled. However, this is not recommended for
completely new installations. The following describes the sequence, if lifted into place.
The assembly sequence in general is the same if the kiln hood is installed in its final
position.
Install inspection ports and prepare kiln hood door for assembly
Weld hood segments air tight - do not weld arch segments around opening for kiln
insert point, since kiln will be installed after hood installation
A0552_016_0000_H2_001_D_B_GUIDELINE.D
09.04.2014 Page 34 of 52
OCX
8.10 Dep. 15 AG 0760: Kiln Outlet Seal
Install mounting ring on the kiln hood
A0552_016_0000_H2_001_D_B_GUIDELINE.D
09.04.2014 Page 35 of 52
OCX
Fig. 28. Seal Direction
A0552_016_0000_H2_001_D_B_GUIDELINE.D
09.04.2014 Page 36 of 52
OCX
Fig. 30. Incorrectly Installed Sealing Lamellas
9 Tolerances
Where levelling of equipment is required, IKN has foreseen adjustment bolts or shims
for easy alignment. The reference for any installation work will be the movable
structure which will be aligned together with the IKN supervisor by using a Leica total
station. Alignment work of the movable structure first becomes necessary for the units
consisting of LPS stands with their pendulum cross beams. The LPS units are
designed for alignment via adjustment bolts. The equipment of the movable structure
is prepared for the temporary insertion of prisms which are reference points for the
alignment by means of a Leica total station. The movable structure was furthermore
completely pre-assembled at the workshop and was there prepared with pins as far as
possible.
Following the complete alignment of the movable structure, the movable air beams will
be installed onto the saddles that are located on the movable beams. Contact
surfaces on the air beams and movable beams are machined. For this reason, only
the position to the centre line needs to be confirmed to be +/- 1 mm since the movable
air beams are the reference for the installation of the fixed structure. Tolerances as
above apply.
The fixed air beams will be mounted, with shims for height adjustment, on the fixed
structure and need to be aligned with the movable air beams. This is done with the
IKN alignment tool. The alignment tool has a mechanical bed stop for reference.
The alignment of the buttress fork flanges for the hydraulic cylinders has to be carried
out with the distance gauges and a high-accuracy spirit level (machine level).
A0552_016_0000_H2_001_D_B_GUIDELINE.D
09.04.2014 Page 37 of 52
OCX
The boxes of the Coanda nozzles need to be installed parallel to each other. The
overall width of each row as well as the clearance against the next row must be
+/-1 mm.
The remaining installation of the sealing, crusher, housing segments, air ducts, etc.
are all relative to the grate structure and may require minor adjustment in order to limit
the overall alignment work. The air ducts of the cooling fans contain necessary loose
flanges to compensate any difference between the fan position and the position of
connection to the housing.
The installation of the remaining cooler equipment has to be of good workmanship and
according to IKN‟s high quality standards.
A0552_016_0000_H2_001_D_B_GUIDELINE.D
09.04.2014 Page 38 of 52
OCX
10 Preparations for Cold Commissioning
In order to make sure that the cooler is ready for cold commissioning, a set of photos
should be sent to the IKN service department (service@ikn.eu). The following should
be visible on these photos:
hydraulic power pack
hydraulic cylinder
main electrical cabinet (CGS) from inside and outside
if applicable, inside and outside views of local boards and terminal boxes supplied
by IKN, but not mentioned above.
The following must be available before arrival of the IKN commissioning engineer:
hydraulic oil to fill the tank, type and quantity according to the specification
included in the IKN manual*
grease for the roller crusher bearings, type and quantity according to the
specification included in the IKN manual*
cooling water, type and quantity according to the specification included in the IKN
manual* (if applicable)
nitrogen gas to fill the accumulator tanks, quantity according to the specification
included in the IKN manual*
electrical power
clean, dry compressed air for the air blowing units and the heat shield, in case
installed the latter
All cable connections as shown in the IKN wiring diagrams must have been
completed. Filling of hydraulic oil and nitrogen gas into the respective tanks should
only be done in the presence of the IKN engineer. Communication between the IKN
PLC and the plant control system must have been established and running. The
cooler grate must be clear of scaffolding and obstructions and completely clean after
completion of the refractory work.
* Please see the “Introduction” section of the IKN operation and maintenance manual.
A0552_016_0000_H2_001_D_B_GUIDELINE.D
09.04.2014 Page 39 of 52
OCX
11 Preparations for Hot Commissioning
In order to make sure that the cooler is ready for hot commissioning, the following
points should be fulfilled:
Cooling fans:
tables for grate speed and fan flow set points should be prepared. Please see the
section „Interlocks‟ of the IKN Operation and Maintenance Manual.
IKN Grate:
the cooler grate needs to be completely clean for the final inspection and fan test
run before start-up.
A0552_016_0000_H2_001_D_B_GUIDELINE.D
09.04.2014 Page 40 of 52
OCX
12 3D Views (example)
A0552_016_0000_H2_001_D_B_GUIDELINE.D
09.04.2014 Page 41 of 52
OCX
Fig. 32. AG002 Air Ducts
A0552_016_0000_H2_001_D_B_GUIDELINE.D
09.04.2014 Page 42 of 52
OCX
Fig. 33. AG007 Dust Pipe
A0552_016_0000_H2_001_D_B_GUIDELINE.D
09.04.2014 Page 43 of 52
OCX
Fig. 34. AG011 Fixed Grate Structure
A0552_016_0000_H2_001_D_B_GUIDELINE.D
09.04.2014 Page 44 of 52
OCX
Fig. 35. AG013 Roller Crusher
A0552_016_0000_H2_001_D_B_GUIDELINE.D
09.04.2014 Page 45 of 52
OCX
Fig. 36. AG014 Hydraulics
A0552_016_0000_H2_001_D_B_GUIDELINE.D
09.04.2014 Page 46 of 52
OCX
Fig. 37. AG016 TDE
A0552_016_0000_H2_001_D_B_GUIDELINE.D
09.04.2014 Page 47 of 52
OCX
Fig. 38. AG017 Clinker Discharge
A0552_016_0000_H2_001_D_B_GUIDELINE.D
09.04.2014 Page 48 of 52
OCX
Fig. 39. AG018 Cooler Housing
A0552_016_0000_H2_001_D_B_GUIDELINE.D
09.04.2014 Page 49 of 52
OCX
Fig. 40. AG020 Platforms and Stairs
A0552_016_0000_H2_001_D_B_GUIDELINE.D
09.04.2014 Page 50 of 52
OCX
Fig. 41. AG050 Foundations
A0552_016_0000_H2_001_D_B_GUIDELINE.D
09.04.2014 Page 51 of 52
OCX
Fig. 42. AG070 Air Blower Unit
A0552_016_0000_H2_001_D_B_GUIDELINE.D
09.04.2014 Page 52 of 52
OCX