Beruflich Dokumente
Kultur Dokumente
Foundations
17.1. General Standard Specifications. This approach differs from
17.2. Structural Foundation Engineering that for superstructures, where a common safety level
Report has been selected for all superstructure types.
17.3. Footings and Caps
17.4. Driven Piles Historically, the primary cause of bridge collapse has
17.5. Drilled Shafts been the scouring of in-situ materials. Accordingly,
17.6. Lateral Loading of Deep Foundation the LRFD Specifications contain a variety of strict
Elements provisions for scour protection, which may result in
deeper foundations.
17.1. General
17.1.2. LRFD Resistance Factors for
A critical consideration for the satisfactory Foundations
performance of any structure is the proper selection LRFD Article 10.5.5.1 presents resistance factors for
and design of a foundation that will provide adequate the Service limit states, which are typically 1.0.
support. This chapter discusses Alaska-specific LRFD Articles 10.5.5.2.2, 10.5.5.2.3, and 10.5.5.2.4,
criteria that supplement Section 10 of the LRFD present resistance factors for the Strength limit state
Specifications for the design of spread footings, driven for spread footings, driven piles, and drilled shafts
piles, and drilled shafts. Chapter 17 is intended respectively.
primarily for use by the bridge engineer.
17.1.3. Arctic Engineering
Section 11.7 of this Manual presents DOT&PF
Some areas of Alaska have ground conditions that
criteria for selecting an appropriate foundation type
include permafrost, which is ground that has remained
within the context of structure-type selection. The
at or below 32°F for two or more years. The active
Alaska Geotechnical Procedures Manual discusses
layer is the surficial layer of soil that undergoes
the geotechnical considerations for bridge foundation
seasonal freeze/thaw cycles.
design.
Two methods are usually recommended for installing
17.1.1. Design Methodology
deep foundations in permafrost. For warm permafrost
The following summarizes the concepts in the LRFD (31°F), drive piles through the permafrost layer. For
Specifications for the design of foundations. cold permafrost (25°F to 27°F), cut or drill a hole, set
Considering basic design principles for foundations, the pile into the hole, and then fill the annulus with
the LRFD Specifications implemented a major change slurry. The project-specific installation method will
when compared to the traditional principles of the be identified in the Structural Foundation Engineering
AASHTO Standard Specifications for Highway Report (SFER).
Bridges (Standard Specifications). The LRFD After installation, isolate piles from the soils in the
Specifications distinguishes between the strength of active layer. DOT&PF prohibits thermal piles.
the in-situ materials (soils and rock strata) supporting
the bridge and the strength of the structural For seismic design, consider both the thawed and
components transmitting force effects to these frozen conditions.
materials. The LRFD Specifications emphasize the
distinction by addressing in-situ materials in Section 17.1.4. Differential Settlement
10 “Foundations” and structural components in Reference: LRFD Articles 3.12.6, 10.6.2.2, and
Sections 5 and 6, which specify requirements for 10.7.2.3
concrete and steel elements. The bridge engineer
Differential settlement is the difference between the
applies the appropriate provisions from these sections
settlements of two adjacent foundations. In the LRFD
in the structural design of footings, steel and concrete
Specifications, differential settlement (SE) is a
piles, and drilled shafts.
superstructure load.
The user selects the target safety levels for each type
of foundation to achieve a level of safety comparable
to that inherent in those foundations designed with the
The general DOT&PF practices on the acceptable 2. Joint Movements. A change in bridge
limits for settlement are: geometry due to settlement causes movement in
deck joints that should be considered in joint
1. Estimated Differential Settlement. If detailing, especially for deep superstructures.
Statewide Materials estimates that the
differential settlement is less than one-half of 3. Profile Distortion. Excessive differential
the total estimated settlement, the bridge settlement may cause a distortion of the
engineer may usually ignore the effects of roadway profile that may be undesirable for
differential settlement in the structural design of vehicles traveling at high speed.
the bridge.
4. Appearance. Viewing excessive differential
2. Angular Distortion. Angular distortion is the settlement may create a perception of lack of
differential settlement divided by the distance safety.
between the adjacent foundations.
Foundation Settlement Mitigation
LRFD Article C10.5.2.2 states that angular Use ground modification techniques to improve the
distortions between adjacent foundations greater soil to address differential settlement concerns. Some
than 0.008 radians in simple spans and 0.004 available techniques include:
radians in continuous spans should not be
ordinarily permitted, and the Article suggests chemical grouting
that other considerations may govern. over-excavation and replacement
surcharging
DOT&PF does not use the LRFD limits for installation of stone columns
design, which are related to structural distress, compaction grouting
because these angular distortions yield deep dynamic compaction
unacceptable impacts on ride-ability and
aesthetics. Typically, meeting the requirements
of Item 1. Estimated Differential Settlement
should preclude exceeding the angular
distortions allowed by the LRFD Specifications.
3. Piers. Consider deep foundations where
differential settlement is a concern between
columns within a pier.
Foundation Settlement Effects
If varying site conditions exist, the Final SFER will
address settlement. Consider the following effects:
1. Structural. The differential settlement of
substructures causes the development of force
effects in continuous superstructures. These
force effects are directly proportional to
structure depth and inversely proportional to
span length, indicating a preference for shallow,
long-span structures.
The force effects from settlement are normally
smaller than expected and tend to be reduced in
the final total factored loads (Strength I) to the the description of bedrock properties when
foundation (these values will be provided in the present, including planes of weakness, joints,
foundation Data Table on the Site Plan drawing) faults, rock type, Rock Quality Designation
Table 17-2
Drilled Shaft Data Table Example
DRILLED SHAFT DATA TABLE
Table 17-3
Footing Pressure Table Example
provide the associated Resistance Factor in the Pile Resistance, in most cases, will be greater than the
Data (see Table 17-1 for an example). Currently, a Nominal Resistance.
Resistance Factor value of 0.50 indicates that “Wave
equation analysis without pile dynamic The Nominal Resistance of the pile is the anticipated
measurements” will be used. A Resistance Factor pile capacity after all applicable pile resistance
value of 0.65 indicates that a “Driving criteria reductions have occurred. The Strength I Factored
established by dynamic test with signal matching” is Load must be less than the Nominal Resistance
required. multiplied by the Resistance Factor.
Minimum penetration of the pile is typically based Bridge will provide a Drilled Shaft Data table (see
upon lateral resistance requirements (e.g., seismic or Table 17-2 for an example) in all bridge plans that use
ice demands). Base the Estimated Pile Tip Elevation drilled shaft foundations.
upon the factored estimated resistance after scour, Provide the drilled shaft Tip Elevation and Minimum
downdrag, liquefaction, and all other pile resistance Rock Socket Length in the SFER. Do not include the
conditions have been considered. Because scour, material that is encountered above the specified
downdrag, and other pile resistance reductions are not Minimum Top of Rock Socket Elevation in the
present during pile driving, the Minimum Driving Minimum Rock Socket Length (e.g., in Table 17-2,
The Nominal Resistance of the drilled shaft is the review the adequacy of the Contractor’s
anticipated shaft capacity after all applicable proposed pile driving plan;
reductions have occurred. The Strength I Factored review the adequacy of the Contractor’s
Load must be less than the Nominal Resistance proposed pile driving hammer;
multiplied by the appropriate Resistance Factor(s).
provide the pile driving acceptance criteria (also
Bridge will provide the level of field inspection for
known as the inspector’s chart) when a “Wave
drilled shafts (e.g., down-hole inspection and bottom
equation analysis without pile dynamic
cleanliness) in the special provisions.
measurements” is specified;
Bridge will provide a Footing Pressure table (see
provide preliminary pile driving acceptance
Table 17-3 for an example) in all bridge plans that use
criteria when “Driving criteria established by
shallow foundations.
dynamic test with signal matching” is specified;
Seismic Parameters and
Bridge will provide the seismic design parameters, as generate the scope of services for the
shown in Figure 17-2, in the “GENERAL NOTES” of Construction Project Engineer when a “Driving
the Site Plan drawing. Provide the spectral criteria established by dynamic test with signal
acceleration values in the AASHTO LRFD Bridge matching” is specified and interact with the
Design Specifications and the AASHTO Guide PDA consultant once its services have been
Specifications for LRFD Seismic Bridge Design. acquired.
Provide the Site Class and Liquefaction Potential in
the SFER For drilled shaft foundations, both Geotech and
Bridge will be required to:
For Site Class F soils or other situations where a site-
specific response spectra is used in the bridge design, review the adequacy of the Contractor’s
include the site-specific spectra on the bridge plans proposed shaft installation plan; and
sheets. review field inspection reports (e.g., shaft
cleanliness, cross-hole-sonic logs).
Log of Test Hole Borings
Bridge will incorporate the sealed and signed test hole For shallow foundations, Geotech may be required to
location and boring log plan sheets in the final bridge evaluate foundation adequacy when the actual soils
plans. deviate from those presented in the Foundation
Geology Report and Final SFER (e.g., groundwater
17.2.5. Construction Support table, rock characteristics, soil type).
Both Geotech and Bridge must be available during
construction to address construction-related
foundation and geotechnical questions and problems
Figure 17-3
Stepped Footings/Caps Pile Caps/Footings
Rock or dense soil where end bearing is desirable and lateral flexibility in
Steel H-pile one direction is not critical. Common at abutments and for pile footings,
but not typically used in liquefiable soils.
Loose to medium dense soils or clays where skin friction is the primary
Steel pipe pile resistance and lateral stiffness in both directions is desirable, especially
(closed or open end) in rivers where deep scour or liquefaction is anticipated and high lateral
stiffness is needed.
Figure 17-4
Driven Pile Selection
Figure 17-6
Steel Pipe Pile Connection
2. Location of Top of Shaft. Typically, terminate 7. Constructability. Detail drilled shafts and
drilled shafts 6 inches above the finished grade columns to accommodate concrete placement
or at 12 inches above the water elevation through the layers of reinforcing steel. Limit
anticipated during construction. lap splices in the drilled shaft locations and
Figure 17-7
Typical Drilled Shaft
Figure 17-9
Method of Modeling Deep Foundation Stiffness
φyi (H + Ls )2
∆yi =
3
Mu
Pu =
H + Lm
Mu
∆u = ∆y + Lp (φu - φyi ) (H + Lm )
Myi
where:
Pyi = idealized lateral yield force
Myi = idealized yield moment
H = pile or shaft height measured from the ground line
to the top of the section
Δyi = idealized lateral yield displacement