Sie sind auf Seite 1von 3

PMP Study Group October-2018

A Quiz for Chapter 1

1. All the following are characteristics of the project except:


a. It may produce a unique product
b. It has a repetitive nature
c. It could be undertaken at all organizational levels.
d. It might include several deliverables

2. The benefit from projects may be tangible such as:


a. Goodwill
b. Trademarks
c. Monetary assets
d. Reputation

3. Leaders might initiate projects in response with the all following


factors, except:
a. Satisfy stakeholder requests or needs
b. Implement or change business or technological strategies
c. Meet regulatory, legal, or social requirements
d. Satisfy customers requirements for a big order of products

4. Poorly managed projects would result in:


a. Identify failing projects
b. Rework due to failing projects
c. Recovery of failing projects
d. Termination of failing projects

5. “A group of related projects managed in a coordinated manner to


obtain benefits not available from managing them individually” is the
definition of:
a. Project
b. Mega project
c. Program
d. Portfolio

Prepared by Mohamed ElSaadany


MSc., PMP, CCP, PMI-RMP
Page |1
PMP Study Group October-2018
A Quiz for Chapter 1

6. Do the right projects is an example of the ………………………


management activities.
a. Project
b. Mega project
c. Program
d. Portfolio

7. The project lifecycle could be divided into:


a. Sub-projects
b. Phases
c. Gates
d. Knowledge areas

8. Initiation processes could be performed ……………….


a. When we need to close the project.
b. Whenever we terminate a project.
c. Only at the beginning of the project.
d. At the beginning of the project and could be during the project.

9. ……………………. includes the processes and activities to identify, define,


combine, unify, and coordinate the various processes.
a. Project management body of knowledge
b. Monitoring and Controlling Process Group
c. Project Integration Management
d. Processes standard. A practice Guide

10. …………………… used to establish the validity of the benefits of selected


components. It’s also used as a basis for the authorization of further
project management activities.
a. Project management plan
b. Benefits management plan
c. Project charter
d. Project Business case
Prepared by Mohamed ElSaadany
MSc., PMP, CCP, PMI-RMP
Page |2
PMP Study Group October-2018
A Quiz for Chapter 1

Answers:
1-b
2-c
3- d
4-b
5-c
6-d
7-b
8-d
9-c
10-d

Prepared by Mohamed ElSaadany


MSc., PMP, CCP, PMI-RMP
Page |3