Project : Exterior Works

Location : San Leonardo, Nueva Ecija


Subject : BILL OF QUANTITIES
Owner : Mrs. Irish Buenaventura

ITEM MATERIALS COST


DESCRIPTION UNIT QUANTITY
NO. UNIT COST

I. PRELIMINARIES
Mobilization/ Demobilization lot 1.00
Temporary Facilities(BY THE OWNER) lot 1.00
Building Permits (LEGWORK ONLY)
As-built Drawings(by designer)

II. STRUCTURAL WORKS

Concrete canopy for Windows cum. 0.45


Cement Bags 4.00 230.00
Sand Cum. 0.50 700.00
Gravel Cum. 0.50 1,100.00
10mm dia.x6.0m Pcs. 30.00 136.00
Tiewire # 16 Kgs. 6.00 80.00

III. CARPENTRY WORKS


Scaffolding lot 1.00 5,000.00
IV. MASONRY WORKS
CHB walls including rebars and mortars
walls 4" chb sqm. 3.00 500.00

V. Plastering
wall sqm. 260.00 180.00
Corner Edge Lm. 40.00 80.00

VI. ARCHITECTURAL FINISHES


Ceiling works
Ceiling eave sqm. 38.00 1,000.00
PAINTING
Walls(all walls) sqm. 260.00 180.00

TOTAL MATERIAL COST


TOTAL LABOR COS
A. TOTAL MATERIAL AND LABOR COST(DIRECT COST)
B. PRELIMINARIES
SUB-TOTAL
Plus 15% profit
GRAND TOTAL
TERIALS COST LABOR COST
AMOUNT UNIT COST AMOUNT TOTAL AMOUNT

8,000.00 8,000.00
- -

-
-

920.00 103.50 414.00 1,334.00


350.00 315.00 157.50 507.50
550.00 495.00 247.50 797.50
4,080.00 61.20 1,836.00 5,916.00
480.00 36.00 216.00 696.00
-

-
5,000.00 1,800.00 1,800.00 6,800.00
-
-
-
-
1,500.00 250.00 750.00 2,250.00

-
-
-
46,800.00 250.00 65,000.00 111,800.00
3,200.00 150.00 6,000.00 9,200.00
-

38,000.00 250.00 9,500.00 47,500.00

46,800.00 100.00 26,000.00 72,800.00

147,680.00
111,921.00
259,601.00
8,000.00
267,601.00
40,140.15
307,741.15