CONSTRUCTION METHODOLOGY & METHOD OF STATEMENT
system after
installation, and to BROWSE BY TOPICS
ensure the
performance of the installed system meets the speci ed Aluminium & Glass Work
design intent through a series of tests and adjustments. Methods (6)
Finally to capture and record performance data of the whole Building Management
installation as the baseline for future operation and System (24)
maintenance. Civil Downloads (35)
Civil Engineering Methods
Preparation & Pre Testing & Commissioning Work: Before
(123)
start of testing & commissioning the completeness of the
Construction Method
system shall be ensured by physical inspections and
Statements (168)
interpreting the previously submitted and approved work
inspection reports/records.
https://methodstatementhq.com/testing-commissioning-of-cctv-cameras-method-statement.html 1/6
10/17/2019 Testing & Commissioning Of CCTV Camera - Method Statement - Method Statement HQ
https://methodstatementhq.com/testing-commissioning-of-cctv-cameras-method-statement.html 2/6
10/17/2019 Testing & Commissioning Of CCTV Camera - Method Statement - Method Statement HQ
RECENT ARTICLES
Looking for networking
opportunities in the KSA power Toolbox Talk Topics: Why
market? Register now for free Accidents Occur
Method Statement for
MEE Saudi Ad Installation of Fire
Protection Services
ﻣﻌرﻓﺔ اﻟﻣزﯾد
YStrainer Installation and
Ensure all installation works are complete as per approved Maintenance Guidelines
method statement for installation of CCTV system and Glass Cutting Method
drawings. Also ensure that ICT data network is ready and Using Automatic Machine
commissioned. Method Statement for
First step involved in pre commissioning is to establish LAN Installation of Fan
network between Encoder and commissioning laptop. Powered Box Units
Connect network port to the portable POE network switch Method Statement for
from the patch panel in respective communication room. Installation of Sanitary
Plug the commissioning laptop to the other port of the Vent and Storm Drainage
portable network switch Piping
Set the IP address of commissioning laptop to the required Butter y Valve Installation
range and Maintenance
Open the video encoder with default IP address from web Procedure
browser. Download Construction
Enter the Username with Password Project Risk Assessment
Go to encoder settings for selecting the pro le – Covering 40 Activities
Now go to system settings and set password and date and Software Quality
time. For date and time de ne the IP address of respective Assurance Framework &
communication gateway. Methodologies
Go to network settings and change the IP address same as What is Unsafe Act &
of IT network plan. Unsafe Condition? Toolbox
Now change the IP address of commissioning laptop same Talk Topics
as of IT network plan.
Open the web browser of encoder with new IP address.
Login to encoder web browser by entering user name and
password.
https://methodstatementhq.com/testing-commissioning-of-cctv-cameras-method-statement.html 3/6
10/17/2019 Testing & Commissioning Of CCTV Camera - Method Statement - Method Statement HQ
https://methodstatementhq.com/testing-commissioning-of-cctv-cameras-method-statement.html 4/6
10/17/2019 Testing & Commissioning Of CCTV Camera - Method Statement - Method Statement HQ
. ﻗدّم ﻓورا. أﻓﺿل اﻟﺷرﻛﺎت10000 أﻛﺛر ﻣن. وظﺎﺋف ﻣﺑﺎﺷرة350000 أﻛﺛر ﻣن
https://methodstatementhq.com/testing-commissioning-of-cctv-cameras-method-statement.html 5/6
10/17/2019 Testing & Commissioning Of CCTV Camera - Method Statement - Method Statement HQ
Save More
Related
https://methodstatementhq.com/testing-commissioning-of-cctv-cameras-method-statement.html 6/6