CRONOGRAMA VALORIZADO DE AVANCE DE OBRA

OBRA : " MEJORAMIENTO DEL SERVICIO DE EDUCACION INICIAL Y PRIMARIA DE LA I.E. PARROQUIAL MADRE DE
CRISTO – DISTRITO DE LA ESPERANZA – PROVINCIA DE TRUJILLO – REGION LA LIBERTAD "

UBICACIÓN : ESPERANZA - TRUJILLO - LA IBERTAD

FECHA : DICIEMBRE _ 2013

SECCION PRIMER MES SEGUNDO MES TERCER MES CUARTO MES QUINTO MES SEXTO MES TOTAL

ESTRUCTURAS S/. 233,628.75 S/. 262,832.34 S/. 379,646.72 S/. 379,646.72 S/. 175,221.56 S/. 29,203.60 S/. 1,460,179.69

ARQUITECTURA S/. 37,525.15 S/. 56,287.73 S/. 206,388.34 S/. 243,913.49 S/. 281,438.64 S/. 112,575.46 S/. 938,128.81

INST. ELECTRICAS S/. 0.00 S/. 27,134.28 S/. 54,268.56 S/. 75,975.98 S/. 97,683.40 S/. 16,280.56 S/. 271,342.78

INST. SANITARIAS S/. 0.00 S/. 4,200.47 S/. 6,300.71 S/. 9,101.02 S/. 9,801.10 S/. 5,600.63 S/. 35,003.93

COSTO DIRECTO S/. 271,153.90 S/. 350,454.82 S/. 646,604.33 S/. 708,637.21 S/. 564,144.70 S/. 163,660.25 S/. 2,704,655.21

GASTOS GENERALES (10 %) S/. 270,465.52

UTILIDADES (5%) S/. 135,232.76


===========

SUB TOTAL S/. 3,110,353.49

IGV 19% S/. 559,863.63


===========

TOTAL PRESUPUESTADO S/. 3,670,217.12