The New Austrian Tunnelling method (NATM), also known as Sequential Excavation Method
(SEM), describes a popular method of modern tunnel design and construction. This technique first
gained attention in the 1960s based on the work of Ladislaus von Rabcewicz, Leopold Müller and Franz
Pacher between 1957 and 1965 in Austria. The name NATM was intended to distinguish it from the old
Austrian tunnelling approach. The fundamental difference between this new method of tunneling, as
opposed to earlier methods, comes from the economic advantages made available by taking advantage
[1]
of the inherent geological strength available in the surrounding rock mass to stabilize the tunnel .

NATM/SEM is generally thought to have helped revolutionise the modern tunnelling industry. Many of
the most famous modern tunnels have used this excavation technique.

Contents
■ 1 Principles
■ 2 Variant names
■ 3 Key features
■ 4 See also
■ 5 References
■ 6 Further reading

Principles
The NATM integrates the principles of the behaviour of rock masses under load and monitoring the
performance of underground construction during construction. The NATM has often been referred to as
a "design as you go" approach, by providing an optimized support based on observed ground conditions.
More correctly it can be described as a "design as you monitor" approach, based on observed
convergence and divergence in the lining and mapping of prevailing rock conditions. It is not a set of
specific excavation and support techniques.

NATM has seven elements:

■ Exploitation of the strength of native rock mass - Relies on the inherent strength of the
surrounding rock mass being conserved as the main component of tunnel support. Primary support
is directed to enable the rock to support itself.
■ Shotcrete protection - Loosening and excessive rock deformation must be minimised. This is
achieved by applying a thin layer of shotcrete immediately after face advance.

http://en.wikipedia.org/wiki/New_Austrian_Tunnelling_method 10/7/2014
New Austrian Tunnelling method - Wikipedia, the free encyclopedia Page 2 of 4

■ Measurement and monitoring - Potential deformations of the excavation must be carefully


monitored. NATM requires installation of sophisticated measurement instrumentation. It is
embedded in lining, ground, and boreholes. In the event of observed movements, additional
supports are installed only when needed, with a resultant overall economy to the total cost of the
project.
■ Flexible support - The primary lining is thin and reflects recent strata conditions. Active rather
than passive support is used and the tunnel is strengthened by a flexible combination of rock bolts,
wire mesh and steel ribs, not by a thicker concrete lining.
■ Closing of the invert - Especially crucial in soft ground, the quick closing of the invert (the bottom
portion of the tunnel) which creates a load-bearing ring is important, and has the advantage of
engaging the inherent strength of the rock mass surrounding the tunnel.
■ Contractual arrangements - Since the NATM is based on monitoring measurements, changes in
support and construction method are possible, but only if the contractual system enables them.
■ Rock mass classification, ranging from very hard to very soft, determines the minimum support
measures required and avoids economic waste that comes from needlessly strong support
measures. Support system designs exist for each of the main rock classes. These serve as the
guidelines for tunnel reinforcement.

Based on the computation of the optimal cross section, only a thin shotcrete protection is necessary. It is
applied immediately behind the tunnel boring machine, to create a natural load-bearing ring and
minimize the rock's deformation. Geotechnical instruments are installed to measure the later
deformation of excavation. Monitoring of the stress distribution within the rock is possible.

This monitoring makes the method very flexible, even if teams encounter unexpected changes in the
geomechanical rock consistency, e.g. by crevices or pit water. Reinforcement is done by wired concrete
that can be combined with steel ribs or lug bolts, not with thicker shotcrete,

The measured rock properties suggest the appropriate tools for tunnel strengthening. Since the turn of
the 21st century, NATM has been used for soft ground excavations and making tunnels in porous
sediments. NATM enables immediate adjustments in the construction details, but requires a flexible
contractual system to support such changes.

Variant names
NATM was originally developed for use in the Alps, where tunnels are commonly excavated at depth
and in high in situ stress conditions. The principles of NATM are fundamental to modern-day
tunnelling, and NATM fundamentally involves specifically addressing the specific soil conditions being
encountered. Most city tunnels are built at shallow depth and need not control the release of in situ stress
seen with the original NATM in the Alps. Projects in cities place a higher priority on minimizing
settlement therefore they tend to use different support methods that the original NATM. This has led to a
confusion in terminology in that tunnelling engineers use "NATM" to mean different things. New terms

http://en.wikipedia.org/wiki/New_Austrian_Tunnelling_method 10/7/2014
New Austrian Tunnelling method - Wikipedia, the free encyclopedia Page 3 of 4

have arisen and alternative names for certain aspects of NATM have been adopted as its use has spread.
This is partly caused by an increased use of this tunneling method in the USA, particularly in soft
ground shallow tunnels.

Other designations are seen for this modern tunneling style, e.g. Sequential Excavation Method (SEM)
or Sprayed Concrete Lining (SCL) are often used in shallower tunnels. In Japan the terms Centre
Dividing Wall NATM or Cross Diaphragm Method (both abbreviated to CDM), and Upper Half Vertical
Subdivision method (UHVS) are used.

The Austrian Society of Engineers and Architects defines NATM as "a method where the surrounding
rock or soil formations of a tunnel are integrated into an overall ring-like support structure. Thus the
supporting formations will themselves be part of this supporting structure."[2]

Some engineers use NATM whenever proposing shotcrete for initial ground support of an open-face
tunnel. The term NATM can be misleading in relation to soft-ground tunnels. As noted by Emit Brown,
NATM can refer to both a design philosophy and a construction method.[3]

Key features
Key features of the NATM design philosophy refer to:

■ The strength of the ground around a tunnel is deliberately mobilized to the maximum extent
possible.
■ Mobilization of ground strength is achieved by allowing controlled deformation of the ground.
■ Initial primary support is installed having load-deformation characteristics appropriate to the
ground conditions, and installation is timed with respect to ground deformations.
■ Instrumentation is installed to monitor deformations in the initial support system, as well as to
form the basis of varying the initial support design and the sequence of excavation.

When NATM is seen as a construction method, the key features are:

■ The tunnel is sequentially excavated and supported, and the excavation sequences can be varied to
efficiently address the specific rock conditions being encountered.
■ The initial ground support is provided by shotcrete in combination with fiber or welded-wire
fabric reinforcement, steel arches (usually lattice girders), and sometimes ground reinforcement
(e.g. soil nails, spiling).
■ The permanent support is typically a cast-in-place concrete lining placed over a waterproofing
membrane.

http://en.wikipedia.org/wiki/New_Austrian_Tunnelling_method 10/7/2014
New Austrian Tunnelling method - Wikipedia, the free encyclopedia Page 4 of 4

See also
■ Geotechnical engineering
■ Rock mass classification
■ Tunnels

References
1. ^ Özdemir, Levent (2006). North American Tunneling 2006. Washington, DC: Taylor & Francis. p. 246.
ISBN 0-415-40128-3.
2. ^ Tunnelling: Management by Design, Alan Muir Wood, Taylor & Francis, 2002, ISBN 0203477669
3. ^ Jacobs & Associates Newsletter, Spring 2002, NATM IN SOFT-GROUND: A CONTRADICTION OF
TERMS?[1] (http://www.jacobssf.com/images/uploads/2002_Romero_NATM.pdf), Victor Romero.

Further reading
■ Johann Golser, The New Austrian Tunneling Method (NATM), Theoretical Background &
Practical Experiences. 2nd Shotcrete conference, Easton, Pennsylvania (USA), 4-8 Oct 1976.

Retrieved from "http://en.wikipedia.org/w/index.php?


title=New_Austrian_Tunnelling_method&oldid=585572680"
Categories: Geotechnical engineering Rock mass classification Tunnels

■ This page was last modified on 11 December 2013 at 10:01.


■ Text is available under the Creative Commons Attribution-ShareAlike License; additional terms
may apply. By using this site, you agree to the Terms of Use and Privacy Policy. Wikipedia® is a
registered trademark of the Wikimedia Foundation, Inc., a non-profit organization.

http://en.wikipedia.org/wiki/New_Austrian_Tunnelling_method 10/7/2014

Das könnte Ihnen auch gefallen