JOB SAFETY ANALYSIS Format No.

APPL-EHS-001
Rev 00
Date :10.11.2015
PROJECT : JSA NUMBER : APPL/LLV/JSA0022
JOB TITLE:SUSPENDED ROPE PLATFORM NAME OF THE CONTRACTOR : Anukar projects pvt ltd
S.NO ACTIVITIES HAZARD RISK CONTROL MEASURES
1 Untrained worker, lack of skill Personal Only inducted worker shall be deputed at the work
awareness injury place.
Manpower Given tool box talk to all workers
Mobilization Work should carry under supervision
Medical checkup should be done before start work
Safety induction should be given to all workers
Gate pass & required PPE’S.Safety helmet, safety
shoes, reflective jocket,handgloves, safety goggle
etc.Must be provided
2 Fall of materials Personal Access should be clear form objects
injury and Only trained and experience workers to be allowed to
Material shifting Slips, trips property the work
from ground damage Proper manual handling method should be used and
floor to terrace Cut injuries applied to carrying and transport the counter weights
In case of a heavy weight 50kg or above it should be
carried by two or more persons
Maintained sufficient clearance from the live electrical
Use proper PPE’S (Helmet, safety shoes and cut
resistance hand gloves.
Personal Counter weight area should be placed on firm ground
injury and level
3 Ground level Instability of ground property Maintained good housekeeping at counter wait area
preparation damage Unwanted and sharp edges removed from the area
Counter weight area should be barricaded and kept a
sign board
Barricaded the unwanted materials (wire ropes, upper
column, middle beam ,rear beam & counter waits)
Improper method of erection Personal Under supervision of competent person erect the
injury and suspended working platform
Inadequate experiencedpersonnel property
Only trained and experience workmen should erected
damage
the suspended working platform
safe working load (S.W.L)are unclear
Suspended rope platform erected as per manual
instruction or method statement.
Improper electrical connections
Display the safe working load on the working platform
4 Erection of Using of damaged wire rope Ensure all electrical connection should be in good
suspended rope condition
platform Fall of suspended working plat form Give the electrical connection through 30ma ELCB
Only authorized electrician give the electrical
Fall of men and materials Ensure wire rope should be in good condition
Don’t use the damage wire rope
Platform should be top rail,mid rail & toe board.
Platform should be neat and clean
While working in platform wear the safety harness
Ensure safety lock should be in working conditions
Counter weights fixed as per the manufacture
instruction
Joint pin should be tied properly.
Equipment should be third party certificate
Electrical shocks Personal Electrical connections give through ELCB
injury Don’t use the damage electrical cables
5 Operating of Fall of working platform falling of Panel board should be protected from rain
suspended rope load, Use industrial plug tops.
platform Fall of men and materials Avoid jointing cable
Safety lock should be in working condition
Slings failures Wire rope should be locked properly
Platform should be top rail, mid rail & toe board.
Damage to the building
While working in platform wear double lanyard safety
belt
Don’t use the damage wire rope
Suspended working platform should not be used in
heavy wind
Wire rope should be in good condition
Don’t remove the counter weights while operating the
suspended rope platform
Ensure no one is under the load
Always secure the area where the load will be moved
keep peopleout
Improper Material handling Personal Only trained and experienced workmen should
Injury dismantling the suspended rope platform
6 Dismantling of Fall of materials Under supervision of competent person dismantling of
suspended rope suspended rope platform
platform Disposal of material and components .components
should not be through on ground.
suspended area should be barricaded& kept a sign
board
Before dismantling the suspended rope plat form
remove all electrical cables.
Incase of confusion Personal Give awareness about emergency evacuation plan,
Emergency Injury keep emergency contact Number. Aware about
7 assembly Point
Remarks or any instruction
Sign

Engineer EHS project Co-ordinator EHS Dept


Prepared By Checked By Reviewed Reviewed By Approved By
By