Beruflich Dokumente
Kultur Dokumente
Over 130 key players were interviewed for this book, and the
Australian Defence Department allowed access to its classified archives
and the Australian Navy archives. Vividly illustrated with photographs
from the collections of the Royal Australian Navy and ASC Pty Ltd,
The Collins Class Submarine Story: Steel, Spies and Spin is a riveting
and accessibly written chronicle of a grand-scale quest for excellence.
PETER YULE
DEREK WOOLNER
cambridge university press
Cambridge, New York, Melbourne, Madrid, Cape Town,
Singapore, São Paulo, Delhi, Tokyo, Mexico City
Published in the United States of America by Cambridge University Press, New York
www.cambridge.org
Information on this title: www.cambridge.org/9780521868945
A catalogue record for this publication is available from the British Library
v
vi CONTENTS
Notes 330
Index 349
LIST OF KEY PEOPLE
vii
viii LIST OF KEY PEOPLE
xv
INTRODUCTION
xvii
xviii INTRODUCTION
the Royal Australian Navy; ASC Pty Ltd; Defence Science and
Technology Organisation, Department of Defence; Force Element
Group, Department of Defence.
Of the thousands of people involved in designing, building
and operating the Collins class submarines, no two people fully
agree on the ‘real story’ of the submarine project. Similarly few
people will agree with all details in the book, and many will be
angered by some of the conclusions reached. While the authors
accept responsibility for any errors of fact or interpretation, the
lack of agreement on many issues remains one of the key features
of the Collins submarine project, with the noise of the disputes
still overshadowing the scale of the achievement.
Peter Yule
PART 1
3
4 THE COLLINS CLASS SUBMARINE STORY
discussion led to a general belief that the faults were far worse than
they really were. Further, the debate was deliberately fanned by
leading figures in the navy and the government who were opposed
to having submarines at all.
Submarines have long been controversial in Australia. From
the earliest days of the navy the same topics have been debated.
Should the navy have submarines? If so, should they be built in
Australia or overseas? Does Australia have the ability to build
submarines? What are the most suitable submarines? Will they
prove too expensive? Will they perform as intended? The debates
have been more bitter and prolonged with the Collins class than
with any other, but most of the issues raised in the controversies
over Collins have familiar resonances over the century since Alfred
Deakin first proposed submarines for the Australian navy.
In April 1904 Admiral Sir John Fisher, the architect of British
naval policy before the First World War, described an incident he
observed during British naval exercises off Portsmouth:
Here . . . is the battleship Empress of India engaged in
manoeuvres and knowing of the proximity of Submarines, . . .
so self-confident of safety and so oblivious of the possibilities
of modern warfare that the Admiral is smoking his cigarette,
the Captain is calmly seeing defaulters down on the
half-deck, no one caring an iota of what is going on, and
suddenly they see a Whitehead torpedo miss their stern by a
few feet! And how fired? From a submarine [which] followed
that battleship for a solid two hours under water.3
11
12 THE COLLINS CLASS SUBMARINE STORY
The report asserted that ‘one nuclear submarine can do the effec-
tive patrol work of two conventional submarines’ but, at one-
sixth the cost, conventional submarines were more efficient. The
report did not consider whether Australia could maintain nuclear
submarines without a nuclear industry.
In July 1959 Gorton advised Athol Townley, the Minister for
Defence, that he was preparing to recommend the purchase of
submarines to cabinet. Townley was cautious. When questioned
in parliament he commented that: ‘Australia will have to be pretty
careful before it goes into the submarine arm again and will have to
take every precaution and examine the position very thoroughly,
because three times this country has become involved in sub-
marines and three times it has been pleased to get out of this
arm of the Navy.’3
It took more than three years, and the formal announcement
by the British in 1961 that they would be withdrawing their
submarines by the end of the decade, for Gorton to overcome
Townley and some members of the Naval Board. On 23 January
1963 he announced cabinet approval to order four Oberon class
submarines from Britain for delivery between 1966 and 1968.
Commander Henry Cook, a former Royal Navy submarine
commander who had transferred to the Australian navy, was
involved in the acquisition and recalls that talks with the British
began before 1961 about the possibility of buying Oberons. In
AUSTRALIA’S OBERON CLASS SUBMARINES 13
1962 the Naval Board formally evaluated the Oberon and the
American Barbel. The Barbel was rejected partly on cost grounds
and partly because it was soon to be taken out of service.4 Tra-
dition, together with the fact that the Oberon was a tried and
successful design, meant that the decision to buy from Britain was
not questioned.
However, there was some controversy over the navy’s decision
to order four submarines from Britain without investigating the
possibility of building at least two of them in Australia. Even
before the official announcement, H. P. Weymouth, the chairman
of the Australian Shipbuilding Board, wrote to Hubert Opperman,
the Minister for Shipping and Transport:
British flotilla departed, and they would cost too much. The report
analysed in some detail what would be involved in Australian
construction:
It was also suggested that the British Admiralty would not pro-
vide specifications to Australian tenderers or help assess tenders
submitted by Australian dockyards.14
The Joint Committee on War Production, which was also
attempting to assess the issue of Australia’s ability to build
AUSTRALIA’S OBERON CLASS SUBMARINES 17
The response from London does not appear to have been over-
enthusiastic and Cockatoo Island made little headway with its
lobbying in Australia.
However, the suggestion that Cockatoo might be interested in
building the submarines led the navy to introduce a new note of
warning into the debate, arguing that the Canadians were show-
ing interest in ordering Oberons from Britain, so Australia would
need to confirm its order immediately to ensure early delivery.
The issue was finally resolved when Gorton told the Minister for
18 THE COLLINS CLASS SUBMARINE STORY
As the Oberons aged, refits became more difficult as parts wore out
and corroded sections of the pressure hull required replacement.
About 30 000 individual items were needed for each refit and the
early refits depended heavily on spares from the UK, although
‘local industry gradually became qualified for the supply of some
parts, reducing this dependency’.20
The performance of the Oberons convinced Australian navy
planners of the need for submarines, but their maintenance
AUSTRALIA’S OBERON CLASS SUBMARINES 19
20
THE SUBMARINE WEAPONS UPDATE PROGRAM 21
together the case for why Australia should have submarines, look-
ing at the role of submarines at that time and 20 years ahead. In
simple terms, intelligence gathering was the most important rea-
son. When he had demonstrated that submarines were necessary,
the question then became, ‘what sort of submarines?’ He con-
cluded there were no suitable designs because none met the range
performance desired by the navy.
In 1980, as the program began to take shape, Lieutenant
Frank Owen was appointed ‘follow-on submarine project officer’
attached to the directorate of submarine policy. His job was to
pull together the key characteristics of the new submarine. Owen
recalls that the first big argument they had to win was for big,
long-range submarines rather than small, short-range submarines
based in the north at Cairns or Darwin. He put together a substan-
tial paper on this issue and by early 1982 had achieved broad sup-
port for both the proposed characteristics of the new submarines
and for investigating their construction in Australia. Gaining the
endorsement of the operational requirements committee was rea-
sonably straightforward, but it proved more difficult to convince
the force structure committee.
One of the roles of this committee was to assess each new
equipment project against defence policy to identify its priority
for the money the government had allocated over the next five
years. Its power lay in recommending the funding for projects in
future budgets. A limited allocation could delay a project by years
or, if other projects were considered more important, a diversion
of funds could force a fundamental change in the nature of the new
submarine force. Service people were suspicious of the committee
because most of its members were civilians (although its decisions
were not made on a vote) and it was chaired by a deputy sec-
retary of the department who was also responsible for the force
development and analysis division.
From May 1982 the chair was Alan Wrigley, recruited to the
Defence Department in 1975 to help establish force development
and analysis. He was to become the staunchest critic of the navy’s
proposals for a new submarine. Wrigley’s major weapon, he says,
was the ambition of the submariners. At each stage of develop-
ment the submarine project would be likely to cost more than
previously thought and, importantly, more than was allocated in
future spending plans. Since future financial allocations were fixed
THE SUBMARINE WEAPONS UPDATE PROGRAM 29
30
THE NEW SUBMARINE PROJECT 31
available and none matched what they had done with the Oberons,
let alone their vision of the future.
In the early 1980s it was revolutionary to think of the com-
bat system separately – the combat system had been standard
equipment in the Oberons. Andrew Johnson, Rick Neilson and
the team at the SWSC were not interested in the selection of the
submarine hull and thought no submarine builder would provide
them with the combat system they wanted, so they broke the two
things apart. By the time the acquisition strategy was put together
in 1982 it was clear that the platform and the combat system
were two different things – they should be developed and built
separately and then integrated.
The new Oberon combat system worked well but had a wide
variety of displays, consoles and software, and the control room
was crammed with black boxes that could not talk to each other.
It had seven different types of display, seven different processors
and seven different languages. Spares for all the displays and pro-
cessors could not be carried on board and training was extremely
complicated.8
Andrew Johnson was the development leader and conceived
the idea of using common consoles, common processors and a
common language to avoid these problems. Instead of a central
mainframe computer performing all the data analysis, the new
system would use a data bus to distribute information to a num-
ber of computers, each of which would be capable of acquiring
and processing information from any of the submarine’s sensors –
what was known in the computer jargon of the time as distributed
architecture.
The submarine operators at the SWSC and at the project office
quickly seized on this vision. Peter Briggs recalls that they began
giving a series of good lunches at HMAS Watson for the various
combat system makers and told them of their ideas for the new
system. ‘They all shook their heads and said it couldn’t be done.’9
Despite the scepticism of those who would be asked to build it, the
concept of a fully integrated combat system with distributed archi-
tecture became part of the requirements for the new submarine.
The attitude of the submariners, inspired by the Oberon update,
was: ‘We don’t want yesterday’s system. We want tomorrow’s!’
In 1981 Captain Orm Cooper was the director of naval
weapons design, and recalls that one thing that particularly
36 THE COLLINS CLASS SUBMARINE STORY
worried him with the new combat system specifications was Peter
Briggs’ insistence that it be able to assimilate and correlate up to
1000 contacts simultaneously, and reduce them to the six most
threatening contacts. This demanded enormous data processing
power and was a major technical challenge, but Briggs always
postulated sitting off the straits of Malacca where the submarine
had to know what was going on when there were ships and boats
everywhere.
The requirements that emerged from the combined efforts of
the various groups over several years and were issued in February
1983 were for a large submarine with a range of 10 000 nautical
miles; submerged endurance of 10 weeks; an indiscretion rate and
noise signature significantly better than the Oberons; 25–30 per
cent faster; better availability for operations; cheaper, quicker and
less frequent refits; and a modern combat system.
But where were the new submarines to be built? At Vickers’
yards at Barrow alongside the Royal Navy’s mighty nuclear sub-
marines? At another European shipyard? At one of Australia’s
historic naval dockyards, Cockatoo Island or Williamstown? And
how would they be built? By the traditional craft methods of
Vickers at Barrow or Electric Boat at Groton, Connecticut? Or
with the new modular construction techniques being developed
by European submarine builders? And would Australian indus-
try be tossed a few crumbs off the table or did the project offer
genuine potential for industrial regeneration and technological
progress? The surprising answers that were developed to these
questions came from an even more surprising source – a little-
known and now forgotten engineering company, headed by a
German described as ‘the most difficult man you will ever meet’10
and an Australian engineer with expertise in falling bridges and
offshore oil platforms.
CHAPTER 5
‘We can’t build submarines, go away’:
Eglo Engineering and the submarine
project
37
38 THE COLLINS CLASS SUBMARINE STORY
The site was later to expand into that which built the Collins class
submarines. It was an Australian pioneer of novel shipbuilding
techniques and more flexible working arrangements.
As the 1970s resources boom faded in the early 1980s Hans
Ohff realised that future work for Eglo Engineering lay beyond
the resources sector. It was then the British Vickers company
approached Eglo to assist with the feasibility study for the
next Australian submarine. Hans Ohff, always fascinated by
submarines, quickly became enthusiastic about Eglo becoming
involved in building them. However, he concluded that Vickers did
not want to build in Australia but at most to assemble imported
submarine ‘kits’ at Cockatoo Island or send some Australian com-
ponents to Britain.
But Hans Ohff was convinced that submarines could be built in
Australia. Often angered by Australian insecurity and reluctance
to take on big projects, Ohff was sure all the capabilities were
present and proof was all that was needed. As he says, ‘I was
innocent enough to believe that we would be capable of doing
it, but once you’re in it you curse yourself for being so stupid
in taking it on’. He saw the submarine project as providing a
massive contract for his company but, beyond this, as revitalising
Australia’s manufacturing industry.
Eglo was an Australian listed stock and had majority Aus-
tralian ownership but was partly owned by a German company,
and with Hans Ohff as its public face it was widely regarded as
German. Ohff felt it needed an Australian image, so he recruited
Dr John White from Woodside Petroleum. White had ‘a good
engineering brain and very clear thought processes’ and Ohff
approached him to run a campaign to build the new submarines
in Australia, with Eglo as the prime contractor.
John White had trained in civil engineering at the University
of Adelaide before working at the federal Department of Works,
where he was a structural engineer on projects like the Black
Mountain telecommunications tower and the Casuarina Hospital
in Darwin. He was involved in the investigation into the collapse
40 THE COLLINS CLASS SUBMARINE STORY
projects. Ohff and White were intrigued by the Swedes. They had
known little about them before the visit, but were impressed by
their good English, engineering skills, technical innovation, hon-
esty and general likeability. The Dutch had the only submarine
that approached compliance with the Australian requirements,
but it was hard to build and expensive. Ohff and White felt Vickers
treated them with complete disdain, despite their archaic facilities
and union-dominated yards.
Ohff and White decided that pro-British sentiment in Australia
and a lingering anti-German feeling would prevent the Germans
beating Vickers in a head-to-head contest, so they decided that
Eglo should try to create a viable, if unlikely, third competitor.
Consequently, they continued talking with the Swedes, and pro-
moted them vigorously in Australia. In 1982 Eglo Engineering
formed a joint venture with Kockums to put together a bid – on
the basis that either side could opt out if it believed the bid would
not win.5
The currents of history and the vagaries of luck came together
to favour the campaign to build submarines in Australia. The
growth of the Australian economy since 1945 came to a sud-
den end in 1974 when the profligacy of the Whitlam government
coincided with the first oil shock to produce a severe recession
accompanied by rampant inflation. High unemployment and high
inflation continued throughout the Fraser government of 1975–
83, leading to a rising groundswell of opinion questioning the
central tenets of the ‘Deakinite settlement’ that had been the basis
of Australian public policy since the early years of federation.
The settlement had been based on the White Australia policy,
centralised wage fixing and protection of industry. It was inher-
ently introspective, defensive and dependent, fostering ‘a weak
domestically oriented business culture and a union mythology
of a workers’ paradise’.6 After a century of protectionism,
Australian manufacturing industry was inefficient, uncompetitive
and focused on making products for the small domestic market.
Unusually for a developed country, Australia’s exports were over-
whelmingly of primary products, leaving it highly vulnerable to
price fluctuations on world markets.
The nature and causes of and remedies for the structural defi-
ciencies of the Australian economy were fiercely debated through-
out the 1980s and a consensus emerged – transcending traditional
42 THE COLLINS CLASS SUBMARINE STORY
44
THE ACTS OF THE APOSTLES 45
widespread belief that Australia could not make the light, strong,
high-yield steel required, and at first the project team did not ques-
tion this. They made enquiries overseas to source steel supplies and
were surprised when foreign manufacturers replied that Bunge
Industrial Steels in Port Kembla was a world leader in high-yield
steel. The team was assured by Bunge’s chemist and production
manager that such steel could be supplied. Told 12 000 tonnes
would be needed, the production manager said Bunge could sup-
ply it in a fortnight if they worked double shifts.
After this, the project team began applying the same test to
everything: ‘You can’t build static converters in Australia’; ‘Who
says so?’ and they would go looking – often beginning with the
Yellow Pages – for Australian companies that made a particu-
lar product or were involved in a particular area. In most cases
they were surprised at how many Australian companies could do
the work, although most had no previous experience of defence
work.
Another central issue for the project team was quality assur-
ance. Sheltered behind high tariffs, Australian manufacturing had
never had to compete on quality, and standards were variable at
best and appalling at worst. Attempts to implement international
standards in Australia were first made in the late 1970s, for the
Oberon refits. The new submarine project became the catalyst
for the much wider diffusion of quality control systems. Defence
work, and submarine construction in particular, demands higher
quality than normal, and in the early 1980s only 35 Australian
companies were certified. To achieve the building (rather than
just assembly) of submarines in Australia, companies across a
broad range of industries had to be able to meet the required
standards. The South Australian task force gave enormous sup-
port in this area, calculating that emphasis on quality would
favour a new site rather than the archaic dockyards in the eastern
states.
The project team spread the word about quality assurance
and quality control. They had to persuade companies to invest
in gaining quality assurance accreditation. This was hard to jus-
tify just for six submarines, so they emphasised the broader view
that the step would bring wider benefits, particularly in open-
ing export markets. The campaign was highly successful and by
1998 more than 1500 companies were certified for defence work,
THE ACTS OF THE APOSTLES 49
The rest of the navy was anti-submarine and there were big
problems keeping support for the project in the navy. A
critical element of this was to keep the price down – they had
to convince the government that it would not be too
expensive building in Australia, and a central part of this was
the development of an appropriate industrial environment.
This led the project team into negotiations with the
ACTU and especially the leaders of the Metal Workers Union
such as John Halfpenny. These blokes, who I wouldn’t have
given two bob for before, understood exactly what they
wanted and understood the need to reform industrial
practices so that shipbuilding could be kept in Australia. The
project team wanted a greenfields site with just one union
operating in order to avoid the demarcation disputes which
crippled Williamstown and Cockatoo. The project team
talked to the ACTU to minimise the industrial risk and also
to develop something like workplace agreements. The
submarine project office did not get officially involved in
these negotiations as they felt it would not look good for
uniformed officers to be talking to union officials. But in the
informal talks they got the unions to agree to the basic needs
of the project and this was central to the good industrial
relations throughout the project.13
sought subsidies and tariffs. The unions were locked into protec-
tion as the solution to job losses in manufacturing.’22 To Button,
the cures for Australia’s economic woes did not lie in increasing
protection but in ‘revitalising manufacturing by means of better
technology, a skilled workforce and flexible work practices’ – a
similar mantra to the one coming from the submarine project
team.
John Button found Graham White ‘the most impressive of the
navy people’, and he accepted White’s arguments for building the
submarines in Australia. Button was ‘strongly opposed to buy-
ing “off-the-shelf” submarines or anything else’ and he believed
that the project could have enormous spin-offs for the revitalisa-
tion of manufacturing. Although he feels the claim that he was
responsible for the decision to build the submarines in Australia
overstates his influence, most people close to the project feel that
his role was crucial and he was one of the submarine project’s
staunchest supporters in the cabinet.
In 1984 John Button was one of several cabinet ministers to
visit Sweden. One of his meetings was at the Federation of Swedish
Industry, and he recalled that: ‘At lunch I found myself sitting
next to Mr Roger Sprimont, a former naval officer and a director
of the shipbuilding company, Kockums. It was not, I think, an
accident.’23
CHAPTER 7
‘But how will you judge them?’: the
tender evaluation process 1984–85
58
BUT HOW WILL YOU JUDGE THEM? 59
The board noted that the 2400A failed to meet the require-
ments for submerged endurance by as much as 30 per cent
because it lacked sufficient battery storage.18 Electrical generat-
ing capacity was inadequate and during snorting both converters
would be required to keep systems functioning while the batteries
recharged.19 An overload would cut power to lighting, commu-
nications, hydraulics, air conditioning and the combat system.
Despite its size, the Type 2400A lacked space to carry the weapon
load the navy wanted.
While considerable redesign would be necessary to accommo-
date the four additional weapons required, the evaluation board
considered that the technology of the Type 2400A was of a high
level and acknowledged the value of continuing Australia’s close
ties to the Royal Navy and Britain’s military research and devel-
opment program. The 2400A was rated overall as a ‘marginal’
proposal.
The Kockums proposal, the Type 471, was also a design for a
large submarine of 2215 tons. It was the only design apart from
the Type 2400A that could fit the large bow sonar that was part
of the Rockwell combat system. With a high volume allocated
to batteries the assessment indicated that the battery endurance
requirement could be exceeded by 75 per cent. It was also capable
of exceeding the deep diving depth by 18 per cent. On the other
hand, at periscope depth the Type 471 could reach only 75 per cent
of the specified speed before the propeller started to cavitate.20
Noting that the design ‘has not undertaken any tank testing’,
the board thought that the cavitation problem could be recti-
fied by such testing, perhaps in conjunction with a new propeller
design.21 A number of other problems were identified, including
the use of seawater cooling systems and unsuitable high-pressure
air distribution.22
It was the ‘novelty’ of the Swedish proposal and Kockums’ lack
of experience with large submarines that most worried the board.
Furthermore, Sweden was not part of NATO and this raised
concerns that the United States might refuse to supply informa-
tion about American weapons and systems. Indeed, the US Navy
had advised Admiral Rourke in May 1984 that it was unlikely
the United States would release technology to Sweden. Kock-
ums’ response was to propose sub-contracting the development
of the weapons handling system and torpedo tubes to the British
BUT HOW WILL YOU JUDGE THEM? 67
Even the favoured IKL design failed to meet all of the required
ship’s characteristics. Considerable additional effort would be
required during the definition study to design the submarine that
the navy wanted. The problem confronting the Tender Evaluation
Board was to identify the companies that could best undertake
that task.
The invitation to express interest in supplying the combat
systems for the new submarines attracted five acceptable pro-
posals. These were from the Dutch firm of Hollandse Signaal-
apparaten (Signaal); a German-British consortium of Krupp Atlas
Elektronik and Ferranti Computer Systems; the British company
Plessey; the French company Sintra Alcatel; and a consortium
led by the American Rockwell Corporation, consisting of Singer
Librascope, French sonar manufacturer Thomson CSF and the
partially Australian-owned software company Computer Sciences
of Australia.
While the initial evaluation of the submarine designs left the
final decision up in the air, the choice of combat system seemed to
be far clearer.
There were some important limitations to all the combat sys-
tem proposals. The request was for designs based on a distributed
architecture. Yet there was no widely accepted definition of what
constituted distributed processing, merely a generally accepted set
of characteristics: that particular functions were not dependent on
a single processor, that system databases were replicated around
a network, and that there was automatic backup around the net-
work in the event of a partial failure.26
The requirement also called for the system to be written in
Ada, an untested software language defined by American defence
development guidelines since no functional specifications existed.
Harry Dalrymple recognised that the selection of systems language
was crucial because it would drive the future costs and support
requirements of the combat system, so, after an evaluation of pro-
gramming languages by DSTO, each supplier was asked to provide
prices for using Ada or alternative programming languages.
Faced by conceptual novelty and technological risk, none of
the tenderers used a distributed architecture and two chose not to
adopt Ada. Most adopted close-coupled federated systems, while
Rockwell’s proposal was described as a loose-coupled federated
system. The difference appears to have been that where, for
BUT HOW WILL YOU JUDGE THEM? 69
While the tenders for the submarines came from individual Euro-
pean companies, the contracts for the project definition study
were made with consortia formed by Kockums and HDW with
Australian industry partners.
The joint venture formed by HDW and Eglo Engineering was
not the result of love at first sight. In early 1983 Hans Ohff and
John White of Eglo visited all the major submarine builders in
Europe. Ohff recalls:
76
SPIES, LEAKS AND SACKINGS 77
Once the short-list was announced CBI tried to sell itself to Kock-
ums, which was impressed with the company’s project manage-
ment skills, but worried by its American ownership, feeling that
this would be politically unpalatable with the focus so strongly
on Australian involvement. Kockums knew that the Australian
government would insist on at least 50 per cent Australian own-
ership. Ross Milton recalls that the CBI team was talking with
Roger Sprimont and Olle Holmdahl in the Wentworth Hotel in
Sydney when Sprimont suggested that they should call Geoff Davis
of Wormald International.
Wormald had grown from its origins as a fire protection com-
pany to be one of Australia’s largest diversified conglomerates in
the mid-1980s. By the late 1970s Wormald was trading in more
than 70 countries, with sales of over $1 billion and a workforce
of more than 20 000. Its main businesses after fire protection and
security were electronics and engineering, and it was looking to
develop its defence business.
Geoff Davis, Wormald’s managing director, had a close work-
ing relationship with senior members of the Labor Party and the
trade unions and he received strong hints that the government
would be happy to see Wormald involved in a consortium with
Kockums. He was at the Wentworth Hotel 15 minutes after being
called. He had already discussed with Industry Minister John
Button his view that a viable consortium would consist of
Kockums as designer, CBI as project manager and hull fabricator,
Wormald to manufacture mechanical and defence equipment, and
the Australian Industry Development Corporation as the financial
partner. Davis suggested calling AIDC, which quickly agreed to
join the consortium.
80 THE COLLINS CLASS SUBMARINE STORY
the Swedish government denied that there had been any breach
of security at Kockums, Sinclair maintained his concern about
Swedish security.8 For their part, the Swedes believed the story
was built up by the Germans in an attempt to discredit Kockums,
as part of a campaign in Australia.9 However, the political oppo-
sition to the project in Australia was generally pro-British and
wanted to discredit both short-listed companies, as shown by
attention drawn to security lapses of the West German govern-
ment and the allegations that IKL/HDW had used bribery to win
the Indian submarine contest.10
While the ‘Swedish spy’ story had little substance or signifi-
cance, another controversy with even less substance had serious
repercussions. The day before the announcement of the companies
selected for the project definition study, the project team was to
brief the ALP Caucus. This was a formal courtesy largely intended
to assist government back-benchers defend the decision in public
discussions, and had no influence on deciding the winners. The
Caucus was not familiar with the details of the program and asked
the project team to prepare a list of questions that would ensure
the briefing covered its most important aspects. The meeting was
also to be briefed by the submarine design tenderers.
The IKL/HDW team was unsure of the nature of the event and
asked Graham White what matters the politicians were likely to
pursue. White recalls that he told them the project had been so
extensively covered that a search of the newspapers would garner a
good idea of potential questions. The Germans took this seriously
and, combined with Juergen Ritterhoff’s deep knowledge of his
design, answered questions so easily they appeared to have had
advance knowledge of the questions.
Others, however, still maintain that the list of questions pre-
pared for Caucus was passed to the Germans. Whether this was
so or the Germans were exceedingly diligent, the smoothness of
their presentation did not pass unnoticed, especially by Graham
Campbell, the maverick Labor member for Kalgoorlie and a
prominent supporter of the British bid. Campbell later instigated
an Ombudsman’s investigation into whether assistance to the
German team constituted improper dealing in the selection of the
definition study participants.
The German team was oblivious to the commotion. They
always prepared carefully for meetings with the help of Peter
84 THE COLLINS CLASS SUBMARINE STORY
There was never any chance that a Queensland bid could succeed
with Labor in power federally, and Tasmania and Western Aus-
tralia were seen as lacking the necessary industrial base. Victoria’s
bid never gathered momentum and none of the builders liked its
proposed site north of Geelong. The New South Wales campaign
lacked focus in the early years, with Cockatoo Island, the Newcas-
tle state dockyard and even Jervis Bay fighting to be the preferred
site.
A year before the decision the New South Wales Labor gov-
ernment gave an open chequebook to the Newcastle bid, which
had formidable support from the right-wing of the state ALP. One
senior faction member allegedly told Geoff Davis of ASC: ‘You’ve
got to understand about the ALP right – we make people or
we break them. Do you want to be made or broken?’ However,
the Newcastle bid was not helped by some bizarre campaigning.
Barry Unsworth, who became premier in 1986, argued that the
submarines should be built in Newcastle to scare the Russians. Jim
Duncan retorted that the balance sheet of the hopelessly insolvent
state dockyard would scare them more.
Consequently, the South Australian campaign had sufficient
momentum and economic logic to retain its lead and, in spite of
some last minute scares, both submarine builders and the federal
government supported Adelaide as the preferred site.15
CHAPTER 9
The project definition study 1985–86
89
90 THE COLLINS CLASS SUBMARINE STORY
With Oscar Hughes in charge of the project office and the con-
sortia in place, the new submarine project entered one of its most
crucial and controversial periods. Most people with a background
understanding of submarine design and development expected
that IKL/HDW would be one of the participants in the project
definition study; the inclusion of Kockums was startling. The
promising but untested German design was not without risks and
prudence might have suggested a more predictable counterbal-
ance. The British and Dutch camps expected their more mature
designs would put them in this role.2
Yet the Swedish Type 471 appeared even riskier than its Ger-
man competitor: it was more than twice as large as any of
Kockums’ previous submarines, the company had no experi-
ence in managing overseas building programs and Sweden’s non-
membership of NATO posed security problems. There was a
widespread feeling that Kockums was chosen as a straw man to
be tried, found inadequate and thus ensure the selection of the
German submarine.3
If the bets were on IKL/HDW to be accepted as the submarine
builder, no odds would have been posted against Rockwell to
provide the combat system. Cabinet insisted on a competition,
but it was clear that Rockwell was the preferred tenderer and
most people thought that Signaal was in the competition simply
to entice a better offer from Rockwell.4
To assist the designers to understand the navy’s expectations,
the project appointed liaison teams to work with each company.
These were made up of submariners, navy and civilian engineers
and naval architects and, on the combat system side, some of the
software engineers from the SWSC who had designed the ambi-
tious combat system requirements. Mick Millington from the cen-
tre went to Signaal in Holland with submariner Rod Fayle from the
project office. Rick Neilson went to the Rockwell headquarters
in Anaheim together with submariner John Dikkenberg who,
because he spoke Dutch, had expected that his posting would
be with Signaal.5
Engineer Greg Stuart and Commander Rick Canham went
to Malmö to work with Kockums, while engineer Peter Bull
and Commander Tony Parkin were sent to Lübeck and Kiel as
the liaison team with IKL/HDW. Greg Stuart had been working
with submarines since 1972 and wondered if going to Sweden
THE PROJECT DEFINITION STUDY 1985–86 91
The general perception of those involved was that the liaison team
with IKL/HDW was less effective in guiding the designers to meet
the Australian requirements. The liaison team in Germany was
housed in separate buildings from the designers and they never
became close to the IKL and HDW staff. Later, after Australian
Maritime Systems had lost the competition, John White observed
that there seemed to have been bias in the operation of the liaison
teams, with that in Sweden more closely involved than the team at
IKL/HDW. However, for their part, the German members of the
consortium felt that relations with the liaison team assigned to
them were efficient and useful, although they now think perhaps
not as harmonious as in Sweden.8
While the project teams were packing their bags and head-
ing to Europe or America late in 1985, Oscar Hughes and John
Batten at the project office were developing a new management
control system to compare the costs of every element of the
different proposals under study. When in charge of naval pro-
duction, Hughes had concluded that contractual measures for
evaluating shipbuilders’ progress and authorising payment were
unsatisfactory. The system of ‘milestone’ payments used on
projects in the 1970s and early 1980s proved difficult to moni-
tor as it was hard to check that everything necessary had been
done for each milestone. For example, if the milestone was that
the funnels were to be completed, there had to be a way to check
that all the necessary piping and fittings had also been completed,
94 THE COLLINS CLASS SUBMARINE STORY
Hughes told him: ‘That’s all very well but I can’t afford any more
money.’21 The directive was authoritative and, for the remainder
of the definition study, Neilson and his colleague John Dikkenberg
told Rockwell to cut costs. They were so persistent that Rockwell
reduced the number of control consoles in its design to reach a bid
price of around $460 million. Nonetheless, Neilson and Dikken-
berg remained impressed by the development of the Rockwell
system and the full-scale control room mock-ups, which allowed
them to see how the system would function.
From August 1985 Neilson’s colleague from SWSC, Andrew
Johnson, was also in Anaheim representing Computer Sciences in
Rockwell’s consortium. Having been one of the leaders in devel-
oping the combat system concept, Johnson had a good idea of
how it was supposed to work. However, he found that Rockwell
knew little about submarine combat systems and that it had
entered the Australian competition to gain an entry into this mar-
ket. That was all too apparent to another consortium member,
Singer Librascope, which owned the expertise and had no desire
to create a competitor. Rockwell also had difficulty working with
Thomson CSF, the French sonar makers, which also feared for
its intellectual property. Well into the project the problem of link-
ing the components together with software written for Rockwell’s
data bus was looking no closer to solution.
Singer Librascope had expected to build and integrate the
system and write the system software but not to reveal source
codes as this would threaten its market position. This undermined
Rockwell’s strategy, so it proposed to Johnson that CSA should
write the software, thus creating a system that Rockwell could
market. CSA had entered the consortium to perform a compara-
tively modest $40 million task of assembling the Australian end
of the project and producing things such as land-based training
systems. Writing all the software would be worth around $100
million and placed CSA at the centre of the system’s development,
but at the cost of reducing or removing access to Singer Libra-
scope’s expertise. Johnson agreed and, he says, ‘within that deci-
sion the Greek tragedy starts’.22
Oscar Hughes also visited Signaal in mid-1986 and Mick
Millington recalls him reinforcing the line of financial discipline,
telling the Dutch company’s executives: ‘If you come in at one dol-
lar over $500 million we’re not going to talk to you any more.’23
THE PROJECT DEFINITION STUDY 1985–86 99
Signaal’s financial manager was absent from the meeting and was
unimpressed by the imposition of a cost ceiling. Unlike their coun-
terparts in the US, the liaison team was unable to convince Signaal
to heed the warning and the company continued a single-
minded pursuit of the specifications, designing a system it priced
at $520 million. Then, over lunch with senior defence bureaucrat
Malcolm McIntosh, Signaal’s Canberra representative, Altingh
von Geuzau, learned that Rockwell had reduced the quality and
cost of its bid. The Dutch followed suit, tendering their bid a week
late at a more modest cost of $480 million.24
Having changed its early conservative course, Signaal devel-
oped the combat system of Millington’s aspirations. Further,
Millington had come to respect Signaal’s abilities and had no
doubt that it could deliver the system it promised. ‘With the Dutch
and Germans a handshake is a firm commitment, it is solid stuff,
while my experience with American companies is that the hand-
shake is only the beginning of negotiations for contract amend-
ments.’ However, Signaal’s late change of direction meant that it
was unable to adequately document its new system so that when
the evaluation began it was difficult to match the documentation
with the specifications.
In Sweden, Kockums continued to develop its design appar-
ently uninhibited by costs. Greg Stuart noted that the company
had little commercial sense, as it had only designed for the Swedish
navy in an arrangement that was closely consultative. He found
that Kockums’ approach was very different to any in his experi-
ence, as it was forced to constantly evolve its own designs because
of Sweden’s isolation from NATO. Stuart, who has the reputation
of being an engineering perfectionist, concluded that in subma-
rine building there was ‘the right way, the wrong way and the
Swedish way – the Swedish way is not necessarily wrong, but it is
different’.25
Olle Holmdahl headed the massive design effort by Kockums,
where the company contained its costs within the $10 million
provided by the Commonwealth only by discounting the design-
hour rate. The effort of the 50-strong design team was focused on
the central design issues by allowing them to select the best for-
eign equipment in specialist areas. This was familiar practice for
Kockums but generally unusual in submarine design, where most
builders preferred their own nation’s components. The Swedish
100 THE COLLINS CLASS SUBMARINE STORY
101
102 THE COLLINS CLASS SUBMARINE STORY
As Greg Stuart put it: ‘With the German submarine, if the crew
were in bed, the combat system turned off, the lights off, etc then
it could do what it claimed – but it could not do it in a real-
istic operational mode.’ This was because, at speeds less than
seven knots, propulsion demanded only a low drain on the bat-
teries. Other requirements of a submarine’s ‘hotel load’ provided
the main demand for power. A submarine could greatly extend
104 THE COLLINS CLASS SUBMARINE STORY
Greg Stuart agrees with this assessment, but people from the centre
deny this was their aim, claiming that the combat system was
designed to have links with the ship management system but that
they were always intended to be separate systems.
In essence, the final conclusion of the evaluation of the sub-
marines was that Kockums had designed a warship where the
Germans had designed a product:
The navy was satisfied with the technology that the definition
study had delivered. Both combat systems appeared to meet the
navy’s ambitious objectives, were within budget and appeared to
need no major modification. It was only later that members of the
evaluation team reflected that the time available for the definition
study evaluation had been far too short to form an accurate picture
of the likely performance of either.16
With the submarine design, the project had again produced
an unexpected result. Many submariners felt that the evaluation
was flawed and that the German design should have won, but
others involved thought the result unsurprising and the quality
of the two designs as different as chalk and cheese.17 The senior
naval command felt that the outcome was sufficiently unusual to
order a review to see if the required ship’s characteristics were
misleading. Kim Beazley, too, was surprised and a little concerned
as, like most others, he had expected the German bid to win. He
was reassured when told that the Americans had been informed
of the choice of Kockums and had supported it. Significantly, Kim
Beazley recalls being told that: ‘The Americans were surprised at
the Swedish quietening techniques and in some aspects they saw
them as well in advance of their own and they were going to seek
further information on them.’ Further, he says: ‘I have a bit of
a suspicion that they [the Americans] may have played a much
larger role than even I suspected at the time.’18
Surprised though it might be at the results of the evaluation,
the navy now faced a more serious and unexpected problem. The
definition study had failed to produce its central outcome, a set
of firm performance and production details that could easily be
turned into contractual form. The proposals were considered to
be at the preliminary design stage and ‘requiring substantial devel-
opment before a build specification could be prepared’. This was
110 THE COLLINS CLASS SUBMARINE STORY
The German design team do not accept that there were legiti-
mate technical grounds for their loss and argue that the decision
was made at a higher level that the Swedish bid should win.
The evaluation was controversial. The transformation of
the German design from clear favourite to failing to meet
many requirements was unexpected and the recalculation of the
designers’ claims caused uproar. Following the decision, Jürgen
Ritterhoff said:
Hans Saeger and Jürgen Ritterhoff still think ‘it was hard for
the evaluation to make us a loser’. They believe their offer was
superior on every count, although they concede that: ‘Maybe we
were not flexible enough.’ Yet the Australian submarine opera-
tors and engineers believed they were well qualified to analyse
the German design after two decades of sustaining Oberon opera-
tions. Ritterhoff had read the Australian requirement as an exten-
sion of the Oberon design line and pursued a design philosophy
that avoided too radical a departure from that tradition, so the
Australians readily understood his approach.
To Oscar Hughes and the project team, the greater risk of the
Swedish proposal would be partially managed by designing it to
Swedish naval standards, which the Australians considered to be
‘fully professional’. Hughes was confident that the project could
manage the risk and that the more innovative Swedish design
would produce a more effective submarine for the 1990s and
beyond than would the German design ‘in which I had very little
confidence’.29
Hans Ohff believes that the Germans were too conservative
with their design and since the Swedes were agreeing to give
Australia everything it asked for the Germans should have
responded. The late 1980s was an era of risk-taking and he could
sense that the Australians were prepared to take a risk with their
submarine design in an effort to get the best – though he is certain
that they were not aware what an enormous risk the Swedish boat
really was. But Ohff says that message never got through to the
German designers, who remained with their strategy of satisfying
the base requirement and winning on price.
For Kockums, the Australian deal represented the possible sal-
vation of the company, while for HDW it was only one of many
export projects they were pursuing. Consequently the key people
at HDW did not concentrate on Australia and there was a con-
tinuously changing mood on HDW’s board. In contrast, Roger
Sprimont ‘made it his heart project’, and the Swedish marketing
was brilliant.
John Bannon, who was Premier of South Australia and presi-
dent of the Labor Party, always believed the Swedes would win.
He points to the enthusiasm for Swedish industrial methods in
the Labor movement in the 1970s and early 1980s.30 Although
some high-profile Labor leaders such as Paul Keating and Lionel
116 THE COLLINS CLASS SUBMARINE STORY
Bowen supported the German bid, they were in a minority and the
general feeling in the Labor movement was very much in favour
of the Swedes.
Complementing the enthusiasm for Sweden in the Labor move-
ment, many in the submarine community came to support the
Kockums design. The Australian submariners, flushed with the
success of the Oberons’ weapons update and the glamour of their
operations in distant waters, were determined to have the most
advanced submarine they could persuade the government to buy.
They were not looking for a conservative, risk-free design, but
something at the leading edge of technology – not a production-
line Volkswagen but a custom-made Ferrari. All these factors pro-
vided strong if subtle pressure in favour of the Swedish design.
PART 2
THE HONEYMOON
YEARS 1987–92
CHAPTER 11
‘Keen as mustard to do a good job’:
setting to work 1987–89
119
120 THE COLLINS CLASS SUBMARINE STORY
the project and they were never fully replaced. The later history
of the project would have been very different if one or both had
remained involved.
The schedule for building the submarines was always seen as
being ambitious, and ASC had to plan rapidly to mobilise peo-
ple and resources to get the project moving. Olle Holmdahl of
Kockums recalls that CBI played a crucial role at this stage:
It was very important for ASC to have CBI on board for the
early years. They had submarine expertise . . . they knew steel
construction, and they were experienced project managers.
They knew how to set up projects in new countries. Kockums
did not have the skills, people or experience to do this. So it
was CBI people who did all of the work in setting up the
project.1
Wormald, Ross Milton, Jim Berger, Jim Muth and Graeme Ching
of CBI and Bath Ironworks, and John O’Neill and Olle Holmdahl
of Kockums. However, most of these people left the project or
returned to their parent companies when CBI and Wormald were
bought out and the shareholding arrangements in ASC changed.
There was a major recruiting program for staff at all levels.
The first chief executive, Don Williams, began work on 1 January
1988. A civil engineer with a background in railways and a doc-
torate from Imperial College in London, he came to prominence
for his work on rebuilding Melbourne’s West Gate bridge. Before
coming to ASC he was general manager of Australian National
Railways.
Although views on Williams have been coloured by later
events, there is general agreement that he was ‘a great influence
and a good one for the early part of the project’.3 He was intelli-
gent, a good public speaker, politically astute and had many con-
tacts in Canberra. He was somewhat aloof from his staff, but
drove the project forward with enormous energy. Oscar Hughes
saw him as ‘a visionary in the context of doing things for Australia
[who] fought hard to make ASC a success’.
From late 1987 a large number of engineers and other profes-
sionals joined ASC. Martin Edwards had worked for DSTO at
Salisbury, north of Adelaide, for eight years before joining ASC in
January 1988. There were two intakes that month of people who
were to be seconded to Sweden, to work either for Kockums or at
the ASC project office in Malmö. After a brief induction program
about 24 ASC staff were sent off to mid-winter in Sweden. Most
of them were young, with the average age being in the mid-20s.
Edwards worked with the design team at Kockums for more than
two years before returning to Adelaide.
Jack Atkinson had worked for the Department of Defence as
a software engineer for 14 years before joining ASC in 1988. He
came as a senior systems engineer to work on the weapons system
integration. Software quickly came to be seen as one of the main
risk areas of the project and ASC built up a far greater capabil-
ity in the area than originally planned. Ron Dicker, who had led
the Signaal combat system bid, recalls that he was on holiday in
Italy when Roger Sprimont called. He was concerned about the
combat system contract and needed experience and knowledge to
monitor Rockwell and protect Kockums’ interests. Dicker set up
124 THE COLLINS CLASS SUBMARINE STORY
Grieg, recalls that: ‘He was not the easiest person to work with,
but I guess he wasn’t trying to be easy.’
The Swedes, both at Kockums and in the Ministry of Defence,
respected and admired Oscar Hughes. Major General Kurt Blixt,
who chaired the committee supervising the memorandum of
understanding between the Swedish and Australian governments,
says: ‘We had no problems getting on with Oscar Hughes – he
had a role to take the project forward. He was rather hard when
it came to discussions but he was always fair.’ Similarly Tomy
Hjorth, managing director of Kockums and chairman of ASC from
1990 to 2000, thought Hughes an excellent project director: ‘He
made many decisions at a time when decisions were needed on a
continuous basis; he made deals, most of which were reasonable.’
However, Hjorth also observed that: ‘Oscar Hughes was running
the project outside the rest of the navy. This was necessary but it
created enemies for the project.’
Others shared this view that the project had become dissoci-
ated from the navy. Paddy Hodgman, who was the navy’s public
information officer from 1990–93, observed that:
In the late 1980s there was a substantially independent and
powerful submarine project. They still saw the chief of the
navy as being in charge but there were centrifugal forces and
divergences of view and approach between the project and
stakeholders such as the submarine community, the rest of
the navy and others in defence and government. This meant
that ASC was always able to find folk to play off against each
other. Defence did not have it in one sock – it did not have
unity in what it wanted, what was wrong, what the fix might
be – effectively defence had disempowered itself.11
The consequences of this were not evident at the time, but became
clear when the submarine project ran into strife later in the 1990s.
Generally, the feeling around the project – at ASC, Kockums and
the project office – was that the project’s early stages had been
well managed and that all was going well.
CHAPTER 12
Designing the Collins class1
130
DESIGNING THE COLLINS CLASS 131
Further, almost all of the equipment that went into the submarines
was specific to purpose and very little ‘off-the-shelf’ equipment
134 THE COLLINS CLASS SUBMARINE STORY
was used.3 Kockums, even where it did not design the equipment
itself, was responsible for supervising the sub-contractor and for
integration. The company had 25 000 drawings to do, as well as
drawing up parts lists and preparing the procedures for production
and testing.
Kockums’ partners in ASC felt that the biggest risk of the
project was the design process, and feared that this might be
beyond Kockums. Although Kockums’ risk management evalu-
ation convinced the partners that the potential problems could be
successfully overcome, most people involved believe that Kock-
ums underestimated the size of the design task. Mark Gairey, a
naval architect with the Australian navy team in Malmö, says that:
had a pretty good idea what they had to do. They’d been
designing and building submarines for 70 odd years.
However, one of the problems we encountered was that they
kept looking at things in a Swedish frame of reference. There
were some interesting and prolonged discussions which
ended up with us saying: ‘That’s fine but we simply can’t live
with that solution in an open ocean environment. It’s all very
fine for you guys where, if it goes wrong, you’re sitting in a
little puddle of water and can fix it, but we can’t.’ We had
several discussions of that type on and off because ultimately
we had a specification but there were still gaps in it.
When the navy team and Kockums could not agree on an issue,
they would report back to the project office in Canberra outlining
the problem and saying what they thought should be done. It then
became a contractual matter back in Australia between the project
office and ASC.
To help ASC achieve 70 per cent Australian content Kock-
ums set up a design office in Adelaide. This office was manned
by Swedes and Australians, with most of the Australians who had
been working in Malmö returning to Adelaide by 1990 or 1991. At
its peak this office had about 40 Australian and 20 Swedish staff,
headed first by Jan Hansson and later by Martin Edwards. The
fact that an Australian took over from a Swede was in itself one of
many vindications of the project’s aspiration to develop Australian
skills. As design manager at ASC Edwards was responsible for all
the detailed design groups and some of the engineering support.
The design groups covered hull design, mechanical design, out-
fitting design, weapons handling, electrical design and electrical
installation, focusing on finalising the detailed design components
and supporting production.
With design work proceeding on opposite sides of the world,
communication between the design offices was vital. There were
many issues that required discussion and debate between Adelaide
and Malmö and, with e-mail only coming into common use about
halfway through the project, they had to be resolved by fax or
telephone discussion. It was vital that both design offices have the
same drawings and documentation, so a dedicated link was set up
for daily transfers. Drawings done in Malmö would be encrypted
and sent by satellite, navy to navy, to Adelaide.
DESIGNING THE COLLINS CLASS 137
the sonar and the design had to be stretched one metre forward
to accommodate the sonar accessories and one metre aft to retain
balance, while the sonar bow dome shape had to be drastically
re-designed. The modified design was not tank tested, mainly due
to disagreement about who should bear the cost of building a new
model to test.4
Mark Gairey says that in retrospect both the Swedes and
the Australians were looking at potential noise problems from
the perspective of the Oberons, where the noise came mainly
from the machinery. Machinery noise was overcome in Swedish-
designed submarines by construction using resilient platforms
with rubber isolation elements. This link between the design and
the modular construction techniques had been one of the great
attractions of the Swedish bid. However, while concentrating
on eliminating machinery noise, neither the Swedes nor the
Australians anticipated problems with hydrodynamic noise.
Gairey suggests that:
In part it was our inexperience and in part because of the
way the Swedes operated their submarines, they had never
seen these problems. I’m sure that their submarines would
have the same problems if operated by our people, but they
didn’t so it was a surprise for them as well.
The Swedes operated at very short range. They’re very
much a coastal defence force . . . They went four hours out of
harbour and sat there. They weren’t running at any sort of
speed for any sort of distance . . . Whereas we had big
distances to transit to an operating area and we wanted to
transit as quickly as we could, while remaining undetected. It
was a completely new set of requirements . . . Maybe they
could have done more model testing but they were looking at
Collins through a Swedish frame of reference. They didn’t do
with their submarines what we did so they didn’t have the
problems and they didn’t anticipate that we would. They
didn’t realise our operating environment was so different. In
retrospect they should have done more testing but at the time
it seemed that what they did was fine. We were totally
surprised by the problems we had and the Swedes were just
as surprised.
on six torpedo tubes across the front so that the submarine has a
front like a circumcised dick.’5 The designers agree that the snub
nose of the Collins class creates turbulence when on the surface,
but the submarine spends most of its time submerged, where the
bow shape works well, although the area aft of the bow where
the sonar dome joins the casing was later found to be a source of
turbulence.
Gunnar Öhlund, who worked on the bow design, says the
arrangement of tubes side by side provides compact weapons stor-
age and enables fully automated handling and loading. He argues
that this had no consequences for the hull shape and there are ben-
efits for firing in keeping the torpedo tubes below the boat’s centre
line. This design has worked well with the Swedish submarines.6
SSPA in Göteborg was closely involved in the design of pro-
pellers for Swedish submarines and also for the new Australian
submarine. In the 1980s the Swedish submarines had a problem
with a ‘singing’ propeller but a lot of research and then a few small
marks on the propellers were enough to fix this. However, cavita-
tion was always the main concern with Swedish propellers. SSPA
developed a computer program that prevented the crew operating
the submarines in a way that caused cavitation and this essentially
solved the problem on Swedish submarines before the Australian
project, although it could emerge if the design was changed or the
propeller was poorly manufactured.
Generally the requirements for the submarines were stated in
performance terms, but in some areas design requirements were
specified. One of these was that the propellers be made from
Sonoston or a similar highly damped alloy because it had been
used in recent American submarine propellers.7 Unfortunately the
Australian navy did not known that the alloy was liable to crack
and had been abandoned by the Americans. Mark Gairey com-
ments that: ‘In hindsight, this was a mistake and we should have
concentrated on the “no cavitation” requirement and left it to the
designer to solve.’
A controversial aspect of the design of the new submarines
was the decision to have flat rather than round bulkheads in the
bow and stern sections. The Swedish navy had used both round
and flat bulkheads and decided that either worked. Kockums saw
flat bulkheads as robust, saving space and allowing the torpedo
tubes to be positioned identically. They have been used in Swedish
submarines since the Sea Serpent class of the 1960s, which are still
140 THE COLLINS CLASS SUBMARINE STORY
in service with the Singapore navy, indicating that hulls built with
flat bulkheads can have a very long life.8
Some significant design changes were initiated by the Aus-
tralian navy team at Malmö which, while beneficial, often caused
contractual difficulties. One such change occurred with the air
purification system. Greg Stuart, the senior engineer with the
project, recalls that the Swedish system in the original design
was ‘heavy and inefficient’. Stuart contacted Wellman Processing
Engineering of Birmingham, England, which owned the technol-
ogy used for air purification on some British and American sub-
marines. Working with Wellman, Stuart calculated that changing
the air purification system could save length and weight on the
submarines, and he developed a proposal for a ‘mini-scrubber’
to remove carbon dioxide and other acid gases. The first unit
was called ‘Kylie’, ‘the little Aussie scrubber’, and the second was
called ‘Dannii’. Although Oscar Hughes as project director always
resisted changes as they would threaten the budget and the sched-
ule, he realised that the new air purifier would benefit the project
and approved the change, even though there was an argument
that it should have been a designer’s change rather than a cost to
the project. Greg Stuart says that: ‘We could have left the scrubber
until they did trials and told Kockums that their system did not
meet endurance specifications, but the new system would have
been hard or impossible to back-fit and . . . the boat was getting
too heavy and the scrubber change helped reduce this.’
Another change made late in the design process was the speci-
fication for electrical cabling. A particular ‘low fire hazard’ cable
had been specified in the contract but later tests showed that it
was a serious fire risk. Greg Stuart recalls going to see Oscar
Hughes and saying that the cable would cause a disaster one day.
Although the project was in a poor position to enforce a change
and it would cause delays and increased weight, Hughes agreed
that it was needed.9
The way the change was implemented showed a degree of
commonsense and flexibility that was perhaps lacking later in the
project. Oscar Hughes recalls:
142
BUILDING SUBMARINES 143
he got off the plane. They looked at the two sections without
telling anyone, but the Swedes soon heard that the Australian
admiral was in the submarine wearing a hard hat and overalls.
When Hughes and Stuart emerged there was a line-up of senior
Kockums executives waiting for them. Hughes told them: ‘There’s
a big problem and we need to sort it out.’
Stuart recalls that Kockums held a meeting with its welding
engineers and others who said that the welding problems were not
serious. He disagreed strongly, saying that there were hundreds of
visually identifiable defects and he believed that the safety of the
hull was in question.3
Tomy Hjorth, chairman of Kockums and ASC, recalls that
Kockums suggested keeping the sections in Sweden for several
months to repair the defective welds, but Don Williams and Oscar
Hughes were committed to maintaining schedule and asked that
they be sent to Australia where ASC would make the repairs. The
Australians were doing all they could to keep the project moving
and feared that repairing the welds in Sweden would cause lengthy
delays. On the other hand, Mark Gairey saw it as ‘a game call as
at that stage we were not as certain then of the conservative design
and therefore of Collins’ safety’. Nor were they yet certain that
ASC’s welding at Adelaide would reach the required standard.
Accepting the sections with known welding defects involved a
degree of risk.
How did the problem arise? Greg Stuart argues that the main
reason was that the submarines were built with a new steel
alloy developed in Sweden and improved by BHP and Australian
defence scientists, which required different welding techniques
to those normally used by Kockums’ welders. In addition, the
Australian navy required the use of full penetration welds – where
the Swedes had always used partial penetration welds – and a
new type of welding rod. Stuart’s view is that Kockums was over-
confident in the ability of its welders to adapt to the new tech-
niques and did not rigorously supervise and inspect the work.
Those at Kockums generally agree that the welding was
faulty, but contend that its seriousness was exaggerated and used
by the Commonwealth as a bargaining tool after the relation-
ship between Kockums and the Commonwealth collapsed in the
late 1990s. While conceding that their welders did not prop-
erly follow procedures with the new steel and techniques, they
146 THE COLLINS CLASS SUBMARINE STORY
Mark Gobell, who had worked for O’Connor since 1973, was
among the staff who transferred after ASC Engineering’s takeover
in 1991. One of the first things that happened was that he and
several others went to Sweden to see how Kockums outfitted the
platforms on their sections of the first submarine. They returned to
prepare ASC Engineering to fit out the platforms when delivered
by Perry Engineering. All the equipment, mechanical components,
piping, electrical components and even the trim and fittings were
attached and some pre-testing of the systems undertaken before
the platforms were transported to ASC for insertion into the sub-
marine.
As with all the Australian sub-contractors, ASC Engineering
had to take special steps to meet the project’s quality standards.
It gained quality certification and trained staff, particularly in the
areas of welding and electrical work, to standards far more rigor-
ous than for civilian work. All sub-contractor work was physically
inspected by the submarine project team. At the project office John
Batten was responsible for enforcing contract standards. Batten
recalls that his staff continually checked factories around Aus-
tralia and sampled by physical inspection almost 20 per cent of
the work done. Each month about 160 large reports were made on
the progress of the sub-contractors and the quality of their work.
While the sub-contractors around the world were building
their particular components, ASC’s yard was proceeding steadily
on the construction of the hulls.4 An important milestone was
the ‘keel-laying’ ceremony for the first submarine on 14 Febru-
ary 1990, at which Kim Beazley announced the names of the six
submarines. They were named for six Australian sailors of the Sec-
ond World War – Collins, Farncomb, Waller, Dechaineux, Sheean
and Rankin. HMAS Collins, as the first boat, gave its name to the
class.5
Each submarine was built in six sections, each of which con-
sisted of several ‘cans’. The sections were numbered 100, 200,
300, 400, 500 and 600, with 600 being the forward section and
100 being the aft section. Each sub-section was numbered; so, for
example, the 200 section is made up of a 210, 220, 230, with 210
made up of two cans, 220 of three cans and 230 of two cans –
seven cans welded together to make the complete section.
The first major work at Osborne was welding three curved
plates of steel to make the cans and then welding the cans together
148 THE COLLINS CLASS SUBMARINE STORY
to make four hull sections for the first submarine. Welding the
cans and sections was among the most critical and risky parts
of the whole project. The high-tensile steel used for submarine
hulls required the highest quality welding, with welding problems
being among the most frequent reasons for delays or even failure
of submarine projects around the world. One of the great suc-
cess stories of the project was that the welding techniques used
by ASC, developed in conjunction with DSTO, proved highly
successful.6
The hull construction shop is 150 metres long and 40 metres
wide and is divided into a series of workstations. At workstation
100 the curved plates from CBI were welded to form the can,
using full penetration, manual metal arc welding. The can of about
20 tonnes then moved to workstation 200. Here the ‘T’ stiffeners
from CBI and bulkheads from Perry Engineering were welded into
the cans. The stiffeners were welded to the inner part of the hull
with an automated submerged arc welding machine. One side of
the can would be fully welded and then the whole can would be
picked up, spun around and put down to allow work on the other
side of the T-stiffener welds. Magnetic particle testing occurred in
the weld prior to welding the second side. After the second side
weld was complete there would be 100 per cent visual, 100 per
cent magnetic particle and 100 per cent ultrasonic inspections;
10 per cent of the welds on the pressure hull were also subjected
to X-ray inspections.
All the material on the hull was micro-alloy steel, designed
to absorb energy and buckle rather than fracture if subjected to
explosions. However, such steel loses its granular structure and
therefore its strength if it is cooled too quickly. Consequently, the
steel structure had to be preheated and postheated for all welding
operations. It was potentially extremely dangerous to use heaters
while welding in confined spaces, so ASC developed a process
of heating the steel using low voltage heaters that lessened the
chances of accidents.
With stiffeners and bulkheads in place, the cans were moved on
to workstation 300, put on rollers and welded using an automated
process developed by ASC. The cans rotated past the fixed welding
machine, joining seven cans to make a complete section.
Four sections were built from the outside in – first putting the
cans together, then adding the frames – but several cans in two
BUILDING SUBMARINES 149
sections were built from the inside out. These were the cans with
flat bulkheads in the front and mid sections. In these cans shear
plates were welded first, followed by the stiffeners, the frames
and the infill plates, and finally the hull plate was welded around
the fabricated section, becoming so strong that the production
workers called it the ‘egg crate’.
Before all the sections were welded together most of the tanks
were welded into the hull. There are over 50 tanks in each sub-
marine, including freshwater tanks, ballast tanks, trim tanks, fuel
tanks, waste water tanks and torpedo compensation tanks.
As the cans were joined into sections, they were put in cradles
so they could be moved around the hull shop by rail, and eventu-
ally the whole submarine could be rolled out to the ship lift.
After the welders had finished as much ‘hot work’ as possible,
sections went to the blast and paint chamber, which was fully
enclosed and designed to take all the submarine sections. It would
take several months to blast and paint each section – a source of
frustration because meanwhile nothing else could be done with
the section.
Blasting in the confined spaces of the submarine sections was
difficult and unpleasant work. At each stage the section had to be
vacuumed and inspected before painting. Blasting and painting the
external hull was comparatively easy, especially compared to work
inside the tanks. It was often impossible to paint in winter because
of cold surfaces, and later ASC installed heating to improve the
schedule.
After several months in the blast and paint shop it was on to the
outfitting shop. Göran Christensson from Kockums was the first
manager of the outfitting shop, and when he returned to Sweden
in 1990 Robert Lemonius from Cockatoo Island took over the
role.
The 200 section of each submarine was always the first to enter
outfitting, where the major equipment received from Australia
and overseas would be installed. For the first boat much of this
came from overseas, but afterwards from Perry Engineering (steel
fabrication) and ASC Engineering (outfitting) in Adelaide. The
machinery and platforms arrived in the outfitting shop with the
sections outfitted sufficiently for platforms to be installed. These
came from Kockums for the first section of the first submarine,
but thereafter were made in Adelaide by Johns Perry.
150 THE COLLINS CLASS SUBMARINE STORY
152
THE AUTOMATED INTEGRATED VISION 153
Rick Neilson recalls that he was the person who said when prepar-
ing the requirements, ‘we will do this combat system in Ada’. This
turned out to be a problem, although he argues that Ada as a
language was not the problem; rather it was the newness of the
language, which meant that much of the support for it was uncer-
tain. This showed up particularly in the choice of compilers for
converting the Ada software to machine code compatible with the
68000 processor series. It was not clear which compiler was most
suitable and Rockwell gambled by choosing Verdix, which proved
slow, and could produce corrupt code. Nevertheless, the Rockwell
consortium was stuck with them.5 The problem became critical
when Rockwell wanted to further upgrade its processor (after hav-
ing done so before with the 68030 and 68040) and Verdix refused
to develop another new compiler for the 68060.
The decision to use the Motorola family of 68000 processors
was itself an issue, heading up a dead end. In the mid-1980s the
68000s were the best available, but the triumph of Microsoft and
Windows over Apple’s Macs meant development of the 68000
ceased while the power of Intel processors multiplied exponen-
tially. The decision to use Motorola processors was made by Rock-
well (with the encouragement, at least, of the project office) at
an early stage in putting together its bid, and was subsequently
incorporated in the combat system specification.6 This was one of
several decisions that pushed the project into technological back-
waters.
Many of the woes of the combat system project were the result
of unlucky timing. Critical decisions were made just as the PC
revolution was beginning. One of the consequences of this was
that almost all the hardware the project used was custom built
and better commercial hardware was available shortly afterwards.
Chris Miller of Computer Sciences recalled that:
The displays were custom built and programmed using
Librascope code. The disks were built using custom
hardware and then programmed from the ground up (with
156 THE COLLINS CLASS SUBMARINE STORY
the result that accessing the disks was a task in itself). The
backbone fibre optic bus that connected all the components
and the software that was written to run it was developed
from scratch. Likewise for the command plot, the plasma
display units and so on.7
the bugs and then re-engineer the system to fix them. Feasible
with American production runs, the approach was not viable for
Australia’s six units. With the Collins system each fix was a loss
and by 1990 the company was starting to lose money.
Pascall recalls an incident revealing something of Rockwell’s
approach to the project. At one stage he had told Rockwell that
its practice of adding patches with myriad wires and switches
breached all NATO standards, to be told that the patches were
temporary and would be fixed ‘at the next contract’. Rockwell did
not understand that Oscar Hughes was determined there would
not be a ‘next contract’.
Computer Sciences of Australia’s primary task was writing
the software for the tactical data handling system, ‘the bubble
in the middle of the combat system’. Within the tactical data
handling system were three major elements: the multi-function
common consoles, the command plot and the two systems super-
visory units, with CSA’s software running these central hardware
systems.
Computer Sciences was taking on by far the biggest defence
project it had been involved with, and attempted to plan its work
using the latest tools. ‘Teamwork’ – ‘a structured analysis
technique using data flow diagrams’ – was used to produce its
‘requirement specification’ based on the contracted performance
specification. It took a team of about 25 engineers 18 months to do
the requirements analysis but at the end ‘the navy saw it and asked
“What does it mean and what can we do with it?”’ Teamwork had
‘pushed out documents that were monumental and unreadable by
humans’.8
The story of Teamwork epitomises a central problem with
Computer Sciences’ approach to its task: it became overly con-
cerned with computer science issues and lost sight of the ultimate
aim of the project – to produce an efficient and effective sub-
marine combat system. Computer Sciences spent over 18 months
planning its work and undertaking the requirement analysis. Rod
Farrow, who was project manager from 1988 to 1993, thinks that
in hindsight the timetable was ludicrous. Computer Sciences had a
contract to develop the tactical data handling system in 48 months
from 9 September 1987. After about 36 months, Computer Sci-
ences produced a ‘build zero’ of the system. This ‘showed they’d
got the run time execution working’ and a few other parts of the
158 THE COLLINS CLASS SUBMARINE STORY
system also, but ‘it wasn’t very much and they were a long way
from producing a tactical data handling system that would enable
Rockwell to make a combat system’.9
Chris Miller, who had worked with Computer Sciences on the
navy’s helicopter simulator at Nowra before moving to the sub-
marine project in 1989, had the same view. He ‘never saw a plain
English description of what the combat system was meant to do’
and felt that the combat system project was focused more on com-
puter sciences than ‘how it would work with people sailing around
with it’.
The biggest challenge for Computer Sciences was the require-
ment for ‘graceful degradation’. In the architecture of the system
there were two systems supervisory units (which were like servers
with hard disks), seven multi-function consoles and a command
plot. The system had to be able to keep working even if the SSUs
and three of the consoles were damaged or otherwise out of action,
‘gracefully degrade’ down to just four consoles that could take
over the functions of the SSUs the instant they crashed. At this
time computer memory was a scarce and precious commodity
and the requirement for graceful degradation was responsible for
‘eating up’ much of the available memory and crashing the system.
Tony Smith, a former submarine commander who had worked
on the specifications in the early 1980s and later tried to build
the combat system when Boeing took over Rockwell’s defence
business, argues that the initial operational requirements were
misinterpreted when they were converted into performance spec-
ifications. The submarine operators wanted all the information
available on all the multi-function consoles so that there would
be no loss of data if one or more crashed or were damaged. In
the specifications this was interpreted as a requirement for zero
latency – that the information had to be available simultaneously
and instantly on all consoles – but the processing power to do
this was still 10 years away. It did not really have to be instan-
taneous for all functions – a three-second delay for some would
have been quite acceptable for the submariners. Smith’s view is
that the requirements had become too demanding for no sensible
reason and there was no contractual flexibility to change these
requirements.
While the teams at Rockwell and Computer Sciences in Syd-
ney were facing growing difficulties with their parts of the combat
THE AUTOMATED INTEGRATED VISION 159
166
E A R LY T E C H N O L O G I C A L S U P P O R T F O R T H E S U B M A R I N E S 167
2 ASC negotiation team of the day, Canberra, January 1987. Front row from right:
Roger Sprimont, Bo Bennell, Pelle Stenberg, Olle Holmdahl. Gunnar Ohland third
from the left. (Photograph courtesy of Pelle Stenberg.)
3 Contract signature day for the Collins project: (l-r) Rear Admiral Oscar Hughes,
Geoff Davis, Fred Bennett, Kim Beazley, Roger Sprimont. (Photograph courtesy of
RAN.)
4 Singer Librascope staff, including Bill Hudson (centre) and Arnold Peters
(second right), with Oscar Hughes (second left) and Rick Neilson (right) at Singer
Librascope in Glendale, California. (Photograph courtesy of Defence Materiel
Organisation archives)
5 From left: Pär Bunke, Ian Nicholson (Australian Ambassador to Sweden), Paul
Pålsson, Rick Canham and Kurt Jönsson (Kockums’ construction and outfitting
manager) in front of a Västergötland class submarine at Kockums’ yards in Malmö.
(Photograph courtesy of Defence Materiel Organisation archives)
6 Stiffening frames being lowered into a hull can before welding. (Photograph
courtesy of ASC Pty Ltd.)
7 Hull section or ‘can’ being welded. ASC welders achieved world-class results,
with a remarkably low number of faults and very accurate circularity, a critical
factor in hull strength. (Photograph courtesy of ASC Pty Ltd.)
8 Central section of submarine under construction at ASC. Control room viewed
from aft. (Photograph courtesy of ASC Pty Ltd.)
9 Equipment platform being inserted into the control room section. All major
pieces of equipment and wiring have been already been installed. (Photograph
courtesy of ASC Pty Ltd.)
10 Submarine under construction at ASC, with hatch in the bow over cylindrical
array removed for access. (Photograph courtesy of ASC Pty Ltd.)
11 The engine room team of marine technicians and engineering officer from
HMAS Collins at the start of sea trials, 31 October 1994. Front l-r: Anthony ‘Dog’
Masters, Paul ‘Bulkhead’ Newman, Troy Battishall; 2nd Row l-r: CPO Phil Ivins
(DMEO), Mark ‘Artie’ Beetson, Jim Taaffe, Marcos Alfonso (MEO), George ‘Eugene’
Lakey, Lindsay Hinch, Sammy Brennan, Gary ‘Chook’ Fowler; Back right-hand side:
Andrew ‘Birdman’ Ravenscroft. (Photograph courtesy of Marcos Alfonso.)
12 L-r: Hans Ohff, Rear Admiral Peter Purcell, Captain Paul Greenfield, Olle
Holmdahl, Commodore Geoff Rose, Captain Kit Carson, Commander Peter Sinclair.
(Photograph courtesy of Peter Sinclair.)
13 Kim Beazley and Commander Peter Sinclair at HMAS Collins periscope. (Photograph courtesy of Peter Sinclair.)
14 Rear Admiral Peter Briggs and Commander Peter Sinclair. (Photograph
courtesy of Peter Sinclair.)
15 General John Baker, Chief of Defence Force, standing left, and Ian McLachlan,
Minister for Defence, right, at sea on a Collins, looking over the shoulder of a
combat system operator. (Photograph courtesy of RAN.)
16 Farncomb at sea, 1997. Far left: Bronwyn Bishop, Minister for Defence Support;
second right: Hans Ohff. (Photograph courtesy of RAN.)
17 A Mark 48 torpedo fired from over the horizon by HMAS Farncomb hits the
ex-HMAS Torrens off the WA coast 14 June 1999. (Photograph courtesy of RAN.)
18 HMAS Farncomb arrives at Fleet Base West from an operational deployment
with a broom and Jolly Roger flying – traditional symbols of success. (Photograph
courtesy of RAN.)
23 HMAS Sheean sails from Fleet Base West, radar mast raised. (Photograph
courtesy RAN.)
24 HMAS Collins with communications, periscope and snort induction masts
raised. (Photograph courtesy RAN.)
and the guidance that would overlay the welding processes and
equipment chosen by Kockums for the exacting task of submarine
building. The key processes were manual metal arc (conventional
stick welding) and the automated process of submerged arc weld-
ing, in which a machine feeds welding wire and pours a layer of
174 THE COLLINS CLASS SUBMARINE STORY
181
182 THE COLLINS CLASS SUBMARINE STORY
of ASC, but it did not want this held by the Commonwealth. Con-
sequently, in December 1990 Kockums, somewhat unwillingly,
sold a 2.5 per cent holding to James Hardie Industries, a major
Australian industrial company, and in early 1992, following fur-
ther government pressure, it sold a further one per cent to AIDC.
James Hardie was never anything more than a passive investor
whose sole role was to maintain majority Australian ownership.
Kockums’ background of working very closely with the
Swedish navy and procurement organisation produced a corpo-
rate culture where it was ‘not interested in being the tallest pole
in the tent’.4 Even when Kockums became the majority share-
holder in ASC, there was a widespread perception (shared by many
Kockums personnel) that it was not willing or able to accept the
responsibility and challenges this involved.
The first significant dispute between ASC and the project office
was over issues with insurance left unresolved from the contract
negotiations. These had concluded that ASC should take out com-
mercial insurance, but the price of this became an issue. It had also
been agreed to divide risk between dry (in the yard, ASC’s risk)
and wet (at sea, Commonwealth risk), but even in the latter case
ASC retained liability for faulty design or workmanship.
Ron McLaren, now Oscar Hughes’ financial manager, felt ASC
was trying to use insurance as protection against the risks of the
project and push this cost onto the Commonwealth through the
premium. Oscar Hughes considered the cost of the ‘all risk’ com-
mercial insurance unacceptable as ‘it would kill my project’. He
recalls beginning the insurance negotiations soon after signing
the contract: ‘No sooner had we started than one of the Dutch
Walruses caught fire while it was being built and a Japanese sub-
marine rammed a ferry while on its sea trials with great loss of
life – it was not a good start to insurance discussions.’
ASC negotiated a cover with Lloyds for everything includ-
ing faulty design and workmanship, but for a price of about
$20 million per submarine. This was agreed with the Common-
wealth in a settlement in December 1988, to cover the dry risk for
the first boat, but was too costly for a general settlement. Hughes
insisted on separate quotes for dry risk and wet risk and ASC
was as insistent that the Commonwealth bear the full insurance
cost. It took four years of negotiation and litigation to resolve the
issue. Wet and dry risks were separated and the cost reduced to
‘ON TIME AND ON BUDGET’ 185
the original ceiling of about $75 million. Pär Bunke, the commer-
cial manager of ASC, saw the insurance issue as one of the biggest
problems the project faced in its early years, and it inevitably
affected the overall relationship.
The insurance issue had a further unexpected resonance. One
major criticism of the project was that ASC was paid too much
too soon, allowing the company to pay excessive early dividends
retain while retaining insufficient money to fix the defects found
in the submarines in the later 1990s. This criticism was made in an
Auditor-General’s report in 1992 and is a view almost universally
held within the navy. They argue that for a fixed price contract
with a high degree of risk, dividends should have been paid only
after the submarines were at sea, because: ‘As it was when they
found things didn’t work like they should there was no money left
to fix them and this led to bitterness toward Kockums and ASC.’5
Most former executives of ASC and its shareholders agree
that the contract provided for ample early payments, with over
75 per cent of total payments received before the launch of the
first submarine. Geoff Davis saw the contract as generous, with
ASC making good profits and paying substantial dividends to its
shareholders. About six months after winning the contract, Davis,
as chairman of ASC, recommended to the board that $4 million be
distributed to the shareholders – ‘we were not there to play games
but had to maintain the financial performance of our businesses’.
Pär Bunke agrees that hindsight suggests ASC should have kept
more money in reserve, but points out that the company had no
further contracts and there was a strong feeling there was no pur-
pose in retaining money in the company. He emphasises that until
1993 ASC believed it was covered by its insurance policy for
faulty design and workmanship, so there was no need to keep
large amounts of money in reserve.
For Kockums the Australian submarine project restored finan-
cial health to a struggling company, so much so that 1990 was the
most profitable year in the company’s 140-year history.6 How-
ever, Kockums was not able to invest these profits into its subma-
rine business, as most of the money was funnelled into the parent
company, Celsius, which used it to buy moribund Swedish defence
companies.
Oscar Hughes was criticised in the Auditor-General’s report
for paying ASC too much before the program was sufficiently
186 THE COLLINS CLASS SUBMARINE STORY
five submarines following over the next five years, to see the final
submarine in the water in 1999. Fairly early on in the project
this was revised to have the first launch in 1993 and, after several
minor revisions, the launch was set for 23 August 1993.
The project’s quarterly reports in the early 1990s have a strong
focus on the schedule. Thus, in June 1990 it was reported that
the project was ‘generally on cost and schedule’ but there were
some ‘pressure points’, notably Kockums’ design and fabrication
activity was behind, ASC’s procurement activity was behind, and
the insurance for the last five submarines had not been agreed.
Nonetheless it was believed that these would not delay the launch
of the first submarine. By September 1990 Collins was 38 per
cent completed, which implied a ‘seven month slippage against the
original plan and three months against the current plan’. However,
after this time the ‘slippage’ gradually reduced as ASC put more
resources into Collins, although this had consequences for the later
submarines. In March 1992 ‘significant pressures’ still remained
on the production schedule for Collins, but the launch had been
set for 23 August 1993, which happened to be Don Williams’
birthday. Coincidence or not, it is widely believed that the launch
was rushed to make sure it happened on this anniversary.
Pär Bunke recalls that ASC had graphs on the production of
each submarine, showing how it was going against the schedule
and the work that still needed to be done. By 1992 the graph for
the first submarine was nearly vertical, showing that it could not
be ready on time, and because of the delays in the first submarine
the graphs were growing steeper for the later boats.
In hindsight, most involved with the project think that the
schedule was always over-ambitious for a massive development
project. Ross Milton points out that the sheer complexity of
the project, with about half a million often unique items to be
designed, procured and installed in each submarine, meant that
any delay in any part of the production process had a ripple effect
on the whole project.
Despite the pressures Don Williams and Oscar Hughes insisted
that Collins must be launched as scheduled – the band was booked,
the caterers had their orders and the Prime Minister was rehearsing
his speech.
But more seriously, Hughes saw maintaining the schedule as
critical for the success of the project. He believed that: ‘Once you
‘ON TIME AND ON BUDGET’ 189
take your eyes off the schedule you never get back in control –
launching the boat and keeping to the time scale helped to focus
people’s minds. Once you let an eel go, you can never grasp it
again!’10
While attention in the early years was focused almost entirely
on the progress of Collins, construction of all the other submarines
had begun according to schedule. However, as the schedule for
the launch of Collins became tighter, work on the other sub-
marines suffered. As early as the spring of 1991, section 100 of
Farncomb was sent to Newcastle for completion to free up space
and resources at ASC, and over the next few years the attention
of ASC and the project office was far more on Collins than on the
later submarines.
On 23 August 1993 a crowd of 4500 saw the launch of HMAS
Collins. Several dignitaries spoke, but the only words anyone
recalls are those of Don Williams: ‘We’ve launched on time and
on budget, so put that in your pipe and smoke it.’
PART 3
‘A STRANGE SENSE
OF UNEASE’ 1993–98
CHAPTER 17
End of the honeymoon
193
194 THE COLLINS CLASS SUBMARINE STORY
awareness that the larger part of the work on the contract lay in
front of them, while the payments would steadily diminish. For
Ohff every cent spent was a cent off the profit from the contract.
At ASC the office lights were no longer left on at night, people
wrote memos on the back of old envelopes and travel was cut
back. The new managing director led by example, often driving
interminably around city blocks hunting for a free car park.
Hans Ohff brought an aggressive and often confrontational
approach to the submarine project. It was said at ASC that the
epitaph on his tombstone should be ‘Kick the door in first, you
can always apologise later’. Many in the navy and defence found
him an inflexible and belligerent negotiator and almost impos-
sible to deal with. They felt that his policy was never to admit
that any problems with the submarines were ASC’s responsibil-
ity, causing even minor faults to become major issues between the
parties.
Hans Ohff admits that he was results-driven and used to deal-
ing with profit-focused companies, and his personality was not
good for dealing with an organisation like the navy, with its
amorphous and continually changing group of people with little
commercial acumen and greatly differing interests and agendas.
Nonetheless he feels that his motives were often misunderstood –
few remembered that he had been largely responsible for the deci-
sion to build the submarines in Australia and he had an enormous
personal commitment to making the project a success. He points
out that as an experienced contractor he could have treated the
navy like ‘lambs to the slaughterhouse’ because in a $5 billion
project the client is captive as the contractor cannot be sacked –
it would be politically and financially impossible to cancel the
contract and start again. A contractor could always take advan-
tage of the client in that sort of relationship because the client is
so big and bureaucratic and unable to watch everything. How-
ever, Ohff insists that he has ‘always been performance driven: a
safe and speedy delivery of a project would deliver a satisfied cus-
tomer and translate into increasing profits for the shareholders’.
If the company performed well there were large profits to be made
without ripping off the client.
Hans Ohff came to ASC with the philosophy that ‘the rela-
tionship between the customer and the contractor can never be
too close’, and his efforts to put this into place illustrate one
END OF THE HONEYMOON 197
Geoff Rose was perplexed. His view was that he had a job to do
based on the contract, and if new requirements were introduced
and the submarines ‘I produced to the requirements of the contract
would not be acceptable to the navy; not only did the goal posts
seem to be moving, the game being played had changed as well’.
His confusion was never resolved.
One of the central commandments of the project from the
beginning had been to avoid changes to the contracted require-
ments because changes cost time and money. In addition, many
believe that submariners were kept away from the project to avoid
‘spec creep’, although the truth is that the submarine squadron
was too short of sailors and too preoccupied with the Oberons
to spare experienced operators for the new submarine project.
Consequently, the project was run by engineers, not submariners.
However, once Collins was handed over to its crew, the project
was suddenly open to scrutiny from the submariners – and they
were not entirely happy with what they found. The submariners
judged the submarines by what they wanted and expected, not by
the fine print of the contract, yet it was by the contract that ASC
and the project insisted that the submarines be judged.
Over the next few years contract interpretation and reinter-
pretation became a major preoccupation. The contract prepared
under pressure in early 1987 was subjected to minute scrutiny,
and every weakness was glaringly exposed.
Throughout 1993 ASC’s executives and shareholders were
deeply divided over two major issues that had enormous ramifica-
tions for the future of the whole project: what action should ASC
as prime contractor take against Rockwell for failure to deliver
the combat system, and what strategies could be used to sell
Australian-made submarines overseas? The company remained
divided on both issues and these divisions ensured that no effec-
tive action took place on either.
Wariness of Rockwell and the dangers of responsibility for the
combat system was always a major concern of the ASC board,
and this concern increased as the reports on the progress of the
combat system became increasingly dismal. Tomy Hjorth recalls
END OF THE HONEYMOON 199
New Zealand has never had submarines, but in the early 1980s
the National Party government’s concern at the cost of new sur-
face ships led it to investigate buying four submarines as a more
cost-effective deterrent. As New Zealand had no infrastructure
for supporting submarines, it made sense to work closely with
Australia and an NZ officer, Andy Millar, was sent to Australia
in October 1982 to join Graham White’s project team.
However, the elections in July 1984 led to a change of gov-
ernment and within 24 hours of becoming prime minister, David
Lange announced that New Zealand would not be getting sub-
marines. Andy Millar heard the news on the radio that New
Zealand had withdrawn from the submarine project and that the
officer on the project team had been sent home – and soon he was.
Millar shortly afterwards accepted an invitation from Admiral Bill
Rourke to return to the Australian submarine project, but New
Zealand’s interest was at an end.
The Canadians remained with the Australian project until
1985 but then went home and nothing more was heard from
them for several years. In 1987 a defence review recommended
that Canada should acquire 12 nuclear submarines, and it was not
until this fantasy was exploded that the Canadian navy returned
to the market for conventional submarines.
An important part of the Hawke Labor government’s overhaul
of defence industries in the 1980s was to build up defence exports,
and the successful sale of submarines would be clear proof of the
success of this policy.8 In October 1989 Kim Beazley optimistically
said that:
class. This brought out the conflict of interest between ASC and
Kockums.
By 1992, when Malaysia was inviting expressions of interest,
AIDC was becoming interested in extending its involvement in
military industries. Inspired by Peter Horobin, it attempted to put
together a bid for a submarine for Malaysia, involving a pro-
posal to build the Swedish A19 Gotland design in Adelaide, but
with a Rockwell combat system. This proposal was made with-
out telling Kockums, which submitted a separate bid, also for the
A19, but with a Saab combat system. The consequence of the
disunity between ASC, AIDC and Kockums was that Malaysia
bought French submarines.
A final strange postscript to the export story came with a let-
ter from an unknown merchant banker claiming to be acting on
behalf of the Taiwanese government. In the letter an offer was
made to buy six Collins submarines, with a further incentive
being an offer to buy South Australia’s entire wine production.15
Although this was probably a hoax, it is likely that Taiwan would
have bought Australian submarines if it had been politically pos-
sible. Indeed the only rumours of export sales since 1999 have
been for Collins class submarines to be built in America for sale
to Taiwan.16
An old retailing truism is: ‘You don’t make money yelling
“Stinking fish for sale”.’ Any realistic chance of selling Australian
submarines ended in the mid-1990s when a storm of media criti-
cism made them virtually unsaleable.
But was Collins a stinking fish? While the first submarine had
been taking shape in the shed at ASC, its commanding officer had
been appointed and the crew assembled. Training had been under
way for several years and, with Collins back in the water, the trials
process was about to begin. Would the submarine meet the hopes
of those who had worked for years planning and building it, and
the expectations of those who were waiting to sail in it?
CHAPTER 18
The trials of Collins
205
206 THE COLLINS CLASS SUBMARINE STORY
In spite of this early notice, the prediction came true and the
early training was patchy, superficial and often a waste of time.
The chief source of difficulty for ASC was that the late comple-
tion of the design of many systems and the failure of many sub-
contractors to provide information on their equipment made it
difficult to plan the training. It is obviously difficult to train peo-
ple to use a system that has not been designed and of which the
trainer has no knowledge.2
THE TRIALS OF COLLINS 207
In the crew’s view, the training for Collins presumed that nothing
would ever break down. The levels of redundancy in the sub-
marines were believed to be so great that the crews would need
to know little about maintaining systems while at sea. As a result
there was little training given for this, so when things did break
down the crews had to teach themselves how to repair them.
Marcos Alfonso, the first marine engineer on Collins, joined the
crew in January 1993, and says that they lost some crew because
some older sailors were unable to grasp the ‘fly by wire’ concept
of the new submarines. The Oberons were mechanical and manu-
ally intensive, while the new submarines were electronic and auto-
mated. In the Oberons the crew had to walk around to open and
208 THE COLLINS CLASS SUBMARINE STORY
they were in Adelaide they were allowed to walk around the sub-
marines but it was strictly a ‘look but don’t touch’ situation. They
could learn about the components and their location but they did
not learn how to operate them – this was learned at sea, ‘where
equipment was damaged due to lack of knowledge of how to
operate it’.
Graham White felt that there was an attitude of complacency
among the crews, which stemmed from the general view in the
navy that the contractor would supply the submarines and the
navy would simply take them over and drive them. They expected
that new submarines would be like new cars, where you just turn
the key and drive away. There was no understanding that the RAN
was the parent navy for the submarines and had a much greater
responsibility for the product than the buyer of a new car.
One week before the launch of Collins Trevor Robertson
resigned his command and left the navy. He felt frustrated that his
attempts to fix the problems on the submarine had been ignored
and more generally felt that he and his crew had been poorly
looked after by the navy. However, the main reason he left was
that he realised he would be posted away from Collins before he
had a chance to take it to sea and, after the excitement of sub-
marine command, he did not want to go and sit behind a desk.
The timing of the resignation was not designed to embarrass the
navy, but Robertson felt that once he had accepted a job out of the
navy, it would not be honest to stand up on the platform during
the launch ceremony.
Robertson was succeeded as commanding officer of Collins by
Peter Sinclair, another experienced Oberon captain. After attend-
ing the launch, he and the crew spent most of the next year training
in the simulators in Western Australia and Sydney while Collins
was prepared for the contractor’s sea trials. Sinclair recalls:
the water a week after launch and her fit out completed. This
gave the crew the opportunity to be heavily involved in the
systems set to work program and the extensive licensing
process. System task books were produced that ensured each
member of the crew was competent in their specific ‘part of
ship’. Notably in the 12 months before the submarine was
launched for the second time there were no resignations and
the crew went to sea for the first time with a high team
spirit.
safety. Each of the members had power of veto and could stop the
submarine from sailing for trials or stop the trials program and
bring the boat home.
The trials process involved achieving a staged sequence of
licences, with the first allowing the submarine to run on the sur-
face, followed by shallow static dives and gradually progressing
to unaccompanied deep dives. The delivery of a submarine to the
navy could not take place until the trials were completed and all
licences achieved. The licensing program was developed so that
the competence of the crew and the material state of the submarine
matched the increasing levels of hazard in the trials program.
The licensing program also included licensing the crew by
putting them through countless emergency drills in the simulator
and on the submarine, alongside and at sea. Peter Sinclair recalls:
This was an exhausting period: constantly practising
emergency drills and standard operating procedures, floods,
fires, hydraulic bursts. It often meant changing procedures on
the spot. With the excellent support of Mike Gallagher and
his sea training group and the professionalism of the crew we
became more confident and competent each day . . . What we
weren’t prepared for was the number of intermediate or
docking level defects that occurred in those early months.
Our inability to fix these problems stemmed from a lack of
in-depth training for our engineers. In hindsight though I
must give praise to them, because they handled every
circumstance with utter professionalism.
Originally Collins’ trials were due to begin early in 1994, but this
was too optimistic and trials did not begin until 31 October 1994.
The combat system was the source of greatest frustration. The
submarine could not go to sea without at least a rudimentary com-
bat system, as the radar, sonars and periscopes are required for safe
navigation. During 1994 there were constant disputes between
Rockwell and the project on the minimum combat system perfor-
mance needed to allow the sea trials to begin. The major problem
was that the whole system was extremely slow, constantly crashed
(taking up to eight hours to re-boot) and could not perform many
tasks. Another serious difficulty at this stage was integrating the
French-made sonars with the Australian tactical data handling
system.
212 THE COLLINS CLASS SUBMARINE STORY
Ironically, one of the main reasons why the project office had
refused to countenance defaulting Rockwell in September 1993
was that the combat system would be needed for Collins’ sea trials,
yet the performance in mid-1994 was so poor that Collins actually
went to sea and did most of its trials using little of Rockwell’s
system. In its place they used ‘stand alone’ equipment to run the
navigation, with specific software for the navigation functions and
a stand-alone navigation display to get Collins to sea. For example,
the combat system was unable to process data from the sonars,
so the project had to pay the sonar sub-contractor, Thomson, to
install a back-up sonar with a separate sonar display.5
On 8 August 1994 ‘basin trials’ began and the main motor was
turned for the first time. During September Collins was fuelled and
stored and ‘she proceeded to sea under her own power at 10.00
on Monday 31st of October to surface sea trials in the Gulf of
St Vincent’.6 Mike Gallagher recalls that: ‘Peter Sinclair disap-
peared at a great rate of knots . . . there was something of a sense
of sheer delight in actually getting the boat to sea.’ But at the same
time Marcos Alfonso and his engineering team were beginning a
long struggle with the diesel engines. By the time Collins passed
the Young Endeavour (which was coming into Port Adelaide) two
of the engines had broken down.
Collins’ first static dive was on 9 November and the submarine
remained submerged for 12 hours carrying out trim and inclin-
ing trials. Trials continued throughout November, after which the
project director reported that:
Despite appalling weather Collins performed extremely well
in the first phase contractor sea trials in November exceeding
the contracted requirements in many areas. Dive trials will
commence early in 1995 and Collins remains on schedule for
delivery and commissioning in November 1995.
then we got in the car and drove back to Adelaide and went
home and I thought that in anyone else’s navy there’d have
been ships and planes and press and stuff everywhere and we
just toddled out in the middle of the sea there and did it.
221
222 THE COLLINS CLASS SUBMARINE STORY
that the final tank never had any water in it, to avoid water being
drawn into the engines.
However, in operation substantial amounts of salt water
entered the engines, causing myriad further problems. The crews
and the navy blamed the design of the fuel system. Greg Stuart
traces this back to the environment in which the Swedes operated
their submarines. The Baltic Sea is small and both calmer and less
salty than the oceans. With less distance to cover their submarines
carried less fuel. They did not do much snorting in their normal
operations and when they did they were less likely to have rough
seas. Further, the fresher water of the Baltic was less corrosive than
the salt water of the oceans if it did get into the engines. Conse-
quently, the Swedes did not place a high priority on keeping salt
water out of the engines when designing the fuel system, relying
primarily on gravity separation. When the submarines operated
in the rough, salty waters of the Southern Ocean, the fuel was agi-
tated during snorting and when sailing on the surface, mixing the
oil with salt water, and it was almost impossible to avoid drawing
salt water into the engines.5
While the submarines’ designers concede that the fuel system
was complicated, they believe that the crews were poorly trained
in its use (training being an ASC responsibility as prime contrac-
tor). In their view the crews tried to operate the fuel system in
the same way as they had on the Oberons, rather than following
the procedures laid down for the new submarines. Olle Holmdahl
saw the main problem as being the crews’ practice of taking fuel
from any of the tanks rather than following the recommended
sequence. They were meant to keep the valves shut unless there
were exceptional circumstances, but Holmdahl believes they rou-
tinely opened them.6
Eoin Asker and others connected with the project office tend to
take a neutral view, conceding that the system was unnecessarily
complicated, but also seeing poor crew training as exacerbating
the problems. The problem of salt water entering the engines grad-
ually lessened as the crews became used to the fuel system, but it
was not until the system was supplemented with a navy-supplied
fuel coalescer in 1999 that the problem was overcome.
Crew members bridle at the claim that they were responsible
for the failures of the diesel engines. Peter Sinclair says that the
224 THE COLLINS CLASS SUBMARINE STORY
crews were trained to follow procedures to the letter and ‘on the
odd occasion [they] made mistakes but the problems that continu-
ally occurred were due to design or manufacturing faults and any
engineer or manufacturer that blamed the crews invariably knew
he had problems’.
The problems with the fuel system were exacerbated in the mid-
1990s by persistent contamination of the fuel supplied to ASC by
the navy. Throughout 1995 and 1996 the project office regularly
reported that Collins’ trials were delayed by bacterial contam-
ination in the fuel. This caused many problems in the engines,
the most serious being damage to the fuel pumps. Swedish diesel
engine consultant Olle Person recalls that he was asked by Hans
Ohff to investigate the problems with the fuel pumps. After dis-
cussions with the sub-contractors he decided that it was not a
manufacturing fault but caused by a bacillus living in the fuel.
Some products of the bacilli were corrosive and this caused the
fuel pumps to stick. They had never had bacteria in diesel fuel
in Sweden so this problem was new to them. The problem was
eventually controlled by the addition of a biocide to the fuel.
Salt water and fuel contamination were the most serious prob-
lems with the diesel engines and lay behind many of the other
difficulties, which included cracked or broken parts and exces-
sive fuel consumption. However, there were other factors which
are widely regarded as contributing to the failures of the engines.
Quite early in the design phase, the decision was made to take the
500-kilogram flywheel off the engines to save weight. Experts are
divided over the effect this had, but many think that this made
the engines less reliable and, by changing the natural frequency of
the engine causing it to vibrate at its specified nominal operating
revolutions, led to problems of cracking and breakages.7
Greg Stuart, however, traces the excessive vibration to the fuel
problems. He notes that:
submarines were extremely quiet and there was always the expec-
tation that the Australian submarines would have the same char-
acteristics. Further, the Swedish design had been assessed in 1987
by the Australian evaluation teams as meeting the noise require-
ments. In the Oberons the main noise concerns came from internal
machinery, and consequently the Swedish technique of isolating
all machinery from the pressure hull by mounting it on platforms
was attractive for its potential to reduce machinery noise to an
absolute minimum.
During the Cold War the Swedish submarine force was
designed primarily to sit off the coast to attack a Soviet inva-
sion fleet. The submarines did not have to cover great distances
or run at high speed, so they were designed to be virtually silent
at low speeds, in the ‘quiet patrol state’. In contrast, Australian
submarines have long distances to travel to their operating areas
and they want to do that as quickly as is possible while remaining
undetected.
While the requirements for range and endurance were clearly
set out in the contract, the requirements for noise were less clear.
This is indicated by the fact that there were bitter arguments at
the time over what was actually required, and even today there is
nothing approaching agreement on what the noise requirements
really were.
There is, however, general agreement that the original noise
requirements and the way the requirements were expressed in the
contract lay at the heart of the disputes over noise. Andy Millar
suggests that the original specifications were vague because of a
lack of technical understanding of noise issues in the Australian
navy in the early 1980s. The Oberons were quiet, and when the
specifications for the new submarines were being prepared it was
decided to ask for them to be ‘twice as quiet’, even though it
was not known whether this was achievable. Millar suspects that
Kockums was uncertain whether the requirement was achievable
but assumed it would get close.9
However, even if the submarines had completely met the noise
specifications set down in the 1987 contract, this would no longer
satisfy the navy because expectations had grown. The contractual
noise requirements concentrated on noise levels at quiet patrol
state and when snorting, but were vague on noise levels at high
speed, yet by the mid-1990s the navy saw an increasing role for the
‘THEY WERE PROBLEMS WE DIDN’T EXPECT’ 227
As this report indicates, the results of the noise range tests showed
that the submarines were noisier than expected but there were
arguments over whether the tests were accurate enough to estab-
lish whether the submarines reached the contractual requirements.
Hans Ohff agrees that ‘the submarines never met the hugely ambi-
tious specifications for noise’, but argues that ‘it was hard to prove
this because the background noise in the sea is greater than the
noise level specified for the submarines’.
While there is nothing approaching consensus on the noise
levels of the first two submarines during their trials in 1996 and
1997, the ‘median’ view is probably that of Peter Clarke, who
judged that:
The boats did not meet the noise specifications though they
were not as far away as the navy tried to make out. At slow
speed the boats exceeded the contract specifications for noise,
but above seven knots it was iffy and at high speeds it was . . .
over the contract.
Whatever the exact noise levels, there is no doubt that the sub-
marines were not as quiet as had been hoped and expected. What
were the sources of the unexpected noise?
Early in Collins’ trials there were some minor problems with
mechanical noise, notably from the weight compensation pump,
but these were quickly resolved. The main concerns were with
hydrodynamic noise made by the flow of water over the hull, and
noise and cavitation from the propeller. Critics like Mick Dunne
and Bill Owen argue that the design of the submarine is inherently
and irreparably noisy. While this view has been taken up by the
general public, it is not shared by either the submarines’ builders or
their operators. Peter Sinclair, as the first skipper of Collins, bore
the brunt of the ‘first of class’ faults, but he is adamant that ‘she
‘THEY WERE PROBLEMS WE DIDN’T EXPECT’ 229
is super quiet, really, really super quiet at slow speed, quieter than
anything else in the world’. However, most agree with Sinclair’s
observations that the submarines’ flow noise increased greatly as
their speed increased and share his view that the shape of the
casing was the main cause.
When the Type 471 was first designed the casing was smooth
and even, being virtually indistinguishable from the Swedish
Västergötland class.12 A one-sixteenth scale model of this design
was extensively tank tested in 1986 during the project definition
study, showing hydrodynamic flows and noise levels nearly iden-
tical to those of the Västergötland.13 However, after 1987 the
designers at Kockums were forced to make changes to this tested
design. The most important of these was the sonar dome in the
bow, which Kockums wanted to place low down, but the project
office insisted that it be high to minimise the ‘blind’ area behind
the submarine. The initial plans had a low bow but the changes
resulted in a large and bulbous bow that is generally believed to
be the major cause of turbulence and noise.14
The changes to the bow were made with what appears to have
been remarkably little consideration of the consequences for water
flow. Although the issue was raised by members of the navy team
in Sweden, they were told money was not available for a new
model or test program.15 Consequently, the revised design with
the larger bow was not tank tested. This reflects an early failure
of communication between Kockums, the project office and the
Australian navy. It was not until after tank testing and air flow
analysis was carried out in the late 1990s that some relatively
simple modifications were made to the casing that appear to have
reduced the flow noise.
The other noise-related concern was the cavitation from the
propeller. Peter Sinclair recalls that during Collins’ trials they grad-
ually became aware that at some speeds there was no cavitation,
but at other speeds the water flow over the control surfaces onto
the propeller did cause cavitation. Although the propellers and
cavitation were hardly mentioned in the project office’s reports
of the early trials, by 1997 they were among the major concerns.
The chief of the navy, Don Chalmers, and American submarine
expert, Admiral Phil Davis, both saw excessive cavitation as mak-
ing the submarines unfit for combat. Don Chalmers recalls that
the contract did not specify cavitation levels but:
230 THE COLLINS CLASS SUBMARINE STORY
What it said about cavitation was along the lines of ‘the boat
should not cavitate’. But the boat did cavitate . . . I had one
of my famous blow-ups with Hans who said: ‘That’s only
because you don’t know how to handle the boat.’ And I said:
‘I don’t care how quiet the boat is [at slow speeds], but if it’s
detected it has to use speed to evade and this boat’s going to
cavitate and that’s death to submariners.’
project office reported that the leak problems in Collins and Farn-
comb were not finally resolved, but the modified seals allowed sea
trials to continue while they waited for re-designed seals. Signif-
icantly, the report in December 1996 noted that: ‘Helpful advice
has been provided by US Navy sources where similar seals and
problems have been encountered.’ This is possibly the first men-
tion in the whole history of the project of assistance received from
the American navy. In December 1997 the project office reported
that a re-designed shaft seal from a new supplier had been fitted
on Farncomb and successfully tested to deep diving depth.
Many defects found in Collins and Farncomb were fixed by
ASC and its sub-contractors, and the lessons learnt were able to be
applied to the later submarines. In March 1998 the project office
recorded: ‘The first review of Waller’s form TI 338 A [the formal
record of shortcomings on delivery] indicates a large number of
defects overall but with significantly fewer causing concern than
for the first two submarines.’ For each successive submarine the
list was shorter and the defects less serious.
The early submarines suffered from numerous mechanical and
technical defects. These would all have been seen as normal ‘first
of class’ issues if not for three things. Firstly, the breakdown in the
relationships between ASC, Kockums, the project office and the
navy meant that many simple problems were not simply solved
but became subject to bitter dispute. Secondly, the change of gov-
ernment after the federal election of March 1996 made the project
the subject of political controversy. Thirdly, and most importantly,
the combat system still did not work at anything like the level that
had been hoped for. If the combat system had worked to expecta-
tions the other problems with the submarines would have faded
into insignificance and the new submarine project would never
have been seen as anything but an outstanding success.
CHAPTER 20
The role of Defence Science: noise
and diesels
235
236 THE COLLINS CLASS SUBMARINE STORY
modelling was used, even though the available software was not
entirely suitable and was developed as the experiments progressed.
This procedure differed little from the design of the whole exper-
iment, however, as all the data yielded had to be interpreted to
allow for the differences between air and sea water in density, vis-
cosity and other parameters. The outcome was interesting enough
for Wyllie to remark on the number of senior US Navy officers
who began to visit DSTO’s Fishermans Bend facility and how this
promoted collaborative research between DSTO and its American
equivalents.
In 1993 the project office had sought contacts in the US Navy’s
engineering and research establishments. At first the Americans
resisted talking about their submarine technologies, but even-
tually an exchange developed over aspects of ‘technologies’ to
do with the sub-marine environment. As the Collins acoustic
signature became an increasing problem, Greg Stuart from the
project worked with diplomatic and scientific staff in the USA and
Australia to gain access to the US Navy’s expertise in acoustics.
The Americans closely guard this expertise, but eventually agreed
to model the performance of the Collins. The results correlated
closely with those of DSTO’s wind tunnel tests and confirmed
what the acoustics group had been telling the navy.
Several features of the Collins hull shape generated significant
turbulence: the cylindrical array knuckle, the fin, and the hull cas-
ing. This disturbed mass of water was tumbling over the abrupt
end of the casing and arriving at the propeller in two turbulent
streams that were nicknamed ‘rabbit’s ears’. Each propeller blade
hit turbulence twice in every revolution, increasing their natural
vibration and inducing cavitation. Kockums had tested a model
of the Collins propeller and was certain it did not cavitate, but
in the tank tests Kockums had trialled the propeller behind a per-
fectly cylindrical mount; there were no ‘rabbit’s ears’ to excite the
blades.
The findings from this research at DSTO and in America led to
the design of a series of modifications to the fibreglass casing and to
the fin. These succeeded in taming the ‘rabbit’s ears’ but the seven-
tonne propeller remained a problem. The propellers made for the
Collins class were cast from Sonoston and the first batch were
hand-chiselled from the casting – with the result that they were far
from the high-tolerance product of multi-axis machine tools that
THE ROLE OF DEFENCE SCIENCE: NOISE AND DIESELS 239
and twist along its length, especially in the region of the bell hous-
ing. In the same way that a ruler can be ‘twanged’, this could
generate vibration at a natural frequency. This was the vibration
that Kockums sought to isolate with the tuned absorbers and that
DSTO’s acoustic group was seeking to correct.
From Geoff Goodwin’s viewpoint, this natural frequency of
the generator set was too close to others generated by the engine
and could start enough vibration to damage other components.
Already, there were reports of cracked and leaking auxiliary pip-
ing. The navy tried to manage the problem by slightly increasing
the diesel’s running speed, but the situation worsened, and so the
diesel speed was reduced. This reduced the vibration but Jeumont
Schneider warned that this would cook their generators. A com-
promise engine speed was agreed, but the consequence was that
the generators produced slightly less power and recharging the
batteries took a little longer.
The propulsion group also developed a computer model of
the engine to determine its natural frequencies. Validation of the
model was achieved by placing 14 accelerometers around a gen-
erator set on Dechaineux and then striking the end of the diesel
with a 15-pound plastic-faced mallet. This enabled a full struc-
tural model of the generator set to be completed by a team of
four scientists. The model was ‘fitted’ with stiffeners and bracing
bars that joined the engine block and generator across the bell
housing, and increased the lateral bending stiffness of the unit.
Results showed that the natural frequency of the stiffened unit
should have changed by several Hertz. A slightly lesser result was
achieved in practice; nevertheless, this simple modification was
good enough to halve the vibration. The mass of the bracing units
totalled less than 100 kilograms.
The propulsion group later received broken parts from auxil-
iary gearboxes that had failed. This was not unusual for DSTO,
as one of its standard roles is to improve the operation of defence
equipment by analysing recurring faults. Goodwin’s preferred
approach was to consult with the manufacturer and encourage
them to accept a need for change and to supply a modified part as
manufacturer’s components, carrying a stock number and a guar-
antee. The gearbox in the submarines is fitted with two starter
motors because the engine starts as an air pump, to blow water out
of the exhaust system when the submarine begins to snort. It was
THE ROLE OF DEFENCE SCIENCE: NOISE AND DIESELS 243
the first Hedemora engine where two starter motors were needed,
and consequently there was more starting torque than in any other
Hedemora engine. The propulsion group put a failed interme-
diate gear through stress analysis and the part was redesigned.
The results were turned over to Hedemora, who did their own
checks and came back with a part that was even stronger than
had been recommended by DSTO. The problem was solved. For
his part, Goodwin enjoyed working with Hedemora and found
them responsive to his suggestions.
DSTO’s Propulsion and Energy Management Technologies
Group continues its work on the Hedemora generator sets and is
conducting thermal modelling and other experiments to improve
the consistency of operation of the turbocharger turbines. It has
continued to study problems with some nozzle failures, provid-
ing data for a management program to minimise the damage
that malfunction of these components can cause. This is a prob-
lem that has occasionally appeared in Hedemora engines for
many years, but is more common in the submarine environment.
Goodwin thinks they are approaching an understanding of the
issue that will allow a lasting solution, and will further improve
engine reliability and effectiveness. DSTO hopes to contribute to
further gains in reliability and performance, and reductions in fuel
consumption and noise, so the engines will serve the Collins class
well in the remaining 20 or so years of life for the class.
CHAPTER 21
‘A patch on this and chewing gum on
that’: the combat system 1993–97
In 1993 the submarine project office told ASC that the combat
system would be delivered in two stages – the first stage (release
1.5) sufficient for the first submarine’s trials, with the second stage
(release 2) being the complete system to be delivered for the trials
of the second submarine. Throughout the period 1993 to 1997
this remained the plan, but the delivery of stage two increas-
ingly seemed like a mirage, shimmering in the distance, while the
submarine project staggered thirstily through the desert of end-
less ‘releases’ and ‘drops’ of successive versions of stage one. As
the contractors and the project office tried desperately to cobble
together a system that would allow the submarines to go to sea,
the hopes that had inspired the ambitious specifications for the
‘world’s best combat system’ seemed distant indeed.
The project office’s quarterly reports chart the story of the
incremental releases, together with the ever more distant deliv-
ery of the complete combat system and the steady elimination of
the more demanding requirements.
In September 1993 Computer Sciences was testing release 1.5
of the combat system software and ‘to date there do not appear
to be any fundamental problems’, although ‘the overall stability
244
THE COMBAT SYSTEM 1993–97 245
together with related software problems. The fact that this caused
system-wide failures shows the immaturity and fragility of the
system.
In September 1996 the project office reported on a further
review of the combat system, which concluded that Rockwell
could not complete the final software release as scheduled. The
stark reality now was that the schedule for the withdrawal of
the Oberons from service meant that soon only the new sub-
marines would be in service and, unless the combat system rapidly
improved, these would be less capable than the submarines they
were replacing.
During late 1996 and early 1997 several drops of release 1.5.5
followed each other in quick succession, but with only marginal
improvements in performance. One of the priorities was to get the
software to the level where the submarines could fire torpedoes.
In March 1997 the project office reported on firing preparations,
saying that ‘confidence in the system as a whole has increased, but
unexplained behaviour still occurs’. By the end of 1997 progress
on release 2 had stalled so that its completion by September 1999
was seen as ‘high risk’.
The project office reports are a chronicle of endless delays and
frustrations with the combat system, numerous reductions in per-
formance expectations and frantic efforts to stitch together a sys-
tem to get the submarines to sea. For the crews of Collins and
Farncomb the situation was extremely discouraging. Having been
led to believe that they would be given the world’s best conven-
tional submarine with the world’s most advanced combat system,
it was deflating to find that the performance of the combat system
struggled to match that of the Oberons. Peter Sinclair felt that:
‘The biggest bugbear was the combat system because this just did
not eventuate and we ended up commissioning the submarine with
what could only be described as an antiquated system and no real
fix in hand.’ Asked how the system compared with the Oberons,
Sinclair described it as
For those who had spent years working on the combat system,
reports of this sort were devastating – nobody ever questioned
that they were trying their best to get it right. At Rockwell and
its main sub-contractor Computer Sciences of Australia the mid-
1990s were years of turmoil and upheaval, with changes of own-
ership adding to the technical and contractual quagmire of the
combat system project.
During 1993 AMP sold Computer Sciences Australia to its
original parent company, Computer Sciences Corporation of
America. Chris Miller recalls that the takeover process took a
long time, during which the company was in limbo, although the
technical people tried hard ‘to clean up the mess’ and many things
were fixed before the new management moved in.
The new American owners sent out ‘a couple of really hard-
nosed guys’, Martin Babst and Al David, to run the combat sys-
tem project and they introduced a new focus into the company’s
work.4 They were prompted largely by a major dispute with Rock-
well in late 1993, when Rockwell defaulted Computer Sciences
for failing to agree to a release 2 delivery date. This action by
Rockwell prompted the new American management of Computer
Sciences, together with the contract manager, Tony Houseman,
to take the approach that it would do what it was contracted
to do and nothing more – there would be no more changes of
direction and no more changes to the requirements. The empha-
sis in the company changed from development to closure, from
250 THE COLLINS CLASS SUBMARINE STORY
RESOLUTION
CHAPTER 22
‘Hardly a day went by without the
project getting a hammering in the
press’: the project in crisis 1997–98
257
258 THE COLLINS CLASS SUBMARINE STORY
Ron Dicker believes that the ‘TI338 regime’ contributed to the dif-
ficulties between ASC and the project. The TI338 was the form on
which warranty defects were recorded and before anything could
be done they had to be evaluated to decide whether ASC or the
project would carry the cost. This resulted in endless arguments.
Dicker found it was not an efficient process for fixing the boats
and keeping them at sea. In other projects he had been involved
in there was a system whereby any defect was analysed and fixed,
and then the responsibility for it was arbitrated by an independent
body.
Many people in the navy and the project office tell of their
confrontations with Hans Ohff during this period. Peter Clarke,
who was project manager during 1998, deliberately set about pro-
ducing a harder, tougher relationship with Hans Ohff by insisting
on ASC meeting its milestones as ‘the overall project plan had
been lost sight of’. Although he had previously got on well with
Hans Ohff, within a few weeks of beginning his new job they were
shouting at each other: ‘Hans Ohff would say things like, “You’re
only taking this line to get yourself promoted”.’9 Clarke claims
that Hans Ohff ‘is the only man ever to have hung up on me – all
the others have been females,’ but that being said, they remained
friends throughout the project.
Hans Ohff’s attitude and motives are little understood and crit-
icisms of him are often made by people with little knowledge of
his full role in the submarine project. He had a greater emotional
commitment to the project than almost anyone else involved, and
those who might match him for commitment – like Oscar Hughes,
Graham White, Andy Millar and other long-serving members of
the project team – largely share his perspective on the problems of
the submarines. Ohff’s entire working life since he arrived in Aus-
tralia had been devoted to the development of Australian engineer-
ing, and for him building submarines in Australia was the great
nation-building project for his generation. He had been the first to
argue seriously that the submarines could be built in Australia, and
then devoted much time and money to spreading his vision to gov-
ernments and industry. Devastated when Eglo Engineering chose
the wrong side in the selection process, he saw his return to the
project as the opportunity to ensure its success. When he screamed
at the crew of a submarine returning to Osborne after a break-
down, ‘What have you done with my submarine?’ he expressed a
THE PROJECT IN CRISIS 1997–98 263
genuine feeling of ownership that was hard for senior navy person-
nel on two- or three-year rotations to comprehend. While Hans
Ohff always conceded that the submarines had teething difficul-
ties, particularly with the diesel engines, and that there were some
issues where compromises on performance were struck between
ASC and the project office, he genuinely believes that the prob-
lems were greatly exaggerated by anti-submarine elements in the
navy and by Coalition politicians looking to damage Kim Beazley.
For him, the navy and the politicians ‘took the elation out of the
project’.10
While the combat system remained the most intractable prob-
lem with the submarines during 1997 and 1998, on most other
issues there was clear if slow improvement, and some (such as the
leaking shaft seals) were dealt with completely. However, in 1998
a new issue developed with the propellers which proved difficult
to resolve and led to bitter recriminations between ASC, the navy
and Kockums.
For over a year there had been growing concern about cavi-
tation from the propellers and the usual disagreements between
ASC, which said the cavitation resulted from the way the sub-
marines were operated, and the navy, which blamed design and
manufacturing flaws. However, in August 1998 a crack was found
in Collins’ propeller during routine maintenance, and checks of
the other submarines revealed incipient cracking problems. Kock-
ums and ASC claimed there was nothing wrong with the design of
the propellers, but the Sonoston alloy demanded extremely pre-
cise manufacturing techniques and they accepted that some of the
early propellers were not made to the required standard. The navy
and the project office, however, believed that the problems were
more fundamental and argued that the propellers should be re-
designed. When Eoin Asker went overseas to look for advice, he
felt that Kockums was a company in crisis, its design expertise was
declining and its response to the problem was slow. In contrast
the Americans were keen to help, offering to remodel a propeller
to try on one of the Australian submarines.
In response to this offer, a Swedish-designed propeller was sent
to America. In Asker’s view ‘this was an operational imperative –
it would have taken ages for the Swedes to deal with it and it
wasn’t in Australia’s interest to muck around’. A second propeller
was sent later and a third in 2000.
264 THE COLLINS CLASS SUBMARINE STORY
for the submarine project and, rather than dismantle the program,
he looked to extend it by taking the option in the contract to build
two more submarines.17
While McLachlan became a supporter of the new submarines,
during 1997 he was increasingly uneasy about the problems fac-
ing the project. Peter Jennings, his chief of staff, recalls that
McLachlan’s concerns were initially prompted by the navy’s
request for approval to refit two Oberons to keep them in service
until the new submarines finally arrived, and then his attention
was galvanised by the increasingly critical media coverage of the
project. By the end of 1997 he was looking for suggestions ‘to
bring the project to finality’.18
Before 1993 there was little interest in the submarine project at
the higher levels of the navy. Under Oscar Hughes the project was
like a medieval city state with nominal loyalty to its titular suzerain
but in fact operating independently and rejecting any interfer-
ence. Following Hughes’ retirement the navy moved to reduce
the project’s independence by downgrading the project director’s
position from two-star to one-star rank, but it took several years
before the navy began to accept any responsibility for the project
and longer still before it began to understand what was involved
in being the parent navy for the new submarines.
Rod Taylor, who was chief of the naval staff from 1994 to
1997, began to be concerned about the state of the project and
the suitability of the submarines for naval service. He was cau-
tious and conservative and concerned that there might be a royal
commission if things went wrong, so he began to document care-
fully the unfolding situation with the project, and set down the
major issues in papers that were considered by all the main defence
committees.19
However, the concerns in navy and defence at this stage appear
strangely academic, with no sense of ownership of the project, no
enthusiasm or excitement and no understanding of the magnitude
of the challenges that ASC and the project team faced. The Aus-
tralian navy and the Defence Department seem to have regarded
the submarines as if they were a standard product ordered from
a foreign shipyard. It only gradually dawned on them that ulti-
mately they were responsible for the submarines. If they did not
work as the navy wanted, then the navy must lead the way in
fixing them.
268 THE COLLINS CLASS SUBMARINE STORY
Many believe that the real source of the problems the navy had
in dealing with the submarine project was the anti-submarine feel-
ings common among surface sailors. There is a strong conviction
among submariners, ASC staff and members of the project office
that there was a strong faction in the navy opposed to the sub-
marine project and determined to make sure that the government
would never approve the construction of two more submarines.20
They believe that many of the critical media stories were based on
leaks from within the navy. One long-time project member says
that:
The thing that really got me in 1998 was that hardly a day
went by without the project getting a hammering in the press.
We did not deny that there were issues, but in most cases we
knew the solutions and were working towards them . . . The
stuff in the press was beyond belief. Journalists didn’t want to
know that what they were publishing was a load of nonsense.
I couldn’t understand why we had such a problem at the
time but I did find out years later why and that’s because of
where it was coming from. Now that’s one thing I won’t tell
you but suffice to say it was coming from a very senior
credible naval source who was doing it for his own political
reasons which were really to try to scuttle the submarine
project to get money to spend the money on surface ships.21
While the surface sailors see views like this as pure paranoia and
deny strenuously that they sabotaged the submarine project, the
fact that such views grew up and persisted is symptomatic of the
divisions and suspicions that bedevilled the project from the mid-
1990s.
In 1997 Don Chalmers followed Rod Taylor as chief of the
navy, and in February 1998 Paul Barratt succeeded Tony Ayers
as secretary of the Department of Defence. Barratt thought the
submarine project looked like many disparate projects with peo-
ple working hard but often at cross purposes, and he decided
that one of his priorities must be to draw it all together. Working
closely with Don Chalmers, Garry Jones of the Defence Acqui-
sition Organisation, and Richard Brabin-Smith, the chief defence
scientist, agreement was reached on the steps to take, most notably
that the US navy should be asked to help.22
THE PROJECT IN CRISIS 1997–98 269
274
THE MCINTOSH-PRESCOTT REPORT 275
The military seemed to have the attitude that the minister’s role
was to get money from the parliament and then leave them to
spend it free of supervision or control. The navy in particular, he
felt, had ‘a delightful indifference to government’.1
From the beginning Moore was wary of the advice he was
given by the department and looked for counsel to Sir Malcolm
McIntosh, then chief executive of the CSIRO. A career public
servant, McIntosh had been involved in the submarine project as
a deputy secretary of defence in charge of acquisitions in the late
1980s before achieving fame and a knighthood as head of defence
procurement in the United Kingdom from 1991 to 1996. Moore
found McIntosh ‘was a source of enormous comfort in explaining
complex matters in a way that was easy to understand’.
At the time he became minister there was enormous publicity
about the problems with the submarines and ‘the Americans were
poking their noses in the project and wondering what was hap-
pening’. Malcolm McIntosh told him there was a major problem
with the submarine project and ‘the whole thing is out of con-
trol and needs a broom through it’. Consequently Moore asked
the secretary of the department, Paul Barratt, for a report on the
submarines to explain why they were built, what was wrong with
them, how they were going to be fixed, and how much it would
cost. The report came back but Moore saw it as ‘a complete white-
wash’ so he asked for further reports – one to be signed by Barratt
and Chris Barrie, the chief of the defence force, to confirm that they
both agreed the answers were correct – but in Moore’s view they
were ‘all whitewashes’. Moore showed the reports to Malcolm
McIntosh, who agreed that they skated over the surface of the
problems. Asked what should be done, McIntosh said: ‘Appoint
me to investigate.’
Not surprisingly, Paul Barratt has a different perspective on
these events. Even before the new ministry was announced, it had
been suggested to him that he might like to move from defence,
but he rejected this as he enjoyed defence and saw much that
needed to be done. When Moore was appointed, Barratt and Chris
Barrie asked when they could brief the new minister, but were
told this would not be necessary, and when the new minister met
the departmental executive a few days later he was continually
quoting Malcolm McIntosh on the deficiencies of the department
and how to fix them.
276 THE COLLINS CLASS SUBMARINE STORY
The chief of the navy, Don Chalmers, held similar views to Paul
Barratt on John Moore’s approach. He says:
My view is that he took a very political stand on the
submarine. This was a Bomber Beazley contract – it wasn’t
working and he was going to get as much political mileage
out of it as he could. He wanted a submarine that worked
but he was going to get as much as he could out of it.
. . . I quite often had difficulty talking with him. I didn’t
get on with his chief of staff so I didn’t get in the door . . . As
we moved ahead talking to the minister about the submarine
became really difficult . . . On one occasion he told me that
he got more information on the Collins class from his
newsagent than he did from navy briefings. It was a prickly
relationship, one might say.
One important factor in the relationship between the navy and the
minister is that John Moore always had a struggle with dyslexia.
He found reading difficult and preferred to get information ver-
bally or in a one-page précis. The lengthy reports sent to him by
the department and the navy went unread, while those with the
gift of succinctness like Malcolm McIntosh gained his attention.
Garry Jones, Eoin Asker, Paul Barratt and the admirals believed
that they understood the problems with the submarine project and
were confident that, with American help, they had developed a
viable plan to overcome them. Their problem was that the minister
did not believe them.
Convinced he was not being told the full story by the navy and
the Defence Department, in March 1999 John Moore decided to
follow Malcolm McIntosh’s advice and appointed him to inves-
tigate. As McIntosh was already terminally ill, Moore appointed
John Prescott, formerly managing director of BHP, to work with
him on the report.
Paul Greenfield was selected to support the investigation and
provide technical submarine knowledge. After several years work-
ing on the submarine project based in Adelaide, he had recently
been appointed to command HMAS Cerberus at Flinders, but he
had not been there two months when he was told he had been cho-
sen to help McIntosh and Prescott. He went very much against his
will as he felt it would be a disastrous career move – he recalls a
navy colleague telling him, ‘I see you’re part of the Tainted Team’!
278 THE COLLINS CLASS SUBMARINE STORY
The report concluded that ‘the essential and visible problem with
the Collins Class submarines is that they cannot perform at the lev-
els required for military operations’. It acknowledged that in some
high-risk areas such as the high tensile steel, the Australian weld-
ing and the ship control and management system, the submarines
‘exceeded expectations’ and that some serious defects such as the
propeller shaft seals had been fixed. The authors also accepted
that some technical deficiencies were inevitable ‘in a new class of
equipment as complex as a submarine’, but they were ‘astonished
at how many there still are some 6 years after the first boat was
launched, the range and extent of them, the seriousness of some
of them, the areas in which they have occurred, and how slowly
they are being remedied’.
The report identified the most serious remaining defects as
the diesel engines, noise, propellers, periscopes and masts, and
the combat system. While accepting that on some issues such as
noise there were significant differences between ‘the contracted
requirements and the Navy’s current operational requirements’,
McIntosh and Prescott concluded that there were serious defi-
ciencies in the design and manufacture of the submarines. The
authors also accepted that in some areas, such as the propellers
and periscopes, problems were due in part at least to inappropriate
requirements, notably the use of Sonoston for the propellers.
McIntosh and Prescott emphasised that the combat system was
the central problem:
Basically the system does not work, the quality of
information from individual sensors has been compromised
and their display on screen is inferior to that of the signals
actually processed. Relatively routine interrogation of targets
causes failures in the displays and inordinate delays occur in
bringing multiple sets of information together in the manner
planned. The number of targets that can be dealt with at one
time is far less than specified or required. In fact the tracking,
282 THE COLLINS CLASS SUBMARINE STORY
They argued that these problems arose from the unique military
specifications and the decision to include the combat system with
the platform in the single prime contract, with the subsequent
refusal to change course or modify the contract. In contrast,
Britain and the United States both started down the same path
in the 1980s but later moved to structure their systems around
commercial, off-the-shelf technology.
Looking at the causes of the problems with the submarine
project, McIntosh and Prescott saw deficiencies in the structure
of the contract, notably the difficulty of negotiating changes, the
small contingency and the combination of performance specifica-
tions with some detailed specifications as to how the performance
should be achieved. They also saw a lack of overall direction and
understanding of the aims of the project6 and conflicts of interest
in the ownership structure of ASC, which had led to a situation
like trench warfare with all parties being ‘far more antagonistic,
defensive, uncooperative and at cross-purposes than should be the
case in a project like this’.
McIntosh and Prescott accepted that fixes were already under
way for most of the mechanical problems such as the diesel
engines, noise and propellers, but saw the combat system as more
of a challenge. In their view there was no hope that the combat sys-
tem could ever ‘be transformed to an effective performance level’
and recommended that it be replaced with a ‘proven in-service’
system based on commercial off-the-shelf equipment.
There was one rather strange reaction to the project. While the
media and opponents of the project leapt on the headline state-
ments such as ‘are bedevilled by a myriad of design deficiencies’, a
surprisingly large number of people close to the project, but with
widely differing views, claimed to have authored large parts of
the report or at least to have provided the inspiration for much
of it. Mick Dunne claims that ‘the McIntosh-Prescott review was
almost transcribed directly from a document I did for Chalmers at
the end of 1997’. Similarly, John Dikkenberg says: ‘They basically
came and took our report and 70, 80 per cent of what they wrote
in their thing came directly from our analysis.’ Again, Paul Barratt
THE MCINTOSH-PRESCOTT REPORT 283
states: ‘In the end the famous report which the government always
refers to as independent is little more than a version of the report
that I had earlier given to the minister – the difference was that
my report was classified “Secret” and could not be released.’ The
willingness of people to claim authorship suggests that the find-
ings of the report were not controversial – most people connected
with the project agree that the report raised nothing new.
Yet the government presented the report as ground-breaking
and the media reacted similarly. John Moore says:
Kerry O’Brien: But what does it say that it’s taken this long
to actually bring together all of the things that people have
either known about or expected for so long – diesel
engines, noise, sonar, combat system, as you say. Even the
periscope shakes.
John Moore: Well, there are certainly a number of
complaints there and problems, but I think all of those can
be fixed, and my job is to make sure these submarines are
fully operational and in the sea as quickly as possible,
because they are very important to Australian defence.
Kerry O’Brien: But what does it say about the people who
have been monitoring this, who have been responsible for
this whole submarine program from the outset, that this
extraordinary litany of faults are still there, this far into it?
284 THE COLLINS CLASS SUBMARINE STORY
The reaction to the report from people connected with the project
varied greatly. In most, but not all, cases the response was pre-
dictable. The navy hierarchy and the upper echelons of defence
were angry and perplexed. They believed they had been giving
the minister essentially the same message as the report since he
took office and could not comprehend that they were now blamed
for not telling him. They did not argue with the report’s findings
because it was their contention that they had been saying the same
things.
One exception to this is the view of Paddy Hodgman, Don
Chalmers’ chief staff officer. He saw a number of the findings, par-
ticularly on the combat system, as ‘fundamentally flawed’, with
the report overall deferring too much to grand political gestures
rather than what was best for the submarines. In his view the
report led to delay and waste. Hodgman is particularly critical of
the recommendation to scrap the combat system as ‘we hadn’t fin-
ished testing the fixes’ suggested by the Americans, so ‘we didn’t
know what we were throwing away’. Similarly, Andrew John-
son believes it would have been cheaper and easier to make the
existing combat system work than to start again. Otherwise, he
thought the McIntosh-Prescott report quite competent, though in
the atmosphere of the late 1990s ‘it was a bit like bayoneting the
wounded’.
The Kockums’ perspective on the report is that it is ‘a mixed
bag of flaws with no analysis as to their seriousness’. Except for
the combat system (which was not their responsibility), the Swedes
felt that the problems with the submarines were ‘small and what
you would expect with any new design’.8
The general view of the report among submariners is that it was
a fair analysis of the situation of the submarine project. While the
report did not say anything new, it acted as a ‘circuit breaker that
was desperately needed to turn the project around’.9 This view
had some support within ASC. Martin Edwards recalls:
[Although] it was obviously being done to achieve an
outcome, I think most people who had spent 10 or 12 years
THE MCINTOSH-PRESCOTT REPORT 285
that level. However, once Barratt went, Jones soon followed. The
McIntosh-Prescott report recommended upgrading the position
of head of procurement, suggesting that the new head come from
the private sector, and this provided the justification for removing
Jones.
Barratt’s own appointment was terminated at the end of August
1999. He did not go quietly but fought a lengthy court action
alleging wrongful dismissal. The final result of the case was that
the court decided ministers could sack departmental heads for no
reason and did not need to justify their decision.
As Kerry O’Brien noted when interviewing John Moore after
the release of the McIntosh-Prescott report, the minister seemed
very calm in the face of a ‘diabolical’ report on the state of his
department’s largest project. But Moore saw the problems as being
Beazley’s problems, not his own. His task was to sell the solution,
not excuse the problems. The centrepiece of his program to fix
the submarines was to appoint Peter Briggs to head a new team to
‘fast-track’ the work needed to make the submarines operational.
As Moore said: ‘Admiral Briggs is the most senior submariner in
Australia and I have no doubt he will play a very prominent part
in getting all this up and going.’10
CHAPTER 24
‘That villain Briggs’ and the submarine
‘get-well’ program
In the early 1980s Peter Briggs was one of the driving forces in
drawing up the ambitious requirements for the new submarines,
but from 1985 his postings took him away from the project, and in
the 1990s away from submarines altogether as he held a succession
of senior positions, concluding with appointment as head of the
strategic command division in 1997. In mid-1999 he was among
the contenders to replace Don Chalmers as chief of the navy. When
he was passed over as chief he began planning his retirement,
but put this on hold when he was asked to take charge of the
submarine project with the task of ‘achieving a fully operational
and sustainable submarine capability as quickly as possible’. He
‘came into the job with nothing to lose, a problem to solve and
a nicely defined period to do it in’ and felt that this ‘suited my
personality of quick answers and no prisoners between here and
there’.1
John Moore believed that the project had been strangled by
committees, with nobody accepting responsibility, and he wanted
one person to take charge, with wide powers and reporting directly
to the minister. Consequently Peter Briggs was given power to
cut through red tape, let contracts without going through the
287
288 THE COLLINS CLASS SUBMARINE STORY
On receiving this draft, Peter Briggs sent this e-mail to the senior
staff of the capability team, the project office and the submarine
squadron:
Peter Briggs recalls that when Waller went to Hawaii, the Collins
project was still at a critical stage and he spoke with Admiral
Konetzni, who told him: ‘Don’t worry, we’ll make your boys look
good.’ Consequently Waller did well – the crew performed well
with the equipment they had – but it was not a balanced test;
the playing field was tilted in Waller’s favour to allow for what
it could do well without exposing its weaknesses, particularly its
noise at speed and dysfunctional combat system. The submarine
was quiet at low speeds and the exercise was set up so Waller
did not have to move fast. She impressed the Americans with her
potential and did better than expected, ‘but if you have a chance
to get more money for the submarines you don’t throw it away’.
‘THAT VILLAIN BRIGGS’ 297
In early August 2000 Peter Briggs and Paul Greenfield gave a brief-
ing on progress with the submarine ‘get-well’ program. Comment-
ing on the combat system, Briggs said:
Last week Collins successfully launched the first Harpoon
missile fired by a Collins class submarine. It constituted one
of a series of tests to prove that the Harpoon missile has been
integrated and can be initialised and fired by the combat
system.
[Don’t] draw any judgements that the combat system is
suddenly passing its exams. It’s not. The combat system must
be replaced. The system is cumbersome and difficult to
operate. It doesn’t handle the data adequately and it’s too
slow. It’s been overtaken by the computer revolution.
My recommendation remains: the cheapest, the fastest
and the most effective way from where we are now is to
replace it.1
Peter Briggs asked how long it would take before a contract could
be signed for the new system, saying he wanted it within a year.
When he was told it would take at least four years to call for
299
300 THE COLLINS CLASS SUBMARINE STORY
tenders, assess them, go through the committees and get the con-
tract set up, Briggs said (as Paul Greenfield recalls), ‘Read my
lips, we will have it within a year’. Greenfield was put in charge
of the project to buy a replacement combat system and, follow-
ing Briggs’ advice to cut corners and ‘work with a room full of
experts rather than a room full of paper’, the selection was made in
10 months.2
Greenfield’s brief was to follow the recommendation of the
McIntosh-Prescott report and recommend the best ‘new, modern
COTS [commercial off-the-shelf] based combat system against a
minimal dot point specification’.3 McIntosh and Prescott empha-
sised that the new combat system should be in service and proven.
Greenfield asked for guidance from the navy on strategic consid-
erations – such as the impact on the American alliance – to be
taken into account in the choice, but none was given.
Four main contenders were identified and early in 2000 all
except Lockheed Martin brought operational versions of their
systems to the DSTO laboratories at Salisbury in South Australia,
where they were plugged into the ‘virtual Collins’ to evaluate their
performance. These were the German STN Atlas’s ISUS 90–55
system, Raytheon’s CCS Mk2 system, and the French Thales-led
consortium’s Subtics system. The Thales and Lockheed Martin
systems were eliminated in May 2000 and then teams of scien-
tists and engineers went around the world to look at the STN and
Raytheon systems at work in operational submarines.
Todd Mansell of DSTO’s submarine combat systems team saw
the STN Atlas system on an Israeli Dolphin class submarine and
the Raytheon system on the 6000-ton Los Angeles class nuclear
attack submarine USS Montpelier. While the visit to the American
submarine was more comfortable, the Australians were far more
impressed with the combat system on the Israeli submarine.4
STN Atlas was always aware that Raytheon had an advantage,
as the US Navy would be wary of the possibility of a European
company gaining access to the secrets of its weapons systems and
tactics. Consequently, it teamed up with Lockheed Martin to han-
dle the weapons interface and provide the weapons software for
the Australian bid in order to mitigate the security concerns.
The evaluation team found that the STN Atlas system was
clearly superior. It generally met or exceeded all the navy’s
requirements without need for significant modification, while the
THE SAGA OF THE REPLACEMENT COMBAT SYSTEM 301
The evaluation team argued that this problem had been foreseen.
They had arranged to purchase all the source code and to include
an ‘Australian eyes only’ support facility in Australia for the sys-
tem. In addition Lockheed Martin was part of the STN team and
would provide all the weapons software, which the evaluation
team believed would have avoided any difficulties with US infor-
mation being given to the Germans.16 Shackleton was not con-
vinced.
Shackleton denies that he was pressured to reject a European
solution:
The decision to buy American rather than German paved the way
for a formal agreement on cooperation on all submarine-related
matters, which was signed in Washington on 10 September 2001.
Admiral Phil Davis analysed the agreement and its consequences
from the American perspective:
310
KOCKUMS, ASC AND ELECTRIC BOAT 311
been identified while the sections were still in Sweden and these
had been worked on at various times by ASC, an independent
review found numerous faulty welds and cracks in the Swedish
sections while the Australian-built sections showed close to zero
defects. The consequence for Collins was that the full-cycle dock-
ing took four years to complete.
However, the news of the defects was far from unwelcome to
those involved in the negotiations with Kockums over intellectual
property, as it gave them a strong bargaining chip. Kockums was
looking for a payment of about $50 million for its intellectual
property, and the cost of fixing the welding defects was a use-
ful tool for bringing that sum down. While not denying that the
welding was poorly done, the Kockums view is that the Common-
wealth exaggerated the defects because they saw it as the ‘counter
to use to trade for Kockums’ intellectual property’.10
The issues were discussed with considerable vigour until the
middle of 2004, when a settlement was finally agreed. The central
terms of the settlement were:
Defence and ASC have full access to Kockums’ intellectual
property for maintaining, supporting and upgrading the
Collins Class submarines throughout the life of the Class.
Formal termination of the various contracts between the
parties for the design and construction of the submarines,
and subsequent settlement of all claims arising from these
contracts.
Provision of a contract under which Defence and ASC
may have access to Kockums’ design services for support of
the Collins Class submarines as required.11
Kockums was paid $25 million for its intellectual property rights
and was released from its warranty under the contract.12 The
settlement gave the Defence Department, ASC and their sub-
contractors access to Kockums’ intellectual property, within a
framework that gave some protection to Kockums’ proprietary
information without restricting Australian access to US subma-
rine technology.
The sixth and final submarine, HMAS Rankin, was launched
on 7 November 2001. Following its contractor’s sea trials it
was formally delivered by ASC on 18 March 2003 and commis-
sioned into naval service on 29 March 2003. Rankin was delayed
318 THE COLLINS CLASS SUBMARINE STORY
319
320 THE COLLINS CLASS SUBMARINE STORY
At the same time Electric Boat was also building several Trident
nuclear submarines, but progress was ‘truly glacial’ because ‘the
new generation of nuclear submarines was proving so complex,
so sophisticated as to rival in scope the great medieval cathedrals
of Europe, where tradesmen passed their tasks from generation to
generation, each hoping he would be among those to pray inside’.2
The problems with the Los Angeles and Trident classes were
due, at least in part, to specific difficulties within Electric Boat and
its parent company, General Dynamics, at that time. Nonetheless,
the next American submarine project, the Seawolf class, was even
more disastrous. The Seawolf project suffered from substantial
cost increases, lengthy schedule delays and serious welding fail-
ures. The architecture for the combat system proved too hard to
build and had to be completely redesigned.3
Britain has been building submarines for over a century, but
several recent projects have had major problems. Of most interest
from the Australian point of view is the Upholder project, as this
class was touted as the low-risk choice for Australia’s new sub-
marine. Mike Gallagher saw that ‘the Upholders had significant
tales of woe’. He was in England during the period they were com-
missioned and decommissioned and he recalls that they were well
behind schedule (with the first boat taking seven years from build
to in service), they had great difficulties firing their weapons and
major problems with their drive trains. Similarly Jim Ring, in his
account of Britain’s submariners during the Cold War, comments
COMPARISON AND RETROSPECT 321
The Collins class submarines each have almost four million parts,
75 kilometres of cable, 200 000 on-board connections, 23.5 kilo-
metres of pipe, 14 000 pipe welds and 34.5 kilometres of hull
welding. These figures are impressive, but even more striking is the
systems integration task involved in assembling the submarines.
Using components from many countries, ASC installed hundreds
of electronic, electrical and mechanical systems and ensured they
worked together as intended. The Collins submarine project was
the biggest systems integration task ever undertaken in Australia.
The submarine project involved far more risks than were
admitted – at least publicly – at the time the contracts were
signed. The original requirement that the winning submarine
design should be in service or close to in service with a parent
navy was quietly dropped and the Swedish design that won the
competition was, as its detractors claimed, a paper boat. Further,
it was a bold and innovative design, as the Swedes had sensed
that their chance to win lay with meeting the high demands of
Australia’s submariners, flushed with the success of the Oberon
COMPARISON AND RETROSPECT 323
specifications had been met, and even harder to get the parties
involved to agree on whether they had been met. This was further
complicated because the navy’s expectations had changed since
the specifications were established, due primarily to advances in
technology. What the 1987 contract laid down was not always
what the navy wanted in 1997, yet under a fixed-price contract
ASC was determined (and well within its rights) to do no more
than it was contractually bound to do.
There was no effective mechanism for resolving the disputes
over whether the specifications had been met or for meeting the
navy’s enhanced expectations. ASC, Kockums, the project office,
the navy and the newly-established Defence Acquisitions Organi-
sation spent several years shouting at each other and threatening
litigation, while relatively straightforward engineering problems
went unfixed. Not surprisingly, the media and politicians mis-
took the cacophony of noise coming from the submarine project
as showing that the submarines were seriously flawed. Equally
unsurprisingly, politicians found it impossible to resist the temp-
tation to use the project’s disarray for political point-scoring.
Many people have seen the fixed-price contract with limited
contingency as the main cause of the project’s problems, arguing
that it meant there was limited money to fix faults and no flexibil-
ity to allow for changed operational requirements or technological
progress. Peter Briggs has noted that of the $1.17 billion allo-
cated to ‘fix’ the submarines after the McIntosh-Prescott report,
only $143 million was for areas where the submarines failed to
meet the contractual requirements (in other words, to fix the sub-
marines); $300 million was for changed operational requirements
and $727 million for technological obsolescence. He argues that
the submarines should have been treated as a research and devel-
opment project, with DSTO, the SWSC and the submarine oper-
ators continuously involved and some form of flexible alliance
contract with the builder.
On the other hand, the contractors themselves, along with
Oscar Hughes, argue that the fixed-price contract had substan-
tial benefits. The greatest of these is that the project was a rar-
ity among military procurements in that the original budget was
still relevant at the end of the project. The general public percep-
tion – encouraged by members of the Coalition government – is
that the project was a financial disaster.7 This is not true. While
COMPARISON AND RETROSPECT 325
Introduction
1. It remained so until the goverment’s decision in 2007 to spend $6.6 billion on
F/A18 F Super Hornets and $8 billion on air warfare destroyers.
330
NOTES TO PAGES 7–16 331
23. John Button, Flying the kite: Travels of an Australian politician, Random
House, Sydney, 1994, p. 73.
20. Cavitation occurs when bubbles of air are separated from the water through
which the propeller is travelling, greatly increasing the submarine’s noise levels.
21. Report of the Tender Evaluation Board, p. 5-32.
22. ibid., p. 5-33.
23. While Dalrymple does not dispute this position he thinks that he probably made
the point more to contrast with what he thought was the superior quality of the
IKL/HDW design. He notes that the board report did not always accurately
report the tone or scope of discussions.
24. Report of the Tender Evaluation Board, p. 5-38.
25. ibid., p. 5-20.
26. ibid., p. 6-4.
27. ibid., p. 6-38.
28. ibid., p. 6-16.
29. Interview with Ron Dicker.
30. Report of the Tender Evaluation Board, p. 6-45.
31. ibid., p. 6-13.
32. ibid., p. 6-45.
33. ibid., p. 7-4.
34. ibid., p. 8-25.
35. ibid., p. 5-67.
36. ibid., p. 5-68.
37. ibid., p. 5-68.
38. Diary of Jim Duncan, 21 November 1984; Carney Hocking & Day, ‘Report with
recommendations to Vickers Shipbuilding and Engineering Limited’, May 1984.
39. Report of the Tender Evaluation Board, p. 8-22.
40. ibid., p. 8-23.
41. ibid., p. 8-27.
42. ibid., p. 9-3.
43. ibid., p. 9-1.
44. ibid., p. 10-1.
45. ibid., p. 9-5.
46. ibid., p. 9-3.
15. The section on the states’ campaigns is based on interviews with John Bannon,
Jim Duncan, Ross Milton, Roger Sprimont, Graham White and Geoff Rose.
28. Ritterhoff’s comments quoted in Heinz Schulte, Frank Cranston & Tony Banks,
‘IKL accuses Australia over Type 2000 submarine rejection’, Jane’s Defence
Weekly, 18 July 1987, pp. 1087–8.
29. Note from Oscar Hughes to authors, August 2007.
30. Interview with John Bannon.
14. Australian National Audit Office, Report No. 22, New submarine project, 1992.
15. Interviews with Ken Grieg and Hans Ohff.
16. For McLachlan’s leadership of the economic ‘dries’ in the 1980s see Paul Kelly,
The end of certainty: Power, politics and business in Australia, rev. edn, Allen &
Unwin, Sydney, 1994, pp. 253–4.
17. Unfortunately the authors were unable to interview Mr McLachlan for this
book. This assessment of his views is based on interviews with Hans Ohff, John
Bannon, Eoin Asker, Peter Jennings and Paul Barratt.
18. Interview with Paul Barratt.
19. Interview with Chris Oxenbould.
20. Their view is supported by Paul Barratt, who comments: ‘I had the strong sense
that some of the surface sailors felt that a dollar spent on submarines was a
dollar not available to be spent on the surface fleet. No-one could accuse them
of having the nation’s defence uppermost in their minds.’ Note to authors, July
2007.
21. Interview with Mark Gairey.
22. Interview with Paul Barratt.
23. Interview with Don Chalmers.
24. Admiral Riddell was the US Navy’s senior adviser to allied navies.
25. Interview with Admiral John Butler.
26. Australian, 16 May 2000.
27. In discussions with the authors several Americans referred to the possibility of
supplying Australian submarine technology to ‘a third party’, and it was clear
from the context they were referring to Taiwan.
28. Review of Auditor-General’s Report No. 34 1997–98, New submarine project,
p. 64. http://www.aph.gov.au/house/committee/jpaa/
submarine/CHAPTER9.PDF
29. Essentially up to this point the submarines were ‘owned’ by the DAO and
responsibility for their operation and maintenance was ASC’s through the
contract between DAO and ASC. The navy is the DAO’s customer and as soon
as the navy accepts the submarine it is responsible for support and repairs.
30. Project office quarterly report, June 1998. Views on this issue are based on
interviews with Don Chalmers, Hans Ohff, Paul Armarego, Wal Jurkiewicz,
Peter Briggs, Paddy Hodgman, Terry Roach and Hugh White.
10. Interviews with David Shackleton and John Moore; Australian, 22 and 23
December 2000.
11. Interview with Kevin Scarce.
12. Interviews with Peter Sinclair and Peter Briggs.
13. Project office report, September 2001, p. 16.
14. Interview with David Shackleton.
15. Notes from David Shackleton to authors, July 2007.
16. Interview with Peter Briggs.
17. Interview with David Shackleton.
18. ibid.
19. Notes from David Shackleton to author, July 2007.
20. Project office report, December 2000.
21. Interview with Peter Briggs.
22. Interview with David Shackleton.
23. Interview with Phil Davis.
24. Note to authors, August 2007.
25. ibid.
26. Interviews with Bob Clark and Ted Vanderhoek.
7. One of the authors was told by a senior minister during a conversation in a lift
that: ‘Oh, so you’re writing about the submarines? They were a financial
disaster – they’ve cost us billions.’
8. The figures from DMO’s file on SEA1114 – the original Collins
project – are:
349
350 INDEX