SUMMARY OF PROGRESS TRANSHIPMENT ON VESSEL

MV. MANALAGI TISYA

NAME OF VESSEL : MV. MANALAGI TISYA START LOADING ON VESSEL : September 30, 2018 at 18.20 LT
STOWAGE PLAN : 51.500 WMT COMPLETED LOADING ON VESSEL : October 10, 2018 at 19.15 LT
DATE IN : September 30, 2018 at 06.00 LT TOTAL CARGO LOADED : 51.500 WMT
NOR TENDERED : September 30, 2018 at 06.00 LT DATE OUT : October 11, 2018 at 03.00 LT
COMMENCED OF LOADING : September 30, 2018 at 18.20 LT DATE OF COMPLETE LOADING LIMIT : October 10, 2018 at 22.00 LT

A. PLAN OF ORE LOADING ON VESSEL


NO Description BARGE SIMULATION TOTAL
BARGE 1 BARGE 2 BARGE 3 BARGE 4 BARGE 5 BARGE 6 BARGE 7 BARGE 8 BARGE 9 BARGE 10 10 Barges
1 NUMBER OF BARGE
JAWA RTB 2 JAWA RTB 2 JAWA RTB 2 JAWA RTB 2 JAWA RTB 2
2 DATE OF LOADING 30-Sep-18 1-Oct-18 2-Oct-18 3-Oct-18 4-Oct-18 5-Oct-18 6-Oct-18 7-Oct-18 8-Oct-18 9-Oct-18 10 Days
3 BARGE CAPACITY 5,200 5,200 5,200 5,200 5,200 5,200 5,200 5,200 5,200 5,200 52,000
4 NUMBER OF TRIP 250 250 250 250 250 250 250 250 250 215 2,465 Trips
5 PLAN OF CARGO LOADING 5,250 5,250 5,250 5,250 5,250 5,250 5,250 5,250 5,250 4,515 51,765 WMT

B. PROGRESS OF ORE LOADING ON VESSEL

NO Description ORE LOADING PROGRESS REMARKS


1 NUMBER OF BARGE BARGE 1 BARGE 2 BARGE 3 BARGE 4 BARGE 5 BARGE 6 BARGE 7 BARGE 8 BARGE 9 BARGE 10 10 Barges
2 NAME OF BARGE JAWA RTB II JAWA RTB 2 JAWA RTB 2 JAWA RTB 2 JAWA RTB 2 1. Initial draft survey
3 NAME OF TUGBOAT Delta Jaya 1 Delta Jaya 3 Delta Jaya 2 Kalindo Utama 2 Delta Jaya 1 Delta Jaya 3 Delta Jaya 2 Kalindo Utama 2 Delta Jaya 1 Delta Jaya 3 on September 30, 2018 at 11.00 - 11.30 LT
DAY 30-Sep-18 30-Sep-18 2-Oct-18 3-Oct-18 4-Oct-18 5-Oct-18 6-Oct-18 7-Oct-18 9-Oct-18 10-Oct-18 2. Hatch inspection by Surveyor
4 ALONGSIDE
TIME 17.20 LT 18.30 LT 08.35 LT 05.40 LT 07.20 LT 04.45 LT 12.40 LT 16.15 LT 05.30 LT 05.00 LT on September 30, 2018 at 11.30 - 12.00 LT
DAY 30-Sep-18 1-Oct-18 2-Oct-18 3-Oct-18 4-Oct-18 5-Oct-18 6-Oct-18 7-Oct-18 9-Oct-18 10-Oct-18 3. Final draft survey
5 START LOADING
TIME 18.20 LT 12.00 LT 08.45 LT 09.00 LT 07.30 LT 04.55 LT 12.50 LT 16.25 LT 05.40 LT 05.10 LT on October 10, 2018 at 19.15 - 19.45 LT
DAY 1-Oct-18 2-Oct-18 2-Oct-18 3-Oct-18 5-Oct-18 5-Oct-18 7-Oct-18 8-Oct-18 10-Oct-18 10-Oct-18 4. Completed loading on Vessel
6 COMPLETED LOADING
TIME 10.45 LT 03.05 LT 20.00 LT 20.15 LT 02.45 LT 20.35 LT 08.45 LT 04.30 LT 24.25 LT 19.15 LT on October 10, 2018 at 19.15 LT
CAST OFF FROM DAY 1-Oct-18 8-Sep-18 3-Oct-18 4-Oct-18 5-Oct-18 6-Oct-18 7-Oct-18 9-Oct-18 10-Oct-18 10-Oct-18 5. Completed loading in about 9 days 11 hours
7
VESSEL TIME 10.50 LT 09.05 LT 04.35 LT 06.20 LT 03.15 LT 11.10 LT 15.20 LT 04.30 LT 04.30 LT 19.45 LT
8 WAITING CARGO 0 5.5 9.6 10.7 2 16.0 7.5 25 0.0 0.0 76 Hours
9 RAIN TIME 0 0 3.1 0 4 1.25 4.5 0 0.5 1 14 Hours
10 NUMBER OF TRIP (Trip) 250 225 245 268 270 260 270 270 270 250 2,578 Trips
11 CARGO LOADED (WMT) 4,767 6,779 4,778 5,467 7,175 2,827 4,760 5,652 5,473 3,825 51,503 WMT