3. Action plan for disaster No action plan for disaster Make action Plan for the
• enrolled for Disaster
insurance/Officers
Group has action plan for
disaster
Financial
1. Segregated financial management No segregated financial Put additional personnel with
duties and responsibilities management duties and segregated roles and
Collection responsibilities responsibilities
Cashiering
Recording
Audit and Inventory
2. Inventory and recoding No proper Inventory and recording Conduct of Inventory of
Conduct of regular inventory Materials
of materials and inventory
3. Bank Account No clear signatories of existing Bank Check existing bank account
Existing bank account with account as to the required signatories
leastthree(3) signatories
Account signatories are not
personally related
4. Expenditures No available Disbursement vouchers, Reproduction of Disbursement
Approved Disbursement OR and pre-numbered invoice Vouchers & Pre-
numbered Invoice
voucher for every
disbursement or substitute
OR issued
Pre-numbered Invoice issued
5. Books of Accounts No books of accounts Purchase Books of
Record of collections Accounts for financial
Record of account receivables records
Record of expenses (cash
book)
Record of Accounts payable
6. Financial reports No preparation of Regular Prepare Financial Reports
Periodic Report of Income Financial reports every meeting
and Expenses
Balance Sheet
7. Financial Control No financial control measures Conduct Regular Financial
Conduct of regular internal Control measures
audit
Conduct of on-the-spot cash
check
Conduct of external audit
8. Collection efficiency No Official receipt Purchase Official receipt
Collection mechanism with duplicate copy for
Proof of Collection (OR/AR monthly collection of Tariff
issued for collections or
substitute) with duplicate
copy
9. Petty Cash Fund No established petty cash fund Establishment of Petty cash
With available petty cash Fund
fund
Physical and Technical
1. Intake Box/Source NA NA
▪ Walls, Top Slab &
Foundation
▪ Pipe Fittings; Over Flow,
Valves
▪ Perimeter Diversion
canal
▪ Perimeter fence
▪ Tree planting within the
Surcharge Area
2. Reservoir Presence of leaks in the reservoir Repair / patching of leaks
▪ Walls, Top Slab &
Foundation
▪ Pipe Fittings; Over Flow,
Valves, Vents
▪ Perimeter Diversion canal
▪ Perimeter fence
3. Pipelines (Transmission & Leaking and defective distribution Repair of leaking and
Distribution) lines defective Pipelines
▪ Exposure/Soil covering
for HDPE & uPVC pipeline,
Supports and fittings for
GI Pipes,
▪ Presence of Leaks and
other defects.
4. Tap Stand NA NA
▪ Stability of pedestal
▪ Condition of Faucets
▪ Stability of Concrete flat
form
▪ Diversion canal
▪ Flow of Water supply
5. Others, specify Presence of New water source
Resurvey of new source Survey new spring as proposed
as new water source
New Reservoir Propose to make new reservoir Make new reservoir from
surveyed source
Apply for potability test Propose potability test for the new Conduct potability test
source