Beruflich Dokumente
Kultur Dokumente
Management
What is a Project
Projects and Operations
What is a Project
• It is common practice for an organization to have
more than one project active at a time. In fact,
several projects that share common characteristics
or are related in some way are often grouped
together to make management or the project more
efficient.
Do • Execution
Done • PPR
Organizational Influences
Organizational Influences…
Organizational Influences…
WBS
Project Management Estimation
Scheduling
How To Schedule
• 1. Identify “what” needs to be done
• Work Breakdown Structure (WBS)
• 2. Identify “how much” (the size)
• Size estimation techniques
• 3. Identify the dependency between tasks
• Dependency graph, network diagram
• 4. Estimate total duration of the work to be
done
• The actual schedule
Project Elements
• A Project: functions, activities, tasks
A Full WBS Structure
• Up to six levels (3-6 usually) such as
Bottom-Up
• Time consuming
WBS • Needs more requirements complete
Techniques Analogy
• Based on past actual experience
Rolling Wave
• 1st pass: go 1-3 levels deep
• Gather more requirements or data
• Add more detail later
Apply Earned Value
Analysis
33
November 21, 2005
34
• Schedule Variance
• = EV – PV = $5,000 – $7,500 = - $2,500
• Schedule Performance Index (SPI)
• = EV/PV = $5,000 / $7,500 = .66
• Cost Variance
What is the •
•
= EV – AC = $5,000 - $9,000 = - $4,000
Cost Performance Index (CPI)
project health? • = EV/AC = $5,000 / $9,000 = .55
38
Cost
Performance
Index (CPI).
• A project with a CPI of .93 means you are spending 1.00 for every .93
worth of work accomplished. Therefore, a CPI under 1.00 means the
project is performing poorly against the plan.
• EAC=Budget at Completion (BAC)/Cost
Performance Index (CPI)
• For example, if the project’s BAC is
$575,000 and the CPI is .91, the
EAC for this project is $631,868
EAC/ETC • Estimate to Complete (ETC)
• ETC=EAC-AC
• Traffic Light status is useful in
Establish conveying overall project with one
color
Ranges to • Establish objective SPI and CPI ranges
to determine the true project color.
Guide Traffic • Green [1.0 - .95]
Light Status • Yellow [.94-.85]
• Red [.84, 0]
You are the Program Manager managing the construction of a new airport. Five
project managers are directly reporting to you. Each project manager is assigned a
part of the total scope of works to be executed independently. The total duration
allowed to complete all works is 24 months and the total approved budget is
$10,000,000.
At the end of the first year, you should have completed $6,000,000 worth of work
but the project is only 50% complete. Actual costs reported by each project
manager for the first year are:
Project manager 1: $200,000 , Project manager 2: $1,200,000 , Project manager 3:
$1,800,000 ,Project manager 4: $500,000 , Project manager 5: $900,000