Sie sind auf Seite 1von 15

RULES AND REGULATIONS FOR THE CLASSIFICATION OF A FLOATING OFFSHORE INSTALLATION AT A FIXED LOCATION, June 2013

Oil Engines Part 5, Chapter 2


Section 8

8.7.5 The valves are to be provided with a copy of the 8.9.4 In determining the volume of the crankcase for the
manufacturer’s installation and maintenance manual for the purpose of calculating the combined free area of the
size and type of valve being supplied. The manual is to crankcase relief valves, the volume of the stationary parts
contain the following information: within the crankcase may be deducted from the total
(a) Description of valve with details of function and design internal volume of the crankcase.
limits.
(b) Copy of type test certification.
(c) nstallation instructions. 8.10 Vent pipes
(d) Maintenance and in-service instructions to include
testing and renewal of any sealing arrangements. 8.10.1 Where crankcase vent or breather pipes are fitted,
(e) Actions required after a crankcase explosion. they are to be made as small as practicable and/or as long
as possible to minimise the inrush of air after an explosion.
8.7.6 A copy of the installation and maintenance manual
required by 8.7.3 is to be provided on board the unit.
8.11 Dead ship condition starting arrangements
8.7.7 Plans showing details and arrangements of the
crankcase relief valves are to be submitted for approval, 8.11.1 Means are to be provided to ensure that machinery
see 1.1. can be brought into operation from the dead ship condition
without external aid.
8.7.8 The valves are to be provided with suitable markings
that include the following information: 8.11.2 Dead ship condition for the purpose of 8.1.1 is to be
(a) Name and address of manufacturer. understood to mean a condition under which the main
(b) Designation and size. propulsion plant, boilers and auxiliaries are not in operation.
(c) Month/year of manufacture. In restoring propulsion, no stored energy for starting and
(d) Approved installation orientation. operating the propulsion plant is assumed to be available.
Additionally, neither the main source of electrical power nor
other essential auxiliaries are assumed to be available for
8.8 Number of crankcase relief valves starting and operating the propulsion plant.

8.8.1 In compressors having cylinders exceeding 200 mm 8.11.3 Where the emergency source of power is an
but not exceeding 250 mm bore, at least two relief valves emergency generator which fully complies with the
are to be fitted; where more than one relief valve is requirements of Pt 6, Ch 2, this generator may be used for
required, the valves are to be located at or near the ends of restoring operation of the main propulsion plant, boilers and
the crankcase. auxiliaries where any power supplies necessary for engine
operation are also protected to a similar level as the starting
8.8.2 In compressors having cylinders exceeding 250 mm arrangements.
but not exceeding 300 mm bore, at least one relief valve is
to be fitted in way of each alternate crankthrow with a 8.11.4 Where there is no emergency generator installed or an
minimum of two valves. For compressors having 3, 5, 7, 9, emergency generator does not comply with Pt 6, Ch 2, the
etc., crankthrows, the number of relief valves is not to be arrangements for bringing main and auxiliary machinery into
less than 2, 3, 4, 5, etc., respectively. operation are to be such that the initial charge of starting air or
initial electrical power and any power supplies for engine
8.8.3 In compressors having cylinders exceeding 300 mm operation can be developed on board without external aid. If for
bore, at least one valve is to be fitted in way of each main this purpose an emergency air compressor or an electric
crankthrow. generator is required, these units are to be powered by a hand-
starting oil engine or a hand-operated compressor. The
8.8.4 Additional relief valves are to be fitted for separate arrangements for bringing main and auxiliary machinery into
spaces on the crankcase, such as gear or chain cases, operation are to have capacity such that the starting energy
3 and any power supplies for engine operation are available
when the gross volume of such spaces exceeds 0,6 m .
within 30 minutes of a dead ship condition.

8.9 Size of crankcase relief valves


8.12 Air receiver capacity
8.9.1 The combined free area of the crankcase relief valves
2 3 8.12.1 Where the main engine is arranged for air starting,
fitted on a compressor is to be not less than 115 cm /m
the total air receiver capacity is to be sufficient to provide,
based on the volume of the crankcase.
without replenishment, no fewer than 12 consecutive starts
8.9.2 The free area of each relief valve is to be not less of the main engine, alternating between ahead and astern if
2 of the reversible type and no fewer than six consecutive
than 45 cm .
starts if of the non-reversible type. At least two air receivers
8.9.3 The free area of the relief valve is the minimum flow of approximately equal capacity are to be provided. For
area at any section through the valve when the valve is fully scantlings and fittings of air receivers, see Chapter 11.
open.

16 LLOYD’S REGISTER
RULES AND REGULATIONS FOR THE CLASSIFICATION OF A FLOATING OFFSHORE INSTALLATION AT A FIXED LOCATION, June 2013

Oil Engines Part 5, Chapter 2


Section 8

8.12.2 For multi-engine installations, the number of starts 8.14.2 Each emergency generator that is arranged to be
required for each engine is to be as follows: automatically started is to be equipped with an approved
(a) Two engines through common reduction gearing: starting system having two independent sources of stored
six starts per engine for fixed pitch energy, each of which is sufficient for at least three
propeller/propellers; three starts per engine for consecutive starts. When hand (manual) starting is
controllable pitch propeller/ propellers. demonstrated to be effective, only one source of stored
(b) Three engines or more through common reduction energy need be provided. However, this source of stored
gearing: three starts per engine. energy is to be protected against depletion below the level
required for starting.
8.12.3 No engine is to have fewer than three starts for any
arrangement. For electric propulsion arrangements, a 8.14.3 Provision is to be made to maintain continuously the
minimum of three starts per engine with a minimum stored energy at all times, and for this purpose:
capacity of 12 starts of the largest start air consumption (a) Electrical and hydraulic starting systems are to be
engine in total is required. maintained from the emergency switchboard.
(b) Compressed air starting systems may be maintained by
the main or auxiliary compressed air receivers, through a
8.13 Electric starting suitable non-return valve, or by an emergency air
compressor energised by the emergency switchboard.
8.13.1 Where main engines are fitted with electric starters, (c) All these starting, charging and energy storing devices
two batteries are to be fitted. Each battery is to be capable are to be located in the emergency generator room.
of starting the engines when cold and the combined These devices are not to be used for any purpose
capacity is to be sufficient without recharging to provide the other than the operation of the emergency generator.
number of starts of the main engines as required by 8.12.
In other respects, batteries are to comply with the 8.14.4 When automatic starting is not required by the Rules
requirements of Pt 6, Ch 2,12. and where it can be demonstrated as being effective, hand
(manual) starting is permissible, such as manual cranking,
8.13.2 Electric starting arrangements for auxiliary engines inertial starters, manual hydraulic accumulators, powder
are to have two separate batteries or be supplied by charge cartridges.
separate circuits from the main engine batteries when such
are provided. Where one of the auxiliary engines only is 8.14.5 When hand (manual) starting is not practicable, the
fitted with an electric starter, one battery will be acceptable. provisions under 8.14.2 and 8.14.3 are to be complied with,
except that starting may be manually initiated.
8.13.3 The combined capacity of the batteries for starting
the auxiliary engines is to be sufficient for at least three 8.14.6 Electric starting arrangements are also to satisfy
starts for each engine. 8.13.2 to 8.13.5.

8.13.4 Engine starting batteries are to be used only for the


purposes of starting the engines and for the engines’ own 8.15 Engine control, alarm monitoring and safety
control, alarm, monitoring and safety arrangements. Means system power supplies
are to be provided to ensure that the stored energy in the
batteries is maintained at a level required to start the 8.15.1 Power supplies are to be arranged so that power for
engines, as defined in 8.13.1 and 8.13.3. electrically powered control, alarm, monitoring and safety
systems required for engine starting and operation will remain
8.13.5 Where engines are fitted with electric starting available in the event of a failure. Power is to remain available
batteries, an alarm is to be provided for low battery charge to permit starting attempts for the number of starts specified by
level. this Section for each individual source of stored energy.

8.15.2 Where adequate battery and charging capacity


8.14 Starting of the emergency source of power exists, an engine starting battery may be used as one
source of electrical power required by 8.15.1.
8.14.1 Emergency generators are to be capable of being
readily started in their cold conditions down to a 8.15.3 An alarm is to be activated in the event of failure of a
temperature of 0°C. If this is impracticable, or if lower power supply and, where applicable, low battery charge
temperatures are likely to be encountered, consideration is level. Manual power supply changeover facilities are
to be given to the provision and maintenance of heating permitted.
arrangements, so that ready starting will be assured.

LLOYD’S REGISTER 17
RULES AND REGULATIONS FOR THE CLASSIFICATION OF A FLOATING OFFSHORE INSTALLATION AT A FIXED LOCATION, June 2013

Oil Engines Part 5, Chapter 2


Section 9

■ Section 9 9.3 Engine type testing

Component tests and engine type 9.3.1 New engine types or developments of existing types
testing are to be subjected to an agreed programme of type testing
to complement the design appraisal and review of
9.1 Hydraulic tests documentation.

9.1.1 In general, items are to be tested by hydraulic pressure 9.3.2 Guidelines for type testing of engines will be supplied
as indicated in Table 2.9.1. Where design features are such on application.
that modifications to the test requirements shown in Table 2.9.1
are necessary, alternative proposals for hydraulic tests are to 9.3.3 Wherever practical, type tests are to be conducted
be submitted for special consideration. with the engine control systems operational in the approved
configuration, see 1.1.4 and 1.1.5. Configuration
9.1.2 Where a manufacturer has demonstrated to LR that management documents are to be reviewed at testing for
they have an acceptable Quality Management System, a validity and referenced in the type test report.
manufacturer’s hydraulic test certificate may be accepted
for engine driven pumps as detailed in Table 2.9.1. 9.3.4 An engine type is defined in terms of:
Recognition and acceptance of the works, Quality Control • basic engine data: e.g. bore, stroke;
processes can be by one of the following routes: • working cycle: 2 stroke, 4 stroke;
(a) Approval under the LR Quality Scheme for Machinery. • cylinder arrangement: in-line, vee;
(b) Approval of an alternative quality scheme recognised • cylinder rating;
by LR. • fuel supply: e.g. direct, or indirect injection, dual fuel; and
(c) Approval by LR through auditing of the manufacturer’s • gas exchange: natural aspiration, pressure charging
Quality System. arrangement.

9.3.5 Where an engine type has subsequently proved


9.2 Alignment gauges satisfactory in service with a number of applications, a
maximum uprating of 10 per cent may be considered
9.2.1 All main and auxiliary oil engines exceeding 220 kW (300 without a further complete type test.
shp) are to be provided with an alignment gauge which may be
either a bridge weardown gauge, or a micrometer clock gauge 9.3.6 A type test will be considered to cover engines of a
for use between the crankwebs. Only one micrometer clock given design for a range of cylinder numbers in a given
gauge need be supplied for each unit provided the gauge is cylinder arrangement.
suitable for use on all engines.

Table 2.9.1 Test pressures for oil engine components


Item Test pressure

}
Pump body, pressure side

Fuel injection system {PipeValve


The lesser of 1,5p or p + 300 bar

}
Cylinder cover, cooling space
Cylinder liner, over the whole length of cooling space 7,0 bar
Piston crown, cooling space (where piston rod seals cooling
space, test after assembly)

}
Cylinder jacket, cooling space

Exhaust valve, cooling space


Turbo-charger, cooling space The greater of 4,0 bar or 1,5p
Exhaust pipe, cooling space
Coolers, each side
Engine driven pumps (oil, water, fuel, bilge)
Air compressor, including cylinders, covers, intercoolers and Air side: 1,5p
aftercoolers Water side: The greater of 4,0 bar or 1,5p
Scavenge pump cylinder 4,0 bar

Hydraulic systems (piping, pumps, actuators) 1,5p

NOTES
1. p is the maximum working pressure in the item concerned.
2. Pumps used in jerk or timed pump systems need only have the assembled high pressure-containing components hydraulically tested.
3. Turbo-charger air coolers need only be tested on the water side.
4. For forged steel cylinder covers and piston crowns, alternative testing methods may be specially considered.
5. For hydraulic systems where design features are such that modifications to the test requirements are necessary, alternative
proposals for hydraulic tests are to be submitted for special consideration.

18 LLOYD’S REGISTER
RULES AND REGULATIONS FOR THE CLASSIFICATION OF A FLOATING OFFSHORE INSTALLATION AT A FIXED LOCATION, June 2013

Oil Engines Part 5, Chapter 2


Sections 10 & 11

■ Section 10 ■ Section 11
Turbo-chargers Mass produced engines
10.1 Plans and particulars 11.1 Definition

10.1.1 The following plans and particulars are to be 11.1.1 Mass produced engines, for main and auxiliary
submitted for information: purposes, are defined as those which are produced under
• Cross-sectional plans of the assembled turbo-charger the following criteria:
with main dimensions. (a) In quantity under strict Quality Control of material and
• Fully dimensioned plans of the rotor. parts, according to a quality assurance scheme
• Material particulars with details of welding and surface accept-able to LR.
treatments. (b) By the use of jigs and automatic machine tools
• Turbo-charger operating and test data. designed to machine parts to specified tolerances for
• A selected turbo-charger is to be type tested. inter-changeability, and which are verified on a regular
• Manufacturer’s burst test assessment. inspection basis.
(c) By assembly with parts taken from stock and requiring
little or no fitting.
10.2 Type test (d) With bench tests carried out on individual assembled
engines according to a specified programme.
10.2.1 A type test is to consist of a hot gas running test of (e) With appraisal by final examination of engines
at least one hour’s duration at the maximum permissible selected at random after workshop testing.
speed and maximum permissible temperature. Following
the test, the turbo-charger is to be completely dismantled 11.1.2 Castings, forgings and other parts for use in mass
for examination of all parts. produced engines are also to be produced by methods
similar to those given in 11.1.1(a), (b) and (c), with
10.2.2 Alternative arrangements will be specially appropriate inspection.
considered.
11.1.3 Pressure testing of components is to comply with
9.1.1.
10.3 Dynamic balancing
11.1.4 The specification of a mass produced engine is to
10.3.1 All rotors are to be dynamically balanced on final define the limits of manufacture of all component parts. The
assembly to the Surveyor’s satisfaction. total production output is to be certified by the manufacturer
and verified as may be required by LR, in accordance with
the agreed manufacturer’s Quality Assurance scheme, see
10.4 Overspeed test 11.1.1(a).

10.4.1 All fully bladed rotor sections and impeller/inducer


wheels are to be overspeed-tested for three minutes at 11.2 Procedure for approval of mass produced
either 20 per cent above the maximum permissible speed engines
at room temperature or 10 per cent above the maximum
permissible speed at the normal working temperature. 11.2.1 The procedure outlined in 11.2.2 to 11.2.5 applies to
the inspection and certification of mass produced oil
engines having a bore not exceeding 300 mm.
10.5 Mechanical running test
11.2.2 For the approval of a mass produced engine type,
10.5.1 Turbo-chargers are to be given a mechanical the manufacturer is to submit:
running test of 20 minutes, duration at the maximum (a) The plans and particulars required by 1.1 for assessment.
permissible speed. (b) The information required by 3.2 for assessment.
(c) A list of subcontractors for main parts.
10.5.2 Upon application, with details of an historical audit (d) Procedures for the configuring of control, alarm
covering previous testing of turbo-chargers manufactured monitoring and safety systems during engine commis-
under an approved quality assurance scheme, sioning.
consideration will be given to confining the test outlined in
10.5.1 to a representative sample of turbo-chargers. 11.2.3 The manufacturer is to supply full information
regarding the manufacturing processes and Quality Control
procedures applied in the workshops. The information is to
address the following:
(a) Organisation of Quality Control systems.
(b) Recording of Quality Control operations.
(c) Qualification and independence of personnel in charge
of Quality Control.

LLOYD’S REGISTER 19
RULES AND REGULATIONS FOR THE CLASSIFICATION OF A FLOATING OFFSHORE INSTALLATION AT A FIXED LOCATION, June 2013

Oil Engines Part 5, Chapter 2


Section 11

11.2.4 A running type test of at least 100 hours’ duration is 11.5.3 The type tests are to be conducted with the engine
to be carried out on an engine chosen from the production control systems operational in the approved configuration,
line. The type testing is to comply with 11.5. see 1.1.4 and 1.1.5. Configuration management documents
are to be reviewed at testing for validity and referenced in
11.2.5 LR reserves the right to limit the duration of validity the type test report.
of approval of a mass produced engine. LR is to be
informed, without delay, of any change in the design of the 11.5.4 The duration and programme of type tests is to
engine, including changes to the software and control, include the following:
alarm monitoring or safety systems, in the manufacturing or (a) 80 h at rated output.
quality control processes, in the selection of materials or in (b) 8 h at 110 per cent overload.
the list of subcontractors for main parts. (c) 10 h at varying partial loads (25 per cent, 50 per cent,
75 per cent and 90 per cent of rated output).
(d) 2 h at maximum intermittent loads.
11.3 Continuous review of production (e) Starting tests.
(f) Reverse running of direct reversing engines.
11.3.1 LR Surveyors are to be provided free access to the (g) Testing of speed governor.
manufacturer’s workshops and to the quality control files. (h) Testing of overspeed device.
(j) Testing of lubricating oil system failure alarm device.
11.3.2 The control of production, which is subject to survey, (k) Testing of the engine with turbo-charger out of action
is to include the following: when applicable.
(a) Inspection and testing records are to be maintained to (l) Testing of minimum speed for main propulsion engines
the satisfaction of the Surveyor. and the idling speed for auxiliary engines.
(b) The system for identification of parts is to be in accor-
dance with recognised practice, and acceptable to LR. 11.5.5 The type tests in 11.5.4 at the required outputs are to
(c) The manufacturer is to provide full information about be combined together in working cycles for the whole
the quality control of the parts supplied by duration within the limits indicated. See also 11.5.11 and
subcontractors for which certification may be required. 11.5.12.
LR reserves the right to apply direct and individual
inspection procedures for parts supplied by 11.5.6 The overload testing required by 11.5.4 is to be
subcontractors when deemed necessary. carried out with the following conditions:
(d) At the request of an attending LR Surveyor, a workshop (a) 110 per cent of rated power at 103 per cent revolutions
test may be required for an individual engine. per minute for engines directly driving propellers.
(b) 110 per cent of rated power at 100 per cent revolutions
per minute for engines driving electrical generators or
11.4 Compliance and inspection certificate for other auxiliary purposes.

11.4.1 Each engine which is to be installed on a unit 11.5.7 For prototype engines, the duration and programme
classed by LR is to be supplied with a statement certifying of tests are to be specially agreed between the
that the engine is identical to the one which underwent the manufacturer and LR.
tests specified in 11.2.4, and state the test and inspection
results. The statement is to be made on a form agreed with 11.5.8 As far as practicable during type testing, the
LR. Each statement is to include the identification number following particulars are to be continuously recorded:
which appears on the engine. A copy of this statement is to (a) Ambient air temperature.
be submitted to LR. (b) Ambient air pressure.
(c) Atmospheric humidity.
11.4.2 The certificate is to include reference to the (d) External cooling water temperature.
manufacturer’s procedures to be followed during (e) Fuel and lubrication oil characteristics.
commissioning for configuring control, alarm monitoring
and safety systems for multi-purpose engines or other 11.5.9 In addition to the particulars stated in 11.5.8 and as
engine types that require parameters and settings to be far as practicable, the following are also to be continuously
adjusted for the intended application. measured and recorded:
(a) Engine revolutions per minute.
(b) Brake power.
11.5 Type test conditions (c) Torque.
(d) Maximum combustion pressure.
11.5.1 The requirements in this Section are applicable to (e) Indicator pressure diagrams where practicable.
the type testing of mass produced internal combustion (f) Exhaust smoke (with an approved smoke meter).
engines where the manufacturer has requested approval. (g) Lubricating oil pressure and temperature.
Omission or simplification of the type test requirements will (h) Exhaust gas temperature in exhaust manifold, and,
be considered by LR for engines of an established type on where facilities are available, from each cylinder.
application by the manufacturer.

11.5.2 The engine to be tested is to be selected from the


production line and agreed by LR.

20 LLOYD’S REGISTER
RULES AND REGULATIONS FOR THE CLASSIFICATION OF A FLOATING OFFSHORE INSTALLATION AT A FIXED LOCATION, June 2013

Oil Engines Part 5, Chapter 2


Sections 11 & 12

(j) For turbo-charged engines: 12.2.4 A type test, see 10.2, is to be carried out on a
• Turbo-charger revolutions per minute. standard unit taken from the assembly line and is to be
• Air temperature and pressures before and after witnessed by the Surveyor. The performance data which
turbo-blower and charge cooler. may have to be verified are to be made available at the
• Exhaust gas temperature and pressures before time of the type test. For manufacturers who have facilities
and after the turbine. for testing the turbo-charger unit on an engine for which the
• The cooling water inlet temperature to the charge turbo-charger is intended, substitution of the hot running
air cooler. test by a test run of one hour’s duration at overload (110
per cent of the rated output) may be considered.
11.5.10 After the type test, the main parts and especially
those subject to wear are to be dismantled for examination 12.2.5 LR reserves the right to limit the duration of validity
by LR Surveyors. of approval of a mass produced turbo-charger. LR is to be
informed, without delay, of any change in the design of the
11.5.11 For engines that are required to be approved for turbo-charger, in the manufacturing or control processes, in
different purposes (multi-purpose engines), and that have the selection of materials or in the list of subcontractors for
different performances profiles and control, alarm monitoring main parts.
and safety systems configurations for each purpose, the
programme and duration of test is to be modified to cover the
whole range of the engine performance, taking into account the 12.3 Continuous inspection of individual units
most severe conditions and intended purpose(s).
12.3.1 LR Surveyors are to be provided with free access to the
11.5.12 The rated output for which the engine is to be manufacturer’s workshop to inspect at random the Quality
tested is the output corresponding to that declared by the Control measures and to witness the tests required by 12.3.3
manufacturer and agreed by LR, i.e., actual maximum to 12.3.7 as deemed necessary, and to have free access to all
power which the engine is capable of delivering control records and subcontractor’s certificates.
continuously between the normal maintenance intervals
stated by the manufacturer at the rated speed and under 12.3.2 Each individual unit is to be tested in accordance
the stated ambient conditions. with 12.3.4 to 12.3.7 by the maker, who is to issue a final
certificate.

12.3.3 Rotating parts of the turbo-charger blower are to be


marked for easy identification with the appropriate
■ Section 12 certificate.
Mass produced turbo-chargers
12.3.4 Material tests of the rotating parts are to be carried
12.1 Application out by the maker or his subcontractor in accordance with
the requirements of the Rules for Materials, as applicable.
12.1.1 The following procedure applies to the inspection of The relevant certificate is to be produced and filed to the
exhaust driven turbo-chargers which are manufactured on the satisfaction of the Surveyor.
basis of mass production methods similar to 11.1, as
12.3.5 Pressure tests are to be carried out in accordance
applicable, and for which the maker has requested approval.
with Table 2.9.1. Special consideration will be given where
design or testing features may require modification of the
12.2 Procedure for approval of mass produced test requirements.
turbo-chargers
12.3.6 Dynamic balancing and overspeed tests are to be
carried out, see 10.3 and 10.4, in accordance with the
12.2.1 The procedure outlined in 12.2.2 to 12.2.5 applies to
approved procedure for quality control. If each forged wheel
the inspection and certification of mass produced turbo-
is individually controlled by an approved non-destructive
chargers when a simplified method of inspection has been
examination method, then no overspeed test may be
requested by the manufacturers.
required except for wheels of the test unit.
12.2.2 For the approval of a mass produced turbo-charger,
the manufacturer is to submit, in addition to the plans and 12.3.7 A mechanical running test, see 10.5, is to be carried
out. The duration of the running test may be reduced to 10
particulars required by 10.1.1, a list of main current
suppliers and subcontractors for rotating parts and an minutes, provided that the manufacturer is able to verify the
distribution of defects established during the running tests
operation and maintenance manual.
on the basis of a sufficient number of tested turbo-chargers.
12.2.3 The manufacturer will supply full information For manufacturers who have facilities in their works for
regarding the material and Quality Control system used in testing the turbo-chargers on an engine for which the turbo-
the organisation as well as the inspection methods, the way chargers are intended, the bench test may be replaced by a
of recording and proposed frequency, and the method of test run of 20 minutes at overload (110 per cent of the rated
material testing of important parts. output) on this engine.

LLOYD’S REGISTER 21
RULES AND REGULATIONS FOR THE CLASSIFICATION OF A FLOATING OFFSHORE INSTALLATION AT A FIXED LOCATION, June 2013

Oil Engines Part 5, Chapter 2


Sections 12 & 13

12.4 Compliance and certificate (f) The pressure measuring equipment is to be capable of
measuring the pressure in the test vessel in at least two
12.4.1 For every turbo-charger unit liable to be installed on positions, one at the valve and the other at the test vessel
an engine intended for a unit classed by LR, the centre. The measuring arrangements are to be capable of
manufacturer is to supply a statement certifying that the measuring and recording the pressure changes
turbo-charger is identical with one that underwent the tests throughout an explosion test at a frequency recognising
specified in 12.2.4 and that prescribed tests were carried the speed of events during an explosion. The result of
out. Results of these tests are to be also stated. This each test is to be documented by electronic recording and
statement is to be made on a form agreed with LR and a by recording with a heat sensitive camera.
copy is to be sent to LR. Each statement must have a (g) The test vessel for explosion testing is to have docu-
number which is to appear on the turbo-charger. mented dimensions. The dimensions are to be such
that the vessel is not pipe-like with the distance
between dished ends being not more than 2,5 times
the diameter. The internal volume of the test vessel is
to include any standpipe arrangements.
■ Section 13 (h) The test vessel is to be provided with a flange, located
Type testing procedure for centrally at one end at 90° to the vessel’s longitudinal
axis for mounting the explosion relief valve. The test
crankcase explosion relief valves vessel is to be arranged in an orientation
consistent with how the valve will be installed in service,
13.1 Scope i.e., in the vertical plane or the horizontal plane.
(j) A circular flat plate is to be provided for fitting between
13.1.1 To specify type tests and identify standard test the pressure vessel flange and valve to be tested with
conditions using methane gas and air mixture to demonstrate the following dimensions:
that LR requirements are satisfied for crankcase explosion (i) Outside diameter of two times the outer diameter
relief valves intended to be fitted to engines and gear cases. of the valve top cover.
(ii) Internal bore having the same internal diameter
13.1.2 The test procedure is only applicable to explosion as the valve to be tested.
relief valves fitted with flame arresters. Where internal oil (k) The test vessel is to have connections for measuring
wetting of a flame arrester is a design feature of an the methane in air mixture at the top and bottom.
explosion relief valve, alternative testing arrangements that (l) The test vessel is to be provided with a means of fitting an
demonstrate compliance with these requirements may be ignition source at a position as specified in 13.4.3.
proposed by the manufacturer. The alternative testing (m) The test vessel volume is to be, as far as practicable,
arrangements are to be submitted to LR for approval. related to the size and capability of the relief valve to be
tested. In general, the volume is to correspond to the
requirement in 6.3.1 for the free area of explosion relief
2 3
13.2 Purpose valve to be not less than 115 cm /m of crankcase gross
2
volume, e.g., the testing of a valve having 1150 cm of
13.2.1 The purpose of type testing crankcase explosion free area would require a test vessel with a volume of 10
relief valves is fourfold: 3
m . The following is to apply:
(a) To verify the effectiveness of the flame arrester. (i) Where the free area of relief valves is greater
(b) To verify that the valve closes after an explosion. 2 3
than 115 cm /m of the crankcase gross volume,
(c) To verify that the valve is gas/air tight after an explosion.
the volume of the test vessel is to be consistent
(d) To establish the level of overpressure protection with the design ratio.
provided by the valve. (ii) In no case is the volume of the test vessel to vary
by more than ±15 per cent from the design
2 3
cm /m volume ratio.
13.3 Test facilities

13.3.1 Test houses carrying out type testing of crankcase 13.4 Explosion test process
explosion relief valves are to meet the following requirements:
(a) The test houses where testing is carried out are to be 13.4.1 All explosion tests to verify the functionality of crankcase
accredited to a National or International Standard for explosion relief valves are to be carried out using an air and
the testing of explosion protection devices such as methane mixture with a volumetric methane concentration of
ISO/ IEC 17025. 9,5 per cent ±0,5 per cent. The pressure in the test vessel is to
(b) The test facilities are to be acceptable to LR. be not less than atmospheric and is not to exceed the opening
(c) The test facilities are to be equipped so that they can pressure of the relief valve.
perform and record explosion testing in accordance
with this procedure. 13.4.2 The concentration of methane in the test vessel is to
(d) The test facilities are to have equipment for controlling be measured at the top and bottom of the vessel and these
and measuring a methane gas in air concentration concentrations are not to differ by more than 0,5 per cent.
within a test vessel to an accuracy of ±0,1 per cent.
(e) The test facilities are to be capable of effective point
located ignition of a methane gas in air mixture.

22 LLOYD’S REGISTER
RULES AND REGULATIONS FOR THE CLASSIFICATION OF A FLOATING OFFSHORE INSTALLATION AT A FIXED LOCATION, June 2013

Oil Engines Part 5, Chapter 2


Section 13

13.4.3 The ignition of the methane and air mixture is to be 13.6.3 Stage 1. Two explosion tests are to be carried out in
made at the centreline of the test vessel at a position the test vessel with the circular plate as specified in
approximately one-third of the height or length of the test 13.3.1(j) fitted and the opening in the plate covered by a
vessel opposite to where the valve is mounted. 0,05 mm thick polythene film. These tests establish a
reference pressure level for determination of the capability
13.4.4 The ignition is to be made using a maximum of a relief valve in terms of pressure rise in the test vessel,
100 joule explosive charge. see 13.7.1(f).

13.6.4 Stage 2:
13.5 Valves to be tested (a) Two explosion tests are to be carried out on three
different valves of the same size. Each valve is to be
13.5.1 The valves used for type testing (including testing mounted in the orientation for which approval is sought,
specified in 13.5.3) are to be selected from the i.e., in the vertical or horizontal position with the circular
manufacturer’s normal production line for such valves by plate described in 13.3.1(j) located between the valve and
the LR Surveyor witnessing the tests. pressure vessel mounting flange.
(b) The first of the two tests on each valve is to be carried out
13.5.2 For approval of a specific valve size, three valves with a 0,05 mm thick polythene bag, having a minimum
are to be tested in accordance with 13.5.3 and 13.6. For a diameter of three times the diameter of the circular plate
series of valves, see 13.8. and volume not less than 30 per cent of the test vessel,
enclosing the valve and circular plate. Before carrying out
13.5.3 The valves selected for type testing are to have been the explosion test the polythene bag is to be empty of air.
previously tested at the manufacturer’s works to demonstrate The polythene bag is required to provide a readily visible
that the opening pressure is in accordance with the means of assessing whether there is flame transmission
specification within a tolerance of ±20 per cent and that the through the relief valve following an explosion. During the
valve is airtight at a pressure below the opening pressure for at test, the explosion pressure will open the valve and some
least 30 seconds. This test is to verify that the valve is airtight unburned methane/air mixture will be collected in the
following assembly at the manufacturer’s works and that the polythene bag. When the flame reaches the flame
valve begins to open at the required pressure, demonstrating arrester and if there is flame transmission through the
that the correct spring has been fitted. flame arrester, the methane/air mixture in the bag will be
ignited and this will be visible.
13.5.4 The type testing of valves is to recognise the (c) Provided that the first explosion test successfully
orientation in which they are intended to be installed on the demonstrated that there was no indication of combustion
engine or gear case. Three valves of each size are to be outside the flame arrester and there are no signs of
tested for each intended installation orientation, i.e., in the damage to the flame arrester or valve, a second
vertical and/or horizontal positions. explosion test without the polythene bag arrangement is
to be carried out as quickly as possible after the first test.
During the second explosion test, the valve is to be
13.6 Method visually monitored for any indication of combustion
outside the flame arrester and electronic records are to be
13.6.1 The following requirements are to be satisfied at kept for subsequent analysis. The second test is required
explosion testing: to demonstrate that the valve can still function in the
(a) The explosion testing is to be witnessed by a LR event of a secondary crankcase explosion.
Surveyor. (d) After each explosion, the test vessel is to be maintained
(b) Where valves are to be installed on an engine or gear in the closed condition for at least 10 seconds to enable
case with shielding arrangements to deflect the the tightness of the valve to be ascertained. The tightness
emission of explosion combustion products, the valves of the valve can be verified during the test from the
are to be tested with the shielding arrangements fitted. pressure/time records or by a separate test after
(c) Successive explosion testing to establish a valve’s completing the second explosion test.
functionality is to be carried out as quickly as possible
during stable weather conditions. 13.6.5 Stage 3. Carry out two further explosion tests as
(d) The pressure rise and decay during all explosion described in Stage 1. These further tests are required to
testing is to be recorded. provide an average baseline value for assessment of
(e) The external condition of the valves is to be monitored pressure rise, recognising that the test vessel ambient
during each test for indication of any flame release by conditions may have changed during the testing of the
electronic recording and heat sensitive camera. explosion relief valves in Stage 2.

13.6.2 The explosion testing is to be in three stages for


each valve that is required to be approved as being type
tested.

LLOYD’S REGISTER 23
RULES AND REGULATIONS FOR THE CLASSIFICATION OF A FLOATING OFFSHORE INSTALLATION AT A FIXED LOCATION, June 2013

Oil Engines Part 5, Chapter 2


Section 13

13.7 Assessment and records 13.8.2 The quenching ability of a flame arrester depends on
the total mass of quenching lamellas/mesh. Provided the
13.7.1 For the purposes of verifying compliance with the materials, thickness of materials, length of lamellas/thickness
requirements of this Section, the assessment and records of mesh layer and the quenching gaps are the same, then the
of the valves used for explosion testing is to address the same quenching ability can be qualified for different sizes of
following: flame arresters, subject to (a) and (b) being satisfied.
(a) The valves to be tested are to have evidence of n S
appraisal/approval by LR, see also 13.5.1. (a) 1 = 1

(b) The designation, dimensions and characteristics of the n S


2 2
valves to be tested are to be recorded. This is to
include the free area of the valve and of the flame
A S
(b) 1 = 1
arrester and the amount of valve lift at 0,2 bar. A2S2
(c) The test vessel volume is to be determined and
where
recorded. n
1 = total depth of flame arrester corresponding to the
(d) For acceptance of the functioning of the flame
number of lamellas of size 1 quenching device for a
arrester, there is not to be any indication of flame or
valve with a relief area equal to S1
combustion outside the valve during an explosion test.
n2 = total depth of flame arrester corresponding to the
(e) The pressure rise and decay during an explosion is to
number of lamellas of size 2 quenching device for a
be recorded, with indication of the pressure variation
valve with a relief area equal to S2
showing the maximum overpressure and steady
A1 = free area of quenching device for a valve with a
under-pressure in the test vessel during testing. The
relief area equal to S1
pressure variation is to be recorded at two points in
A2 = free area of quenching device for a valve with a
the pressure vessel.
(f) The effect of an explosion relief valve in terms of pressure relief area equal to S2.
rise following an explosion is ascertained from maximum
13.8.3 The qualification of explosion relief valves of larger
pressures recorded at the centre of the test vessel during
sizes than that which has been previously satisfactorily
the three stages. The pressure rise within the test vessel
tested in accordance with 13.6 and 13.7 can be evaluated
due to the installation of a relief valve is the difference
where valves are of identical type and have identical
between average pressure of the four explosions from
features of construction subject to the following:
Stages 1 and 3 and the average of the first tests on the
(a) The free area of a larger valve does not exceed three
three valves in Stage 2. The pressure rise is not to
times +5 per cent that of the valve that has been
exceed the limit specified by the manufacturer.
satisfactorily tested.
(g) The valve tightness is to be ascertained by verifying from
(b) One valve of the largest size, subject to (a), requiring
the records at the time of testing that an under-pressure
qualification is subject to satisfactory testing required
of at least 0,3 bar is held by the test vessel for at least 10
by 13.5.3 and 13.6.4 except that a single valve will be
seconds following an explosion. This test is to verify that
accepted in 13.6.4(a) and the volume of the test
the valve has effectively closed and is reasonably gas-
vessel is not to be less than one-third of the volume
tight following dynamic operation during an explosion.
required by 13.3.1(m).
(h) After each explosion test in Stage 2, the external condi-
(c) The assessment and records are to be in accordance
tion of the flame arrester is to be examined for signs of
with 13.7, noting that 13.7.1(f) will only be applicable
serious damage and/or deformation that may affect
to Stage 2 for a single valve.
the operation of the valve.
(j) After completing the explosion tests, the valves are to
13.8.4 The qualification of explosion relief valves of smaller
be dismantled and the condition of all components
sizes than that which has been previously satisfactorily
ascer-tained and documented. In particular, any
tested in accordance with 13.6 and 13.7 can be evaluated
indication of valve sticking or uneven opening that
where valves are of identical type and have identical
may affect the operation of the valve is to be noted.
features of construction subject to the following:
Photographic records of the valve condition are to be (a) The free area of a smaller valve is not less than one-third
taken and included in the report. of that of the valve that has been satisfactorily tested.
(b) One valve of the smallest size, subject to (a), requiring
qualification is subject to satisfactory testing required by
13.8 Design series qualification
13.5.3 and 13.6.4 except that a single valve will be
accepted in 13.6.4(a) and the volume of the test vessel is
13.8.1 The qualification of quenching devices to prevent the not to be more than the volume required by 13.3.1(m).
passage of flame can be evaluated for other similar devices
(c) The assessment and records are to be in accordance
of identical type where one device has been tested and
with 13.7, noting that 13.7.1(f) will only be applicable
found satisfactory.
to Stage 2 for a single valve.

24 LLOYD’S REGISTER
RULES AND REGULATIONS FOR THE CLASSIFICATION OF A FLOATING OFFSHORE INSTALLATION AT A FIXED LOCATION, June 2013

Oil Engines Part 5, Chapter 2


Sections 13 & 14

13.9 The report (b) The test house that verifies the functionality of the
equip-ment is to be equipped so that it can control,
13.9.1 The test house is to deliver a full report that includes measure and record oil mist concentration levels in
the following information and documents: terms of mg/l to an accuracy of ±10 per cent in
(a) Test specification. accordance with this procedure.
(b) Details of test pressure vessel and valves tested.
(c) The orientation in which the valve was tested, (vertical
or horizontal position). 14.4 Equipment testing
(d) Methane in air concentration for each test.
(e) Ignition source. 14.4.1 The range of tests is to include the following for the
(f) Pressure curves for each test. alarm/monitoring panel:
(g) Electronic recordings of each valve test. (a) Functional tests described in 14.5.
(h) The assessment and records stated in 13.7. (b) Electrical power supply failure test.
(c) Power supply variation test.
(d) Dry heat test.
13.10 Approval (e) Damp heat test.
(f) Vibration test.
13.10.1 The approval of an explosion relief valve is at the (g) EMC test.
discretion of LR, based on the appraisal of plans and (h) Insulation resistance test.
particulars and the test facility’s report of the results of type (j) High voltage test.
testing. (k) Static and dynamic inclinations, if moving parts are
contained.

14.4.2 The range of tests is to include the following for the


detectors:
■ Section 14 (a) Functional tests described in 14.5.
Type testing procedure for (b) Electrical power supply failure test.
(c) Power supply variation test.
crankcase oil mist detection and (d) Dry heat test.
alarm equipment (e) Damp heat test.
(f) Vibration test.
14.1 Scope (g) EMC test.
(h) Insulation resistance test.
14.1.1 To specify the tests required to demonstrate that (j) High voltage test.
crankcase oil mist detection and alarm equipment intended (k) Static and dynamic inclinations.
to be fitted to diesel engines satisfies LR requirements.

14.1.2 This test procedure is also applicable to oil mist 14.5 Functional tests
detection and alarm arrangements intended for gear cases.
14.5.1 All tests to verify the functionality of crankcase oil
mist detection and alarm equipment are to be carried out in
14.2 Purpose accordance with 14.5.2 to 14.5.6 with an oil mist
concentration in air, known in terms of mg/l to an accuracy
14.2.1 The purpose of type testing crankcase oil mist of ±10 per cent.
detection and alarm equipment is seven fold:
(a) To verify the functionality of the system. 14.5.2 The concentration of oil mist in the test chamber is to
(b) To verify the effectiveness of the oil mist detectors. be measured in the top and bottom of the chamber and
(c) To verify the accuracy of oil mist detectors. these concentrations are not to differ by more than 10 per
(d) To verify the alarm set points. cent. See 14.7.2(a).
(e) To verify time delays between oil mist leaving the
source and alarm activation. 14.5.3 The oil mist monitoring arrangements are to be capable
(f) To verify functional failure detection. of detecting oil mist in air concentrations of between 0 and 10
(g) To verify the influence of optical obscuration on per cent of the lower explosive limit (LEL), which corresponds
detection. to an oil mist concentration of approximately 50 mg/l (13 per
cent oil-air mixture) or between 0 and a percentage
corresponding to a level not less than twice the maximum oil
14.3 Test facilities mist concentration alarm set point.

14.3.1 Test houses carrying out type testing of crankcase 14.5.4 The alarm set point for oil mist concentration in air is
detection and alarm equipment are to satisfy the following to provide an alarm at a maximum setting corresponding to
criteria: not more than 5 per cent of the LEL or approximately 2,5
(a) A full range of facilities for carrying out the mg/l.
environmental and functionality tests required by this
procedure is to be available and be acceptable to LR.

LLOYD’S REGISTER 25
RULES AND REGULATIONS FOR THE CLASSIFICATION OF A FLOATING OFFSHORE INSTALLATION AT A FIXED LOCATION, June 2013

Oil Engines Part 5, Chapter 2


Section 14

14.5.5 Where alarm set points can be altered, the means of (b) The oil mist concentrations used are to be ascertained by
adjustment and indication of set points are to be verified the gravimetric deterministic method or equivalent. For
against the equipment manufacturer’s instructions. this test, the gravimetric deterministic method is a process
where the difference in weight of a 0,8 µm pore size
14.5.6 Where oil mist is drawn into a detector via piping membrane filter is ascertained from weighing the filter
arrangements, the time delay between the sample leaving before and after drawing one litre of oil mist through the
the crankcase and operation of the alarm is to be filter from the oil mist test chamber. The oil mist chamber
determined for the longest and shortest lengths of pipes is to be fitted with a recirculating fan.
recommended by the manufacturer. The pipe arrangements (c) Samples of oil mist are to be taken at regular intervals
are to be in accordance with the manufacturer’s and the results plotted against the oil mist detector
instructions/ recommendations. output. The oil mist detector is to be located adjacent
to where the oil mist samples are drawn off.
14.5.7 Detector equipment that is in contact with the (d) The results of a gravimetric analysis are considered
crankcase atmosphere and may be exposed to oil splash invalid and are to be rejected if the resultant calibration
and spray from engine lubricating oil is to be tested to curve has an increasing gradient with respect to the oil
demonstrate that openings do not occlude or become mist detection reading. This situation occurs when
blocked under continuous oil splash or spray conditions. insufficient time has been allowed for the oil mist to
Testing is to be in accordance with arrangements proposed become homogeneous. Single results that are more
by the manufacturer and agreed by LR. than 10 per cent below the calibration curve are to be
rejected. This situation occurs when the integrity of the
14.5.8 Detector equipment may be exposed to water vapour filter unit has been compromised and not all of the oil
from the crankcase atmosphere which may affect the is collected on the filter paper.
sensitivity of the equipment, it is to be demonstrated that (e) The filters require to be weighed to a precision of 0,1
exposure to such conditions will not affect the functional mg and the volume of air/oil mist sampled to 10 ml.
operation of the detector equipment. Where exposure to water
vapour and/or water condensation has been identified as a 14.7.3 The testing is to be witnessed by an LR Surveyor
possible source of equipment malfunctioning, testing is to where type testing approval is required by LR.
demonstrate that any mitigating arrangements such as heating
are effective. Testing is to be in accordance with arrangements 14.7.4 Oil mist detection equipment is to be tested in the
proposed by the manufacturer and agreed by LR. This testing orientation (vertical, horizontal or inclined) in which it is
is in addition to that required by 14.4.2(e) and is concerned intended to be installed on an engine or gear case as
with the effects of condensation caused by the detection specified by the equipment manufacturer.
equipment being at a lower temperature than the crankcase
atmosphere. 14.7.5 Type testing is to be carried out for each type of oil
mist detection and alarm equipment for which a
manufacturer seeks LR approval. Where sensitivity levels
14.6 Detectors and alarm equipment to be tested can be adjusted, testing is to be carried out at the extreme
and mid-point level settings.
14.6.1 The detectors and alarm equipment selected for the
type testing are to be selected from the manufacturer’s
normal production line by the LR Surveyor witnessing the 14.8 Assessment
tests.
14.8.1 Assessment of oil mist detection equipment devices
14.6.2 Two detectors are to be tested. One is to be tested after testing is to address the following:
in the clean condition and the other in a condition (a) The equipment to be tested is to have evidence of
representing the maximum level of lens obscuration design appraisal/approval by LR, See also 14.6.1.
specified by the manufacturer. (b) Details of the detection equipment to be tested are to
be recorded, such as name of manufacturer, type
designa-tion, oil mist concentration assessment
14.7 Method capability and alarm settings.
(c) After completing the tests, the detection equipment is
14.7.1 The requirements of 14.7 are to be satisfied at type to be examined and the condition of all components
testing. ascer-tained and documented. Photographic records
of the monitoring equipment condition are to be taken
14.7.2 Oil mist generation is to satisfy the following: and included in the report.
(a) Oil mist is to be generated with suitable equipment
using an SAE 80 monograde mineral oil or equivalent
and supplied to a test chamber having a volume of not 14.9 Design series qualification
3
less than 1 m . The oil mist produced is to have a
maximum droplet size of 5 µm. The oil droplet size is 14.9.1 The approval of one type of detection equipment
to be checked using the sedimentation method. may be used to qualify other devices having identical
construction details. Proposals are to be submitted for
consideration.

26 LLOYD’S REGISTER
RULES AND REGULATIONS FOR THE CLASSIFICATION OF A FLOATING OFFSHORE INSTALLATION AT A FIXED LOCATION, June 2013

Oil Engines Part 5, Chapter 2


Sections 14 & 15

14.10 The report 15.1.3 The operation of these engines relies on the
effective monitoring of a number of parameters such as
14.10.1 The test house is to provide a full report which crank angle, engine speed, temperatures and pressures
includes the following information and documents: using programmable electronic systems to provide the
(a) Test specification. services essential for the operation of the engine such as
(b) Details of equipment tested. fuel injection, air inlet, exhaust and speed control.
(c) Results of tests.
15.1.4 Details of proposals to deviate from the
requirements of this Section are to be submitted and will be
14.11 Acceptance considered on the basis of a technical justification produced
by the Enginebuilder.
14.11.1 Acceptance of crankcase oil mist detection
equipment is at the discretion of LR, based on the appraisal 15.1.5 Each engine is to be configured for the specified
of plans and particulars and the test house report of the performance and is to satisfy the relevant requirements for
results of type testing. propulsion, auxiliary or emergency engines.

14.11.2 The following information is to be submitted to LR 15.1.6 During the life of the engine details of any proposed
for acceptance of oil mist detection equipment and alarm changes to control, alarm, monitoring or safety systems
arrangements: which may affect safety and the reliable operation of the
(a) Description of oil mist detection equipment and system engine are to be submitted to LR for approval.
including alarms.
(b) Copy of the test house report identified in 14.10.
(c) Schematic layout of engine oil mist detection arrange- 15.2 Plans and particulars
ments showing location of detectors/sensors and
piping arrangements and dimensions. 15.2.1 In addition to the plans and particulars required by
(d) Maintenance and test manual which is to include the Section 1, the following information is to be submitted:
following information: (a) A general overview of the operating principles, supported
• Intended use of equipment and its operation. by schematics explaining the functionality of individual
• Functionality tests to demonstrate that the equip- systems and sub-systems. The information is to relate to
ment is operational and that any faults can be the engine capability and functionality under defined
identified and corrective actions notified. operating and emergency conditions such as recovery
• Maintenance routines and spare parts from a failure or malfunction, with particular reference to
recommen-dations. the functioning of programmable electronic systems and
• Limit setting and instructions for safe limit levels. any sub-systems. The information is also to indicate if the
• Where necessary, details of configurations in engine has different modes of opera-tion, such as to limit
which the equipment is and is not to be used. exhaust gas emissions and/or to run under an economic
fuel consumption mode or any other mode that is
electronically controlled.
(b) Operating manuals which describe the particulars of
each system and, together with maintenance instruc-
■ Section 15 tions, include reference to the functioning of sub-
systems.
Electronically controlled engines
(c) A risk-based analysis of the mechanical, pressure
containing, electrical, electronic and programmable
15.1 Scope
electronic systems and arrangements that support the
operation of the engine. The analysis is to
15.1.1 The requirements of this Section are applicable to
demonstrate that suitable risk mitigation has been
engines for propulsion, auxiliary or emergency power purposes
achieved in accor-dance with 15.3.
with programmable electronic systems implemented and used
(d) Details of hydraulic systems for actuation of sub-
to control fuel injection timing and duration, and which may
systems (fuel injection or exhaust), to include details of
also control combustion air or exhaust systems. The
the design/construction of pipes, pumps, valves,
requirements of this Section also apply to programmable
accumulators and the control of valves/pumps. Details
electronic systems used to control other functions (e.g.,
of pump drive arrangements are also to be included.
starting and control air, cylinder lubrication etc.) where
(e) Quality plan for sourcing, design, installation and testing
essential for the operation of the engine.
of all components used in the fuel oil and hydraulic oil
systems installed with the engine for engine operation.
15.1.2 These engines may be of the slow, medium or
(f) Fatigue analysis for all high pressure fuel oil and
highspeed type. They generally have no direct camshaft
hydraulic oil piping arrangements required for engine
driven fuel systems, but have common rail fuel/hydraulic
operation where failure of the pipe or its connection or
arrangements and may have hydraulic actuating systems
a component would be the cause of engine
for the functioning of the exhaust systems.
unavailability. The analysis is to concentrate on high
pressure components and sub-systems and recognise
the pressures and fluctuating stresses that the pipe
system may be subject to in normal service.

LLOYD’S REGISTER 27
RULES AND REGULATIONS FOR THE CLASSIFICATION OF A FLOATING OFFSHORE INSTALLATION AT A FIXED LOCATION, June 2013

Oil Engines Part 5, Chapter 2


Section 15

(g) Evidence of type testing of the engine with the 15.3.3 A risk-based analysis is to be carried out for:
programmable electronic system, or a proposed test plan (a) main engines on units with multiple main engines or
at the Enginebuilders with the programmable electronic other means of providing propulsion power; and/or
system functioning, to verify the functionality and (b) auxiliary engines intended to drive electric generators
behaviour under normal operating and fault conditions of forming the unit’s main source of electrical power or
the programmable electronic control system. otherwise providing power for essential services. The
(h) Schedule of testing at Enginebuilders, pre-sea trial analysis is to demonstrate that adequate hazard
commissioning and sea trials. The test schedules are mitigation has been incorporated in electronically
to identify all modes of engine operation and the sea controlled engine systems or the overall unit installation
trials are to include typical port manoeuvres under the with respect to personnel safety and providing propulsion
intended engine operating modes. The schedule is to power and/or power for essential services for the safety of
include: the unit. Arrangements satisfying the criteria of 15.3.2(a)
(i) testing and trials to demonstrate that the engine to (c) will also be acceptable.
is capable of operating as described in (a);
(ii) tests to verify that the response of the complete 15.3.4 For engines for emergency power purposes, a risk-
mechanical, hydraulic, electrical and electronic based analysis is to be carried out to demonstrate that the
system is as predicted for the intended design incorporates adequate hazard mitigation such that the
operational modes; and likelihood of an electronic control system failure resulting in the
(iii) testing required to verify the conclusions of the risk- loss of the ability to provide emergency power when required
based analysis. has been reduced to a level considered acceptable by LR and
The scope of these tests is to be agreed with LR. that means are provided to detect failures and permit
personnel to restore engine availability to operate on demand.
15.2.2 In addition to the applicable plans and particulars Failures which would result in engine failure and/or damage or
required by Pt 6, Ch 1,1.2.3 to 1.2.7, the following loss of availability are to be identified and the report is to
information for control, alarm, monitoring and safety include documentation of:
systems relating to the operation of an electronically (a) component reliability evidence;
controlled engine is to be submitted: (b) failure detection and alarms; and
(a) Engine configuration details , see 15.5.2. (c) failure response required to restore engine availability
(b) Software quality plans, including configuration and maintain personnel safety.
manage-ment documents.
(c) Software safety evidence. 15.3.5 The risk-based analysis report is to:
(d) Software assessment inspection report. (a) Identify the standards used for analysis and system
design.
(b) Identify the engine, its purpose and the associated
15.3 Risk-based analysis objectives of the analysis.
(c) Identify any assumptions made in the analysis.
15.3.1 An analysis is to be carried out in accordance with (d) Identify the equipment, system or sub-system, mode
relevant Standards acceptable to LR to demonstrate of operation and the equipment.
compliance with the applicable requirements of this sub- (e) Identify potential failure modes and their causes.
Section, appropriate to the engine application. The analysis (f) Evaluate the local effects (e.g., fuel injection failure)
is to be a risk-based consideration of engine operation and and the effects on the system as a whole (e.g., loss of
unit and personnel safety, and is to demonstrate adequate propulsion power) of each failure mode.
risk mitigation through fault tolerance and/or reliability in (g) Identify measures for reducing the risks associated with
accordance with the specified criteria in 15.3.2 to 15.3.4 each failure mode (e.g., system design, failure detection
relevant to the engine application. and alarms, redundancy, quality control procedures for
sourcing, manufacture and testing, etc.).
15.3.2 For units with a single main propulsion engine, a (h) Identify trials and testing necessary to prove conclusions.
Failure Mode and Effects Analysis (FMEA), or alternative
recognised analysis of system reliability, is to be carried out 15.3.6 At sub-system level it is acceptable to consider
and is to demonstrate that an electronic control system failure of equipment items and their functions, e.g., failure
failure: of a pump to produce flow or pressure head. It is not
(a) will not result in the loss of the ability to provide the required that the failure of components within that pump be
services essential for the operation of the engine, see analysed, and failure need only be dealt with as a cause of
Pt 6, Ch 1,2.5.8 and 2.12.2 of the Rules for Ships; failure of the pump.
(b) will not affect the normal operation of the services
essential for the operation of the engine other than
those services dependent upon the failed part, see Pt 15.4 Fuel oil and hydraulic oil systems
6, Ch 1,2.13.4 and 2.13.5 of the Rules for Ships; and
(c) will not leave either the engine, or any equipment or 15.4.1 Fuel oil and hydraulic oil piping systems
machinery associated with the engine, or the unit in an arrangements are to comply with Chapters 2, 11, 12, 13
unsafe condition, see Pt 6, Ch 1,2.3.12, 2.4.6, 2.5.4, and 14 as applicable.
2.10.3, 2.10.4 and 2.13.5 of the Rules for Ships.

28 LLOYD’S REGISTER
RULES AND REGULATIONS FOR THE CLASSIFICATION OF A FLOATING OFFSHORE INSTALLATION AT A FIXED LOCATION, June 2013

Oil Engines Part 5, Chapter 2


Section 15

15.4.2 Where pumps are essential for engine operation, no 15.4.12 For high pressure oil-containing and mechanical
fewer than two fuel oil and two hydraulic oil pressure power transmission systems, the quality plan for sourcing,
pumps are to be provided for their respective service and design, installation and testing of components is to address
arranged such that failure of one pump does not render the the following issues:
other inoperative. Each oil fuel pump and hydraulic oil (a) Design and manufacturing standard(s) applied.
pump is to be capable of supplying the quantity of oil for (b) Materials used for construction of key components and
engine operation at its maximum continuous rating and their sources.
arranged ready for immediate use. (c) Details of the quality control system applied during
manufacture and testing.
15.4.3 The fuel oil pressure piping between the oil fuel high (d) Details of type approval, type testing or approved type
pressure pumps and the fuel injectors is to be protected status assigned to the machinery or equipment.
with a jacketed piping system capable of containing fuel oil (e) Details of installation and testing recommendations for
leakage from a high pressure pipe failure. the machinery or equipment.

15.4.4 The hydraulic oil pressure piping between the high


pressure hydraulic pumps and hydraulic actuators is to be 15.5 Control engineering systems
protected with a jacketed piping system capable of
containing hydraulic oil leakage from a high pressure pipe 15.5.1 Control, alarm, monitoring, safety and programmable
failure. electronic systems are to comply with Pt 6, Ch 1 as
applicable.
15.4.5 Accumulators and associated high pressure piping
are to be designed, manufactured and tested in accordance 15.5.2 The engine control, alarm monitoring and safety
with a standard applicable to the maximum pressure and systems are to be configured to comply with the relevant
temperature rating of the system. requirements (e.g., operating profile, alarms, shut-downs,
etc.) of this Chapter and Pt 6, Ch 1 for an engine for main,
15.4.6 All valves, cocks and screwed connections are to be auxiliary or emergency power purposes. Details of the
of a type tested type applicable to the maximum service engine configuration are to be submitted for consideration
conditions anticipated in normal service. identifying:
(a) Local and remote means to carry out system
15.4.7 Isolating valves and cocks are to be located as near configuration.
as practicable to the equipment to be isolated. All valves (b) Enginebuilder procedures for undertaking configuring.
forming part of the fuel oil and hydraulic oil installation are (c) Roles and responsibilities for configuration (e.g.,
to be capable of being controlled from readily accessible Enginebuilder, engine packager, system integrator or
positions above the working platform. other nominated party) with accompanying schedule.
(d) Configurable settings and parameters (including those
15.4.8 High pressure fuel oil and high pressure hydraulic oil not to be modified from a default value).
piping systems are to be provided with high pressure (e) Configuration for propulsion, auxiliary or emergency
alarms with set points that do not exceed the system engine application. Configuration records are to be
design pressures. maintained and are to be made available to the Surveyor
at testing and trials and on request in accordance with Pt
15.4.9 High pressure fuel oil and high pressure hydraulic 6, Ch 1,1.4 and 7.1.3 of the Rules for Ships.
piping systems are to be provided with suitable relief valves
on any part of the system that can be isolated and in which
pressure can be generated. The settings of the relief valves 15.6 Software
are not to exceed the design pressures. The valves are to
be of adequate size and so arranged as to avoid an undue 15.6.1 Software lifecycle activities are to be carried out in
rise in pressure above the design pressures. accordance with an acceptable quality management
system, see Pt 6, Ch 1,2.10.20, 2.13.2 and 2.13.8 of the
15.4.10 Equipment fitted for monitoring pressures and Rules for Ships.
temperatures in the high pressure fuel oil and high pressure
hydraulic oil systems is to comply with a recognised 15.6.2 Appropriate safety related processes, methods,
Standard suitable to the anticipated vibration and techniques and tools are to be applied to software
temperature conditions. development and maintenance by the Enginebuilder.
Selection and application of techniques and measures in
15.4.11 A fatigue analysis is to be carried out in accordance accordance with Annex A of IEC 61508-3, Functional safety
with a standard applicable to the system under of electrical/electronic/programmable electronic systems:
consideration and all anticipated pressure, pulsation and Software requirements, or other relevant Standards or
vibration loads are to be addressed. The analysis is to Codes acceptable to LR, will generally be acceptable.
demonstrate that the design and arrangements are such
that the likelihood of failure is as low as reasonably
practicable. The analysis is to identify all assumptions
made and standards to be applied during manufacture and
testing of the system. Any potential weak points which may
develop due to incorrect construction or assembly are also
to be identified.

LLOYD’S REGISTER 29
RULES AND REGULATIONS FOR THE CLASSIFICATION OF A FLOATING OFFSHORE INSTALLATION AT A FIXED LOCATION, June 2013

Oil Engines Part 5, Chapter 2


Sections 15, 16 & 17

15.6.3 To demonstrate compliance with 15.6.1 and Table 2.16.1 Alarms and safeguards for
15.6.2: emergency diesel engines
(a) software quality plans and safety evidence are to be
submitted for consideration, see 15.2.2(b) and (c); and Item Alarm Alarm Note
(b) an assessment inspection of the Enginebuilder’s Emergency Diesel Engine ≥ 220 kW <220 kW
completed development is to be carried out by LR.
Fuel oil leakage from Leakage Leakage See 7.1.2
The inspection is to be tailored to verify application of
the Standards and Codes used in software safety pressure pipes
assurance accepted by LR. Lubricating oil High — —

temperature
Lubricating oil pressure Low Low —

■ Section 16 Oil mist concentration in High — See Note

Alarms and safeguards for crankcase


emergency diesel engines Coolant pressure or flow Low — —

Coolant Temperature High High —


16.1 Application
(can be air )
16.1.1 These requirements apply to emergency diesel engines
Overspeed High — Automatic
required to be immediately available in an emergency and
capable of being controlled remotely or automatically. shut-down

NOTE
16.2 Alarms and safeguards For engines having a power of more than 2250 kW or a
cylinder bore of more than 300 mm.
16.2.1 Alarm and safety systems are to comply with the
requirements of Pt 6, Ch 1.

16.2.2 Alarms and safeguards are to be fitted in


accordance with Table 2.16.1.
■ Section 17
16.2.3 The safety and alarm systems are to be designed to
‘fail safe’. The characteristics of the ‘fail safe’ operation are
General requirements
to be evaluated on the basis not only of the system and its
17.1 Turning gear
associated machinery, but also the complete installation, as
well as the unit.
17.1.1 Turning gear is to be provided for all engines to
facilitate operating and maintenance regimes as required
16.2.4 Regardless of the engine output, if shut-downs
additional to those specified in Table 2.16.1 are provided by the manufacturer.
except for the overspeed shut-down, they are to be
automatically overridden when the engine is in automatic or 17.1.2 The turning gear for all main propulsion engines is to
be power-driven and, if electric, is to be continuously rated
remote control mode during navigation.
at a value to ensure protection to the weakest part of the
16.2.5 Grouped alarms of at least those items listed in machinery.
Table 2.16.1 are to be arranged on the bridge.
17.1.3 The turning gear for auxiliary engines may be hand
16.2.6 In addition to the fuel oil control from outside the space, operated (manual) except where this is not practicable, in
which case the provision of 17.1.2 is to be complied with.
a local means of engine shut-down is to be provided.

16.2.7 Local indications of at least those items listed in 17.1.4 The turning gear for all engines is to be fitted with
Table 2.16.1 are to be provided within the same space as safety interlocks which prevent engine operation when
the diesel engines and are to remain operational in the engaged, see Ch 1,3.10. Indication of engaged/not
event of failure of the alarm and safety systems. engaged is to be provided at all start positions.

17.1.5 The remote control device of power-driven turning


gear is to be so designed that power is removed from the
turning gear when the operating switch is released.

17.1.6 Means are to be provided to secure the turning gear


when disengaged.

30 LLOYD’S REGISTER

Das könnte Ihnen auch gefallen