1 Earth Works
i Structural excavation including dewatering and sides safety protection/bracing in soils
and removal of unsuitable material from site including clearing, grubbing & slush
removal, complete in all respects as per entire satisfaction of client/consultant. 272500 cft 8 2,180,000
ii Backfilling in foundation trenches and under floors with ghassu filling /sand compacted
up to 95%MPD complete in all respects as per entire satisfaction of client/consultant. 255000 cft 10 2,550,000
iii Backfilling in foundation trenches and under floors with 50/50 sub base material
compacted up to 95%MPD complete in all respects as per entire satisfaction of 212500 cft 60 12,750,000
client/consultant.
2 Termite proofing -
Providing and applying antitermite treatment in foundations and under floor using
approved quality solution using biflex,dursban or equivalent complete in all respects as 110000 sft -
per entire satisfaction of client/consultant.
-
3 Concrete Works -
i Laying of PCC 1:4:8 of blinding layer under floor & foundations having min compressive
cube strength 1000 psi at 28 days complete in all respects as per entire satisfaction of
client/consultant. 17605 cft 175 3,080,875
-
iii Providing and laying cast in situ structural cement concrete of specified min cement
content of 325 kg/CM with minimum compressive cylinder strength of 3000 Psi at 28
days, conveyed and placed as per good Engineering practice, Lawrencepure sand and
Margalla Crush including Form work, Scaffolding etc complete in all respects as per -
entire satisfaction of client/consultant.
5 Brick Masonry -
Providing and laying first class solid brick masonry at any floor of approved quality,
shape, design and thickness in superstructure laid in 1:4 cement sand mortar using
chenab sand i/c all required scaffolding raking out and cleaning of joints, curing, -
complete as per specification and instruction of the Consultant.
1
Below Plinth Level: 18400 cft 195 3,588,000
Above Plinth Level: 29966 cft 210 6,292,860
-
Plastering -
6
Providing and laying varying from 12mm to 20mm thick 1:4 c/s plaster on walls to
achieve smooth aligned surface using one part of grey cement and four part of sand
(50% chenab, 50% local), making of edges, grooves, corners including 123805 sft 24 2,971,320
curing,scaffolding etc , complete in all respects as per entire satisfaction of
cleint/consultant.
Providing and laying varying from 12mm to 20mm thick 1:3 c/s plaster on roof to
achieve smooth aligned surface using one part of grey cement and three part of chenab
sand with scaffolding etc , complete in all respects as per entire satisfaction of 47360 sft 25 1,184,000
cleint/consultant.
7 Waterproofing of Roof: -
i Cleaning of Roof -
ii 2 coats of hot bitumen @ 15 Kg/100 sft -
iii Two layer of heavy duty polythene sheet. -
iv 1-1/2" thick jumbolon sheet -
-
-
-
TOTAL COST
120,649,275
2
Concrete A1 01:02:04
Quantity "Cft" 7064 200CUM PDAY
Cement "Bags" 1,300 620 806,000 6.5
Sand "Cft" 3,108 50 155,408 15.5408
Crush "Cft" 6,216 70 435,142 31.0816
wastage 5% 69,828
Concrete Plant 10,000
TM 3 7,000 21,000
Concrete Laying 7,064 12 84,768
Shuttering 7,064 5 35,320
Staff -
S.Total 1,617,466
15% OH/P 1,860,086
RATE PER CFT 263.32
RATE PER CUM 9,300
Concrete A3 1:1.5:3
Quantity "Cft" 7064 200CUM PDAY
Cement "Bags" 1,700 620 1,054,000
Sand "Cft" 2,966 50 148,300
Crush "Cft" 5,933 70 415,310
wastage 5% 80,881
Concrete Plant 10,000
TM 3 7,000 21,000
Concrete Laying 7,064 12 84,768
Shuttering 7,064 5 35,320
Staff -
S.Total 1,849,579
15% OH/P 2,127,015
RATE PER CFT 301.11
RATE PER CUM 10,635
Concrete A3 1:4:8
Quantity "Cft" 7064 200CUM PDAY
Cement "Bags" 670 620 415,400
Sand "Cft" 3,347 50 167,350
Crush "Cft" 6,694 70 468,580
wastage 5% 52,567
Concrete Plant 10,000
TM 3 7,000 21,000
Concrete Laying 7,064 12 84,768
Shuttering 7,064 5 35,320
Staff -
S.Total 1,254,985
15% OH/P 1,254,984.50
RATE PER CFT 177.66
RATE PER CUM 6,275