Beruflich Dokumente
Kultur Dokumente
Foundation Engineering 2
Institut Teknologi Adhitama Surabaya
Created by :
Mila Kusuma Wardani ST.,MT
1
Learning Outcomes
Superstructure
Substructure
Foundation
Function of a foundation is to transfer the structural loads from a building
safely into the ground. A backyard tool shed may need only wooden skids to
spread its load across an area of ground surface, whereas a house would
need greater stability and consequently its foundation should reach the
underlying soil that is free of organic matter and unreachable by the
winter’s frost.
5. Construction schedule
6. Construction risks
TYPES OF SOILS AND CHARACTERISTICS
Rocks and soils - Rocks: Broken into regular and irregular sizes by
joints - Soils (particulate earth material):
Boulder (too large to be lifted by hands), cobble (particle that can be
lifted by a single hand),
gravel aggregates (course grained particle larger than 6.4mm) ,
sand (frictional, size varies from 6.4 to 0.06mm), silts (frictional, low
surface-area to volume ratio, size varies from 0.06 mm to 0.002mm)
and clays (cohesive - fine grained - high surface-area to volume ratio,
size smaller than 0.002 mm) –
Peat (soils not suitable for foundations)
GRAVEL
• Gravel can be well compacted and allows water to drain freely.
• Gravel soils do not hold water.
• The variety in particle sizes in gravel means that even when
closely packed it still contains voids and drains well.
• Gravel is least likely to be affected by drying out.
SAND
Data required
•Soil parameters like cohesion c, angle of internal friction ø, adhesion factor
between soil and pile material, etc.
•SPT Values ( N values).
•Average cone resistance in case of CPT, etc.
Pile Foundations
Situations Which Demand Pile Foundation :
Sub-soil water table is so high that it can easily affect the other foundations.
Load coming form the structure is heavy and non uniform.
Where grillage or raft foundations are either very costly or their adoption
impossible due to local difficulties.
When it is not possible to maintain foundation trenches in dry condition by
pumping, due to very heavy inflow of seepage or capillary water.
When it is not possible to timber the excavation trenches in the case of deep strip
foundation. (strip foundation- spread footing under wall ).
When overlay soil is compressible, and water-logged and firm hard bearing strata
is located at quite a large depth.
When structures are located on river-bed or sea-shore and foundations are likely to
be scoured due to action of water.
Large fluctuations in sub-soil water level.
Canal or deep drainage lines exist near the foundations.
In the construction of docks, piers and other marine structures they are used as
fender piles.
Deep Foundations - Purpose
Transfer Building Loads Deep Into The Earth
Basic types
– Drilled (& poured)
– Driven
Design And Analysis Of Deep Foundation
Composite piles
Numerous types of piles of composite construction may be formed by combining units in each of
the above categories, or by adopting combinations of piles in more than one category. Thus
composite piles of a displacement type can be formed by jointing a timber section to a precast
concrete section, or a precast concrete pile can have an H-section jointed to its lower extremity.
Composite piles consisting of more than one type can be formed by driving a steel or precast
concrete unit at the base of a drilled hole, or by driving a tube and then drilling out the soil and
extending the drill hole to form a bored and castin- place pile.
Pile material
Steel; H- piles, Steel pipe
Concrete; Site cast or Precast
Wood; Timber
Composite
Types of Concrete Piles
Concrete Piles are of 3 types:
Pre-cast Piles
Cast in situ Piles
Prestressed Concrete Piles
Precast Concrete Plies
Concrete Piles ( contd)
Concrete Piles ( contd)
Prestressed Concrete Piles
Prestressed concrete piles are provided with lifting hooks at
1/5th ( 0.2L, L= length of pile ) of pile length from each end.
Piles length 50 times the thickness →single point pick up
More than 50 times the thickness →two point pick up at 0.2L
from either end.
Piles 500 sq. mm and smaller→ cast solid.
Piles over 500 sq. mm may be cast with 200mm to 300mm
cored hole (void).
Pre stressed piles are always pre- cast.
Concrete Piles ( contd)
Cast-in-Situ Piles:
Cast in position inside the ground.
First of all a bore is dug by driving a casing pipe into the ground.
Then the soil from the casing is jetted out and filled with cement
concrete after placing necessary reinforcement in it.
44
45
Selection of Type of Pile
The nature of the ground, where piling operation is to be carried
out, determines to a large extent the choice of type of pile to be
used.
In addition, the other important factors which must be considered
in this regard are:
The nature of the structure.
Loading conditions.
Elevation of the ground water level with respect to the pile cap.
Probable length of pile required.
Availability of materials and equipment.
Factors which may cause deterioration of pile.
Probable cost of pile.
Causes of Failure of Piles
Load on the pile is more than the designed load.
Defective workmanship during casting of the pile.
Displacement of reinforcement during casting.
Bearing pile resting on a soft strata.
Improper classification of soil.
Improper choice of the type of pile.
Insufficient reinforcement in the pile.
Decay of timber piles due to attack by insects.
Buckling of piles due to inadequate lateral support.
Defective method adopted for driving the pile.
Incorrect assessment of the bearing capacity of the pile.
Lateral forces not considered in the design of piles.
Load Transfer Mechanism of Piles
53
Load Transfer Mechanism of Piles
54
57
58
59
Point load capacity
60
Point Load Capacity
Janbu’s(1976) Method.
Point load capacity
62
Point Load capacity resting on Rock
.
63
Frictional Resistance of pile
.Granular Soil
64
Frictional Resistance of pile
Sand.
65
Frictional Resistance of pile
Cohesionless Soils.
66
Frictional Resistance of pile
Cohesionless Soils.
67
Frictional Resistance of pile
Cohesionless Soils.
68
Frictional Resistance of pile
Cohesion Soils.
69
Frictional Resistance of pile
Cohesion Soils.
70
Frictional Resistance of pile
Cohesion Soils.
71
Total Pile capacity in Cohesion Soils
72
Total Pile capacity in Cohesionless Soils
73
75
76
77
78
79
80
81
82
Limiting End Bearing Resistance (t/m2)
as per IS 2911
Limiting End Bearing Resistance
(t/m2) as per IS 2911
Bored Piles Driven Piles
1000 - 1100 1500
Limiting Frictional
Type of Soil
Resistance (t/m2)
Sand 6
Silt 6
Clay 7
85
PILE GROUP EFFICIENCY
CAPACITY OF PILE GROUP
• Feld’s Rule (Reduces the capacity of each pile
by 1/16 for each adjacent pile)
• Converse-Labarre Formula
Vesic (1977)
S = total settlement,
Sp = settlement of the pile tip,
Sf = settlement due to the deformation of the pile Shaft.
Qp= point load, Qf = friction load,
d = diameter of the pile L = pile length,
at the base, A = cross-sectional area
q pu - ultimate point of the pile,
resistance per unit area, E = modulus of
Dr = relative density of deformation of the pile
the sand, shaft,
Cw = settlement α = coefficient which
coefficient, depends on the
= 0.04 for driven piles distribution of skin
= 0.05 for jacked piles friction along the shaft
= 0.18 for bored piles, and can be taken equal to
0.6.
SETTLEMENT OF PILES AND PILE GROUPS IN SANDS AND
GRAVELS
Curve showing the relationship between group settlement
ratio and relative widths of pile groups in sand (Vesic, 1967)
Curve showing relationship between Fg and pile group
width (Skempton, et al., 1953)
IS 8009 (Part 2), Settlement of Pile Group by
Skempton, et al., 1953
Where,
Sf = Final Settlement of Pile Group (cm)
S1 = Final Settlement of Single Pile (cm)
B = Width of Pile Group (cm)
s = Ratio of spacing of piles to pile diameter
r = No. of rows in the square group
SETTLEMENT OF PILE GROUPS IN COHESIVE SOILS
Settlement of Pile Groups in Cohesive
Soil
CASE 1
The soil is homogeneous clay.
The load Qg is assumed to act on a
fictitious footing at a depth 2/3L
from the surface and distributed
over the sectional area of the
group.
The load on the pile group acting
at this level is assumed to spread
out at a 2 Vert : 1 Horiz slope.
Settlement of Pile Groups in
Cohesive Soil
CASE 2
The pile passes through
a very weak layer of
depth L1 and the lower
portion of length L2 is
embedded in a strong
layer.
In this case, the load Q
is assumed to act at a
depth equal to 2/3 L2
below the surface of the
strong layer and spreads
at a 2 : 1
Settlement of Pile Groups in
Cohesive Soil
CASE 3
• The piles are point
bearing piles.
• The load in this case is
assumed to act at the
level of the firm
stratum and spreads
out at a 2 : 1 slope.
Consolidation Settlement of Group Piles
NEGATIVE FRICTION
4. In cases, where the piles are driven through a strata of soft clay into
firmer soils and the soft clay tends to settle relative to the pile
5. Piles in a clay stratum which undergoes shrinkage settlement
Methods of Mitigating Negative Skin
Friction
1) Coat the surface of the precast pile with thick coat of special bitumenous
paint which have been proved to reduce skin friction as much as 90% of the
theoretical value.
2) Drive the piles inside a casing. In the top negative friction height, the space
between the pile and casing is filled with a viscous material and the casing is
withdrwan after installing the pile.
3) Smaller c/s area shaft along pile length compared to base of pile may reduce
the negative friction along the pile shaft. However, this is possible only for
pure end bearing piles (not depending on shaft resistance).
PRECAUTIONS TO BE TAKEN
Retaining walls to hold the soil back from caving in: Types of failure
such as overturning, sliding and undermining should be avoided,
non-reinforced or/and reinforced cantilevered retaining walls, drainage
behind the wall to eliminate piping of water in soil - Water proofing (use
waterproof membranes, asphalt coating) and drainage (perforated
pipes) of foundations.