Beruflich Dokumente
Kultur Dokumente
It has been 50 years since the first AIChE ammonia safety symposium was held and a
comprehensive review was made of more than 1200 papers that were presented over the last 49
years. This review includes various topics such as accidents, fires, explosions, safety
developments, benchmark studies, technological advances, and process and maintenance
improvements.
The paper also highlights the key lessons learned by the ammonia and syngas industries across
the globe from past experiences.
And
1 9 9 7 -9 8 32%
No Fire s
1 9 9 4 -9 6 39%
2000-01 42% 1 9 8 2 -8 5
1997-98 42% 1 9 7 8 -8 1
1 9 7 3 -7 6
1994-96 41%
0% 10% 20% 30% 40% 50%
1982-85 30%
2000-01 7%
1997-98 18%
Figure 1. Ammonia Plants Reporting No Fires
1994-96 14%
Figures 2, 3, and 4 show the trend of Fatalities,
1982-85
Lost Time Injuries (LTI) and Explosions/Ruptures
reported for benchmarking survey periods. This 1978-81
information is limited to the plants that 1973-76
participated in the surveys and it does not reflect
the whole ammonia industry. However, the survey 0% 5% 10% 15% 20%
0% 1% 2% 3% 4% 5%
1. Compressor explosion during a routine shop
test killed 6 people.
Figure 2. Ammonia plants reporting Fatalities
A major disaster occurred during a routine shop
One fatality was reported in each benchmarking test of a centrifugal compressor at the Ingersoll-
survey period. Rand Phillipsburg, N.J. plant. The accident killed
6 people and hospitalised 6 more for varying
In 2000-01 survey, a contractor’s employee
periods of time.
accidentally fell through a plastic sky light on the
roof of the compressor house. He fell 15 meter and The reference for this example provides an
died from his injuries the following day. Work on external view of the building and gives an idea of
the roof was authorised and the work area was the damage done. The investigation team
defined by taping. The incident occurred outside of identified the probable cause was the ignition of an
the authorised work area. oil-air mixture that occurred in the compressor as
air was used for testing the compressor.
In 1997-98 survey, a contract employee died when
he fell in to a high temperature shift reactor while To prevent a recurrence, it was recommended to
loading catalyst in to the vessel. use only inert gas in all future testing of
compressors.
In 1994-96 survey, a welder died from burns
received while working inside a steam boiler. 2. One person killed in an explosion while
breaking in a compressor.
2005 13 AMMONIA TECHNICAL MANUAL
An explosion on the fourth stage synthesis gas - The formation of a less stable intermediate
compressor discharge killed one person. carbide.
The cause of the accident was the use of air to C) Failures in waste heat boilers
lubricate the compressor at higher pressures,
Thielsch Engineering presented a paper in 1994
which increased the air temperature.
with case histories of waste heat boiler failures and
It was suggested to use only nitrogen to lubricate the remedial actions taken to restore those boilers
compressors. for continued service.
3. Suffocation of workers in CO shift converter The failures were caused by various factors
killed 3 people. including design deficiencies; defects introduced
during manufacturing or fabrication, service-
The accident occurred on 17 December 1960 at
related deterioration and/or upset plant operating
Asahi Chemical Industry Co. Ltd, Japan. Three
conditions.
people died from suffocation due to lack of oxygen
in the CO shift converter. D) Failure and repair of two primary make
gas boilers
One person entered the shift converter without
knowing that the vessel was being purged with ICI Chemicals and Polymers Ltd, Billingham plant
nitrogen after a catalyst change out. Two other in England reported tube failure of primary waste
workers also died from suffocation as they tried heat boilers.
rescuing the first worker. The principal damage had occurred as a
New safety measures were implemented for consequence of ferrule failures and subsequent
confined space entry. loss of refractory. The importance of ferrules and
refractory cannot be over emphasised. The choice
4. Many failures were reported on front-end of material should be taken into consideration both
waste heat boilers. from mechanical and corrosion resistance aspects.
A) Cause of damage and repair of reformed The total duration of the inspection and repair
gas fire tube boiler including the replacement of ferrules was 35 days
The secondary reformer waste heat boiler was and involved approximately 4,000 man-hours.
damaged due to the high pH level of boiler water Another lesson learned from this failure is that
at Jianfeng Chemicals, Fuling, Sichuan, Peoples prolonged operation with serious tube leaks should
Republic of China. be avoided, as it will almost inevitably lead to
The boiler was repaired in-situ in 115 days and the severe boiler damage.
repaired unit achieved the design heat transfer rate. E) Repair and retubing of reformed gas boiler
B) Experience with metal dusting in waste Tube leaks were detected on the reformed gas
heat boilers boiler after 600 days of plant operation at
Metal dusting was reported to occur in ammonia Rashtriya Chemicals & Fertilisers Ltd (RCF))
plant 3 of DSM Fertilisers, The Netherlands. In ammonia plant in India. The leaks were found
ammonia plants metal dusting can occur in the from the cracks behind the tube-to-tubesheet weld
process equipment between the secondary joint on the hot compartment of the boiler.
reformer outlet and the inlet of the high On some occasions the water level in the boiler
temperature shift converter. was very low while the plant was still in operation.
Modern ammonia plants generally operate at low About 33 tubes were leaking badly and half of the
steam/carbon ratios and higher front end pressures. tubes collapsed within one-meter distance from the
Both conditions will increase the CO-content in inlet. Some tubes had pits up to 2 mm diameter
the process gas leaving the secondary reformer and and 1-2 mm deep.
will therefore increase the temperature range over Also, a whitish layer of phosphate deposit was
which the formation of carbon can happen. noticed on the tube surfaces with a possible
The metal dusting process can be slowed or even accumulation of sludge and sediments inspite of
halted by: continuous and intermittent boiler blow down.
- The prevention of carbon formation. In-situ retubing of the boiler was completed in
about 34 days.
- the prevention of carbon adsorption, and
Each has advantages and disadvantages and all Developed axial-radial baskets for ammonia
these have improved ammonia plant efficiency and synthesis converters and these were installed in all
increased plant production rates by about 6%. types of converters. This has helped many
[5] Primary Reformer Failure [18] Remedial Actions to Reformer Waste Heat
D.H. Timbres and Mark McConnell Boilers
Vol 42 AIChE Symposium, 2001 M.Boumaza and M.El Ketroussi
Vol 37 AIChE Symposium, 1996
[6]Failure of Inner Shell of Double Walled
Atmospheric Ammonia Tank [19] Failure, Repair and Replacement of Waste
K.A.Nair and N.V.Jagan Mohan Heat Boiler
Vol 42 AIChE Symposium, 2001 Shahid Ahmed and Zaheer Anwar
Vol 37 AIChE Symposium, 1996
[7] Explosion of MDEA Storage Tank
Russell R. Peterson, David C. Haring, Timothy G. [20] Dissimilar Weld Cracking and Repairs on
Johnson, and James M. Senn Primary Reformer Exit Header
Vol 41 AIChE Symposium, 2000 Andrew Walker and Neil Mackenzie
Vol 36 AIChE Symposium, 1995
[8] Explosion of Hydrogen in a Pipeline for CO2
2005 31 AMMONIA TECHNICAL MANUAL
[21] Failure and Repair of Two Primary Make Gas [33] March 20, 1989 Accident in Lithuanian
Boilers Fertiliser Plant
Philip Bailey and John MacDonald Bengt Orval Andersson
Vol 35 AIChE Symposium, 1994 Vol 31 AIChE Symposium, 1990
[22] Tube Failure in a Waste Heat Boiler in [34] Explosion of Synloop Ammonia Separator
Ammonia Synthesis Section Hans-Dieter Marsch
Reinhard Michel and Hans-Dieter Marsch Vol 31 AIChE Symposium, 1990
Vol 35 AIChE Symposium, 1994
[35] Stress Corrosion in a 12-ltonne Fully –
[23] Failures in Waste Heat Boilers Refrigerated Ammonia Storage Tank
Helmut Thielsch, Florence Cone, and Jonathan J.R.Byme and F.E.Moir
Freeman R.D. Williams
Vol 35 AIChE Symposium, 1994 Vol 29 AIChE Symposium, 1988
[24] Experience with Metal Dusting in Waste Heat [36] Failure and Repair of a Primary Waste Heat
Boilers Boiler
R.J. Gommans and T.L. Huurdeman V. Sitaraman, Eko Santoso, and S. Sathe
Vol 35 AIChE Symposium, 1994 Vol 28 AIChE Symposium, 1987
[25] Repair and Retubing of Reformed Gas Boiler [37] Damage to and Replacement of an Ammonia
Anil Bhaskar Tipnis, Dilip Deshmukh, and Nirmal Storage Tank Foundation
Chandra Bandopadhyay O.A.Martinez, S.Madhavan, D.J.Kellett and
Vol 34 AIChE Symposium, 1993 H.Hamrouni
Vol 27 AIChE Symposium, 1986
[26] Repair of Waste Heat Boiler in Synloop of
NH3-Plant [38] Failure of Ammonia Converter Start-Up
Wolfgang Bickel, Maximilian Walter, and Konrad Heater Tube
Nassauer R.J. Mack and J.T Shultz
Vol 34 AIChE Symposium, 1993 Vol 27 AIChE Symposium, 1986
[27] Further Cracking in Converter Effluent/BFW [39] Failure of Ammonia Converter/Feed
Exchanger Exchanger
Philip J. Bailey and John G. MacDonald S. Karkhanis and W.H. Van Moorsel
Vol 34 AIChE Symposium, 1993 Vol 27 AIChE Symposium, 1986
[28] Failure of Waste-Heat Boiler after [40] Investigation of Damage and repair of a 1000
Debottlenecking Process Air Compressor MTD Horizontal Ammonia Converter
Edgar Lebold, Joerg Reininghaus, and Roland Subir Rao, R.C.A. Wiltzen and Wesley Jacobs
Schober Vol 26 AIChE Symposium, 1985
Vol 33 AIChE Symposium, 1992
[41] Failure and Repair of the Shell of a Primary
[29] Causes and Prevention of Explosion and Fire Waste Heat Boiler on a 1,100 ton/d Ammonia
in Synthesis Section Plant
A.K. Mukhopadhyay and P.P. Singh A.F. Pariag, I.E. Welch, and G.E. Kerns
Vol 33 AIChE Symposium, 1992 Vol 26 AIChE Symposium, 1985
[30] Failure of Waste Heat Boiler Downstream of [42] Explosion of a Benfield Solution Storage
Secondary Reformer Tank
S.K. Mukherjee, S.R. Ghosh, and S. Chatterjee J.T. McDaniel
Vol 32 AIChE Symposium, 1991 Vol 26 AIChE Symposium, 1985
[31] Failure and Novel Repair of Thick-Wall [43] Rupture of the Start-Up Heater Coil in the
Synthesis Converter Forgings Synthesis Loop of the New Ammonia Plant
James D.Campbell and Robert L. Rawlinson Wolfgang Rall and Heinz Spaehn
Keith C.Wilson Vol 25 AIChE Symposium, 1984
Vol 32 AIChE Symposium, 1991
[44] Stress Corrosion Cracking in Syngas Heat
[32] Major Incident Following the Failure of an Exchangers
Ammonia Injector on a Urea Plant H.G. Orbons and T.L. Huurdemann
P.J. Nightingale Vol 25 AIChE Symposium, 1984
Vol 31 AIChE Symposium, 1990
AMMONIA TECHNICAL MANUAL 32 2005
[45] Failure of Dissimilar Metals Weld in [59] Explosion During Breaking-in of a
Reformer Tubes Compressor
Osama El Ganainy S. Strelzoff
Vol 25 AIChE Symposium, 1984 Vol 6 AIChE Symposium, 1963
[46] Waste Heat Boiler Failure and Modifications [60] Compressor Explosion
M. Lufti El-Migharbil and E.M. Hasaballah C.W. Gibbs
Vol 22 AIChE Symposium, 1979 Vol 2 AIChE Symposium, 1959
[47] Partial Collapse of an Atmospheric Ammonia
Storage Tank
Bruce H.Winegar
Vol 22 AIChE Symposium, 1979
[48] Synthesis Start-Up Heater Failure
F.G. Kokemor
Vol 22 AIChE Symposium, 1979
[49] Ammonia Loading Line Rupture
R. Hakansson
Vol 19 AIChE Symposium, 1976
[49] Ammonia Loading Line Rupture
R. Hakansson
Vol 19 AIChE Symposium, 1976
[50] Ammonia Plant Converter Basket Failure
R.L. Thompson and J.B. Brooks
Vol 19 AIChE Symposium, 1976
[51] Fatal Accident in CO2 Removal System
T.R. Visvanathan
Vol 18 AIChE Symposium, 1975
[52] Failure and Repair of Ammonia Converter
Basket
A.Kusha and D.Lloyd
Vol 18 AIChE Symposium, 1975
[53] Failure in Start-Up Heater Tube
J. Mitcalf
Vol 17 AIChE Symposium, 1974
[54] Ammonia Tank Failure - South Africa
H. Lonsdale
Vol 17 AIChE Symposium, 1974
[55] Failure of a Boiler Pressure Shell
W.W. Patterson
Vol 15 AIChE Symposium, 1972
[56] Ammonia Storage Tank Repair
J.G.MacArthur
Vol 14 AIChE Symposium, 1971
[57] Brittle Fracture of an Ammonia Synthesis
Heat Exchanger
H.K. Karinen
Vol 13 AIChE Symposium, 1970
[58] Suffocation of Workers in a CO Converter
R.K. Simms
Vol 7 AIChE Symposium, 1964
34
5. 1960 Heat exchanger explosion at a Accumulation of nitrous oxides Systems put in place to reduce nitrous oxide accumulations.
nitrogen wash unit
6. 1960 Rupture of carbon steel piping on Heavy thermal shock resulting from low Carbon steel piping replaced; provided additional
nitrogen wash unit temperatures instrumentation.
7. 1961 Hydrogen fire from reverse flow Check valve on pump discharge failed Flow control valve installed on discharge of each pump.
on pump
8. 1961 Oxygen trailer fire Leaking hose on the trailer Procedure to stop liquid oxygen transfer in case of any leaks.
Remote isolation on liquid discharge lines
9. 1961 Air fractionation plant explosion Wooden structures on oxygen plant Wooden equipment removed from the cold box shell after
maintenance work.
10. 1962 Oil separator explosion in an Air Oil mixed with O2 rich waste gas New O2 analyser installed.
Separation plant.
11. 1962 Hydrogen compressor cylinder Interchangeable valves on compressor Installed non-interchangeable suction & discharge valves.
explosion
12. 1962 Nitrogen compression system Electrical failure led to hydrocarbon New alarms, safety instrumented system, O2 analyser
explosion contamination
2005
2005
Item Year Incident Root Cause Remedy Action Taken
Reported
13. 1963 Failure of primary reformer High temperature stress rupture in 304SS Replaced outlet piping with incoloy 800 material.
outlet piping piping resulted in weld seam failure due to
brittleness at 787oC
14. 1963 Explosion in after cooler of a Combustion on the compression cylinder Changed the cooler design.
compressor using synthetic created shock pressure wave that led to
lubricant explosion
15. 1963 Explosion during breaking of a Air used to test synthesis gas compressor Do not use air for compressor testing at higher pressures, use
compressor incident killed one at higher pressures that increased air only N2 pressures.
person temperature.
16. 1963 Air heater explosion Oversized heating element installed as part New thermocouples installed to monitor temperatures on air
of earlier modification. heater. Heaters protected by circuit breakers.
17. 1963 Air separation plant fire Trapped oil accumulation on liquid O2 Eliminated liquid O2 pump.
reflux pump
18. 1963 Oxidising salt explosion Mixing of oxidising & reducing materials Seals/gaskets made of non-combustible materials.
19. 1964 Catastrophic oxidation on Localised formation of molybdenum oxide Avoid using 316 SS
primary reformer outlet piping rich slag.
20. 1964 Suffocation of workers in a CO Confined space entry in “CO” atmosphere Stringent procedures developed for confined space entry.
35
converter, 3 people killed
21. 1964 Explosion in N2 gas compressor O2 Contamination of N2 compressor Installed dual range O2 analyser and trip system to S/D O2
compressor.
22. 1964 Explosion of condenser in an O2 Hydrocarbon caused combustion of Installed a recycling absorber. Installed a trap to drain liquid
plant material in condenser O2.
23. 1965 Explosion in expander discharge Oil accumulation in expander piping New analytical equipment installed.
piping
24. 1965 Liquid O2 disposal vessel Hydrocarbon contamination New heating procedures incorporated.
explosion
25. 1965 Nitric oxide explosion Reaction with hydrocarbons New method of removing NO from the gas stream developed.
26. 1965 Oxygen fire HP Oxygen pump seals failed Dereming and replacement of silica gel carried out. Seal was
redesigned.
36
of air piping & subsequent fire additional instrumentation
34. 1966 Distance piece explosion A loose piston nut & slipper failure on Using only two bolts on the distance piece.
reciprocating compressor
35. 1966 Methanol plant explosion Rupture of oil blowdown line allowed Changes made to control room building.
compressor synthesis loop to depressure
in a reverse flow direction
36. 1966 Nitric acid plant explosion Accumulation of ammonium nitrite during Changes made to plant startup procedures.
a prolonged startup.
37. 1967 Air separation plant incident Reaction in hydrocarbon Liquid dump from the column separated. Dead leg
absorber eliminated.
38. 1967 High speed coupling failure Misalignment, poor control & assembly Long bolts, good tolerance & assembly controls
procedures.
39. 1968 Reformer manifold cracking Oxidation & magnetism Cracks repaired.
40. 1969 Rupture of ammonia tanker Stress corrosion cracking Ceased using TI built tankers.
41. 1969 Transfer line failure Higher water boil off than anticipated Improved insulation on jacket water.
2005
2005
Item Year Incident Root Cause Remedy Action Taken
Reported
42. 1969 Failure of primary waste heat Silica carry over from refractory Refractory was replaced with low silica refractory.
boiler
43. 1970 An ammonia tank car Hole on the tanker following a collision Tanker repaired, new procedures put in place.
emergency with another tanker.
44. 1970 Failure of low temperature NH3 Free thaw cycle between the pipe sleeve Seal between the sleeve and the pipe made more
line & the pipe watertight.
Non freezing solution added to the sleeved portion of the
line.
45. 1970 Explosion in feed gas section Ignition of a mixture of O2, H2 and N2 Continuous on stream analysis. Trip system provided.
46. 1970 Brittle fracture of an ammonia Materials, light forging & defective heat Right materials heat exchanger selected.
synthesis heat exchanger treatment
47. 1970 Explosion in the feed gas Cracks developed during welding, poor Preheat on welding attachments controlled carefully
section heat treatment. when making main seam.
48. 1971 Ammonia tank overflow Failure of high level alarm and S/D Installed reliable additional high-level alarms/trip
system systems.
37
49. 1971 Catalyst fusion in secondary Loss of natural gas feed and continued Trip system checked thoroughly.
reformer airflow
50. 1971 Failure of an exchanger Corrosion in hot MEA, floating heat New corrosion inhibitor installed.
exchanger.
51. 1971 Failure of ammonia loading Sudden pressure build up in hose due to Do not drag hose over docks or decks. Do not roll hose
hose failed switch on ship. more than one revolution. Avoid sharply bent, curved or
twisted hoses
52. 1971 Failure of reformer outlet header Creep rupture resulted from extensive Bulge monitoring devices installed regular optical
intergranular cracking. pyrometer surveys of the tubes, pigtails, and tube
supports.
53. 1971 Hydrogen damage to a Hydrogen attack on ammonia converter Replaced carbon steel forgings with 2-1/4CR. – 1Mo
converter. alloy steel.
54. 1971 Nitriding in an ammonia plant Nitriding on synloop WHB Repairs made on cracks.
38
unit ammonium nitrate & oxidisation of resin. sulphate discontinued as algicide.
62. 1973 Failure of ammonia storage tank Freeze thaw cycle on foam glass 85% of the insulation replaced with urethane.
insulation insulation
63. 1973 Steam generating tube failure Accumulation of boiler chemicals & low Increased circulation rate, change over of water
circulation treatment program
64. 1973 Steam reformer tube failure Water carry over in steam drum Horizontal perforated baffle plates installed above
steam/water inlets. Secondary separator installed
between steam drum & superheater.
65. 1973 Expansion joint failure Heat treatments at wrong temperatures Stringent procedures adopted at the shop.
66. 1973 Explosion in vent stack Reverse flow of burning gas Vent heater drain lines provided with water seals.
Continuous N2 purge. Ruptured 24” elbow replaced.
67. 1973 Air steam coil failure Relief valve failed to lift. PSV relocated, properly designed and braced.
68. 1974 Secondary reformer air inlet Intergranular cracking of weld joints Repairs done using new type of welding rods.
nozzles failure
2005
2005
Item Year Incident Root Cause Remedy Action Taken
Reported
69. 1974 Waste heat boiler failure Downcomer drain lines ruptured. Loss of Letdown valves replaced with high-pressure rating.
circulation in WHB
70. 1974 Explosion in Urea Plant Presence of oil traces & H2 gas in CO2 Operating procedures changed to keep scrubber off gas
feed out of explosion limits.
71. 1974 Ammonia Tank failure in South Brittle fracture of dished end of pressure Undefined
Africa, 18 people killed storage bullet. The vessel not stress
relieved
72. 1974 Ammonia reformer freeze up Reverse flow water from leaking WHB Avoid cold weather shutdowns. Keep reformer warm
freeze up on reformer tubes, resulted into during S/D & pay attention to draining liquid
rupture of tubes
73. 1974 Coupling failure between Misalignment of LP case of syngas Misalignment corrected using optical alignment.
compressors compressor. Extreme care taken in tightening coupling bolts.
74. 1974 Explosion of ammonia liquor Internal overpressure due to combustion New operating procedures/codes developed.
tank of NH3, H2, methane gas above the liquor
75. 1974 Failure in secondary reformer Failure of refractory lining on the vessel. Monolith refractory lining replaced with a two-phase
vessel. system. Installed thermal siphons & water jacket.
39
76. 1974 Failure of start up heater tube. Nitriding of heater coils and temperature Undefined
imbalance on coils
77. 1975 Corrosion in the Naphtha Wrong outlet materials of construction Repaired outlet pigtails.
reformer
78. 1975 Failure & repair of ammonia Chloride stress corrosion cracking from Vessel repaired.
converter basket insulation
79. 1975 Fatal accident in CO2 removal Rupture of CS elbow in CO2 CS elbows replaced with SS, glass panels reduced in the
system, 9 people killed. removal system caused by erosion with control room.
impingement of high velocity stream of
hot liquid.
80. 1975 Rupture in ammonia shift Corrosion resulted from poor water Distributor tray provided, pH measured at more points.
conversion unit distribution & lack of good pH control. Corrosion probes installed in the loops.
81. 1976 Ammonia converter basket Stress corrosion cracking from chlorides Converter basket was replaced.
failure in hydrotest water, insulation.
40
converter forging
91. 1976 Replacement of ammonia Chloride attack resulted from insulation, Basket replaced.
converter basket hydrotest water & catalyst.
92. 1977 Corrosion of ammonia plant Hydrogen attack. Exchanger was repaired & heat-treated per procedure.
heat exchanger
93. 1977 CO2 stripper explosion. H2 gas or natural gas dissolved in solvent. Wash trays & demisting pads replaced.
94. 1977 Tube damage in NH3 plant Vibration damage. Baffle design modified from double-segmented, baffle
exchangers thickness doubled.
95. 1977 Problems with waste heat boiler. Excessive fouling resulted from high Low silica alumina balls installed. Catalyst changed in
silica support balls. secondary reformer.
96. 1978 Ammonia separator accident. Nozzle failure on multi layer vessel. Vessel was repaired.
97. 1978 Ammonia storage vent accident Refrigeration compressor tripped out, Flare was relocated; emergency manway vent replaced
released NH3 vapours, ignited by the flare with a standard relief vacuum breaker.
on top of the tank.
2005
2005
Item Year Incident Root Cause Remedy Action Taken
Reported
98. 1978 Failure at the inlet nozzle of Hydrogen embrittlement at the location of A new nozzle with the upgraded material installed on
ammonia converter. forging LAP converter inlet.
99. 1978 Reformer riser pressure shell Gas leaks on transfer header and riser Replaced transfer header, modification made to risers.
leak. tube.
100. 1978 Start up damage to a CO2 Internal explosion resulted from Control circuits for air trip valve modified.
absorber combustible gas mixture.
101. 1978 Stress corrosion cracked Corrosion by ammonium nitrate. The syngas line was repaired.
synthesis gas line.
102. 1978 Urea reactor failure. Plugged weep holes & corroded liner Weepholes increased, automatic and reliable monitoring
shell. system installed.
103. 1979 Cracking in ammonia converters High thermal stress from many cycles Cracks repaired.
caused cracking on multi wall converter.
104. 1979 Partial collapse of an Failure of vacuum relief valves. Tank was repaired.
atmospheric storage tank
105. 1979 Stress corrosion cracking in Inadequate purging of air before Welding repairs done on tank.
ammonia storage. introducing liquid NH3,
41
106. 1979 Synthesis startup heater failure. Localised overheating due to low flow. New interlocks provided and coil material upgraded.
107. 1979 Urea reactor bottom failure. Micro cracking in the lap weld joint due Welding repairs carried out.
to stress from thermal expansion &
contracting of lining sleeves.
108. 1979 Waste heat boiler failure. Thick tube sheets and long tubes, New double compartment design developed.
sensitive to thermal shocks.
109. 1980 Failure of superheated steam Overheating, overstressing distortion. Weld repairs done on failed piping.
header.
110. 1980 Small leak caused a big leak. Ignition of a pigtail leak initiated catalyst Leaks repaired.
tube flange leaks.
111. 1980 Temperatures run away of a Thermowell temperatures were lower than All thermocouples made horizontal.
methanator. gas temp. Gas temp lower than that of
bulk gas.
112 1981 Failure of process air line Back flow of process gas in to air line and Operating procedures changed and modified surge
failure of check valve control system.
42
122. 1983 Reformer pigtail cracks. Movement caused by thermal expansion. Bearing rollers installed on process gas line to pigtails.
123. 1983 Secondary reformer catalyst Explosion in secondary reformer. New temporary catalyst support installed.
support dome failure
124 1983 Shell rupture of a secondary Overheating near the steam water New lining and refractory installed. Repairs done on the
reformer interface. vessel.
125 1984 Cracks in the outlet section of Presence of water in condensed form. Damaged tubes replaced.
the steam reformer tubes
126 1984 Failure of dissimilar welds in Hydrogen induced crack formation. Leaking tubes repaired. External insulation applied on the
reformer tubes weld.
127. 1984 Fire in primary reformer Riser rupture & gas leak. Riser tube repaired.
penthouse.
128. 1984 Rupture of startup heater coil. Hydrogen induced cracks; condensing of Coil repaired, new thermocouples installed on the coils
moisture on the tube outer surface.
129. 1984 Stress corrosion cracking in Corrosion from contaminated water of Protective painting underneath insulation material.
syngas heat exchanger. wetting the insulated equipment.
2005
2005
Item Year Incident Root Cause Remedy Action Taken
Reported
130. 1984 NH3, Storage tank roof rupture. Deficiency in the roof to wall weld Weld was properly repaired.
connection, resulted into high stress low
fatigue.
131. 1985 Corrosion in CO2 Carbonic acid impingement. Repairs done to absorption tower.
absorption tower.
132. 1985 Damage at syngas turbine by Defect in control system, loss of process New trip system on steam superheat control.
excessive steam superheating air.
133. 1985 Explosion of a Benfield solution Hydrogen gas ingress into storage tank, New tank designed with no ingress of H2. New operational
storage tank ignition by static charge. procedures adopted.
134. 1985 Explosion in cold storage kills Ignition of a hazardous accumulation of Undefined
fire fighter NH3 gas
135. 1985 Extra low S/C ratio caused over Malfunction of steam flow control. Tight shut off valves were provided on impulse line drain
reduction of HTS catalyst. valves.
136. 1985 Failure & repair of primary Thermally induced stresses due to liquid Coating the upper exposed area of the shell and use of
waste heat boiler. level fluctuation. oxygen scavengers in BFW.
137. 1985 Failure of high-pressure Severe hydrogen attack. Converter inlet piping changed to right material.
synthesis pipe.
43
138. 1985 Firebox explosion in a primary Leaking reformer tube. Reformer tube replaced.
reformer
139. 1985 Damage & repair of a horizontal Reverse flow from syngas compressor due Internal repairs made to basket.
ammonia converter. to diaphragm failure.
140. 1985 Leak in ammonia plant reformer Overheating of pre-heat coils. Part of pre-heat coil replaced
convection section natural gas
preheat coil.
141. 1985 Major fire in a steam methane Weld quality, shortening of pigtails. Furnace rebuilt with new tubes.
reformer furnace.
142. 1985 Multiple cracking & leakage of Incorrect heat treatment, and nitriding All cracks were repaired.
hot synthesis gas pipe
143. 1985 Severe carry over phenomena in Incomplete seal welds and cracked welds Steam drum internals modified.
methanol plant due to strain and high temperatures.
144. 1985 Tube failure on the synthesis gas Flow induced tube vibration. Cross baffle design modified.
compressor after cooler.
44
153. 1986 Overheating of syngas Rag in compressor suction line. Removed rag.
compressor.
154. 1987 Piping failure in a high pressure Localised thermal strain due to Piping design modified to hold temperature and eliminate
steam system accumulation of condensation. condensation.
155. 1987 Failure and repair of a primary Localised refractory failure, subsequent The bottom head was replaced.
waste heat boiler overheating, and high temperature stress
rupture.
156. 1987 Pipe rupture caused by Improper safety valve, piping layout and Safety valve inspection program enforced to minimise future
vibrations of a safety valve supports. risks.
157. 1987 Weld cracking in reformer outlet Difference in mechanical and physical Repairs carried out on weld failures.
parts properties of base and weld metal.
158. 1987 Synthesis gas compressor failure Unconventional repairs, due to lack of Diameter of balancing drum reduced. Quick closing NRV
spare diaphragm assembly. was modified.
159. 1987 Failure of secondary reformer Insufficient combustion zone. Catalyst hold-down layer of alumina balls was reduced.
catalyst and air burner
2005
2005
Item Year Incident Root Cause Remedy Action Taken
Reported
160 1987 Corrosion in hot potassium CO2 Failure of corrosion inhibition system. Bottom section of the shell was SS overlaid, stress relieved
absorber and passivated.
161. 1987 Stress corrosion cracking in Presence of oxygen. Post weld heat treatment carried out.
field ammonia storage tanks
162. 1988 Rupture of HTS exit process gas Rapid temperature rise. Provided high temperature alarms and second gas flow
line meter.
163. 1988 Explosion that occurred during a Inadequate isolation procedures and Process isolation procedures modified.
welding operation monitoring techniques.
164. 1988 Synthesis gas compressor Fatigue initiation. Clean lubrication system.
coupling corrosion fatigue
failures
165. 1988 Severe cracking of CO2 Stress corrosion cracking. Cracks repaired.
absorber exit line
166. 1988 Stress corrosion in a 12,000 Material used and weld procedures All defects repaired.
tonne ammonia storage tank adopted susceptible to SCC and H2
cracking.
167. 1988 Problems in a process gas cooler Poor BFW quality. Cooler leaks were repaired.
45
168. 1988 Explosion in a nitric acid tail gas Difficulty in obtaining even H2 Two bellows replaced. Piping modifications carried out.
duct distribution, leakage of gas compressor
discharge valves.
169. 1989 Anhydrous ammonia release Buckling of tank floor due to deterioration Storage tank decommissioned, mothballed.
of foam glass insulation.
170. 1989 New cases of SCC in ammonia SCC in O2 atmosphere. Cathodic polarisation.
storage tank
171. 1989 Near failure of 50 bar nitrogen Brittle fracture failure due to reverse flow. Installed an inverted ‘U’ tube in N2 line.
supply line
172. 1989 Explosion in synthesis gas Backflow of synthesis gas through Additional safety valves were installed.
compressor compressor recycle lines.
173. 1989 Structural integrity of 12,000 Signs of stress corrosion cracking. Tank integrity monitoring put in place.
tonne ammonia tank in the
presence of SCC
46
182. 1990 Failure of syngas compressor Improper design and operation of anti- Surge control system was redesigned.
surge system.
183. 1990 Failure of LTS exit process gas SS line ruptured and exploded due to Piping was replaced with new liner and nozzle.
line thermal cycle stress fatigue along seam
weld.
184. 1990 Failure of process air preheat Coil deformed due to thermal expansion. Coil redesigned with a two-piece tube support system.
coil
185. 1990 Cracking in ammonia converter Hydrogen embrittlement. Cracks were grounded and repaired.
effluent BFW exchanger
186. 1991 Failure and novel repair of thick Low cycle thermal fatigue initiated Modified design for converter forging.
wall synthesis converter forging cracking.
187. 1991 Crack formation in welds in the Hydrogen induced static fatigue. Sections of piping replaced.
outlet lines of an ammonia
converter.
2005
2005
Item Year Incident Root Cause Remedy Action Taken
Reported
188. 1991 Catalyst tubes failure following High temperature stress, thermal shock, Operating temperatures lowered. Eddy current inspection
furnace fire inside surface carbonisation employed.
189. 1991 Failure of secondary reformer High thermal stress between tube to tube Routine intermittent blow down restored.
waste heat boiler sheet joints.
190. 1991 Failure of two 100 bar BFW High flow velocities caused erosion in BFW piping was repaired.
lines BFW piping.
191. 1991 Failure of two CO2 regenerators Vacuum formation. Operating procedures changed.
192. 1991 Explosion in Purge Gas Missing of gasket during original Damaged tail gas line was replaced along with the jacket
Recovery (PGR) unit cold box installation. water line.
193. 1991 Weld failure in 2 -1/4 Cr- 1 Mo Use of agglomerated flux in conjunction Undefined
ammonia converter with a LTPLHT.
194. 1991 Steam system contaminated by Using steam condensate as pump seal Catacarb pump seal flush system modified.
Catacarb solution flush water
195. 1991 Leak in thick walled synthesis Undefined Cracked weld seam was cut out and completely re-
converter welded.
196 1991 Hydrogen attack in 2-25 Cr – Formation of nitrides/carbonitrides out of
47
1Mo steels below Nelson curve the pre-existing carbides, led to hydrogen Undefined
attack.
197. 1992 Timely detection of damaged Carburisation and plastic deformation due New gas distributor installed.
gas distributor avoided failures to overheating.
198. 1992 Impeller failure of a process air Fatigue failure. Improvements made on anti-surge control system.
compressor
199. 1992 Failure of WHB after Malfunction of water circulation in boiler WHB repaired.
debottlenecking air compressor tubes, resulted two-phase flow.
200. 1992 Explosion and fire in synthesis Explosive mixture in vent tail pipe from Vent header drain system modified. PSV’s relocated.
section passing drain valves and lifting of PSV. Provided continuous purging of N2 air vents
201. 1992 Incident on motive steam raising Crevice corrosion promoted by chlorides. New design cooler installed.
gas cooler
48
210. 1993 Retubing of reformed gas boiler Boiler water deposits caused build-up on Insitu replacement done of all tubes.
tubes.
211 1994 Stress corrosion in ammonia High O2 content of 10 ppm. Maintain water content of about 0.2%.
storage tanks
212 1994 Tube failure in Synloop WHB Lack of water circulation. Leaking tubes plugged, repaired.
213. 1994 Creep damages in outlet Creep cracking after 25 years in Full manifold was replaced.
manifolds and primary reformer operation.
214. 1994 Failure of two primary make gas Loss of BFW flow, brittle fracture of Boiler tubes repaired, replaced, plugged.
boilers ferrules.
215. 1994 Failures in waste heat boilers Design deficiencies, defects during Repairs carried out on WHB’s.
fabrication, plant upsets.
216. 1994 Ammonia waste heat boiler Boiler ran dry. New boiler of floating head type was installed.
replacement
2005
2005
Item Year Incident Root Cause Remedy Action Taken
Reported
217. 1994 Weld zone cracks in repaired 2- Manufacturing defects, hydrogen attack. Cracks repaired.
1/4-1 Mo ammonia converter
218. 1994 Metal dusting in waste heat Carbon deposition, wrong materials. Avoid carbon formation, use refractory liners.
boilers
219 1994 Heavy corrosion problem in Failure of Benfield solution quality. The system was shutdown, cleaned, passivated and
Benfield CO2 removal system restarted.
220. 1994 Severe leakage in CO2 stripper Failure of floating head gasket. Gasket replaced and new shell of SS ordered.
reboiler
221. 1994 Failures in urea strippers Stress corrosion cracking in ammoniacal Bottom channel heads replaced.
solution.
222 1995 Dissimilar weld cracking & Low temperature created aggressive A heater installed on dissimilar metal weld (DMW) joint
repairs on primary reformer environment with carbonic acid. for S/D purpose - new temperature monitoring system
outlet header installed.
223. 1995 Vibration problems with Contamination of the compressor with CS suction lines replaced with SS.
revamped air compressor corrosion products.
224. 1995 Catastrophic failure of Pre-ignition of air/ammonia mixture by Mixer pipe was replaced.
49
ammonia/air mixer catalyst, rust.
225. 1995 Failure of CW circulation pump Malfunction of overspeed trip device and New vibration monitors installed. Thrust wear trip
governor of turbine. provided.
226. 1995 Problematic LTS catalyst Incorrect operation of vent valve on Careful planning improved catalyst reduction systems.
reduction corner gas line.
227. 1995 Nitriding in ammonia reactor Nitriding caused by failed protection Materials resistant nitriding installed.
tubing.
228. 1995 Fatigue cracking of absorber on Defect from hydration propagation. Crack was repaired.
hydrogen plant PSA unit
229. 1995 Repairs on CO2 absorber. Corrosion by CO2 attack on MEA system. Organic coating employed on MEA absorber.
230. 1995 Failures in urea reactors Defects during fabrication, plant upsets, Repairs carried out on liners
operating condition.
231. 1995 Crack formation in welds in Low cycle thermal fatigue. Welds were repaired.
converter outlet lines
50
boilers
240. 1996 Replacement of NH3 storage Did not meet any standards for tanks. A new tank was built.
tank
241. 1996 Corrosion assisted cracking in SCC, stress, media Vessel scrapped.
CS wall of urea reactor
242. 1996 Contamination of Benfield CO2 Organic acids produced in ‘CO’ shift Process condensate treatment system installed.
removal system reactor.
243. 1997 Repair of CO2 stripper column Chloride stress corrosion caused by wet Repaired CO2 stripper - revised operating controls.
insulation.
244. 1997 Weld cracks in NH3 converter Hydrogen induced cracks Welds repaired.
245. 1997 Defects with NH3 plant stacks Localised internal combustion overheated Deformed bend was cut out and replaced.
base of the stack.
246. 1998 Shroud failures of process air High stress levels on the shrouds. Shrouds and blading modified.
compressor turbine
2005
2005
Item Year Incident Root Cause Remedy Action Taken
Reported
247. 1998 Explosion in primary reformer Explosive gas mixture in reformer Burner management system modified.
furnace.
248. 1998 Pressure relief valve piping Inadequate support for pressure relief Developed new piping support criteria.
failures and fire in synthesis piping.
loop
249. 1997 Stress corrosion of Nb Caustic produced from hydrolysis Spare parts should be kept in dry condition.
containing cast alloys reaction.
250 1998 Plugging of bayonet/scabbard Power failure caused damage to boilers. Leaking tubes plugged.
tube WHB
251. 1998 Inner basket failure of NH3 Numerous plant trips. Failure of bolts and Basket internals were repaired.
booster reactor trip valves/check valves.
252. 1998 Damage of electric motor of Reverse rotation of pumps from failed NRV piping sizing increased to minimise flow induced
Benfield solution pump Non Return Valves’ (NRV). vibrations.
253 1998 Primary WHB shell failure Hydrogen attack, creep rupture, Use of 1¼Cr-½ Mo for WHB shells.
mechanical, thermal cyclical stress.
254. 1999 Strain-age cracking of Alloy 601 Stress relaxation cracking. Extensive repairs made to reformer outlet piping.
51
tubes at 600oC.
255. 1999 Catalyst leakage in ammonia Restriction in thermal expansion of screen Centre screen was repaired.
converter wires caused excessive compressor stress.
256. 1999 Failure of aMDEA line Instrument failure led to flow induced Failed piping was replaced.
vibrations of piping.
257. 1999 Natural gas feed preheater fire Flame impingement led to overheating. Trip system was modified.
258. 1999 Ammonia converter joint failure Hydrogen induced cracking due to poor Converter was repaired.
PWHT.
259. 1999 Failure of Benfield flash drum Fatigue failure of upper baffles. Repairs made to flash drum, PWHT also done.
260. 1999 Corrosion in CO2 removal Arsenic based vetrocoke system. Solvent system replaced with a new one.
section
261. 1999 Air and refrigeration machine Failure of refrigeration compressor seals - Many hardware modifications implemented.
oil console fire resulted to the breakage of oil line.
262. 1999 Air compressor inter cooler Vibrations of tubes on ‘U’ tube design. U tubes provided with supports. Velocity increased in
leakage tubes.
52
271. 2001 Natural gas line failure Corrosion resulted from carbonic acid. Gas line replaced with upgraded material.
272. 2001 Fire in secondary reformer Hydrogen attack, thermal cycling. Damaged portion of piping replaced with Inconel 601.
outlet line to WHB
273. 2001 Primary reformer failure Overheating at no steam flow condition. New trip system installed for start-up operation.
274. 2002 Auxiliary boiler failures Poor water quality. Not properly cleaned All the BFW and steam system chemically cleaned.
steam system.
275. 2002 Failure and repair of secondary Hydrogen assisted cracking. Repairs made on all cracks.
reformer
276. 2002 Burst before leak failure of High Strain ageing. Leaks were repaired.
temperature shift effluent WHB
277. 2002 Failure of molecular sieve dryer Delayed hydrogen attack. Undefined
278 2002 Failure and damage of High Excessive heat generated from air Catalyst was replaced. Air valve repaired.
temperature shift converter oxidation of catalyst
279. 2002 Hot spot and ruby formation in Dehydration and deposition of ruby. Upper part of catalyst replaced - alumina tiles replaced
secondary reformer with hexagonal bricks.
2005
2005
Item Year Incident Root Cause Remedy Action Taken
Reported
280. 2002 Explosion in air line to Contamination in process air line due to Start-up procedures modified. Trip valve replaced with
secondary reformer backflow. ball type.
281. 2002 Liner cracks in a gas phase area Cyclic thermal stresses. Relining done.
of urea reactor
282. 2002 Cracks in ammonia converter Hydrogen embrittlement, poor weld repair Cracks repaired.
during fabrication.
283. 2003 Synloop waste heat boiler exit High transient stress and strain. Repairs done on failures.
line failure
284. 2003 Explosion of auxiliary boiler Leaking fuel gas valves. Reliability of safety trip system improved.
285. 2003 Secondary reformer WHB Sludge deposits and corrosion under Exchanger design modified to allow intermittent
failure sludge. blowdown.
286. 2003 Embrittlement in cast reformer Formation of niobium rich silcide Undefined
outlet manifold components intermetallics.
287. 2003 Lifting of inner cup of NH3 Earthquake. Inner cup was lifted, levelled the cup.
storage tank
288. 2003 Axial flow air compressor Loose blade in inner ring. Second row blades made stronger.
53
failure
289. 2004 Steam explosion in ammonia Overfilling of steam drum, passing valves Repairs made to waste heat boiler.
plant in BFW lines.
290. 2004 Failure of Catacarb solution Reverse rotation of pump, failed check Changed check valve design. Installed remote operated
pump valves. discharge valves.
Operating Service
Survey No. No. Factor Operating Total Factor
No. Years Survey Period Plants % Factor dpy spy %
54
8 2 2000 - 2001 55 89.6% 37.8 5.7 91.5%
Plant Surveys International, Inc. (PSI) was established in 1996 and conducted Surveys 6, 7, and 8. These were fee-based multi-client benchmarking studies.
2005