Sie sind auf Seite 1von 61

PROJECT SCHEDULING

PRECEDENCE DIAGRAM METHOD

1
DPWH | Bureau of Construction
COURSE OUTLINE
OBJECTIVES
D.O. NO. 133, SERIES OF 2015
PERT
CPM
WORKSHOP NO. 1
PDM
2
DPWH | Bureau of Construction
COURSE OUTLINE
WORKSHOP NO. 2
LIMITATIONS OF PERT/CPM
ADVANTAGES OF PDM
DISADVANTAGES OF PDM
THINGS TO REMEMBER

3
DPWH | Bureau of Construction
Department order no. 133, s. 2015

4
DPWH | Bureau of Construction
PERT 10
A
30 C.D.
20

CPM 10
A

30 C.D.
20

PDM Item No.

0
0
10

ACTIVITY A

30
30
30

5
PERT - PROGRAM EVALUATION
AND REVIEW TECHNIQUE

ANALYZE the involved tasks in completing a given project, the time needed to
To

COMPLETE each task, and to IDENTIFY the MINIMUM time


needed to complete the total project.

6
DPWH | Bureau of Construction
PERT - PROGRAM EVALUATION
AND REVIEW TECHNIQUE

U.S. NAVY SPECIAL PROJECTS


Developed for the

OFFICE in 1957

7
DPWH | Bureau of Construction
CRITICAL PATH METHOD - CPM
CALCULATES THE LONGEST PATH

8
DPWH | Bureau of Construction
CRITICAL PATH METHOD - CPM
SHOWS THE EARLIEST AND LATEST TIME FOR

EACH ACTIVITY TO START AND FINISH

9
DPWH | Bureau of Construction
CRITICAL PATH METHOD - CPM
DETERMINES THE ACTIVITIES THAT ARE CRITICAL AND HAVE
FLOAT

10
DPWH | Bureau of Construction
CRITICAL PATH METHOD - CPM
DEVELOPED BY MORGAN
R. WALKER OF DU PONT AND
JAMES E. KELLEY, JR. OF REMINGTON RAND IN
1950s

11
DPWH | Bureau of Construction
PERT/CPM

12
DPWH | Bureau of Construction
BASICS OF PROJECT SCHEDULING TECHNIQUE

EARLY START TIME (EST)


EARLY FINISH TIME (EFT)
LATE START TIME (LST)
LATE FINISH TIME (LFT)
FREE FLOAT (FF)
TOTAL FLOAT (TF)
13
DPWH | Bureau of Construction
PERT/CPM LAYOUT

1 ACTIVITY NAME 2
ES LS DURATION EF LF

14
DPWH | Bureau of Construction
PDM -
PRECEDENCE DIAGRAM
METHOD

SHOWS INTER-DEPENDENCIES AMONG EACH ACTIVITIES

15
DPWH | Bureau of Construction
PRECEDENCE DIAGRAM
METHOD
- PDM
REPLACED ACTIVITY-ON-ARROW TO
ACTIVITY-ON-NODE
Item No. 10 30

ACTIVITY A

0 30
0 30

16
DPWH | Bureau of Construction
PRECEDENCE DIAGRAM
METHOD
- PDM
ACTIVITIES ARE REPRESENTED IN BOXES

17
DPWH | Bureau of Construction
PRECEDENCE DIAGRAM
METHOD
- PDM
DEVELOPED BY H.B. ZACHRY IN COOPERATION WITH IBM IN 1960s

18
DPWH | Bureau of Construction
PDM LAYOUT

19
DPWH | Bureau of Construction
PRECEDENCE DIAGRAM METHOD

20
DPWH | Bureau of Construction
LOGICAL RELATIONSHIPS
OF ACTIVITIES ON PDM
FINISH-TO-START A B

A
FINISH-TO-FINISH
B

START-TO-START A
B

A
START-TO-FINISH
B
21
DPWH | Bureau of Construction
FINISH-TO-START

100 1 3 102 2 4
A B

0 3 3 7
0 3 3 7

ACTIVITY B can only START after ACTIVITY A has FINISHED

22
DPWH | Bureau of Construction
FINISH-TO-FINISH

100 1 4
A
0 4

102 2 4
B
0 4

ACTIVITY A must be COMPLETED before ACTIVITY B can FINISH 23


DPWH | Bureau of Construction
START-TO-START

100 1 3
A
0 3

102 2 4
B
0 4

ACTIVITY B can START after ACTIVITY A has STARTED


24
DPWH | Bureau of Construction
START-TO-FINISH

100 1 3
A
0 3

102 2 4
B
0 4

ACTIVITY B can only FINISH once ACTIVITY A starts


25
DPWH | Bureau of Construction
LEAD TIME

LEAD TIME - an OVERLAP between the FIRST and SECOND


ACTIVITY
ACTIVITY A

FINISH-TO-START
ACTIVITY WITH LEAD }LEAD TIME
ACTIVITY B

When an ACTIVITY is still RUNNING and the next ACTIVITY STARTS


26
DPWH | Bureau of Construction
LEAD TIME

100 1 10
A
0 10
ACTIVITY B can already START
5 DAYS before ACTIVITY A
F-S 102 2 8 FINISHES
(-)5 B
5 13

27
DPWH | Bureau of Construction
LAG TIME

LAG TIME - the DELAY between TWO ACTIVITIES

ACTIVITY A

}
LAG TIME
FINISH-TO-START
ACTIVITY WITH LAG ACTIVITY B

When ONE ACTIVITY COMPLETES and there is a WAITING PERIOD


before the SECOND ACTIVITY can START

28
DPWH | Bureau of Construction
LAG TIME

100 1 10
A
ACTIVITY B must start 3 DAYS
0 10 after ACTIVITY A has FINISHED

102 2 8
F-S B
3
13 21

29
DPWH | Bureau of Construction
FORWARD PASS

A FORWARD PASS through the network determines the


EARLIEST TIME each activity can START and
FINISH.

It also determines the TOTAL DURATION of the Project

30
DPWH | Bureau of Construction
FORWARD PASS
General Rule in Calculating Early Start Time (EST) & Early
Finish Time (EFT) (F-S):
Begin from Start Event and move towards the End Event
The EST for the starting activity = 0
The EST of an activity = latest (or maximum) EFT of the
activities directly preceding it
The EFT of an activity = its Early Start + Duration required to
perform the current activity

31
DPWH | Bureau of Construction
FORWARD PASS

SPL - 3 1 3 102(2)b 2 9
ROADWAY EXCAVATION
MOBILIZATION (SURPLUS COMMON)
0 3 3 12

32
DPWH | Bureau of Construction
FORWARD PASS WITH MULTIPLE PREDECESSORS

104(1)b 3 7
EMBANKMENT FROM
102(2)b 2 9 ROADWAY EXCAVATION
200 5 8
ROADWAY EXCAVATION 12 19
(SURPLUS COMMON)
AGGREGATE
SUBBASE COURSE
3 12
105(1) 4 5 19 27

SUBGRADE PREPARATION

12 17

33
DPWH | Bureau of Construction
FORWARD PASS (S-S & F-F)
3 104(1)b 7

EMBANKMENT FROM
2 102(2)b 9 ROADWAY EXCAVATION
5 200 8
ROADWAY EXCAVATION 12 19
(SURPLUS COMMON)
AGGREGATE
SUBBASE COURSE
3 12
4 105(1) 5 19 27

SUBGRADE PREPARATION

12 19

34
DPWH | Bureau of Construction
FORWARD PASS WITH LEAD TIME AND LAG TIME

WITH LEAD OR LAG TIMES


If there is a Lead Time (-) between two activities; ES of
the Current Activity = EF of the Preceding Activity + (-
LEAD TIME) and EF will still be equal to ES+ its Duration

For Lag Time (+); ES of the Current Activity = EF of the


Preceding Activity + (Lag Time)

35
DPWH | Bureau of Construction
FORWARD PASS WITH LAG TIME

SPL - 3 1 3 102(2)b 2 9

2 ROADWAY EXCAVATION
MOBILIZATION (SURPLUS COMMON)
0 3 5 14

36
DPWH | Bureau of Construction
FORWARD PASS WITH LEAD TIME

SPL - 3 1 3 102(2)b 2 9

(-)2 ROADWAY EXCAVATION


MOBILIZATION (SURPLUS COMMON)
0 3 1 10

37
DPWH | Bureau of Construction
FORWARD PASS
(S-S & F-F AND LEAD TIME AND LAG TIME)

104(1)b 3 7
EMBANKMENT FROM
102(2)b 2 9 ROADWAY EXCAVATION
200 5 8
12 19 3
ROADWAY EXCAVATION
(SURPLUS COMMON)
AGGREGATE
SUBBASE COURSE
3 12
105(1) 4 5 22 30

(-)2 SUBGRADE PREPARATION

10 22

38
DPWH | Bureau of Construction
BACKWARD PASS

A BACKWARD PASS through the network


determines the LATEST TIME each activity can
START and FINISH without delaying completion of
the project.
It also helps determine the activities that can be
DELAYED or not.

39
DPWH | Bureau of Construction
Backward Pass
General Rule in Calculating Late Start Time (LST) & Late
Finish Time (LFT) (F-S):
Begin from End Event and move towards the Start Event.
Assume reverse direction of arrows.
The LFT for the final activity = its EFT as determined by
forward pass.
The LFT for an activity = earliest (or minimum) LST of the
activities directly following (succeeding) it
The LST of an activity = its LFT - Duration required to perform
the current activity
40
DPWH | Bureau of Construction
BACKWARD PASS

SPL - 3 1 3 102(2)b 2 9
ROADWAY EXCAVATION
MOBILIZATION (SURPLUS COMMON)
0 3 3 12
0 3 3 12

41
DPWH | Bureau of Construction
BACKWARD PASS WITH MULTIPLE PREDECESSORS

104(1)b 3 7
EMBANKMENT FROM
102(2)b 2 9 ROADWAY EXCAVATION
200 5 8
ROADWAY EXCAVATION 12 19
(SURPLUS COMMON) 12 19 AGGREGATE
SUBBASE COURSE
3 12
105(1) 4 5 19 27
3 12
19 27
SUBGRADE PREPARATION

12 17
14 19
42
DPWH | Bureau of Construction
BACKWARD PASS (S-S & F-F)
104(1)b 3 7

EMBANKMENT FROM
102(2)b 2 9 ROADWAY EXCAVATION
200 5 8
ROADWAY EXCAVATION 12 19
(SURPLUS COMMON) 12 19 AGGREGATE
SUBBASE COURSE
3 12
105(1) 4 5 19 27
3 12
19 27
SUBGRADE PREPARATION

12 19
14 19
43
DPWH | Bureau of Construction
BACKWARD PASS WITH LEAD TIME AND LAG TIME

If there is a Lead Time (-) between two activities;


LF of the Current Activity = LS of the Previous
Activity - (- LEAD TIME) and LS will still be equal
to LF – Duration

For Lag Time (+); LF of the Current Activity = LS


of the Previous Activity - (Lag Time)
44
DPWH | Bureau of Construction
BACKWARD PASS WITH LAG TIME

SPL - 3 1 3 102(2)b 2 9

2 ROADWAY EXCAVATION
MOBILIZATION (SURPLUS COMMON)
0 3 5 14
0 3 5 14

45
DPWH | Bureau of Construction
BACKWARD PASS
(S-S & F-F AND LEAD TIME AND LAG TIME)

104(1)b 3 7
EMBANKMENT FROM
102(2)b 2 9 ROADWAY EXCAVATION
200 5 8
12 19 3
ROADWAY EXCAVATION
(SURPLUS COMMON) 12 19 AGGREGATE
SUBBASE COURSE
3 12
105(1) 4 5 22 30
3 12
22 30
(-)2 SUBGRADE PREPARATION

10 22
17 22
46
DPWH | Bureau of Construction
LIMITATIONS of PERT/CPM

ONLY ALLOW FINISH-TO-START RELATIONSHIP


In PERT/CPM, since it only uses a F-S relationship, the presentation
of activity relationship shows that succeeding activity CANNOT
START until its preceding ACTIVITY HAS BEEN
COMPLETED.

47
DPWH | Bureau of Construction
LIMITATIONS of PERT/CPM

If there are overlapping of activities, sometimes the approach used is


through REPETITION OF ACTIVITIES.

48
DPWH | Bureau of Construction
LIMITATIONS of PERT/CPM

LAG RELATIONSHIP CANNOT BE SHOWN

Lag is always ZERO

PRESENCE of DUMMY ACTIVITIES.

49
DPWH | Bureau of Construction
ADVANTAGES OF PDM

PDM is very USEFUL when representing


REPETITIVE CONSTRUCTION activities, e.g.,
highways construction & multi-storey buildings.
50
DPWH | Bureau of Construction
ADVANTAGES OF PDM

The ability to show relationships other than finish-to-


start.

51
DPWH | Bureau of Construction
ADVANTAGES OF PDM

The technique is more VERSATILE as compared to


other network planning.

52
DPWH | Bureau of Construction
ADVANTAGES OF PDM
Availability of lag has made this technique more
ADAPTABLE to the planner’s needs.

53
DPWH | Bureau of Construction
ADVANTAGES OF PDM
This tool can guide managers in MAKING CRITICAL
DECISIONS such as to DEPLOY RESOURCES based
on priority.

54
DPWH | Bureau of Construction
ADVANTAGES OF PDM
PDM allows complex CPM schedules to be created with fewer activities.

55
DPWH | Bureau of Construction
ADVANTAGES OF PDM?

Most Software use PDM in generating the Network Diagram

56
DPWH | Bureau of Construction
DISADVANTAGES Of PDM

 Manual Calculation is more complicated


 May produce different dates on different software
 Updating and Managing change can be challenging

57
DPWH | Bureau of Construction
THINGS TO REMEMBER

In PDM, the RELATIONSHIP between the current and


previous activities CAN BE BETTER CALCULATED
by using TWO OR MORE of the four possible logical
relationships than by using only one relationship

58
DPWH | Bureau of Construction
THINGS TO REMEMBER

Calculation of the critical path requires consideration of


the logical relationship of each activity

59
DPWH | Bureau of Construction
THINGS TO REMEMBER

Usually activities with a START-TO-START


RELATIONSHIP will also have a FINISH-TO-
FINISH RELATIONSHIP

60
DPWH | Bureau of Construction
THINGS TO REMEMBER

In a comprehensive schedule all activities except the first


and last nodes should have at least ONE PRECEDING
ACTIVITY and at least ONE SUCCEEDING
ACTIVITY

61
DPWH | Bureau of Construction

Das könnte Ihnen auch gefallen