Beruflich Dokumente
Kultur Dokumente
1
DPWH | Bureau of Construction
COURSE OUTLINE
OBJECTIVES
D.O. NO. 133, SERIES OF 2015
PERT
CPM
WORKSHOP NO. 1
PDM
2
DPWH | Bureau of Construction
COURSE OUTLINE
WORKSHOP NO. 2
LIMITATIONS OF PERT/CPM
ADVANTAGES OF PDM
DISADVANTAGES OF PDM
THINGS TO REMEMBER
3
DPWH | Bureau of Construction
Department order no. 133, s. 2015
4
DPWH | Bureau of Construction
PERT 10
A
30 C.D.
20
CPM 10
A
30 C.D.
20
0
0
10
ACTIVITY A
30
30
30
5
PERT - PROGRAM EVALUATION
AND REVIEW TECHNIQUE
ANALYZE the involved tasks in completing a given project, the time needed to
To
6
DPWH | Bureau of Construction
PERT - PROGRAM EVALUATION
AND REVIEW TECHNIQUE
OFFICE in 1957
7
DPWH | Bureau of Construction
CRITICAL PATH METHOD - CPM
CALCULATES THE LONGEST PATH
8
DPWH | Bureau of Construction
CRITICAL PATH METHOD - CPM
SHOWS THE EARLIEST AND LATEST TIME FOR
9
DPWH | Bureau of Construction
CRITICAL PATH METHOD - CPM
DETERMINES THE ACTIVITIES THAT ARE CRITICAL AND HAVE
FLOAT
10
DPWH | Bureau of Construction
CRITICAL PATH METHOD - CPM
DEVELOPED BY MORGAN
R. WALKER OF DU PONT AND
JAMES E. KELLEY, JR. OF REMINGTON RAND IN
1950s
11
DPWH | Bureau of Construction
PERT/CPM
12
DPWH | Bureau of Construction
BASICS OF PROJECT SCHEDULING TECHNIQUE
1 ACTIVITY NAME 2
ES LS DURATION EF LF
14
DPWH | Bureau of Construction
PDM -
PRECEDENCE DIAGRAM
METHOD
15
DPWH | Bureau of Construction
PRECEDENCE DIAGRAM
METHOD
- PDM
REPLACED ACTIVITY-ON-ARROW TO
ACTIVITY-ON-NODE
Item No. 10 30
ACTIVITY A
0 30
0 30
16
DPWH | Bureau of Construction
PRECEDENCE DIAGRAM
METHOD
- PDM
ACTIVITIES ARE REPRESENTED IN BOXES
17
DPWH | Bureau of Construction
PRECEDENCE DIAGRAM
METHOD
- PDM
DEVELOPED BY H.B. ZACHRY IN COOPERATION WITH IBM IN 1960s
18
DPWH | Bureau of Construction
PDM LAYOUT
19
DPWH | Bureau of Construction
PRECEDENCE DIAGRAM METHOD
20
DPWH | Bureau of Construction
LOGICAL RELATIONSHIPS
OF ACTIVITIES ON PDM
FINISH-TO-START A B
A
FINISH-TO-FINISH
B
START-TO-START A
B
A
START-TO-FINISH
B
21
DPWH | Bureau of Construction
FINISH-TO-START
100 1 3 102 2 4
A B
0 3 3 7
0 3 3 7
22
DPWH | Bureau of Construction
FINISH-TO-FINISH
100 1 4
A
0 4
102 2 4
B
0 4
100 1 3
A
0 3
102 2 4
B
0 4
100 1 3
A
0 3
102 2 4
B
0 4
FINISH-TO-START
ACTIVITY WITH LEAD }LEAD TIME
ACTIVITY B
100 1 10
A
0 10
ACTIVITY B can already START
5 DAYS before ACTIVITY A
F-S 102 2 8 FINISHES
(-)5 B
5 13
27
DPWH | Bureau of Construction
LAG TIME
ACTIVITY A
}
LAG TIME
FINISH-TO-START
ACTIVITY WITH LAG ACTIVITY B
28
DPWH | Bureau of Construction
LAG TIME
100 1 10
A
ACTIVITY B must start 3 DAYS
0 10 after ACTIVITY A has FINISHED
102 2 8
F-S B
3
13 21
29
DPWH | Bureau of Construction
FORWARD PASS
30
DPWH | Bureau of Construction
FORWARD PASS
General Rule in Calculating Early Start Time (EST) & Early
Finish Time (EFT) (F-S):
Begin from Start Event and move towards the End Event
The EST for the starting activity = 0
The EST of an activity = latest (or maximum) EFT of the
activities directly preceding it
The EFT of an activity = its Early Start + Duration required to
perform the current activity
31
DPWH | Bureau of Construction
FORWARD PASS
SPL - 3 1 3 102(2)b 2 9
ROADWAY EXCAVATION
MOBILIZATION (SURPLUS COMMON)
0 3 3 12
32
DPWH | Bureau of Construction
FORWARD PASS WITH MULTIPLE PREDECESSORS
104(1)b 3 7
EMBANKMENT FROM
102(2)b 2 9 ROADWAY EXCAVATION
200 5 8
ROADWAY EXCAVATION 12 19
(SURPLUS COMMON)
AGGREGATE
SUBBASE COURSE
3 12
105(1) 4 5 19 27
SUBGRADE PREPARATION
12 17
33
DPWH | Bureau of Construction
FORWARD PASS (S-S & F-F)
3 104(1)b 7
EMBANKMENT FROM
2 102(2)b 9 ROADWAY EXCAVATION
5 200 8
ROADWAY EXCAVATION 12 19
(SURPLUS COMMON)
AGGREGATE
SUBBASE COURSE
3 12
4 105(1) 5 19 27
SUBGRADE PREPARATION
12 19
34
DPWH | Bureau of Construction
FORWARD PASS WITH LEAD TIME AND LAG TIME
35
DPWH | Bureau of Construction
FORWARD PASS WITH LAG TIME
SPL - 3 1 3 102(2)b 2 9
2 ROADWAY EXCAVATION
MOBILIZATION (SURPLUS COMMON)
0 3 5 14
36
DPWH | Bureau of Construction
FORWARD PASS WITH LEAD TIME
SPL - 3 1 3 102(2)b 2 9
37
DPWH | Bureau of Construction
FORWARD PASS
(S-S & F-F AND LEAD TIME AND LAG TIME)
104(1)b 3 7
EMBANKMENT FROM
102(2)b 2 9 ROADWAY EXCAVATION
200 5 8
12 19 3
ROADWAY EXCAVATION
(SURPLUS COMMON)
AGGREGATE
SUBBASE COURSE
3 12
105(1) 4 5 22 30
10 22
38
DPWH | Bureau of Construction
BACKWARD PASS
39
DPWH | Bureau of Construction
Backward Pass
General Rule in Calculating Late Start Time (LST) & Late
Finish Time (LFT) (F-S):
Begin from End Event and move towards the Start Event.
Assume reverse direction of arrows.
The LFT for the final activity = its EFT as determined by
forward pass.
The LFT for an activity = earliest (or minimum) LST of the
activities directly following (succeeding) it
The LST of an activity = its LFT - Duration required to perform
the current activity
40
DPWH | Bureau of Construction
BACKWARD PASS
SPL - 3 1 3 102(2)b 2 9
ROADWAY EXCAVATION
MOBILIZATION (SURPLUS COMMON)
0 3 3 12
0 3 3 12
41
DPWH | Bureau of Construction
BACKWARD PASS WITH MULTIPLE PREDECESSORS
104(1)b 3 7
EMBANKMENT FROM
102(2)b 2 9 ROADWAY EXCAVATION
200 5 8
ROADWAY EXCAVATION 12 19
(SURPLUS COMMON) 12 19 AGGREGATE
SUBBASE COURSE
3 12
105(1) 4 5 19 27
3 12
19 27
SUBGRADE PREPARATION
12 17
14 19
42
DPWH | Bureau of Construction
BACKWARD PASS (S-S & F-F)
104(1)b 3 7
EMBANKMENT FROM
102(2)b 2 9 ROADWAY EXCAVATION
200 5 8
ROADWAY EXCAVATION 12 19
(SURPLUS COMMON) 12 19 AGGREGATE
SUBBASE COURSE
3 12
105(1) 4 5 19 27
3 12
19 27
SUBGRADE PREPARATION
12 19
14 19
43
DPWH | Bureau of Construction
BACKWARD PASS WITH LEAD TIME AND LAG TIME
SPL - 3 1 3 102(2)b 2 9
2 ROADWAY EXCAVATION
MOBILIZATION (SURPLUS COMMON)
0 3 5 14
0 3 5 14
45
DPWH | Bureau of Construction
BACKWARD PASS
(S-S & F-F AND LEAD TIME AND LAG TIME)
104(1)b 3 7
EMBANKMENT FROM
102(2)b 2 9 ROADWAY EXCAVATION
200 5 8
12 19 3
ROADWAY EXCAVATION
(SURPLUS COMMON) 12 19 AGGREGATE
SUBBASE COURSE
3 12
105(1) 4 5 22 30
3 12
22 30
(-)2 SUBGRADE PREPARATION
10 22
17 22
46
DPWH | Bureau of Construction
LIMITATIONS of PERT/CPM
47
DPWH | Bureau of Construction
LIMITATIONS of PERT/CPM
48
DPWH | Bureau of Construction
LIMITATIONS of PERT/CPM
49
DPWH | Bureau of Construction
ADVANTAGES OF PDM
51
DPWH | Bureau of Construction
ADVANTAGES OF PDM
52
DPWH | Bureau of Construction
ADVANTAGES OF PDM
Availability of lag has made this technique more
ADAPTABLE to the planner’s needs.
53
DPWH | Bureau of Construction
ADVANTAGES OF PDM
This tool can guide managers in MAKING CRITICAL
DECISIONS such as to DEPLOY RESOURCES based
on priority.
54
DPWH | Bureau of Construction
ADVANTAGES OF PDM
PDM allows complex CPM schedules to be created with fewer activities.
55
DPWH | Bureau of Construction
ADVANTAGES OF PDM?
56
DPWH | Bureau of Construction
DISADVANTAGES Of PDM
57
DPWH | Bureau of Construction
THINGS TO REMEMBER
58
DPWH | Bureau of Construction
THINGS TO REMEMBER
59
DPWH | Bureau of Construction
THINGS TO REMEMBER
60
DPWH | Bureau of Construction
THINGS TO REMEMBER
61
DPWH | Bureau of Construction