Document No.
ID-F-NB-P-JP-002-H05-0001
PT. NIPPON STEEL CONSTRUCTION
INDONESIA
For
D MOS MAN 25-Juni-07
Comments
For 26-Dec.-
0 MOS MAN
Construction 07
TABLE OF CONTENTS
1 GENERAL 4
3 FUNCTIONAL TEST 5
4 CLEANLINESS TEST 8
1 GENERAL
No Document
Documents Company Doc. Num.
. Number
General Arrangement Drawing 837005-IN-WHCP-
1 ID-F-NB-P-JP-002-B01-0001
006
Schematic Diagram 837005-IN-WHCP-
2 ID-F-NB-P-JP-002-C03-0101
009
Instrument Data Sheets 837005-IN-WHCP-
3 ID-F-NB-P-JP-002-C15-0001
010
Block Wiring Diagram 837005-IN-WHCP-
4 ID-F-NB-P-JP-002-C19-0001
011
Name Plate Format Drawings 837005-IN-WHCP-
5 ID-F-NB-P-JP-002-D01-0101
013
Detailed Fabrication Drawings 837005-IN-WHCP-
6 ID-F-NB-P-JP-002-D04-0001
014
Electrical Connection Diagram 837005-IN-WHCP-
7 ID-F-NB-P-JP-002-D06-0101
015
Instrument/Electrical Panel Detail 837005-IN-WHCP-
8 ID-F-NB-P-JP-002-E01-0101
Drawings 016
Calculation notes 837005-IN-WHCP-
9 ID-F-NB-P-JP-002-F04-0001
018
Cause and Effect Chart 837005-IN-WHCP-
10 ID-F-NB-P-JP-002-C16-0001
029
Labeling
Front Side
Left Side
Right Side
Rear Side
3 FUNCTIONAL TEST
Pressurized the initial Pressure in Hydraulic Accumulator with Nitrogen gas (90% of
minimum operating pressure) and the results shall be recorded.
Required several preparation & check items to be done, before running the
Wellhead Control Panel as follows:
Fill the hydraulic tank with “Tellus 32” until 75% of the full tank.
Tighten all the tubing and pipe connection.
Plug the output to all Wing Valve, SSV, and SCSSV bulkheads.
Open all valve
Close the ball valve in return line.
Connect Pressure Transmitters to Junction Box.
Connect SOV to Junction Box.
Connect Push Button to Junction Box.
Connect all Junction Box to PLC simulator.
Install power and control cable to each motor.
Show oil cleanliness to NAS 1638 class 6.
The Function test will be perform for each module of well and all part of
instruments. For the leak test will be perform and record. Duration for the leak test
is 12 hours.
NORTH BELUT PROJECT
WHP EPC
PT.
NISCONI PT. IBP
RE
TITLE DOCUMENT NUMBER V DATE PAGE
PERFORMACE TESTING AND
ACCEPTANCE TEST ID-F-NB-P-JP-002-H05-0001 0 26-Dec.-07 6 of 35
PROCEDURE
3.2.1 Start & Stop Motor Pump on Manual Condition (Without PLC
Simulator)
The purposes of this test are to ensure Motor can be run by Local control station on
Wellhead Control Panel and to ensure a relief valves setting pressure are working
properly.
Without PLC simulator motor can be run until the pressure reach set point of relief
valve (3,300 psig for MP & 6,050 psig for HP), because if we used PLC simulator
motor will be stop at 3,000 psig (MP) & 5,500 psig (HP) according to set point of
start & stop for motor. The test result will be reported (Form 2 A).
3.2.2 Start & Stop Motor Pump on Remote Condition (With PLC Simulator)
The purposes of this test are to ensure the whole system will work properly after
WHCP are connected to PSD system. The PSD system represent by PLC Simulator.
For pressurize the system we sequence to start & stop the motor pump. Depend
which motor pump need to be used.
- Pump 30-QJP-001-2A
Working Step:
1. Open the line of pump 30-QJP-001-2A (AC-4, AC-5, AC-6, AC-8,CD-13)
2. Open isolation valve to accumulator CA5 & CA6, and close the return line
3. Start the motor and automatically stop when the pressure of the hydraulic
already reach 3000 Psig (Check on PI-1020A and PT-1014)
4. Check the running time duration of the motor to reach the desired
operating pressure.
5. If the pressure lines drop before 30 minutes, check the fitting and tubing
connections, which leakage may occur, repeat step 4 to 7.
- Pump 30-QJP-001-2B
Working Step:
1. Close valve AC-3
2. Open the return/bleed line of accumulator CA-5 & CA6
3. Check on PI-1020B, the pressure should back to initial pressure.
4. Close return/bleed line of accumulator CA-5 & CA-6
5. Close the line to Pump 30-QJP-001-2A (AC-4), open valve AC-3
6. Open the line of pump 30-QJP-001-2B (AC-9, AC-10, AC-11, CD-14)
7. Start the motor and automatically stop when the pressure of the hydraulic
already reaches 3000 Psig (Check on PI-1020B and PT-1014).
6. Check the running time duration of the motor to reach the desired
operating pressure.
NORTH BELUT PROJECT
WHP EPC
PT.
NISCONI PT. IBP
RE
TITLE DOCUMENT NUMBER V DATE PAGE
PERFORMACE TESTING AND
ACCEPTANCE TEST ID-F-NB-P-JP-002-H05-0001 0 26-Dec.-07 7 of 35
PROCEDURE
- Pump 30-QJP-001-1A
Working Step:
1. Valve AC-2 open position
2. Open the line of pump 30-QJP-001-1A (AC-12, AC-13, AC-14, AC-16, CD-
15)
3. Open isolation valve to accumulator CA-11 & CA-12, and close the return
line
4. Start the motor and automatically stop the motor if the pressure of the
hydraulic already reach 5500 Psig (Check on PI-1021A and PT-1015)
5. Check the running time duration of the motor to reach the desired
operating pressure.
6. While all motor in stop condition, wait for 30 minutes. If the line pressure
keeps in the working pressure, mean the Hydraulic Unit working properly.
7. If the pressure line drops before 30 minutes, check the fitting and tubing
connections, which leakage may occur, repeat step 4 to 7.
- Pump 30-QJP-001-1B
Working Step:
1. Close valve AC-2
2. Open the return/bleed line of accumulator CA-11, CA-12
3. Check on PI-1021A, the pressure should back to initial pressure.
4. Close return/bleed line of accumulator CA-11, CA-12
5. Close the line to pump 30-QJP-001-1A (AC-12)
6. Open the line of pump 30-QJP-001-1B (AC-17, AC-18, AC-19)
7. Start the motor and automatically stop the motor if the pressures of the
hydraulic already reach 5500 Psig (Check on PI-1021B and PT-1015).
8. Check the running time duration of the motor to reach the desired
operating pressure.
Working Step :
1. Close valve AC-3
2. Open return line of accumulator CA-5 and CA-6
3. Check the pressure on PI-1020A and PI-1020B, the pressure should back
to initial pressure
4. Close the return line of accumulator CA-5 and CA-6.
5. Close valves AC-9, AC-8, and CD-14.
6. Open Valves AC-3, AC-4, AC-5, AC-6, AC-7, AG-1, CD-13.
NORTH BELUT PROJECT
WHP EPC
PT.
NISCONI PT. IBP
RE
TITLE DOCUMENT NUMBER V DATE PAGE
PERFORMACE TESTING AND
ACCEPTANCE TEST ID-F-NB-P-JP-002-H05-0001 0 26-Dec.-07 8 of 35
PROCEDURE
7. Open valve AB-11 and start the hand pump until the pressure on PI-1020A
reach 3300 psi
Working Step :
1. Close valve AC-2
2. Open return line of accumulator CA-11 and CA-12
3. Check the pressure on PI-1021A and PI-1021B, the pressure should back
to initial pressure
4. Close the return line of accumulator CA-11 and CA-12.
5. Close valves AC-17, AC-16, and CD-16.
6. Open Valves AC-2, AC-12, AC-13, AC-14, AC-15, Af-1, CD-15.
7. Open valve AB-12 and start the hand pump until the pressure on PI-1021A
reach 6050 psi
For the detailed instruction WHCP Function test fill the WHCP function test Form
(Form 3)
4 CLEANLINESS TEST
Cleaning test shall be done to check particle contamination level of hydraulic oil
after circulating in the HPU unit. System Cleanliness standard will refer to NAS
1638 class 6 (AEROSPACE INDUSTRIES ASSOCIATION OF AMERICA, INC.).
The result of the checks and measurement done during Factory Acceptance Test
shall be recorded on the following test forms:
A. BODY INSPECTION
CONFORMITY
Aspect To be Checked Yes No N/A
General Aspect
Size (Dimensional Check)
Front Side
Rear Side
Right Side
Left Side
CONFORMITY
Aspect To be Checked Yes No N/A
Equipment Conformity
Equipment Location
Labeling
Cleanliness
NORTH BELUT PROJECT
WHP EPC
PT.
NISCONI PT. IBP
RE
TITLE DOCUMENT NUMBER V DATE PAGE
PERFORMACE TESTING AND
ACCEPTANCE TEST ID-F-NB-P-JP-002-H05-0001 0 26-Dec.-07 10 of 35
PROCEDURE
Tubing Works
Wiring and Terminations
FA2 6050
FA3 6050
FB1 3300
FB2 3300
C. LEAK TEST
Recorded
ACTION CLEARANC
No. PUNCH LIST DESCRIPTION REMARKS
BY E STATUS